Slide 1
Slide 2
Plant history & Details
1985:
TEXMACO LTD
1993:
Enhanced
Production
1500 to 1800TPD
1995:
Management
Took over by
ZCL
1998-99 :
Enhanced
Clinker Prod
1.6 to
1.8MTPA
2000:
50:50 Joint
venture
with
Italcementi
Group
2006:
Italcementi
become
100 % share
holder in ZCL
2009:
Enhanced
Clinker Product
1.8 to
2.0 MTPA
2010 :
New
Clinker Line
(2.3 MTPA)
Commissioned
2016 :
Management
Took over by
HEIDELBERG
CEMENT
❖1985 –M/s M/S TEXMACO LTD Capacity – 1500TPD Cement Plant
❖1993 –Enhanced production capacity from -1500 TPD to 1800TPD
❖1995–Management Change to ZUARI INDUSTRIES LIMITED
❖1998 –Plant capacity has enhanced to 5000 TPD (1.8MTPA- Clinker) .
❖2000 –50:50 Joint venture with Italcementi Group
❖2006 –Become 100 % share holder in ZCL.
❖2009 –Clinker production cap. increased to 1.8 to 2.0MTPA Clinker
❖2010 –Second Clinker Line(2.3 MTPA) Commissioned
❖2016 – Management took over by HEIDELBERG CEMENT
Slide 3
ZCL – Yerraguntla Plant
Installed Capacity (Clinker) - 4.3 mMTPA
Installed Capacity (Cement) - 5.4 mMTPA
Wind Power Installed Capacity - 6 MW
Solar Power Installed Capacity - 550 Kw
Product Range - OPC , PPC , PSC and MC
Slide 4
Energy Saving Projects Implemented during last 3 years
with No Investments
Sl. No.
Title of Project Year
Annual Electrical
Saving (kWh)
Annual Electrical
Cost Saving (Rs million)
Annual Thermal Saving
(Ton/year)
Annual Thermal
Saving (Rs million)
Total Annual Savings
(Rs million)
Investment Made
(Rs million)
Payback
(Mon)
1 Reduction of damper loss in line-2 cooler vent fan2014-
15158400 0.95 0.00 0.00 0.95 0.00 0
2 Optimization of Quarry Water Pumps2014-
15175200 1.05 0.00 0.00 1.05 0.00 0
3Optimized use of pet coke with red mud & Increased clinker production
2014-15
1500000 9.00 650.00 3.25 12.25 0.00 0
4 Optimization of Raw Mill grinding media2014-
15270000 1.62 0.00 0.00 1.62 0.00 0
5 Optimization of Cement Mill-3 grinding media2014-
15288000 1.73 0.00 0.00 1.73 0.00 0
6Optimization idle running power by logic modification
2014-15
401500 2.41 0.00 0.00 2.41 0.00 0
7 Punch plate removal in Raw mill-32014-
15693000 4.2 0 0 4.2 0 0
8Avoiding Coal crusher running during imported & pet coke unloading
2014-15
74880 0.4 0 0 0.4 0 0
9Reducing the line-2 water pump speed during kiln shut down
2015-16
20300 0.1 0.1 0 0
10 Replacement of diesel with pyrolysis oil2015-
16436 7.2 7.2 0 0
Slide 5
Energy Saving Projects Implemented during last 3 years
with No Investments
Sl. No.
Title of Project Year
Annual Electrical
Saving (kWh)
Annual Electrical Cost
Saving (Rs million)
Annual Thermal Saving
(Ton/year)
Annual Thermal Saving
(Rs million)
Total Annual Savings
(Rs million)
Investment Made
(Rs million)
Payback
(Mon)
11 Reduction of surface in 43 grade cement 2015-16
249480 1.6 1.6 0 0
12Coal Crusher bypass during fine (imported) coal unloading.
2015-16
149760 1.0 1.0 0 0
13 Increased OK mill PPC grinding2015-
16229635 1.5 1.5 0 0
14Maximizing unloading fly ash in bin instead of unloading in silo
2015-16
59705 0.4 0.4 0 0
15 Coal mill CA fan inlet damper removal2016-
1714932 0.1 0.1 0 0
16 K String PH fan trimming 2016-
17396000 2.4 2.4 0 0
17 Arresting leakages in VRM-12016-
17158400 1.0 1.0 0 0
18Arresting leakages in Line-1 PH and optimised PC fan
2016-17
198000 1.2 1.2 0 0
19 OK Mill Reject pipe modification2016-
17158400 1.0 1.0 0 0
20Installation of Fly ash feeding to mill discharge arrangement
2016-17
36324 0.2 0.2 0 0
Slide 6
Energy Saving Projects Implemented during last 3
years with Investments
Sl. No.
Title of Project Year
Annual Electrical Saving (kWh)
Annual Electrical Cost
Saving (Rs million)
Annual Thermal Saving
(Ton/year)
Annual Thermal Saving
(Rs million)
Total Annual Savings
(Rs million)
Investment Made
(Rs million)
Payback
(Months)
21Optimization of Raw mill-3 circuit air flow volume after reject BE installation
2014-15
2079000 12.47 0.00 0.00 12.47 9.00 8.7
22Reduction of Pressure drop across venturi in VRM-1
2014-15
726000 4.36 0.00 0.00 4.36 3.00 8.3
23 Optimization of coal transport blower in kiln-22014-
15363000 2.18 0.00 0.00 2.18 0.05 0.3
24 Line-2 Pyro section compressors Optimization2014-
151815000 10.89 0.00 0.00 10.89 1.00 1.1
25Line-2 Cement Mill section compressors Optimization
2014-15
1485000 8.91 0.00 0.00 8.91 1.00 1.3
26 Line-1 Pyro section compressors Optimization2014-
15360000 2.16 0.00 0.00 2.16 1.20 6.7
27 Optimization of pyro cooling water circuit 2014-
15363000 2.18 0.00 0.00 2.18 1.00 5.5
28Optimization of line-1 Cement cooling water circuit
2014-15
330000 1.98 0.00 0.00 1.98 1.00 6.1
29Reduction of pressure drop between bag house outlet to Fan inlet in CM-4
2014-15
330000 1.98 0.00 0.00 1.98 0.15 0.9
30 Street lights Optimization2014-
1562480 0.37 0.00 0.00 0.37 0.49 15.7
Slide 7
Energy Saving Projects implemented during last 3
years with Investments
Sl. No.
Title of Project Year
Annual Electrical Saving (kWh)
Annual Electrical
Cost Saving (Rs million)
Annual Thermal Saving
(Ton/year)
Annual Thermal
Saving (Rs million)
Total Annual Savings
(Rs million)
Investment Made
(Rs million)
Payback
(Months)
31Cement Mill-2 bag house fan replaced with high efficiency fan
2014-15
72600 0.44 0.00 0.00 0.44 3.00 82.6
32Optimization of Line-2 water pump by Installation of VFD
2015-16
486382 3.2 3.2 0.8 3.0
33Damper and LRS losses reduced by installation of VFD for CM-2 sepax fan
2015-16
316800 2.1 2.1 1.6 9.3
34Damper and LRS losses reduced by installation of VFD for CM-3 sepax fan
2015-16
356400 2.3 2.3 1.6 8.3
35Optimised EEL packer Bag filter by Instaltion of VFD
2015-16
158400 1.0 1.0 0.45 5.3
36 Line-2 PA Fan optimised by Instaltion of VFD 2015-
16158400 1.0 1.0 0.95 11.1
37Direct feeding of cement to EEL packer-2 vibrating screen bypassing CB-2 circuit
2015-16
633600 4.1 4.1 0.6 1.8
38 OK mill separator Felt seal arrangement 2015-
16150480 1.0 1.0 0.1 1.2
39Line-1 Calciner coal firing blower speed reduced by 10%
2015-16
198000 1.3 1.3 0.05 0.5
40 CM-2 Grinding media optimisation2015-
16522720 3.4 3.4 2.275 8.1
Slide 8
Energy Saving Projects implemented during last 3
years with Investments
Sl. No.
Title of Project Year
Annual Electrical Saving (kWh)
Annual Electrical Cost
Saving (Rs million)
Annual Thermal Saving
(Ton/year)
Annual Thermal Saving
(Rs million)
Total Annual Savings
(Rs million)
Investment Made
(Rs million)
Payback
(Months)
41Cooler vent fan HT motor replaced with LT Motor and installed VFD
2015-16
633600 4.1 4.1 1.6 4.7
42Installation of VFD for Line-1 Post Clinker Water Pupms
2015-16
157680 1.0 1.0 0.45 5.3
43Replacement of 250w HPSV street lights with 60 W LED lights
2015-16
48545 0.3 0.3 0.525 20.0
44Coal firing blower optimised with reducing blower speed by changing pully
2015-16
201818 1.3 1.3 0.05 0.5
45Installation of high efficiency bag house fan in cement mill -2
2015-16
31680 0.2 0.2 0.8 46.7
46Installation of high efficiency bag house fan in cement mill -3
2015-16
31680 0.2 0.2 0.8 46.7
47Installation of Solenoid Valve system In packing Plant for optimization of compressed air
2015-16
298935 1.9 1.9 0.6 3.7
48Rawmix optimisation after installation of crosbelt analyser
2016-17
477 2.73 2.7 18 79.2
49Avoiding pnumatic conveying by Installation of new steel silo for export and slag cement.
2016-17
330523 2.0 2.0 50 302.6
50Replacement of 250w HPSV street lights with 60 W LED lights
2016-17
138700 0.8 0.8 0.92 13.3
Slide 9
Energy Saving Projects implemented during last 3
years with Investments
Sl. No.
Title of Project Year
Annual Electrical Saving (kWh)
Annual Electrical
Cost Saving (Rs million)
Annual Thermal Saving
(Ton/year)
Annual Thermal Saving
(Rs million)
Total Annual Savings
(Rs million)
Investment Made
(Rs million)
Payback
(Months)
51 Installation of VFD for Coal Mill FK Pump2016-
17184800 1.1 1.1 1.0 10.8
52Optimisation of CF silo dedusting bag filter fan by Installing VFD
2016-17
158400 1.0 1.0 0.3 3.8
53Optimisation of post clinker compressor power by installing dedicated small compressor with VFD
2016-17
615938 3.7 3.7 1 3.2
54Replacement of line-1 VCLM CA Fan HT motor with high efficiency motor along with VFD
2016-17
209052 1.3 1.3 1.2 11.5
55 Calciner Coal firing points connecting to feed box2016-
17203 1.16 1.2 0.2 2.1
56 Coal Mill-2 separator rotor replacement2016-
17237600 1.4 1.4 0.5 4.2
57Increased usage of liquid pharma waste by installing storage system
2016-17
2877 16.47 16.5 12 8.7
Slide 10
710
712
714
716
718
720
722
724
726
2013-14 2014-15 2015-16 2016-17 2017-18Target
720
718
717
725
715
Specific Energy Consumption
Pet coke usage
56.0
57.0
58.0
59.0
60.0
61.0
62.0
63.0
64.0
65.0
66.0
67.0
2013-14 2014-15 2015-16 2016-17 2017-18Target
66.5
63.6
59.9
61.8
61.0
7.6 % Reduced
74.0
76.0
78.0
80.0
82.0
84.0
86.0
88.0
90.0
92.0
2013-14 2014-15 2015-16 2016-17 2017-18Target
91.5
85.5
82.1
82.181.1
11.4 % Reduced
Description Unit 2013-14 2014-15 2015-16 2016-17
Kiln-1 Utilization ( 4th stage PH ) % 57.5 43.6 27.6 65.8
Pet coke usage % 0 20.0 28.5 72.0
CK Ratio % 82.3 79.3 78.9 80.8
Slide 11
Specific energy consumption ZCL AchievedNational bench
markInternational bench mark
Thermal - Kcal/Kg clinker 725 667 660
Electrical-kWh/T of cement 82 67 65
Specific energy consumption
ZCL Achieved
ICL,Chilamkur
Bharathi Cements
UltratechCement
Thermal - Kcal/Kg clinker
725 834 722 723
Electrical-kWh/T of cement
82 102.5 78 84.1
Comparison with Global Benchmark Data
Comparison with nearest competitors
Global norms/Bench mark Data & Competitors
Slide 12
Energy conservation projects planned 2017-2018
Sl. No Title of Project Year
Estimated Annual
Electrical Savings
(kWh/year)
Thermal Savings
(Ton/year)
1 Kiln-1 K-String top HP cyclones (1A,1B&1C) modification to LP cyclone 2017-18 1650000
2 Kiln-1 Old Pre heater Fan replacing with high efficiency fan. 2017-18 1868545
3 Raw Mill-3 rollers and Mill internals modification 2017-18 848232
4 Kiln-1 cooler modification ( ABC inlet ) 2017-18 1422.4
5 Installation of line-1 fine coal dosing system 2017-18 1832
6 Reduction of Pressure drop in C - line bag house out let to fan inlet duct 2017-18 372240
7 Installation of Pyrojet burner for line-2 2017-18 916
8 Kiln-2 cooler modification ( ABC inlet ) 2017-18 1650
9 Replacement of 70w HPSV area lights with 30 W LED lights 2017-18 29200
10 Replacement of 250w HPSV street lights with 70 W LED lights 2017-18 131400
11 Installation of mill scan for cement mill-2 2017-18 435600
12 Installation of mill scan for cement mill-3 2017-18 435600
13 Installation of WHR system for Line-1 and Line-2 2017-18 83397600
Slide 13
2282 Kwh / day , 10.2 Tons of coal /Day
380 Lakhs per Annum
30 Lakhs
1 month
✓Pond ash is having higher moisture and high foreign materials ( wood, stone) resulted jamming
of chutes damaging belt conveyors.
✓Also unable to feed fly ash requirement to the Mill resulted lesser fly ash consumption and
frequent stoppages of the mill. ZCL developed vibro feeder as a pilot plant for improving feeding
and separating foreign materials
Increased usage of Pond Ash from 30% to 33.5%
Installing vibro feeder
Utilizing 100% pond ash for PPC production is first in India and In-housedesign of vibro feeder for separating foreign materials and improvingfeeding is known concept but applied differently and also it is beyond thescope of OEM and having high Replication Potential in the sector
Innovative project- 1: Increased usage of Pond Ash
Slide 14
✓ZCl installed Atox 20 coal mill in 1998. Mill Main drive is designed with LRS system for running
full speed 980 RPM for normal coal grinding. As a sustainable and cost economic initiative ZCL
decided to use pet coke for kiln firing. Main drive full speed is not required for Pet coke grinding
but present LRS system is not possible to control the speed. So ZCL decided to modify LRS system
to LRC system by Installing heat exchanger, installing circulating pump and arranged controlled
electrodes movements from CCR resulted Main drive speed reduced from 980 RPM to 760 RPM
Inhouse convertion of LRS system to LRC system in Atox-20 coal mill
Innovative project- 2 : Inhouse Convertion of LRS system to LRC system in Atox-20 coal mill
In-house modification of LRS system to LRCsystem is known concept but applieduniquely. This project is high ReplicationPotential for the similar companies
60 Kw
10.8 Lakhs per Annum
1.5 Lakhs
2 month
Slide 15
✓ATOX-55 is the first mill in Asia order by Zuari cement ltd with design capacity of 430 TPH. Mill is
taking higher power So ZCL decided to take the risk and modified the mill internals
1. Mill Fan trimming by 120 mm 2.Armour ring removed 3. Mill Internal Reject pipes extended
4.Water spray nozzle modified 5. Mill table area blocked by 50 Installed small receiver tanks for
critical locations
Innovative project- 3 : Optimization of VRM-2
Mill Fan Trimming
ZCL taken the risk and modified the mill internals . All those modifications are in-house andbeyond the scope of OEM and having high Replication Potential in the sector
0.5
Kwh / Ton of mat
77.3
Lakhs per Annum
After removing Armour ring Water SprayReject Pipe extension
Slide 16
Replacement of Electrical Energy with Renewable Energy
DescriptionInstalled Capacity
(kW)
2014-15 (million kWh)
% Share2015-16
(million kWh)%
Share2016-17
(million kWh)%
Share
Wind Energy 6000 3.08 1.19 14.81 6.68 16.31 6.27
Solar Energy 550 0.7 0.27 0.75 0.34 0.71 0.27
Total 3.79 1.46 15.57 7.02 17.01 6.54
Utilization of Renewable energy ( % of Total Energy)
Replacement of Thermal Energy with Renewable Energy
DescriptionFuel Savings in
2014-15 (million kcal/year)
% Share
Fuel Savings in 2015-16 (million
kcal/year)
% Share
Fuel Savings in 2016-17 (million
kcal/year)
% Share
Biomass 91324 4.80 83067 4.84 17165 2.8
Slide 17
Utilization of Waste as Fuel
Name of the Fuel
2014-2015 2015-2016 2016-2017Waste Fuel as
% of total energy used
Quantity of waste Fuel used (MT)
Heat Value (million
kcal/year)
Quantity of waste Fuel used (MT)
Heat Value (million
kcal/year)
Quantity of waste Fuel used (MT)
Heat Value (million
kcal/year)
Rice husk 11285 36891 13925 45855 5107 13568 1.75Ground nut shell 2744 8827 1790 6866 329 975 0.30Bangal gram 41 121 20 69 1 1 0.00Sun flower 0 0 0 0 0 0.00Sugar cane 42 107 59 203 0 1 0.01Coconut 1169 2490 33 104 1019 2287 0.09RDF 5683 13872 4931 17263 1426 4830 0.65Ecalyptus 5812 9415 0 1 2 0.17Areca nut waste 0 0 0 1 0 0.00Mangokarnel 1582 2977 173 648 0 2 0.07Carbon waste 0 0 0 0 0 0.00Dolachar 17242 41950 1862 5094 3031 8540 1.01Shredded tyres 0 0 424 2798 943 5697 0.15Jawar husk 9076 27019 6408.5 22513 119 326 0.91Supari Husk 0 0 0 0 0.00Subabul bark 1078 3475 1951 6809 1 3 0.19
Liquid Alternative Fuel 0 123.5 764 27 73 0.02
Spent carbon 0 630 1859 3655 4799 0.12
Liquid pharma waste 0 2543 6762 13187 16306 0.42
Solid pharma waste 0 2423 5781 14344 17963 0.43Solid cake 52 246 0.00
Total 55754 147145 37296 123390 43242 75620 6.29
Slide 18
YearScope 1
emissions CO2e (MT)
Scope 2 emissions CO2e (MT)
Scope 3 emissions CO2e (MT)
kg CO2e/ MTof
cement
MitigationTotal Reduction in emission intensity since baseline year
study CO2e (MT)
2013 (Baseline Year)
2005334 223291 304517 838 Baseline Year
2014 2170295 232377 273047 786 142,577
2015 1815948 185529 228503 773 -303,163
2016 2365370 214562 290683 773 337,473
2017 Target 2280667 215328 293333 761
GHG Emission Inventorisation
8.4 % Specific CO2 emission reduced compared to baseline year
Slide 19
GreenCo and ISO Cetification
GreenCo Gold , ISO 9001:2000 and ISO 14001 certified Cement Plant
Slide 20
% Investment for Energy Conservation Projects on turnover
S.No Description Units Investment
1 Total budget MINR 348.3
2 CBA MINR 20
3 ATS MINR 50
4 Silo MINR 54.5
5 VFD MINR 6
6 Bag filter MINR 5
7 Dip tubes MINR 20
8 PLC upgrade MINR 15
9 Nox measure MINR 4
10 Pharma waste syst MINR 25
11 Cooler esp MINR 17.5
12 Lights LED MINR 0.92
13 Total MINR 217.9
14 % in total budget % 63
15 Turnover of the Unit MINR 11660
16 % investment on turnover % 2
Slide 21
✓ Energy management cell formed with cross function team members.✓ The coordinator for the Energy management cell is Energy Manager.✓We launched ‘’CIP Continues improvement program‘’ program as plat form for key performance improvement✓ Ideas generation from the all the employees and tracking the work process based on the priority.✓ The daily review of energy monitoring by each section .✓Weekly review by plant head. ✓ Awards for the best idea & Energy savings implemented✓SMS alert system for stoppages to control the down time.
Monitoring , Reporting & Implementation Methodologies
Power Consumption Report for 21-Aug-15
Description
On Date MTD YTD
Prod
in
Ton
s
R.Hr
sTPH Kwh
Kw
h/H
r
Kw
h/
T
Of
mat
Kw
h/
T
Cli
Kw
h/
T
OP
C
K
w
h/
T
P
P
C
Kwh/
T
ceme
nt
Pro
d
in
Ton
s
R.Hr
sTPH Kwh
Kw
h/H
r
Kw
h/
T
Of
ma
t
Kw
h/
T
Cli
Kw
h/
T
OP
C
Kw
h/
T
PP
C
Kwh
/
T
cem
ent
Prod
in
Tons
R.
Hr
s
TPH Kwh
Kw
h/H
r
Kw
h/
T
Of
mat
Kw
h/
T
Cli
Kw
h/
T
OP
C
Kwh
/
T
PPC
Kwh
/
T
cem
ent
Crusher #3
MD
Aux
VRM
MD
Fan
Aux
KILN -2 &
Cooler
MD
ID Fan-1
ID Fan-2
BH Fan
C Vent fan
C Fans
Aux
VCLM
MD
Fan
Booster fan
Aux
OK Mill
MD
BH Fan
Booster fan
Aux
OK Mill
total
P.Plant
Utilities
All sections
Total
Incomer
power
Misc
Total
0.0 0.0 0.0 0.00.
00.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
Slide 22
Head production
DGM-process
Maintenance head
GM- Mech
Quality headG.M -QC
Head Electrical &
Instrumentation
Team 2:
Kiln & Coal mill section head &
engineers
Team 3:
Crushers & raw mill section engineers
Team 5:
Cement grinding
incharge & engineers
Team 4:
Packing & dispatch section
engineers
Plant Head S.V.P-Works
Energy Manager
Head MinesGM-Mines
Team 1:
Mines section head &
engineers
Energy Management Committee
Monitoring , Reporting & Implementation Methodologies
Energy Management Committee includes One Energy Auditor & Two Energy Managers :
➢ Mr. Jignesh Kumar Duva – DGM (Production) - EA
➢ Mr. P. Raghuram – DGM (Electrical & Instrumentation) - EM
➢ Mr. G.SaiSunil Bharathbabu – Dy. Manager (Electrical) - EM
Idea generation and Tracking Form
Slide 23
Team work Efforts made in Encon Projects
S.NoDescription of En-
Con ProjectSource of En-
Con Idea
Idea Originated
Year
Extent of man power involved
Progress of implementati
on
Methodology adopted to overcome the constraints
1
Avoiding pnumatic
conveying by Installation of
new steel silo for export and slag
cement.
Senior Management
2016-17
Mr.P.S Murthy D.G.M - Mech , Mr.Krishna Reddy
Sr.Manager - Elect Mr.Ravi subrahmanyam
Asst.Manager - Inst Mr.Satya Narayana Asst.Manager -
Mech
Implemented
1.New steel silo 2 no'sInstalled 2. Ensuring Grinding of PSC and Export in steel silos
3.Planning the dispatch accordingly
2
Replacement of VCLM CA fan HT motor with high efficiency motor along with VFD
Engineer 2016-17
Mr. P.Raguram D.G.M – E&I , Mr.Janardhan Reddy Dy.Man
- Mech , Mr.Madhu babu Man - Op Mr.Subba Reddy
Sr.Man -Inst Mr.Satyanarayana D.M –
Elect
Implemented1.HT motor replaced with LT motor 2. VFD installed
3. Reducing fan speed
3
Optimization of CF silo dedusting bag filter fan by Installing VFD
Workmen 2016-17
Mr.G.Venkateshwarlu S.M-Op , Mr.Ashok Kumar D.M - Inst Mr.N.Rajesh A.M-Elect Mr.
Ravi Varman D.M-Mech
Implemented
1.Core team formed for monitoring the bag filter
2.VFD installed 3. Reducing fan speed
Slide 24
Team work Efforts made in Encon Projects
S.NoDescription of En-
Con ProjectSource of En-
Con Idea Idea Originated
Year Extent of man power
involved
Progress of implementatio
n
Methodology adopted to overcome
the constraints
4
Installation of Fly ash feeding to mill
discharge arrangement
Supervisor 2016-17
Mr.Phani Kiran Manager-Prod , Mr.
Murali Sr.Man -Mech , Mr.Subramanyam
Sr.Officer -Op , Mr.Ragava employee
- Prod
Implemented
1.Extended Airslide 2.Arranged chute to feed fly ash in BE 3.
Continuous monitoring of quality
and power
5
Raw mix optimization after
installation of crosbelt analyzer
Top Management
2016-17
Mr.K.Suresh G.M-QC , Mr.Nareshkumar
A.G.M -Proces ,Mr.Madhusudan
Sr.Officer - Op , Mr. P.Ramesh AGM -Inst
Implemented
1.Installed cross belt analyzer 2.Continuous
monitoring of the quality parameters.
6Installation of VFD
for Coal Mill FK Pump
Engineer 2016-17
Mr. K.Ravi , Manager-Mech, Mr. Subhash, Engineer-Process, Mr.Sunil-
Man- Elec , Mr. Srinivas DM –Inst
Implemented
1.Core team formed for study FK pump2.VFD installed 3.
Reducing fan speed
Slide 25
Best Suggestion
Ideas Contribution
Rcognisation Program for Encon Efforts
Slide 26
……..aiming to conserve natural resources
26
When we heal the earth, we heal ourselves ~ David Orr
Great things are not done by impulse, but by a series of small things
brought together