Data Date 20APR05Run Date 27APR05 14:24
3 MONTH ROLLING PROGRAMMEMonthly Update
Detailed Works Progr.(DWP) re
Progress Bar
Critical Activity
Act.ID
ActivityDescription
OrigDur
EarlyStart
EarlyFinish
%Compl.
DWP %Compl.
RemDur
TotalFloat
VarianceEarly Finish
GENERAL & PRELIMINARIESSUBMITTALS & APPROVALSDRAWING SUBMITTAL & APPROVAL
8014 Prep. & Sub. Combined Services Dwgs for ENT 48 20MAR04A 07JUN05 85 100 40 56 -371
8023 Prep.&Sub. Independ't Services Dwgs for ENT 48 24JUN04A 17JUN05 85 100 48 56 -295
8031 Prep. & Sub. Comb. Services Dwgs for SHT&T3&LCK 48 20JUL04A 17JUN05 87 100 48 116 -247
8034 Prep.&Sub. Independ't Serv. Dwgs for SHT&T3&LCK 48 04AUG04A 17JUN05 85 100 48 116 -157
8024 Engineer Comment / Approve ENT ISD Submissions 18 06AUG04A 11MAY05 60 100 18 56 -247
8030 Res-sub. & Approv of ENT ISD 24 06SEP04A 19MAY05 20 100 24 56 -229
8035 Engineer Comment / Approve SHT&T3LCK ISD Sub. 24 13SEP04A 30JUL05 55 100 84 116 -169
8032 Engineer Comment / Approve SHT&T3&LCK CSD Sub. 18 25OCT04A 17JUN05 25 100 48 116 -229
8033 Re-sub. & Approv. of SHT & T3 & LCK CSD 24 18JUN05 16JUL05 0 100 24 116 -229
SEM INTERFACE WITH SHT & T3SHATIN HEIGHTS TUNNEL
2458 Apprv.for Det.Engineering of Tnnl.Vent.Fans 24 08JUL04A 19MAY05 80 100 24 66 -356
2463 Order Tnnl.Vent.Fans 0 15JUL05 0 100 0 19 -403
SHT RC FULL ENCLOSURE2473 Apprv.for Det.Engineering of Encl.Vent.Fans 12 07JUL04A 04MAY05 80 100 12 86 -407
T3 UNDERPASS2481 Apprv.for Det.Engineering of T3 Underpass 12 07JUL04A 04MAY05 80 100 12 86 -407
FEB MAR APR MAY JUN JUL AUG17 18 19 20 21 22 2
7 14 21 28 7 14 21 28 4 11 18 25 2 9 16 23 30 6 13 20 27 4 11 18 25 1 8 1
© Primavera Systems, Inc.
LEIGHTON - KUMAGAI JVR8- EAGLE'S NEST TUNNEL
DETAILED WORKS PROGRAMME REVISION C
Proj. Name: W06CLayout: 3 MONTHS ROLLING PROGRAMMEFilter: 3 MONTH ROLLING PROGRAMMECurrent Proj: W06CTarget 1 Proj: BLRCTaget 2 Proj: MSRB
Sheet 1 of 35
LKJV/ENT/DWP/BDate Revision CheckedApproved
26APR05Prog update April 05 IT RB
Sheet 2 of 35
Act.ID
ActivityDescription
OrigDur
EarlyStart
EarlyFinish
%Compl.
DWP %Compl.
RemDur
TotalFloat
VarianceEarly Finish
LAI CHI KOK VIADUCTSUBMITTALS & APPROVALS E&M EQPT./MTRL SUBMITTALS
8313 LCKVd-Sub. Enclosure Lgt sys (incl Excision NEs) 78 02JUL04A 23JUL05 80 0 78 -49 11
E&M EQPT./MTRL.APPROVALS BY ENGINEER8314 LCKVd-App.Enclosure Lgt sys (incl Excision NEs) 18 05AUG04A 26OCT05 30 0 156 -49 -49
BUTTERFLY VALLEYSUBMITTALS & APPROVALSGENERAL
1079 WA2 Mines Approval Slope BV-S2 blasting 6 17MAR05A 22MAR05A 100 100 0 -137
DESIGN & ENGINEERING PERMANENT WORKS
1654 Eng Approve Dsg Shek Lei Pui Water Tr. Works 12 18JAN05A 26APR05 50 100 6 -37 -146
1655 ApprovedConstr.Dwgs Shek Lei Pui Water Tr. Works 0 05MAY05 0 100 0 -37 -146
CONSTRUCTION WORKSEARTHWORKS & SLOPEWORKSSITE CLEARANCE & TEMPORARY ACCESS
2235 WA2 Slope Site Clearance BV-S2 90 22DEC03A 26APR05 95 100 6 -204 -213
2345 WA2 Haul Rd Ch 1+830 - 2+020 36 26JUL04A 04MAY05 90 100 12 -38 -198
2344 WA1 Haul Rd Ch.1+620-1+830 22 01DEC04A 04MAY05 90 100 12 205 -254
SLOPE 11NW-A/C4353794 11NW-A/C435 hydro-seeding & tensar mat 24 11MAR05A 20APR05 90 100 1 472 -305
SLOPE SP-S2 & SP-S3EXCAVATION (SOFT & ROCK)
1111 New Activity - 200dia watermain diversion + test 63 20APR05* 06JUL05 0 N/A 63 -64 0
1109 SP-S2/S3 Slope excavation 12 07JUL05 20JUL05 0 100 12 -64 -304
SLOPE STABILISATION (SOIL NAILS,ROCK BOLTS ETC)
1110 SP-S2/S3 Inst.Soil Nails & Test (97nr.w/3rig) 18 14JUL05 03AUG05 0 100 18 -64 -304
SLOPE BV-S2EXCAVATION (SOFT & ROCK)
2681 BV-S2/6 Slope excavation (soft & rock) 58 24JAN05A 26MAR05A 100 100 0 -123
FEB MAR APR MAY JUN JUL AUG17 18 19 20 21 22 2
7 14 21 28 7 14 21 28 4 11 18 25 2 9 16 23 30 6 13 20 27 4 11 18 25 1 8 1
Sheet 2 of 35
Sheet 3 of 35
Act.ID
ActivityDescription
OrigDur
EarlyStart
EarlyFinish
%Compl.
DWP %Compl.
RemDur
TotalFloat
VarianceEarly Finish
EXCAVATION (SOFT & ROCK)
1078 BV-S2 - Trial Blasting 10 20APR05 30APR05 0 100 10 -204 -193
2683 BV-S2/7 Slope excavation (soft & rock) 56 03MAY05 09JUL05 0 100 56 -204 -179
2689 BV-S2/8 Slope excavation (rock & soft) 82 19JUL05 25OCT05 0 82 -204 -179
SLOPE STABILISATION (SOIL NAILS,ROCK BOLTS ETC)
2697 BV-S2/7 Row E2/E3 Soil Nail & Test 100nr.w/3.rig 19 27JUN05 19JUL05 0 100 19 -198 -179
2688 BV-S2/7 Inst.Rock bolts & Test (12nr.w/1.rig) 13 09JUL05 23JUL05 0 100 13 -204 -179
2684 BV-S2/7 Row D3/D4 Soil Nails & Test 49nr.w/2.rig 14 20JUL05 04AUG05 0 100 14 -198 -179
HYDRO-SEEDING & TENSAR MAT
3802 BV-S2 Berm 5 hydro-seeding & tensar mat 10 02FEB05A 26APR05 80 100 6 431 -175
3803 BV-S2 Berm 6 hydro-seeding & tensar mat 12 05MAY05 19MAY05 0 100 12 425 -119
SURFACE DRAINAGE
3693 BV-S2 Berm 6 Surface drainage 12 23MAR05A 04MAY05 50 100 12 393 -119
SLOPE BV-S3COMPACTED FILLING
2702 BV-S3 Compact Fill to +48.5mPD ch.1+740 to 1+860 72 20APR05 16JUL05 0 100 72 -154 -198
1987 BV-S3 Compact Fill to +56.0mPD ch.1+740 to 1+860 72 12MAY05 06AUG05 0 100 72 -154 -198
SURFACE DRAINAGE
1981 BV-S3 Slope Surface Drainage +33.5mPD 12 10JUN05 24JUN05 0 100 12 -143 -198
1982 BV-S3 Slope Surface Drainage +41.0mPD 37 09JUL05 20AUG05 0 100 37 -154 -198
SLOPE BV-S4EXCAVATION (SOFT & ROCK)
2355 BV-S4/3a Excav.slope [soft] 7 15APR05A 25APR05 15 100 5 205 -214
2368 BV-S4 Excavate CLP Cable Trough [soft] 24 20APR05 19MAY05 0 100 24 27 -314
2357 BV-S4/4a Excav.slope [soft] 7 12MAY05 20MAY05 0 100 7 205 -212
2359 BV-S4/5 Excav.slope [soft] 7 13JUN05 20JUN05 0 100 7 205 -212
SLOPE STABILISATION (SOIL NAILS,ROCK BOLTS ETC)
2367 New Act - 11NW-A/C434 - Soil Nail & Test 21 20JAN05A 04MAY05 84 100 12 211 -191
2352 BV-S4/4b Row A2/A3 Soil Nail & Test 28nr.w/2rig 13 20APR05 05MAY05 0 100 13 38 -280
FEB MAR APR MAY JUN JUL AUG17 18 19 20 21 22 2
7 14 21 28 7 14 21 28 4 11 18 25 2 9 16 23 30 6 13 20 27 4 11 18 25 1 8 1
Sheet 3 of 35
Sheet 4 of 35
Act.ID
ActivityDescription
OrigDur
EarlyStart
EarlyFinish
%Compl.
DWP %Compl.
RemDur
TotalFloat
VarianceEarly Finish
SLOPE STABILISATION (SOIL NAILS,ROCK BOLTS ETC)
2356 BV-S4/3 Row A1 Soil Nail & Test 29nr.w/1rig 16 22APR05 11MAY05 0 100 16 205 -212
2349 BV-S4/3 Row C5/C6 Soil Nail & Test 77nr.w/2rig 22 05MAY05 31MAY05 0 100 22 211 -320
2358 BV-S4/4a Row A2/A3 Soil Nail & Test 67nr.w/2rig 19 20MAY05 10JUN05 0 100 19 205 -212
2361 BV-S4/5 Row A4 Soil Nails & Test 25nr.w/1rig 14 20JUN05 06JUL05 0 100 14 205 -212
SLOPE FINISHES
1137 (BV-S4) RC CLP Cable Trough 54 20MAY05 23JUL05 0 100 54 27 -276
SURFACE DRAINAGE
3714 11NW-A/C434 Surface Drainage 8 03JAN05A 26APR05 80 100 6 247 -214
3705 BV-S4/3 Surface Drainage 8 01JUN05 09JUN05 0 100 8 211 -320
3706 BV-S4/4 Surface Drainage 12 10JUN05 24JUN05 0 100 12 214 -220
3707 BV-S4/5 Surface Drainage 10 07JUL05 18JUL05 0 100 10 205 -212
SLOPE SP-S1EXCAVATION (SOFT & ROCK)
1330 SP-S1 Bulk Exc.to formation (rock) NB/SB 18 21MAR05A 04MAY05 50 100 12 -113 -147
SURFACE DRAINAGE
3711 Sp-S1/4 Surface Drainage 7 06JUL04A 27APR05 40 100 7 466 -217
RC STRUCTURESRETAINING WALL BV-R1PILING WORKS
1140 BV-R1(C) Pre-Bore & Report 14 20JUL05 04AUG05 0 100 14 -100 -179
RETAINING WALL BV-R2PILING WORKS
1113 BV-R2(C) Pre-Bore & Report 6 18MAR05A 31MAR05A 100 100 0 -165
1114 BV-R2(C) Bored Pile 6nr. 42 12APR05A 28MAY05 20 100 32 -95 -158
1115 BV-R2(C) Bored Pile Test & Report 8 14JUN05 22JUN05 0 100 8 -95 -158
CONCRETE WORKS
1121 BV-R2(B) RC Ret.Wall 30 11MAR05A 06APR05A 100 100 0 11
1116 BV-R2(C) Pile Capping Beam 12 30JUN05 14JUL05 0 100 12 -95 -136
1117 BV-R2(C) RC Wall 30 15JUL05 18AUG05 0 100 30 -95 -136
FEB MAR APR MAY JUN JUL AUG17 18 19 20 21 22 2
7 14 21 28 7 14 21 28 4 11 18 25 2 9 16 23 30 6 13 20 27 4 11 18 25 1 8 1
Sheet 4 of 35
Sheet 5 of 35
Act.ID
ActivityDescription
OrigDur
EarlyStart
EarlyFinish
%Compl.
DWP %Compl.
RemDur
TotalFloat
VarianceEarly Finish
FINISHES
1123 BV-R2 Wall finishes 60 23JUN05 01SEP05 0 0 60 297 -46
BACKFILLING
1122 BV-R2(A&B) Granular Drain & Compacted Backfill 36 07APR05A 02JUN05 5 0 36 303 0
RETAINING WALL BV-R3CONCRETE WORKS
2760 BV-R3(A) RC Base Slab 5 12MAY05 18MAY05 0 100 5 -7 -141
2761 BV-R3(A) RC Ret.Wall 8 19MAY05 27MAY05 0 100 8 -2 -141
2762 BV-R3(B) RC Base Slab 5 19MAY05 24MAY05 0 100 5 -7 -141
2763 BV-R3(B) RC Ret.Wall 8 25MAY05 02JUN05 0 100 8 -7 -141
BACKFILLING
2764 BV-R3 Granular Drain & Compacted Backfill 12 03JUN05 17JUN05 0 100 12 -7 -141
STEPPED CHANNEL & BOX CULVERTCONCRETE WORKS
1158 Box culvert bay 1,2,3,4 35 01DEC04A 09APR05A 100 100 0 -167
FILLING
1914 Fill over box culvert bays 1,2,3,4 18 20APR05 11MAY05 0 100 18 -7 -175
2714 Fill behind stepped channel bay 3-4 8 20APR05 28APR05 0 100 8 67 -332
INLET HEADWALLS INLET HEAD WALL
3715 Inlet headwall @SP-S2/3 30 21JUL05 24AUG05 0 100 30 368 -304
WSD WORKSWSD 900 MAIN DIVERSION
1171 Pipe bridge 'A' (DN900) fnds.only 66 20APR05* 09JUL05 0 100 66 263 -358
1173 Pipe bridge 'C' - DN900 30 29APR05 04JUN05 0 100 30 67 -230
1174 Inst.DN900 pipe (incl.thrust blocks) to BV-S4 66 11JUL05 26SEP05 0 100 66 287 -258
1928 Pipe bridge 'A' (DN900) - Bridge section 90 11JUL05 26OCT05 0 100 90 263 -264
1929 Inst.900.dia pipe (incl.thrust blocks) westside 90 11JUL05 26OCT05 0 100 90 263 -264
WSD 2x600 MAIN DIVERSION1169 Inst.2xDN600 WSD Pipe down BV-S2/6-7 90 20APR05 06AUG05 0 100 90 -50 -141
FEB MAR APR MAY JUN JUL AUG17 18 19 20 21 22 2
7 14 21 28 7 14 21 28 4 11 18 25 2 9 16 23 30 6 13 20 27 4 11 18 25 1 8 1
Sheet 5 of 35
Sheet 6 of 35
Act.ID
ActivityDescription
OrigDur
EarlyStart
EarlyFinish
%Compl.
DWP %Compl.
RemDur
TotalFloat
VarianceEarly Finish
WSD 2x600 MAIN DIVERSION1166 Construct DN600 Pipe Bridge 'D' 18 18JUN05 09JUL05 0 100 18 -7 -141
1164 Inst.DN600 WSD Pipe in Pipe Tunnel & valley 36 11JUL05 20AUG05 0 100 36 -7 -108
WSD 200 MAIN2338 Inst.DN200 pipe (incl.thrust blocks) to BV-S4 60 25JUL05 04OCT05 0 100 60 27 -270
TERRAIN MITIGATIONNTMM - BV-S2
2389 NTMM - Site Clearance 18 03MAR05A 11APR05A 100 100 0 -116
2391 NTMM - Inst.Raking Drains 33 12APR05A 13MAY05 33 100 20 -105 -110
2392 NTMM - Constr.Peforated Drain Channel 24 14MAY05 13JUN05 0 100 24 -105 -110
2350 NTMM - Afforestation of Area 60 14JUN05 23AUG05 0 70 60 369 -110
RECREATED STREAM3808 Recreated stream DN525 pipe (east) ch.1+740 18 29APR05 21MAY05 0 100 18 182 -273
EXCISION WORKS - NOISE BARRIERS & ENCLOSURESNOISE SEMI-ENCLOSURE [SB)
2738 SB Semi-Encl.Fnds. - Piling (C3,C4,I2) 24 27MAY05 24JUN05 0 100 24 -92 -108
1177 SB Semi-Encl.Fnds. - Piling (C3) 17 04JUN05 24JUN05 0 100 17 -92 -115
2734 SB Semi-Encl.Fnds. - Piling (C4) 21 25JUN05 20JUL05 0 100 21 -92 -115
2739 SB Semi-Encl.Fnds.- RC Base (C3,C4,I2) 51 25JUN05 24AUG05 0 100 51 -85 -108
2736 SB Semi-Encl.Fnds.- Piling (I2) 13 21JUL05 04AUG05 0 100 13 -82 -115
SB/NB ROADWORKS & FINISHES ROADS - FORMATION FILLING
1103 BV Compact.Fill to Form.ch.1+920 to 2+020 84 14JUN04A 31MAY05 65 100 34 -92 -76
1102 BV Compact.Fill to Form.ch.2+020 - 2+200 48 11AUG04A 26MAY05 55 100 30 -92 -108
DRAINAGE
2381 SB/NB Sth.Appr.Rd.Drainage ch.2+030 - 2+200 114 27MAY05 12OCT05 0 80 114 -49 -108
FEB MAR APR MAY JUN JUL AUG17 18 19 20 21 22 2
7 14 21 28 7 14 21 28 4 11 18 25 2 9 16 23 30 6 13 20 27 4 11 18 25 1 8 1
Sheet 6 of 35
Sheet 7 of 35
Act.ID
ActivityDescription
OrigDur
EarlyStart
EarlyFinish
%Compl.
DWP %Compl.
RemDur
TotalFloat
VarianceEarly Finish
EVA ROADWORKS & FINISHESSB (EAST SIDE) EVA ROADWORKSDRAINAGE
1979 SB EVA rd.drainage (east) ch.2+000 to 2+200 31 11APR05A 04MAY05 50 0 12 303 55
1978 SB EVA rd.drain testing (east) ch.2+000 to 2+200 18 05MAY05 26MAY05 0 0 18 303 55
EXCISION WORK-SHEK LEI PUI WATER TREATMENT PLANT1618 Soilid Barrier Type II - Foundations 21 30NOV04A 24MAR05A 100 100 0 -64
1619 Soilid Barrier Type I - Foundations 17 13DEC04A 28APR05 80 100 8 -26 -73
1621 Soilid Barrier Type IV - Foundations 18 20DEC04A 04MAY05 40 100 12 18 -27
2747 Soilid Barrier Type II - Structural Steelwork 30 20APR05 26MAY05 0 100 30 -54 -82
2748 Soilid Barrier Type I - Structural Steelwork 18 27MAY05 17JUN05 0 100 18 -48 -82
2751 Soilid Barrier Type II - Cladding 30 27MAY05 02JUL05 0 100 30 -54 -82
2749 Soilid Barrier Type III - Structural Steelwork 24 18JUN05 16JUL05 0 100 24 -48 -81
2752 Soilid Barrier Type I - Cladding 18 04JUL05 23JUL05 0 100 18 -54 -82
2750 Soilid Barrier Type IV - Structural Steelwork 18 18JUL05 06AUG05 0 60 18 -42 -81
2753 Soilid Barrier Type III - Cladding 24 25JUL05 20AUG05 0 20 24 -54 -82
ENT SOUTH PORTAL VENTILATION BUILDINGSUBMITTALS & APPROVALSE&M EQPT.& MATERIAL.SUBMITTALS
8201 EntSpBldg-Sub.MVAC MCC, power & control sys 54 02JUL04A 24JUN05 75 100 54 26 -88
8204 EntSpBldg-Sub.TVF, Ductworks & Control sys 78 02JUL04A 23JUL05 80 100 78 44 -91
8209 EntSpBldg-Sub.HV/`LV main & submain cable sys 54 02JUL04A 24JUN05 70 100 54 2 -55
8212 EntSpBldg-Sub.FS AFA & FM200 sys 54 05JUL04A 24JUN05 90 0 54 170 46
8490 EntSpBldg-Sub. building related luminaires 54 06JUL04A 24JUN05 80 90 54 50 -44
8203 EntSpBldg-Sub.LV power dist. sys 54 07JUL04A 24JUN05 85 100 54 -16 -79
8210 EntSpBldg-Sub.MVAC mech.vent. sys 54 03AUG04A 24JUN05 80 80 54 116 -40
FEB MAR APR MAY JUN JUL AUG17 18 19 20 21 22 2
7 14 21 28 7 14 21 28 4 11 18 25 2 9 16 23 30 6 13 20 27 4 11 18 25 1 8 1
Sheet 7 of 35
Sheet 8 of 35
Act.ID
ActivityDescription
OrigDur
EarlyStart
EarlyFinish
%Compl.
DWP %Compl.
RemDur
TotalFloat
VarianceEarly Finish
E&M EQPT.& MATERIAL.SUBMITTALS8207 EntSpBldg-Sub.FS wet sys 54 05AUG04A 24JUN05 95 100 54 128 -77
8208 EntSpBldg-Sub.MVAC / TVF pneumatic sys 54 14AUG04A 17JUN05 50 0 48 122 107
8200 EntSpBldg-Sub.CMCS & ELV sys 78 26AUG04A 23JUL05 65 90 78 50 -67
8206 EntSpBldg-Sub.PD cleans. & flush water sys 54 20OCT04A 20JUN05 90 100 50 146 -79
8211 EntSpBldg-Sub.MVAC Package AC Units 54 17JAN05A 24JUN05 85 0 54 182 89
8205 EntSpBldg-Sub.PD irrig. sys 54 04FEB05A 30JUL05 50 100 54 62 -113
1922 SP.Bldg. - Prep & submit louvre details 24 11JUL05 06AUG05 0 100 24 -82 -115
1940 SP.Bldg. - Prep & sub balustrade & metal wks 24 11JUL05 06AUG05 0 100 24 -88 -113
1942 SP.Bldg. - Prep & sub aluminium cladding 24 11JUL05 06AUG05 0 100 24 -82 -115
E&M EQPT.& MATERIAL APPROVALS6001 EntSpBldg-App. HV power dist. sys 18 14JUL04A 11MAY05 85 100 18 -28 -49
6002 EntSpBldg-App. LV power dist. sys 18 13AUG04A 11MAY05 70 100 18 -16 -25
8491 EntSpBldg-App. building related luminaires 18 18AUG04A 11MAY05 60 0 18 50 10
6006 EntSpBldg-App. FS wet sys 18 04SEP04A 11MAY05 60 0 18 128 -23
6036 EntSpBldg-App. FS AFA & FM200 sys 18 14SEP04A 11MAY05 55 0 18 170 100
6192 EntSpBldg-App. of CMCS & ELV sys 18 20SEP04A 11MAY05 45 0 18 50 11
6005 EntSpBldg-App. MVAC mech.vent. sys 18 23SEP04A 11MAY05 35 0 18 116 14
6003 EntSpBldg-App. PD cleans. & flush water sys 18 04NOV04A 11MAY05 40 100 18 146 -29
6742 EntSpBldg-App. MVAC MCC, power & control sys 18 12NOV04A 11MAY05 50 100 18 26 -34
6760 EntSpBldg-App. TVF, Ductworks & Control sys 18 12NOV04A 11MAY05 40 90 18 44 -13
7615 EntSpBldg-App. HV/LV main & submain cable sys 18 07DEC04A 11MAY05 35 10 18 2 -1
6013 EntSpBldg-App. MVAC Package AC Unit sys 18 01FEB05A 11MAY05 30 0 18 182 143
FEB MAR APR MAY JUN JUL AUG17 18 19 20 21 22 2
7 14 21 28 7 14 21 28 4 11 18 25 2 9 16 23 30 6 13 20 27 4 11 18 25 1 8 1
Sheet 8 of 35
Sheet 9 of 35
Act.ID
ActivityDescription
OrigDur
EarlyStart
EarlyFinish
%Compl.
DWP %Compl.
RemDur
TotalFloat
VarianceEarly Finish
EAGLES NEST TUNNELSUBMITTALS & APPROVALS E&M EQPT./ MTRL.DETAIL SUBMITTAL
8214 EntRtNb-Sub.Tunnel Lgt sys 78 02JUL04A 23JUL05 80 100 78 -64 -199
8216 EntRtNb-Sub.LV main & submain dist sys 54 02JUL04A 24JUN05 70 100 54 -52 -183
8217 EntRtNb-Sub.TVS control sys 54 02JUL04A 24JUN05 80 90 54 68 -49
8220 EntRtSb&VA-Sub.TVS control sys 54 02JUL04A 24JUN05 80 100 54 68 -61
8222 EntRtSb&VA-Sub.LV main & submain dist. sys 54 02JUL04A 24JUN05 70 100 54 -64 -193
8223 EntRtSb&VA-Sub.Tunnel Lgt sys 78 02JUL04A 23JUL05 80 100 78 -67 -202
8215 EntRtNb-Sub.FS AFA & Linear sys 54 05JUL04A 20JUN05 90 100 50 -82 -261
8219 EntRtSb&VA-Sub.FS AFA & Linear sys 54 05JUL04A 20JUN05 90 100 50 -82 -270
8218 EntRtNb-Sub.TVS in Tunnel 54 07JUL04A 24JUN05 80 100 54 -76 -193
8224 EntRtSb&VA-Sub.TVS in Tunnel 54 07JUL04A 11MAY05 80 100 18 -76 -169
8213 EntRtNb-Sub.CMCS & ELV sys 78 26AUG04A 23JUL05 65 100 78 20 -145
8221 EntRtSb&VA-Sub.CMCS & ELV sys 78 26AUG04A 23JUL05 65 100 78 20 -151
E&M EQPT./MTRL.APPROVAL BY ENGINEER7618 EntRtSb&VA-App. TVS in Tunnel 18 29JUL04A 11MAY05 70 100 18 -76 -151
7621 EntRtNb-App. TVS in Tunnel 18 29JUL04A 11MAY05 70 100 18 -76 -139
6808 EntRtSb&VA-App. Tunnel Lgt sys 18 05AUG04A 07MAY05 60 100 15 -67 -121
6878 EntRtNb-App. Tunnel Lgt sys 18 05AUG04A 11MAY05 60 100 18 -64 -121
6802 EntRtSb&VA-App. LV main & submain dist. sys 18 13AUG04A 11MAY05 35 100 18 -64 -139
6882 EntRtNb-App. LV main & submain dist. sys 18 13AUG04A 11MAY05 35 100 18 -52 -129
6785 EntRtSb&VA-App. FS AFA & Linear sys 18 14SEP04A 11MAY05 55 100 18 -82 -220
6880 EntRtNb-App. FS AFA & Linear sys 18 14SEP04A 11MAY05 55 100 18 -82 -211
6798 EntRtSb&VA-App. CMCS & ELV sys 18 20SEP04A 11MAY05 35 100 18 20 -73
FEB MAR APR MAY JUN JUL AUG17 18 19 20 21 22 2
7 14 21 28 7 14 21 28 4 11 18 25 2 9 16 23 30 6 13 20 27 4 11 18 25 1 8 1
Sheet 9 of 35
Sheet 10 of 35
Act.ID
ActivityDescription
OrigDur
EarlyStart
EarlyFinish
%Compl.
DWP %Compl.
RemDur
TotalFloat
VarianceEarly Finish
E&M EQPT./MTRL.APPROVAL BY ENGINEER6877 EntRtNb-App. CMCS & ELV sys 18 20SEP04A 11MAY05 45 100 18 20 -67
6795 EntRtSb&VA-App. TVS control sys 18 12NOV04A 11MAY05 60 40 18 68 -7
6884 EntRtNb-App. TVS control sys 18 12NOV04A 11MAY05 60 0 18 68 5
DESIGN & ENGINEERING PERMANENT WORKS TUNNEL
1667 Design/ICE Check X-passage/Adit Fire Doors 36 20APR05 02JUN05 0 100 36 -147 -202
1668 Eng Approve Dsg X-passage/Adit Fire Doors 12 03JUN05 17JUN05 0 100 12 -147 -202
1669 Issue Constr Dwgs X-passage/Adit Fire Doors 0 25JUN05 0 100 0 -147 -202
PROCUREMENT - MATERIALTUNNEL
1705 Order/Manuf/Del X-passages Forms 78 26APR04A 19APR05A 100 100 0 -118
1685 Order/Manufact/Del Fire Doors 100 27JUN05 25OCT05 0 95 100 -147 -152
NORTHBOUND TUNNEL6883 EntRtNb-Proc & Manuf. FS AFA & Linear sys 180 12MAY05 14DEC05 0 100 180 -82 -211
6885 EntRtNb-Proc & Manuf. ES Cabling 180 12MAY05 14DEC05 0 70 180 -52 -129
7622 EntRtNb-Proc & Manuf. TVS in Tunnel 180 12MAY05 14DEC05 0 70 180 -76 -139
6881 EntRtNb-Proc & Manuf. Tunnel Lgt sys 180 28JUN05 08FEB06 0 70 180 -102 -159
6879 EntRtNb-Proc & Manuf. CMCS & ELV sys 180 25JUL05 06MAR06 0 30 180 -40 -127
SOUTHBOUND TUNNEL & V.A TUNNEL6786 EntRtSb&VA-Proc & Manuf. FS AFA & Linear sys 180 12MAY05 14DEC05 0 100 180 -82 -220
7619 EntRtSb&VA-Proc & Manuf. TVS in Tunnel 180 12MAY05 14DEC05 0 80 180 -76 -151
6803 EntRtSb&VA-Proc & Manuf. ES Cabling 180 31MAY05 04JAN06 0 80 180 -79 -154
6809 EntRtSb&VA-Proc & Manuf. Tunnel Lgt sys 180 28JUN05 08FEB06 0 70 180 -108 -162
FEB MAR APR MAY JUN JUL AUG17 18 19 20 21 22 2
7 14 21 28 7 14 21 28 4 11 18 25 2 9 16 23 30 6 13 20 27 4 11 18 25 1 8 1
Sheet 10 of 35
Sheet 11 of 35
Act.ID
ActivityDescription
OrigDur
EarlyStart
EarlyFinish
%Compl.
DWP %Compl.
RemDur
TotalFloat
VarianceEarly Finish
MAJOR EQUIPMENT DELIVERYTUNNEL
3590 Order/Manufact/Deliver - Travelling Forms (SP) 150 06MAR04A 21MAY05 83 100 26 -102 -108
CONSTRUCTION WORKSTUNNEL PREPARATION WORKSTUNNEL LININGNORTH PORTAL
1278 Erect Lining Form SB at Toll Plaza (NP) 24 19FEB05A 07APR05A 100 100 0 -170
3221 Erect OHVD form NB at Toll Plaza (NP) 24 02MAR05A 23MAR05A 100 100 0 -128
3177 Erect OHVD Form SB at Toll Plaza (NP) 24 11APR05A 04MAY05 100 100 12 -168
NORTHBOUND TUNNEL DRIVETUNNEL EXCAVATION & PRIMARY SUPPORTNORTH PORTAL
3015 D&B NB 39m Tch.2+502 to 2+463 fr.NP 6 12MAR05A 11APR05A 100 100 0 -87
3016 D&B NB 20m Tch.2+463 to 2+443 fr.NP 3 11APR05A 14APR05A 100 100 0 -87
3017 D&B NB 10m Tch.2+443 to 2+433 fr.NP 2 15APR05A 16APR05A 100 100 0 -87
3018 D&B NB 20m Tch.2+433 to 2+413 fr.NP 3 18APR05A 19APR05A 100 100 0 -86
3019 D&B NB 10m Tch.2+413 to 2+403 fr.NP 2 20APR05 21APR05 0 100 2 -81 -86
3020 D&B NB 20m Tch.2+404 to 2+384 fr.NP 3 22APR05 25APR05 0 100 3 -81 -86
3021 D&B NB 10m Tch.2+384 to 2+374 fr.NP 4 26APR05 29APR05 0 100 4 -81 -86
3022 D&B NB 20m Tch.2+374 to 2+354 fr.NP 3 30APR05 04MAY05 0 100 3 -81 -86
3023 D&B NB 10m Tch.2+354 to 2+344 fr.NP 4 05MAY05 09MAY05 0 100 4 -81 -86
3024 D&B NB 20m Tch.2+344 to 2+325 fr.NP 3 10MAY05 12MAY05 0 100 3 -81 -86
3025 D&B NB 20m Tch.2+325 to 2+305 fr.NP 3 13MAY05 17MAY05 0 100 3 -81 -86
3026 D&B NB 20m Tch.2+305 to 2+285 fr.NP 3 18MAY05 20MAY05 0 100 3 -81 -86
3027 D&B NB 10m Tch.2+285 to 2+275 fr.NP* 3 21MAY05 24MAY05 0 100 3 -81 -86
3028 D&B NB 20m Tch.2+276 to 2+256 fr.NP 3 25MAY05 27MAY05 0 100 3 -81 -86
FEB MAR APR MAY JUN JUL AUG17 18 19 20 21 22 2
7 14 21 28 7 14 21 28 4 11 18 25 2 9 16 23 30 6 13 20 27 4 11 18 25 1 8 1
Sheet 11 of 35
Sheet 12 of 35
Act.ID
ActivityDescription
OrigDur
EarlyStart
EarlyFinish
%Compl.
DWP %Compl.
RemDur
TotalFloat
VarianceEarly Finish
NORTH PORTAL
3029 D&B NB 10m Tch.2+256 to 2+246 fr.NP 2 28MAY05 30MAY05 0 100 2 -81 -86
3030 D&B NB 49m Tch.2+246 to 2+197 fr.NP 8 31MAY05 08JUN05 0 100 8 -81 -86
3031 D&B NB 10m Tch.2+197 to 2+187 fr.NP* 3 09JUN05 13JUN05 0 100 3 -81 -86
3147 D&B NB 40m Tch.2+187 to 2+147 fr.NP 6 14JUN05 20JUN05 0 100 6 -81 -86
3032 D&B NB 39m Tch.2+147 to 2+108 fr.NP 6 21JUN05 27JUN05 0 100 6 -81 -86
3033 D&B NB 59m Tch.2+108 to 2+049 fr.NP 9 28JUN05 08JUL05 0 100 9 -81 -86
3034 D&B NB 10m Tch.2+049 to 2+039 fr.NP 2 09JUL05 11JUL05 0 100 2 -79 -86
3035 D&B NB 30m Tch.2+039 to 2+009 fr.NP 5 12JUL05 16JUL05 0 100 5 -79 -86
3036 D&B NB 10m Tch.2+009 to 1+999 fr.NP* 3 18JUL05 20JUL05 0 100 3 -79 -86
3037 D&B NB 20m Tch.1+999 to 1+979 fr.NP 3 21JUL05 23JUL05 0 100 3 -79 -86
3038 D&B NB 29m Tch.1+979 to 1+950 fr.NP 5 25JUL05 29JUL05 0 100 5 -79 -86
SOUTH PORTAL
1287 D&B.(limit) NB 22m UH Tch.1+141 to 1+163 fr.SP 24 28FEB05A 06APR05A 100 100 0 -100
1292 D&B.NB LH Tch.1+064 to 1+317 (253m) 80 29MAR05A 14JUN05 8 100 45 -100 -100
3054 D&B.(limit) NB 72m Tch.1+163 to 1+235 fr.SP 22 07APR05A 09MAY05 28 100 16 -101 -105
3055 D&B.(limit) NB 20m UH Tch.1+235 to 1+255 fr.SP 6 10MAY05 17MAY05 0 100 6 -101 -105
3056 D&B.(limit) NB 31m UH Tch.1+255 to 1+286 fr.SP 8 18MAY05 26MAY05 0 100 8 -101 -105
3057 D&B.(limit) NB 10m UH Tch.1+286 to 1+296 fr.SP 2 27MAY05 28MAY05 0 100 2 -101 -105
3058 D&B.(limit) NB 21m UH Tch.1+296 to 1+317 fr.SP 4 30MAY05 02JUN05 0 100 4 -101 -105
3059 D&B.NB 20m FF Tch.1+317 to 1+337 fr.SP 3 03JUN05 06JUN05 0 100 3 -101 -105
3060 D&B.NB 10m FF Tch.1+337 to 1+347 fr.SP 2 07JUN05 08JUN05 0 100 2 -101 -105
3061 D&B.NB 20m FF Tch.1+347 to 1+367 fr.SP 3 09JUN05 13JUN05 0 100 3 -101 -105
3062 D&B.NB 10m FF Tch.1+367 to 1+377 fr.SP 2 14JUN05 15JUN05 0 100 2 -101 -105
3063 D&B.NB 20m FF Tch.1+377 to 1+397 fr.SP* 8 16JUN05 24JUN05 0 100 8 -101 -101
FEB MAR APR MAY JUN JUL AUG17 18 19 20 21 22 2
7 14 21 28 7 14 21 28 4 11 18 25 2 9 16 23 30 6 13 20 27 4 11 18 25 1 8 1
Sheet 12 of 35
Sheet 13 of 35
Act.ID
ActivityDescription
OrigDur
EarlyStart
EarlyFinish
%Compl.
DWP %Compl.
RemDur
TotalFloat
VarianceEarly Finish
SOUTH PORTAL
3064 D&B.NB 10m FF Tch.1+397 to 1+407 fr.SP 2 25JUN05 27JUN05 0 100 2 -101 -101
3065 D&B.NB 84m FF Tch.1+407 to 1+491 fr.SP 13 28JUN05 13JUL05 0 100 13 -101 -101
3066 D&B NB 5m FF Tch.1+491 to 1+496 fr.SP 1 14JUL05 14JUL05 0 100 1 -101 -101
3067 D&B NB 30m FF Tch.1+496 to 1+526 fr.SP 6 15JUL05 21JUL05 0 100 6 -101 -101
3068 D&B NB 10m FF Tch.1+526 to 1+536 fr.SP 2 22JUL05 23JUL05 0 100 2 -101 -101
3069 D&B NB 17m FF Tch.1+536 to 1+553 fr.SP 3 25JUL05 27JUL05 0 100 3 -101 -101
TUNNEL INVERTNORTH PORTAL
3181 NB exc.grnd/foul water drain trough 116m(fr.NP) 21 18JAN05A 08APR05A 100 100 0 -122
3191 NB Invert Cleaning (fr.NP 116m) 20 18JAN05A 08APR05A 100 100 0 -119
3201 NB Kicker/form part Service Trough (fr.NP) 116m 22 24MAR05A 17MAY05 0 100 22 -92 -142
3182 NB exc.grnd/foul water drain trough 149m(fr.NP) 28 20APR05 24MAY05 0 100 28 -97 -129
3183 NB exc.grnd/foul water drain trough 128m(fr.NP) 24 20APR05 19MAY05 0 100 24 -51 -106
3184 NB exc.grnd/foul water drain trough 139m(fr.NP) 27 22APR05 25MAY05 0 100 27 -53 -86
3192 NB Invert Cleaning (fr.NP 149m) 24 28APR05 27MAY05 0 100 24 -97 -129
3502 NB Invert lining type 'D' 121m - Rightside 60 17MAY05 27JUL05 0 100 60 -14 -138
3202 NB Kicker/form part Service Trough (fr.NP) 149m 23 18MAY05 14JUN05 0 100 23 -92 -137
3185 NB exc.grnd/foul water drain trough 150m(fr.NP) 28 28MAY05 30JUN05 0 100 28 -59 -86
3193 NB Invert Cleaning (fr.NP 128m) 22 28MAY05 23JUN05 0 100 22 -97 -129
3365 NB Foulwater Gulley ENF-40 to ENF-41 [55m] 12 31MAY05 14JUN05 0 100 12 571 -138
3451 NB Ground water ENG-40 to ENG-41B [55m] 12 31MAY05 14JUN05 0 100 12 574 -138
3203 NB Kicker/form part Service Trough (fr.NP) 128m 22 15JUN05 11JUL05 0 100 22 -92 -137
3364 NB Foulwater Gulley ENF-39 to ENF-40 [50m] 14 15JUN05 30JUN05 0 100 14 571 -138
3366 NB Foulwater Gulley ENF-41 to ENF-42 [52m] 18 15JUN05 06JUL05 0 100 18 798 -138
FEB MAR APR MAY JUN JUL AUG17 18 19 20 21 22 2
7 14 21 28 7 14 21 28 4 11 18 25 2 9 16 23 30 6 13 20 27 4 11 18 25 1 8 1
Sheet 13 of 35
Sheet 14 of 35
Act.ID
ActivityDescription
OrigDur
EarlyStart
EarlyFinish
%Compl.
DWP %Compl.
RemDur
TotalFloat
VarianceEarly Finish
NORTH PORTAL
3450 NB Ground water ENG-39 to ENG-40 [50m] 11 15JUN05 27JUN05 0 100 11 574 -138
3452 NB Ground water ENG-41B to ENG-41A 6 15JUN05 21JUN05 0 100 6 799 -138
3453 NB Ground water ENG-41B to ENG-42 [49m] 11 22JUN05 05JUL05 0 100 11 799 -138
3194 NB Invert Cleaning (fr.NP 139m) 23 24JUN05 21JUL05 0 100 23 -97 -129
3186 NB exc.grnd/foul water drain trough 148m(fr.NP) 27 28JUN05 29JUL05 0 30 27 -59 -86
3449 NB Ground water ENG-38 to ENG-39 [50m] 11 28JUN05 11JUL05 0 100 11 574 -138
3363 NB Foulwater Gulley ENF-38 to ENF-39 [50m] 11 02JUL05 14JUL05 0 100 11 571 -138
3204 NB Kicker/form part Service Trough (fr.NP) 139m 22 12JUL05 05AUG05 0 100 22 -92 -136
3448 NB Ground water ENG-37 to ENG-38 [50m] 11 12JUL05 23JUL05 0 100 11 574 -138
3362 NB Foulwater Gulley ENF-37 to ENF-38 [50m] 11 15JUL05 27JUL05 0 100 11 571 -138
3195 NB Invert Cleaning (fr.NP 150m) 24 22JUL05 18AUG05 0 100 24 -97 -124
3187 NB exc.grnd/foul water drain trough 129m(fr.NP) 24 25JUL05 20AUG05 0 40 24 -60 -86
3447 NB Ground water ENG-36 to ENG-37 [49m] 11 25JUL05 05AUG05 0 100 11 574 -138
SOUTH PORTAL
3210 NB exc.grnd/foul water drain trough 253m(fr.SP) 50 21APR05 21JUN05 0 100 50 -100 -100
3216 NB Invert Cleaning [fr.SP] 253m 18 03JUN05 24JUN05 0 100 18 -100 -100
3226 NB Kicker/form part Service Trough (fr.SP) 253m 35 10JUN05 22JUL05 0 100 35 -100 -100
3211 NB exc.grnd/foul water drain trough 90m(fr.SP) 21 28JUN05 22JUL05 0 100 21 -27 -101
3217 NB Invert Cleaning [fr.SP] 90m 20 04JUL05 26JUL05 0 100 20 -24 -101
3227 NB Kicker/form part Service Trough (fr.SP) 90m 13 23JUL05 06AUG05 0 100 13 -16 -100
TUNNEL LININGNORTH PORTAL
3235 NB NP Arch Lining 150m Tch.3+030 to 2+880 30 27FEB05A 04MAY05 46 100 12 -138 -141
3245 NB NP OHVD 150m Tch.3+030 to 2+880 30 31MAR05A 14MAY05 21 100 21 -138 -138
3236 NB NP Arch Lining 150m Tch.2+880 to 2+730 30 05MAY05 09JUN05 0 100 30 -137 -141
FEB MAR APR MAY JUN JUL AUG17 18 19 20 21 22 2
7 14 21 28 7 14 21 28 4 11 18 25 2 9 16 23 30 6 13 20 27 4 11 18 25 1 8 1
Sheet 14 of 35
Sheet 15 of 35
Act.ID
ActivityDescription
OrigDur
EarlyStart
EarlyFinish
%Compl.
DWP %Compl.
RemDur
TotalFloat
VarianceEarly Finish
NORTH PORTAL
3246 NB NP OHVD 150m Tch.2+880 to 2+730 30 17MAY05 21JUN05 0 100 30 -138 -138
3237 NB NP Arch Lining 150m Tch.2+730 to 2+580 30 10JUN05 16JUL05 0 100 30 -137 -141
3247 NB NP OHVD 150m Tch.2+730 to 2+580 30 22JUN05 27JUL05 0 100 30 -138 -138
3238 NB NP Arch Lining 150m Tch.2+580 to 2+430 30 18JUL05 20AUG05 0 100 30 -137 -141
SOUTH PORTAL
3310 NB SP Arch Lining 150m Tch.1+063 to 1+213 42 21JUN05 09AUG05 0 100 42 -102 -102
3314 NB NP OHVD 150m Tch.1+063 to 1+213 30 20JUL05 23AUG05 0 100 30 -84 -108
TUNNEL FINISHING WORKSSERVICE TROUGH & UTILITIES
3511 NB NP 200 main 183m Tch.3+063 to 2+880 fr.NP 23 22APR05 20MAY05 0 100 23 -116 -131
3527 NB service trough 150m Tch.3+030 to 2+880 fr.NP 23 07MAY05 03JUN05 0 100 23 -116 -131
3512 NB NP 200 main 150m Tch.2+880 to 2+730 fr.NP 23 31MAY05 27JUN05 0 100 23 -116 -138
3528 NB service trough 150m Tch.2+880 to 2+730 fr.NP 23 04JUN05 02JUL05 0 100 23 -116 -131
3513 NB NP 200 main 150m Tch.2+730 to 2+580 fr.NP 23 07JUL05 02AUG05 0 100 23 -123 -138
3529 NB service trough 150m Tch.2+730 to 2+580 fr.NP 23 12JUL05 06AUG05 0 100 23 -123 -138
TUNNEL DRIVE SOUTHBOUNDTUNNEL EXCAVATION & PRIMARY SUPPORTNORTH PORTAL
3088 D&B SB 40m Tch.2+597 to 2+557 fr.NP 6 17MAR05A 23MAR05A 100 100 0 -88
3089 D&B SB 41m Tch.2+557 to 2+516 fr.NP 6 25MAR05A 03APR05A 100 100 0 -88
3090 D&B SB 40m Tch.2+516 to 2+476 fr.NP 6 04APR05A 12APR05A 100 100 0 -89
3091 D&B SB 21m Tch.2+476 to 2+455 fr.NP 3 13APR05A 16APR05A 100 100 0 -90
3092 D&B SB 10m Tch.2+455 to 2+445 fr.NP 2 17APR05A 18APR05A 100 100 0 -89
3093 D&B SB 20m Tch.2+445 to 2+425 fr.NP 3 19APR05A 20APR05 70 100 1 -83 -88
3094 D&B SB 10m Tch.2+425 to 2+415 fr.NP 2 21APR05 22APR05 0 100 2 -83 -88
3095 D&B SB 20m Tch.2+415 to 2+395 fr.NP 3 23APR05 26APR05 0 100 3 -83 -88
FEB MAR APR MAY JUN JUL AUG17 18 19 20 21 22 2
7 14 21 28 7 14 21 28 4 11 18 25 2 9 16 23 30 6 13 20 27 4 11 18 25 1 8 1
Sheet 15 of 35
Sheet 16 of 35
Act.ID
ActivityDescription
OrigDur
EarlyStart
EarlyFinish
%Compl.
DWP %Compl.
RemDur
TotalFloat
VarianceEarly Finish
NORTH PORTAL
3096 D&B SB 10m Tch.2+395 to 2+384 fr.NP* 4 27APR05 30APR05 0 100 4 -83 -88
3097 D&B SB 20m Tch.2+384 to 2+364 fr.NP 3 03MAY05 05MAY05 0 100 3 -83 -88
3098 D&B SB 10m Tch.2+364 to 2+354 fr.NP 5 06MAY05 11MAY05 0 100 5 -83 -88
3099 D&B SB 20m Tch.2+354 to 2+334 fr.NP 3 12MAY05 14MAY05 0 100 3 -83 -88
3100 D&B SB 21m Tch.2+334 to 2+313 fr.NP 3 17MAY05 19MAY05 0 100 3 -83 -88
3101 D&B SB 20m Tch.2+313 to 2+293 fr.NP 3 20MAY05 23MAY05 0 100 3 -83 -88
3102 D&B SB 10m Tch.2+293 to 2+283 fr.NP 5 24MAY05 28MAY05 0 100 5 -83 -88
3103 D&B SB 20m Tch.2+283 to 2+263 fr.NP 3 30MAY05 01JUN05 0 100 3 -83 -88
3104 D&B SB 10m Tch.2+263 to 2+252 fr.NP 2 02JUN05 03JUN05 0 100 2 -83 -88
3105 D&B SB 50m Tch.2+252 to 2+202 fr.NP 8 04JUN05 14JUN05 0 100 8 -83 -88
3106 D&B SB 10m Tch.2+202 to 2+192 fr.NP 2 15JUN05 16JUN05 0 100 2 -83 -88
3107 D&B SB 41m Tch.2+192 to 2+151 fr.NP 6 17JUN05 23JUN05 0 100 6 -83 -88
3108 D&B SB 40m Tch.2+151 to 2+111 fr.NP 6 24JUN05 30JUN05 0 100 6 -83 -88
3109 D&B SB 61m Tch.2+111 to 2+050 fr.NP 9 02JUL05 12JUL05 0 100 9 -83 -88
3110 D&B SB 10m Tch.2+050 to 2+040 fr.NP 2 13JUL05 14JUL05 0 100 2 -83 -88
3111 D&B SB 31m Tch.2+040 to 2+009 fr.NP 5 15JUL05 20JUL05 0 100 5 -83 -88
3112 D&B SB 10m Tch.2+009 to 1+999 fr.NP* 4 21JUL05 25JUL05 0 100 4 -83 -88
3113 D&B SB 20m Tch.1+999 to 1+979 fr.NP 3 26JUL05 28JUL05 0 100 3 -83 -88
SOUTH PORTAL
3129 D&B (limit) SB 30m UH Tch.1+120 to 1+150 fr.SP 39 07FEB05A 21MAY05 67 100 26 -110 -113
1297 D&B SB LH Tch.1+063 to 1+152 (89m) 30 05MAY05 09JUN05 0 100 30 -113 -120
3130 D&B(No Blast) SB 2m UH Tch.1+150 to 1+152 fr.SP 3 23MAY05 25MAY05 0 100 3 -110 -113
3131 D&B (limit) SB 15m UH Tch.1+152 to 1+167 fr.SP 10 26MAY05 06JUN05 0 100 10 -110 -113
3132 D&B (limit) SB 57m UH Tch.1+167 to 1+224 fr.SP 30 07JUN05 13JUL05 0 100 30 -110 -113
FEB MAR APR MAY JUN JUL AUG17 18 19 20 21 22 2
7 14 21 28 7 14 21 28 4 11 18 25 2 9 16 23 30 6 13 20 27 4 11 18 25 1 8 1
Sheet 16 of 35
Sheet 17 of 35
Act.ID
ActivityDescription
OrigDur
EarlyStart
EarlyFinish
%Compl.
DWP %Compl.
RemDur
TotalFloat
VarianceEarly Finish
SOUTH PORTAL
3165 D&B SB LH Tch.1+152 to 1+302 (150m) 42 29JUN05 17AUG05 0 100 42 -110 -113
3133 D&B (limit) SB 19m UH Tch.1+224 to 1+243 fr.SP 11 14JUL05 26JUL05 0 100 11 -110 -113
3134 D&B (limit) SB 29m UH Tch.1+243 to 1+272 fr.SP 7 27JUL05 03AUG05 0 100 7 -110 -113
VENTILATION ADIT
3122 D&B SB 40m UH Tch.1+644 to 1+604 fr.VA->SP 8 12MAR05A 28APR05 10 100 8 -92 -92
3123 D&B SB 20m UH Tch.1+604 to 1+584 fr.VA->SP 4 29APR05 04MAY05 0 100 4 -92 -92
3124 D&B SB 10m UH Tch.1+584 to 1+574 fr.VA->SP 2 05MAY05 06MAY05 0 100 2 -92 -92
3125 D&B SB 51m UH Tch.1+574 to 1+523 fr.VA->SP 11 07MAY05 20MAY05 0 100 11 -92 -92
3145 D&B SB 10m UH Tch.1+523 to 1+513 fr.VA->SP 2 21MAY05 23MAY05 0 100 2 -92 -92
3144 D&B SB 30m UH Tch.1+513 to 1+483 fr.VA->SP 6 24MAY05 30MAY05 0 100 6 -92 -92
3143 D&B SB 91m UH Tch.1+483 to 1+392 fr.VA->SP 19 31MAY05 22JUN05 0 100 19 -92 -92
3142 D&B SB 10m UH Tch.1+392 to 1+382 fr.VA->SP 2 23JUN05 24JUN05 0 100 2 -92 -92
3141 D&B SB 20m FF Tch.1+382 to 1+362 fr.VA->SP 8 25JUN05 05JUL05 0 100 8 -92 -92
3140 D&B SB 10m FF Tch.1+362 to 1+352 fr.VA->SP 3 06JUL05 08JUL05 0 100 3 -92 -92
3139 D&B SB 20m FF Tch.1+352 to 1+332 fr.VA->SP 4 09JUL05 13JUL05 0 100 4 -92 -92
3138 D&B SB 10m FF Tch.1+332 to 1+322 fr.VA->SP 2 14JUL05 15JUL05 0 100 2 -92 -92
3137 D&B SB 20m FF Tch.1+322 to 1+302 fr.VA->SP 4 16JUL05 20JUL05 0 100 4 -92 -92
TUNNEL INVERTNORTH PORTAL
1930 SB Kicker/form part Service Trough (fr.NP) 146m 20 16FEB05A 19APR05A 100 100 0 -154
1568 SB exc.grnd/foul water drain trough 156m(fr.NP) 28 21FEB05A 21MAY05 10 100 26 -131 -156
1931 SB Kicker/form part Service Trough (fr.NP) 156m 22 31MAR05A 04MAY05 30 100 12 -115 -120
1569 SB exc.grnd/foul water drain trough 162m(fr.NP) 30 20APR05 26MAY05 0 100 30 -126 -130
1570 SB exc.grnd/foul water drain trough 152m(fr.NP) 28 20APR05 24MAY05 0 100 28 -93 -101
1594 SB Invert Cleaning (fr.NP) 156m 20 30APR05 25MAY05 0 100 20 -131 -156
FEB MAR APR MAY JUN JUL AUG17 18 19 20 21 22 2
7 14 21 28 7 14 21 28 4 11 18 25 2 9 16 23 30 6 13 20 27 4 11 18 25 1 8 1
Sheet 17 of 35
Sheet 18 of 35
Act.ID
ActivityDescription
OrigDur
EarlyStart
EarlyFinish
%Compl.
DWP %Compl.
RemDur
TotalFloat
VarianceEarly Finish
NORTH PORTAL
1579 SB exc.grnd/foul water drain trough 151m(fr.NP) 28 12MAY05 15JUN05 0 100 28 -81 -88
1595 SB Invert Cleaning (fr.NP) 162m 22 26MAY05 21JUN05 0 100 22 -131 -148
1932 SB Kicker/form part Service Trough (fr.NP) 162m 23 02JUN05 29JUN05 0 100 23 -131 -135
3500 SB Invert lining type 'D' 121m - Rightside 60 10JUN05 20AUG05 0 100 60 -75 -168
1580 SB exc.grnd/foul water drain trough 137m(fr.NP) 25 17JUN05 16JUL05 0 100 25 -63 -88
1596 SB Invert Cleaning (fr.NP) 152m 18 22JUN05 13JUL05 0 100 18 -122 -139
3408 SB Foulwater Gulley ESF-40 to ESF-41 [55m] 12 25JUN05 09JUL05 0 100 12 -56 -168
3495 SB Ground water ESG-40 to ESG-41B [55m] 12 25JUN05 09JUL05 0 100 12 -68 -168
1933 SB Kicker/form part Service Trough (fr.NP) 152m 22 30JUN05 26JUL05 0 100 22 -123 -131
3407 SB Foulwater Gulley ESF-39 to ESF-40 [50m] 11 11JUL05 22JUL05 0 100 11 -56 -168
3409 SB Foulwater Gulley ESF-41 to ESF-42 [48m] 11 11JUL05 22JUL05 0 100 11 784 -168
3494 SB Ground water ESG-39 to ESG-40 [50m] 11 11JUL05 22JUL05 0 100 11 -56 -168
3497 SB Ground water ESG-41B to ESG-42 [153m] 34 11JUL05 18AUG05 0 100 34 -68 -168
1581 SB exc.grnd/foul water drain trough 152m(fr.NP) 28 13JUL05 13AUG05 0 80 28 -62 -88
1597 SB Invert Cleaning (fr.NP) 150m 18 14JUL05 03AUG05 0 100 18 -110 -126
3406 SB Foulwater Gulley ESF-38 to ESF-39 [50m] 11 23JUL05 04AUG05 0 100 11 -56 -168
3493 SB Ground water ESG-38 to ESG-39 [50m] 11 23JUL05 04AUG05 0 100 11 -56 -168
1934 SB Kicker/form part Service Trough (fr.NP) 150m 22 27JUL05 20AUG05 0 100 22 -115 -122
SOUTH PORTAL
1583 SB exc.grnd/foul water drain trough 89m(fr.SP) 25 19MAY05 17JUN05 0 100 25 -113 -120
1311 SB Invert Cleaning (fr.SP) 239m 66 18JUN05 03SEP05 0 100 66 -113 -113
3741 SB Kicker/form part Service Trough (fr.SP) 89m 13 25JUN05 11JUL05 0 100 13 -83 -113
1584 SB exc.grnd/foul water drain trough 150m(fr.SP) 41 08JUL05 24AUG05 0 100 41 -110 -110
FEB MAR APR MAY JUN JUL AUG17 18 19 20 21 22 2
7 14 21 28 7 14 21 28 4 11 18 25 2 9 16 23 30 6 13 20 27 4 11 18 25 1 8 1
Sheet 18 of 35
Sheet 19 of 35
Act.ID
ActivityDescription
OrigDur
EarlyStart
EarlyFinish
%Compl.
DWP %Compl.
RemDur
TotalFloat
VarianceEarly Finish
VENTILATION ADIT
1586 SB exc.grnd/foul water drain trough 342m(fr.VA) 60 15JUN05 24AUG05 0 100 60 -110 -110
3166 SB Invert Cleaning (fr.SP 342m) 48 07JUL05 31AUG05 0 100 48 -110 -110
TUNNEL LININGNORTH PORTAL
2186 SB NP Arch Lining 150m Tch.3+035 to 2+885 30 02APR05A 19MAY05 9 100 24 -157 -162
3153 SB NP OHVD 150m Tch.3+035 to 2+885 30 05MAY05 09JUN05 0 100 30 -167 -168
2187 SB NP Arch Lining 150m Tch.2+885 to 2+735 30 20MAY05 24JUN05 0 100 30 -157 -162
3154 SB NP OHVD 150m Tch.2+885 to 2+735 30 10JUN05 16JUL05 0 100 30 -167 -168
2188 SB NP Arch Lining 150m Tch.2+735 to 2+585 30 25JUN05 30JUL05 0 100 30 -157 -161
3155 SB NP OHVD 150m Tch.2+735 to 2+585 30 18JUL05 20AUG05 0 100 30 -167 -168
TUNNEL FINISHING WORKSSERVICE TROUGH & UTILITIES
3545 SB NP 200 main 150m Tch.3+035 to 2+885 fr.NP 23 20MAY05 16JUN05 0 100 23 -139 -168
3560 SB service trough 150m Tch.3+035 to 2+885 fr.NP 23 25MAY05 21JUN05 0 100 23 -139 -168
3546 SB NP 200 main 150m Tch.2+885 to 2+735 fr.NP 23 25JUN05 22JUL05 0 100 23 -146 -168
3561 SB service trough 150m Tch.2+885 to 2+735 fr.NP 23 30JUN05 27JUL05 0 100 23 -146 -168
CROSS PASSAGESX-PASSAGE EXCAVATION
2573 Excavate Part Cross Passage CP.17 from SB 2 19FEB05A 22MAR05A 100 100 0 -100
2553 Excavate Part Cross Passage CP.16 from NB 2 30MAR05A 14APR05A 100 100 0 -100
2574 Excavate Part Cross Passage CP.16 from SB 2 30MAR05A 04APR05A 100 100 0 -93
2554 Excavate Part Cross Passage CP.15 from NB 2 20APR05 21APR05 0 100 2 -46 -91
2575 Excavate Part Cross Passage CP.15 from SB 2 20APR05 21APR05 0 100 2 -46 -92
2583 Excavate Part Cross Passage CP.2 from SB 16 20APR05 09MAY05 0 100 16 -33 -93
2567 Excavate Part Cross Passage CP.2 from NB 16 27APR05 17MAY05 0 100 16 -27 -98
2555 Excavate Part Cross Passage CP.14 from NB 2 10MAY05 11MAY05 0 100 2 -52 -86
FEB MAR APR MAY JUN JUL AUG17 18 19 20 21 22 2
7 14 21 28 7 14 21 28 4 11 18 25 2 9 16 23 30 6 13 20 27 4 11 18 25 1 8 1
Sheet 19 of 35
Sheet 20 of 35
Act.ID
ActivityDescription
OrigDur
EarlyStart
EarlyFinish
%Compl.
DWP %Compl.
RemDur
TotalFloat
VarianceEarly Finish
X-PASSAGE EXCAVATION2576 Excavate Part Cross Passage CP.14 from SB 2 12MAY05 13MAY05 0 100 2 -54 -88
2556 Excavate Part Cross Passage CP.13 from NB 2 31MAY05 01JUN05 0 100 2 -59 -86
2577 Excavate Part Cross Passage CP.13 from SB 2 04JUN05 06JUN05 0 100 2 -63 -88
2566 Excavate Part Cross Passage CP.3 from NB 2 17JUN05 18JUN05 0 100 2 -27 -98
2557 Excavate Part Cross Passage CP.12 from NB 2 21JUN05 22JUN05 0 100 2 -66 -86
2578 Excavate Part Cross Passage CP.12 from SB 2 24JUN05 25JUN05 0 100 2 -69 -88
2584 Excavate Part Cross Passage CP.3 from SB 2 29JUN05 30JUN05 0 100 2 -33 -93
2558 Excavate Part Cross Passage CP.11 from NB 2 09JUL05 11JUL05 0 100 2 -81 -86
2565 Excavate Part Cross Passage CP.4 from NB 2 12JUL05 13JUL05 0 100 2 -27 -98
2579 Excavate Part Cross Passage CP.11 from SB 2 13JUL05 14JUL05 0 100 2 -74 -88
2585 Excavate Part Cross Passage CP.4 from SB 2 23JUL05 25JUL05 0 100 2 -33 -93
X-PASSAGE LINING2590 Invert Clean & Lining to CP.20 10 14JUN05 24JUN05 0 100 10 -138 -162
2591 Invert Clean & Lining to CP.19 10 25JUN05 07JUL05 0 100 10 -138 -162
2592 Invert Clean & Lining to CP.18 10 08JUL05 19JUL05 0 100 10 -138 -162
2593 Invert Clean & Lining to CP.17 10 20JUL05 30JUL05 0 100 10 -138 -162
X-PASSAGE INVERT2610 Invert Lining to CP.20 8 11JUL05 19JUL05 0 100 8 -112 -162
2611 Invert Lining to CP.19 8 22JUL05 30JUL05 0 100 8 -110 -162
X-PASSAGE FINISHING WORKS2630 Construct Rooms (incl.ABWF) at CP.20 24 27JUL05 23AUG05 0 100 24 -112 -162
VENTILATION ADIT & BUILDINGSUBMITTALS & APPROVALSABWF & BUILDER'S WORKS
1973 VA Bldg. - Prep & submit louvre details 90 07APR05A 07APR05A 100 100 0 -15
FEB MAR APR MAY JUN JUL AUG17 18 19 20 21 22 2
7 14 21 28 7 14 21 28 4 11 18 25 2 9 16 23 30 6 13 20 27 4 11 18 25 1 8 1
Sheet 20 of 35
Sheet 21 of 35
Act.ID
ActivityDescription
OrigDur
EarlyStart
EarlyFinish
%Compl.
DWP %Compl.
RemDur
TotalFloat
VarianceEarly Finish
ABWF & BUILDER'S WORKS1974 VA Bldg. - Approve louvre details 24 07APR05A 07APR05A 100 100 0 9
1975 VA Bldg. - Prep & sub balustrade & metal wks 90 20APR05 06AUG05 0 100 90 -88 -113
1985 VA Bldg. - Prep & sub aluminium cladding 90 20APR05 06AUG05 0 100 90 -82 -115
1971 VA Bldg. - Prep & submit door & window detail 90 30JUN05 17OCT05 0 60 90 -80 -113
E&M EQPT./MTRL.DETAIL SUBMITTAL8232 VaBldg-Sub.TVF, Ductworks & Control sys 78 02JUL04A 23JUL05 80 30 78 101 -22
8234 VaBldg-Sub.MVAC MCC, power & control sys 54 02JUL04A 24JUN05 75 100 54 49 -78
8231 VaBldg-Sub.FS AFA & FM200 sys 54 05JUL04A 24JUN05 90 40 54 161 -18
8494 VaBldg-Sub. building related luminaires 54 06JUL04A 13MAY05 80 100 20 65 -26
8226 VaBldg-Sub.LV power dist. sys 54 07JUL04A 24JUN05 85 100 54 47 -66
8229 VaBldg-Sub.MVAC mech.vent. sys 54 03AUG04A 24JUN05 80 100 54 29 -66
8228 VaBldg-Sub.FS wet sys 54 05AUG04A 24JUN05 95 30 54 161 -18
8233 VaBldg-Sub.MVAC / TVF pneumatic sys 54 14AUG04A 17JUN05 50 0 48 125 66
8230 VaBldg-Sub.CMCS & ELV sys 78 26AUG04A 23JUL05 65 80 78 53 -60
8227 VaBldg-Sub.PD all fresh & flush water sys 54 20OCT04A 20JUN05 90 55 50 111 -26
8514 VaBldg-Sub.MVAC Package AC Units 54 17JAN05A 24JUN05 85 0 54 173 24
8235 VaBldg-Sub.PD irrig. sys 54 04FEB05A 04AUG05 50 80 54 67 -70
E&M EQPT./MTRL.APPROVAL BY ENGINEER6578 VaBldg-App. HV power dist. sys 18 14JUL04A 22JUN05 85 100 18 7 -70
6579 VaBldg-App. LV power dist. sys 18 13AUG04A 11MAY05 70 80 18 47 -12
8495 VaBldg-App. building related luminaires 18 18AUG04A 11MAY05 60 20 18 65 -6
6581 VaBldg-App. FS wet sys 18 04SEP04A 11MAY05 60 0 18 161 36
6590 VaBldg-App. FS AFA & FM200 sys 18 14SEP04A 11MAY05 55 0 18 161 36
6587 VaBldg-App. of CMCS & ELV sys 18 20SEP04A 11MAY05 45 0 18 53 18
FEB MAR APR MAY JUN JUL AUG17 18 19 20 21 22 2
7 14 21 28 7 14 21 28 4 11 18 25 2 9 16 23 30 6 13 20 27 4 11 18 25 1 8 1
Sheet 21 of 35
Sheet 22 of 35
Act.ID
ActivityDescription
OrigDur
EarlyStart
EarlyFinish
%Compl.
DWP %Compl.
RemDur
TotalFloat
VarianceEarly Finish
E&M EQPT./MTRL.APPROVAL BY ENGINEER6582 VaBldg-App. MVAC mech.vent. sys 18 23SEP04A 11MAY05 20 80 18 29 -12
6580 VaBldg-App. PD all fresh & flush water sys 18 04NOV04A 20JUN05 40 0 50 111 -8
6850 VaBldg-App. TVF, Ductworks & Control sys 18 12NOV04A 11MAY05 40 0 18 101 56
6864 V6aBldg-App. MVAC MCC, power & control sys 18 12NOV04A 11MAY05 50 100 18 49 -24
8515 VaBldg-App. MVAC Package AC Unit sys 18 01FEB05A 11MAY05 30 0 18 173 78
PROCUREMENTARCHITECTURAL
1993 VA Bldg. - Procure louvres 180 10JUN05 14JAN06 0 30 180 -79 -101
1995 VA Bldg. - Procure aluminium cladding 180 10JUN05 14JAN06 0 30 180 -79 -101
1996 VA Bldg. - Procure fall arrest system 180 10JUN05 14JAN06 0 30 180 -79 -101
1997 VA Bldg. - Procure slate cladding 180 10JUN05 14JAN06 0 30 180 -79 -101
E&M MATERIALS6583 VaBldg-Proc. & Manuf. of HV dist. equip't 180 23JUN05 26JAN06 0 10 180 7 -70
6588 VaBldg-Proc & Manuf. MVAC mech.vent. sys 180 06JUL05 15FEB06 0 0 180 -15 -56
6865 VaBldg-Proc & Manuf. MCC, power & control sys 180 08JUL05 17FEB06 0 5 180 3 -70
6584 VaBldg-Proc & Manuf. LV power dist. equip't 180 22JUL05 03MAR06 0 0 180 -11 -70
CONSTRUCTION WORKSADIT TUNNELVA TRANSITION STRUCTURE
1565 VA Excav.VA-RT LH Junction 54m w/CP.7 10 05MAR05A 25APR05 52 100 5 -63 -117
1566 VA Excav.VA-RT SB Junction UH 16m (8+8m) 20 26APR05 20MAY05 0 100 20 -63 -117
SUBSTRUCTURE6589 VaBldg Drainage & Earth mat 48 05JUL05 29AUG05 0 90 48 -99 -101
ENT NORTH PORTAL VENTILATION BUILDINGSUBMITTALS & APPROVALSE&M EQPT.& MATERIAL.SUBMITTALS
8260 EntNpBldg-Sub.MVAC MCC, power & control sys 54 02JUL04A 24JUN05 72 100 54 2 -117
FEB MAR APR MAY JUN JUL AUG17 18 19 20 21 22 2
7 14 21 28 7 14 21 28 4 11 18 25 2 9 16 23 30 6 13 20 27 4 11 18 25 1 8 1
Sheet 22 of 35
Sheet 23 of 35
Act.ID
ActivityDescription
OrigDur
EarlyStart
EarlyFinish
%Compl.
DWP %Compl.
RemDur
TotalFloat
VarianceEarly Finish
E&M EQPT.& MATERIAL.SUBMITTALS8257 EntNpBldg-Sub.FS AFA & FM200 sys 54 05JUL04A 24JUN05 85 0 54 158 35
8498 EntNpBldg-Sub. building related luminaires 54 06JUL04A 13MAY05 80 100 20 74 -39
8251 EntNpBldg-Sub.LV power dist. sys 54 07JUL04A 24JUN05 85 100 54 -4 -87
8254 EntNpBldg-Sub.MVAC mech.vent. sys 54 03AUG04A 24JUN05 80 100 54 -4 -129
8253 EntNpBldg-Sub.FS wet sys 54 05AUG04A 24JUN05 95 100 54 152 -49
8259 EntNpBldg-Sub.MVAC / TVF pneumatic sys 54 14AUG04A 17JUN05 50 0 48 122 81
8255 EntNpBldg-Sub.CMCS & ELV sys 78 28AUG04A 23JUL05 65 95 78 50 -75
8252 EntNpBldg-Sub.PD cleans. & flush water sys 54 20OCT04A 20JUN05 90 100 50 152 -63
8256 EntNpBldg-Sub.MVAC Package AC Units 54 17JAN05A 24JUN05 85 0 54 170 81
E&M EQPT.& MATERIAL APPROVALS6196 EntNpBldg-App. HV power dist. sys 18 14JUL04A 11MAY05 85 100 18 2 -69
6197 EntNpBldg-App. LV power dist. sys 18 13AUG04A 11MAY05 70 100 18 -4 -33
8499 EntNpBldg-App. building related luminaires 18 18AUG04A 11MAY05 60 100 18 74 -19
6199 EntNpBldg-App. FS wet sys 18 04SEP04A 11MAY05 60 0 18 152 5
6210 EntNpBldg-App. FS AFA & FM200 sys 18 14SEP04A 11MAY05 55 0 18 158 89
6203 EntNpBldg-App. CMCS & ELV sys 18 20SEP04A 09JUL05 45 0 18 2 -45
6200 EntNpBldg-App. MVAC mech.vent. sys 18 23SEP04A 11MAY05 35 100 18 -4 -75
6198 EntNpBldg-App. PD cleans. & flush water sys 18 04NOV04A 11MAY05 40 90 18 152 -13
6823 EntNpBldg-App. TVF, Ductworks & Control sys 18 12NOV04A 11MAY05 40 50 18 50 -7
6837 EntNpBldg-App. MVAC MCC, power & control sys 18 12NOV04A 11MAY05 50 100 18 2 -63
6207 EntNpBldg-App. MVAC Package AC Unit sys 18 01FEB05A 11MAY05 30 0 18 170 135
PROCUREMENT - MATERIAL ABWF WORKS
1955 NP.Bldg. - Prep & submit louvre details 24 20APR05 19MAY05 0 100 24 -34 -117
FEB MAR APR MAY JUN JUL AUG17 18 19 20 21 22 2
7 14 21 28 7 14 21 28 4 11 18 25 2 9 16 23 30 6 13 20 27 4 11 18 25 1 8 1
Sheet 23 of 35
Sheet 24 of 35
Act.ID
ActivityDescription
OrigDur
EarlyStart
EarlyFinish
%Compl.
DWP %Compl.
RemDur
TotalFloat
VarianceEarly Finish
ABWF WORKS1957 NP.Bldg. - Prep & sub balustrade & metal wks 24 20APR05 19MAY05 0 100 24 -56 -67
1959 NP.Bldg. - Prep & sub aluminium cladding 24 20APR05 19MAY05 0 100 24 -34 -117
1946 NP.Bldg. - Prep & submit door & window detail 24 12MAY05 09JUN05 0 100 24 44 -67
1956 NP.Bldg. - Approve louvre details 24 20MAY05 17JUN05 0 100 24 -34 -117
1958 NP.Bldg. - Approve balustrade & metal works 24 20MAY05 17JUN05 0 100 24 -56 -67
1960 NP.Bldg. - Approve aluminium cladding 24 20MAY05 17JUN05 0 100 24 -34 -117
1963 NP.Bldg. - Approve slate cladding 24 20MAY05 17JUN05 0 100 24 -34 -117
1954 NP.Bldg. - Approve door & window details 24 10JUN05 09JUL05 0 100 24 44 -67
1965 NP.Bldg. - Procure louvre details 180 18JUN05 21JAN06 0 40 180 -34 -117
1966 NP.Bldg. - Procure balustrade & metal works 120 18JUN05 09NOV05 0 20 120 -56 -67
1967 NP.Bldg. - Procure aluminium cladding 180 18JUN05 21JAN06 0 40 180 -34 -117
1969 NP.Bldg. - Procure slate cladding 180 18JUN05 21JAN06 0 40 180 -34 -117
1961 NP.Bldg. - Prep & sub fall arrest system 24 04JUL05 30JUL05 0 100 24 -34 -117
1964 NP.Bldg. - Procure doors & windows 120 11JUL05 30NOV05 0 5 120 44 -67
E&M WORKS6201 EntNpBldg-Proc. & Manuf. of HV dist. equip't 180 12MAY05 14DEC05 0 30 180 2 -69
6206 EntNpBldg-Proc & Manuf. MVAC mech.vent. sys 180 12MAY05 14DEC05 0 30 180 -4 -75
6838 EntNpBldg-Proc & Manuf. MCC, power & control sys 180 12MAY05 14DEC05 0 20 180 2 -63
6202 EntNpBldg-Proc & Manuf. LV power dist. equip't 180 18JUN05 21JAN06 0 10 180 -34 -63
8500 EntNpBldg-Proc & Manf bldg related luminaires 180 06JUL05 15FEB06 0 5 180 30 -63
6208 EntNpBldg-Proc. & Manuf. of CMCS & ELV sys 180 11JUL05 20FEB06 0 0 180 2 -45
6204 EntNpBldg-Proc & Manuf. Cleans & flush water sys 120 18JUL05 07DEC05 0 0 120 98 -67
FEB MAR APR MAY JUN JUL AUG17 18 19 20 21 22 2
7 14 21 28 7 14 21 28 4 11 18 25 2 9 16 23 30 6 13 20 27 4 11 18 25 1 8 1
Sheet 24 of 35
Sheet 25 of 35
Act.ID
ActivityDescription
OrigDur
EarlyStart
EarlyFinish
%Compl.
DWP %Compl.
RemDur
TotalFloat
VarianceEarly Finish
CONSTRUCTIONSUBSTRUCTURERC WORKS
1386 NP.Bldg. - RC Found & Drainage GL.A-K/2-6 54 14FEB05A 21MAY05 20 100 26 -36 -47
SUPERSTRUCTURE RC WORKSNB CARRIAGEWAY & CENTRAL RESERVE
1384 NP.Bldg. - Nth Bound C/Way RC Base Slab 18 07MAY05 28MAY05 0 100 18 -36 -47
1387 NP.Bldg. - RC Cols.& Walls to 1FL.GL.A-K/2-6 18 14MAY05 04JUN05 0 100 18 -32 -47
1385 NP.Bldg. - Nth Bound C/Way RC Ret. Wall W1 24 23MAY05 20JUN05 0 95 24 -36 -47
1388 NP.Bldg. - RC Walls to Tanks/Pits GL.A-K/2-6 18 23MAY05 13JUN05 0 0 18 -32 -47
1389 NP.Bldg. - RC S/Slab 1FL.+72.50mPD GL.A-K/2-6 18 14JUN05 05JUL05 0 10 18 -32 -47
1390 NP.Bldg. - RC Cols.& Walls to 2FL.GL.A-K/2-6 18 28JUN05 19JUL05 0 0 18 -32 -47
1391 NP.Bldg. - RC S/Slab LPL.+74.40mPD GL.A-K/2-6 12 13JUL05 26JUL05 0 0 12 -32 -47
1392 NP.Bldg. - RC S/Slab LPL.+75.50mPD GL.G-K/2-6 12 20JUL05 02AUG05 0 0 12 -32 -47
SB CARRIAGEWAY
1404 NP.Bldg. - Sth Bound C/Way RC Base Slab 18 21JUN05 12JUL05 0 0 18 -36 -47
1405 NP.Bldg. - Sth Bound C/Way RC Ret Wall W2 24 13JUL05 09AUG05 0 0 24 -36 -47
TOLL PLAZA & ANCILLIARY STRUCTURESCONTRACT DEFINED DATES & SECTIONSPROGRAMME RESTRAINTS
CT_PLAZA Loss of Access to Toll Plaza Temp. Access Road 0 21MAY05 0 0 0 1,043 0
SUBMITTALS & APPROVALSABWF & BUILDER'S WORKS
1513 TP/FB - Engineering & Submit lift details (x2) 78 22FEB05A 19MAY05 60 90 24 41 -7
1524 TP/FB - Prep & submit footbridge details 24 20APR05 19MAY05 0 100 24 -1 -176
1514 TP/FB - Approve lifts (x2) details 24 20MAY05 17JUN05 0 0 24 41 -7
1522 TP/FB - Approve footbridge details 24 20MAY05 17JUN05 0 100 24 -1 -176
FEB MAR APR MAY JUN JUL AUG17 18 19 20 21 22 2
7 14 21 28 7 14 21 28 4 11 18 25 2 9 16 23 30 6 13 20 27 4 11 18 25 1 8 1
Sheet 25 of 35
Sheet 26 of 35
Act.ID
ActivityDescription
OrigDur
EarlyStart
EarlyFinish
%Compl.
DWP %Compl.
RemDur
TotalFloat
VarianceEarly Finish
E&M EQPT. / MTRL. SUBMITTALS8258 EntNpBldg-Sub.TVF 78 02JUL04A 23JUL05 80 100 78 50 -85
8236 TP-Sub.MVAC Package AC Units 54 17JAN05A 13MAR06 85 0 54 23 -64
E&M EQPT. / MTRL. APPROVALS7547 TP-App. MVAC Package AC Unit sys 18 01FEB05A 21JAN06 30 0 18 23 -10
DESIGN & ENGINEERING TEMPORARY WORKS
1345 Design/ICE Temp Falsework Foot Bridge Piers 24 18JUN05 16JUL05 0 100 24 68 -107
PERMANENT WORKS1650 Design/ICE Check Foot Bridge 36 16JUN05 28JUL05 0 0 36 12 0
PROCUREMENT - MAJOR MATERIALTOLL PLAZA
1512 TP/FB - Procure & maunfacture lifts (x2) 270 18JUN05 22MAY06 0 0 270 41 -7
1521 TP/FB - Procure & fabricate footbridge 180 18JUN05 21JAN06 0 80 180 -1 -176
CONSTRUCTION WORKSTOLL PLAZA ROADWORKSROADS - FORMATION
1770 TP/Rd - Perm materials storage area; Ptn D2 & D3 175 01JUN04A 14MAY05 86 90 21 41 32
TOLL PLAZA COLLECTOR'S SUBWAYSTRUCTURE
1467 TP/CS - Excavation - Ptn A 8 20APR05 28APR05 0 100 8 20 -23
1468 TP/CS - Excavation - Ptn B 8 05MAY05 13MAY05 0 100 8 26 -21
1469 TP/CS - Excavation - Ptn C 8 14MAY05 24MAY05 0 0 8 42 -15
TOLL PLAZA FOOTBRIDGEFOUNDATIONS
1677 TP/FB - Pile Cap - Cap FT3 12 14MAR05A 30APR05 10 0 10 6 17
1493 TP/FB - Pile Cap - Cap FT4 12 03MAY05 17MAY05 0 0 12 6 -9
1690 TP/FB - Pile Cap - Cap FT2 12 18MAY05 31MAY05 0 0 12 36 7
FEB MAR APR MAY JUN JUL AUG17 18 19 20 21 22 2
7 14 21 28 7 14 21 28 4 11 18 25 2 9 16 23 30 6 13 20 27 4 11 18 25 1 8 1
Sheet 26 of 35
Sheet 27 of 35
Act.ID
ActivityDescription
OrigDur
EarlyStart
EarlyFinish
%Compl.
DWP %Compl.
RemDur
TotalFloat
VarianceEarly Finish
RC SUPERSTRUCTURE1707 TP/FB - Column & bearings C1 12 01JUN05 15JUN05 0 0 12 181 7
ADMINISTRATION BUILDING SUBMITTALS & APPROVALSABWF & BUILDER'S WORKS
1517 Admin Bldg - Engineering & Submit lift details 78 22FEB05A 03SEP05 60 100 24 -70 -122
E&M EQPT. / MTRL. SUBMITTALS8244 AdmBldg-Sub.FS AFA & FM200 sys 54 05JUL04A 24JUN05 90 0 54 140 12
8502 AdmBldg-Sub. building related luminaires 54 06JUL04A 24JUN05 80 100 54 56 -54
8238 AdmBldg-Sub.LV power dist. sys 54 07JUL04A 24JUN05 85 100 54 26 -168
8241 AdmBldg-Sub.MVAC mech.vent. sys 54 03AUG04A 24JUN05 80 100 54 -10 -144
8240 AdmBldg-Sub.FS wet sys 54 05AUG04A 24JUN05 95 100 54 116 -132
8242 AdmBldg-Sub.CMCS, TCS & ELV sys 78 26AUG04A 23JUL05 65 100 78 -8 -122
8239 AdmBldg-Sub.PD all fresh & flush water sys 54 20OCT04A 20JUN05 90 100 50 116 -152
8245 AdmBldg-Sub.Chiller & Pumps 54 30DEC04A 19SEP05 85 100 54 -22 -234
8243 AdmBldg-Sub.FCUs & PAUs 54 04JAN05A 24JUN05 80 100 54 -7 -204
8247 AdmBldg-Design LPG sys 54 07APR05A 14JAN06 80 20 54 -73 -176
8248 AdmBldg-Engineer to provide Cater'g equip detail 0 07APR05A 100 100 0 3
8249 AdmBldg-Sub.LPG sys 54 07APR05A 14JAN06 80 0 54 -73 -122
E&M EQPT. / MTRL. APPROVALS6385 AdmBldg-App. HV power dist. sys 18 14JUL04A 17JUN05 80 100 18 -4 -180
6386 AdmBldg-App. LV power dist. sys 18 13AUG04A 11MAY05 70 100 18 26 -114
8503 AdmBldg-App. building related luminaires 18 18AUG04A 11MAY05 60 0 18 56 0
6388 AdmBldg-App. FS wet sys 18 04SEP04A 11MAY05 60 100 18 116 -78
6399 AdmBldg-App. FS AFA & FM200 sys 18 14SEP04A 11MAY05 55 0 18 140 66
6392 AdmBldg-App. of CMCS, TCS & ELV sys 18 20SEP04A 11MAY05 30 100 18 -8 -44
FEB MAR APR MAY JUN JUL AUG17 18 19 20 21 22 2
7 14 21 28 7 14 21 28 4 11 18 25 2 9 16 23 30 6 13 20 27 4 11 18 25 1 8 1
Sheet 27 of 35
Sheet 28 of 35
Act.ID
ActivityDescription
OrigDur
EarlyStart
EarlyFinish
%Compl.
DWP %Compl.
RemDur
TotalFloat
VarianceEarly Finish
E&M EQPT. / MTRL. APPROVALS6389 AdmBldg-App. MVAC mech.vent. sys 18 23SEP04A 11MAY05 35 100 18 -10 -90
6396 AdmBldg-App. FCUs & PAUs 18 23SEP04A 17JUN05 45 100 15 -40 -180
6387 AdmBldg-App. PD all fresh & flush water sys 18 04NOV04A 11MAY05 50 100 18 116 -102
6478 AdmBldg-App. Chiller & Pumps 18 17JAN05A 06AUG05 30 100 18 -22 -180
DESIGN & ENGINEERING TEMPORARY WORKS
1373 Design/ICE Temp False/Formwork Admin Bldg 48 20APR05 17JUN05 0 100 48 -122 -122
ABWF WORKS1893 Admin.Bldg. - Prep & submit louvre details 24 07APR05A 07APR05A 100 100 0 -154
1879 Admin.Bldg. - Prep & submit glass canopy details 24 20APR05 19MAY05 0 100 24 -110 -188
1883 Admin.Bldg. - Prep & sub sheet decking details 24 20APR05 19MAY05 0 100 24 -116 -122
1891 Admin.Bldg. - Prep & submit door & window detail 24 20APR05 19MAY05 0 100 24 -116 -122
1897 Admin.Bldg. - Prep & sub aluminium cladding 24 20APR05 19MAY05 0 100 24 -110 -188
1885 Admin.Bldg. - Prep & submit wood ceiling details 24 27APR05 26MAY05 0 100 24 -122 -122
1880 Admin.Bldg. - Approve glass canopy details 24 20MAY05 17JUN05 0 100 24 -110 -188
1884 Admin.Bldg. - Approve sheet decking details 24 20MAY05 17JUN05 0 100 24 -116 -122
1889 Admin.Bldg. - Prep & submit curtain wall details 24 20MAY05 17JUN05 0 100 24 -116 -182
1892 Admin.Bldg. - Approve door & window details 24 20MAY05 17JUN05 0 100 24 -116 -122
1894 Admin.Bldg. - Approve louvre details 24 20MAY05 17JUN05 0 100 24 -110 -188
1898 Admin.Bldg. - Approve aluminium cladding 24 20MAY05 17JUN05 0 100 24 -110 -188
1886 Admin.Bldg. - Approve wood ceiling details 24 27MAY05 24JUN05 0 100 24 -122 -122
1899 Admin.Bldg. - Prep & sub fall arrest system 24 27MAY05 24JUN05 0 100 24 -94 -122
1895 Admin.Bldg. - Prep & sub balustrade & metal wks 24 10JUN05 09JUL05 0 100 24 -98 -122
1881 Admin.Bldg. - Prep & sub GRP water tank details 24 18JUN05 16JUL05 0 100 24 -116 -122
FEB MAR APR MAY JUN JUL AUG17 18 19 20 21 22 2
7 14 21 28 7 14 21 28 4 11 18 25 2 9 16 23 30 6 13 20 27 4 11 18 25 1 8 1
Sheet 28 of 35
Sheet 29 of 35
Act.ID
ActivityDescription
OrigDur
EarlyStart
EarlyFinish
%Compl.
DWP %Compl.
RemDur
TotalFloat
VarianceEarly Finish
ABWF WORKS1890 Admin.Bldg. - Approve curtain wall details 24 18JUN05 16JUL05 0 100 24 -116 -182
1900 Admin.Bldg. - Approve fall arrest system 24 25JUN05 23JUL05 0 100 24 -94 -122
1896 Admin.Bldg. - Approve balustrade & metal works 24 11JUL05 06AUG05 0 100 24 -98 -122
1802 Admin.Bldg. - Design stone cladding 36 18JUL05 27AUG05 0 100 36 -70 -122
1803 Admin.Bldg. - Design slate cladding 36 18JUL05 27AUG05 0 100 36 -70 -122
1882 Admin.Bldg. - Approve GRP water tank details 24 18JUL05 13AUG05 0 100 24 -116 -122
PROCUREMENT - MATERIALABWF WORKS
6393 AdmBldg-Proc & Manuf. PD fresh & flush water sys 120 03JUN05 26OCT05 0 70 120 98 -120
1901 Admin.Bldg. - Procure glass canopy 120 18JUN05 09NOV05 0 80 120 -110 -128
1903 Admin.Bldg. - Procure sheet decking 120 18JUN05 09NOV05 0 70 120 -116 -122
1907 Admin.Bldg. - Procure doors & windows 120 18JUN05 09NOV05 0 70 120 -116 -122
1908 Admin.Bldg. - Procure louvres 120 18JUN05 09NOV05 0 80 120 -110 -128
1910 Admin.Bldg. - Procure aluminium cladding 120 18JUN05 09NOV05 0 80 120 -110 -128
6390 AdmBldg-Proc & Manuf. of HV dist. equip't 120 18JUN05 09NOV05 0 80 120 -4 -120
6395 AdmBldg-Proc & Manuf. MVAC mech.vent. sys 120 18JUN05 09NOV05 0 70 120 -40 -120
6415 AdmBldg-Proc & Manuf. FCUs & PAUs 120 18JUN05 09NOV05 0 80 120 -40 -120
1904 Admin.Bldg. - Procure wood ceiling 180 25JUN05 06FEB06 0 50 180 -122 -122
6394 AdmBldg-Proc & Manuf. FS wet sys 120 04JUL05 23NOV05 0 50 120 74 -120
1906 Admin.Bldg. - Procure curtain wall 120 18JUL05 07DEC05 0 60 120 -116 -122
1915 Admin.Bldg. - Procure fall arrest system 120 25JUL05 14DEC05 0 40 120 -94 -122
CONSTRUCTIONCIVIL & ABWF WORKSBORED PILES
1362 Admin.Bldg. - Bored Piling 1.5m dia 33nr. 26 28OCT04A 23MAR05A 100 100 0 -69
FEB MAR APR MAY JUN JUL AUG17 18 19 20 21 22 2
7 14 21 28 7 14 21 28 4 11 18 25 2 9 16 23 30 6 13 20 27 4 11 18 25 1 8 1
Sheet 29 of 35
Sheet 30 of 35
Act.ID
ActivityDescription
OrigDur
EarlyStart
EarlyFinish
%Compl.
DWP %Compl.
RemDur
TotalFloat
VarianceEarly Finish
BORED PILES1363 Admin.Bldg. - Bored Piling 2.0m dia 17nr. 80 17NOV04A 24MAR05A 100 100 0 -16
1368 Admin.Bldg. - Bored Piling 1.0m dia 4nr. 9 17JAN05A 21MAR05A 100 100 0 -16
SUBSTRUCTURE6398 Admin.Bldg. - Earth Mat & Rods - All in ptn D4 36 20APR05 02JUN05 0 100 36 -98 -98
1417 Admin.Bldg. - Pile caps 74nr. 52 03JUN05 04AUG05 0 100 52 -98 -98
1364 Admin.Bldg. - Ground slab drainage 46 25JUN05 18AUG05 0 100 46 -98 -98
SHATIN HEIGHTS SOUTH PORTAL BUILDINGSUBMITTALS & APPROVALSABWF & BUILDER'S WORKS
1998 SHT SPB - Prep & submit door & window detail 24 13JUL05 09AUG05 0 0 24 18 0
1999 SHT NPB - Prep & submit door & window detail 24 13JUL05 09AUG05 0 0 24 12 0
2006 SHT SPB - Prep & sub balustrade & metal wks 24 13JUL05 09AUG05 0 0 24 0 0
2008 SHT NPB - Prep & sub balustrade & metal wks 24 13JUL05 09AUG05 0 0 24 0 0
E&M EQPT. / MTRL. SUBMITTALS8266 ShtSpBldg-Sub.TVF, Ductworks & Control sys 78 02JUL04A 23JUL05 80 40 78 50 -28
8268 ShtSpBldg-Sub.MVAC MCC, power & control sys 54 02JUL04A 24JUN05 75 80 54 20 -34
8284 ShtRtSb-Sub.HV/LV main & submain dist. sys 54 02JUL04A 24JUN05 70 40 54 44 -19
8270 ShtSpBldg-Sub.FS AFA & FM200 sys 54 05JUL04A 24JUN05 90 0 54 182 100
8506 ShtSpBldg-Sub. building related luminaires 54 06JUL04A 13MAY05 80 20 20 80 24
8510 ShtSpBldg-Sub. building related luminaires 54 06JUL04A 13MAY05 80 0 20 84 42
8262 ShtSpBldg-Sub.LV power dist. sys 54 07JUL04A 24JUN05 85 80 54 44 -34
8265 ShtSpBldg-Sub.MVAC mech.vent. sys 54 03AUG04A 24JUN05 80 0 54 82 26
8269 ShtSpBldg-Sub.FS wet sys 54 05AUG04A 24JUN05 95 0 54 124 20
8267 ShtSpBldg-Sub.MVAC / TVF pneumatic sys 54 14AUG04A 17JUN05 50 0 48 128 128
8263 ShtSpBldg-Sub.CMCS & ELV sys 78 26AUG04A 23JUL05 65 0 78 92 8
FEB MAR APR MAY JUN JUL AUG17 18 19 20 21 22 2
7 14 21 28 7 14 21 28 4 11 18 25 2 9 16 23 30 6 13 20 27 4 11 18 25 1 8 1
Sheet 30 of 35
Sheet 31 of 35
Act.ID
ActivityDescription
OrigDur
EarlyStart
EarlyFinish
%Compl.
DWP %Compl.
RemDur
TotalFloat
VarianceEarly Finish
E&M EQPT. / MTRL. SUBMITTALS8271 ShtSpBldg-Sub.PD cleans. & flush water sys 54 20OCT04A 20JUN05 90 0 50 104 18
8264 ShtSpBldg-Sub.MVAC Package AC Units 54 17JAN05A 24JUN05 85 0 54 158 80
8272 ShtSpBldg-Sub.PD irrig. sys 54 04FEB05A 24JUN05 50 0 54 88 14
E&M EQPT. / MTRL. APPROVALS7040 ShtSpBldg-App. HV power dist. sys 18 14JUL04A 11MAY05 85 0 18 56 14
7209 ShtSpBldg-App. PD cleans. & flush water sys 18 04AUG04A 20JUN05 40 0 50 104 36
7046 ShtSpBldg-App. LV power dist. sys 18 13AUG04A 11MAY05 70 0 18 44 20
8507 ShtSpBldg-App. building related luminaires 18 18AUG04A 11MAY05 60 0 18 80 44
7155 ShtSpBldg-App. FS wet sys 18 04SEP04A 11MAY05 60 0 18 124 74
7205 ShtSpBldg-App. FS AFA & FM200 sys 18 14SEP04A 11MAY05 55 0 18 182 154
7085 ShtSpBldg-App. of CMCS & ELV sys 18 20SEP04A 11MAY05 45 0 18 92 86
7116 ShtSpBldg-App. MVAC mech.vent. sys 18 23SEP04A 11MAY05 35 0 18 82 80
7133 ShtSpBldg-App. TVF, Ductworks & Control sys 18 12NOV04A 11MAY05 40 0 18 50 50
7147 ShtSpBldg-App. MVAC MCC, power & control sys 18 12NOV04A 11MAY05 50 0 18 20 20
7101 ShtSpBldg-App. MVAC Package AC Unit sys 18 01FEB05A 11MAY05 30 0 18 158 134
7229 ShtSpBldg-App. PD irrig. sys 18 13JUL05 02AUG05 0 0 18 74 0
PROCUREMENT - MATERIALE & M WORKS
7041 ShtSpBldg-Proc. & Manuf. of HV dist. equip't 180 30MAY05 03JAN06 0 0 180 42 0
7047 ShtSpBldg-Proc & Manuf. LV power dist. equip't 180 06JUN05 10JAN06 0 0 180 24 0
7148 ShtSpBldg-Proc & Manuf. MCC, power & control sys 180 06JUN05 10JAN06 0 0 180 0 0
8508 ShtSpBldg-Proc & Manf bldg related luminaires 180 06JUL05 15FEB06 0 0 180 36 0
7134 ShtSpBldg-Proc & Manuf. TVF,Ductwks & Cont'l sys 180 13JUL05 22FEB06 0 0 180 0 0
FEB MAR APR MAY JUN JUL AUG17 18 19 20 21 22 2
7 14 21 28 7 14 21 28 4 11 18 25 2 9 16 23 30 6 13 20 27 4 11 18 25 1 8 1
Sheet 31 of 35
Sheet 32 of 35
Act.ID
ActivityDescription
OrigDur
EarlyStart
EarlyFinish
%Compl.
DWP %Compl.
RemDur
TotalFloat
VarianceEarly Finish
SHT TUNNELSUBMITTALS & APPROVALS E&M EQPT. / MTRL. SUBMITTALS
8279 ShtRtNb-Sub.Tunnel Lgt sys 78 02JUL04A 23JUL05 80 40 78 47 -31
8281 ShtRtNb-Sub.TVS control sys 54 02JUL04A 24JUN05 80 0 54 102 29
8285 ShtRtSb-Sub.Tunnel Lgt sys 78 02JUL04A 23JUL05 80 20 78 68 -13
8287 ShtRtSb-Sub.TVS control sys 54 02JUL04A 24JUN05 80 0 54 102 29
8282 ShtRtNb-Sub.FS AFA & Linear sys 54 05JUL04A 24JUN05 85 90 54 36 -49
8288 ShtRtSb-Sub.FS AFA & Linear sys 54 05JUL04A 24JUN05 90 90 54 36 -49
8278 ShtRtNb-Sub.HV/LV main & submain dist. sys 54 07JUL04A 24JUN05 85 50 54 44 -19
8283 ShtRtNb-Sub. TVS in Tunnel 54 07JUL04A 24JUN05 80 5 54 72 -1
8289 ShtRtSb-Sub. TVS in Tunnel 54 07JUL04A 11MAY05 80 5 18 72 35
8280 ShtRtNb-Sub.CMCS & ELV sys 78 26AUG04A 23JUL05 60 20 78 66 -12
8286 ShtRtSb-Sub.CMCS & ELV sys 78 26AUG04A 23JUL05 65 10 78 74 -4
E&M EQPT. / MTRL. APPROVALS7624 ShtRtSb-App. TVS in Tunnel 18 29JUL04A 11MAY05 70 0 18 72 53
7627 ShtRtNb-App. TVS in Tunnel 18 29JUL04A 11MAY05 70 0 18 72 53
6938 ShtRtSb-App. Tunnel Lgt sys 18 05AUG04A 11MAY05 60 0 18 68 65
6991 ShtRtNb-App. Tunnel Lgt sys 18 05AUG04A 11MAY05 60 0 18 47 47
6932 ShtRtSb-App. HV/LV main & submain dist. sys 18 13AUG04A 11MAY05 35 0 18 44 35
6985 ShtRtNb-App. HV/LV main & submain dist. sys 18 13AUG04A 11MAY05 70 0 18 44 35
6969 ShtRtSb-App. FS AFA & Linear sys 18 14SEP04A 11MAY05 55 0 18 36 5
7022 ShtRtNb-App. FS AFA & Linear sys 18 14SEP04A 11MAY05 55 0 18 36 5
6945 ShtRtSb-App. CMCS & TCS & ELV sys 18 20SEP04A 11MAY05 45 0 18 74 74
6998 ShtRtNb-App. CMCS & ELV sys 18 20SEP04A 11MAY05 45 0 18 66 66
FEB MAR APR MAY JUN JUL AUG17 18 19 20 21 22 2
7 14 21 28 7 14 21 28 4 11 18 25 2 9 16 23 30 6 13 20 27 4 11 18 25 1 8 1
Sheet 32 of 35
Sheet 33 of 35
Act.ID
ActivityDescription
OrigDur
EarlyStart
EarlyFinish
%Compl.
DWP %Compl.
RemDur
TotalFloat
VarianceEarly Finish
E&M EQPT. / MTRL. APPROVALS6957 ShtRtSb-App. TVS control sys 18 12NOV04A 11MAY05 60 0 18 102 83
7010 ShtRtNb-App. TVS control sys 18 12NOV04A 11MAY05 60 0 18 102 83
PROCUREMENT - MATERIALSHT TUNNEL NORTHBOUND
7023 ShtRtNb-Proc & Manuf. FS AFA & Linear sys 180 19MAY05 20DEC05 0 0 180 31 0
6986 ShtRtNb-Proc & Manuf. ES Main & submain dist. 180 24JUN05 27JAN06 0 0 180 9 0
6992 ShtRtNb-Proc & Manuf. Tunnel Lgt sys 180 09JUL05 18FEB06 0 0 180 0 0
7628 ShtRtNb-Proc & Manuf. TVS in Tunnel 180 16JUL05 25FEB06 0 0 180 19 0
SHT TUNNEL SOUTHBOUND6970 ShtRtSb-Proc & Manuf. FS AFA & Linear sys 180 19MAY05 20DEC05 0 0 180 31 0
6933 ShtRtSb-Proc & Manuf. ES Main & submain dist. 180 24JUN05 27JAN06 0 0 180 9 0
7625 ShtRtSb-Proc & Manuf. TVS in Tunnel 180 16JUL05 25FEB06 0 0 180 19 0
SHT NORTH PORTAL BUILDING SUBMITTALS & APPROVALSE&M EQPT. / MTRL. SUBMITTALS
8295 ShtNpBldg-Sub.TVF, Ductworks & Control sys 78 02JUL04A 23JUL05 80 40 78 54 -24
8297 ShtNpBldg-Sub.MVAC MCC, power & control sys 54 02JUL04A 24JUN05 75 100 54 2 -52
8299 ShtNpBldg-Sub.FS AFA & FM200 sys 54 05JUL04A 24JUN05 90 0 54 152 74
8291 ShtNpBldg-Sub.LV power dist. sys 54 07JUL04A 24JUN05 85 60 54 26 -28
8294 ShtNpBldg-Sub.MVAC mech.vent. sys 54 03AUG04A 24JUN05 80 0 54 83 26
8298 ShtNpBldg-Sub.FS wet sys 54 05AUG04A 24JUN05 95 0 54 146 32
8296 ShtNpBldg-Sub.MVAC / TVF pneumatic sys 54 14AUG04A 17JUN05 50 0 48 126 126
8292 ShtNpBldg-Sub.of CMCS & ELV sys 78 26AUG04A 23JUL05 65 5 78 78 -4
8300 ShtNpBldg-Sub.PD cleans. & flush water sys 54 20OCT04A 20JUN05 90 0 50 134 18
8293 ShtNpBldg-Sub.MVAC Package AC Units 54 17JAN05A 24JUN05 85 0 54 174 86
FEB MAR APR MAY JUN JUL AUG17 18 19 20 21 22 2
7 14 21 28 7 14 21 28 4 11 18 25 2 9 16 23 30 6 13 20 27 4 11 18 25 1 8 1
Sheet 33 of 35
Sheet 34 of 35
Act.ID
ActivityDescription
OrigDur
EarlyStart
EarlyFinish
%Compl.
DWP %Compl.
RemDur
TotalFloat
VarianceEarly Finish
E&M EQPT. / MTRL. APPROVALS7262 ShtNpBldg-App. HV power dist. sys 18 14JUL04A 11MAY05 85 0 18 30 26
7268 ShtNpBldg-App. LV power dist. sys 18 13AUG04A 11MAY05 70 0 18 26 26
8511 ShtSpBldg-App. building related luminaires 18 18AUG04A 11MAY05 60 0 18 84 62
7377 ShtNpBldg-App. FS wet sys 18 02SEP04A 11MAY05 60 0 18 146 86
7427 ShtNpBldg-App. FS AFA & FM200 sys 18 14SEP04A 11MAY05 55 0 18 152 128
7307 ShtNpBldg-App. of CMCS & ELV sys 18 20SEP04A 11MAY05 45 0 18 78 74
7338 ShtNpBldg-App. MVAC mech.vent. sys 18 23SEP04A 11MAY05 35 0 18 83 80
7431 ShtNpBldg-App. PD cleans. & flush water sys 18 04NOV04A 11MAY05 40 0 18 134 68
7355 ShtNpBldg-App. TVF, Ductworks & Control sys 18 12NOV04A 11MAY05 40 0 18 54 54
7369 ShtNpBldg-App. MVAC MCC, power & control sys 18 12NOV04A 11MAY05 50 0 18 2 2
7323 ShtNpBldg-App. MVAC Package AC Unit sys 18 01FEB05A 11MAY05 30 0 18 174 140
PROCUREMENT - MATERIALABWF WORKS
7370 ShtNpBldg-Proc & Manuf. MCC, power & control sys 180 14MAY05 16DEC05 0 0 180 0 0
7263 ShtNpBldg-Proc. & Manuf. of HV dist. equip't 180 14JUN05 17JAN06 0 0 180 4 0
7269 ShtNpBldg-Proc & Manuf. LV power dist. equip't 180 14JUN05 17JAN06 0 0 180 0 0
7356 ShtNpBldg-Proc & Manuf. TVF,Ductwks&Cont'l sys 180 18JUL05 27FEB06 0 0 180 0 0
8512 ShtSpBldg-Proc & Manf bldg related luminaires 180 27JUL05 08MAR06 0 0 180 22 0
SHT RC ENCLOSURE & T3 UNDERPASSSUBMITTALS & APPROVALS E&M EQPT./ MTRL.SUBMITTALS
8302 Sht-N.R9-Sub.Tunnel Lgt sys 78 02JUL04A 23JUL05 80 0 78 80 2
8304 Sht-N.R9-Sub.TVS control sys 54 02JUL04A 24JUN05 80 0 54 66 48
8307 Sht-N.R9-Sub.TVF, Ductworks & Control sys 78 02JUL04A 23JUL05 75 0 78 80 2
8309 Sht-N.R9-Sub.MCC, power & control sys 54 02JUL04A 24JUN05 75 0 54 87 33
FEB MAR APR MAY JUN JUL AUG17 18 19 20 21 22 2
7 14 21 28 7 14 21 28 4 11 18 25 2 9 16 23 30 6 13 20 27 4 11 18 25 1 8 1
Sheet 34 of 35
Sheet 35 of 35
Act.ID
ActivityDescription
OrigDur
EarlyStart
EarlyFinish
%Compl.
DWP %Compl.
RemDur
TotalFloat
VarianceEarly Finish
E&M EQPT./ MTRL.SUBMITTALS8305 Sht-N.R9-Sub.FS AFA & Linear sys 54 05JUL04A 24JUN05 90 0 54 131 61
8301 Sht-N.R9-Sub.HV/LV main & submain dist. sys 54 07JUL04A 24JUN05 85 0 54 89 35
8308 Sht-N.R9-Sub.LCC, power & control sys 54 07JUL04A 24JUN05 40 0 54 101 47
8303 Sht-N.R9-Sub.CMCS & ELV sys 78 26AUG04A 23JUL05 65 0 78 109 31
E&M EQP. / MTRL. APPROVALS7487 Sht-N.R9-App. Tunnel Lgt sys 18 05AUG04A 11MAY05 60 0 18 80 80
7481 Sht-N.R9-App. HV/LV main & submain dist. sys 18 13AUG04A 11MAY05 70 0 18 89 89
7604 Sht-N.R9-App. LCC, power & control sys 18 18AUG04A 11MAY05 35 0 18 101 101
7517 Sht-N.R9-App. FS AFA & Linear sys 18 14SEP04A 11MAY05 55 0 18 131 115
7494 Sht-N.R9-App. CMCS & ELV sys 18 20SEP04A 11MAY05 45 0 18 109 109
7505 Sht-N.R9-App. TVS control sys 18 12NOV04A 24JUN05 60 0 54 66 66
7529 Sht-N.R9-App. TVF, Ductworks & Control sys 18 12NOV04A 11MAY05 40 0 18 80 80
7612 Sht-N.R9-App. MCC, power & control sys 18 12NOV04A 11MAY05 50 0 18 87 87
FEB MAR APR MAY JUN JUL AUG17 18 19 20 21 22 2
7 14 21 28 7 14 21 28 4 11 18 25 2 9 16 23 30 6 13 20 27 4 11 18 25 1 8 1