+ All Categories
Home > Documents > Using Primavera Project Planner Ver 3.1 Courseware

Using Primavera Project Planner Ver 3.1 Courseware

Date post: 26-Nov-2015
Category:
Upload: q8peoples
View: 24 times
Download: 1 times
Share this document with a friend
Description:
This courseware is for new and novice users of Primavera Project Planner (P3) Ver. 3.1. It coversthe beginners and intermediate levels.
Popular Tags:
250
Using Primavera Project Planner Ver. 3.1 Courseware
Transcript
  • Using Primavera Project Planner Ver. 3.1 Courseware

  • Version 1.0, 2004 All rights reserved. No part of this publication may be reproduced or used in any form or by any means graphic, electronic or mechanical, including photocopying, mimeographing, recording, taping or in information storage and retrieval systems without the permission of the author or the publisher. Primavera Project Planner is a trademark of Primavera Systems, Inc. Other trademarks are for their relative owners

  • Courseware Purpose & Objectives This courseware is for new and novice users of Primavera Project Planner (P3) Ver. 3.1. It covers the beginners and intermediate levels. The courseware demonstrates in a very simple step-by-step procedure the building up of project while the Planning phase (before the actual start of the project) listing all the data needed to complete the plan. The last module discusses the Monitoring phase, which takes place after the actual start of the project, and all of its data, and calculation. At the completion of this course, the trainee will be able to: Differentiate between the projects phases Create a new project Create Activity Codes dictionary, and link them to activities Input activity list Input logical Relationships Run Schedule command and understand the results Input activity calendars Create Resource/Cost Account dictionaries, and assign resources and costs to activities Formatting P3, and creating Layouts Printing Layouts Creating Targets Updating projects

  • Table of Contents

    Module 1 Introduction to Primavera Project Planner Ver. 3.1 What is Primavera Project Planner?.. 1-3 How to Start P3?....... 1-5 Opening a Project in P3..... 1-6 P3 Bar Chart Screen.. 1-8 P3 PERT Screen 1-9 Method of Working... 1-10 Creating a New Project.. 1-10 Workshop 1... 1-12 Module Review. 1-13 Module Review Answers.. 1-14

    Module 2 Classification Using Activity Codes and IDs The Importance of Classification.. 2-3 Before You Start 2-3 Activity Code Command... 2-5 Activity ID tab in Activity Code... 2-7 Set the Order for Codes and IDs... 2-9 Validate Against Dictionary and Refresh.. 2-10 Printing Activity Code Dictionary 2-11 Transferring Activity Code Dictionary. 2-13 Notes.. 2-14 Workshop 2... 2-15 Module Review. 2-17 Module Review Answers.. 2-18

    Module 3 Inputting Basic Activity Data What is Activity?................................................................................................................................... 3-3 Activity ID. 3-4 Activity Description.. 3-4 Activity Original Duration (OD)... 3-5 Activity Type. 3-6 Before You Start 3-8 Adding Activities.. 3-9 Deleting Activities. 3-10 Editing Activities... 3-10 Copying Activities. 3-12 Linking Activities with Codes... 3-13 Workshop 3... 3-14 Module Review. 3-17 Module Review Answers.. 3-18

  • Module 4 Inputting Logic Relationships What is Logic Relationship?.................................................................................................................. 4-3 Predecessor and Successor. 4-4 Types of Relationships... 4-5 Relationships with Lag... 4-7 Examples of Relationships with Lag.. 4-8 Inputting Relationships Using Bar Chart View: Step 1. 4-9 Inputting Relationships Using Bar Chart View: Step 2. 4-10 Inputting Relationships Using Bar Chart View: Step 3. 4-13 Inputting Relationships Using PERT View: Step 1, 2, and 3 4-14 Editing Relationships. 4-17 Tracing Logic in PERT View. 4-19 Link and Unlink Activities. 4-19 Autolink Activities. 4-20 Workshop 4 4-21 Module Review.. 4-23 Module Review Answers... 4-24

    Module 5 First Schedule Run Introduction 5-3 Automatic Schedule vs. Manual Schedule. 5-3 The Schedule Passes... 5-6 Total Float.. 5-8 Free Float 5-9 Other Data Checked for While Scheduling 5-9 Schedule Command 5-11 Workshop 5 5-14 The View after Schedule 5-15 Schedule Report. 5-16 Notes... 5-19 Workshop 6 5-20 Module Review.. 5-21 Module Review Answers... 5-22

  • Module 6 Inputting Activity Calendar Introduction... 6-3 Global Calendar. 6-4 Individual Calendar... 6-7 Assigning Individual Calendar to an Activity... 6-10 Imposing a Finish Date on the Project.. 6-10 Other Ways to Define Holidays 6-12 Printing Calendars. 6-13 Transferring Activity Calendar. 6-16 Notes.. 6-18 Workshop 7... 6-19 Module Review. 6-21 Module Review Answers.. 6-22

    Module 7 Resources and Cost Assignment Introduction... 7-3 How to Create Resource Dictionary?.................................................................................................... 7-4 How to Create Cost Account Dictionary?............................................................................................. 7-7 Workshop 8... 7-11 Assigning Resources and Cost to Activities.. 7-12 Workshop 9... 7-17 Resource and Cost Profile (Histograms)... 7-18 Resource and Cost Tabular Reports.. 7-23 Notes.. 7-28 Workshop 10. 7-29 Module Review. 7-31 Module Review Answers.. 7-32

    Module 8 Layout and Formatting Options What is Layout in P3?............................................................................................................................ 8-3 Formatting Columns... 8-5 Workshop 11.. 8-7 Formatting Selected Bars... 8-8 Workshop 12.. 8-10 Global Bar Formatting... 8-11 Workshop 13.. 8-16 Module Review. 8-17 Module Review Answers.. 8-18

  • Module 9 More Formatting Options Formatting Options... 9-3 Timescale Formatting 9-4 Sight Lines Formatting.. 9-6 Screen Colors Formatting.. 9-8 Fonts Formatting... 9-9 Dates Formatting... 9-10 Organizing. 9-11 How P3 Calculates the Dates If Totals are Displayed?......................................................................... 9-13 Reorganize Now 9-13 Summarize. 9-14 Filters. 9-16 Selecting Using Filters.. 9-19 Workshop 14. 9-20 Module Review. 9-23 Module Review Answers.. 9-24

    Module 10 Printing Layouts Introduction........ 10-3 Printer Setup... 10-3 Page Setup.. 10-6 Print Preview.. 10-11 Print Command.. 10-13 Workshop 15.. 10-15 Module Review. 10-17 Module Review Answers.. 10-18

    Module 11 Project Updating Before the Actual Start of the Project 11-3 Workshop 16.. 11-4 Actual Work Started What Should I Do?............................................................................................... 11-5 Updating Using Progress Spotlight 11-9 Earned Value.. 11-10 Workshop 17.. 11-13 Making Backup of Your Project 11-15 Restoring Your Project... 11-16 Creating Updating Layouts 11-17 Creating Tabular Reports... 11-18 Workshop 18.. 11-25 Module Review. 11-27 Module Review Answers.. 11-28

  • Preface Primavera Project Planner (P3) is a tool for Planners, Project

    Managers, and any person needs to plan-control a project

    This courseware is perfect for new and novice users of P3. It is a very handy tool for teachers in colleges and universities whom they are teaching P3

    This courseware will not teach the reader Project (Construction) Management. It is a pre-requisite to know the science behind PM or CM by at least reading a book, or taking a course

    This courseware can be used as instructor-led courseware, or teach-your-self courseware:

    As for the first option, the estimated time would be 3 days, 8 hours a day

    As for the second option, the reader can take it up to his/her convenience

    There are 18 workshops, which will complete a full (small) project starting from creating the project, up until the updating process. Solving all workshops will lead to:

    Simulate a real life project from beginning to end, hence putting the reader in the practical mode

    Organize the information in a very logical order Not overlooking any of the basic and necessary commands and

    functions in P3

    This courseware will cover the basic and intermediate levels of knowledge in P3

    This courseware is covering P3 Ver. 3.1

  • 1-1

    Module 1:

    Introduction to Primavera Project Planner Ver. 3.1 This module contains: What is Primavera Project Planner (P3)? How to deal with P3 file commands? P3 screens Method of working How to create a new project

  • Using Primavera Project Planner Ver. 3.1

    1-2

  • Module 1: Introduction to Primavera Project Planner Ver. 3.1

    1-3

    What is Primavera Project Planner?

    Primavera Project Planner is the flagship product of Primavera Systems, Inc. the leader in the management software since 1982

    Primavera Project Planner is abbreviated P3 P3 is specialized in managing all types of projects: small, medium,

    and large

    Big projects through the world were planned and controlled using P3

    P3 is used in almost all countries of the world Mainly there are two stages in Project Management to manage any

    project:

    Planning stage Monitoring stage

    In Planning stage, which takes place before the practical start of the project, the management team will plan for the following factors:

    Time Resources Cost

    To mention few things takes place in Planning stage: Calculating activity duration based on work demanded,

    productivity, and efficiency of the different resources

    Understanding the logic sequence of the project Assigning Resources and Costs to activity, hence, view the

    Resource/Cost histograms

    Generating a Procurement plan Anticipating problems may take place in all parts of the project

  • Using Primavera Project Planner Ver. 3.1

    1-4

    Planning team will use:

    Previous management experiences Previous practical experiences of similar projects Historical data collected actually from the field

    The plan generated should be practical and doable, and not ideal, and impossible to be accomplished

    In the Monitoring stage, the management team will: Specify the type of data to be collected from the field Decide on which forms should be used in collecting data (you

    can use international pre-defined forms, or customize your own)

    Collect actual data from the field, in daily basis The data collected should cover the three main areas planned for,

    namely; Time, Resources, and Cost

    P3 has the sufficient functions to help the user plan for the time, resources, and cost, and then later monitor them

    P3 has enormous pre-made reports to aid the user producing all the necessary information about the project in either phase of the project

    Also, P3 has the ability to customize layouts with tables and graphics (controlling colors, fonts, etc.) and produce very handsome and colorful reports

  • Module 1: Introduction to Primavera Project Planner Ver. 3.1

    1-5

    How to start P3?

    You have two ways to start P3:

    If there is a shortcut in the desktop simply double-click it From Windows taskbar, click Start / Programs / Primavera /

    Primavera Project Planner

    P3 will start with no projects open, like the following:

  • Using Primavera Project Planner Ver. 3.1

    1-6

    Opening a project in P3

    From the toolbar click Open tool, or from menus select File/Open The following dialogue box will appear:

    Specify the Drive you want to open the project from Specify the Folders In the Projects table your project should be displayed in the list,

    click on it (dont double-click unless you are sure that this project is the desired one)

  • Module 1: Introduction to Primavera Project Planner Ver. 3.1

    1-7

    If you want to make sure that the selected project, is your desired project, simply click Overview button, and the following dialogue box will be displayed:

    In this dialogue box you can see almost all the needed information including: Project title, Company name, Planning unit, Project Start date, and Data date, Activity count, Early Finish of the project

    If this is the file, click Open, otherwise click Cancel, and select another file

    P3 has two Displays to work with (as illustrated in the next two pages):

    Bar Chart view PERT view

    Note You can open 4 different projects simultaneously in P3

  • Using Primavera Project Planner Ver. 3.1

    1-8

    P3 Bar Chart Screen

    Title Bar Menu Bar Toolbar

    Status Bar Bar AreaActivity Table

  • Module 1: Introduction to Primavera Project Planner Ver. 3.1

    1-9

    P3 PERT Screen

  • Using Primavera Project Planner Ver. 3.1

    1-10

    Method of Working

    P3 is using Critical Path Method (CPM) in calculating the dates and floats of the activities

    P3 is using Precedence Diagramming Method (PDM) in presenting the network

    P3 will calculate the schedule reference to the Data Date (DD), which is defined as Time Now:

    If you are in the Planning phase DD is the Start Date of the Project

    If you are in Monitoring phase, it will be the date of the day you will run the Schedule command in

    Creating a New project

    From the toolbar click New button, or from menus select File/New The following dialogue box will appear:

  • Module 1: Introduction to Primavera Project Planner Ver. 3.1

    1-11

    Input the Project name (should be always 4 characters) Input Number/Version, if you want to signify the trial number Input the Project title, and Company name Input the Planning unit (You have four choices, Hour, Day, Week,

    and Month). Accordingly, the Activities will be measured using the selected planning unit

    Input Workdays/week, which is the number of working days per a given week

    Input Week starts on, you have the choice of starting the week from any day you would like

    Input the Project start date Input when the Project must finish by date. This piece of

    information is optional, hence we prefer, if you leave it empty, and we will later input it

    Once you are done, click Add, a new empty project will be opening

  • Using Primavera Project Planner Ver. 3.1

    1-12

    Creating New Project

    Workshop 1 Our workshops are built around a medium project issued by Technology

    University. The project is to construct two new buildings, and to renovate an existing one. Technology University wants to build up a new building, which will be devoted for Classrooms (it will be a concrete structure), another building is a Gymnasium with high modern standards (it will be steel structure), and finally wants to renovate the existing lab building. 1. Create a new folder holding your name (this is a non-professional way

    to name a folder, but we will use it for its easiness)

    2. Start P3

    3. Create a new file and save it in your folder

    4. Input the following data:

    a. Project Name: SCIE

    b. Number/Version: 1.0

    c. Project Title: Science College Expansion Project

    d. Company Name: Technology University

    e. Planning Unit: Day

    f. Work days/Week: 5

    g. Week Starts On: Monday

    h. Project Starts: 27 JUN 2005

    5. Leave the rest of data as is, and click Add

  • Module 1: Introduction to Primavera Project Planner Ver. 3.1

    1-13

    Module Review

    1. P3 means:

    a. Primavera software version 3

    b. Primavera software goes through 3 stages of work

    c. Primavera Project Planner

    d. All of the above

    2. Project Management goes through two main stages: _____________ and ____________

    3. P3 can deal with:

    a. 1 file at a time

    b. 2 files at a time

    c. 3 files at a time

    d. 4 files at a time

    4. You input actual data in the Planning stage:

    a. True

    b. False

    5. DD definition is:

    a. Start Date

    b. Time Now

    c. Data Date

    d. B & C

    6. CPM means ______________________________________________________________.

  • Using Primavera Project Planner Ver. 3.1

    1-14

    Module Review Answers 1. c

    2. Planning and Monitoring

    3. d

    4. b

    5. d

    6. Critical Path Method

  • 2-1

    Module 2:

    Classification Using Activity Codes and IDs This module contains: The importance of Classification in projects The difference between Activity Codes and Activity IDs Steps to create Activity Code Dictionary Printing and Sharing Activity Code Dictionary

  • Using Primavera Project Planner Ver. 3.1

    2-2

  • Module 2: Classification Using Activity Codes and IDs

    2-3

    The Importance of Classification

    Activities are the main component of a project Mid-sized projects may reach 1000 to 4000 activities Dealing with such big number of Activities needs from the user to

    classify the activities to achieve all/any of the following:

    Organize and group the activities according to common code which will lead to produce good looking Layouts (will be discussed later)

    Produce complex reports fast and accurate Answer urgent questions (e.g. in meetings) using simple steps

    Classification of Activities can be done using: Activity Codes (Code or ID) WBS (Work Breakdown Structure)

    We will discuss in this courseware the Activity Codes Before You Start

    Before you start inputting data to P3, go through the following steps: Draw diagram (or diagrams, depends on your case) to show the

    types of classifications and their expected values, like the diagram below:

    Internal Finishing External Finishing Construction

    Phase

  • Using Primavera Project Planner Ver. 3.1

    2-4

    Then type a code for each classification and its values:

    From the diagram above, we can see the following: The classification (we will call it Activity Code) is Phase, and its

    abbreviation is PHAS

    The expected values for this Activity Code are: Construction CN, Internal Finishing IF, and External Finishin EF

    The number of characters for each value is 2 Repeat the same steps for other classifications

    Internal FinishingIF

    External FinishingEF

    ConstructionCN

    PhasePHAS

  • Module 2: Classification Using Activity Codes and IDs

    2-5

    Activity Code Command

    From menus select Data/Activity Codes, the following dialogue box will appear:

    In the Activity Code tab you will find actvitiy codes defined in your project (these are the default activity codes, and they will be copied to any new project automatically) so the first step will be to delete the existing codes

    Input the Activity Codes taking into consideration the following: The Name of the code shouldnt exceed 4 characters The Length, which is the number of characters for the values of

    this code (i.e. in our previous example it was 2). Sum of all lenghts shouldnt exceed 64 characters

    The Description, which is a brief description of the code

  • Using Primavera Project Planner Ver. 3.1

    2-6

    You will get something like the dialogue box shown below:

    Now input the values for each Activity Code, like below:

    Repeat the same steps for other Activity Codes

  • Module 2: Classification Using Activity Codes and IDs

    2-7

    Activity ID tab in Activity Code

    In the Activity Code dialogue box there is a tab titled Activity ID:

    What is the significance of Activity ID in P3? To answer this question, we have to know that each and every activity in P3 should have an Activity ID (which is the Activity Name), which may be anything you wish, like:

    AA1, AA2, AA3, etc. 123, 124, 125, etc. AAA, AAB, AAC, etc.

    But as you can see the above IDs dont reflect any meaning or any type of information

    P3 suggests to utilize the Activity ID part to do two things: Name our activities intelligently Calssify our activities just like we did in Activity Codes

    You can have up to four classifications as Activity ID Click on the Activity ID tab, and do as you did in the Activity Code

    tab:

    The Name of the ID shouldnt exceed 4 characters The Length, which is the number of characters for the values of

    this ID. The sum of all lenghts shouldnt exceed 10 characters

    The Description, which is a brief description of the ID

  • Using Primavera Project Planner Ver. 3.1

    2-8

    You will get something like the below:

  • Module 2: Classification Using Activity Codes and IDs

    2-9

    Set the Order for Codes and IDs

    One of most important reasons we use Activity Codes, and Activity IDs is to organize and group activities, like in the picture below:

    In Order field you will specify which group will apear first If you didnt interfere in the order, P3 will order them alphabetically Check the below dialogue box:

  • Using Primavera Project Planner Ver. 3.1

    2-10

    Validate Against Dictionary and Refresh

    If the planner while linking Activity Codes (or Activity ID) to an activity input a value that doesnt exist in the dictionary, how P3 will react?

    It depends on your project settings. There are two methods: Automatic method Manual method

    Automatic method

    From menus select Data/Activity Codes In the bottom portion of dialogue box, there is a checkbox says:

    When new code values occurs in project, validate against dictionary

    Click this checkbox on From now on, whenever the user input any value that doesnt exist in

    the dictionary, P3 will add this value

    User should later input the the description, and order Manual method From menus select Data/Activity Codes

    Click off the checkbox says: When new code values occurs in project, validate against dictionary

    From now on, whenever the user input any value that doesnt exist in the dictionary, P3 will not add this value to the dictionary, but rather will wait for the user to do that manaully

    To do that manually, click Refresh button

  • Module 2: Classification Using Activity Codes and IDs

    2-11

    Printing Activity Code Dictionary

    In order to include the classifiaction hierarchy with your project papers, so other out-siders would understand the coding structure of your project, you can print a report and save it

    Click the Print button, P3 will give you the following warning message:

    Click OK, the following dialgoue box will appear:

    A report will be produced, just like the one on the next page

  • Using Primavera Project Planner Ver. 3.1

    2-12

    This is a sample of a report:

  • Module 2: Classification Using Activity Codes and IDs

    2-13

    Transferring Activity Code Dictionary

    You can transfer Activity Code Dictionary between projects Go to the new project you want to transfer to From menus select Data/Activity Codes

    Click the Transfer button, the following warning message will appear:

    Click OK. The following dialogue box will appear:

    Specify the Driver and Folder which the desired project you want to copy from resides in, then at the top portion of the dialogue box specify the project. Now click Transfer

    The dictionary will be copied to your project

  • Using Primavera Project Planner Ver. 3.1

    2-14

    Notes

  • Module 2: Classification Using Activity Codes and IDs

    2-15

    Creating And Inputting Activity Codes and IDs

    Workshop 2 1. Open SCIE project

    2. Delete the existing Activity Codes

    3. Using the following diagram, create Activity Code PHAS and its values in the Activity Code tab (Use numbers for Order):

    4. Using the following diagram, create Activity Code RESP and its values in the Activity Code tab:

    Tom HunterTH (2)

    Liza MorrottoLM (3)

    Michael MannMM (1)

    ResponsibilityRESP

    Internal Finishing IF (3)

    External Finishing EF (2)

    ConstructionCN (1)

    Phase PHAS

    Handing Over HO (4)

  • Using Primavera Project Planner Ver. 3.1

    2-16

    5. Using the following diagram, create Activity ID BLDG and its values in

    the Activity ID tab:

    6. Produce a print out of your dictionary

    GymGM (3)

    LabLB (2)

    ClassroomsCR (1)

    BuildingBLDG

  • Module 2: Classification Using Activity Codes and IDs

    2-17

    Module Review

    1. We need Activity Codes to:

    a. Classify our activities

    b. Organize and Group our activities

    c. Produce Layouts

    d. All of the above

    2. The Name of Activity Code should not exceed _____________ characters

    3. One of the following statements are true about Activity Code Order

    a. Affect the activities grouping

    b. Affect whether this code is useable or not

    c. Differentiate between Activity Code and Activity ID

    d. Specify the maximum length of code value

    4. The number of values for any Activity Code or ID is limited by 10

    a. True

    b. False

    5. The only difference between Activity Code and Activity ID is:

    a. There is no difference

    b. Activity ID coding will appear as part of the Activity ID

    c. Activity code will appear as part of the Activity ID

    d. Both will appear as part of the Activity ID

    6. If you transfer an Activity Code Dictionary from project to another project, the transferred Dictionary will _________.the existing one.

  • Using Primavera Project Planner Ver. 3.1

    2-18

    Module Review Answers 1. d

    2. 4

    3. a

    4. b

    5. b

    6. Overwrite

  • 3-1

    Module 3:

    Inputting Basic Activity Data This module contains: What is activity? The basic activity data needed to input an activity Preparation before you input an activity Adding/Deleting/Editing Activities Copying activities Linking activities with Activity Codes

  • Using Primavera Project Planner Ver. 3.1

    3-2

  • Module 3: Inputting Basic Activity Data

    3-3

    What is Activity?

    Activity is the basic component of any project We can define activity as any work you want to accomplish Work is a very loose word, each one of us can look at it from

    different angle

    For instance, one will consider Constructing First Floor Slab as a single activity

    Another will consider: Formwork for First Floor Slab as an activity Re-baring for First Floor Slab as an activity Concrete Placement for First Floor Slab as an activity

    It is a common knowledge that if two planners were given the same project, the activity list will be very different

    This will highlight the fact that Activity List writing is not exact science

    We can input lots of information pieces for an activity, but initially we need only four:

    Activity ID Activity Description Activity Original Duration (abbreviated as OD) Activity Type

  • Using Primavera Project Planner Ver. 3.1

    3-4

    Activity ID

    Activity ID is the Activity Name It is the only compulsory piece of information P3 asks for, other data

    either can be left empty, or there is a default value for it

    In Module 2, we selected the Building to be our Activity ID, with expected values Classrooms CR, Gym GM, and Lab LB

    Now, each activity ID in our project will start with either CR, GM, or LB, example would be CR100, GM205, and LB303

    The numbers after the two characters would be sequential number, which would be left to the user

    Activity ID could be as long as 10 characters (spaces are allowed and counted)

    Activity Description

    This piece of information is devoted for the user to write a short description about the activity

    You can leave it empty if you wish (P3 will not generate any error messages)

    You can type up to 48 characters (including spaces)

  • Module 3: Inputting Basic Activity Data

    3-5

    Activity Original Duration (OD)

    Activity Original Duration can be either input by the user, or calculated by P3

    It depends on the type of resources which will be assigned to it: If the resources were Non-Driving, the user will assign the

    duration

    If the resources were Driving, P3 will calculate the duration In this courseware, we will tackle only the first type of activities,

    hence we need to calculate the OD manually then input the value to P3

    Some guidelines to help calculating OD would be: Prepare for each activity a worksheet (this can be a piece of paper

    or MS Excel sheet)

    List the resources which will work on the activity List the amount of work in which each resource can accomplish Specify the productivity, and estimated count of each resource to

    be assigned

    With the above information available the user can produce correct OD which is based on real calculation

  • Using Primavera Project Planner Ver. 3.1

    3-6

    Activity Type

    In P3, there are 9 types of activities Each one would suit a certain case The default type is Task activity In this courseware, we will discuss only five of them, they are:

    Task activity Start Milestone activity (SM) Finish Milestone activity (FM) Start Flag activity (SF) Finish Flag activity (FF)

    Task Activity The default type of activities Task activity is any activity has a duration, the start and finish of it

    will be calculated according to the activity base calendar

    Duration should be input by the user if no resources or Non-Driving resources were assigned to the activity. In case of Driving Resources P3 will calculate the duration

    Start and Finish Milestone

    Zero-Duration activities Start Milestone used to signify the beginning of an activity or group

    of related activities. Finish Milestone used to signify the ending of an activity or group of related activities

    Start Milestone considered to be a Constraint, as all of the activities related to it directly cant start before it, but rather with it, or after it

    Finish Milestone considered to be a Constraint, as all of the activities related to it directly cant finish after it, but rather with it, or before it

    Start Milestone should be updated, and will have Actual Start Finish Milestone should be updated, and will have Actual Finish

  • Module 3: Inputting Basic Activity Data

    3-7

    Start and Finish

    Flag Zero-Duration activities Start Flag used to signify the beginning of an activity or group of

    activities. Finish Flag used to signify the ending of an activity or group of activities

    Start Flag considered to be a Constraint, as all of the activities related to it directly cant start before it, but rather with it, or after it

    Finish Flag considered to be a Constraint, as all of the activities related to it directly cant finish after it, but with it, or before it

    Start Flag, and Finish Flag are always Successors to other Activities and never considered as Predecessors to other Activities. Accordingly, SF will accept neither Start-To-Finish, nor Finish-To-Finish relationships. In addition, FF will accept neither Finish-To-Start, nor Start-To-Start relationships.

    Start Flag, and Finish Flag will not be updated by the user, but P3 will update them according to the activities linked to them

    Example of Milestones

    Activity A StartMilestone Activity C

    Activity D

    Activity B

    Activity E

    Activity F

    FinishMilestone

  • Using Primavera Project Planner Ver. 3.1

    3-8

    Example of Flags

    Before You Start

    Before you start inputting basic activity data, from menus select Tools/Options/Activity Inserting, the following dialogue box will appear:

    You have three choices to select from: To Automatically number activities without showing the

    Actvitiy Form

    To Automatically number activities and showing the Actvitiy Form

    To show the Activity Form only Using the Activity Form only will give you more control over the

    process of inputting activities. Consequently, do the following:

    Click off Automatically number activities Click on Use activity form when inserting an activity

    Activity A Activity C

    Activity D

    Activity B

    Activity E

    Activity F

    Start Flag

    Finish Flag

  • Module 3: Inputting Basic Activity Data

    3-9

    Adding Activities

    From the Edit Bar, click the button with plus sign The Activity Form will appear automatically:

    You will find the cursor blinking in the ID part, type in the Activity ID, then press Tab key, or click the next field (dont press Enter, as this means that you are done with inputting)

    Next field is Activity Description, type in the activity description, press Tab key

    The cursor will go directly to the OD field, input the estimated origianl duration of your activity

    Specify the Activity Type, you have two choices: If your activity is Task, click OK, or press Enter If your activity is SM, FM, SF, or FF, right-click on the Type

    field, the following menu will appear:

    Select the desired activity type Click OK, or press Enter, the Activity Form will disappear To add another activity click below the last activity in the activity

    table, or click plus sign again

  • Using Primavera Project Planner Ver. 3.1

    3-10

    Deleting Activities

    Select the activity (or activities) to be deleted From Edit bar, click minus sign, or from menus click Edit/Delete The following dialogue box will appear:

    If you are sure of what you are doing click Yes, the activity will be deleted

    If not click No, the deleting process will stop Editing Activities

    There are two methods to edit the activity data: Editing all types of data Editing single data

    Editing all activity data

    Double-Click on any activity, the Activity Form will appear, then you can edit whatever data you would like

    The same can happen if you select from menus Edit/Edit Activity Editing single

    activity data Select the cell which contains the data you want to edit (the cell

    selector is a bold frame appears around the cell required), just like the below example:

    The contents of the cell will appear in the Edit bar Click the Edit bar, or press F2 to edit the contents

  • Module 3: Inputting Basic Activity Data

    3-11

    Note Other ways to show the Activity Form permenantly are:

    From menus select View/Activity Form Press F7

    From toolbar click Activity Form icon These 3 ways are ON/OFF functions, which means they will show

    or hide the Activity Form

    Using the baove methods of editing activites is applicable to all types of data except two types:

    All the data calculated by P3 (like ES, EF, LS, LF, TF, etc.) which we will discuss later

    Activity ID, unless you opened your project as Exclusive (which is a checkbox in the Open dialogue box)

  • Using Primavera Project Planner Ver. 3.1

    3-12

    Copying Activities

    Copying activities means copying the whole data of single activity or activities

    Copying can be done from a project to the same project, or across projects

    Select the desired activity (or activities) From menues select Edit/Copy, Ctrl+C, or right-click and select

    Copy

    Go to the desired place (the same project, or open another project) From menus select Edit/Paste, Ctrl+V, or right-click and select Paste In order for P3 to make sure that no duplication of the same activity

    ID will take place, the following dilaogue box will appear:

    You can select one of the four choices available: Rename duplicates only Rename all Prefix or suffix Auto-increment

  • Module 3: Inputting Basic Activity Data

    3-13

    Rename

    duplicates only P3 will select the coming activities with maching IDs only to be

    renamed, the rest will be pasted without any change

    Rename All P3 will show all activities to be renamed Prefix or suffix It is a fast way to rename activities, by suggesting a character (or

    characters) to appear to the left of the coming activities IDs (this is prefix) or appear to the right of the coming activities IDs (this is suffix)

    Auto-increment It is another fast way to rename activities, by suggesting a base name (for instance GM100) and then an increment number (for instance 10) this will allow P3 to rename all the coming activites easily

    Also you can make sure that the coming activities are the desired ones, by clicking Contents buttom which will display the names of the coming activities

    Linking Activities with Codes

    In Module 2 we created Activity Code Dictionary In this Module we will link each activity with the proper code value The lower left part Activity Form contains the Activity Codes

    defined and its value

    Right-click on the desired code, a list of the available values will be displayed, select the desired value

    Do the same for the other codes

  • Using Primavera Project Planner Ver. 3.1

    3-14

    Inputting Basic Activity Data

    Workshop 3 1. Open SCIE project

    2. Input the activities from next pages

    3. Taking into consideration the following notes:

    a. Read the whole list first, and identify the similarity between the IDs, and description of different activities

    b. Utilize Activity Copying utility, which will minimize the time of data input. Also, utilize of renaming of activities

  • Module 3: Inputting Basic Activity Data

    3-15

    N

    o. Activity

    ID Activity Description Type

    Dur

    atio

    n

    Phas

    e

    Res

    p

    1 CR050 Site Preparation & Mobilization for Classrooms Task 18 CN MM2 CR100 Start of Classrooms Construction SM 0 CN MM3 CR105 Excavation for Classrooms Task 25 CN MM4 CR110 Concrete Works for Foundation for Classrooms Task 28 CN MM5 CR115 Filling and Compacting Soil for Classrooms Task 15 CN MM6 CR120 Start of Concrete Skeleton for Classrooms SF 0 CN MM7 CR125 Beams/Columns/Slabs for 1st Floor (Classroom) Task 38 CN MM8 CR130 Beams/Columns/Slabs for 2nd Floor (Classroom) Task 38 CN MM9 CR135 Beams/Columns/Slabs for 3rd Floor (Classroom) Task 38 CN MM10 CR140 Finish of Concrete Skeleton for Classrooms FF 0 CN MM11 CR200 External Stone Fixing for Classrooms Task 65 EF LM 12 CR205 Waxing External Stones for Classrooms Task 12 EF LM 13 CR300 Preliminary Plumbing, Elec. & HVAC for Classrooms Task 16 IF TH 14 CR305 Internal Finishing for Classrooms Task 38 IF TH 15 CR310 Final Plumbing, Elec. & HVAC for Classrooms Task 22 IF TH 16 CR315 Paining of Classrooms Task 44 IF TH 17 CR400 Finish of Classrooms Construction FM 0 HO MM18 CR500 Handing Over Classroom Building Task 5 HO MM19 GM050 Site Preparation & Mobilization for Gym Task 12 CN MM20 GM100 Start of Gym Construction SM 0 CN MM21 GM105 Excavation for Gym Task 25 CN MM22 GM110 Concrete Works for Foundation for Gym Task 28 CN MM23 GM115 Filling and Compacting Soil for Gym Task 15 CN MM24 GM120 Steel Skeleton for Gym Task 36 CN MM25 GM200 Precast-Concrete Cladding for Gym Task 35 EF LM 26 GM205 Cleaning and Waxing Concrete Cladding for Gym Task 12 EF LM 27 GM300 Install Plumbing, Elec., and HVAC for Gym Task 40 IF TH 28 GM305 Special Wooden Floor Fixing for Gym Task 27 IF TH 29 GM310 Fixing Seats in Gym Task 24 IF TH 30 GM400 Finish of Gym Construction FM 0 HO MM31 GM500 Handing Over Gym Building Task 5 HO MM32 LB100 Start of renovation of Lab SM 0 IF MM33 LB105 Stripping the existing Lab Task 18 IF LM 34 LB110 Preliminary Plumbing, Elec. & HVAC for Lab Task 26 IF TH

  • Using Primavera Project Planner Ver. 3.1

    3-16

    35 LB115 Install Base Cabinets Task 18 IF LM 36 LB120 Install Fume Hood Task 12 IF LM 37 LB125 Install Wall Cabinets Task 29 IF LM 38 LB130 Install Chemical Sink Task 15 IF LM 39 LB135 Final Plumbing, Elec. & HVAC for Lab Task 32 IF TH 40 LB140 Lay PVC tiles over Lab Floor Task 38 IF TH 41 LB200 Finish of renovation of Lab FM 0 HO MM42 LB500 Handing Over Lab Building Task 5 HO MM

  • Module 3: Inputting Basic Activity Data

    3-17

    Module Review

    1. How many activity types available in P3:

    a. 8

    b. 9

    c. 7

    d. 5

    2. ____________ should not have a successor

    3. One of the following is considered an intelligent Activity ID:

    a. 123, 124, 125

    b. A125, A126, A127

    c. CR105, GM110, LB200

    d. All of the above

    4. I can edit the Activity ID of a certain activity

    a. True

    b. False

    5. P3 will not permit to have two activities with the same ID in the same project

    a. True

    b. False

    6. Using _________________, or ______________________ I can edit the all types of data for certain activity

  • Using Primavera Project Planner Ver. 3.1

    3-18

    Module Review Answers 1. b

    2. Flags

    3. c

    4. a

    5. a

    6. Double-click, or Edit/Edit Activity

  • 4-1

    Module 4:

    Inputting Logic Relationships This module contains: What is logic relationship? Predecessor and Successor Types of relationship Inputting relationships using Bar Chart view Inputting relationships using PERT view Editing relationships Tracing relationships Link and unlink activities Using Autolink function

  • Using Primavera Project Planner Ver. 3.1

    4-2

  • Module 4: Inputting Logic Relationships

    4-3

    What is Logic Relationship?

    In Module 1 it was mentioned that P3 uses PDM (Precedence Diagramming Method) in representing the network

    There are mainly two methods to represent a network: Activity-On-Arrow Activity-On-Node

    Activity-On-Arrow

    Also known ADM (Arrow Diagramming Method) The old method of representing the network To go from event A to event B, you will do certain thing:

    Almost none of the software in the current market is offering this method for representing the network

    Activity-On-Node Also known as PDM The activities are at the two nodes of a logic relationship Logic relationship is a link which ties two activities in a sequence

    manner, for instance:

    The name Logic indicates that the relationship is not compulsory but rather it represents how the planner is viewing the sequence of the project, hence any delay in start or end, is acceptable

    A B CExcavation Foundation

    Excavation Foundation Filling

  • Using Primavera Project Planner Ver. 3.1

    4-4

    Predecessor and Successor

    Based on the above each activity will have: Predecessor (or Predecessors) Successor (or Successors)

    Predecessor Is any activity takes place in time before a given activity There could be more than one predecessor for a given activity

    Successor Is any activity takes place in time after a given activity There could be more than one successor for a given activity

    One of the common practices is to prepare a table called either the Successor table or Predecessor table, depends on the way you want to take it:

    If you want to start with the first activity and go all the way to the right, you should produce a Successor table

    If you want to start with the last activity and go all the way to the left, you should produce a Predecessor table

    A successor table may look something like the following: Activity Successor

    CR050 CR100, GM050, LB100 CR100 CR105 CR105 CR110

  • Module 4: Inputting Logic Relationships

    4-5

    Types of Relationships

    P3 supports four types of relationships: Finish-To-Start (known as FS) Start-To-Start (known as SS) Finish-To-Finish (known as FF) Start-To-Finish (known as SF)

    Note When we say Start, that means the start of a working day When we say Finish, that means the finish of working day

    Finish-To-Start The most commonly used relationship, and the default relationship in P3

    When A finishes B starts the next day:

    Start-To-Start One of two relationships which allows parallel activities When A starts B starts at the same day:

    Note In the above case A is considered to be a Predecessor of B although A and B starts at the same day

    AOD=7

    BOD=10

    S=1 F=7 S=8 F=17

    BOD=10

    S=5 F=14

    AOD=7

    S=5 F=11

  • Using Primavera Project Planner Ver. 3.1

    4-6

    Finish-To-Finish The second relationship which allows parallel activities

    When A finishes B finishes at the same day:

    Note In the above case A is considered to be a Predecessor of B although A and B finishes at the same day

    Start-To-Finish This relationship is seldom used by planners It can be used effectively with flags If you want to link a start of an activity with a Finish Flag you can

    use Start-To-Finish relationship

    When A starts B finishes

    BOD=10

    F=14

    AOD=7

    F=14

    A

    B

  • Module 4: Inputting Logic Relationships

    4-7

    Relationships with Lag

    Normally the following applies to relationship: In FS relationship if the predecessor finishes in day 5 (for

    instance) the successor will start at day 6

    In SS relationship if the predecessor starts at day 5, the successor will start at day 5

    In FF relationship if the predecessor finishes at day 11, the successor will finish at day 11

    The above shows that relationships dictate immediate start or finish for the successor. If you dont want immediate start or finish for the relationship, you have to use the Lag time

    Lag time is the number of time-periods (days in our case) which you delay the successor from its predecessor. Lag time can be positive, or negative, check the following examples in the next page:

  • Using Primavera Project Planner Ver. 3.1

    4-8

    Examples of Relationship with Lag

    A BFS 7

    Finish-To-Start with +ve Lag

    A

    B

    FF 4

    Finish-To-Finish with +ve Lag

    A

    B

    Finish-To-Start with -ve Lag

    FS -3

    A

    BSS 6

    Start-To-Start with +ve Lag

  • Module 4: Inputting Logic Relationships

    4-9

    Inputting Relationships Using Bar Chart View: Step 1

    Draw your network on paper first: The biggest mistake a planner can do is to start inputting

    relationships without preparing it on paper first

    The management team should have more than one meeting discussing the logic of the network

    Drawing the network and the logic sequence is not an easy job, it needs:

    Huge field experience Team work and discussion (even sometimes needs Brain

    Storming)

    Deciding which is more important to the planner (it differs from owner point-of-view, to contractor point-of-view) the completion time, or the expenditure of money and resources. Hence creating more serial fashion relationships, or parallel (or overlapping) fashion relationships

  • Using Primavera Project Planner Ver. 3.1

    4-10

    Inputting Relationships Using Bar Chart View: Step 2

    Prepare the layout so you can easily see the relationship lines. This involves three steps to do:

    Make sure that the relationship lines is shown Increase the Row Height Learn how to Find Activities

    Show Relationship lines

    The relationships can be either displayed, or hidden To make sure, do the following:

    From menus choose View, the following menu will appear:

    If you see (3) beside Relationships, you will know that the relationship lines will be displayed, if not, do one of the following:

    From menus select View/Relationships Press F3

    From toolbar, click Relationship Lines tool

  • Module 4: Inputting Logic Relationships

    4-11

    Increase Row

    Height Increasing Row Height is to spread the activities vertically so you

    can view the relationship lines better, see the following examples:

    Without Increasing the row height:

    With Increasing the row height:

    Select one of the activities From menus select Format/Row Height, the following dialogue

    box will appear:

    Do the following steps: Turn off the check box Automatic Size Set the Row height in points value to the desired number Click on All Activities under Apply to part Click OK

  • Using Primavera Project Planner Ver. 3.1

    4-12

    Find activity This function is very important, as sometimes you need to locate an

    activity to start defining its successor(s)

    Do one of the following: From menus select Edit/Find Activity Press Ctrl+F

    From toolbar, click Find Activity tool Using any of the above the following dialogue box will appear:

    Type in the Activity ID, select All activities, then click Find

  • Module 4: Inputting Logic Relationships

    4-13

    Inputting Relationships Using Bar Chart View: Step 3

    You can input the relationships using: Activity Form Graphically

    Using Activity Form

    Select (or Find) the activity you want to define either successor(s), or predecessor(s) for

    Press F7

    Click either Pred, or Succ buttons The following dialogue box will appear

    Click (+) sign, type in the predecessor (or successor) ID Specify the Rel (which is the relationship). The default is FS If there is any Lag, specify it You can define more than one predecessor, or successor

    Select one of the predecessors, or successors, and click Jump, to go to it. Then continue defining relationships

    This what you may get:

  • Using Primavera Project Planner Ver. 3.1

    4-14

    Using

    Graphically method

    Specify the end (Start, or Finish) you want to start with for a certain activity

    Get closer to it, up until the cursor change to Relationship cursor Now click and hold. The relationship line will appear Go to the other desired end, and drop the relationship line

    The relationship line will be created Inputting Relationships Using PERT View: Step 1, 2, and 3

    All the notes we highlighted in the Bar Chart for Step 1, applies to PERT

    From menus select View/PERT The following view will appear:

  • Module 4: Inputting Logic Relationships

    4-15

    Each activity is represented by a box, the left part of the box is the

    start, and the right part is the finish

    As you can see the boxes are very close to each other To spread the boxes horizontally and vertically, you can increase the

    spacing

    From menus select Format/Organize, the following dialogue box will appear, select the Spacing tab:

    Change to the new value for the spacing horizontally, and vertically

  • Using Primavera Project Planner Ver. 3.1

    4-16

    The result may look something like the following:

    The relationship lines are by default shown But still we need to find activities, like we did in the Bar chart view To input relationships, use one of the two methods mentioned in Bar

    chart view (namely; using the Activity Form, or the Graphical method)

  • Module 4: Inputting Logic Relationships

    4-17

    Editing Relationships

    For both Bar chart view, and PERT view, the editing methods are the same

    Available editing methods are: Using Activity Form Graphical method

    Using Activity Form

    Find the activity you want to edit the relationship for Press F7 The Activity Form will appear

    Click both Pred, or Succ buttons This what you will see:

    You can add new relationship, edit an existing one, or delete a relationships according to your need

    Once you are done, close the two forms, on the Activity Form click OK. Now find another activity to edit its relationships

  • Using Primavera Project Planner Ver. 3.1

    4-18

    Graphical

    method It is better to do it in the PERT view, as the relationship lines appear

    clearer in this view

    Go to PERT view Find the desired relationship to be edited Click the relationship line, the following dialogue box will appear:

    The dialogue box will show the following information: The current Predecessor (un-editable) The current Successor (un-editable) The relationship type The Lag

    Change either the relationship type, or the lag

    Or you can delete the relationship by clicking the Delete button

  • Module 4: Inputting Logic Relationships

    4-19

    Tracing Logic in PERT View

    One of the greatest methods to check your logic Go to PERT view Select an activity From menus View/Trace Logic The screen will be cut into two halves. The lower half will show the

    current activity, its predecessor(s), and its successor(s):

    Check your work, then select another activity from the upper half, or from the lower half

    Link and Unlink Activities

    This should be done only Bar chart view If you have a series of activities and all of them are connected with

    FS relationship, you can link them fast and smoothly using Link activity function, do the following steps:

    Select the desired activities From menus select Edit/Link Activities The activities will be linked with FS relationship

    You can unlink activities if they were linked with FS relationships: Select the desired activities From menus select Edit/Unlink Activities The activities will be unlinked

  • Using Primavera Project Planner Ver. 3.1

    4-20

    Autolink Activities

    This facility is an automatic method of linking activities as you input them

    From menus select Insert/Autolink Select an activity (this is a very important step) which will be the

    predecessor of the coming activities

    Start adding activities Whenever you are done, an FS relationship will be added to the new

    activity

    To stop this facility, from menus select Insert/Autolink again

  • Module 4: Inputting Logic Relationships

    4-21

    Inputting Logic Relationship

    Workshop 4 1. Open SCIE project

    2. Choose whether you want to input the relationships using Bar chart view, or PERT view

    3. Accordingly, setup the activities in a way to help you do your job better

    4. Input the relationships as indicated in the next page, taking into consideration the following points:

    a. The graphical is more convenient if you are dealing with PERT view

    b. If there are lots of activities connected with FS relationship, utilize Link, and Unlink

    c. After you are done, make sure to use Trace Logic function, to check the network accuracy

  • Using Primavera Project Planner Ver. 3.1

    4-22

    CR

    050

    OD

    =18

    CR

    100

    CR

    105

    OD

    =25

    CR

    110

    OD

    =28

    CR

    115

    OD

    =15

    CR

    125

    OD

    =38

    CR

    120

    SS

    CR

    135

    OD

    =38

    CR

    130

    OD

    =38

    CR

    200

    OD

    =65

    CR

    140

    FF

    CR

    205

    OD

    =12

    CR

    300

    OD

    =16

    SS14

    CR

    305

    OD

    =38

    CR

    310

    OD

    =22

    CR

    315

    OD

    =44

    CR

    400

    CR

    500

    OD

    =5

    GM

    050

    OD

    =12

    GM

    100

    GM

    105

    OD

    =25

    GM

    110

    OD

    =28

    GM

    115

    OD

    =15

    GM

    120

    OD

    =36

    GM

    200

    OD

    =35

    GM

    205

    OD

    =12

    GM

    300

    OD

    =40

    SS14

    GM

    305

    OD

    =27

    GM

    310

    OD

    =24

    GM

    400

    GM

    500

    OD

    =5

    LB10

    0LB

    105

    OD

    =18

    LB11

    0O

    D=2

    6LB

    115

    OD

    =18

    LB12

    0O

    D=1

    2LB

    125

    OD

    =29

    LB13

    0O

    D=1

    5LB

    135

    OD

    =32

    LB14

    0O

    D=3

    8LB

    200

    LB50

    0O

    D=5

  • Module 4: Inputting Logic Relationships

    4-23

    Module Review

    1. Almost all of the management software in the world are using

    a. PDM

    b. ADM

    c. Both PDM and ADM

    d. None of the above

    2. _______ is the default relationship type

    3. I can link activities as I add them up using Autolink function

    a. True

    b. False

    4. Which is true about Trace Logic:

    a. Used only in PERT view

    b. You should select an activity first

    c. To trace the predecessor(s) and the successor(s) of a selected activity

    d. All of the above

    5. In PERT there is no need to make sure that relationship lines are shown or hidden, as they are always shown

    a. True

    b. False

    6. From menus select _____________________ to spread the activity boxes horizontally and vertically in PERT view

  • Using Primavera Project Planner Ver. 3.1

    4-24

    Module Review Answers 1. a

    2. FS

    3. a

    4. d

    5. a

    6. Format/Organize

  • 5-1

    Module 5:

    First Schedule Run This module contains: Automatic vs. Manual Scheduling Schedule Passes Total and Free Float The Schedule command The view after Scheduling Schedule report

  • Using Primavera Project Planner Ver. 3.1

    5-2

  • Module 5: First Schedule Run

    5-3

    Introduction

    Schedule is to calculate the start and finish dates for each activity, hence will produce the finish date of the project

    Normally in Planning phase, the planner will perform scheduling several times, and the first one should be after finishing inputting activities and relationships

    The purpose of the first run, is to get the initial dates, so it can be used in the coming meetings

    Also, the initial dates may be submitted to Procurement department so they will have some sort of deadlines they can include in their RFQ to be issued

    Automatic Schedule vs. Manual Schedule

    In P3 there are two types of scheduling: Automatic Manual

    Automatic Schedule

    From menus select Tools/Schedule, the following dialogue box will appear:

  • Using Primavera Project Planner Ver. 3.1

    5-4

    Click the Options button, the following dialogue box will appear:

    Under Automatic scheduling and leveling, make sure that Schedule automatically is selected, then click OK

    If you turn the automatic schedule on, that means, P3 will always recalculate the dates if any new data and/or editing took place in your project

    This method will not produce any schedule reports, which will deprive the user from knowing and documenting the changes happened on the dates through out the development of the plan

    We dont recommend this method

  • Module 5: First Schedule Run

    5-5

    Manual Schedule Under Automatic scheduling and leveling, make sure that

    Schedule automatically is NOT selected, instead select Off, then click OK

    This method means you have to issue the command of Tools / Schedule each and every time your perform any changes on your project which will affect the start and finish dates

    It will produce a scheduling report (will be shown later in this Module) which contains great information to the planner, also, it is considered a documenting tool to show the development of the plan

    It is highly recommended

  • Using Primavera Project Planner Ver. 3.1

    5-6

    The Schedule Passes

    When the user issue the Schedule command, P3 will perform two passes:

    Forward Pass, which will start from the first activity with no predecessor, all the way to the last activity with no successor

    Backward Pass, which will start from the last activity with no successor, all the way to the first activity with no predecessor

    Forward Pass To calcualte the Early Start (ES), and the Early Finish (EF), which we call them Early dates

    Early dates are the earliest dates an activity can start and finish after the finish of its predecessor(s)

    P3 will first locate the first activity with no predecessor. It could be more than one activity

    The ES of the first activity is the start date of the project (which you input when you created the project)

    To calcualte the EF, P3 will use the following EF=ES+Dur-1 Why the -1? Comparing to the text books in management, this

    formula is different. The formula used there is EF=ES+Dur. The answer to that question is; text books starts at day 0, which is not practical. Yet in P3 we start at day 1, and hence we have to deduct 1 from the duration

    See the following example: OD=4 EF=4ES=1

    Activity A

    OD=16 EF=24ES=9

    Activity C

    OD=8 EF=8ES=1

    Activity B

  • Module 5: First Schedule Run

    5-7

    Note Activity C, waited for all of its predecessors to finish, hence started

    at day 9

    The calculated finish date of this small project derived from the EF of the last activity, which is 24 days

    Backward Pass To calcualte the Late Start (LS), and the Late Finish (LF), which we call them Late dates

    Late dates are the latest dates an activity can start and finish without delaying the calculated finish date of the project

    P3 will locate the last activity with no successor. It could be more than one activity

    The LF of the last activity is the calcualted EF which was produced in the Forward Pass

    To calcualte the LS, P3 will use the following LS=LF-Dur+1 As we deduct 1 in the Forward Pass, we have to add 1 in the

    Backward Pass, so we can finish with day 1

    See the following example:

    OD=4 EF=4

    LS=5 LF=8

    ES=1

    Activity A

    OD=16 EF=24

    LS=9 LF=24

    ES=9

    Activity C

    OD=8 EF=8

    LS=1 LF=8

    ES=1

    Activity B

    Note LF of activity A, and B is the day before LS of activity C, hence the LF is day 8

  • Using Primavera Project Planner Ver. 3.1

    5-8

    Total Float

    As a result of the Forward Pass, and Backward Pass, four dates will be produced (namely; ES, EF, LS, and LF)

    In view of that, P3 will calculate the Total Float (TF) Total Float is the number of days you can delay the start of an

    activity without starting at ES, but without delaying the whole project

    TF = LF EF Accordingly the Backward Pass will be:

    OD=4 EF=4

    LS=5 TF=4 LF=8

    ES=1

    Activity A

    OD=16 EF=24

    LS=9 TF=0 LF=24

    ES=9

    Activity C

    OD=8 EF=8

    LS=1 TF=0 LF=8

    ES=1

    Activity B

    If there is no Imposed Finish Date (dicussed in the next Module), or any type of Constraint the lowest TF for any activity would be 0 (zero)

    We call the activities with TF = 0 Critical activities We call the activities with TF > 0 Non-Critical activities We call the path that links the Critical activities; the Critical Path Critical Path is the longest path in the netwrok A given network may have more than one Critical Path We call the above method of calculation, the Critical Path Method

    (CPM)

  • Module 5: First Schedule Run

    5-9

    Free Float

    P3 also will calculate the Free Float (FF) Free Float is the number of days you can delay the start of an

    activity without starting at ES, but without delaying the successor

    TF = ES of the successor - EF of the activity - 1 FF can be equal to TF, and can be different

    Other Data Checked for While Scheduling

    As you can see from the previous discussion, when the user issues the Schedule command, P3 will calculate six types of data, which they are:

    Two Early Dates (ES, EF) Two Late Dates (LS, LF) Two Floats (TF, FF)

    Other data checked for, while scheduling are: Circular Loops Constraints Activities Open Ends Activities Out-of-Sequence Activities

    Circular Loop The Circular Loop is the relationships that starts at an activity and return back to the same activity

    If P3 detect any loop, it will stop the Schedule calcualtion and produce a report stating the relationships which led to the loop

    A B C

  • Using Primavera Project Planner Ver. 3.1

    5-10

    Here is an example of the Circular Loop:

    Constraints Activities

    P3 will identify any activity with constraints imposed on it, and report it in the Schedule report

    The four types of activities SM, FM, SF, FF, are all considered Constraints, hence they will be reported in the Schedule report

    Open Ends Activities

    P3 will assume that each activity will have at least one predecessor, and one successor

    Any activity with no predecessor, or with no successor, is considered an open end

    Planners as they are creating their network will cosider the recommendation that network should start with one activity, and finish with one activity (although, neither networking methods, nor P3 will object if the network started with 100 activities, and finished with 100 activities)

    If the Planners abide to the above rule, they will have a prior knowledge that two activities will be mentioned in the report as Open Ends. So, if more than these were mentioned, planners will know that they overlooked a relationship

    Out-of-Sequence Activities

    If an activity started the actual work before the finish of its predecessor, this activity is considered to be out-of-sequence

    This is evident when the actual work starts and not while Planning phase

  • Module 5: First Schedule Run

    5-11

    Schedule Command

    From menus select Tools/Schedule

    Or from toolbar, click Schedule button, the following dialogue box will appear:

    Specify Data Date, as mentioned in Module 1, Data Date definition is Time Now:

    In the Planning phase the Data Date is always the first day of the project as defined when the project was created

    Once you start inputting actual data, Data Date will be the day of which you performed the schedule in

    If you want to include in you report: Constraint listing, click this checkbox on Open Ends listing, click this checkbox on Out-of-Sequence activities listing, click this checkbox on

    Click Schedule Now button, the following dialogue box will appear:

  • Using Primavera Project Planner Ver. 3.1

    5-12

    Make sure that View on screen is selected, then click OK P3 will start performing the calculation P3 will then produce the Schedule report The Schedule Report is a very valuable tool for planners, as it will

    help in the following points:

    It contains valuable information about the project and the network

    It will work as a tool in the hand of the planner to docuemt how the project evoleved through the Planning phase

    The following is an example of a Schedule report:

  • Module 5: First Schedule Run

    5-13

    Note If you press F9 the following dialogue box will appear:

    This is identical to the command above except it will not produce the report

  • Using Primavera Project Planner Ver. 3.1

    5-14

    Calculate the Schedule

    Workshop 5 1. Open SCIE project

    2. Using Tools/Schedule calculate the schedule using the default Data Date, making sure that all the checkboxes are on. Click Schedule Now

    3. From the Schedule report answer the following questions:

    a. How many activities in your project? ______________ (42)

    b. How many critical activities do you have in your project? ______________ (15)

    c. How many relationships are there in your project? ______________(43) (Hint: the number 43 is excluding the two relationships of the two Flags)

    d. How many Flags defined in your project?____________ (2)

    e. When the project will finish? _______________(12OCT06)

  • Module 5: First Schedule Run

    5-15

    The View after Schedule

    We recommend, that immediately you close your project and re-open it again, so the sorting will take place

    You will see two groups of activities: Red Activities, which means Critical activities Green Activities, which means Non-Critical activities

    Activities will be sorted according to their ES, and then TF, therefore the list of activities will be different

  • Using Primavera Project Planner Ver. 3.1

    5-16

    Schedule Report

    P3 is equipped with lots of pre-defined tabular reports, One of these is the Schedule Report

    From menus select Tools/Tabular Reports/Schedule, the following dialogue box will appear:

    Click the Add button, the following dialogue box will appear:

    Each Schedule report will have an ID, starting with the letters SR, then a sequential number (which is given by P3), click Add, to accept the number. The dialogue box in the next page will be displayed

  • Module 5: First Schedule Run

    5-17

    Type in the Title of the report (highly recommended), so you can utilize it

    In Content tab, and under Include the following data, the following applies:

    Leave Activity Code line there. This line shows the basic activity data

    You can add to this basic data other information like Predecessor, Successor, and lots of other types

    In Content tab, and under Show these codes on activity code line, you can specify up to five different codes for each activity

  • Using Primavera Project Planner Ver. 3.1

    5-18

    Click the Format tab, you will see the following:

    Set the Sort by criteria Select the information to be displayed

    Once you are done, click Run button, accordingly the report will be produced, hence you can print it, or save it

  • Module 5: First Schedule Run

    5-19

    Notes

  • Using Primavera Project Planner Ver. 3.1

    5-20

    Schedule Report

    Workshop 6 1. Open SCIE project

    2. Produce Schedule report using the following points

    a. Title: First Schedule Report

    b. In Content tab, and under Activity code line, add Predecessor activity, and Successor activity, make sure to put Skip Lines to 1 for all three of the entries

    c. In Format tab, make sure that activities are sorted according to ES, and then TF using Ascending fashion

    d. Dont include in the report Calendar, and Activity Codes

    3. Click Run to produce the report

    4. Save it under the name Sched01.out

  • Module 5: First Schedule Run

    5-21

    Module Review

    1. In Schedule, P3 calculates:

    a. 6 types of data

    b. 5 types of data

    c. 2 types of data

    d. 4 types of data

    2. __________ is the other type of floats after Total Float

    3. Total Float is calculated after the Forward Pass

    a. True

    b. False

    4. ES+Duration-1 is the formula to calculate

    a. Late Start

    b. Late Finish

    c. Early Start

    d. Early Finish

    5. The calculated finish date of the project is

    a. Late Finish of the last activity

    b. Early Finish of the last activity

    c. Late or Early they are equal

    d. Imposed Finish Date by the user

    6. The activity with _________ color is considered critical activities, but with _______ color they will be non-critical

  • Using Primavera Project Planner Ver. 3.1

    5-22

    Module Review Answers 1. a

    2. FF

    3. b

    4. d

    5. b

    6. Red, Green

  • 6-1

    Module 6:

    Inputting Activity Calendar This module contains: What is global calendar What is individual calendar Assigning calendars to activities Imposing a Finish date on the project Defining Holidays Printing calendars Transferring calendars

  • Primavera Project Planner Ver. 3.1 Level 1

    6-2

  • Module 6: Inputting Activity Calendar

    6-3

    Introduction

    When we created the project, P3 asked two questions: Workdays/Week Weeks starts on

    Let us assume that you answered the first question with 5, and the second question with Monday

    Accordingly P3 will create an individual calendar, and its ID is 1, which contains that the working days of the week are Monday, Tuesday, Wednesday, Thursday, and Friday, and the two weekends are Saturday and Sunday

    All of the 42 activities we input in our workshop were assigned Calendar 1, hence the Finish date of the project (i.e. 12OCT06) was calculated also based on Calendar 1

    However, not all activities will work the same working days. Also, Calendar 1, does not contain any holidays

    Activity calendar means calendar attached to an activity, affecting the Schedule calculation of this activity

    Schedule will not calculate an ES (for instance) in a day that considered as holiday or weekend in the calendar of an activity

    So sometimes one of the techniques to decrease the total duration of projects is to assign the critical activities to calendars with more working days per week

  • Primavera Project Planner Ver. 3.1 Level 1

    6-4

    Global Calendar

    P3 has a unique calendar called Global calendar This calendar contains information which will affect the whole

    project and the other individual calendars

    Global Calendar cant be assigned to activities From menus select Data/Calendars, the following dialogue box

    will appear:

  • Module 6: Inputting Activity Calendar

    6-5

    From the upper list, click on Global Calendar

    Click the Standard button, the following dialogue box will appear:

    You can change the following data: In which day the week will start When the calendar will start (always P3 will assume that calendar

    will start a year before the starting date of the project)

    When the project will start When is the Data Date Imposed Finish Date (will be discussed later in this Module) If a holiday occurs in a weekend, how should P3 treats it. It is

    either by turining this rule off, and hence you do it manually. Or turning this rule on, and let P3 handles it, by making the nearest workday as a holiday

  • Primavera Project Planner Ver. 3.1 Level 1

    6-6

    Click the Holidays button, the following dialogue box will appear:

    The holidays will be defined here will affect all individual calendars, for that reason, we call it Global Holidays

    In the table titled Nonworkperiods, specify the holidays. The following rules apply:

    If you have one day holiday, define it in the Start field If you have multiple uninterrupted holiday, define the Start field

    and the Finish field

    If this holiday occurs at the same period every year, make this holiday Repeating

    If you have an interrupted holiday, simply specify the whole holiday in the Nonworkperiods table, then specify the working days within the holiday in the Exceptions table

  • Module 6: Inputting Activity Calendar

    6-7

    Individual Calendar

    P3 has up to 31 individual calendars These calendars will be assigned to activities Individual calendar contains information which will affect only the

    activities attached to it

    Select an individual calendar, then click Standard button, the following dialogue box will appear:

    In this dialogue box you can do two things: Type in a title for the calendar (highly recommended) Set the working days per week

    All the things discussed in Holidays of the Global calendar applies on the individual calendars Contrary to Global Calendar holidays, the defined holidays in

    individual calendar will affect the activities attached to it only and not all activities

  • Primavera Project Planner Ver. 3.1 Level 1

    6-8

    How to create

    New Individual Calendar

    From menus select Data/Calendars, the following dialogue box will appear:

    Click Add button, the following dialogue box will appear:

    P3 will give it a new ID, which you can change it Type in the desired title, and click OK

  • Module 6: Inputting Activity Calendar

    6-9

    You can see that a new calendar is shown in the list Make sure it is selected, and click Standards, you will see the

    following dialogue box:

    As you can see from above, when you create a new individual calendar, all of the days will be considered workdays

    Click off the desired weekends, and click OK How to delete an existing calendar

    From menus select Data/Calendars Select the desired calendar

    Click Delete button, the following warning message will appear:

    If you are sure of what you are doing click Yes, if not click No to stop the precess of deletion

  • Primavera Project Planner Ver. 3.1 Level 1

    6-10

    Assigning Individual Calendar to an Activity

    Either double-click on the desired activity, or select the activity and press F7

    The Activity Form will appear:

    Right Click on Cal field, a list of the available individual calendars will be shown, select the desired calendar, and click OK

    Imposing a Finish Date on the Project

    In Global calendar at the Standard dialogue box, we saw that we can impose a finish date on the project

    Most likely this will be the contractual finish date of the project We need to input it in our project, so we can compare the calculated

    finish to the imposed finish

    It will replace the LF of the last activity:

    OD=4 EF=4

    LS=3 TF=2 LF=6

    ES=1

    Activity A

    OD=16 EF=24

    LS=7 TF=-2 LF=22

    ES=9

    Activity C

    OD=8 EF=8

    LS=-1 TF=-2 LF=6

    ES=1

    Activity B

  • Module 6: Inputting Activity Calendar

    6-11

    The difference between the Imposed finish date and Calculated

    finish date may be:

    Zero, if they are equal (rare cases) Negative, if the Calculated > Imposed (most likely) Positive, if the Calculated < Imposed (rare cases)

    As you can see in the above example, the TF of the critical path equals to -2, and that is because Calculated > Imposed

    The negative TF tells us how many days we need to compress our critical path to meet the contractual finish date of the project

    By default negative TF, LS, or LF is not acceptable We will accept it right now for the sake of completing the rest of

    data (like resources and costs), and after we are done, we can sit and try to find a solution to compress our critical path

    So dont try to find a definition, or explanation, of negative TF, LS, or LF

  • Primavera Project Planner Ver. 3.1 Level 1

    6-12

    Other ways to define Holidays

    The method mentioned above to define holidays is the most practical method, but there are other methods

    All of the methods applies to the Global holidays, and Individual holidays as well

    Double-Clicking Choose a single day, and double click it It will become hatched indicating it became a holiday If you are inside the Global calendar, you will see the letter G at the

    top left of the day:

    If you double-click it again, you will turn a holiday to a workday Using Nonwork

    button Select multiple days (consecutive by clicking and dragging, or non-

    consecutive by using Ctrl key and clicking)

    Click Nonwork button, the selected days will become holidays

  • Module 6: Inputting Activity Calendar

    6-13

    Also, if you double-click the heading of a day, just like below:

    Then you click Nonwork button, this day in the current month will become a holiday

    At any moment select a holiday, and click Work button, you will turn it into workday Printing Calendars

    Unfortunately, you cant preview calendars before printing them This command will print all your calendars You have two modes:

    Summary printout Detailed printout

    Summary printout

    It will produce a table contains: At the horizontal; list of the calendars At the vertical; list of days starting from the start of the project At the core of the table the holidays

  • Primavera Project Planner Ver. 3.1 Level 1

    6-14

    Example of Surramry printout:

    Detailed printout It will print a wall-like calendar, indicating the holidays in each month, starting from the start date of the project

  • Module 6: Inputting Activity Calendar

    6-15

    Example of Deatiled printout:

  • Primavera Project Planner Ver. 3.1 Level 1

    6-16

    From the Calendars dialogue box, click Print, the following dialogue box will appear:

    Select the desired Style, whether Summary, or Details Select the time Span, and click OK

    Transferring Activity Calendars

    You can transfer Activity Calendars between projects Go to the new project you want to transfer to From menus select Data/Calendars

    Click the Transfer button, the following dialogue box will appear:

  • Module 6: Inputting Activity Calendar

    6-17

    Transfer

    Individual calendar

    If you want to copy an individual calendar to another calendar within the same project

    Specify the source calendar and the target calendar, then click Transfer

    Transfer All calendars

    Click All calendars choice, the dialogue box will change to:

    Specify the Driver and Folder which the desired project you want to copy from resides in, then specify the project. Now click Transfer

    The calendars will be copied to your project

  • Primavera Project Planner Ver. 3.1 Level 1

    6-18

    Notes:

  • Module 6: Inputting Activity Calendar

    6-19

    Inputting Activity Calendars

    Workshop 7 1. Open SCIE project

    2. In Global calendar, define the following holidays:

    Start End Repeating 17JAN05 21FEB05 17MAR 7 15MAY05 30MAY05 04JUL 7 05SEP05 10OCT05 31OCT 7 02NOV05 11NOV 7 24NOV05 24DEC05 08JAN06 16JAN06 20FEB06 21MAY06 29MAY06 04SEP06 09OCT06 23NOV06

    3. Input the following Exceptions:

    Start End Repeating

    29DEC05 30DEC05

  • Primavera Project Planner Ver. 3.1 Level 1

    6-20

    4. From the Global calendar, impose a Finish date of 15AUG06

    5. Type in a new title for Calendar 1 Five Days Cal

    6. Define the following holidays only for Calendar 1:

    Start End Repeating

    08MAY06 14JUN 7 24OCT 7

    7. Create a new individual calendar, which will be assigned ID=2, and give

    it the following title Six Days Cal, and set the weekend to be only Sunday

    8. Assign Calendar 2 to all activates starting with CR (all the Classroom activities) (Hint: Select the first activity which is CR050, press F7, change the calendar, then click Next button on the Activity Form, if the activity starts with CR, change the calendar, if not click Next again, and so on)

    9. Run the Schedule command (without changing the DD) to see the effect of the changes you made, reading the report, answer the following questions:

    a. What is the Imposed Finish Date of the Project? (15AUG06)

    b. What is the Latest Calculated Early Finish of the Project? ____________ (25AUG06)

    10. Close the Scheduling report, without saving

    11. Select one of the critical activities, double-click on it, and check the value of TF? ___________ (-9)

  • Module 6: Inputting Activity Calendar

    6-21

    Module Review

    1. You can exchange Calendars between Projects in P3

    a. True

    b. False

    2. __________ cant be assigned to activities

    3. Imposed finish date will replace:

    a. ES of the first activity

    b. EF of the first activity

    c. LF of the first activity

    d. LF of the last activity

    4. I can preview the calendar printout before printing:

    a. True

    b. False

    5. Negative values of LS, LF, or TF are:

    a. Not acceptable, and should be solved before the end of the Planning phase

    b. Acceptable

    c. If you saw a negative TF, change the value to 0

    d. There is no way on earth the value of LS, LF, or TF will be negative

    6. I can set the Imposed finish date using Global Calendar, clicking the ____________ button

  • Primavera Project Planner Ver. 3.1 Level 1

    6-22

    Module Review Answers 1. a

    2. Global Calendar

    3. d

    4. b

    5. a

    6. Standard

  • 7-1

    Module 7:

    Resources and Cost Assignment This module contains: How to create Resource dictionary? How to create Cost Account dictionary? Assigning resources and cost to activity Viewing resources and cost profiles Producing tabular resources and cost reports

  • Using Primavera Project Planner Ver. 3.1

    7-2

  • Module 7: Resources and Cost Assignment

    7-3

    Introduction

    Resources and cost assignment goes into two main steps: Creating the Resource Dictionary, and Cost Account Dictionary

    (or transferring them from other projects)

    Assignment of resources Most likely you have to create the Resource Dictionary and Cost

    Account Dictionary once, and then you can transfer them from project to another

    For resources, the first step is to create a list of the resources available to complete any project taking into consideration the following:

    Resource name Resource unit of measure Resource description Resource availability (Normal and Maximum) Resource unit cost

    For cost accounts, create a hierarchy showing the relationship between the different cost accounts, taking into consideration the following:

    Cost account number Cost account description Cost Category

  • Using Primavera Project Planner Ver. 3.1

    7-4

    How to Create Resource Dictionary?

    As a first step prepare your work on a paper, listing all the resources available showing the following information:

    The Resource name (code for the resource up to 8 characters, spaces are allowed)

    Unit of measure (P3 doesnt have any predefined unit of measure), for instance you can type m, sq.m, cu.m, ton, mh (man-hour), md (man-day), etc, up to four characters

    Resource description (up to 40 characters) Resource limits, which states the number of units of this resource

    available for the current project in Normal times, and the maximum number of units, which can be provided. If this resource limits change with time record the date of change

    Resource Price/Unit, which states the cost of the unit. If this price/unit change with time record the date of change (P3 will not check for consistency, for instance you typed the unit of a certain resource is md, then you input the cost of mh)

    Once you are done with this list, now, go to the menus selecting Data/Resources, the following dialogue box will appear:

  • Module 7: Resources and Cost Assignment

    7-5

    It is preferable to do the inputting as follows:

    Input the resource name, the unit, and the description for all of the resources

    Then select the first resource, and specify the limits and price for it, now select the second one and so on

    To print the Resource Dictionary, cl


Recommended