+ All Categories
Home > Documents > Project Execution Planning for Building Information Modeling

Project Execution Planning for Building Information Modeling

Date post: 23-Feb-2016
Category:
Upload: candy
View: 28 times
Download: 0 times
Share this document with a friend
Description:
Project Execution Planning for Building Information Modeling. Meeting #8 – April 24 th , 2009. A buildingSMART Alliance project sponsored by: The Charles Pankow Foundation Construction Industry Institute (CII) Penn State Office of Physical Plant (OPP) PACE. Team Members. - PowerPoint PPT Presentation
Popular Tags:
29
Project Execution Planning for Building Information Modeling Meeting #8 – April 24 th , 2009 A buildingSMART Alliance project sponsored by: The Charles Pankow Foundation Construction Industry Institute (CII) Penn State Office of Physical Plant (OPP) PACE
Transcript
Page 1: Project Execution Planning for Building Information Modeling

Project Execution Planning for Building Information Modeling

Meeting #8 – April 24th, 2009

A buildingSMART Alliance project sponsored by:• The Charles Pankow Foundation• Construction Industry Institute (CII)• Penn State Office of Physical Plant (OPP)• PACE

Page 2: Project Execution Planning for Building Information Modeling

Team Members

•Board of Advisory• Deke Smith – Executive Director of buildingSMART Alliance (Industry Champion)• Victor Sanvido – Ph.D., Senior Vice President, Southland Industries• Francois Grobler – Ph.D., US Army CERL and IAI - North America• Steve Hagan – Project Knowledge Center, U.S. General Services Administration• Soad Kousheshi – President, AEC Strategy• Ed Gannon – Manager of Design Services, Penn State Office of Physical Plant• Mark Falzarano – Barton Malow Company• Mark Butler – HDR• Derek Cunz – Director of Project Development, Mortenson Construction• Mark Konchar- Vice President – Balfour Beatty Construction

• CIC Research Program Team Members• John Messner – Director of the CIC Research Program• Chimay Anumba – Professor and Head of Architectural Engineering• Sam Hunter – Assist. Professor of Psychology• Craig Dubler – PhD Student, Architectural Engineering (Construction)• Colleen Kasprzak – MS Student, Architectural Engineering (Operations)• Chitwan Saluja – MS Student, Architectural Engineering (Planning)• Nevena Zikic – MS Student, Architectural Engineering (Design)• Shane Goodman – BAE/MAE Student, Architectural Engineering

• Sponsor Representatives• Bob Tener – Director, The Charles Pankow Foundation • Steve Thomas – Director of Research, The Construction Industry Institute

Page 3: Project Execution Planning for Building Information Modeling

Conference Call Agenda

1. Introductions2. Project Goal and Objectives3. Execution Planning Process4. Discussion Chapters 1 and 25. Overview Chapters 3 and 4

Page 4: Project Execution Planning for Building Information Modeling

Problem Statement

Many owners and team members are struggling with how to effectively implement the BIM throughout the lifecycle of a building project.

Page 5: Project Execution Planning for Building Information Modeling

Project Goal

Develop a guide that will focus on the decisions required to increase the Building Information Modeling process efficiency throughout the stages of a building project: Planning Design Construction Operations

Page 6: Project Execution Planning for Building Information Modeling

Project Deliverables

BIM Execution Planning Guide Includes guidelines for BIM implementation at various project phases. Posted and distributed through the buildingSMART Alliance.

BIM Implementation Resources Spreadsheets, Word Templates, and Process Map Templates Assist Team Member to make decisions necessary for BIM Use

implementation

Page 7: Project Execution Planning for Building Information Modeling

Execution Planning Process

Page 8: Project Execution Planning for Building Information Modeling

Discussion - Chapters 1 and 2

Chapter 1 – Introduction BIM BIM Execution Planning BIM Execution Planning Process Meeting Approach

Chapter 2 – Identify BIM Uses BIM Uses Defined Selection Guidelines “Begin with End in Mind” Approach

Page 9: Project Execution Planning for Building Information Modeling

Chapter 3: Designing the BIM Execution Process

Level 1• BIM Uses

• A high level process map that outlines the various BIM uses in the different phases and information exchange that bind them.

Level 2• Template Process Map

• Template process maps will be mapped out for various BIM uses already identified for the different phases of the project. These can be used by project teams as a reference map.

Level 3• Project Specific Process Map

• The template process maps created in level 2 can then be taken to develop project specific process map, tailored to the project requirements.

Page 10: Project Execution Planning for Building Information Modeling

Level 1• BIM Uses

• A high level process map that outlines the various BIM uses in the different phases and information exchange that bind them.

Level 2• Template Process Map

• Template process maps will be mapped out for various BIM uses already identified for the different phases of the project. These can be used by project teams as a reference map.

Level 3• Project Specific Process Map

• The template process maps created in level 2 can then be taken to develop project specific process map, tailored to the project requirements.

Chapter 3: Designing the BIM Execution Process

Page 11: Project Execution Planning for Building Information Modeling
Page 12: Project Execution Planning for Building Information Modeling

Level 1• BIM Uses

• A high level process map that outlines the various BIM uses in the different phases and information exchange that bind them.

Level 2• Template Process Map

• Template process maps will be mapped out for various BIM uses already identified for the different phases of the project. These can be used by project teams as a reference map.

Level 3• Project Specific Process Map

• The template process maps created in level 2 can then be taken to develop project specific process map, tailored to the project requirements.

Chapter 3: Designing the BIM Execution Process

Page 13: Project Execution Planning for Building Information Modeling
Page 14: Project Execution Planning for Building Information Modeling

Template Process Map – 4D Model

Page 15: Project Execution Planning for Building Information Modeling
Page 16: Project Execution Planning for Building Information Modeling

Template Process Map – Design Coordination

Page 17: Project Execution Planning for Building Information Modeling

Level 1• BIM Uses

• A high level process map that outlines the various BIM uses in the different phases and information exchange that bind them.

Level 2• Template Process Map

• Template process maps will be mapped out for various BIM uses already identified for the different phases of the project. These can be used by project teams as a reference map.

Level 3• Project Specific Process Map

• The template process maps created in level 2 can then be taken to develop project specific process map, tailored to the project requirements.

Chapter 3: Designing the BIM Execution Process

Page 18: Project Execution Planning for Building Information Modeling
Page 19: Project Execution Planning for Building Information Modeling

Project Specific Process Map – Design Coordination (Millennium Science Project)

Page 20: Project Execution Planning for Building Information Modeling

Chapter 4: Creating the BIM Execution Plan

1. Project Goals/BIM Objectives2. BIM Process Design3. Delivery Strategy/Contract4. BIM Scope Definitions5. Organizational Roles and Responsibilities6. Communication Procedures7. Technology Infrastructure Needs8. Model Set-up, Organization and Quality Control9. Project Reference Information

Page 21: Project Execution Planning for Building Information Modeling

Chapter 4: Creating the BIM Execution Plan

Page 22: Project Execution Planning for Building Information Modeling

Chapter 4: Creating the BIM Execution Plan

1. Project Goals/BIM Objectives• References to Chapter 2 – Identify BIM Uses

2. BIM Process Design• References to Chapter 3 – Defining the BIM Execution

Process

3. Delivery Strategy/Contracta) Definition of the Delivery Structure• References to AIA IPD and DB contracts

b) BIM Contractual Requirements• Notes 5 important issues to address in BIM contracts• References to multiples AIA and ConsensusDOCS

BIM contract attachments

Page 23: Project Execution Planning for Building Information Modeling

Chapter 4: Creating the BIM Execution Plan

4. BIM Scope definitionsa) References to AIA E202, USACE BIM Roadmap and

Omniclass Construction Classification Systemb) Building upon AIA E202 to provide a more comprehensive

document with guide• Added to CSI Uniformat• BIM Deliverables instead of Project Phase• LOD (100-500) or project specific language• Grouping description of model components added• MEA removed from document

Page 24: Project Execution Planning for Building Information Modeling

Chapter 4: Creating the BIM Execution Plan

Page 25: Project Execution Planning for Building Information Modeling

Chapter 4: Creating the BIM Execution Plan

Page 26: Project Execution Planning for Building Information Modeling

Chapter 4: Creating the BIM Execution Plan

5. Organizational Roles and Responsibilitiesa) BIM Team composition and responsibilitiesb) BIM Manager selection and responsibilities

6. Communication Proceduresa) Electronic communicationb) Meeting communication

7. Technology Infrastructure Needsa) General overview of software typesb) Specific software and hardware not defined

Page 27: Project Execution Planning for Building Information Modeling

Chapter 4: Creating the BIM Execution Plan

8. Model Set-up, Organization and Quality Controla) Important model set-up, organization and quality control

topicsb) IFC filesc) Types of quality checks

9. Project Reference Informationd) Critical Project Overview Informatione) Key Project Contacts

Page 28: Project Execution Planning for Building Information Modeling

Discussion

Ways that you can help us:• Review Chapters 1 and 2:• Email: [email protected]• Fax: 814-863-4789

• Projects to test drive BIM Execution Plan Process

Page 29: Project Execution Planning for Building Information Modeling

Thank You

Next Meeting Time –


Recommended