Rajiv Misra
PROJECT MANAGEMENT
BIPARD, Patna25th January 2012
Rajiv Misra
CAN A SUCCESSFUL PROJECT MANAGER SUCCEED EVERYWHERE?
Rajiv Misra
WHAT WERE THE DIFFERENT TASKS WE DID?
Rajiv Misra
WHAT WERE THE DIFFERENT TASKS WE DID?
PLANNING STAGE
Rajiv Misra
PRODUCT MIX?
Rajiv Misra
PRODUCT MIX?
Type A, B, C or D?Selecting Dam SiteProject Portfolio Management
Rajiv Misra
ESTIMATION?
Rajiv Misra
ESTIMATION?
No of sheets needed? Nesting etc etcTime Needed?
Benchmark: Internal or External
Rajiv Misra
PROTOTYPING ?
Rajiv Misra
PROTOTYPING ?ACTIVITY AND RESOURCE
To identify the activities and resources (Technological)?Will one scissor be enough (Resource Leveling)?
Generates ideas (Template)Drawing on the paper before (not on each shape)
Rajiv Misra
DECIDING THE ORGANIZATION STRUCTURE
Rajiv Misra
DECIDING THE ORGANIZATION STRUCTURE
Who will do what when?Is the required traits of leader same at all stages?
Rajiv Misra
PROCUREMENT?
Rajiv Misra
PROCUREMENT?
Hiring EquipmentRaw MaterialCONTRACTS
Rajiv Misra
RISK MANAGEMENT
Do not work on the new sheet
WIP will build up
Rajiv Misra
ACTION PLANS FOR ADDRESSING RISKS
Risk Event Impact Total Loss (L)
Prob ofImpact
(PI)
ImpactDrivers
Prob of Risk (PR)
Risk Event
Drivers
Prevention Plans Contingency Plans
Rajiv Misra
ONE SUCH RISK
Heart Attack DeathTotal Loss (L)
25L*10 yrs = 250L
Prob ofImpact
(0.3)
No ambulance
Prob of Risk(0.7)
Stressful jobBeer…..
Prevention Plans Contingency Plans
Retirement: 60CTC: 25L yearly
Rajiv Misra
HOW TO TRACK AND MONITOR?
Rajiv Misra
HOW TO TRACK AND MONITOR?
Intuitively --- ARROWS / CRITICAL PATHNot observed by meTime is coming to an endSome aspects of Risk mitigation (WIP is building etc or ARROWS not complete)
Could result in elaborate FormsProject Forms/ Software Plan (Word Docs)
Rajiv Misra
WHAT WERE THE DIFFERENT TASKS WE DID?
EXECUTION STAGE
Rajiv Misra
PERFORMANCE MONITORING
Rajiv Misra
PERFORMANCE MONITORING
We need to hasten up
Punctuated equilibrium model
Milestones
Rajiv Misra
LEARNING
From own experienceFrom other groups
Rajiv Misra
WHAT WERE THE DIFFERENT TASKS WE DID?
CLOSING STAGE
Rajiv Misra
CALCULATION
Profit or loss?
Rajiv Misra
HANDOVER
As built drawings, workmen statutory clearances, site closingGet back all Bank and Performance GuaranteesScrap Reconciliation
Rajiv Misra
PROJECT MANAGEMENT PROCESSES
Rajiv Misra
PROJECT MANAGEMENT PROCESSES
Gray and Larson: Your book
Rajiv Misra
PROJECT MANAGEMENT PROCESSES
PMBOK
Rajiv Misra
WHY WAS THE QUALITY OF DRAWING NOT SO GOOD?
Rajiv Misra
PROJECT MANAGEMENT
Rajiv Misra
PROJECT MANAGEMENT TRADEOFF
Project Management balances this:
TRADE OFF TRIANGLE
Rajiv Misra
NEED FOR A SEPARATE TECHNIQUE
Rajiv Misra
PROJECT MANAGEMENT
Why is a separate technique for Project Industries needed ?
Daily Passenger versus once in a while traveler – Rly Time Table
Answers to these basic Questions must be provided by any technique
What is to be done?When is it to be done?Are we on schedule?If not, how late and when can we complete
Rajiv Misra
WHAT IS A PROJECT: DEFINITION
Rajiv Misra
PROJECT MANAGEMENT : DEFINED
5.0 DEFINITION OF A PROJECT
“A temporary endeavor to create an unique Product/Service”
(PMBOK www.pmi.org)Evolving Product, Starts & Finish, Transient Teams
Rajiv Misra
PROJECT MANAGEMENT : EXAMPLES
Rajiv Misra
PROJECT MANAGEMENT : EXAMPLES
Trojan Reactor Vessel
Removing a full size Reactor without dismantlingPublic safety concernsNever done beforeSaved 19 million dollars
PMI 2000 International Project of the year
Rajiv Misra
PROJECT MANAGEMENT : EXAMPLES
Mars Pathfinder Mission
Space craft to Mars - landed July 4, 19973 years , 150 million dollarsMotto “Better, Faster, Cheaper”Earlier Viking missions took 6 yearsExtensive Requirement TrackingLessons from past projects and lessons for futureWhat went Right/ What went Wrong (www)
PMI 1998 International Project of the year
Rajiv Misra
NAPOLEON’S PLANS FOR RUSSIA
Rajiv Misra
PROJECT MANAGEMENT : EXAMPLES
PYRAMIDS
Pyramid at Cheops3 BC2,30,000 Stone Blocks weighing 2- 70 tons a pcHeight of a 40 storey buildingBase is 13 acres1,50,00 workmen and their families20 year Project
Rajiv Misra
PROJECT MANAGEMENT : EXAMPLES
LAUNCH OF MICROSOFT PROJECT 2003
Visual Freeze
Rajiv Misra
PROJECT MANAGEMENT : EXAMPLES
RENOVATING THE STATUTE OF LIBERTY
198350 Companies30 month ProjectCrown Windows replacedAncient copper molding technique used for Torch
Rajiv Misra
PROJECT MANAGEMENT : EXAMPLES
OLYMPICS
Rajiv Misra
PROJECT MANAGEMENT : EXAMPLES
PULSE POLIO PROGRAM
Rajiv Misra
PROJECT MANAGEMENT : EXAMPLES
MANUFACTURE OF LUX SOAP
Rajiv Misra
PROJECT MANAGEMENT : EXAMPLES
CRM at Jamshedpur
Rajiv Misra
PROJECT MANAGEMENT : EXAMPLES
REVAMP OF PRODUCT (INDICA – TATA CAR)
Rajiv Misra
PROJECT MANAGEMENT : EXAMPLES
IMPLEMENT ERP
Rajiv Misra
PROJECT MANAGEMENT : EXAMPLES
PRODUCING HR COILS
Rajiv Misra
PROJECT MANAGEMENT : EXAMPLES
RESCUE MISSION AFTER 9/11
Rajiv Misra
PROJECT MANAGEMENT IN INDIA
INDIA’S PROJECT SUCCESSES
ASIADKONKAN RAILWAYSHIGHWAY PROJECTS/ DELHI METRO
INDIAN PROJECT DISASTERSSECTOR COST O/RUN TIME O/RUN
COAL 752% 192%
STEEL 231% 345%
RAILWAYS 470% 121%
POWER 921% 196%
Rajiv Misra
PROJECT MANAGEMENT IN INDIA
Study covered 500 Central Government Projects over 200 crores value each
10% completed within time and cost20% of the projects had cost overruns of 100% Cost overruns of 200-500% not uncommon
Source: www.cidcindia.net
Construction India Development Council’s 2003-04 Study
Rajiv Misra
PROJECT MANAGEMENT IN INDIA
REASONS FOR OVERRUNS
FUNDINGCOMPLICATED PROJECT CLEARANCENO STANDARD PROJECT MGT TECHNIQUE USED
PROJECT MANAGEMENT IN INDIA
LIMITING FACTORS EMERGING CHANGESVARIABILITY NTPC/NHAI INFLUENCE ON USE OF PM
LITTLE GOVT. SUPPORT AVAILABILITY OF DESKTOP S/WLACK OF NATION LEVEL STATISTICS INFLUENCE OF MULTINATIONAL (EPC)CORRUPTION EDUCATION.WHY THE ‘EXTRA MILE’ – CLAIMS LEGAL CHANGES
Rajiv Misra
NETWORK METHODS
Rajiv Misra
NETWORK METHODS
Rajiv Misra
NETWORK METHODS
Time
Activities
HISTORICAL DEVELOPMENT
GANTT CHARTOne Month Delay
1st Jan
Rajiv Misra
NETWORK METHODS
Time
Activities
HISTORICAL DEVELOPMENT
GANTT CHART
WEAKNESSES IN GANTTINTERDEPENDENCIES NOT MODELED
Rajiv Misra
NETWORK METHODS
WHAT ARE THEY
PERTCPM
Rajiv Misra
NETWORK METHODS
NEED: COST AND TIME OVERRUNS – Defense Industry
EFFORTS IN RESEARCH
(1) UK: Central Electricity Board “Master Sequence”
(2) USA-1 : Polaris MissileR and D ProjectLockheed, Navy, and Booz AllenRelied on Probability TheoryResulted in PERT
(3) USA-2 :Maintenance and Construction ProjectsDuPont an RandTime and Cost Trade OffDeterministic TimesResulted in CPM
Rajiv Misra
Programme Evaluation & Review Technique (PERT)
US Navy/ Polaris Missile Project 1958
• U.S Navy, concerned with the control of contracts for its Polaris Missile project.
• 500 main contractors; 3000 sub-contractors
• Contracts consisted of research, development work and manufacturing of parts that were unique and had never been previously undertaken.
PERT
Rajiv Misra
CPM
Rajiv Misra
DRAWING NETWORKS
PROJECT: PREPERATION OF A BUDGET
ACTIVITY ID DEPT TIME PREDECESSOR
Forecast Sales a Sales 14 -
Price Sales b Sales 3 a
Prepare Prodn. Schedule
c Prodn 7 a
Cost Production d Accounts 4 c
Prepare Budget e Treasurer 10 b,d
Rajiv Misra
DRAWING NETWORKS
PROJECT: PREPERATION OF A BUDGET
ACTIVITY ID DEPT TIME PREDECESSOR
Forecast Sales a Sales 14 -
Price Sales b Sales 3 a
Prepare Prodn. Schedule
c Prodn 7 a
Cost Production d Accounts 4 c
Prepare Budget e Treasurer 10 b,d
1 2a (14)
Rajiv Misra
DRAWING NETWORKS
PROJECT: PREPERATION OF A BUDGET
ACTIVITY ID DEPT TIME PREDECESSOR
Forecast Sales a Sales 14 -
Price Sales b Sales 3 a
Prepare Prodn. Schedule
c Prodn 7 a
Cost Production d Accounts 4 c
Prepare Budget e Treasurer 10 b,d
1 2a (14) b (3)
c (7)
Rajiv Misra
DRAWING NETWORKS
PROJECT: PREPERATION OF A BUDGET
ACTIVITY ID DEPT TIME PREDECESSOR
Forecast Sales a Sales 14 -
Price Sales b Sales 3 a
Prepare Prodn. Schedule
c Prodn 7 a
Cost Production d Accounts 4 c
Prepare Budget e Treasurer 10 b,d
1 23
4
5a (14) b (3)
c (7)
d (4)
e (10) PATHS1-2-3-5 = 271-2-4-3-5 = 35 (CRITICAL)
Rajiv Misra
NETWORKS TERMS
Rajiv Misra
NETWORKS TERMS
FLOAT:
Buy Motor
Make Support
Erection
Testing
Day0 10
12
28
31 Finish
30
Let’s Review on11 12 13 14
Free FloatFloatDelayed
12
28
0
31
Rajiv Misra
NETWORK CLASSIFICATION
Rajiv Misra
NETWORK CLASSIFICATION
1. ACTIVITY ON ARROW (AOA)
2. ACTIVITY ON NODE (AON)
a
c
b
S a
b
c
F
3. PRECEDENCE DIAGRAMMING (PDM)
FS, FF, SS, SF BETWEEN PAIR OF ACTIVITIES
Rajiv Misra
NETWORK CLASSIFICATION
Activity Predecessor
A -
B -
C -
D A,B
E B,C
S B
A
C
F
D
E
Activity on Node (AON)
Rajiv Misra
NETWORK CLASSIFICATION
Activity Predecessor
A -
B -
C -
D A,B
E B,C
Activity on Arrow (AOA)
SF
A
B
C
D
E
DUMMY