PSB Injection Overview + Specification changes ABT LIU Project Review 2015 20-11-2015 Wim Weterings.

Date post: 19-Jan-2018
Category:
Upload: maud-atkins
View: 217 times
Download: 0 times
Share this document with a friend
Description:
ABT components and related elements (Small reminder) Vertical Septum BI.SMV Beam slices are further deflected by BI.SMV septa into the BI.BVT vertical dipole to achieve the required booster beam level separation of 360mm between each ring. Proton Distributor BI.DIS System of pulsed magnets, which kick slices of the 160 MeV H - beam from LINAC4 to different vertical positions at the vertical septum BI.SMV. H - Charge-Exchange System The beam is injected through a graphite stripping foil BI.STR to convert ~98% of the beam to H +, using 4 magnets BI.BSW creating the injection bump and a 4 horizontal kickers KSW, outside the injection region, producing the painting bump. PSB Injection Region Related Control systems for all Equipment
14
Transcript
Page 1: PSB Injection Overview + Specification changes ABT LIU Project Review 2015 20-11-2015 Wim Weterings.
Page 2: PSB Injection Overview + Specification changes ABT LIU Project Review 2015 20-11-2015 Wim Weterings.

PSB Injection Overview + Specification changesABT LIU Project Review 2015

20-11-2015

Wim Weterings

Page 3: PSB Injection Overview + Specification changes ABT LIU Project Review 2015 20-11-2015 Wim Weterings.

ABT components and related elements(Small reminder)

Vertical Septum BI.SMVBeam slices are further

deflected by BI.SMV septa into the BI.BVT vertical dipole

to achieve the required booster beam level

separation of 360mm between each ring.

Proton Distributor BI.DISSystem of pulsed magnets, which kick slices of the 160 MeV H- beam from LINAC4

to different vertical positions at the vertical

septum BI.SMV.

H- Charge-Exchange SystemThe beam is injected through a graphite stripping foil BI.STR to convert ~98% of the beam to H+,

using 4 magnets BI.BSW creating the injection bump and a 4 horizontal kickers KSW, outside

the injection region, producing the painting bump.

PSB Injection Region

Related Control systems for all Equipment

Page 4: PSB Injection Overview + Specification changes ABT LIU Project Review 2015 20-11-2015 Wim Weterings.

ABT components and related elements(Small reminder)

Vertical Septum BI.SMVBeam slices are further

deflected by BI.SMV septa into the BI.BVT vertical dipole

to achieve the required booster beam level

separation of 360mm between each ring.

Proton Distributor BI.DISSystem of pulsed magnets, which kick slices of the 160 MeV H- beam from LINAC4

to different vertical positions at the vertical

septum BI.SMV.

H- Charge-Exchange SystemThe beam is injected through a graphite stripping foil BI.STR to convert ~98% of the beam to H+,

using 4 magnets BI.BSW creating the injection bump and a 4 horizontal kickers KSW, outside

the injection region, producing the painting bump.

PSB Injection Region

Related Control systems for all Equipment

Luc ThierryRemy

CedricLuis

Roger & Gregor

Chiara: Beam dynamics

Page 5: PSB Injection Overview + Specification changes ABT LIU Project Review 2015 20-11-2015 Wim Weterings.

BI line and Injection region

KSW

BI Line

Injection Region

Page 6: PSB Injection Overview + Specification changes ABT LIU Project Review 2015 20-11-2015 Wim Weterings.

New Injection Region design For each ring:• 4 BSW chicane magnets• Undulated Inconel

vacuum chambers• 4 Ion pumps• BTV with Camera• Stripping foil unit• Vacuum sectorisation• Beam loss monitors• Internal H0H- dump

Page 7: PSB Injection Overview + Specification changes ABT LIU Project Review 2015 20-11-2015 Wim Weterings.

Planning

Wim Weterings, LIU 2013, April 12, 2013

LIU-PSB timeline for H- injection agreed by the

LIU project.77th IEFC meeting

INDICO event 212744

Stripping foil Test Stand installation Q1 2015

Half Sector Test

Stripping foil Test Stand installation Q1 2016

Page 8: PSB Injection Overview + Specification changes ABT LIU Project Review 2015 20-11-2015 Wim Weterings.

Building 355Mock-up assembly

Page 9: PSB Injection Overview + Specification changes ABT LIU Project Review 2015 20-11-2015 Wim Weterings.

Foil lab space near the PSB

Ghislain Roy has found lab space in building 37 that BE can loan to TE/ABT for a few years (up to LS2).

Office 37/R-023

Page 10: PSB Injection Overview + Specification changes ABT LIU Project Review 2015 20-11-2015 Wim Weterings.

List of all LIU-PSB specificationsList of all LIU-PSB specifications, make sure available and in EDMS Tony

INDICO 357135, ABT LIU project review follow up 10-12-2014

Page 11: PSB Injection Overview + Specification changes ABT LIU Project Review 2015 20-11-2015 Wim Weterings.

Updated list of all LIU-PSB specifications

NewNew

NewNew

New

New

TDR

TDR

TDR

TDR

TDR

Nearly completed PSB-MSMIB-EC-0001

Page 12: PSB Injection Overview + Specification changes ABT LIU Project Review 2015 20-11-2015 Wim Weterings.
Page 13: PSB Injection Overview + Specification changes ABT LIU Project Review 2015 20-11-2015 Wim Weterings.

TotalSchedule Variance

Planned Value

Earned Value

Actual Cost

Total Planned Value

65730 LIU-PSB - injection distributor (BI.DIS) 0 562000 562000 437743 562000

65731 LIU-PSB injection septum (BI.SMV) -157290 1197390 1040100 1143310 1264000

65732 LIU-PSB H- injection stripping foil unit -227905 328546 100641 263273 468000

65733 LIU-PSB Injection Zone Support Structure -85586 161699 76113 105510 242000

65734 LIU-PSB - injection distributor pulse generator (BI.DIS) -371995 1593290 1221295 910653 2255000

65735 LIU-PSB injection bumpers (BI.BS) -863873 1263147 399274 448356 2127000

65736 LIU-PSB - PSB injection painting bumpers (BI.KSW) -30449 331182 300732 334428 346000

65737 LIU-PSB injection kicker electronics & controls -93038 161038 68000 30548 414000

65738 LIU-PSB injection septa electronics & controls -20724 28724 8000 4571 125000

65739 LIU-PSB - injection stripping foil & absorber blocks E+C -46938 134938 88000 39585 266000

65740 LIU-PSB injection paint bump (BI.KSW) electr. & contr. -31093 137093 106000 88661 601000

LIU-PSB 9.2 Total -1928892 5899048 3970156 3812175 8670000

Nov-15

Page 14: PSB Injection Overview + Specification changes ABT LIU Project Review 2015 20-11-2015 Wim Weterings.

THANK YOU FOR YOUR ATTENTION!