+ All Categories
Home > Documents > Research Article Dynamic Modeling of Steam Condenser and...

Research Article Dynamic Modeling of Steam Condenser and...

Date post: 10-Jul-2020
Category:
Upload: others
View: 5 times
Download: 0 times
Share this document with a friend
10
Research Article Dynamic Modeling of Steam Condenser and Design of PI Controller Based on Grey Wolf Optimizer Shu-Xia Li 1 and Jie-Sheng Wang 1,2 1 School of Electronic and Information Engineering, University of Science & Technology Liaoning, Anshan 114044, China 2 National Financial Security and System Equipment Engineering Research Center, University of Science & Technology Liaoning, Anshan 114044, China Correspondence should be addressed to Jie-Sheng Wang; wang [email protected] Received 15 September 2015; Revised 16 November 2015; Accepted 18 November 2015 Academic Editor: Salvatore Alfonzetti Copyright © 2015 S.-X. Li and J.-S. Wang. is is an open access article distributed under the Creative Commons Attribution License, which permits unrestricted use, distribution, and reproduction in any medium, provided the original work is properly cited. Shell-and-tube condenser is a heat exchanger for cooling steam with high temperature and pressure, which is one of the main kinds of heat exchange equipment in thermal, nuclear, and marine power plant. Based on the lumped parameter modeling method, the dynamic mathematical model of the simplified steam condenser is established. en, the pressure PI control system of steam condenser based on the Matlab/Simulink simulation platform is designed. In order to obtain better performance, a new metaheuristic intelligent algorithm, grey wolf optimizer (GWO), is used to realize the fine-tuning of PI controller parameters. On the other hand, the Z-N engineering tuning method, genetic algorithm, and particle swarm algorithm are adopted for tuning PI controller parameters and compared with GWO algorithm. Simulation results show that GWO algorithm has better control performance than other four algorithms. 1. Introduction e condenser is one of the important kinds of equipment in thermal power plant, nuclear power plants, and marine power plant. e reliability of condenser running directly affects the safety and economic operation of the entire power plant or power system [1]. A steam condenser is a piece of machinery that turns steam into water. Many steam-based systems use a circuit of water to maximize their efficiency. Water is heated into steam, the steam provides motivation for a process, a steam condenser turns it back into water, and the cycle begins again [2]. e failure of the condenser may cause the boiler or steam turbine unit to overheat, which endangers the safety of the whole generating unit or power plant. e power plant has strict requirements on the reliability and the tightness of the condenser. In addition to safety considerations, the condensation process of steam in the condenser is an important part of the system thermodynamic cycle, which greatly affects the economic performance of the system. erefore, through the computer simulation experi- ments, the establishment of the dynamic model and under- standing the dynamic characteristics of the condenser have a great significance on improving the safety and economic operation level of the steam condenser [3]. A hybrid modeling approach is proposed to describe the dynamic behavior of the two-phase flow condensers used in air-conditioning and refrigeration systems based on fundamental energy and mass balance governing equations and thermodynamic principles. e model validation studies on an experimental system show that the model predicts the system dynamic well [4]. A method to improve the load change capacity is proposed for the water cooled power plants through controlling the cooling water flow. en, the CCWCS (condenser cooling water control system) is put forward to execute this method on the premise of unit safety [5]. A robust strategy for online fault detection and optimal control of condenser cooling water systems is proposed. e optimal control strategy is for- mulated using a model-based approach, in which simplified models and a hybrid quick search (HQS) method are used to Hindawi Publishing Corporation Mathematical Problems in Engineering Volume 2015, Article ID 120975, 9 pages http://dx.doi.org/10.1155/2015/120975
Transcript
Page 1: Research Article Dynamic Modeling of Steam Condenser and ...downloads.hindawi.com/journals/mpe/2015/120975.pdf · Shell-and-tube condenser is a heat exchanger for cooling steam with

Research ArticleDynamic Modeling of Steam Condenser and Design ofPI Controller Based on Grey Wolf Optimizer

Shu-Xia Li1 and Jie-Sheng Wang12

1School of Electronic and Information Engineering University of Science amp Technology Liaoning Anshan 114044 China2National Financial Security and System Equipment Engineering Research Center University of Science amp Technology LiaoningAnshan 114044 China

Correspondence should be addressed to Jie-Sheng Wang wang jiesheng126com

Received 15 September 2015 Revised 16 November 2015 Accepted 18 November 2015

Academic Editor Salvatore Alfonzetti

Copyright copy 2015 S-X Li and J-S Wang This is an open access article distributed under the Creative Commons AttributionLicense which permits unrestricted use distribution and reproduction in any medium provided the original work is properlycited

Shell-and-tube condenser is a heat exchanger for cooling steam with high temperature and pressure which is one of the mainkinds of heat exchange equipment in thermal nuclear and marine power plant Based on the lumped parameter modelingmethod the dynamic mathematical model of the simplified steam condenser is established Then the pressure PI control systemof steam condenser based on the MatlabSimulink simulation platform is designed In order to obtain better performance a newmetaheuristic intelligent algorithm grey wolf optimizer (GWO) is used to realize the fine-tuning of PI controller parametersOn the other hand the Z-N engineering tuning method genetic algorithm and particle swarm algorithm are adopted for tuningPI controller parameters and compared with GWO algorithm Simulation results show that GWO algorithm has better controlperformance than other four algorithms

1 Introduction

The condenser is one of the important kinds of equipmentin thermal power plant nuclear power plants and marinepower plant The reliability of condenser running directlyaffects the safety and economic operation of the entire powerplant or power system [1] A steam condenser is a piece ofmachinery that turns steam into water Many steam-basedsystems use a circuit of water to maximize their efficiencyWater is heated into steam the steam provides motivation fora process a steam condenser turns it back into water and thecycle begins again [2]The failure of the condenser may causethe boiler or steam turbine unit to overheat which endangersthe safety of the whole generating unit or power plantThe power plant has strict requirements on the reliabilityand the tightness of the condenser In addition to safetyconsiderations the condensation process of steam in thecondenser is an important part of the system thermodynamiccycle which greatly affects the economic performance of thesystem

Therefore through the computer simulation experi-ments the establishment of the dynamic model and under-standing the dynamic characteristics of the condenser havea great significance on improving the safety and economicoperation level of the steamcondenser [3] Ahybridmodelingapproach is proposed to describe the dynamic behavior ofthe two-phase flow condensers used in air-conditioning andrefrigeration systems based on fundamental energy andmassbalance governing equations and thermodynamic principlesThe model validation studies on an experimental systemshow that the model predicts the system dynamic well [4]A method to improve the load change capacity is proposedfor the water cooled power plants through controlling thecooling water flow Then the CCWCS (condenser coolingwater control system) is put forward to execute this methodon the premise of unit safety [5] A robust strategy for onlinefault detection and optimal control of condenser coolingwater systems is proposedThe optimal control strategy is for-mulated using a model-based approach in which simplifiedmodels and a hybrid quick search (HQS) method are used to

Hindawi Publishing CorporationMathematical Problems in EngineeringVolume 2015 Article ID 120975 9 pageshttpdxdoiorg1011552015120975

2 Mathematical Problems in Engineering

optimize the performance of the overall system by changingthe settings of the local process controllers [6] In the fieldof computer simulation the simulation technology is usedto simulate the operation of the condenser system and studyits working performanceThe optimization of the parametersof PID controller can not only satisfy the static accuracy butalso make the system have better stabilization The accuratemathematical model can accurately and comprehensivelyrepresent all working conditions in the real running processof steam condenser system (normal conditions fault condi-tions and transient conditions) andmake them reappear Onthe same time it can be used to carry through the researchon the dynamical characteristic to meet the requirements ofdifferent engineering projects

At present people by simulating biotic population andtheir evolution process in nature have developed a variety ofintelligence algorithms particle swarm optimization (PSO)algorithm ant colony optimization (ACO) algorithm artifi-cial bee colony (ABC) algorithm shuffled frog leaping (SFL)algorithm cuckoo search (CS) algorithm Dolphin partneroptimization (DPO) and Firefly algorithm (FA)

GA is the most typical algorithm of evolutionary branchThis algorithm simulates Darwinian evolution concepts [7]Each new population is created by the combination andmutation of the individuals in the previous generationParticle swarm optimization (PSO) was inspired from thesocial behavior of birds flocking [8] The PSO algorithmemploys multiple particles that chase the position of the bestparticle and their own best positions obtained so far Artificialbee colony (ABC) algorithm mimics the collective behaviorof bees in finding food sources [9] There are three typesof bees in ABC scout onlooker and employed bees Thescout bees are responsible for exploring the search spacewhereas onlooker and employed bees exploit the promisingsolutions found by scout bees Ant colony optimization(ACO) algorithm was inspired by the social behavior of antsin an ant colony In fact the social intelligence of ants infinding the shortest path between the nest and a source offood is themain inspiration of ACO [10] Cuckoo search (CS)algorithm was put forward by Yang and Deb in 2009 [11]This algorithm is mainly based on two aspects the cuckoorsquosparasitic reproduction mechanism and Levy flights searchprinciple Assume each cuckoo only lays one egg at a timeand randomly chooses birdrsquos nest to hatch the egg

The grey wolf optimizer (GWO) as a new swarm intel-ligent algorithm is put forward by Seyedali Mirjalili and soforth in 2014 whichmainlymimics wolf leadership hierarchyand huntingmechanism in nature Seyedali andMirjalili andso forth have proved that the search performance of basicwolf algorithm is superior to that of PSO GSA DE and FEPalgorithm Due to the wolvesrsquo algorithm with the advantagesof being simple in principle having fast seeking speed andhigh search precision and being easy to realize it is moreeasily combined with the practical engineering problems

Many kinds of swarm intelligence are inspired by hunt-ing and search behaviors of a population However GWOalgorithm simulates internal leadership hierarchy of wolvesthus in the searching process the position of best solutioncan be comprehensively assessed by three solutions So the

Cooling water inlet Steam inlet

Cooling Condensatewater outlet water outlet

Figure 1 Structure diagram of shell-and-tube condenser

GWO algorithm is able to greatly reduce the probabilityof producing premature phenomenon and falling into localoptimum

Aiming at the steam condenser pressure control problembased on the MatlabSimulink simulation platform and theestablished mathematical model a closed-loop condenserpressure control system is designed The GWO algorithm isadopted to optimize the parameters of the PI controller Sim-ulation results show the effectiveness of the proposed controlstrategy The paper is organized as follows In Section 2 thetechnique and dynamicmodeling of the shell-and-tube steamcondenser are introduced The GWO algorithm is illustratedin Section 3 The parameter optimization of PI controllerbased on GWO algorithm is described and the simulationexperiments and results analysis are introduced in detail inSection 4 Finally the conclusion illustrates the last part

2 Dynamic Modeling of Steam Condenser

21 Structure Characteristics and Working Principle of SteamCondenser The shell of shell-and-tube type condenser isusually cylindrical or elliptical as shown in Figure 1 which isconnected with end closures for constituting the water cham-bers Between the end closures and the shells a perforatedtube plate is fixed in which a lot of cooling water pipes arearranged hierarchicallyThe entrance pipe of steam is locatedin the upper part of the condenser shell which is directly orindirectly connected with the exhaust equipment through thecompensator In the lower part of the shell there is a gatheringtank (or a hot well water tank) of the condensed waterThe airoutlet port is positioned at the lower part of shell and the airis drawn through this nozzle

Theworking principle of the steam condenser is shown inFigure 2

Steam goes into steam field of the condenser throughsteam admission pipe Steamgets in touchwith the condensertube wall to begin the radiate condensation at the same timethe latent heat is transferred to the cooling water through thesurface of the cooling water pipe Cooling water with inlettemperature is fed into water chamber through the coolingwater pipe where the cooling water is assigned to all pipesof the first procedure in the lower part of the condensershell The cooling water flows into another water chamberalong the first six cooling water pipes and then enters thenext flow pipes and carries through heat exchange withthe steam Through such several procedures in return the

Mathematical Problems in Engineering 3

Steam inlet

Cooling Cooling

Condensate water outlet

Gc Tc1 Gc Tc2

Gh2 Th2

Gh1 Th1

water inlet water outlet

Figure 2 Schematic diagram of condenser

cooling water with the outlet temperature is discharged fromthe outlet pipes Due to the lack of system sealing propertythe air is drawn out from the condenser constantly to ensurethe requirements of the systemrsquos vacuum degree The drawngas contains the air and steam In the beginning of thecondensation the air volume is very smaller than the totalamount of steam With the steam and air flowing toward theexhaust port steam is continuously condensed down Thenthe steam quality in the mixture gradually decreases On thecontrary the relative content of the air increases graduallyUntil the relative content of air fed into the cooling zone airhas reached a great numerical extent the steam condensationprocess terminates

22 Mathematical Model

221 Mathematical Model of Shell Side of Condenser

(1) Steam Zone

(i) Steam mass equation is as follows

119889119866119904

119889119905= 119866st + 119866ost minus 119866119888 minus 119866ss (1)

where 119866119904is the steam content in the shell side of the

condenser (kgs) 119866st is the exhaust volume of steam turbine(kgs)119866ost is the other steam inlet of the condenser (kgs)119866

119888

is the main steam condensate (kgs) and119866ss is the amount ofsteam drawn out by vacuum pumping equipment (kgs)119866ss and 119866119888 are calculated by the following equations

119866ss = 119866ao (1 minus 119877)

119877 =119872119886

119872119904+119872119886

=119875119886119877119904

119875119904119877119886+ 119875119886119877119904

119876119888= 119866119888(119867119904minus 119867cw)

119866119888=

119880119860Δ119905119898

(119867119888minus 119867cw)

(2)

where 119866ao is the quality of the gas mixture pumped by thepumping unit (kgs) 119877 is the share air ratio in the condenser119867119904is the average enthalpy of steam (kJkg) and 119867cw is the

enthalpy of saturated water corresponding to the condenserpressure (kJkg)

(ii) Vapor pressure equation is as follows

119889119875119904

119889119905=119877119904(119889119866119904119889119905)

119881(119879119904+ 27315) (3)

where 119875119904is the internal steam pressure of condenser (Pa)

119877119904is the steam gas constant (04615 kJ(kgK)) 119881 is the

space volume of gas in the condenser (m3) and 119879119904is the

temperature of saturated gas (∘C)

(iii) Average enthalpy of steam in the condenser is as follows

119889119866119904119867119904

119889119905= 119866st times 119867st + 119866ost times 119866ost minus (119866119888 + 119866ss) times 119867119904 (4)

where 119867119904is the average enthalpy of steam (kJkg) 119867st is the

enthalpy of steam turbine exhaust (kJkg) and 119867ost is theother inlet enthalpy (kJkg)

(2) Air Zone

(i) Air mass equation is as follows

119889119866119886

119889119905= 119866vb + 119866119899 + 119866119892 minus 119866119886 (5)

where 119866vb is the air quantity of the condenser from thevacuum break valve (kgs)119866

119899is the air volume of the normal

drain condenser (kgs) 119866119892is the air amount from the seal

leakage of the condenser (kgs) and 119866119886is the air quantity

from air extractor (kgs)

(ii) Air pressure equation is as follows

119889119875119886

119889119905=119877119886(119889119866119886119889119905)

119881(119879119904+ 27315) (6)

where 119875119886is the air pressure in the condenser (Pa) and 119877

119886is

the gas constant of the air (0287 kJ(kgK))

(iii) Absolute pressure of the condenser is as follows

119875119888= 119875119904+ 119875119886 (7)

where 119875119888is the absolute pressure in the condenser (Pa)

(3) Hot Water Area

(i) Hot well water level equation is as follows

119871119888=119866119882

120588119860119908

(8)

where 119871119888is the hot well water level (m) 119866

119882is the hot well

water quality (kgs) 120588 is the hot well water density (kgm3)and 119860

119908is the hot well cross-sectional area (m2)

(ii) Hot water quality equation is as follows

119889119866119908

119889119905= 119866119888+ 119866gp minus 119866wo (9)

4 Mathematical Problems in Engineering

where type119866gp is the bubbling oxygen exhaust volume (kgs)and 119866wo is the condenser water outlet quantity (kgs)

(iii) Enthalpy equation of hot well water is as follows

119889119866119908119867119908

119889119905= 119866119888lowast 119867cw + 119866gp lowast 119867gp minus 119866wo lowast 119867119908 (10)

where 119867gp is the bubbling oxygen exhaust steam enthalpy(kJkg) 119867

119908is the enthalpy of hot well water (kJkg) and

119867cw is the enthalpy of saturated water corresponding to thecondenser pressure (kJkg)

222 Mathematical Model of Condenser Tube Side Thedynamic heat balance equation of the circulating water isdescribed as follows

119872119908119862119908

1198891198792

119889119905= 119876 minus 119876

119908= 119880119860Δ119905

119898minus 119865cw119862119901 (119879 minus 119879cw) (11)

where 119872119908is the circulating water quality (kg) 119862

119901is the

circulating water heat capacity (kJ(kg lowast C)) 119876 is the steamoutlet heat (kJ) 119876

119908is the circulating water heat absorption

quantity (kJ) 119880 is the condenser heat transfer coefficient(W(m2 lowast ∘C)) Δ119905

119898is the logarithmic mean temperature

difference (∘C) 119860 is the condenser heat transfer area (m2)119865cw is the circulating water flow (kgs) 119879cw is the circulatingwater inlet temperature (∘C) and 119879 is the circulating wateroutlet temperature (∘C)

The logarithmic heat transfer temperature difference iscalculated by

Δ119905119898=

119879 minus 119879cwln ((119879

119904minus 119879cw) (119879119904 minus 119879))

(12)

The overcooling of condenser is calculated by

Δ119905119908= 119879119888minus 119879119908 (13)

where 119879119888is the saturated water temperature of the vapor

pressure in the condenser (∘C) and 119879119908is the condenser hot

well water temperature (∘C)The heat transfer error of the condenser is calculated by

120575119905= 119879119904minus 119879 (14)

where 119879119904is the saturated gas temperature corresponding to

saturation pressure in condenser (∘C)

3 Grey Wolf Optimizer

The grey wolf optimizer is a new metaheuristic intelligentalgorithm proposed by Mirjalili et al in 2014 [12] which issuccessfully applied in many fields such as security smartgrid power system management [13] parameter estimation[14] reactive power dispatch problem [15] flow shop schedul-ing problem [16] combined heat and power dispatch [17] andautomatic control [18] For immigrating the wolvesrsquo internalleadership hierarchy the wolves are divided into four typesalpha (120572) beta (120573) delta (120575) and omega (Ω) According

Xlowast minus X

(Xlowast Y)(Xlowast minus X Y)

(X Y)

YlowastminusY

(X Ylowast)

(Xlowast Ylowast)

(Xlowast minus X Ylowast)

(Xlowast minus X Ylowast minus Y)

(Xlowast Ylowast minus Y)

(X Ylowast minus Y)

Figure 3 Position vector of wolf and next moving position in two-dimensional space

to the principle of the wolves hunting the hunt process isdivided into three stages searching prey surrounding preyand attacking prey In the four groups of wolves 120572 120573 and 120575are seen as the three best wolves they guide the otherwolf (Ω)trending in the search space in the best region In the iterativesearching process 120572 120573 120575 and Ω wolves are used to realizethe assessment of prey possible positions in the optimizationprocess The positions of wolves are updated in accordancewith the following equations

=100381610038161003816100381610038161003816 sdot997888997888rarr119883119875(119905) minus (119905)

100381610038161003816100381610038161003816

(119905 + 1) =997888997888rarr119883119875(119905) minus sdot

(15)

where 119905 is the current iteration number and are thecoefficient vector 997888997888rarr119883

119875is the position vector of the prey and

is the position of the wolf The vectors and are expressedas follows

= 2119886 sdot997888rarr1199031minus 119886

= 2 sdot997888rarr1199032

(16)

where the coefficient 119886 linearly increases from 2 to 0 with theincrease of the iteration number and997888rarr119903

1and997888rarr1199032are the random

vector located in the scope [0 1]The principle and concept of the position update (15) are

described in Figure 3 [7]It can be seen from Figure 3 that the wolf in the position

(119883 119884) can be arranged a new location on the basis of theabove formula While Figure 3 shows only the 7 possiblepositions of the wolf the randomly adjusting parameters and can make the wolf move to anywhere in a continuousspace In GWO algorithm the positions of wolves 120572 120573 and120575 are likely the prey (optimal) position In the searchingprocess the previous three best solutions are assumed to be

Mathematical Problems in Engineering 5

Alpha

Beta

Delta Omega

Move

D120572

D120573

D120575

Figure 4 Sketch map of position update of the wolves

120572 120573 and 120575 and then the others are regarded as theΩ wolvesThe positions of 120572 120573 and 120575 are used to update their positionsThe following mathematical formulae are used to adjust theposition of Ω wolf again and the position update schematicgraph is shown in Figures 4 and 5

997888rarr119863120572=100381610038161003816100381610038161003816

997888rarr1198621sdot997888rarr119883120572minus

100381610038161003816100381610038161003816

997888rarr119863120573=100381610038161003816100381610038161003816

997888rarr1198622sdot997888rarr119883120573minus

100381610038161003816100381610038161003816

997888rarr119863120575=100381610038161003816100381610038161003816

997888rarr1198623sdot997888rarr119883120575minus

100381610038161003816100381610038161003816

(17)

where 997888rarr119883120572 997888rarr119883120573 and 997888rarr119883

120575are the position of the wolves 120572 120573

and 120575 respectively 997888rarr1198621 997888rarr1198622and 997888rarr119862

3are random vectors and

represents the position of the current solution Equations (17)are used to calculate the approximate distance between thecurrent position and 120572 120573 and 120575 respectively After definingthe distance between them the final position of the currentsolution is calculated by the following

997888rarr1198831=997888rarr119883120572minus997888rarr1198601sdot (997888rarr119863120572) (18)

997888rarr1198832=997888rarr119883120573minus997888rarr1198602sdot (997888rarr119863120573) (19)

997888rarr1198833=997888rarr119883120575minus997888rarr1198603sdot (997888rarr119863120575) (20)

(119905 + 1) =

997888rarr1198831+997888rarr1198832+997888rarr1198833

3 (21)

where 997888rarr1198601 997888rarr1198602 and 997888rarr119860

3are random vectors and 119905 represents

the number of iterationsSeen from the above equations (17) define the step size

of the wolf Ω tending to the wolves 120572 120573 and 120575 Equations(19)ndash(21) define the final position of Ω wolf

Unexplored

Unexplored

Explored

Explored

If |A|lt 1

If |A|ge 1

Figure 5 Exploration and development of wolves

It can be seen from Figure 4 that the random and adaptivevectors and can be used to balance the explorationand development capabilities of the GWO algorithm When|| gt 1 the wolf has detection ability On the other handwhen the value of vector is greater than 1 it can alsopromote the enhancement of the detection ability of the wolfIn contrast when || lt 1 and 119862 lt 1 the wolf rsquos informationmining capacity is enhanced In order to enhance the abilityof the wolf with the increase of the iteration number isdecreased linearly However is randomly generated in thewhole optimization process which can make the detectionand exploitation ability of the wolf to reach equilibrium at anystage especially in the final stage of the iteration and preventthe algorithm from falling into local optimum

The procedure of the GWO algorithm is described asfollows

Step 1 Initialize the wolves Randomly initialize the positionof the wolves119883

119894(119894 = 1 2 119899) and parameters 119886 119860 and 119862

Step 2 Calculate the fitness of eachwolf and choose the threewolves with best fitness as wolves 120572 120573 and 120575

Step 3 Update positions Based on (17)ndash(21) update thepositions of the other wolves that is to say the positions oftheΩ wolves

Step 4 Update parameters 119886 119860 and 119862

Step 5 Judge whether to meet the termination conditions ornot If satisfied the position of 120572 wolf and the fitness valueare the optimal output If the termination condition is notsatisfied return to Step 2

4 Parameter Optimization of PI ControllerBased on GWO Algorithm

41 Dynamic Model of Steam Condenser Based on Mat-labSimulink Simulation Software The establishment of the

6 Mathematical Problems in Engineering

dynamic mathematical model of the condenser is based onthe following assumption that the total amount of condensa-tion the circulating water flow and the condenser volume arecertain So it is set up based on the dynamic heat balance andmass balance of the condenser water

411 Dynamic Heat Balance In the dynamic heat balance itis assumed that the total amount of condensation is certainand that the input steam and the output condensate aresaturated Therefore the heat from steam to the circulatingwater and the steam potential heat are equal So the steamreleased heat can be approximated calculated by the follow-ing equations

119876 asymp 119880119860Δ119905119898

Δ119905119898=

119879 minus 119879cwln ((119879

119904minus 119879cw) (119879119904 minus 119879))

(22)

The heat transfer coefficient 119880 and the heat transfer area119860 can be replaced by the following exponential equationapproximately

1

119880119860= 1205721119865cwminus08

+ 1205722 (23)

where 1205721and 120572

2are constants

When 119865cwrarrinfin 1205722 is determined by 119880119860 In this case 119880119860is determined by the heat transfer ratio between the steamand the tube wall and the thermal resistance of the tube wallThus by assuming the outlet temperature of the circulatingwater 120572

2can be determined Based on the above assumptions

and equations the dynamic heat balance equation of thecondenser is described as follows

119889119879

119889119905=119865cw119872cw

(119879cw minus 119879) +119876

119872cw119862119901 (24)

412 Mass Balance Themass balance of steam and conden-sate is based on the assumption that the space 119881 is constantand the volume of the steam and air is constant That is tosay in order to maintain the vapor condensation level ofthe condenser (certain vacuum degree) the output flow ofcondensatewater needs to be controlled in a certain range Soin order to simplify the model we assume that the inlet andoutlet of the condensate are saturatedTherefore the ideal gasmodel equation is expressed as

119889119875

119889119905=119877119879119888

119881(119865119904minus 119865119888) (25)

where 119865119904is the steam flow (kgs) and 119865

119888is the condensate

water flow (kgs)Among them the condensationwater temperature119879

119888and

the condenser pressure 119875 have a unique relationship In orderto simplify the model it is approximated by the followinglinear relationship equation

119879119888= 120572119875 + 120573 (26)

The steam condenser model given above has five equa-tions among which two are dynamic equations Here there

Table 1 Parameters of steam condenser

Parameter Parameter value Unit119877 0461526 kJkgK119881 3 m3

120582 226565 kJkg119880119860 356972 kWK119872cw 6500 kg119862119901

42 kJ(kgK)120572 03162 KkPa120573 680958 ∘C1205721

87292e minus 21205722

73787e minus 4

Table 2 Variables of steam condenser

Variable Meaning Variable value Unit119865119904

Steam flow 4 kgs119865119888

Condensate water flow 4 kgs119865cw Cooling water flow 1078881 kgs119875 Condenser pressure 90 kPa119879 Circulating water outlet temperature 80 ∘C119879cw Circulating water inlet temperature 60 ∘C119879119888

Saturated water temperature 965538 ∘C119876 Steam heat 90626 kW

are eight variables (119865119904 119865119888 119865cw 119875 119879 119879cw 119879119888 and 119876) and ten

parameters (119877119881120582119880119860119872cw1198621199011205721205731205721 and1205722)The valuesof ten parameters are shown in Table 1 where 120572

1and 120572

2are

determined under 119879 = 90∘C (119865cw rarr infin) The values of theeight variables are shown in Table 2 under the assumptionthat the system is stable

Based on the above model equations and the softwareMatlabSimulink a simulation model of PI controller forcondenser pressure closed-loop control system is establishedas shown in Figure 6 which includes a first-order delay unitused to represent the actuator with a time constant 120591 = 10 (s)and a lag unit caused by the pressure sensor with the timeconstant 120591 = 5 (s)

42 Encoding and Fitness Function Because the design ofthe PID controller is actually a multidimensional functionoptimization problem the GWO algorithm adopts the realnumber coding So for the parameters optimization of the PIcontroller each wolf can be directly coded as (119870

119901 119870119894)

119883 = 119870119901 119870119894 (27)

The control parameter optimization is designed to makethe control error tend to zero and has a faster response speedand smaller overshoot So the evaluation of the performanceof each set of control parameters is good or bad the integralof the product of absolute error and time is selected as thefitness function

ITAE = intinfin

0

119905 |119890 (119905)| 119889119905 (28)

Mathematical Problems in Engineering 7

Click here to tune the PID controller

60

Reaction curvePID tuning

Steam condenserScope

Pressure setpoint

PID

PID controller

Input step test

4

⟨Fcw⟩⟨T⟩

⟨Q⟩⟨P⟩Tcw

Tcw

Fs

Fs y =

Fcw

+++ minus

Figure 6 MatlabSimulink simulation model of PI controller forcondenser pressure closed-loop control system

0 10 20 30 40 50785

79

795

80

Time (s)

Am

plitu

de

⟨T⟩

ZNGA

PSOGWO

Figure 7 Output response curves of outlet temperature of coolingwater under different algorithms

Table 3 Parameters of PI controller

PID parameters ZN GA PSO GWO119870119901

108 853 707 447119870119894

422 091 104 089

43 Simulation Experiments and Results Analysis of PI Con-troller On the basis of the above established model of steamcondenser the GWO algorithm is adopted to optimize theparameters of the adopted PI controller The self-tuningperformances are compared with the Z-N engineering tun-ing method genetic algorithm (GA) and particle swarmoptimization (PSO) algorithm Respectively run GWO PSOand GA algorithm 30 times and then select the best PIDparameters of each algorithm The output response curvesof cooling water outlet temperature circulating water flowsteam discharge heat and condenser pressure are shown inFigures 7ndash10 The parameters of PI controllers are listed inTable 3

0 10 20 30 40 5095

100

105

110

115

120

125

130

135

140

145

Am

plitu

de

Time (s)

ZNGA

PSOGWO

⟨Fcw⟩

Figure 8 Output response curves of circulating water flow underdifferent algorithms

0 10 20 30 40 508200

8400

8600

8800

9000

9200

9400

9600

9800

10000

10200

Am

plitu

de

⟨Q⟩

Time (s)

ZNGA

PSOGWO

Figure 9 Output response curves of steam heat output underdifferent algorithms

As seen from the above simulation results the PI con-troller under the optimization by the proposed GWO algo-rithm has the best control performance that is to say smallovershoot and short rise time and adjustment time The Z-Nengineering self-tuning method has the worst performancewhere the overshoot is the largest and the rise time andadjustment time are the longest The GWO algorithm caneffectively improve the system control quality and achieve thedesired effect

Because the Z-N method belongs to engineering settingmethod setting the PID parameters depends on experience

8 Mathematical Problems in Engineering

0 10 20 30 40 5081

82

83

84

85

86

87

88

89

90

Am

plitu

de

⟨P⟩

Time (s)

ZNGA

PSOGWO

Figure 10 Output response curves of pressure under differentalgorithms

value so the effect of PID control is poor The GA algorithmand PSO algorithm are intelligent method so control effectof PID controller whose parameters are optimized by thesetwo methods has been greatly improved relative to the Z-Nsetting method But because of their inherent search modeand the defects the search accuracy is not high enough thusresult of parameters setting is poorer than that of grey wolfoptimizer It can be known from searching way of GWOalgorithm above that the grey wolf optimizer is going tosearch solutions in the comprehensive evaluation by threewolves Therefore the GWO algorithm has a high searchprecision which can make it sure to search a better solutionvalue Thus the GWO algorithm increases the probability ofsearching a better group of PID parameters

5 Conclusions

In this paper a dynamic model of steam condenser and theclosed-loop control system are established on the basis of thelumped parameter model of the condenser For the pressureclosed-loop control system in order to improve the systemperformance the GWO algorithm is adopted to optimize thePI parametersThrough the simulation experiments and per-formance comparison of cooling water outlet temperaturecirculating water flow steam discharge heat and condenserpressure the introduction of the GWO algorithm makes thesteam condenser PI controller have better control effect Inorder to have a better control effect of steam condenser wecan try to improve the design of PID controller Since theresearch of grey wolf optimizer is just in its infancy theGWO algorithm should be improved to obtain better PIDparameters in the further study Other superior algorithmsshould be exploited for PID parameter optimization

Conflict of Interests

The authors declare that there is no conflict of interestsregarding the publication of this paper

Authorsrsquo Contribution

Shu-Xia Li participated in the data collection analysis algo-rithm simulation draft writing and critical revision of thispaper Jie-Sheng Wang participated in the concept designand interpretation and commented on the paper

Acknowledgments

This work is partially supported by National Key Technolo-gies R amp D Program of China (Grant no 2014BAF05B01)Project by National Natural Science Foundation of China(Grant no 21576127) Program for Liaoning Excellent Talentsin University (Grant no LR2014008) Project by LiaoningProvincial Natural Science Foundation of China (Grant no2014020177) Program for Research Special Foundation ofUniversity of Science and Technology of Liaoning (Grantno 2015TD04) and Opening Project of National FinancialSecurity and System Equipment Engineering Research Cen-ter (Grant no USTLKEC201401)

References

[1] T Tahri S A Abdul-Wahab A Bettahar M Douani H Al-Hinai and Y Al-Mulla ldquoSimulation of the condenser of theseawater greenhouse Part I theoretical developmentrdquo Journalof Thermal Analysis and Calorimetry vol 96 no 1 pp 35ndash422009

[2] P K Bansal and T C Chin ldquoModelling and optimisation ofwire-and-tube condenserrdquo International Journal of Refrigera-tion vol 26 no 5 pp 601ndash613 2003

[3] M R Malin ldquoModelling flow in an experimental marinecondenserrdquo International Communications in Heat and MassTransfer vol 24 no 5 pp 597ndash608 1997

[4] XDingWCai P Duan and J Yan ldquoHybrid dynamicmodelingfor two phase flow condensersrdquo Applied Thermal Engineeringvol 62 no 2 pp 830ndash837 2014

[5] WWangD Zeng J Liu YNiu andC Cui ldquoFeasibility analysisof changing turbine load in power plants using continuouscondenser pressure adjustmentrdquo Energy vol 64 pp 533ndash5402014

[6] Z Ma and S Wang ldquoOnline fault detection and robust controlof condenser cooling water systems in building central chillerplantsrdquo Energy and Buildings vol 43 no 1 pp 153ndash165 2011

[7] D Whitley ldquoAn executable model of a simple genetic algo-rithmrdquo Foundations of Genetic Algorithms vol 2 no 1519 pp45ndash62 2014

[8] J Kennedy and R Eberhart ldquoParticle swarm optimizationrdquoin Proceedings of the IEEE International Conference on NeuralNetworks pp 1942ndash1948 December 1995

[9] D Karaboga and B Basturk ldquoOn the performance of artificialbee colony (ABC) algorithmrdquo Applied Soft Computing vol 8no 1 pp 687ndash697 2008

Mathematical Problems in Engineering 9

[10] M Dorigo M Birattari and T Stutzle ldquoAnt colony optimiza-tionrdquo IEEE Computational Intelligence Magazine vol 1 no 4pp 28ndash39 2006

[11] X-S Yang and S Deb ldquoCuckoo search via Levy flightsrdquo in Pro-ceedings of the World Congress on Nature amp Biologically InspiredComputing (NABIC rsquo09) pp 210ndash214 IEEE Coimbatore IndiaDecember 2009

[12] S Mirjalili S M Mirjalili and A Lewis ldquoGrey wolf optimizerrdquoAdvances in Engineering Software vol 69 pp 46ndash61 2014

[13] B Mahdad and K Srairi ldquoBlackout risk prevention in a smartgrid based flexible optimal strategy using Grey Wolf-patternsearch algorithmsrdquo Energy Conversion and Management vol98 pp 411ndash429 2015

[14] X Song L Tang S Zhao et al ldquoGrey Wolf Optimizer forparameter estimation in surface wavesrdquo Soil Dynamics andEarthquake Engineering vol 75 pp 147ndash157 2015

[15] M H Sulaiman Z Mustaffa M R Mohamed and O AlimanldquoUsing the gray wolf optimizer for solving optimal reactivepower dispatch problemrdquo Applied Soft Computing vol 32 pp286ndash292 2015

[16] G M Komaki and V Kayvanfar ldquoGrey Wolf Optimizer algo-rithm for the two-stage assembly flow shop scheduling problemwith release timerdquo Journal of Computational Science vol 8 pp109ndash120 2015

[17] N Jayakumar S Subramanian S Ganesan and E BElanchezhian ldquoGrey wolf optimization for combined heatand power dispatch with cogeneration systemsrdquo InternationalJournal of Electrical Power amp Energy Systems vol 74 pp252ndash264 2016

[18] Y Sharma and L C Saikia ldquoAutomatic generation controlof a multi-area STmdashthermal power system using Grey Wolfoptimizer algorithm based classical controllersrdquo InternationalJournal of Electrical Power amp Energy Systems vol 73 pp 853ndash862 2015

Submit your manuscripts athttpwwwhindawicom

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

MathematicsJournal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Mathematical Problems in Engineering

Hindawi Publishing Corporationhttpwwwhindawicom

Differential EquationsInternational Journal of

Volume 2014

Applied MathematicsJournal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Probability and StatisticsHindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Journal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Mathematical PhysicsAdvances in

Complex AnalysisJournal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

OptimizationJournal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

CombinatoricsHindawi Publishing Corporationhttpwwwhindawicom Volume 2014

International Journal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Operations ResearchAdvances in

Journal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Function Spaces

Abstract and Applied AnalysisHindawi Publishing Corporationhttpwwwhindawicom Volume 2014

International Journal of Mathematics and Mathematical Sciences

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

The Scientific World JournalHindawi Publishing Corporation httpwwwhindawicom Volume 2014

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Algebra

Discrete Dynamics in Nature and Society

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Decision SciencesAdvances in

Discrete MathematicsJournal of

Hindawi Publishing Corporationhttpwwwhindawicom

Volume 2014 Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Stochastic AnalysisInternational Journal of

Page 2: Research Article Dynamic Modeling of Steam Condenser and ...downloads.hindawi.com/journals/mpe/2015/120975.pdf · Shell-and-tube condenser is a heat exchanger for cooling steam with

2 Mathematical Problems in Engineering

optimize the performance of the overall system by changingthe settings of the local process controllers [6] In the fieldof computer simulation the simulation technology is usedto simulate the operation of the condenser system and studyits working performanceThe optimization of the parametersof PID controller can not only satisfy the static accuracy butalso make the system have better stabilization The accuratemathematical model can accurately and comprehensivelyrepresent all working conditions in the real running processof steam condenser system (normal conditions fault condi-tions and transient conditions) andmake them reappear Onthe same time it can be used to carry through the researchon the dynamical characteristic to meet the requirements ofdifferent engineering projects

At present people by simulating biotic population andtheir evolution process in nature have developed a variety ofintelligence algorithms particle swarm optimization (PSO)algorithm ant colony optimization (ACO) algorithm artifi-cial bee colony (ABC) algorithm shuffled frog leaping (SFL)algorithm cuckoo search (CS) algorithm Dolphin partneroptimization (DPO) and Firefly algorithm (FA)

GA is the most typical algorithm of evolutionary branchThis algorithm simulates Darwinian evolution concepts [7]Each new population is created by the combination andmutation of the individuals in the previous generationParticle swarm optimization (PSO) was inspired from thesocial behavior of birds flocking [8] The PSO algorithmemploys multiple particles that chase the position of the bestparticle and their own best positions obtained so far Artificialbee colony (ABC) algorithm mimics the collective behaviorof bees in finding food sources [9] There are three typesof bees in ABC scout onlooker and employed bees Thescout bees are responsible for exploring the search spacewhereas onlooker and employed bees exploit the promisingsolutions found by scout bees Ant colony optimization(ACO) algorithm was inspired by the social behavior of antsin an ant colony In fact the social intelligence of ants infinding the shortest path between the nest and a source offood is themain inspiration of ACO [10] Cuckoo search (CS)algorithm was put forward by Yang and Deb in 2009 [11]This algorithm is mainly based on two aspects the cuckoorsquosparasitic reproduction mechanism and Levy flights searchprinciple Assume each cuckoo only lays one egg at a timeand randomly chooses birdrsquos nest to hatch the egg

The grey wolf optimizer (GWO) as a new swarm intel-ligent algorithm is put forward by Seyedali Mirjalili and soforth in 2014 whichmainlymimics wolf leadership hierarchyand huntingmechanism in nature Seyedali andMirjalili andso forth have proved that the search performance of basicwolf algorithm is superior to that of PSO GSA DE and FEPalgorithm Due to the wolvesrsquo algorithm with the advantagesof being simple in principle having fast seeking speed andhigh search precision and being easy to realize it is moreeasily combined with the practical engineering problems

Many kinds of swarm intelligence are inspired by hunt-ing and search behaviors of a population However GWOalgorithm simulates internal leadership hierarchy of wolvesthus in the searching process the position of best solutioncan be comprehensively assessed by three solutions So the

Cooling water inlet Steam inlet

Cooling Condensatewater outlet water outlet

Figure 1 Structure diagram of shell-and-tube condenser

GWO algorithm is able to greatly reduce the probabilityof producing premature phenomenon and falling into localoptimum

Aiming at the steam condenser pressure control problembased on the MatlabSimulink simulation platform and theestablished mathematical model a closed-loop condenserpressure control system is designed The GWO algorithm isadopted to optimize the parameters of the PI controller Sim-ulation results show the effectiveness of the proposed controlstrategy The paper is organized as follows In Section 2 thetechnique and dynamicmodeling of the shell-and-tube steamcondenser are introduced The GWO algorithm is illustratedin Section 3 The parameter optimization of PI controllerbased on GWO algorithm is described and the simulationexperiments and results analysis are introduced in detail inSection 4 Finally the conclusion illustrates the last part

2 Dynamic Modeling of Steam Condenser

21 Structure Characteristics and Working Principle of SteamCondenser The shell of shell-and-tube type condenser isusually cylindrical or elliptical as shown in Figure 1 which isconnected with end closures for constituting the water cham-bers Between the end closures and the shells a perforatedtube plate is fixed in which a lot of cooling water pipes arearranged hierarchicallyThe entrance pipe of steam is locatedin the upper part of the condenser shell which is directly orindirectly connected with the exhaust equipment through thecompensator In the lower part of the shell there is a gatheringtank (or a hot well water tank) of the condensed waterThe airoutlet port is positioned at the lower part of shell and the airis drawn through this nozzle

Theworking principle of the steam condenser is shown inFigure 2

Steam goes into steam field of the condenser throughsteam admission pipe Steamgets in touchwith the condensertube wall to begin the radiate condensation at the same timethe latent heat is transferred to the cooling water through thesurface of the cooling water pipe Cooling water with inlettemperature is fed into water chamber through the coolingwater pipe where the cooling water is assigned to all pipesof the first procedure in the lower part of the condensershell The cooling water flows into another water chamberalong the first six cooling water pipes and then enters thenext flow pipes and carries through heat exchange withthe steam Through such several procedures in return the

Mathematical Problems in Engineering 3

Steam inlet

Cooling Cooling

Condensate water outlet

Gc Tc1 Gc Tc2

Gh2 Th2

Gh1 Th1

water inlet water outlet

Figure 2 Schematic diagram of condenser

cooling water with the outlet temperature is discharged fromthe outlet pipes Due to the lack of system sealing propertythe air is drawn out from the condenser constantly to ensurethe requirements of the systemrsquos vacuum degree The drawngas contains the air and steam In the beginning of thecondensation the air volume is very smaller than the totalamount of steam With the steam and air flowing toward theexhaust port steam is continuously condensed down Thenthe steam quality in the mixture gradually decreases On thecontrary the relative content of the air increases graduallyUntil the relative content of air fed into the cooling zone airhas reached a great numerical extent the steam condensationprocess terminates

22 Mathematical Model

221 Mathematical Model of Shell Side of Condenser

(1) Steam Zone

(i) Steam mass equation is as follows

119889119866119904

119889119905= 119866st + 119866ost minus 119866119888 minus 119866ss (1)

where 119866119904is the steam content in the shell side of the

condenser (kgs) 119866st is the exhaust volume of steam turbine(kgs)119866ost is the other steam inlet of the condenser (kgs)119866

119888

is the main steam condensate (kgs) and119866ss is the amount ofsteam drawn out by vacuum pumping equipment (kgs)119866ss and 119866119888 are calculated by the following equations

119866ss = 119866ao (1 minus 119877)

119877 =119872119886

119872119904+119872119886

=119875119886119877119904

119875119904119877119886+ 119875119886119877119904

119876119888= 119866119888(119867119904minus 119867cw)

119866119888=

119880119860Δ119905119898

(119867119888minus 119867cw)

(2)

where 119866ao is the quality of the gas mixture pumped by thepumping unit (kgs) 119877 is the share air ratio in the condenser119867119904is the average enthalpy of steam (kJkg) and 119867cw is the

enthalpy of saturated water corresponding to the condenserpressure (kJkg)

(ii) Vapor pressure equation is as follows

119889119875119904

119889119905=119877119904(119889119866119904119889119905)

119881(119879119904+ 27315) (3)

where 119875119904is the internal steam pressure of condenser (Pa)

119877119904is the steam gas constant (04615 kJ(kgK)) 119881 is the

space volume of gas in the condenser (m3) and 119879119904is the

temperature of saturated gas (∘C)

(iii) Average enthalpy of steam in the condenser is as follows

119889119866119904119867119904

119889119905= 119866st times 119867st + 119866ost times 119866ost minus (119866119888 + 119866ss) times 119867119904 (4)

where 119867119904is the average enthalpy of steam (kJkg) 119867st is the

enthalpy of steam turbine exhaust (kJkg) and 119867ost is theother inlet enthalpy (kJkg)

(2) Air Zone

(i) Air mass equation is as follows

119889119866119886

119889119905= 119866vb + 119866119899 + 119866119892 minus 119866119886 (5)

where 119866vb is the air quantity of the condenser from thevacuum break valve (kgs)119866

119899is the air volume of the normal

drain condenser (kgs) 119866119892is the air amount from the seal

leakage of the condenser (kgs) and 119866119886is the air quantity

from air extractor (kgs)

(ii) Air pressure equation is as follows

119889119875119886

119889119905=119877119886(119889119866119886119889119905)

119881(119879119904+ 27315) (6)

where 119875119886is the air pressure in the condenser (Pa) and 119877

119886is

the gas constant of the air (0287 kJ(kgK))

(iii) Absolute pressure of the condenser is as follows

119875119888= 119875119904+ 119875119886 (7)

where 119875119888is the absolute pressure in the condenser (Pa)

(3) Hot Water Area

(i) Hot well water level equation is as follows

119871119888=119866119882

120588119860119908

(8)

where 119871119888is the hot well water level (m) 119866

119882is the hot well

water quality (kgs) 120588 is the hot well water density (kgm3)and 119860

119908is the hot well cross-sectional area (m2)

(ii) Hot water quality equation is as follows

119889119866119908

119889119905= 119866119888+ 119866gp minus 119866wo (9)

4 Mathematical Problems in Engineering

where type119866gp is the bubbling oxygen exhaust volume (kgs)and 119866wo is the condenser water outlet quantity (kgs)

(iii) Enthalpy equation of hot well water is as follows

119889119866119908119867119908

119889119905= 119866119888lowast 119867cw + 119866gp lowast 119867gp minus 119866wo lowast 119867119908 (10)

where 119867gp is the bubbling oxygen exhaust steam enthalpy(kJkg) 119867

119908is the enthalpy of hot well water (kJkg) and

119867cw is the enthalpy of saturated water corresponding to thecondenser pressure (kJkg)

222 Mathematical Model of Condenser Tube Side Thedynamic heat balance equation of the circulating water isdescribed as follows

119872119908119862119908

1198891198792

119889119905= 119876 minus 119876

119908= 119880119860Δ119905

119898minus 119865cw119862119901 (119879 minus 119879cw) (11)

where 119872119908is the circulating water quality (kg) 119862

119901is the

circulating water heat capacity (kJ(kg lowast C)) 119876 is the steamoutlet heat (kJ) 119876

119908is the circulating water heat absorption

quantity (kJ) 119880 is the condenser heat transfer coefficient(W(m2 lowast ∘C)) Δ119905

119898is the logarithmic mean temperature

difference (∘C) 119860 is the condenser heat transfer area (m2)119865cw is the circulating water flow (kgs) 119879cw is the circulatingwater inlet temperature (∘C) and 119879 is the circulating wateroutlet temperature (∘C)

The logarithmic heat transfer temperature difference iscalculated by

Δ119905119898=

119879 minus 119879cwln ((119879

119904minus 119879cw) (119879119904 minus 119879))

(12)

The overcooling of condenser is calculated by

Δ119905119908= 119879119888minus 119879119908 (13)

where 119879119888is the saturated water temperature of the vapor

pressure in the condenser (∘C) and 119879119908is the condenser hot

well water temperature (∘C)The heat transfer error of the condenser is calculated by

120575119905= 119879119904minus 119879 (14)

where 119879119904is the saturated gas temperature corresponding to

saturation pressure in condenser (∘C)

3 Grey Wolf Optimizer

The grey wolf optimizer is a new metaheuristic intelligentalgorithm proposed by Mirjalili et al in 2014 [12] which issuccessfully applied in many fields such as security smartgrid power system management [13] parameter estimation[14] reactive power dispatch problem [15] flow shop schedul-ing problem [16] combined heat and power dispatch [17] andautomatic control [18] For immigrating the wolvesrsquo internalleadership hierarchy the wolves are divided into four typesalpha (120572) beta (120573) delta (120575) and omega (Ω) According

Xlowast minus X

(Xlowast Y)(Xlowast minus X Y)

(X Y)

YlowastminusY

(X Ylowast)

(Xlowast Ylowast)

(Xlowast minus X Ylowast)

(Xlowast minus X Ylowast minus Y)

(Xlowast Ylowast minus Y)

(X Ylowast minus Y)

Figure 3 Position vector of wolf and next moving position in two-dimensional space

to the principle of the wolves hunting the hunt process isdivided into three stages searching prey surrounding preyand attacking prey In the four groups of wolves 120572 120573 and 120575are seen as the three best wolves they guide the otherwolf (Ω)trending in the search space in the best region In the iterativesearching process 120572 120573 120575 and Ω wolves are used to realizethe assessment of prey possible positions in the optimizationprocess The positions of wolves are updated in accordancewith the following equations

=100381610038161003816100381610038161003816 sdot997888997888rarr119883119875(119905) minus (119905)

100381610038161003816100381610038161003816

(119905 + 1) =997888997888rarr119883119875(119905) minus sdot

(15)

where 119905 is the current iteration number and are thecoefficient vector 997888997888rarr119883

119875is the position vector of the prey and

is the position of the wolf The vectors and are expressedas follows

= 2119886 sdot997888rarr1199031minus 119886

= 2 sdot997888rarr1199032

(16)

where the coefficient 119886 linearly increases from 2 to 0 with theincrease of the iteration number and997888rarr119903

1and997888rarr1199032are the random

vector located in the scope [0 1]The principle and concept of the position update (15) are

described in Figure 3 [7]It can be seen from Figure 3 that the wolf in the position

(119883 119884) can be arranged a new location on the basis of theabove formula While Figure 3 shows only the 7 possiblepositions of the wolf the randomly adjusting parameters and can make the wolf move to anywhere in a continuousspace In GWO algorithm the positions of wolves 120572 120573 and120575 are likely the prey (optimal) position In the searchingprocess the previous three best solutions are assumed to be

Mathematical Problems in Engineering 5

Alpha

Beta

Delta Omega

Move

D120572

D120573

D120575

Figure 4 Sketch map of position update of the wolves

120572 120573 and 120575 and then the others are regarded as theΩ wolvesThe positions of 120572 120573 and 120575 are used to update their positionsThe following mathematical formulae are used to adjust theposition of Ω wolf again and the position update schematicgraph is shown in Figures 4 and 5

997888rarr119863120572=100381610038161003816100381610038161003816

997888rarr1198621sdot997888rarr119883120572minus

100381610038161003816100381610038161003816

997888rarr119863120573=100381610038161003816100381610038161003816

997888rarr1198622sdot997888rarr119883120573minus

100381610038161003816100381610038161003816

997888rarr119863120575=100381610038161003816100381610038161003816

997888rarr1198623sdot997888rarr119883120575minus

100381610038161003816100381610038161003816

(17)

where 997888rarr119883120572 997888rarr119883120573 and 997888rarr119883

120575are the position of the wolves 120572 120573

and 120575 respectively 997888rarr1198621 997888rarr1198622and 997888rarr119862

3are random vectors and

represents the position of the current solution Equations (17)are used to calculate the approximate distance between thecurrent position and 120572 120573 and 120575 respectively After definingthe distance between them the final position of the currentsolution is calculated by the following

997888rarr1198831=997888rarr119883120572minus997888rarr1198601sdot (997888rarr119863120572) (18)

997888rarr1198832=997888rarr119883120573minus997888rarr1198602sdot (997888rarr119863120573) (19)

997888rarr1198833=997888rarr119883120575minus997888rarr1198603sdot (997888rarr119863120575) (20)

(119905 + 1) =

997888rarr1198831+997888rarr1198832+997888rarr1198833

3 (21)

where 997888rarr1198601 997888rarr1198602 and 997888rarr119860

3are random vectors and 119905 represents

the number of iterationsSeen from the above equations (17) define the step size

of the wolf Ω tending to the wolves 120572 120573 and 120575 Equations(19)ndash(21) define the final position of Ω wolf

Unexplored

Unexplored

Explored

Explored

If |A|lt 1

If |A|ge 1

Figure 5 Exploration and development of wolves

It can be seen from Figure 4 that the random and adaptivevectors and can be used to balance the explorationand development capabilities of the GWO algorithm When|| gt 1 the wolf has detection ability On the other handwhen the value of vector is greater than 1 it can alsopromote the enhancement of the detection ability of the wolfIn contrast when || lt 1 and 119862 lt 1 the wolf rsquos informationmining capacity is enhanced In order to enhance the abilityof the wolf with the increase of the iteration number isdecreased linearly However is randomly generated in thewhole optimization process which can make the detectionand exploitation ability of the wolf to reach equilibrium at anystage especially in the final stage of the iteration and preventthe algorithm from falling into local optimum

The procedure of the GWO algorithm is described asfollows

Step 1 Initialize the wolves Randomly initialize the positionof the wolves119883

119894(119894 = 1 2 119899) and parameters 119886 119860 and 119862

Step 2 Calculate the fitness of eachwolf and choose the threewolves with best fitness as wolves 120572 120573 and 120575

Step 3 Update positions Based on (17)ndash(21) update thepositions of the other wolves that is to say the positions oftheΩ wolves

Step 4 Update parameters 119886 119860 and 119862

Step 5 Judge whether to meet the termination conditions ornot If satisfied the position of 120572 wolf and the fitness valueare the optimal output If the termination condition is notsatisfied return to Step 2

4 Parameter Optimization of PI ControllerBased on GWO Algorithm

41 Dynamic Model of Steam Condenser Based on Mat-labSimulink Simulation Software The establishment of the

6 Mathematical Problems in Engineering

dynamic mathematical model of the condenser is based onthe following assumption that the total amount of condensa-tion the circulating water flow and the condenser volume arecertain So it is set up based on the dynamic heat balance andmass balance of the condenser water

411 Dynamic Heat Balance In the dynamic heat balance itis assumed that the total amount of condensation is certainand that the input steam and the output condensate aresaturated Therefore the heat from steam to the circulatingwater and the steam potential heat are equal So the steamreleased heat can be approximated calculated by the follow-ing equations

119876 asymp 119880119860Δ119905119898

Δ119905119898=

119879 minus 119879cwln ((119879

119904minus 119879cw) (119879119904 minus 119879))

(22)

The heat transfer coefficient 119880 and the heat transfer area119860 can be replaced by the following exponential equationapproximately

1

119880119860= 1205721119865cwminus08

+ 1205722 (23)

where 1205721and 120572

2are constants

When 119865cwrarrinfin 1205722 is determined by 119880119860 In this case 119880119860is determined by the heat transfer ratio between the steamand the tube wall and the thermal resistance of the tube wallThus by assuming the outlet temperature of the circulatingwater 120572

2can be determined Based on the above assumptions

and equations the dynamic heat balance equation of thecondenser is described as follows

119889119879

119889119905=119865cw119872cw

(119879cw minus 119879) +119876

119872cw119862119901 (24)

412 Mass Balance Themass balance of steam and conden-sate is based on the assumption that the space 119881 is constantand the volume of the steam and air is constant That is tosay in order to maintain the vapor condensation level ofthe condenser (certain vacuum degree) the output flow ofcondensatewater needs to be controlled in a certain range Soin order to simplify the model we assume that the inlet andoutlet of the condensate are saturatedTherefore the ideal gasmodel equation is expressed as

119889119875

119889119905=119877119879119888

119881(119865119904minus 119865119888) (25)

where 119865119904is the steam flow (kgs) and 119865

119888is the condensate

water flow (kgs)Among them the condensationwater temperature119879

119888and

the condenser pressure 119875 have a unique relationship In orderto simplify the model it is approximated by the followinglinear relationship equation

119879119888= 120572119875 + 120573 (26)

The steam condenser model given above has five equa-tions among which two are dynamic equations Here there

Table 1 Parameters of steam condenser

Parameter Parameter value Unit119877 0461526 kJkgK119881 3 m3

120582 226565 kJkg119880119860 356972 kWK119872cw 6500 kg119862119901

42 kJ(kgK)120572 03162 KkPa120573 680958 ∘C1205721

87292e minus 21205722

73787e minus 4

Table 2 Variables of steam condenser

Variable Meaning Variable value Unit119865119904

Steam flow 4 kgs119865119888

Condensate water flow 4 kgs119865cw Cooling water flow 1078881 kgs119875 Condenser pressure 90 kPa119879 Circulating water outlet temperature 80 ∘C119879cw Circulating water inlet temperature 60 ∘C119879119888

Saturated water temperature 965538 ∘C119876 Steam heat 90626 kW

are eight variables (119865119904 119865119888 119865cw 119875 119879 119879cw 119879119888 and 119876) and ten

parameters (119877119881120582119880119860119872cw1198621199011205721205731205721 and1205722)The valuesof ten parameters are shown in Table 1 where 120572

1and 120572

2are

determined under 119879 = 90∘C (119865cw rarr infin) The values of theeight variables are shown in Table 2 under the assumptionthat the system is stable

Based on the above model equations and the softwareMatlabSimulink a simulation model of PI controller forcondenser pressure closed-loop control system is establishedas shown in Figure 6 which includes a first-order delay unitused to represent the actuator with a time constant 120591 = 10 (s)and a lag unit caused by the pressure sensor with the timeconstant 120591 = 5 (s)

42 Encoding and Fitness Function Because the design ofthe PID controller is actually a multidimensional functionoptimization problem the GWO algorithm adopts the realnumber coding So for the parameters optimization of the PIcontroller each wolf can be directly coded as (119870

119901 119870119894)

119883 = 119870119901 119870119894 (27)

The control parameter optimization is designed to makethe control error tend to zero and has a faster response speedand smaller overshoot So the evaluation of the performanceof each set of control parameters is good or bad the integralof the product of absolute error and time is selected as thefitness function

ITAE = intinfin

0

119905 |119890 (119905)| 119889119905 (28)

Mathematical Problems in Engineering 7

Click here to tune the PID controller

60

Reaction curvePID tuning

Steam condenserScope

Pressure setpoint

PID

PID controller

Input step test

4

⟨Fcw⟩⟨T⟩

⟨Q⟩⟨P⟩Tcw

Tcw

Fs

Fs y =

Fcw

+++ minus

Figure 6 MatlabSimulink simulation model of PI controller forcondenser pressure closed-loop control system

0 10 20 30 40 50785

79

795

80

Time (s)

Am

plitu

de

⟨T⟩

ZNGA

PSOGWO

Figure 7 Output response curves of outlet temperature of coolingwater under different algorithms

Table 3 Parameters of PI controller

PID parameters ZN GA PSO GWO119870119901

108 853 707 447119870119894

422 091 104 089

43 Simulation Experiments and Results Analysis of PI Con-troller On the basis of the above established model of steamcondenser the GWO algorithm is adopted to optimize theparameters of the adopted PI controller The self-tuningperformances are compared with the Z-N engineering tun-ing method genetic algorithm (GA) and particle swarmoptimization (PSO) algorithm Respectively run GWO PSOand GA algorithm 30 times and then select the best PIDparameters of each algorithm The output response curvesof cooling water outlet temperature circulating water flowsteam discharge heat and condenser pressure are shown inFigures 7ndash10 The parameters of PI controllers are listed inTable 3

0 10 20 30 40 5095

100

105

110

115

120

125

130

135

140

145

Am

plitu

de

Time (s)

ZNGA

PSOGWO

⟨Fcw⟩

Figure 8 Output response curves of circulating water flow underdifferent algorithms

0 10 20 30 40 508200

8400

8600

8800

9000

9200

9400

9600

9800

10000

10200

Am

plitu

de

⟨Q⟩

Time (s)

ZNGA

PSOGWO

Figure 9 Output response curves of steam heat output underdifferent algorithms

As seen from the above simulation results the PI con-troller under the optimization by the proposed GWO algo-rithm has the best control performance that is to say smallovershoot and short rise time and adjustment time The Z-Nengineering self-tuning method has the worst performancewhere the overshoot is the largest and the rise time andadjustment time are the longest The GWO algorithm caneffectively improve the system control quality and achieve thedesired effect

Because the Z-N method belongs to engineering settingmethod setting the PID parameters depends on experience

8 Mathematical Problems in Engineering

0 10 20 30 40 5081

82

83

84

85

86

87

88

89

90

Am

plitu

de

⟨P⟩

Time (s)

ZNGA

PSOGWO

Figure 10 Output response curves of pressure under differentalgorithms

value so the effect of PID control is poor The GA algorithmand PSO algorithm are intelligent method so control effectof PID controller whose parameters are optimized by thesetwo methods has been greatly improved relative to the Z-Nsetting method But because of their inherent search modeand the defects the search accuracy is not high enough thusresult of parameters setting is poorer than that of grey wolfoptimizer It can be known from searching way of GWOalgorithm above that the grey wolf optimizer is going tosearch solutions in the comprehensive evaluation by threewolves Therefore the GWO algorithm has a high searchprecision which can make it sure to search a better solutionvalue Thus the GWO algorithm increases the probability ofsearching a better group of PID parameters

5 Conclusions

In this paper a dynamic model of steam condenser and theclosed-loop control system are established on the basis of thelumped parameter model of the condenser For the pressureclosed-loop control system in order to improve the systemperformance the GWO algorithm is adopted to optimize thePI parametersThrough the simulation experiments and per-formance comparison of cooling water outlet temperaturecirculating water flow steam discharge heat and condenserpressure the introduction of the GWO algorithm makes thesteam condenser PI controller have better control effect Inorder to have a better control effect of steam condenser wecan try to improve the design of PID controller Since theresearch of grey wolf optimizer is just in its infancy theGWO algorithm should be improved to obtain better PIDparameters in the further study Other superior algorithmsshould be exploited for PID parameter optimization

Conflict of Interests

The authors declare that there is no conflict of interestsregarding the publication of this paper

Authorsrsquo Contribution

Shu-Xia Li participated in the data collection analysis algo-rithm simulation draft writing and critical revision of thispaper Jie-Sheng Wang participated in the concept designand interpretation and commented on the paper

Acknowledgments

This work is partially supported by National Key Technolo-gies R amp D Program of China (Grant no 2014BAF05B01)Project by National Natural Science Foundation of China(Grant no 21576127) Program for Liaoning Excellent Talentsin University (Grant no LR2014008) Project by LiaoningProvincial Natural Science Foundation of China (Grant no2014020177) Program for Research Special Foundation ofUniversity of Science and Technology of Liaoning (Grantno 2015TD04) and Opening Project of National FinancialSecurity and System Equipment Engineering Research Cen-ter (Grant no USTLKEC201401)

References

[1] T Tahri S A Abdul-Wahab A Bettahar M Douani H Al-Hinai and Y Al-Mulla ldquoSimulation of the condenser of theseawater greenhouse Part I theoretical developmentrdquo Journalof Thermal Analysis and Calorimetry vol 96 no 1 pp 35ndash422009

[2] P K Bansal and T C Chin ldquoModelling and optimisation ofwire-and-tube condenserrdquo International Journal of Refrigera-tion vol 26 no 5 pp 601ndash613 2003

[3] M R Malin ldquoModelling flow in an experimental marinecondenserrdquo International Communications in Heat and MassTransfer vol 24 no 5 pp 597ndash608 1997

[4] XDingWCai P Duan and J Yan ldquoHybrid dynamicmodelingfor two phase flow condensersrdquo Applied Thermal Engineeringvol 62 no 2 pp 830ndash837 2014

[5] WWangD Zeng J Liu YNiu andC Cui ldquoFeasibility analysisof changing turbine load in power plants using continuouscondenser pressure adjustmentrdquo Energy vol 64 pp 533ndash5402014

[6] Z Ma and S Wang ldquoOnline fault detection and robust controlof condenser cooling water systems in building central chillerplantsrdquo Energy and Buildings vol 43 no 1 pp 153ndash165 2011

[7] D Whitley ldquoAn executable model of a simple genetic algo-rithmrdquo Foundations of Genetic Algorithms vol 2 no 1519 pp45ndash62 2014

[8] J Kennedy and R Eberhart ldquoParticle swarm optimizationrdquoin Proceedings of the IEEE International Conference on NeuralNetworks pp 1942ndash1948 December 1995

[9] D Karaboga and B Basturk ldquoOn the performance of artificialbee colony (ABC) algorithmrdquo Applied Soft Computing vol 8no 1 pp 687ndash697 2008

Mathematical Problems in Engineering 9

[10] M Dorigo M Birattari and T Stutzle ldquoAnt colony optimiza-tionrdquo IEEE Computational Intelligence Magazine vol 1 no 4pp 28ndash39 2006

[11] X-S Yang and S Deb ldquoCuckoo search via Levy flightsrdquo in Pro-ceedings of the World Congress on Nature amp Biologically InspiredComputing (NABIC rsquo09) pp 210ndash214 IEEE Coimbatore IndiaDecember 2009

[12] S Mirjalili S M Mirjalili and A Lewis ldquoGrey wolf optimizerrdquoAdvances in Engineering Software vol 69 pp 46ndash61 2014

[13] B Mahdad and K Srairi ldquoBlackout risk prevention in a smartgrid based flexible optimal strategy using Grey Wolf-patternsearch algorithmsrdquo Energy Conversion and Management vol98 pp 411ndash429 2015

[14] X Song L Tang S Zhao et al ldquoGrey Wolf Optimizer forparameter estimation in surface wavesrdquo Soil Dynamics andEarthquake Engineering vol 75 pp 147ndash157 2015

[15] M H Sulaiman Z Mustaffa M R Mohamed and O AlimanldquoUsing the gray wolf optimizer for solving optimal reactivepower dispatch problemrdquo Applied Soft Computing vol 32 pp286ndash292 2015

[16] G M Komaki and V Kayvanfar ldquoGrey Wolf Optimizer algo-rithm for the two-stage assembly flow shop scheduling problemwith release timerdquo Journal of Computational Science vol 8 pp109ndash120 2015

[17] N Jayakumar S Subramanian S Ganesan and E BElanchezhian ldquoGrey wolf optimization for combined heatand power dispatch with cogeneration systemsrdquo InternationalJournal of Electrical Power amp Energy Systems vol 74 pp252ndash264 2016

[18] Y Sharma and L C Saikia ldquoAutomatic generation controlof a multi-area STmdashthermal power system using Grey Wolfoptimizer algorithm based classical controllersrdquo InternationalJournal of Electrical Power amp Energy Systems vol 73 pp 853ndash862 2015

Submit your manuscripts athttpwwwhindawicom

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

MathematicsJournal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Mathematical Problems in Engineering

Hindawi Publishing Corporationhttpwwwhindawicom

Differential EquationsInternational Journal of

Volume 2014

Applied MathematicsJournal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Probability and StatisticsHindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Journal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Mathematical PhysicsAdvances in

Complex AnalysisJournal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

OptimizationJournal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

CombinatoricsHindawi Publishing Corporationhttpwwwhindawicom Volume 2014

International Journal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Operations ResearchAdvances in

Journal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Function Spaces

Abstract and Applied AnalysisHindawi Publishing Corporationhttpwwwhindawicom Volume 2014

International Journal of Mathematics and Mathematical Sciences

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

The Scientific World JournalHindawi Publishing Corporation httpwwwhindawicom Volume 2014

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Algebra

Discrete Dynamics in Nature and Society

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Decision SciencesAdvances in

Discrete MathematicsJournal of

Hindawi Publishing Corporationhttpwwwhindawicom

Volume 2014 Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Stochastic AnalysisInternational Journal of

Page 3: Research Article Dynamic Modeling of Steam Condenser and ...downloads.hindawi.com/journals/mpe/2015/120975.pdf · Shell-and-tube condenser is a heat exchanger for cooling steam with

Mathematical Problems in Engineering 3

Steam inlet

Cooling Cooling

Condensate water outlet

Gc Tc1 Gc Tc2

Gh2 Th2

Gh1 Th1

water inlet water outlet

Figure 2 Schematic diagram of condenser

cooling water with the outlet temperature is discharged fromthe outlet pipes Due to the lack of system sealing propertythe air is drawn out from the condenser constantly to ensurethe requirements of the systemrsquos vacuum degree The drawngas contains the air and steam In the beginning of thecondensation the air volume is very smaller than the totalamount of steam With the steam and air flowing toward theexhaust port steam is continuously condensed down Thenthe steam quality in the mixture gradually decreases On thecontrary the relative content of the air increases graduallyUntil the relative content of air fed into the cooling zone airhas reached a great numerical extent the steam condensationprocess terminates

22 Mathematical Model

221 Mathematical Model of Shell Side of Condenser

(1) Steam Zone

(i) Steam mass equation is as follows

119889119866119904

119889119905= 119866st + 119866ost minus 119866119888 minus 119866ss (1)

where 119866119904is the steam content in the shell side of the

condenser (kgs) 119866st is the exhaust volume of steam turbine(kgs)119866ost is the other steam inlet of the condenser (kgs)119866

119888

is the main steam condensate (kgs) and119866ss is the amount ofsteam drawn out by vacuum pumping equipment (kgs)119866ss and 119866119888 are calculated by the following equations

119866ss = 119866ao (1 minus 119877)

119877 =119872119886

119872119904+119872119886

=119875119886119877119904

119875119904119877119886+ 119875119886119877119904

119876119888= 119866119888(119867119904minus 119867cw)

119866119888=

119880119860Δ119905119898

(119867119888minus 119867cw)

(2)

where 119866ao is the quality of the gas mixture pumped by thepumping unit (kgs) 119877 is the share air ratio in the condenser119867119904is the average enthalpy of steam (kJkg) and 119867cw is the

enthalpy of saturated water corresponding to the condenserpressure (kJkg)

(ii) Vapor pressure equation is as follows

119889119875119904

119889119905=119877119904(119889119866119904119889119905)

119881(119879119904+ 27315) (3)

where 119875119904is the internal steam pressure of condenser (Pa)

119877119904is the steam gas constant (04615 kJ(kgK)) 119881 is the

space volume of gas in the condenser (m3) and 119879119904is the

temperature of saturated gas (∘C)

(iii) Average enthalpy of steam in the condenser is as follows

119889119866119904119867119904

119889119905= 119866st times 119867st + 119866ost times 119866ost minus (119866119888 + 119866ss) times 119867119904 (4)

where 119867119904is the average enthalpy of steam (kJkg) 119867st is the

enthalpy of steam turbine exhaust (kJkg) and 119867ost is theother inlet enthalpy (kJkg)

(2) Air Zone

(i) Air mass equation is as follows

119889119866119886

119889119905= 119866vb + 119866119899 + 119866119892 minus 119866119886 (5)

where 119866vb is the air quantity of the condenser from thevacuum break valve (kgs)119866

119899is the air volume of the normal

drain condenser (kgs) 119866119892is the air amount from the seal

leakage of the condenser (kgs) and 119866119886is the air quantity

from air extractor (kgs)

(ii) Air pressure equation is as follows

119889119875119886

119889119905=119877119886(119889119866119886119889119905)

119881(119879119904+ 27315) (6)

where 119875119886is the air pressure in the condenser (Pa) and 119877

119886is

the gas constant of the air (0287 kJ(kgK))

(iii) Absolute pressure of the condenser is as follows

119875119888= 119875119904+ 119875119886 (7)

where 119875119888is the absolute pressure in the condenser (Pa)

(3) Hot Water Area

(i) Hot well water level equation is as follows

119871119888=119866119882

120588119860119908

(8)

where 119871119888is the hot well water level (m) 119866

119882is the hot well

water quality (kgs) 120588 is the hot well water density (kgm3)and 119860

119908is the hot well cross-sectional area (m2)

(ii) Hot water quality equation is as follows

119889119866119908

119889119905= 119866119888+ 119866gp minus 119866wo (9)

4 Mathematical Problems in Engineering

where type119866gp is the bubbling oxygen exhaust volume (kgs)and 119866wo is the condenser water outlet quantity (kgs)

(iii) Enthalpy equation of hot well water is as follows

119889119866119908119867119908

119889119905= 119866119888lowast 119867cw + 119866gp lowast 119867gp minus 119866wo lowast 119867119908 (10)

where 119867gp is the bubbling oxygen exhaust steam enthalpy(kJkg) 119867

119908is the enthalpy of hot well water (kJkg) and

119867cw is the enthalpy of saturated water corresponding to thecondenser pressure (kJkg)

222 Mathematical Model of Condenser Tube Side Thedynamic heat balance equation of the circulating water isdescribed as follows

119872119908119862119908

1198891198792

119889119905= 119876 minus 119876

119908= 119880119860Δ119905

119898minus 119865cw119862119901 (119879 minus 119879cw) (11)

where 119872119908is the circulating water quality (kg) 119862

119901is the

circulating water heat capacity (kJ(kg lowast C)) 119876 is the steamoutlet heat (kJ) 119876

119908is the circulating water heat absorption

quantity (kJ) 119880 is the condenser heat transfer coefficient(W(m2 lowast ∘C)) Δ119905

119898is the logarithmic mean temperature

difference (∘C) 119860 is the condenser heat transfer area (m2)119865cw is the circulating water flow (kgs) 119879cw is the circulatingwater inlet temperature (∘C) and 119879 is the circulating wateroutlet temperature (∘C)

The logarithmic heat transfer temperature difference iscalculated by

Δ119905119898=

119879 minus 119879cwln ((119879

119904minus 119879cw) (119879119904 minus 119879))

(12)

The overcooling of condenser is calculated by

Δ119905119908= 119879119888minus 119879119908 (13)

where 119879119888is the saturated water temperature of the vapor

pressure in the condenser (∘C) and 119879119908is the condenser hot

well water temperature (∘C)The heat transfer error of the condenser is calculated by

120575119905= 119879119904minus 119879 (14)

where 119879119904is the saturated gas temperature corresponding to

saturation pressure in condenser (∘C)

3 Grey Wolf Optimizer

The grey wolf optimizer is a new metaheuristic intelligentalgorithm proposed by Mirjalili et al in 2014 [12] which issuccessfully applied in many fields such as security smartgrid power system management [13] parameter estimation[14] reactive power dispatch problem [15] flow shop schedul-ing problem [16] combined heat and power dispatch [17] andautomatic control [18] For immigrating the wolvesrsquo internalleadership hierarchy the wolves are divided into four typesalpha (120572) beta (120573) delta (120575) and omega (Ω) According

Xlowast minus X

(Xlowast Y)(Xlowast minus X Y)

(X Y)

YlowastminusY

(X Ylowast)

(Xlowast Ylowast)

(Xlowast minus X Ylowast)

(Xlowast minus X Ylowast minus Y)

(Xlowast Ylowast minus Y)

(X Ylowast minus Y)

Figure 3 Position vector of wolf and next moving position in two-dimensional space

to the principle of the wolves hunting the hunt process isdivided into three stages searching prey surrounding preyand attacking prey In the four groups of wolves 120572 120573 and 120575are seen as the three best wolves they guide the otherwolf (Ω)trending in the search space in the best region In the iterativesearching process 120572 120573 120575 and Ω wolves are used to realizethe assessment of prey possible positions in the optimizationprocess The positions of wolves are updated in accordancewith the following equations

=100381610038161003816100381610038161003816 sdot997888997888rarr119883119875(119905) minus (119905)

100381610038161003816100381610038161003816

(119905 + 1) =997888997888rarr119883119875(119905) minus sdot

(15)

where 119905 is the current iteration number and are thecoefficient vector 997888997888rarr119883

119875is the position vector of the prey and

is the position of the wolf The vectors and are expressedas follows

= 2119886 sdot997888rarr1199031minus 119886

= 2 sdot997888rarr1199032

(16)

where the coefficient 119886 linearly increases from 2 to 0 with theincrease of the iteration number and997888rarr119903

1and997888rarr1199032are the random

vector located in the scope [0 1]The principle and concept of the position update (15) are

described in Figure 3 [7]It can be seen from Figure 3 that the wolf in the position

(119883 119884) can be arranged a new location on the basis of theabove formula While Figure 3 shows only the 7 possiblepositions of the wolf the randomly adjusting parameters and can make the wolf move to anywhere in a continuousspace In GWO algorithm the positions of wolves 120572 120573 and120575 are likely the prey (optimal) position In the searchingprocess the previous three best solutions are assumed to be

Mathematical Problems in Engineering 5

Alpha

Beta

Delta Omega

Move

D120572

D120573

D120575

Figure 4 Sketch map of position update of the wolves

120572 120573 and 120575 and then the others are regarded as theΩ wolvesThe positions of 120572 120573 and 120575 are used to update their positionsThe following mathematical formulae are used to adjust theposition of Ω wolf again and the position update schematicgraph is shown in Figures 4 and 5

997888rarr119863120572=100381610038161003816100381610038161003816

997888rarr1198621sdot997888rarr119883120572minus

100381610038161003816100381610038161003816

997888rarr119863120573=100381610038161003816100381610038161003816

997888rarr1198622sdot997888rarr119883120573minus

100381610038161003816100381610038161003816

997888rarr119863120575=100381610038161003816100381610038161003816

997888rarr1198623sdot997888rarr119883120575minus

100381610038161003816100381610038161003816

(17)

where 997888rarr119883120572 997888rarr119883120573 and 997888rarr119883

120575are the position of the wolves 120572 120573

and 120575 respectively 997888rarr1198621 997888rarr1198622and 997888rarr119862

3are random vectors and

represents the position of the current solution Equations (17)are used to calculate the approximate distance between thecurrent position and 120572 120573 and 120575 respectively After definingthe distance between them the final position of the currentsolution is calculated by the following

997888rarr1198831=997888rarr119883120572minus997888rarr1198601sdot (997888rarr119863120572) (18)

997888rarr1198832=997888rarr119883120573minus997888rarr1198602sdot (997888rarr119863120573) (19)

997888rarr1198833=997888rarr119883120575minus997888rarr1198603sdot (997888rarr119863120575) (20)

(119905 + 1) =

997888rarr1198831+997888rarr1198832+997888rarr1198833

3 (21)

where 997888rarr1198601 997888rarr1198602 and 997888rarr119860

3are random vectors and 119905 represents

the number of iterationsSeen from the above equations (17) define the step size

of the wolf Ω tending to the wolves 120572 120573 and 120575 Equations(19)ndash(21) define the final position of Ω wolf

Unexplored

Unexplored

Explored

Explored

If |A|lt 1

If |A|ge 1

Figure 5 Exploration and development of wolves

It can be seen from Figure 4 that the random and adaptivevectors and can be used to balance the explorationand development capabilities of the GWO algorithm When|| gt 1 the wolf has detection ability On the other handwhen the value of vector is greater than 1 it can alsopromote the enhancement of the detection ability of the wolfIn contrast when || lt 1 and 119862 lt 1 the wolf rsquos informationmining capacity is enhanced In order to enhance the abilityof the wolf with the increase of the iteration number isdecreased linearly However is randomly generated in thewhole optimization process which can make the detectionand exploitation ability of the wolf to reach equilibrium at anystage especially in the final stage of the iteration and preventthe algorithm from falling into local optimum

The procedure of the GWO algorithm is described asfollows

Step 1 Initialize the wolves Randomly initialize the positionof the wolves119883

119894(119894 = 1 2 119899) and parameters 119886 119860 and 119862

Step 2 Calculate the fitness of eachwolf and choose the threewolves with best fitness as wolves 120572 120573 and 120575

Step 3 Update positions Based on (17)ndash(21) update thepositions of the other wolves that is to say the positions oftheΩ wolves

Step 4 Update parameters 119886 119860 and 119862

Step 5 Judge whether to meet the termination conditions ornot If satisfied the position of 120572 wolf and the fitness valueare the optimal output If the termination condition is notsatisfied return to Step 2

4 Parameter Optimization of PI ControllerBased on GWO Algorithm

41 Dynamic Model of Steam Condenser Based on Mat-labSimulink Simulation Software The establishment of the

6 Mathematical Problems in Engineering

dynamic mathematical model of the condenser is based onthe following assumption that the total amount of condensa-tion the circulating water flow and the condenser volume arecertain So it is set up based on the dynamic heat balance andmass balance of the condenser water

411 Dynamic Heat Balance In the dynamic heat balance itis assumed that the total amount of condensation is certainand that the input steam and the output condensate aresaturated Therefore the heat from steam to the circulatingwater and the steam potential heat are equal So the steamreleased heat can be approximated calculated by the follow-ing equations

119876 asymp 119880119860Δ119905119898

Δ119905119898=

119879 minus 119879cwln ((119879

119904minus 119879cw) (119879119904 minus 119879))

(22)

The heat transfer coefficient 119880 and the heat transfer area119860 can be replaced by the following exponential equationapproximately

1

119880119860= 1205721119865cwminus08

+ 1205722 (23)

where 1205721and 120572

2are constants

When 119865cwrarrinfin 1205722 is determined by 119880119860 In this case 119880119860is determined by the heat transfer ratio between the steamand the tube wall and the thermal resistance of the tube wallThus by assuming the outlet temperature of the circulatingwater 120572

2can be determined Based on the above assumptions

and equations the dynamic heat balance equation of thecondenser is described as follows

119889119879

119889119905=119865cw119872cw

(119879cw minus 119879) +119876

119872cw119862119901 (24)

412 Mass Balance Themass balance of steam and conden-sate is based on the assumption that the space 119881 is constantand the volume of the steam and air is constant That is tosay in order to maintain the vapor condensation level ofthe condenser (certain vacuum degree) the output flow ofcondensatewater needs to be controlled in a certain range Soin order to simplify the model we assume that the inlet andoutlet of the condensate are saturatedTherefore the ideal gasmodel equation is expressed as

119889119875

119889119905=119877119879119888

119881(119865119904minus 119865119888) (25)

where 119865119904is the steam flow (kgs) and 119865

119888is the condensate

water flow (kgs)Among them the condensationwater temperature119879

119888and

the condenser pressure 119875 have a unique relationship In orderto simplify the model it is approximated by the followinglinear relationship equation

119879119888= 120572119875 + 120573 (26)

The steam condenser model given above has five equa-tions among which two are dynamic equations Here there

Table 1 Parameters of steam condenser

Parameter Parameter value Unit119877 0461526 kJkgK119881 3 m3

120582 226565 kJkg119880119860 356972 kWK119872cw 6500 kg119862119901

42 kJ(kgK)120572 03162 KkPa120573 680958 ∘C1205721

87292e minus 21205722

73787e minus 4

Table 2 Variables of steam condenser

Variable Meaning Variable value Unit119865119904

Steam flow 4 kgs119865119888

Condensate water flow 4 kgs119865cw Cooling water flow 1078881 kgs119875 Condenser pressure 90 kPa119879 Circulating water outlet temperature 80 ∘C119879cw Circulating water inlet temperature 60 ∘C119879119888

Saturated water temperature 965538 ∘C119876 Steam heat 90626 kW

are eight variables (119865119904 119865119888 119865cw 119875 119879 119879cw 119879119888 and 119876) and ten

parameters (119877119881120582119880119860119872cw1198621199011205721205731205721 and1205722)The valuesof ten parameters are shown in Table 1 where 120572

1and 120572

2are

determined under 119879 = 90∘C (119865cw rarr infin) The values of theeight variables are shown in Table 2 under the assumptionthat the system is stable

Based on the above model equations and the softwareMatlabSimulink a simulation model of PI controller forcondenser pressure closed-loop control system is establishedas shown in Figure 6 which includes a first-order delay unitused to represent the actuator with a time constant 120591 = 10 (s)and a lag unit caused by the pressure sensor with the timeconstant 120591 = 5 (s)

42 Encoding and Fitness Function Because the design ofthe PID controller is actually a multidimensional functionoptimization problem the GWO algorithm adopts the realnumber coding So for the parameters optimization of the PIcontroller each wolf can be directly coded as (119870

119901 119870119894)

119883 = 119870119901 119870119894 (27)

The control parameter optimization is designed to makethe control error tend to zero and has a faster response speedand smaller overshoot So the evaluation of the performanceof each set of control parameters is good or bad the integralof the product of absolute error and time is selected as thefitness function

ITAE = intinfin

0

119905 |119890 (119905)| 119889119905 (28)

Mathematical Problems in Engineering 7

Click here to tune the PID controller

60

Reaction curvePID tuning

Steam condenserScope

Pressure setpoint

PID

PID controller

Input step test

4

⟨Fcw⟩⟨T⟩

⟨Q⟩⟨P⟩Tcw

Tcw

Fs

Fs y =

Fcw

+++ minus

Figure 6 MatlabSimulink simulation model of PI controller forcondenser pressure closed-loop control system

0 10 20 30 40 50785

79

795

80

Time (s)

Am

plitu

de

⟨T⟩

ZNGA

PSOGWO

Figure 7 Output response curves of outlet temperature of coolingwater under different algorithms

Table 3 Parameters of PI controller

PID parameters ZN GA PSO GWO119870119901

108 853 707 447119870119894

422 091 104 089

43 Simulation Experiments and Results Analysis of PI Con-troller On the basis of the above established model of steamcondenser the GWO algorithm is adopted to optimize theparameters of the adopted PI controller The self-tuningperformances are compared with the Z-N engineering tun-ing method genetic algorithm (GA) and particle swarmoptimization (PSO) algorithm Respectively run GWO PSOand GA algorithm 30 times and then select the best PIDparameters of each algorithm The output response curvesof cooling water outlet temperature circulating water flowsteam discharge heat and condenser pressure are shown inFigures 7ndash10 The parameters of PI controllers are listed inTable 3

0 10 20 30 40 5095

100

105

110

115

120

125

130

135

140

145

Am

plitu

de

Time (s)

ZNGA

PSOGWO

⟨Fcw⟩

Figure 8 Output response curves of circulating water flow underdifferent algorithms

0 10 20 30 40 508200

8400

8600

8800

9000

9200

9400

9600

9800

10000

10200

Am

plitu

de

⟨Q⟩

Time (s)

ZNGA

PSOGWO

Figure 9 Output response curves of steam heat output underdifferent algorithms

As seen from the above simulation results the PI con-troller under the optimization by the proposed GWO algo-rithm has the best control performance that is to say smallovershoot and short rise time and adjustment time The Z-Nengineering self-tuning method has the worst performancewhere the overshoot is the largest and the rise time andadjustment time are the longest The GWO algorithm caneffectively improve the system control quality and achieve thedesired effect

Because the Z-N method belongs to engineering settingmethod setting the PID parameters depends on experience

8 Mathematical Problems in Engineering

0 10 20 30 40 5081

82

83

84

85

86

87

88

89

90

Am

plitu

de

⟨P⟩

Time (s)

ZNGA

PSOGWO

Figure 10 Output response curves of pressure under differentalgorithms

value so the effect of PID control is poor The GA algorithmand PSO algorithm are intelligent method so control effectof PID controller whose parameters are optimized by thesetwo methods has been greatly improved relative to the Z-Nsetting method But because of their inherent search modeand the defects the search accuracy is not high enough thusresult of parameters setting is poorer than that of grey wolfoptimizer It can be known from searching way of GWOalgorithm above that the grey wolf optimizer is going tosearch solutions in the comprehensive evaluation by threewolves Therefore the GWO algorithm has a high searchprecision which can make it sure to search a better solutionvalue Thus the GWO algorithm increases the probability ofsearching a better group of PID parameters

5 Conclusions

In this paper a dynamic model of steam condenser and theclosed-loop control system are established on the basis of thelumped parameter model of the condenser For the pressureclosed-loop control system in order to improve the systemperformance the GWO algorithm is adopted to optimize thePI parametersThrough the simulation experiments and per-formance comparison of cooling water outlet temperaturecirculating water flow steam discharge heat and condenserpressure the introduction of the GWO algorithm makes thesteam condenser PI controller have better control effect Inorder to have a better control effect of steam condenser wecan try to improve the design of PID controller Since theresearch of grey wolf optimizer is just in its infancy theGWO algorithm should be improved to obtain better PIDparameters in the further study Other superior algorithmsshould be exploited for PID parameter optimization

Conflict of Interests

The authors declare that there is no conflict of interestsregarding the publication of this paper

Authorsrsquo Contribution

Shu-Xia Li participated in the data collection analysis algo-rithm simulation draft writing and critical revision of thispaper Jie-Sheng Wang participated in the concept designand interpretation and commented on the paper

Acknowledgments

This work is partially supported by National Key Technolo-gies R amp D Program of China (Grant no 2014BAF05B01)Project by National Natural Science Foundation of China(Grant no 21576127) Program for Liaoning Excellent Talentsin University (Grant no LR2014008) Project by LiaoningProvincial Natural Science Foundation of China (Grant no2014020177) Program for Research Special Foundation ofUniversity of Science and Technology of Liaoning (Grantno 2015TD04) and Opening Project of National FinancialSecurity and System Equipment Engineering Research Cen-ter (Grant no USTLKEC201401)

References

[1] T Tahri S A Abdul-Wahab A Bettahar M Douani H Al-Hinai and Y Al-Mulla ldquoSimulation of the condenser of theseawater greenhouse Part I theoretical developmentrdquo Journalof Thermal Analysis and Calorimetry vol 96 no 1 pp 35ndash422009

[2] P K Bansal and T C Chin ldquoModelling and optimisation ofwire-and-tube condenserrdquo International Journal of Refrigera-tion vol 26 no 5 pp 601ndash613 2003

[3] M R Malin ldquoModelling flow in an experimental marinecondenserrdquo International Communications in Heat and MassTransfer vol 24 no 5 pp 597ndash608 1997

[4] XDingWCai P Duan and J Yan ldquoHybrid dynamicmodelingfor two phase flow condensersrdquo Applied Thermal Engineeringvol 62 no 2 pp 830ndash837 2014

[5] WWangD Zeng J Liu YNiu andC Cui ldquoFeasibility analysisof changing turbine load in power plants using continuouscondenser pressure adjustmentrdquo Energy vol 64 pp 533ndash5402014

[6] Z Ma and S Wang ldquoOnline fault detection and robust controlof condenser cooling water systems in building central chillerplantsrdquo Energy and Buildings vol 43 no 1 pp 153ndash165 2011

[7] D Whitley ldquoAn executable model of a simple genetic algo-rithmrdquo Foundations of Genetic Algorithms vol 2 no 1519 pp45ndash62 2014

[8] J Kennedy and R Eberhart ldquoParticle swarm optimizationrdquoin Proceedings of the IEEE International Conference on NeuralNetworks pp 1942ndash1948 December 1995

[9] D Karaboga and B Basturk ldquoOn the performance of artificialbee colony (ABC) algorithmrdquo Applied Soft Computing vol 8no 1 pp 687ndash697 2008

Mathematical Problems in Engineering 9

[10] M Dorigo M Birattari and T Stutzle ldquoAnt colony optimiza-tionrdquo IEEE Computational Intelligence Magazine vol 1 no 4pp 28ndash39 2006

[11] X-S Yang and S Deb ldquoCuckoo search via Levy flightsrdquo in Pro-ceedings of the World Congress on Nature amp Biologically InspiredComputing (NABIC rsquo09) pp 210ndash214 IEEE Coimbatore IndiaDecember 2009

[12] S Mirjalili S M Mirjalili and A Lewis ldquoGrey wolf optimizerrdquoAdvances in Engineering Software vol 69 pp 46ndash61 2014

[13] B Mahdad and K Srairi ldquoBlackout risk prevention in a smartgrid based flexible optimal strategy using Grey Wolf-patternsearch algorithmsrdquo Energy Conversion and Management vol98 pp 411ndash429 2015

[14] X Song L Tang S Zhao et al ldquoGrey Wolf Optimizer forparameter estimation in surface wavesrdquo Soil Dynamics andEarthquake Engineering vol 75 pp 147ndash157 2015

[15] M H Sulaiman Z Mustaffa M R Mohamed and O AlimanldquoUsing the gray wolf optimizer for solving optimal reactivepower dispatch problemrdquo Applied Soft Computing vol 32 pp286ndash292 2015

[16] G M Komaki and V Kayvanfar ldquoGrey Wolf Optimizer algo-rithm for the two-stage assembly flow shop scheduling problemwith release timerdquo Journal of Computational Science vol 8 pp109ndash120 2015

[17] N Jayakumar S Subramanian S Ganesan and E BElanchezhian ldquoGrey wolf optimization for combined heatand power dispatch with cogeneration systemsrdquo InternationalJournal of Electrical Power amp Energy Systems vol 74 pp252ndash264 2016

[18] Y Sharma and L C Saikia ldquoAutomatic generation controlof a multi-area STmdashthermal power system using Grey Wolfoptimizer algorithm based classical controllersrdquo InternationalJournal of Electrical Power amp Energy Systems vol 73 pp 853ndash862 2015

Submit your manuscripts athttpwwwhindawicom

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

MathematicsJournal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Mathematical Problems in Engineering

Hindawi Publishing Corporationhttpwwwhindawicom

Differential EquationsInternational Journal of

Volume 2014

Applied MathematicsJournal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Probability and StatisticsHindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Journal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Mathematical PhysicsAdvances in

Complex AnalysisJournal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

OptimizationJournal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

CombinatoricsHindawi Publishing Corporationhttpwwwhindawicom Volume 2014

International Journal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Operations ResearchAdvances in

Journal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Function Spaces

Abstract and Applied AnalysisHindawi Publishing Corporationhttpwwwhindawicom Volume 2014

International Journal of Mathematics and Mathematical Sciences

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

The Scientific World JournalHindawi Publishing Corporation httpwwwhindawicom Volume 2014

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Algebra

Discrete Dynamics in Nature and Society

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Decision SciencesAdvances in

Discrete MathematicsJournal of

Hindawi Publishing Corporationhttpwwwhindawicom

Volume 2014 Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Stochastic AnalysisInternational Journal of

Page 4: Research Article Dynamic Modeling of Steam Condenser and ...downloads.hindawi.com/journals/mpe/2015/120975.pdf · Shell-and-tube condenser is a heat exchanger for cooling steam with

4 Mathematical Problems in Engineering

where type119866gp is the bubbling oxygen exhaust volume (kgs)and 119866wo is the condenser water outlet quantity (kgs)

(iii) Enthalpy equation of hot well water is as follows

119889119866119908119867119908

119889119905= 119866119888lowast 119867cw + 119866gp lowast 119867gp minus 119866wo lowast 119867119908 (10)

where 119867gp is the bubbling oxygen exhaust steam enthalpy(kJkg) 119867

119908is the enthalpy of hot well water (kJkg) and

119867cw is the enthalpy of saturated water corresponding to thecondenser pressure (kJkg)

222 Mathematical Model of Condenser Tube Side Thedynamic heat balance equation of the circulating water isdescribed as follows

119872119908119862119908

1198891198792

119889119905= 119876 minus 119876

119908= 119880119860Δ119905

119898minus 119865cw119862119901 (119879 minus 119879cw) (11)

where 119872119908is the circulating water quality (kg) 119862

119901is the

circulating water heat capacity (kJ(kg lowast C)) 119876 is the steamoutlet heat (kJ) 119876

119908is the circulating water heat absorption

quantity (kJ) 119880 is the condenser heat transfer coefficient(W(m2 lowast ∘C)) Δ119905

119898is the logarithmic mean temperature

difference (∘C) 119860 is the condenser heat transfer area (m2)119865cw is the circulating water flow (kgs) 119879cw is the circulatingwater inlet temperature (∘C) and 119879 is the circulating wateroutlet temperature (∘C)

The logarithmic heat transfer temperature difference iscalculated by

Δ119905119898=

119879 minus 119879cwln ((119879

119904minus 119879cw) (119879119904 minus 119879))

(12)

The overcooling of condenser is calculated by

Δ119905119908= 119879119888minus 119879119908 (13)

where 119879119888is the saturated water temperature of the vapor

pressure in the condenser (∘C) and 119879119908is the condenser hot

well water temperature (∘C)The heat transfer error of the condenser is calculated by

120575119905= 119879119904minus 119879 (14)

where 119879119904is the saturated gas temperature corresponding to

saturation pressure in condenser (∘C)

3 Grey Wolf Optimizer

The grey wolf optimizer is a new metaheuristic intelligentalgorithm proposed by Mirjalili et al in 2014 [12] which issuccessfully applied in many fields such as security smartgrid power system management [13] parameter estimation[14] reactive power dispatch problem [15] flow shop schedul-ing problem [16] combined heat and power dispatch [17] andautomatic control [18] For immigrating the wolvesrsquo internalleadership hierarchy the wolves are divided into four typesalpha (120572) beta (120573) delta (120575) and omega (Ω) According

Xlowast minus X

(Xlowast Y)(Xlowast minus X Y)

(X Y)

YlowastminusY

(X Ylowast)

(Xlowast Ylowast)

(Xlowast minus X Ylowast)

(Xlowast minus X Ylowast minus Y)

(Xlowast Ylowast minus Y)

(X Ylowast minus Y)

Figure 3 Position vector of wolf and next moving position in two-dimensional space

to the principle of the wolves hunting the hunt process isdivided into three stages searching prey surrounding preyand attacking prey In the four groups of wolves 120572 120573 and 120575are seen as the three best wolves they guide the otherwolf (Ω)trending in the search space in the best region In the iterativesearching process 120572 120573 120575 and Ω wolves are used to realizethe assessment of prey possible positions in the optimizationprocess The positions of wolves are updated in accordancewith the following equations

=100381610038161003816100381610038161003816 sdot997888997888rarr119883119875(119905) minus (119905)

100381610038161003816100381610038161003816

(119905 + 1) =997888997888rarr119883119875(119905) minus sdot

(15)

where 119905 is the current iteration number and are thecoefficient vector 997888997888rarr119883

119875is the position vector of the prey and

is the position of the wolf The vectors and are expressedas follows

= 2119886 sdot997888rarr1199031minus 119886

= 2 sdot997888rarr1199032

(16)

where the coefficient 119886 linearly increases from 2 to 0 with theincrease of the iteration number and997888rarr119903

1and997888rarr1199032are the random

vector located in the scope [0 1]The principle and concept of the position update (15) are

described in Figure 3 [7]It can be seen from Figure 3 that the wolf in the position

(119883 119884) can be arranged a new location on the basis of theabove formula While Figure 3 shows only the 7 possiblepositions of the wolf the randomly adjusting parameters and can make the wolf move to anywhere in a continuousspace In GWO algorithm the positions of wolves 120572 120573 and120575 are likely the prey (optimal) position In the searchingprocess the previous three best solutions are assumed to be

Mathematical Problems in Engineering 5

Alpha

Beta

Delta Omega

Move

D120572

D120573

D120575

Figure 4 Sketch map of position update of the wolves

120572 120573 and 120575 and then the others are regarded as theΩ wolvesThe positions of 120572 120573 and 120575 are used to update their positionsThe following mathematical formulae are used to adjust theposition of Ω wolf again and the position update schematicgraph is shown in Figures 4 and 5

997888rarr119863120572=100381610038161003816100381610038161003816

997888rarr1198621sdot997888rarr119883120572minus

100381610038161003816100381610038161003816

997888rarr119863120573=100381610038161003816100381610038161003816

997888rarr1198622sdot997888rarr119883120573minus

100381610038161003816100381610038161003816

997888rarr119863120575=100381610038161003816100381610038161003816

997888rarr1198623sdot997888rarr119883120575minus

100381610038161003816100381610038161003816

(17)

where 997888rarr119883120572 997888rarr119883120573 and 997888rarr119883

120575are the position of the wolves 120572 120573

and 120575 respectively 997888rarr1198621 997888rarr1198622and 997888rarr119862

3are random vectors and

represents the position of the current solution Equations (17)are used to calculate the approximate distance between thecurrent position and 120572 120573 and 120575 respectively After definingthe distance between them the final position of the currentsolution is calculated by the following

997888rarr1198831=997888rarr119883120572minus997888rarr1198601sdot (997888rarr119863120572) (18)

997888rarr1198832=997888rarr119883120573minus997888rarr1198602sdot (997888rarr119863120573) (19)

997888rarr1198833=997888rarr119883120575minus997888rarr1198603sdot (997888rarr119863120575) (20)

(119905 + 1) =

997888rarr1198831+997888rarr1198832+997888rarr1198833

3 (21)

where 997888rarr1198601 997888rarr1198602 and 997888rarr119860

3are random vectors and 119905 represents

the number of iterationsSeen from the above equations (17) define the step size

of the wolf Ω tending to the wolves 120572 120573 and 120575 Equations(19)ndash(21) define the final position of Ω wolf

Unexplored

Unexplored

Explored

Explored

If |A|lt 1

If |A|ge 1

Figure 5 Exploration and development of wolves

It can be seen from Figure 4 that the random and adaptivevectors and can be used to balance the explorationand development capabilities of the GWO algorithm When|| gt 1 the wolf has detection ability On the other handwhen the value of vector is greater than 1 it can alsopromote the enhancement of the detection ability of the wolfIn contrast when || lt 1 and 119862 lt 1 the wolf rsquos informationmining capacity is enhanced In order to enhance the abilityof the wolf with the increase of the iteration number isdecreased linearly However is randomly generated in thewhole optimization process which can make the detectionand exploitation ability of the wolf to reach equilibrium at anystage especially in the final stage of the iteration and preventthe algorithm from falling into local optimum

The procedure of the GWO algorithm is described asfollows

Step 1 Initialize the wolves Randomly initialize the positionof the wolves119883

119894(119894 = 1 2 119899) and parameters 119886 119860 and 119862

Step 2 Calculate the fitness of eachwolf and choose the threewolves with best fitness as wolves 120572 120573 and 120575

Step 3 Update positions Based on (17)ndash(21) update thepositions of the other wolves that is to say the positions oftheΩ wolves

Step 4 Update parameters 119886 119860 and 119862

Step 5 Judge whether to meet the termination conditions ornot If satisfied the position of 120572 wolf and the fitness valueare the optimal output If the termination condition is notsatisfied return to Step 2

4 Parameter Optimization of PI ControllerBased on GWO Algorithm

41 Dynamic Model of Steam Condenser Based on Mat-labSimulink Simulation Software The establishment of the

6 Mathematical Problems in Engineering

dynamic mathematical model of the condenser is based onthe following assumption that the total amount of condensa-tion the circulating water flow and the condenser volume arecertain So it is set up based on the dynamic heat balance andmass balance of the condenser water

411 Dynamic Heat Balance In the dynamic heat balance itis assumed that the total amount of condensation is certainand that the input steam and the output condensate aresaturated Therefore the heat from steam to the circulatingwater and the steam potential heat are equal So the steamreleased heat can be approximated calculated by the follow-ing equations

119876 asymp 119880119860Δ119905119898

Δ119905119898=

119879 minus 119879cwln ((119879

119904minus 119879cw) (119879119904 minus 119879))

(22)

The heat transfer coefficient 119880 and the heat transfer area119860 can be replaced by the following exponential equationapproximately

1

119880119860= 1205721119865cwminus08

+ 1205722 (23)

where 1205721and 120572

2are constants

When 119865cwrarrinfin 1205722 is determined by 119880119860 In this case 119880119860is determined by the heat transfer ratio between the steamand the tube wall and the thermal resistance of the tube wallThus by assuming the outlet temperature of the circulatingwater 120572

2can be determined Based on the above assumptions

and equations the dynamic heat balance equation of thecondenser is described as follows

119889119879

119889119905=119865cw119872cw

(119879cw minus 119879) +119876

119872cw119862119901 (24)

412 Mass Balance Themass balance of steam and conden-sate is based on the assumption that the space 119881 is constantand the volume of the steam and air is constant That is tosay in order to maintain the vapor condensation level ofthe condenser (certain vacuum degree) the output flow ofcondensatewater needs to be controlled in a certain range Soin order to simplify the model we assume that the inlet andoutlet of the condensate are saturatedTherefore the ideal gasmodel equation is expressed as

119889119875

119889119905=119877119879119888

119881(119865119904minus 119865119888) (25)

where 119865119904is the steam flow (kgs) and 119865

119888is the condensate

water flow (kgs)Among them the condensationwater temperature119879

119888and

the condenser pressure 119875 have a unique relationship In orderto simplify the model it is approximated by the followinglinear relationship equation

119879119888= 120572119875 + 120573 (26)

The steam condenser model given above has five equa-tions among which two are dynamic equations Here there

Table 1 Parameters of steam condenser

Parameter Parameter value Unit119877 0461526 kJkgK119881 3 m3

120582 226565 kJkg119880119860 356972 kWK119872cw 6500 kg119862119901

42 kJ(kgK)120572 03162 KkPa120573 680958 ∘C1205721

87292e minus 21205722

73787e minus 4

Table 2 Variables of steam condenser

Variable Meaning Variable value Unit119865119904

Steam flow 4 kgs119865119888

Condensate water flow 4 kgs119865cw Cooling water flow 1078881 kgs119875 Condenser pressure 90 kPa119879 Circulating water outlet temperature 80 ∘C119879cw Circulating water inlet temperature 60 ∘C119879119888

Saturated water temperature 965538 ∘C119876 Steam heat 90626 kW

are eight variables (119865119904 119865119888 119865cw 119875 119879 119879cw 119879119888 and 119876) and ten

parameters (119877119881120582119880119860119872cw1198621199011205721205731205721 and1205722)The valuesof ten parameters are shown in Table 1 where 120572

1and 120572

2are

determined under 119879 = 90∘C (119865cw rarr infin) The values of theeight variables are shown in Table 2 under the assumptionthat the system is stable

Based on the above model equations and the softwareMatlabSimulink a simulation model of PI controller forcondenser pressure closed-loop control system is establishedas shown in Figure 6 which includes a first-order delay unitused to represent the actuator with a time constant 120591 = 10 (s)and a lag unit caused by the pressure sensor with the timeconstant 120591 = 5 (s)

42 Encoding and Fitness Function Because the design ofthe PID controller is actually a multidimensional functionoptimization problem the GWO algorithm adopts the realnumber coding So for the parameters optimization of the PIcontroller each wolf can be directly coded as (119870

119901 119870119894)

119883 = 119870119901 119870119894 (27)

The control parameter optimization is designed to makethe control error tend to zero and has a faster response speedand smaller overshoot So the evaluation of the performanceof each set of control parameters is good or bad the integralof the product of absolute error and time is selected as thefitness function

ITAE = intinfin

0

119905 |119890 (119905)| 119889119905 (28)

Mathematical Problems in Engineering 7

Click here to tune the PID controller

60

Reaction curvePID tuning

Steam condenserScope

Pressure setpoint

PID

PID controller

Input step test

4

⟨Fcw⟩⟨T⟩

⟨Q⟩⟨P⟩Tcw

Tcw

Fs

Fs y =

Fcw

+++ minus

Figure 6 MatlabSimulink simulation model of PI controller forcondenser pressure closed-loop control system

0 10 20 30 40 50785

79

795

80

Time (s)

Am

plitu

de

⟨T⟩

ZNGA

PSOGWO

Figure 7 Output response curves of outlet temperature of coolingwater under different algorithms

Table 3 Parameters of PI controller

PID parameters ZN GA PSO GWO119870119901

108 853 707 447119870119894

422 091 104 089

43 Simulation Experiments and Results Analysis of PI Con-troller On the basis of the above established model of steamcondenser the GWO algorithm is adopted to optimize theparameters of the adopted PI controller The self-tuningperformances are compared with the Z-N engineering tun-ing method genetic algorithm (GA) and particle swarmoptimization (PSO) algorithm Respectively run GWO PSOand GA algorithm 30 times and then select the best PIDparameters of each algorithm The output response curvesof cooling water outlet temperature circulating water flowsteam discharge heat and condenser pressure are shown inFigures 7ndash10 The parameters of PI controllers are listed inTable 3

0 10 20 30 40 5095

100

105

110

115

120

125

130

135

140

145

Am

plitu

de

Time (s)

ZNGA

PSOGWO

⟨Fcw⟩

Figure 8 Output response curves of circulating water flow underdifferent algorithms

0 10 20 30 40 508200

8400

8600

8800

9000

9200

9400

9600

9800

10000

10200

Am

plitu

de

⟨Q⟩

Time (s)

ZNGA

PSOGWO

Figure 9 Output response curves of steam heat output underdifferent algorithms

As seen from the above simulation results the PI con-troller under the optimization by the proposed GWO algo-rithm has the best control performance that is to say smallovershoot and short rise time and adjustment time The Z-Nengineering self-tuning method has the worst performancewhere the overshoot is the largest and the rise time andadjustment time are the longest The GWO algorithm caneffectively improve the system control quality and achieve thedesired effect

Because the Z-N method belongs to engineering settingmethod setting the PID parameters depends on experience

8 Mathematical Problems in Engineering

0 10 20 30 40 5081

82

83

84

85

86

87

88

89

90

Am

plitu

de

⟨P⟩

Time (s)

ZNGA

PSOGWO

Figure 10 Output response curves of pressure under differentalgorithms

value so the effect of PID control is poor The GA algorithmand PSO algorithm are intelligent method so control effectof PID controller whose parameters are optimized by thesetwo methods has been greatly improved relative to the Z-Nsetting method But because of their inherent search modeand the defects the search accuracy is not high enough thusresult of parameters setting is poorer than that of grey wolfoptimizer It can be known from searching way of GWOalgorithm above that the grey wolf optimizer is going tosearch solutions in the comprehensive evaluation by threewolves Therefore the GWO algorithm has a high searchprecision which can make it sure to search a better solutionvalue Thus the GWO algorithm increases the probability ofsearching a better group of PID parameters

5 Conclusions

In this paper a dynamic model of steam condenser and theclosed-loop control system are established on the basis of thelumped parameter model of the condenser For the pressureclosed-loop control system in order to improve the systemperformance the GWO algorithm is adopted to optimize thePI parametersThrough the simulation experiments and per-formance comparison of cooling water outlet temperaturecirculating water flow steam discharge heat and condenserpressure the introduction of the GWO algorithm makes thesteam condenser PI controller have better control effect Inorder to have a better control effect of steam condenser wecan try to improve the design of PID controller Since theresearch of grey wolf optimizer is just in its infancy theGWO algorithm should be improved to obtain better PIDparameters in the further study Other superior algorithmsshould be exploited for PID parameter optimization

Conflict of Interests

The authors declare that there is no conflict of interestsregarding the publication of this paper

Authorsrsquo Contribution

Shu-Xia Li participated in the data collection analysis algo-rithm simulation draft writing and critical revision of thispaper Jie-Sheng Wang participated in the concept designand interpretation and commented on the paper

Acknowledgments

This work is partially supported by National Key Technolo-gies R amp D Program of China (Grant no 2014BAF05B01)Project by National Natural Science Foundation of China(Grant no 21576127) Program for Liaoning Excellent Talentsin University (Grant no LR2014008) Project by LiaoningProvincial Natural Science Foundation of China (Grant no2014020177) Program for Research Special Foundation ofUniversity of Science and Technology of Liaoning (Grantno 2015TD04) and Opening Project of National FinancialSecurity and System Equipment Engineering Research Cen-ter (Grant no USTLKEC201401)

References

[1] T Tahri S A Abdul-Wahab A Bettahar M Douani H Al-Hinai and Y Al-Mulla ldquoSimulation of the condenser of theseawater greenhouse Part I theoretical developmentrdquo Journalof Thermal Analysis and Calorimetry vol 96 no 1 pp 35ndash422009

[2] P K Bansal and T C Chin ldquoModelling and optimisation ofwire-and-tube condenserrdquo International Journal of Refrigera-tion vol 26 no 5 pp 601ndash613 2003

[3] M R Malin ldquoModelling flow in an experimental marinecondenserrdquo International Communications in Heat and MassTransfer vol 24 no 5 pp 597ndash608 1997

[4] XDingWCai P Duan and J Yan ldquoHybrid dynamicmodelingfor two phase flow condensersrdquo Applied Thermal Engineeringvol 62 no 2 pp 830ndash837 2014

[5] WWangD Zeng J Liu YNiu andC Cui ldquoFeasibility analysisof changing turbine load in power plants using continuouscondenser pressure adjustmentrdquo Energy vol 64 pp 533ndash5402014

[6] Z Ma and S Wang ldquoOnline fault detection and robust controlof condenser cooling water systems in building central chillerplantsrdquo Energy and Buildings vol 43 no 1 pp 153ndash165 2011

[7] D Whitley ldquoAn executable model of a simple genetic algo-rithmrdquo Foundations of Genetic Algorithms vol 2 no 1519 pp45ndash62 2014

[8] J Kennedy and R Eberhart ldquoParticle swarm optimizationrdquoin Proceedings of the IEEE International Conference on NeuralNetworks pp 1942ndash1948 December 1995

[9] D Karaboga and B Basturk ldquoOn the performance of artificialbee colony (ABC) algorithmrdquo Applied Soft Computing vol 8no 1 pp 687ndash697 2008

Mathematical Problems in Engineering 9

[10] M Dorigo M Birattari and T Stutzle ldquoAnt colony optimiza-tionrdquo IEEE Computational Intelligence Magazine vol 1 no 4pp 28ndash39 2006

[11] X-S Yang and S Deb ldquoCuckoo search via Levy flightsrdquo in Pro-ceedings of the World Congress on Nature amp Biologically InspiredComputing (NABIC rsquo09) pp 210ndash214 IEEE Coimbatore IndiaDecember 2009

[12] S Mirjalili S M Mirjalili and A Lewis ldquoGrey wolf optimizerrdquoAdvances in Engineering Software vol 69 pp 46ndash61 2014

[13] B Mahdad and K Srairi ldquoBlackout risk prevention in a smartgrid based flexible optimal strategy using Grey Wolf-patternsearch algorithmsrdquo Energy Conversion and Management vol98 pp 411ndash429 2015

[14] X Song L Tang S Zhao et al ldquoGrey Wolf Optimizer forparameter estimation in surface wavesrdquo Soil Dynamics andEarthquake Engineering vol 75 pp 147ndash157 2015

[15] M H Sulaiman Z Mustaffa M R Mohamed and O AlimanldquoUsing the gray wolf optimizer for solving optimal reactivepower dispatch problemrdquo Applied Soft Computing vol 32 pp286ndash292 2015

[16] G M Komaki and V Kayvanfar ldquoGrey Wolf Optimizer algo-rithm for the two-stage assembly flow shop scheduling problemwith release timerdquo Journal of Computational Science vol 8 pp109ndash120 2015

[17] N Jayakumar S Subramanian S Ganesan and E BElanchezhian ldquoGrey wolf optimization for combined heatand power dispatch with cogeneration systemsrdquo InternationalJournal of Electrical Power amp Energy Systems vol 74 pp252ndash264 2016

[18] Y Sharma and L C Saikia ldquoAutomatic generation controlof a multi-area STmdashthermal power system using Grey Wolfoptimizer algorithm based classical controllersrdquo InternationalJournal of Electrical Power amp Energy Systems vol 73 pp 853ndash862 2015

Submit your manuscripts athttpwwwhindawicom

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

MathematicsJournal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Mathematical Problems in Engineering

Hindawi Publishing Corporationhttpwwwhindawicom

Differential EquationsInternational Journal of

Volume 2014

Applied MathematicsJournal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Probability and StatisticsHindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Journal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Mathematical PhysicsAdvances in

Complex AnalysisJournal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

OptimizationJournal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

CombinatoricsHindawi Publishing Corporationhttpwwwhindawicom Volume 2014

International Journal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Operations ResearchAdvances in

Journal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Function Spaces

Abstract and Applied AnalysisHindawi Publishing Corporationhttpwwwhindawicom Volume 2014

International Journal of Mathematics and Mathematical Sciences

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

The Scientific World JournalHindawi Publishing Corporation httpwwwhindawicom Volume 2014

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Algebra

Discrete Dynamics in Nature and Society

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Decision SciencesAdvances in

Discrete MathematicsJournal of

Hindawi Publishing Corporationhttpwwwhindawicom

Volume 2014 Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Stochastic AnalysisInternational Journal of

Page 5: Research Article Dynamic Modeling of Steam Condenser and ...downloads.hindawi.com/journals/mpe/2015/120975.pdf · Shell-and-tube condenser is a heat exchanger for cooling steam with

Mathematical Problems in Engineering 5

Alpha

Beta

Delta Omega

Move

D120572

D120573

D120575

Figure 4 Sketch map of position update of the wolves

120572 120573 and 120575 and then the others are regarded as theΩ wolvesThe positions of 120572 120573 and 120575 are used to update their positionsThe following mathematical formulae are used to adjust theposition of Ω wolf again and the position update schematicgraph is shown in Figures 4 and 5

997888rarr119863120572=100381610038161003816100381610038161003816

997888rarr1198621sdot997888rarr119883120572minus

100381610038161003816100381610038161003816

997888rarr119863120573=100381610038161003816100381610038161003816

997888rarr1198622sdot997888rarr119883120573minus

100381610038161003816100381610038161003816

997888rarr119863120575=100381610038161003816100381610038161003816

997888rarr1198623sdot997888rarr119883120575minus

100381610038161003816100381610038161003816

(17)

where 997888rarr119883120572 997888rarr119883120573 and 997888rarr119883

120575are the position of the wolves 120572 120573

and 120575 respectively 997888rarr1198621 997888rarr1198622and 997888rarr119862

3are random vectors and

represents the position of the current solution Equations (17)are used to calculate the approximate distance between thecurrent position and 120572 120573 and 120575 respectively After definingthe distance between them the final position of the currentsolution is calculated by the following

997888rarr1198831=997888rarr119883120572minus997888rarr1198601sdot (997888rarr119863120572) (18)

997888rarr1198832=997888rarr119883120573minus997888rarr1198602sdot (997888rarr119863120573) (19)

997888rarr1198833=997888rarr119883120575minus997888rarr1198603sdot (997888rarr119863120575) (20)

(119905 + 1) =

997888rarr1198831+997888rarr1198832+997888rarr1198833

3 (21)

where 997888rarr1198601 997888rarr1198602 and 997888rarr119860

3are random vectors and 119905 represents

the number of iterationsSeen from the above equations (17) define the step size

of the wolf Ω tending to the wolves 120572 120573 and 120575 Equations(19)ndash(21) define the final position of Ω wolf

Unexplored

Unexplored

Explored

Explored

If |A|lt 1

If |A|ge 1

Figure 5 Exploration and development of wolves

It can be seen from Figure 4 that the random and adaptivevectors and can be used to balance the explorationand development capabilities of the GWO algorithm When|| gt 1 the wolf has detection ability On the other handwhen the value of vector is greater than 1 it can alsopromote the enhancement of the detection ability of the wolfIn contrast when || lt 1 and 119862 lt 1 the wolf rsquos informationmining capacity is enhanced In order to enhance the abilityof the wolf with the increase of the iteration number isdecreased linearly However is randomly generated in thewhole optimization process which can make the detectionand exploitation ability of the wolf to reach equilibrium at anystage especially in the final stage of the iteration and preventthe algorithm from falling into local optimum

The procedure of the GWO algorithm is described asfollows

Step 1 Initialize the wolves Randomly initialize the positionof the wolves119883

119894(119894 = 1 2 119899) and parameters 119886 119860 and 119862

Step 2 Calculate the fitness of eachwolf and choose the threewolves with best fitness as wolves 120572 120573 and 120575

Step 3 Update positions Based on (17)ndash(21) update thepositions of the other wolves that is to say the positions oftheΩ wolves

Step 4 Update parameters 119886 119860 and 119862

Step 5 Judge whether to meet the termination conditions ornot If satisfied the position of 120572 wolf and the fitness valueare the optimal output If the termination condition is notsatisfied return to Step 2

4 Parameter Optimization of PI ControllerBased on GWO Algorithm

41 Dynamic Model of Steam Condenser Based on Mat-labSimulink Simulation Software The establishment of the

6 Mathematical Problems in Engineering

dynamic mathematical model of the condenser is based onthe following assumption that the total amount of condensa-tion the circulating water flow and the condenser volume arecertain So it is set up based on the dynamic heat balance andmass balance of the condenser water

411 Dynamic Heat Balance In the dynamic heat balance itis assumed that the total amount of condensation is certainand that the input steam and the output condensate aresaturated Therefore the heat from steam to the circulatingwater and the steam potential heat are equal So the steamreleased heat can be approximated calculated by the follow-ing equations

119876 asymp 119880119860Δ119905119898

Δ119905119898=

119879 minus 119879cwln ((119879

119904minus 119879cw) (119879119904 minus 119879))

(22)

The heat transfer coefficient 119880 and the heat transfer area119860 can be replaced by the following exponential equationapproximately

1

119880119860= 1205721119865cwminus08

+ 1205722 (23)

where 1205721and 120572

2are constants

When 119865cwrarrinfin 1205722 is determined by 119880119860 In this case 119880119860is determined by the heat transfer ratio between the steamand the tube wall and the thermal resistance of the tube wallThus by assuming the outlet temperature of the circulatingwater 120572

2can be determined Based on the above assumptions

and equations the dynamic heat balance equation of thecondenser is described as follows

119889119879

119889119905=119865cw119872cw

(119879cw minus 119879) +119876

119872cw119862119901 (24)

412 Mass Balance Themass balance of steam and conden-sate is based on the assumption that the space 119881 is constantand the volume of the steam and air is constant That is tosay in order to maintain the vapor condensation level ofthe condenser (certain vacuum degree) the output flow ofcondensatewater needs to be controlled in a certain range Soin order to simplify the model we assume that the inlet andoutlet of the condensate are saturatedTherefore the ideal gasmodel equation is expressed as

119889119875

119889119905=119877119879119888

119881(119865119904minus 119865119888) (25)

where 119865119904is the steam flow (kgs) and 119865

119888is the condensate

water flow (kgs)Among them the condensationwater temperature119879

119888and

the condenser pressure 119875 have a unique relationship In orderto simplify the model it is approximated by the followinglinear relationship equation

119879119888= 120572119875 + 120573 (26)

The steam condenser model given above has five equa-tions among which two are dynamic equations Here there

Table 1 Parameters of steam condenser

Parameter Parameter value Unit119877 0461526 kJkgK119881 3 m3

120582 226565 kJkg119880119860 356972 kWK119872cw 6500 kg119862119901

42 kJ(kgK)120572 03162 KkPa120573 680958 ∘C1205721

87292e minus 21205722

73787e minus 4

Table 2 Variables of steam condenser

Variable Meaning Variable value Unit119865119904

Steam flow 4 kgs119865119888

Condensate water flow 4 kgs119865cw Cooling water flow 1078881 kgs119875 Condenser pressure 90 kPa119879 Circulating water outlet temperature 80 ∘C119879cw Circulating water inlet temperature 60 ∘C119879119888

Saturated water temperature 965538 ∘C119876 Steam heat 90626 kW

are eight variables (119865119904 119865119888 119865cw 119875 119879 119879cw 119879119888 and 119876) and ten

parameters (119877119881120582119880119860119872cw1198621199011205721205731205721 and1205722)The valuesof ten parameters are shown in Table 1 where 120572

1and 120572

2are

determined under 119879 = 90∘C (119865cw rarr infin) The values of theeight variables are shown in Table 2 under the assumptionthat the system is stable

Based on the above model equations and the softwareMatlabSimulink a simulation model of PI controller forcondenser pressure closed-loop control system is establishedas shown in Figure 6 which includes a first-order delay unitused to represent the actuator with a time constant 120591 = 10 (s)and a lag unit caused by the pressure sensor with the timeconstant 120591 = 5 (s)

42 Encoding and Fitness Function Because the design ofthe PID controller is actually a multidimensional functionoptimization problem the GWO algorithm adopts the realnumber coding So for the parameters optimization of the PIcontroller each wolf can be directly coded as (119870

119901 119870119894)

119883 = 119870119901 119870119894 (27)

The control parameter optimization is designed to makethe control error tend to zero and has a faster response speedand smaller overshoot So the evaluation of the performanceof each set of control parameters is good or bad the integralof the product of absolute error and time is selected as thefitness function

ITAE = intinfin

0

119905 |119890 (119905)| 119889119905 (28)

Mathematical Problems in Engineering 7

Click here to tune the PID controller

60

Reaction curvePID tuning

Steam condenserScope

Pressure setpoint

PID

PID controller

Input step test

4

⟨Fcw⟩⟨T⟩

⟨Q⟩⟨P⟩Tcw

Tcw

Fs

Fs y =

Fcw

+++ minus

Figure 6 MatlabSimulink simulation model of PI controller forcondenser pressure closed-loop control system

0 10 20 30 40 50785

79

795

80

Time (s)

Am

plitu

de

⟨T⟩

ZNGA

PSOGWO

Figure 7 Output response curves of outlet temperature of coolingwater under different algorithms

Table 3 Parameters of PI controller

PID parameters ZN GA PSO GWO119870119901

108 853 707 447119870119894

422 091 104 089

43 Simulation Experiments and Results Analysis of PI Con-troller On the basis of the above established model of steamcondenser the GWO algorithm is adopted to optimize theparameters of the adopted PI controller The self-tuningperformances are compared with the Z-N engineering tun-ing method genetic algorithm (GA) and particle swarmoptimization (PSO) algorithm Respectively run GWO PSOand GA algorithm 30 times and then select the best PIDparameters of each algorithm The output response curvesof cooling water outlet temperature circulating water flowsteam discharge heat and condenser pressure are shown inFigures 7ndash10 The parameters of PI controllers are listed inTable 3

0 10 20 30 40 5095

100

105

110

115

120

125

130

135

140

145

Am

plitu

de

Time (s)

ZNGA

PSOGWO

⟨Fcw⟩

Figure 8 Output response curves of circulating water flow underdifferent algorithms

0 10 20 30 40 508200

8400

8600

8800

9000

9200

9400

9600

9800

10000

10200

Am

plitu

de

⟨Q⟩

Time (s)

ZNGA

PSOGWO

Figure 9 Output response curves of steam heat output underdifferent algorithms

As seen from the above simulation results the PI con-troller under the optimization by the proposed GWO algo-rithm has the best control performance that is to say smallovershoot and short rise time and adjustment time The Z-Nengineering self-tuning method has the worst performancewhere the overshoot is the largest and the rise time andadjustment time are the longest The GWO algorithm caneffectively improve the system control quality and achieve thedesired effect

Because the Z-N method belongs to engineering settingmethod setting the PID parameters depends on experience

8 Mathematical Problems in Engineering

0 10 20 30 40 5081

82

83

84

85

86

87

88

89

90

Am

plitu

de

⟨P⟩

Time (s)

ZNGA

PSOGWO

Figure 10 Output response curves of pressure under differentalgorithms

value so the effect of PID control is poor The GA algorithmand PSO algorithm are intelligent method so control effectof PID controller whose parameters are optimized by thesetwo methods has been greatly improved relative to the Z-Nsetting method But because of their inherent search modeand the defects the search accuracy is not high enough thusresult of parameters setting is poorer than that of grey wolfoptimizer It can be known from searching way of GWOalgorithm above that the grey wolf optimizer is going tosearch solutions in the comprehensive evaluation by threewolves Therefore the GWO algorithm has a high searchprecision which can make it sure to search a better solutionvalue Thus the GWO algorithm increases the probability ofsearching a better group of PID parameters

5 Conclusions

In this paper a dynamic model of steam condenser and theclosed-loop control system are established on the basis of thelumped parameter model of the condenser For the pressureclosed-loop control system in order to improve the systemperformance the GWO algorithm is adopted to optimize thePI parametersThrough the simulation experiments and per-formance comparison of cooling water outlet temperaturecirculating water flow steam discharge heat and condenserpressure the introduction of the GWO algorithm makes thesteam condenser PI controller have better control effect Inorder to have a better control effect of steam condenser wecan try to improve the design of PID controller Since theresearch of grey wolf optimizer is just in its infancy theGWO algorithm should be improved to obtain better PIDparameters in the further study Other superior algorithmsshould be exploited for PID parameter optimization

Conflict of Interests

The authors declare that there is no conflict of interestsregarding the publication of this paper

Authorsrsquo Contribution

Shu-Xia Li participated in the data collection analysis algo-rithm simulation draft writing and critical revision of thispaper Jie-Sheng Wang participated in the concept designand interpretation and commented on the paper

Acknowledgments

This work is partially supported by National Key Technolo-gies R amp D Program of China (Grant no 2014BAF05B01)Project by National Natural Science Foundation of China(Grant no 21576127) Program for Liaoning Excellent Talentsin University (Grant no LR2014008) Project by LiaoningProvincial Natural Science Foundation of China (Grant no2014020177) Program for Research Special Foundation ofUniversity of Science and Technology of Liaoning (Grantno 2015TD04) and Opening Project of National FinancialSecurity and System Equipment Engineering Research Cen-ter (Grant no USTLKEC201401)

References

[1] T Tahri S A Abdul-Wahab A Bettahar M Douani H Al-Hinai and Y Al-Mulla ldquoSimulation of the condenser of theseawater greenhouse Part I theoretical developmentrdquo Journalof Thermal Analysis and Calorimetry vol 96 no 1 pp 35ndash422009

[2] P K Bansal and T C Chin ldquoModelling and optimisation ofwire-and-tube condenserrdquo International Journal of Refrigera-tion vol 26 no 5 pp 601ndash613 2003

[3] M R Malin ldquoModelling flow in an experimental marinecondenserrdquo International Communications in Heat and MassTransfer vol 24 no 5 pp 597ndash608 1997

[4] XDingWCai P Duan and J Yan ldquoHybrid dynamicmodelingfor two phase flow condensersrdquo Applied Thermal Engineeringvol 62 no 2 pp 830ndash837 2014

[5] WWangD Zeng J Liu YNiu andC Cui ldquoFeasibility analysisof changing turbine load in power plants using continuouscondenser pressure adjustmentrdquo Energy vol 64 pp 533ndash5402014

[6] Z Ma and S Wang ldquoOnline fault detection and robust controlof condenser cooling water systems in building central chillerplantsrdquo Energy and Buildings vol 43 no 1 pp 153ndash165 2011

[7] D Whitley ldquoAn executable model of a simple genetic algo-rithmrdquo Foundations of Genetic Algorithms vol 2 no 1519 pp45ndash62 2014

[8] J Kennedy and R Eberhart ldquoParticle swarm optimizationrdquoin Proceedings of the IEEE International Conference on NeuralNetworks pp 1942ndash1948 December 1995

[9] D Karaboga and B Basturk ldquoOn the performance of artificialbee colony (ABC) algorithmrdquo Applied Soft Computing vol 8no 1 pp 687ndash697 2008

Mathematical Problems in Engineering 9

[10] M Dorigo M Birattari and T Stutzle ldquoAnt colony optimiza-tionrdquo IEEE Computational Intelligence Magazine vol 1 no 4pp 28ndash39 2006

[11] X-S Yang and S Deb ldquoCuckoo search via Levy flightsrdquo in Pro-ceedings of the World Congress on Nature amp Biologically InspiredComputing (NABIC rsquo09) pp 210ndash214 IEEE Coimbatore IndiaDecember 2009

[12] S Mirjalili S M Mirjalili and A Lewis ldquoGrey wolf optimizerrdquoAdvances in Engineering Software vol 69 pp 46ndash61 2014

[13] B Mahdad and K Srairi ldquoBlackout risk prevention in a smartgrid based flexible optimal strategy using Grey Wolf-patternsearch algorithmsrdquo Energy Conversion and Management vol98 pp 411ndash429 2015

[14] X Song L Tang S Zhao et al ldquoGrey Wolf Optimizer forparameter estimation in surface wavesrdquo Soil Dynamics andEarthquake Engineering vol 75 pp 147ndash157 2015

[15] M H Sulaiman Z Mustaffa M R Mohamed and O AlimanldquoUsing the gray wolf optimizer for solving optimal reactivepower dispatch problemrdquo Applied Soft Computing vol 32 pp286ndash292 2015

[16] G M Komaki and V Kayvanfar ldquoGrey Wolf Optimizer algo-rithm for the two-stage assembly flow shop scheduling problemwith release timerdquo Journal of Computational Science vol 8 pp109ndash120 2015

[17] N Jayakumar S Subramanian S Ganesan and E BElanchezhian ldquoGrey wolf optimization for combined heatand power dispatch with cogeneration systemsrdquo InternationalJournal of Electrical Power amp Energy Systems vol 74 pp252ndash264 2016

[18] Y Sharma and L C Saikia ldquoAutomatic generation controlof a multi-area STmdashthermal power system using Grey Wolfoptimizer algorithm based classical controllersrdquo InternationalJournal of Electrical Power amp Energy Systems vol 73 pp 853ndash862 2015

Submit your manuscripts athttpwwwhindawicom

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

MathematicsJournal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Mathematical Problems in Engineering

Hindawi Publishing Corporationhttpwwwhindawicom

Differential EquationsInternational Journal of

Volume 2014

Applied MathematicsJournal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Probability and StatisticsHindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Journal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Mathematical PhysicsAdvances in

Complex AnalysisJournal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

OptimizationJournal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

CombinatoricsHindawi Publishing Corporationhttpwwwhindawicom Volume 2014

International Journal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Operations ResearchAdvances in

Journal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Function Spaces

Abstract and Applied AnalysisHindawi Publishing Corporationhttpwwwhindawicom Volume 2014

International Journal of Mathematics and Mathematical Sciences

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

The Scientific World JournalHindawi Publishing Corporation httpwwwhindawicom Volume 2014

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Algebra

Discrete Dynamics in Nature and Society

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Decision SciencesAdvances in

Discrete MathematicsJournal of

Hindawi Publishing Corporationhttpwwwhindawicom

Volume 2014 Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Stochastic AnalysisInternational Journal of

Page 6: Research Article Dynamic Modeling of Steam Condenser and ...downloads.hindawi.com/journals/mpe/2015/120975.pdf · Shell-and-tube condenser is a heat exchanger for cooling steam with

6 Mathematical Problems in Engineering

dynamic mathematical model of the condenser is based onthe following assumption that the total amount of condensa-tion the circulating water flow and the condenser volume arecertain So it is set up based on the dynamic heat balance andmass balance of the condenser water

411 Dynamic Heat Balance In the dynamic heat balance itis assumed that the total amount of condensation is certainand that the input steam and the output condensate aresaturated Therefore the heat from steam to the circulatingwater and the steam potential heat are equal So the steamreleased heat can be approximated calculated by the follow-ing equations

119876 asymp 119880119860Δ119905119898

Δ119905119898=

119879 minus 119879cwln ((119879

119904minus 119879cw) (119879119904 minus 119879))

(22)

The heat transfer coefficient 119880 and the heat transfer area119860 can be replaced by the following exponential equationapproximately

1

119880119860= 1205721119865cwminus08

+ 1205722 (23)

where 1205721and 120572

2are constants

When 119865cwrarrinfin 1205722 is determined by 119880119860 In this case 119880119860is determined by the heat transfer ratio between the steamand the tube wall and the thermal resistance of the tube wallThus by assuming the outlet temperature of the circulatingwater 120572

2can be determined Based on the above assumptions

and equations the dynamic heat balance equation of thecondenser is described as follows

119889119879

119889119905=119865cw119872cw

(119879cw minus 119879) +119876

119872cw119862119901 (24)

412 Mass Balance Themass balance of steam and conden-sate is based on the assumption that the space 119881 is constantand the volume of the steam and air is constant That is tosay in order to maintain the vapor condensation level ofthe condenser (certain vacuum degree) the output flow ofcondensatewater needs to be controlled in a certain range Soin order to simplify the model we assume that the inlet andoutlet of the condensate are saturatedTherefore the ideal gasmodel equation is expressed as

119889119875

119889119905=119877119879119888

119881(119865119904minus 119865119888) (25)

where 119865119904is the steam flow (kgs) and 119865

119888is the condensate

water flow (kgs)Among them the condensationwater temperature119879

119888and

the condenser pressure 119875 have a unique relationship In orderto simplify the model it is approximated by the followinglinear relationship equation

119879119888= 120572119875 + 120573 (26)

The steam condenser model given above has five equa-tions among which two are dynamic equations Here there

Table 1 Parameters of steam condenser

Parameter Parameter value Unit119877 0461526 kJkgK119881 3 m3

120582 226565 kJkg119880119860 356972 kWK119872cw 6500 kg119862119901

42 kJ(kgK)120572 03162 KkPa120573 680958 ∘C1205721

87292e minus 21205722

73787e minus 4

Table 2 Variables of steam condenser

Variable Meaning Variable value Unit119865119904

Steam flow 4 kgs119865119888

Condensate water flow 4 kgs119865cw Cooling water flow 1078881 kgs119875 Condenser pressure 90 kPa119879 Circulating water outlet temperature 80 ∘C119879cw Circulating water inlet temperature 60 ∘C119879119888

Saturated water temperature 965538 ∘C119876 Steam heat 90626 kW

are eight variables (119865119904 119865119888 119865cw 119875 119879 119879cw 119879119888 and 119876) and ten

parameters (119877119881120582119880119860119872cw1198621199011205721205731205721 and1205722)The valuesof ten parameters are shown in Table 1 where 120572

1and 120572

2are

determined under 119879 = 90∘C (119865cw rarr infin) The values of theeight variables are shown in Table 2 under the assumptionthat the system is stable

Based on the above model equations and the softwareMatlabSimulink a simulation model of PI controller forcondenser pressure closed-loop control system is establishedas shown in Figure 6 which includes a first-order delay unitused to represent the actuator with a time constant 120591 = 10 (s)and a lag unit caused by the pressure sensor with the timeconstant 120591 = 5 (s)

42 Encoding and Fitness Function Because the design ofthe PID controller is actually a multidimensional functionoptimization problem the GWO algorithm adopts the realnumber coding So for the parameters optimization of the PIcontroller each wolf can be directly coded as (119870

119901 119870119894)

119883 = 119870119901 119870119894 (27)

The control parameter optimization is designed to makethe control error tend to zero and has a faster response speedand smaller overshoot So the evaluation of the performanceof each set of control parameters is good or bad the integralof the product of absolute error and time is selected as thefitness function

ITAE = intinfin

0

119905 |119890 (119905)| 119889119905 (28)

Mathematical Problems in Engineering 7

Click here to tune the PID controller

60

Reaction curvePID tuning

Steam condenserScope

Pressure setpoint

PID

PID controller

Input step test

4

⟨Fcw⟩⟨T⟩

⟨Q⟩⟨P⟩Tcw

Tcw

Fs

Fs y =

Fcw

+++ minus

Figure 6 MatlabSimulink simulation model of PI controller forcondenser pressure closed-loop control system

0 10 20 30 40 50785

79

795

80

Time (s)

Am

plitu

de

⟨T⟩

ZNGA

PSOGWO

Figure 7 Output response curves of outlet temperature of coolingwater under different algorithms

Table 3 Parameters of PI controller

PID parameters ZN GA PSO GWO119870119901

108 853 707 447119870119894

422 091 104 089

43 Simulation Experiments and Results Analysis of PI Con-troller On the basis of the above established model of steamcondenser the GWO algorithm is adopted to optimize theparameters of the adopted PI controller The self-tuningperformances are compared with the Z-N engineering tun-ing method genetic algorithm (GA) and particle swarmoptimization (PSO) algorithm Respectively run GWO PSOand GA algorithm 30 times and then select the best PIDparameters of each algorithm The output response curvesof cooling water outlet temperature circulating water flowsteam discharge heat and condenser pressure are shown inFigures 7ndash10 The parameters of PI controllers are listed inTable 3

0 10 20 30 40 5095

100

105

110

115

120

125

130

135

140

145

Am

plitu

de

Time (s)

ZNGA

PSOGWO

⟨Fcw⟩

Figure 8 Output response curves of circulating water flow underdifferent algorithms

0 10 20 30 40 508200

8400

8600

8800

9000

9200

9400

9600

9800

10000

10200

Am

plitu

de

⟨Q⟩

Time (s)

ZNGA

PSOGWO

Figure 9 Output response curves of steam heat output underdifferent algorithms

As seen from the above simulation results the PI con-troller under the optimization by the proposed GWO algo-rithm has the best control performance that is to say smallovershoot and short rise time and adjustment time The Z-Nengineering self-tuning method has the worst performancewhere the overshoot is the largest and the rise time andadjustment time are the longest The GWO algorithm caneffectively improve the system control quality and achieve thedesired effect

Because the Z-N method belongs to engineering settingmethod setting the PID parameters depends on experience

8 Mathematical Problems in Engineering

0 10 20 30 40 5081

82

83

84

85

86

87

88

89

90

Am

plitu

de

⟨P⟩

Time (s)

ZNGA

PSOGWO

Figure 10 Output response curves of pressure under differentalgorithms

value so the effect of PID control is poor The GA algorithmand PSO algorithm are intelligent method so control effectof PID controller whose parameters are optimized by thesetwo methods has been greatly improved relative to the Z-Nsetting method But because of their inherent search modeand the defects the search accuracy is not high enough thusresult of parameters setting is poorer than that of grey wolfoptimizer It can be known from searching way of GWOalgorithm above that the grey wolf optimizer is going tosearch solutions in the comprehensive evaluation by threewolves Therefore the GWO algorithm has a high searchprecision which can make it sure to search a better solutionvalue Thus the GWO algorithm increases the probability ofsearching a better group of PID parameters

5 Conclusions

In this paper a dynamic model of steam condenser and theclosed-loop control system are established on the basis of thelumped parameter model of the condenser For the pressureclosed-loop control system in order to improve the systemperformance the GWO algorithm is adopted to optimize thePI parametersThrough the simulation experiments and per-formance comparison of cooling water outlet temperaturecirculating water flow steam discharge heat and condenserpressure the introduction of the GWO algorithm makes thesteam condenser PI controller have better control effect Inorder to have a better control effect of steam condenser wecan try to improve the design of PID controller Since theresearch of grey wolf optimizer is just in its infancy theGWO algorithm should be improved to obtain better PIDparameters in the further study Other superior algorithmsshould be exploited for PID parameter optimization

Conflict of Interests

The authors declare that there is no conflict of interestsregarding the publication of this paper

Authorsrsquo Contribution

Shu-Xia Li participated in the data collection analysis algo-rithm simulation draft writing and critical revision of thispaper Jie-Sheng Wang participated in the concept designand interpretation and commented on the paper

Acknowledgments

This work is partially supported by National Key Technolo-gies R amp D Program of China (Grant no 2014BAF05B01)Project by National Natural Science Foundation of China(Grant no 21576127) Program for Liaoning Excellent Talentsin University (Grant no LR2014008) Project by LiaoningProvincial Natural Science Foundation of China (Grant no2014020177) Program for Research Special Foundation ofUniversity of Science and Technology of Liaoning (Grantno 2015TD04) and Opening Project of National FinancialSecurity and System Equipment Engineering Research Cen-ter (Grant no USTLKEC201401)

References

[1] T Tahri S A Abdul-Wahab A Bettahar M Douani H Al-Hinai and Y Al-Mulla ldquoSimulation of the condenser of theseawater greenhouse Part I theoretical developmentrdquo Journalof Thermal Analysis and Calorimetry vol 96 no 1 pp 35ndash422009

[2] P K Bansal and T C Chin ldquoModelling and optimisation ofwire-and-tube condenserrdquo International Journal of Refrigera-tion vol 26 no 5 pp 601ndash613 2003

[3] M R Malin ldquoModelling flow in an experimental marinecondenserrdquo International Communications in Heat and MassTransfer vol 24 no 5 pp 597ndash608 1997

[4] XDingWCai P Duan and J Yan ldquoHybrid dynamicmodelingfor two phase flow condensersrdquo Applied Thermal Engineeringvol 62 no 2 pp 830ndash837 2014

[5] WWangD Zeng J Liu YNiu andC Cui ldquoFeasibility analysisof changing turbine load in power plants using continuouscondenser pressure adjustmentrdquo Energy vol 64 pp 533ndash5402014

[6] Z Ma and S Wang ldquoOnline fault detection and robust controlof condenser cooling water systems in building central chillerplantsrdquo Energy and Buildings vol 43 no 1 pp 153ndash165 2011

[7] D Whitley ldquoAn executable model of a simple genetic algo-rithmrdquo Foundations of Genetic Algorithms vol 2 no 1519 pp45ndash62 2014

[8] J Kennedy and R Eberhart ldquoParticle swarm optimizationrdquoin Proceedings of the IEEE International Conference on NeuralNetworks pp 1942ndash1948 December 1995

[9] D Karaboga and B Basturk ldquoOn the performance of artificialbee colony (ABC) algorithmrdquo Applied Soft Computing vol 8no 1 pp 687ndash697 2008

Mathematical Problems in Engineering 9

[10] M Dorigo M Birattari and T Stutzle ldquoAnt colony optimiza-tionrdquo IEEE Computational Intelligence Magazine vol 1 no 4pp 28ndash39 2006

[11] X-S Yang and S Deb ldquoCuckoo search via Levy flightsrdquo in Pro-ceedings of the World Congress on Nature amp Biologically InspiredComputing (NABIC rsquo09) pp 210ndash214 IEEE Coimbatore IndiaDecember 2009

[12] S Mirjalili S M Mirjalili and A Lewis ldquoGrey wolf optimizerrdquoAdvances in Engineering Software vol 69 pp 46ndash61 2014

[13] B Mahdad and K Srairi ldquoBlackout risk prevention in a smartgrid based flexible optimal strategy using Grey Wolf-patternsearch algorithmsrdquo Energy Conversion and Management vol98 pp 411ndash429 2015

[14] X Song L Tang S Zhao et al ldquoGrey Wolf Optimizer forparameter estimation in surface wavesrdquo Soil Dynamics andEarthquake Engineering vol 75 pp 147ndash157 2015

[15] M H Sulaiman Z Mustaffa M R Mohamed and O AlimanldquoUsing the gray wolf optimizer for solving optimal reactivepower dispatch problemrdquo Applied Soft Computing vol 32 pp286ndash292 2015

[16] G M Komaki and V Kayvanfar ldquoGrey Wolf Optimizer algo-rithm for the two-stage assembly flow shop scheduling problemwith release timerdquo Journal of Computational Science vol 8 pp109ndash120 2015

[17] N Jayakumar S Subramanian S Ganesan and E BElanchezhian ldquoGrey wolf optimization for combined heatand power dispatch with cogeneration systemsrdquo InternationalJournal of Electrical Power amp Energy Systems vol 74 pp252ndash264 2016

[18] Y Sharma and L C Saikia ldquoAutomatic generation controlof a multi-area STmdashthermal power system using Grey Wolfoptimizer algorithm based classical controllersrdquo InternationalJournal of Electrical Power amp Energy Systems vol 73 pp 853ndash862 2015

Submit your manuscripts athttpwwwhindawicom

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

MathematicsJournal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Mathematical Problems in Engineering

Hindawi Publishing Corporationhttpwwwhindawicom

Differential EquationsInternational Journal of

Volume 2014

Applied MathematicsJournal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Probability and StatisticsHindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Journal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Mathematical PhysicsAdvances in

Complex AnalysisJournal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

OptimizationJournal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

CombinatoricsHindawi Publishing Corporationhttpwwwhindawicom Volume 2014

International Journal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Operations ResearchAdvances in

Journal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Function Spaces

Abstract and Applied AnalysisHindawi Publishing Corporationhttpwwwhindawicom Volume 2014

International Journal of Mathematics and Mathematical Sciences

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

The Scientific World JournalHindawi Publishing Corporation httpwwwhindawicom Volume 2014

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Algebra

Discrete Dynamics in Nature and Society

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Decision SciencesAdvances in

Discrete MathematicsJournal of

Hindawi Publishing Corporationhttpwwwhindawicom

Volume 2014 Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Stochastic AnalysisInternational Journal of

Page 7: Research Article Dynamic Modeling of Steam Condenser and ...downloads.hindawi.com/journals/mpe/2015/120975.pdf · Shell-and-tube condenser is a heat exchanger for cooling steam with

Mathematical Problems in Engineering 7

Click here to tune the PID controller

60

Reaction curvePID tuning

Steam condenserScope

Pressure setpoint

PID

PID controller

Input step test

4

⟨Fcw⟩⟨T⟩

⟨Q⟩⟨P⟩Tcw

Tcw

Fs

Fs y =

Fcw

+++ minus

Figure 6 MatlabSimulink simulation model of PI controller forcondenser pressure closed-loop control system

0 10 20 30 40 50785

79

795

80

Time (s)

Am

plitu

de

⟨T⟩

ZNGA

PSOGWO

Figure 7 Output response curves of outlet temperature of coolingwater under different algorithms

Table 3 Parameters of PI controller

PID parameters ZN GA PSO GWO119870119901

108 853 707 447119870119894

422 091 104 089

43 Simulation Experiments and Results Analysis of PI Con-troller On the basis of the above established model of steamcondenser the GWO algorithm is adopted to optimize theparameters of the adopted PI controller The self-tuningperformances are compared with the Z-N engineering tun-ing method genetic algorithm (GA) and particle swarmoptimization (PSO) algorithm Respectively run GWO PSOand GA algorithm 30 times and then select the best PIDparameters of each algorithm The output response curvesof cooling water outlet temperature circulating water flowsteam discharge heat and condenser pressure are shown inFigures 7ndash10 The parameters of PI controllers are listed inTable 3

0 10 20 30 40 5095

100

105

110

115

120

125

130

135

140

145

Am

plitu

de

Time (s)

ZNGA

PSOGWO

⟨Fcw⟩

Figure 8 Output response curves of circulating water flow underdifferent algorithms

0 10 20 30 40 508200

8400

8600

8800

9000

9200

9400

9600

9800

10000

10200

Am

plitu

de

⟨Q⟩

Time (s)

ZNGA

PSOGWO

Figure 9 Output response curves of steam heat output underdifferent algorithms

As seen from the above simulation results the PI con-troller under the optimization by the proposed GWO algo-rithm has the best control performance that is to say smallovershoot and short rise time and adjustment time The Z-Nengineering self-tuning method has the worst performancewhere the overshoot is the largest and the rise time andadjustment time are the longest The GWO algorithm caneffectively improve the system control quality and achieve thedesired effect

Because the Z-N method belongs to engineering settingmethod setting the PID parameters depends on experience

8 Mathematical Problems in Engineering

0 10 20 30 40 5081

82

83

84

85

86

87

88

89

90

Am

plitu

de

⟨P⟩

Time (s)

ZNGA

PSOGWO

Figure 10 Output response curves of pressure under differentalgorithms

value so the effect of PID control is poor The GA algorithmand PSO algorithm are intelligent method so control effectof PID controller whose parameters are optimized by thesetwo methods has been greatly improved relative to the Z-Nsetting method But because of their inherent search modeand the defects the search accuracy is not high enough thusresult of parameters setting is poorer than that of grey wolfoptimizer It can be known from searching way of GWOalgorithm above that the grey wolf optimizer is going tosearch solutions in the comprehensive evaluation by threewolves Therefore the GWO algorithm has a high searchprecision which can make it sure to search a better solutionvalue Thus the GWO algorithm increases the probability ofsearching a better group of PID parameters

5 Conclusions

In this paper a dynamic model of steam condenser and theclosed-loop control system are established on the basis of thelumped parameter model of the condenser For the pressureclosed-loop control system in order to improve the systemperformance the GWO algorithm is adopted to optimize thePI parametersThrough the simulation experiments and per-formance comparison of cooling water outlet temperaturecirculating water flow steam discharge heat and condenserpressure the introduction of the GWO algorithm makes thesteam condenser PI controller have better control effect Inorder to have a better control effect of steam condenser wecan try to improve the design of PID controller Since theresearch of grey wolf optimizer is just in its infancy theGWO algorithm should be improved to obtain better PIDparameters in the further study Other superior algorithmsshould be exploited for PID parameter optimization

Conflict of Interests

The authors declare that there is no conflict of interestsregarding the publication of this paper

Authorsrsquo Contribution

Shu-Xia Li participated in the data collection analysis algo-rithm simulation draft writing and critical revision of thispaper Jie-Sheng Wang participated in the concept designand interpretation and commented on the paper

Acknowledgments

This work is partially supported by National Key Technolo-gies R amp D Program of China (Grant no 2014BAF05B01)Project by National Natural Science Foundation of China(Grant no 21576127) Program for Liaoning Excellent Talentsin University (Grant no LR2014008) Project by LiaoningProvincial Natural Science Foundation of China (Grant no2014020177) Program for Research Special Foundation ofUniversity of Science and Technology of Liaoning (Grantno 2015TD04) and Opening Project of National FinancialSecurity and System Equipment Engineering Research Cen-ter (Grant no USTLKEC201401)

References

[1] T Tahri S A Abdul-Wahab A Bettahar M Douani H Al-Hinai and Y Al-Mulla ldquoSimulation of the condenser of theseawater greenhouse Part I theoretical developmentrdquo Journalof Thermal Analysis and Calorimetry vol 96 no 1 pp 35ndash422009

[2] P K Bansal and T C Chin ldquoModelling and optimisation ofwire-and-tube condenserrdquo International Journal of Refrigera-tion vol 26 no 5 pp 601ndash613 2003

[3] M R Malin ldquoModelling flow in an experimental marinecondenserrdquo International Communications in Heat and MassTransfer vol 24 no 5 pp 597ndash608 1997

[4] XDingWCai P Duan and J Yan ldquoHybrid dynamicmodelingfor two phase flow condensersrdquo Applied Thermal Engineeringvol 62 no 2 pp 830ndash837 2014

[5] WWangD Zeng J Liu YNiu andC Cui ldquoFeasibility analysisof changing turbine load in power plants using continuouscondenser pressure adjustmentrdquo Energy vol 64 pp 533ndash5402014

[6] Z Ma and S Wang ldquoOnline fault detection and robust controlof condenser cooling water systems in building central chillerplantsrdquo Energy and Buildings vol 43 no 1 pp 153ndash165 2011

[7] D Whitley ldquoAn executable model of a simple genetic algo-rithmrdquo Foundations of Genetic Algorithms vol 2 no 1519 pp45ndash62 2014

[8] J Kennedy and R Eberhart ldquoParticle swarm optimizationrdquoin Proceedings of the IEEE International Conference on NeuralNetworks pp 1942ndash1948 December 1995

[9] D Karaboga and B Basturk ldquoOn the performance of artificialbee colony (ABC) algorithmrdquo Applied Soft Computing vol 8no 1 pp 687ndash697 2008

Mathematical Problems in Engineering 9

[10] M Dorigo M Birattari and T Stutzle ldquoAnt colony optimiza-tionrdquo IEEE Computational Intelligence Magazine vol 1 no 4pp 28ndash39 2006

[11] X-S Yang and S Deb ldquoCuckoo search via Levy flightsrdquo in Pro-ceedings of the World Congress on Nature amp Biologically InspiredComputing (NABIC rsquo09) pp 210ndash214 IEEE Coimbatore IndiaDecember 2009

[12] S Mirjalili S M Mirjalili and A Lewis ldquoGrey wolf optimizerrdquoAdvances in Engineering Software vol 69 pp 46ndash61 2014

[13] B Mahdad and K Srairi ldquoBlackout risk prevention in a smartgrid based flexible optimal strategy using Grey Wolf-patternsearch algorithmsrdquo Energy Conversion and Management vol98 pp 411ndash429 2015

[14] X Song L Tang S Zhao et al ldquoGrey Wolf Optimizer forparameter estimation in surface wavesrdquo Soil Dynamics andEarthquake Engineering vol 75 pp 147ndash157 2015

[15] M H Sulaiman Z Mustaffa M R Mohamed and O AlimanldquoUsing the gray wolf optimizer for solving optimal reactivepower dispatch problemrdquo Applied Soft Computing vol 32 pp286ndash292 2015

[16] G M Komaki and V Kayvanfar ldquoGrey Wolf Optimizer algo-rithm for the two-stage assembly flow shop scheduling problemwith release timerdquo Journal of Computational Science vol 8 pp109ndash120 2015

[17] N Jayakumar S Subramanian S Ganesan and E BElanchezhian ldquoGrey wolf optimization for combined heatand power dispatch with cogeneration systemsrdquo InternationalJournal of Electrical Power amp Energy Systems vol 74 pp252ndash264 2016

[18] Y Sharma and L C Saikia ldquoAutomatic generation controlof a multi-area STmdashthermal power system using Grey Wolfoptimizer algorithm based classical controllersrdquo InternationalJournal of Electrical Power amp Energy Systems vol 73 pp 853ndash862 2015

Submit your manuscripts athttpwwwhindawicom

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

MathematicsJournal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Mathematical Problems in Engineering

Hindawi Publishing Corporationhttpwwwhindawicom

Differential EquationsInternational Journal of

Volume 2014

Applied MathematicsJournal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Probability and StatisticsHindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Journal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Mathematical PhysicsAdvances in

Complex AnalysisJournal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

OptimizationJournal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

CombinatoricsHindawi Publishing Corporationhttpwwwhindawicom Volume 2014

International Journal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Operations ResearchAdvances in

Journal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Function Spaces

Abstract and Applied AnalysisHindawi Publishing Corporationhttpwwwhindawicom Volume 2014

International Journal of Mathematics and Mathematical Sciences

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

The Scientific World JournalHindawi Publishing Corporation httpwwwhindawicom Volume 2014

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Algebra

Discrete Dynamics in Nature and Society

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Decision SciencesAdvances in

Discrete MathematicsJournal of

Hindawi Publishing Corporationhttpwwwhindawicom

Volume 2014 Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Stochastic AnalysisInternational Journal of

Page 8: Research Article Dynamic Modeling of Steam Condenser and ...downloads.hindawi.com/journals/mpe/2015/120975.pdf · Shell-and-tube condenser is a heat exchanger for cooling steam with

8 Mathematical Problems in Engineering

0 10 20 30 40 5081

82

83

84

85

86

87

88

89

90

Am

plitu

de

⟨P⟩

Time (s)

ZNGA

PSOGWO

Figure 10 Output response curves of pressure under differentalgorithms

value so the effect of PID control is poor The GA algorithmand PSO algorithm are intelligent method so control effectof PID controller whose parameters are optimized by thesetwo methods has been greatly improved relative to the Z-Nsetting method But because of their inherent search modeand the defects the search accuracy is not high enough thusresult of parameters setting is poorer than that of grey wolfoptimizer It can be known from searching way of GWOalgorithm above that the grey wolf optimizer is going tosearch solutions in the comprehensive evaluation by threewolves Therefore the GWO algorithm has a high searchprecision which can make it sure to search a better solutionvalue Thus the GWO algorithm increases the probability ofsearching a better group of PID parameters

5 Conclusions

In this paper a dynamic model of steam condenser and theclosed-loop control system are established on the basis of thelumped parameter model of the condenser For the pressureclosed-loop control system in order to improve the systemperformance the GWO algorithm is adopted to optimize thePI parametersThrough the simulation experiments and per-formance comparison of cooling water outlet temperaturecirculating water flow steam discharge heat and condenserpressure the introduction of the GWO algorithm makes thesteam condenser PI controller have better control effect Inorder to have a better control effect of steam condenser wecan try to improve the design of PID controller Since theresearch of grey wolf optimizer is just in its infancy theGWO algorithm should be improved to obtain better PIDparameters in the further study Other superior algorithmsshould be exploited for PID parameter optimization

Conflict of Interests

The authors declare that there is no conflict of interestsregarding the publication of this paper

Authorsrsquo Contribution

Shu-Xia Li participated in the data collection analysis algo-rithm simulation draft writing and critical revision of thispaper Jie-Sheng Wang participated in the concept designand interpretation and commented on the paper

Acknowledgments

This work is partially supported by National Key Technolo-gies R amp D Program of China (Grant no 2014BAF05B01)Project by National Natural Science Foundation of China(Grant no 21576127) Program for Liaoning Excellent Talentsin University (Grant no LR2014008) Project by LiaoningProvincial Natural Science Foundation of China (Grant no2014020177) Program for Research Special Foundation ofUniversity of Science and Technology of Liaoning (Grantno 2015TD04) and Opening Project of National FinancialSecurity and System Equipment Engineering Research Cen-ter (Grant no USTLKEC201401)

References

[1] T Tahri S A Abdul-Wahab A Bettahar M Douani H Al-Hinai and Y Al-Mulla ldquoSimulation of the condenser of theseawater greenhouse Part I theoretical developmentrdquo Journalof Thermal Analysis and Calorimetry vol 96 no 1 pp 35ndash422009

[2] P K Bansal and T C Chin ldquoModelling and optimisation ofwire-and-tube condenserrdquo International Journal of Refrigera-tion vol 26 no 5 pp 601ndash613 2003

[3] M R Malin ldquoModelling flow in an experimental marinecondenserrdquo International Communications in Heat and MassTransfer vol 24 no 5 pp 597ndash608 1997

[4] XDingWCai P Duan and J Yan ldquoHybrid dynamicmodelingfor two phase flow condensersrdquo Applied Thermal Engineeringvol 62 no 2 pp 830ndash837 2014

[5] WWangD Zeng J Liu YNiu andC Cui ldquoFeasibility analysisof changing turbine load in power plants using continuouscondenser pressure adjustmentrdquo Energy vol 64 pp 533ndash5402014

[6] Z Ma and S Wang ldquoOnline fault detection and robust controlof condenser cooling water systems in building central chillerplantsrdquo Energy and Buildings vol 43 no 1 pp 153ndash165 2011

[7] D Whitley ldquoAn executable model of a simple genetic algo-rithmrdquo Foundations of Genetic Algorithms vol 2 no 1519 pp45ndash62 2014

[8] J Kennedy and R Eberhart ldquoParticle swarm optimizationrdquoin Proceedings of the IEEE International Conference on NeuralNetworks pp 1942ndash1948 December 1995

[9] D Karaboga and B Basturk ldquoOn the performance of artificialbee colony (ABC) algorithmrdquo Applied Soft Computing vol 8no 1 pp 687ndash697 2008

Mathematical Problems in Engineering 9

[10] M Dorigo M Birattari and T Stutzle ldquoAnt colony optimiza-tionrdquo IEEE Computational Intelligence Magazine vol 1 no 4pp 28ndash39 2006

[11] X-S Yang and S Deb ldquoCuckoo search via Levy flightsrdquo in Pro-ceedings of the World Congress on Nature amp Biologically InspiredComputing (NABIC rsquo09) pp 210ndash214 IEEE Coimbatore IndiaDecember 2009

[12] S Mirjalili S M Mirjalili and A Lewis ldquoGrey wolf optimizerrdquoAdvances in Engineering Software vol 69 pp 46ndash61 2014

[13] B Mahdad and K Srairi ldquoBlackout risk prevention in a smartgrid based flexible optimal strategy using Grey Wolf-patternsearch algorithmsrdquo Energy Conversion and Management vol98 pp 411ndash429 2015

[14] X Song L Tang S Zhao et al ldquoGrey Wolf Optimizer forparameter estimation in surface wavesrdquo Soil Dynamics andEarthquake Engineering vol 75 pp 147ndash157 2015

[15] M H Sulaiman Z Mustaffa M R Mohamed and O AlimanldquoUsing the gray wolf optimizer for solving optimal reactivepower dispatch problemrdquo Applied Soft Computing vol 32 pp286ndash292 2015

[16] G M Komaki and V Kayvanfar ldquoGrey Wolf Optimizer algo-rithm for the two-stage assembly flow shop scheduling problemwith release timerdquo Journal of Computational Science vol 8 pp109ndash120 2015

[17] N Jayakumar S Subramanian S Ganesan and E BElanchezhian ldquoGrey wolf optimization for combined heatand power dispatch with cogeneration systemsrdquo InternationalJournal of Electrical Power amp Energy Systems vol 74 pp252ndash264 2016

[18] Y Sharma and L C Saikia ldquoAutomatic generation controlof a multi-area STmdashthermal power system using Grey Wolfoptimizer algorithm based classical controllersrdquo InternationalJournal of Electrical Power amp Energy Systems vol 73 pp 853ndash862 2015

Submit your manuscripts athttpwwwhindawicom

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

MathematicsJournal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Mathematical Problems in Engineering

Hindawi Publishing Corporationhttpwwwhindawicom

Differential EquationsInternational Journal of

Volume 2014

Applied MathematicsJournal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Probability and StatisticsHindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Journal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Mathematical PhysicsAdvances in

Complex AnalysisJournal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

OptimizationJournal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

CombinatoricsHindawi Publishing Corporationhttpwwwhindawicom Volume 2014

International Journal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Operations ResearchAdvances in

Journal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Function Spaces

Abstract and Applied AnalysisHindawi Publishing Corporationhttpwwwhindawicom Volume 2014

International Journal of Mathematics and Mathematical Sciences

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

The Scientific World JournalHindawi Publishing Corporation httpwwwhindawicom Volume 2014

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Algebra

Discrete Dynamics in Nature and Society

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Decision SciencesAdvances in

Discrete MathematicsJournal of

Hindawi Publishing Corporationhttpwwwhindawicom

Volume 2014 Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Stochastic AnalysisInternational Journal of

Page 9: Research Article Dynamic Modeling of Steam Condenser and ...downloads.hindawi.com/journals/mpe/2015/120975.pdf · Shell-and-tube condenser is a heat exchanger for cooling steam with

Mathematical Problems in Engineering 9

[10] M Dorigo M Birattari and T Stutzle ldquoAnt colony optimiza-tionrdquo IEEE Computational Intelligence Magazine vol 1 no 4pp 28ndash39 2006

[11] X-S Yang and S Deb ldquoCuckoo search via Levy flightsrdquo in Pro-ceedings of the World Congress on Nature amp Biologically InspiredComputing (NABIC rsquo09) pp 210ndash214 IEEE Coimbatore IndiaDecember 2009

[12] S Mirjalili S M Mirjalili and A Lewis ldquoGrey wolf optimizerrdquoAdvances in Engineering Software vol 69 pp 46ndash61 2014

[13] B Mahdad and K Srairi ldquoBlackout risk prevention in a smartgrid based flexible optimal strategy using Grey Wolf-patternsearch algorithmsrdquo Energy Conversion and Management vol98 pp 411ndash429 2015

[14] X Song L Tang S Zhao et al ldquoGrey Wolf Optimizer forparameter estimation in surface wavesrdquo Soil Dynamics andEarthquake Engineering vol 75 pp 147ndash157 2015

[15] M H Sulaiman Z Mustaffa M R Mohamed and O AlimanldquoUsing the gray wolf optimizer for solving optimal reactivepower dispatch problemrdquo Applied Soft Computing vol 32 pp286ndash292 2015

[16] G M Komaki and V Kayvanfar ldquoGrey Wolf Optimizer algo-rithm for the two-stage assembly flow shop scheduling problemwith release timerdquo Journal of Computational Science vol 8 pp109ndash120 2015

[17] N Jayakumar S Subramanian S Ganesan and E BElanchezhian ldquoGrey wolf optimization for combined heatand power dispatch with cogeneration systemsrdquo InternationalJournal of Electrical Power amp Energy Systems vol 74 pp252ndash264 2016

[18] Y Sharma and L C Saikia ldquoAutomatic generation controlof a multi-area STmdashthermal power system using Grey Wolfoptimizer algorithm based classical controllersrdquo InternationalJournal of Electrical Power amp Energy Systems vol 73 pp 853ndash862 2015

Submit your manuscripts athttpwwwhindawicom

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

MathematicsJournal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Mathematical Problems in Engineering

Hindawi Publishing Corporationhttpwwwhindawicom

Differential EquationsInternational Journal of

Volume 2014

Applied MathematicsJournal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Probability and StatisticsHindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Journal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Mathematical PhysicsAdvances in

Complex AnalysisJournal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

OptimizationJournal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

CombinatoricsHindawi Publishing Corporationhttpwwwhindawicom Volume 2014

International Journal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Operations ResearchAdvances in

Journal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Function Spaces

Abstract and Applied AnalysisHindawi Publishing Corporationhttpwwwhindawicom Volume 2014

International Journal of Mathematics and Mathematical Sciences

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

The Scientific World JournalHindawi Publishing Corporation httpwwwhindawicom Volume 2014

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Algebra

Discrete Dynamics in Nature and Society

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Decision SciencesAdvances in

Discrete MathematicsJournal of

Hindawi Publishing Corporationhttpwwwhindawicom

Volume 2014 Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Stochastic AnalysisInternational Journal of

Page 10: Research Article Dynamic Modeling of Steam Condenser and ...downloads.hindawi.com/journals/mpe/2015/120975.pdf · Shell-and-tube condenser is a heat exchanger for cooling steam with

Submit your manuscripts athttpwwwhindawicom

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

MathematicsJournal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Mathematical Problems in Engineering

Hindawi Publishing Corporationhttpwwwhindawicom

Differential EquationsInternational Journal of

Volume 2014

Applied MathematicsJournal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Probability and StatisticsHindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Journal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Mathematical PhysicsAdvances in

Complex AnalysisJournal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

OptimizationJournal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

CombinatoricsHindawi Publishing Corporationhttpwwwhindawicom Volume 2014

International Journal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Operations ResearchAdvances in

Journal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Function Spaces

Abstract and Applied AnalysisHindawi Publishing Corporationhttpwwwhindawicom Volume 2014

International Journal of Mathematics and Mathematical Sciences

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

The Scientific World JournalHindawi Publishing Corporation httpwwwhindawicom Volume 2014

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Algebra

Discrete Dynamics in Nature and Society

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Decision SciencesAdvances in

Discrete MathematicsJournal of

Hindawi Publishing Corporationhttpwwwhindawicom

Volume 2014 Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Stochastic AnalysisInternational Journal of


Recommended