+ All Categories
Home > Documents > Session 8 Long Shutdown 2 Strategy and Preparation

Session 8 Long Shutdown 2 Strategy and Preparation

Date post: 04-Jan-2016
Category:
Upload: raymond-abbott
View: 31 times
Download: 4 times
Share this document with a friend
Description:
Chair : José Miguel Jiménez Scientific Secretary : Jean-Philippe Tock. Session 8 Long Shutdown 2 Strategy and Preparation. Session breakdown Chair: José Miguel Jiménez; Scientific secretary: Jean-Philippe Tock. Scope of the LS2 (making best use of the period 2015-2018) - PowerPoint PPT Presentation
Popular Tags:
29
Transcript
Page 1: Session  8 Long  Shutdown 2 Strategy and  Preparation
Page 2: Session  8 Long  Shutdown 2 Strategy and  Preparation

Dr. José Miguel JIMENEZLS2 CoordinatorLHC Performance Workshop (Chamonix 2014)Session 8 - Long Shutdown 2 Strategy and Preparation - Summary 8th Oct’14

Session 8Long Shutdown 2 Strategy and Preparation

Chair: José Miguel JiménezScientific Secretary: Jean-Philippe Tock

2

Page 3: Session  8 Long  Shutdown 2 Strategy and  Preparation

Dr. José Miguel JIMENEZLS2 CoordinatorLHC Performance Workshop (Chamonix 2014)Session 8 - Long Shutdown 2 Strategy and Preparation - Summary 3

Session breakdown Chair: José Miguel Jiménez; Scientific secretary: Jean-Philippe Tock

• Scope of the LS2 (making best use of the period 2015-2018)• José Miguel Jiménez

• What has been learnt from LS1• Katy Foraz

• Safety & Radiation Aspects• Doris Forkel-Wirth

• LIU Planned Activities • Julie Coupard

• HL-LHC Planned Activities - Accelerator• Isabel Bejar Alonso

• LHC Experiments Upgrade and Maintenance• Werner Riegler

• LHC @ LS2• Marzia Bernardini

8th Oct’14

Page 4: Session  8 Long  Shutdown 2 Strategy and  Preparation

Dr. José Miguel JIMENEZLS2 CoordinatorLHC Performance Workshop (Chamonix 2014)Session 8 - Long Shutdown 2 Strategy and Preparation - Summary 4

Scope of the LS2 (making best use of the period 2015-2018)José Miguel Jiménez

• The project scope covers all activities carried out and resources needed in the context of Long Shutdown 2 over the whole CERN accelerator facilities.

• The preparation, coordination and follow-up till completion of all LS2 activities in the frame of the LIU, HL-LHC Projects and other CERN approved projects.

• The flexibility to use the end-of-year technical stops before and after the LS2 to decrease the load of the LS2 is left at the discretion of the LS2 coordinator and is also part of the scope of the project.

8th Oct’14

LS1Post

Mortem

LS2Day

LS2Day

LS2Day

PLANis madeavailable

ConsolidatedList of tasks

to Director A&T

1st stepfinal

validation

Finalvalidation

Page 5: Session  8 Long  Shutdown 2 Strategy and  Preparation

Dr. José Miguel JIMENEZLS2 CoordinatorLHC Performance Workshop (Chamonix 2014)Session 8 - Long Shutdown 2 Strategy and Preparation - Summary 5

What has been learnt from LS1Katy Foraz

8th Oct’14

Collection and prioritization of activities: a) Plan.cern.ch

• Unique repository to ease information exchange between groups Groups had a clearest picture of the support to be given to other groups

• Attenuate bad surprises• Ease the prioritization process for LS1 team, focusing only on discordance

points

But• Should have come earlier…• Not all activities were announced… • Redundancy of resources details between APT and PLAN…

In the future ?• Use again PLAN tool to collect future activities• Give enough time to groups to fill data• Improve the PLAN tool to better fit with needs: redundancy with other tools,

granularity between items

+

+

+

~

~

~

Page 6: Session  8 Long  Shutdown 2 Strategy and  Preparation

Dr. José Miguel JIMENEZLS2 CoordinatorLHC Performance Workshop (Chamonix 2014)Session 8 - Long Shutdown 2 Strategy and Preparation - Summary 6

What has been learnt from LS1Katy Foraz

“Organize, don't agonize.” Nancy Pelosi

• Coordination• Helps to keep a very good follow-up on fields• Enhances team spirit & eases information flow

• Scheduling• Will keep a member of coordination team (scheduler) within projects• Improves availability of internal production and acceptance tests schedules• Optimizes the start of an activity w.r.t. cooling period

• Documentation• Will continue presenting ECRs in (LSC), LMC, IEFC on regular basis• Will insist to have ECRs edited in due time

• Daily management• Will help to keep working with the same Stakeholders…

• Information exchange• Will improve information flow down to the worksites

• Rationalized project’ information• 1 web page indicating hyperlink to projects ?

• Implement and maintain a repository of services’ unavailability.

8th Oct’14

Page 7: Session  8 Long  Shutdown 2 Strategy and  Preparation

Dr. José Miguel JIMENEZLS2 CoordinatorLHC Performance Workshop (Chamonix 2014)Session 8 - Long Shutdown 2 Strategy and Preparation - Summary 7

Safety & Radiation AspectsDoris Forkel-Wirth

• Regulatory Landscape is introducing new constraints…• Impact will be evaluated in the coming months…• Training preparation and communication will get high priority.

• Radioactive storage (surface & handling) and waste management (volume & weight) is a major issue

• Group’s projections need to be more accurate…

• Injectors will dominate personnel dose rates even though situation in LHC will not improve…

• CERN individual dose objective of 3 mSv over 12 consecutive months will be more challenging…

• Even though ALARA has became an essential and natural part of CERN culture.

• Roadmap towards LS2 is identified, thanks to the lessons learnt from LS1.

8th Oct’14

Page 8: Session  8 Long  Shutdown 2 Strategy and  Preparation

Dr. José Miguel JIMENEZLS2 CoordinatorLHC Performance Workshop (Chamonix 2014)Session 8 - Long Shutdown 2 Strategy and Preparation - Summary 8

LIU Planned Activities Julie Coupard

• Main outcomes• LIU activities fit in the LS2 time window defined for the injectors but

the schedules are very tight with not much margin and already assuming shift activities.

• Consolidation prioritization needs to be coherent with LIU activities…

• Additional studies required:• To evaluate the cabling work load as early as possible in order to estimate

the EN/EL workload and integration.

• For the levelling of the resources of the support/client groups, for example: EN/MME, EN/HE, EN/CV, EN/EL, EN/MEF-SU, GS/CE, TE/VSC.

• With integration studies which need to be completed: 3D models of infrastructures and general services.

• To finalize the needs for design and production of manufacturing drawings.

• To define works that can be anticipated in YETS and EYETS.

8th Oct’14

Page 9: Session  8 Long  Shutdown 2 Strategy and  Preparation

Dr. José Miguel JIMENEZLS2 CoordinatorLHC Performance Workshop (Chamonix 2014)Session 8 - Long Shutdown 2 Strategy and Preparation - Summary 9

LIU Planned Activities – Room for optimization… Julie Coupard

8th Oct’14

Page 10: Session  8 Long  Shutdown 2 Strategy and  Preparation

Dr. José Miguel JIMENEZLS2 CoordinatorLHC Performance Workshop (Chamonix 2014)Session 8 - Long Shutdown 2 Strategy and Preparation - Summary 10

HL-LHC Planned Activities - AcceleratorIsabel Bejar Alonso

• Main outcomes• Identify and prepare work that can be done in LS2 on the time

frame allocated for which the technology/solution is mature and can not bring any risk to the run 3 start date.

• Integrate as early as possible HL-LHC work planning in LS2.

8th Oct’14

Page 11: Session  8 Long  Shutdown 2 Strategy and  Preparation

Dr. José Miguel JIMENEZLS2 CoordinatorLHC Performance Workshop (Chamonix 2014)Session 8 - Long Shutdown 2 Strategy and Preparation - Summary 11

LHC Experiments Upgrade and MaintenanceWerner Riegler

8th Oct’14

Page 12: Session  8 Long  Shutdown 2 Strategy and  Preparation

Dr. José Miguel JIMENEZLS2 CoordinatorLHC Performance Workshop (Chamonix 2014)Session 8 - Long Shutdown 2 Strategy and Preparation - Summary 12

LHC Experiments Upgrade and MaintenanceWerner Riegler

8th Oct’14

Page 13: Session  8 Long  Shutdown 2 Strategy and  Preparation

Dr. José Miguel JIMENEZLS2 CoordinatorLHC Performance Workshop (Chamonix 2014)Session 8 - Long Shutdown 2 Strategy and Preparation - Summary 13

LHC Experiments Upgrade and MaintenanceWerner Riegler

8th Oct’14

Page 14: Session  8 Long  Shutdown 2 Strategy and  Preparation

Dr. José Miguel JIMENEZLS2 CoordinatorLHC Performance Workshop (Chamonix 2014)Session 8 - Long Shutdown 2 Strategy and Preparation - Summary 14

LHC Experiments Upgrade and MaintenanceWerner Riegler

8th Oct’14

Page 15: Session  8 Long  Shutdown 2 Strategy and  Preparation

Dr. José Miguel JIMENEZLS2 CoordinatorLHC Performance Workshop (Chamonix 2014)Session 8 - Long Shutdown 2 Strategy and Preparation - Summary 15

LHC Experiments Upgrade and MaintenanceWerner Riegler

8th Oct’14

Page 16: Session  8 Long  Shutdown 2 Strategy and  Preparation

Dr. José Miguel JIMENEZLS2 CoordinatorLHC Performance Workshop (Chamonix 2014)Session 8 - Long Shutdown 2 Strategy and Preparation - Summary 16

LHC @ LS2Marzia Bernardini

• Key messages• LS2 needs to be prepared NOW!

• LS2 is mainly dedicated to Injectors and LHC Detectors…• ...but in the LHC, Maintenance and Consolidations are important.

• LS2 is an opportunity, for the LHC, to prepare LS3: • Anticipating as much as possible HL-LHC activities from LS3.• Focusing on RP Issues and ALARA procedures stay a priority.

• Support activities will be on the critical path and coordination will be challenged…

• LS2 activities should not compromise LS3 preparation.

• Resources optimisation across the Accelerators and Experiments will be THE key point!

8th Oct’14

Page 17: Session  8 Long  Shutdown 2 Strategy and  Preparation

Dr. José Miguel JIMENEZLS2 CoordinatorLHC Performance Workshop (Chamonix 2014)Session 8 - Long Shutdown 2 Strategy and Preparation - Summary 17

LHC @ LS2Marzia Bernardini

8th Oct’14

2018 2019

Depending on the cool down and warm up sequence

Windows available for activities Between 9 and 13 Months

WARM UP and TESTS

Lift replacement

CRYO Maintenance

Magnets replacement

Other activities…

Radiation Cool Down @ P7

HL activities @ P2, P4 and TZ76

HL activities @ LSS7

COOL DOWN, TESTS and HWC

July '18 Aug. '18Sept. '18

Oct. '18 Nov. '18 Dec. '18 Jan. '19 Feb. '19March

'19April '19 May '19 June '19 July '19 Aug. '19

Sept. '19

Oct. '19 Nov. '19 Dec. '19

ELECTRICAL Maintenance & Consolidation

Skeleton of LS2 Master Schedule (indicative)

Page 18: Session  8 Long  Shutdown 2 Strategy and  Preparation

Dr. José Miguel JIMENEZLS2 CoordinatorLHC Performance Workshop (Chamonix 2014)Session 8 - Long Shutdown 2 Strategy and Preparation - Summary 18

Closing remarks

• Priority of LS2 Coordination towards:• Safety & Radiation readiness: rules, training, communication, temporary storage,

waste management…• Classification levels and dose rates will be of primary criticality• Estimation of temporary storages and waste’s volume and weight is urgently required.

• Injectors (LIU) and LHC Experiments (allow them matching the “compressed” schedule).

• Have already a “skeleton” of LS2 master schedule• LIU & Maintenance well defined (LS1 experience)• HL-LHC & Consolidations to be reviewed

• Prioritisation of Consolidations will need to be assessed in the frame of the available LS2 resources, impact on other groups and coherence with LIU project.

• Collection and prioritization of activities will rely on “PLAN” tool• Unique repository, useful for information exchange between groups

• Groups had a clearest picture of the support to be given to other groups• Mitigates probability of bad surprises…• Ease the prioritization process and allows focusing only on discordances.

8th Oct’14

Page 19: Session  8 Long  Shutdown 2 Strategy and  Preparation
Page 20: Session  8 Long  Shutdown 2 Strategy and  Preparation

Dr. José Miguel JIMENEZLS2 CoordinatorLHC Performance Workshop (Chamonix 2014)Session 8 - Long Shutdown 2 Strategy and Preparation - Summary 20

Safety & Radiation AspectsDoris Forkel-Wirth

8th Oct’14

Critical changesexpected…

Page 21: Session  8 Long  Shutdown 2 Strategy and  Preparation

Dr. José Miguel JIMENEZLS2 CoordinatorLHC Performance Workshop (Chamonix 2014)Session 8 - Long Shutdown 2 Strategy and Preparation - Summary

Equipment on the Beam Tunnel equipment Vert. J Surface Eq. Dis.

DF(X-M) + SC Link DSH (X-M)

Cryo line IR+MSAlignment

QPS2

Magnet systemMQXFA MQXFB, MBXF, MBRD, MQYY,

Q5 1.9, Q6 1.9MCBXFB, MCBXFA, MQSXF, MCTXF, MCTSXF,

MCDXF, MCDSXF, MCOXF, MCOSXF, MCSXF,MCSSXF,MCBRD, MCBYY

Beam vacuum

TAXS, TAXN

Interaction Region and MS IP 1,5

Collimation (TCTPM, TCL, TCLM, TCTP)

Beam diagnosticBPMSQW, BMPSQ, BPMSQT, BMLC

DS Collimation for ion IP 2

H.F. dipoles

Cryo-bypass+TCLD

DFH(X-M) + Power converters

SC link/powering IP 7

Hor. SC Link DSH + DFA

Power converters

EE

Crab Cavity cryomodules

RF systemLoads, circulators, RF power, LLRF, HVPS,

central LLRR

DS Collimation pp (TBC RUN II) IP 1,5

H.F. dipoles

Cryo-bypass+TCLD

DS Collimation pp (TBC RUN II) IP 7

H.F. dipoles

Cryo-bypass+TCLD

Rad-hard electronics for BLM and BPM

CC diagnostic and protection

PIC

BIS

DFA+ SC Link DSHA

DFHA + Power converters

SC link/Powering

arcIP 1,5

Cryoplant IP 1,5

CB Warm compressor and other surface eq.

In orange Works

during LS2

Page 22: Session  8 Long  Shutdown 2 Strategy and  Preparation

Dr. José Miguel JIMENEZLS2 CoordinatorLHC Performance Workshop (Chamonix 2014)Session 8 - Long Shutdown 2 Strategy and Preparation - Summary

Equipment on the Beam Tunnel equipment Vert. J Surface equip. Dis.

Cryo line for RF

Beam diagnostic IP 4

Fast wire scanners BWSF

New light extraction line BSRT

Beam gas vertex detector BGV

Injection protection IP 2 8

TDI (TBC)

TCLIA, TCLIB (TBC)

TCDD TCDDM (TBC)

TCLIM (TBC)

MKI (TBC)

Q5 at point 6 IP 6

Dump (TBC) IP 6

TCDS (TBC)

MKB, TDE (TBC)

PIC

BIS

High rad warm magnets (TBC) IP 7

Collimation upgrade

Secondary TCSPM

Primary TCP TCPP

TCSG, TCLA, TCAP

IP 3 7

IP 3 7

IP 3 7

TCSP IP 6

Mini-TAN IP 8

CB

Cryoplant IP 4

Warm compressor and other surface eq.

In orange Works during

LS2

Page 23: Session  8 Long  Shutdown 2 Strategy and  Preparation

Dr. José Miguel JIMENEZLS2 CoordinatorLHC Performance Workshop (Chamonix 2014)Session 8 - Long Shutdown 2 Strategy and Preparation - Summary 23

LHC @ LS2Marzia Bernardini

8th Oct’14

Mai

nten

ance C

onsolidation

Page 24: Session  8 Long  Shutdown 2 Strategy and  Preparation

Dr. José Miguel JIMENEZLS2 CoordinatorLHC Performance Workshop (Chamonix 2014)Session 8 - Long Shutdown 2 Strategy and Preparation - Summary

LHC Experiments Upgrade and MaintenanceWerner Riegler

• ATLAS Support Needs• Beampipes, Vacuum, Collimators • Detector Cooling

• CMS Support Needs• Beampipes, Vacuum, Collimators • Cooling, Electricity & other services• Magnet• Cranes, Elevators• Complete opening of detector

• ALICE Support Needs• Extension of the computing farm • Beampipes, Vacuum, Collimators • Fibers• Detector Cooling• Change of elevator• PbPb Luminosity

• LHCb Support Needs• New computing farm (2MW)• Beampipes , Vacuum, Collimators (EN, TE)• Fibers• Services and Integration:• Detector Cooling• Change of elevator, crane ? But not during LS2

8th Oct’14

Page 25: Session  8 Long  Shutdown 2 Strategy and  Preparation

Dr. José Miguel JIMENEZLS2 CoordinatorLHC Performance Workshop (Chamonix 2014)Session 8 - Long Shutdown 2 Strategy and Preparation - Summary 8th Oct’14

• Beampipes, Vacuum, Collimators • ATLAS has performed the consolidation of the beampipes and vacuum

equipment already during LS1. Only maintenance foreseen in LS2.

• Detector Cooling• Cooling system consolidation was performed during LS1.• Mainly maintenance during LS2

ATLAS Support Needs

25

Page 26: Session  8 Long  Shutdown 2 Strategy and  Preparation

Dr. José Miguel JIMENEZLS2 CoordinatorLHC Performance Workshop (Chamonix 2014)Session 8 - Long Shutdown 2 Strategy and Preparation - Summary 8th Oct’14

• Beampipes, Vacuum, Collimators • Central pipe was changed in LS1, Change Beampipes (EC HF CT2 FWD) to Al 2219 in

LS2 (TE-VSC). Possible change in pipe geometry (decision 2015) – re-design from scratch.

• Cooling, Electricity & other services• 4 (+1) x500kVA UPS --> 7 (+1) x 500kVA and upgrade of electrical infrastructure (EN-EL)

possible re-siting of battery banks• Revise & extend control room, moving UPS out.• Increase of chilled water production (+1.5MW) (EN-CV) for Phase 2 detectors• Dry gas (air/N2) system (EN-CV) upgrade for Phase 2 detectors• Multi-purpose extension of surface assembly hall (1000m2), EN-CV, EN-EL needs

• Magnet• Refurbishment of magnet control and safety system (PH-DT, TE)• Implement freewheel thyristor for immunity from power converter glitches (TE)

• Cranes, Elevators• Installation of a second UXC crane with suspended cage for personnel access (EN-HE)• Replace Elevator (EN-HE)

• Complete opening of detector • Upgrades + detector maintenance on same scale as LS1 + new beampipes

--> transport, rigging, survey & FSU support on same scale as LS1

CMS Support Needs

26

Page 27: Session  8 Long  Shutdown 2 Strategy and  Preparation

Dr. José Miguel JIMENEZLS2 CoordinatorLHC Performance Workshop (Chamonix 2014)Session 8 - Long Shutdown 2 Strategy and Preparation - Summary 8th Oct’14

• Extension of the computing farm • To be studied whether available space and infrastructure are sufficient (EN-

EL, EN-CV)

• Beampipes, Vacuum, Collimators • New central beampipe + mobile bakeout equipment (TE-VSC)• Modification of Miniframe beampipe, displacement of gauge, ion pump in

Aluminum (TE-VSC)• LSS vacuum consolidation to minimize vacuum pressure (TE-VSC)• New TDI to limit high vacuum pressure from outgassing (EN-STI)• Collimators in dispersion suppressor region to allow maximum PbPb

Luminosity (...)

• Fibers• Possibly already during EYETS 2016/2017

• Detector Cooling• New detector cooling plant for upgraded Inner Tracking System (EN-CV)• Possible upgrade of ITS dry air ventilation system (EN-CV)

• Change of elevator

• PbPb Luminosity• Infrastructure for increase of PbPb luminosity to >6x1027

ALICE Support Needs

27

Page 28: Session  8 Long  Shutdown 2 Strategy and  Preparation

Dr. José Miguel JIMENEZLS2 CoordinatorLHC Performance Workshop (Chamonix 2014)Session 8 - Long Shutdown 2 Strategy and Preparation - Summary 8th Oct’14

• New computing farm (2MW)• Housed in new surface building or container (GS)• Strategy for operational temperature and cooling (EN-CV)• Possible needs for UPS (EN-EL)

• Beampipes , Vacuum, Collimators (EN, TE)• All beampipes in the cavern must be removed and then reinstalled during LS2, no new

beampipes are planned.• Probably a TAS will have to be installed around LHCb• TDI in TI8 injection line to be changed (LS2 ?)

• Fibers• Possibly already during EYETS 2016/2017. (EN-EL ?, other companies ?) make sure

CERN frame contracts are adapted.

• Services and Integration:• For integration of cables, cable trays, cooling lines, access platforms as well as

supervision of the service installation activities LHCb relies on EN-MEF

• Detector Cooling• New Fiber Tracker (SciFi) cooling plant (-40C monophase Freon for SiPMs) (EN-CV) &

adapt OT/PS/SPD cooling plant for SciFi electronics• Possible adaption of TT cooling plant to Fiber Tracker electronics cooling (EN-CV)• (Velo and UT CO2 cooling is done throughP H-DT), but primary cooling with support

from EN-CV.

• Change of elevator, crane ? But not during LS2

LHCb Support Needs

28

Page 29: Session  8 Long  Shutdown 2 Strategy and  Preparation

Dr. José Miguel JIMENEZLS2 CoordinatorLHC Performance Workshop (Chamonix 2014)Session 8 - Long Shutdown 2 Strategy and Preparation - Summary 29

LHC @ LS2Marzia Bernardini

• Outcomes• Maintenance vs Consolidation need to be reworked in the coming

months• No official baseline for consolidation project

• Retuning will be required after decision are taken by PL of Consolidation project

• Replacement of all lifts: 3 months unavailability at least for material transport

• “Optimised” schedule, assuming ALARA lefts only 9 months for HL-LHC in LSS7!

• Resources levelling will be needed

• Temporary storage areas will be installed at the surface max 6 months before and 6 months after LS2

• Existing buffer zones are probably not sufficient

• Performance optimisation of He exchanger in triplets in 1&5• Reassess needs to consolidate them in triplet +&% and 2&8 (ALARA)

8th Oct’14


Recommended