Pleasant Grove High School9531 Bond Road
Elk Grove, CA 95624
JANUARY 14, 20166—8 PM
SHELDON ROAD & BRADSHAW ROAD
INTERSECTION IMPROVEMENT PROJECT
Tom Metcalf (916) 478-2281 [email protected]
City of Elk Grove Public Works Department 8401 Laguna Palms Way Elk Grove, CA 95758
CONTACT US
ROUNDABOUT INTERSECTION
ROUNDABOUT INTERSECTION OPTION
SIGNAL INTERSECTION OPTION
Sheldon RoadSheldon Road
Bra
dsh
aw R
oad
Bra
dsh
aw R
oad
Sheldon RoadSheldon Road
Bra
dsh
aw R
oad
Bra
dsh
aw R
oad
LEGEND:
Proposed Roadway
Proposed Paths
LEGEND:
Proposed Roadway
Proposed Paths
WHAT IS BEING PROPOSED?
Improvements to the intersection of Sheldon Road and Bradshaw Road are planned because threshold values for increased traffic have been met, per the process outlined in the Rural Road Improvement Policy and Standards.
Based on community input and City Council direction, two options are being considered for the intersection: a signal or a roundabout. All proposed designs, currently 35% complete, take into consideration design preferences expressed in the Rural Road Improvement Policy and Standards.
Tonight we would like to get your input on these designs and understand your design preferences.
This Open House meeting is being held to provide the public an opportunity to review the proposed project, view project designs (currently 35% complete), obtain the latest information about the project, ask questions, and offer input to the project team.
WHAT IS THE PURPOSE OF THIS MEETING?
WHAT IS THE PLAN FOR THE EVENING?
6—8 PM OPEN HOUSE Sign in, review displays, provide input, ask questions, and enjoy refreshments
6:30—7 PM PRESENTATION Learn more about the project details.
SIGNAL PROJECT COST = $6.1M$5.2M in federal funds$900K in City funds
ROUNDABOUT PROJECT COST = $7.9M$5.2M in federal funds$2.7M in City funds
WHAT IS THE PROJECT SCHEDULE?
WHAT WILL THIS PROJECT COST?
November 30, 2011 First Open House with the entire Rural Roads area invited to provide input on intersection alternatives to be considered
June 13, 2012 City Council directed to proceed with a signal and a roundabout design
November, 2015 • Design advanced to the 35% level • Environmental field studies completed • Environmental technical reports approved by Caltrans (federal funding requirement)
December, 2015 City environmental document (IS/MND) completed and circulated for public review/comment
January 14, 2016 Community Open House
January 27, 2016 City Council Meeting
Summer 2016 Federal environmental documents approved by Caltrans and FHWA
Early 2017 Community Open House
Summer 2017 Right-of-way acquisition completed
Summer 2017 Final design completed
Fall 2017 Advertise for construction
Late 2017—2018 Construction
DATE MILESTONE
Here we are today!
WHAT IS BEING PROPOSED?
Improvements to the intersection of Sheldon Road and Bradshaw Road are planned because threshold values for increased traffic have been met, per the process outlined in the Rural Road Improvement Policy and Standards.
Based on community input and City Council direction, two options are being considered for the intersection: a signal or a roundabout. All proposed designs, currently 35% complete, take into consideration design preferences expressed in the Rural Road Improvement Policy and Standards.
Tonight we would like to get your input on these designs and understand your design preferences.
This Open House meeting is being held to provide the public an opportunity to review the proposed project, view project designs (currently 35% complete), obtain the latest information about the project, ask questions, and offer input to the project team.
WHAT IS THE PURPOSE OF THIS MEETING?
WHAT IS THE PLAN FOR THE EVENING?
6—8 PM OPEN HOUSE Sign in, review displays, provide input, ask questions, and enjoy refreshments
6:30—7 PM PRESENTATION Learn more about the project details.
SIGNAL PROJECT COST = $6.1M$5.2M in federal funds$900K in City funds
ROUNDABOUT PROJECT COST = $7.9M$5.2M in federal funds$2.7M in City funds
WHAT IS THE PROJECT SCHEDULE?
WHAT WILL THIS PROJECT COST?
November 30, 2011 First Open House with the entire Rural Roads area invited to provide input on intersection alternatives to be considered
June 13, 2012 City Council directed to proceed with a signal and a roundabout design
November, 2015 • Design advanced to the 35% level • Environmental field studies completed • Environmental technical reports approved by Caltrans (federal funding requirement)
December, 2015 City environmental document (IS/MND) completed and circulated for public review/comment
January 14, 2016 Community Open House
January 27, 2016 City Council Meeting
Summer 2016 Federal environmental documents approved by Caltrans and FHWA
Early 2017 Community Open House
Summer 2017 Right-of-way acquisition completed
Summer 2017 Final design completed
Fall 2017 Advertise for construction
Late 2017—2018 Construction
DATE MILESTONE
Here we are today!
Pleasant Grove High School9531 Bond Road
Elk Grove, CA 95624
JANUARY 14, 20166—8 PM
SHELDON ROAD & BRADSHAW ROAD
INTERSECTION IMPROVEMENT PROJECT
Tom Metcalf (916) 478-2281 [email protected]
City of Elk Grove Public Works Department 8401 Laguna Palms Way Elk Grove, CA 95758
CONTACT US
ROUNDABOUT INTERSECTION
ROUNDABOUT INTERSECTION OPTION
SIGNAL INTERSECTION OPTION
Sheldon RoadSheldon Road
Bra
dsh
aw R
oad
Bra
dsh
aw R
oad
Sheldon RoadSheldon Road
Bra
dsh
aw R
oad
Bra
dsh
aw R
oad
LEGEND:
Proposed Roadway
Proposed Paths
LEGEND:
Proposed Roadway
Proposed Paths