PREFERRED SHIPYARD DELIVERING SOLUTIONS ERHAMA BIN JABER AL JALAHMA SHIPYARD Shipyard’s Experience with BWMS Retrofits & Financing Initiative Presented By: Chandru Sirumal Rajwani (CEO of N-KOM)
Transcript
Page 1: Shipyard’s Experience with BWMS Retrofits & Financing ... · Shipyard’s Experience with BWMS Retrofits & Financing Initiative ... BALLAST WATER MANAGEMENT SYSTEM (BWMS) a. IMO

PREFERRED SHIPYARD DELIVERING SOLUTIONSERHAMA BIN JABER AL JALAHMA SHIPYARD

Shipyard’s Experience with BWMS

Retrofits & Financing Initiative

Presented By: Chandru Sirumal Rajwani (CEO of N-KOM)

Page 2: Shipyard’s Experience with BWMS Retrofits & Financing ... · Shipyard’s Experience with BWMS Retrofits & Financing Initiative ... BALLAST WATER MANAGEMENT SYSTEM (BWMS) a. IMO

CONTENTSI. ABOUT N-KOM

II. BALLAST WATER MANAGEMENT SYSTEM (BWMS)

a. IMO Convention 2004

b. Types of BWMS

III. N-KOM BWMS PROJECTS

a. LNGC VESSEL 1 (2013)

b. LNGC VESSEL 2 (2015)

c. VLCC TANKER (2013)

IV. OUR RECOMMENDATIONS

V. EXECUTION STRATEGIES

VI. N-KOM’s BWMS FINANCING SCHEME

Page 3: Shipyard’s Experience with BWMS Retrofits & Financing ... · Shipyard’s Experience with BWMS Retrofits & Financing Initiative ... BALLAST WATER MANAGEMENT SYSTEM (BWMS) a. IMO

Ship repair & conversion Refurbishment & construction Land rigs, Industrial Engineering

& Infrastructure

Nakilat-Keppel Offshore & Marine (N-KOM) is a joint-venture between Qatar Gas Transport Company (NAKILAT), the

world’s leading transporter of liquefied natural gas (LNG), and Keppel Offshore & Marine, the global leader in ship repair,

ship conversion and construction of offshore drilling rigs. N-KOM offers a wide array of repair, conversion and

fabrication services for marine and offshore vessels as well as and onshore structures.

Some of our main clients:

ABOUT N-KOM

Page 4: Shipyard’s Experience with BWMS Retrofits & Financing ... · Shipyard’s Experience with BWMS Retrofits & Financing Initiative ... BALLAST WATER MANAGEMENT SYSTEM (BWMS) a. IMO

Ship repair & conversion Refurbishment & construction Land rigs, Industrial Engineering

& Infrastructure

Leveraging on Keppel Offshore & Marine (KOM)’s strengths and expertise as one of the most established

yards in the maritime industry, N-KOM offers a wide range of services such as:

Ship repair & conversion

Gas solutions (e.g. ME-GI conversion, ISO tank fabrication, etc.)

Green Shipping Solutions (e.g. BWTS installation, Scrubber systems, etc.)

Flying squad (voyage/anchorage repairs)

ABOUT N-KOM

Page 5: Shipyard’s Experience with BWMS Retrofits & Financing ... · Shipyard’s Experience with BWMS Retrofits & Financing Initiative ... BALLAST WATER MANAGEMENT SYSTEM (BWMS) a. IMO

ABOUT N-KOM

Handy-size Floating Dock (Future)

Q-Max Floating Dock (405m x 66m)

Quays & piers: 2,400m

Drydock 1360m x 66m

Drydock 2400m x 80m

Fabrication & Laydown Area

(Un)Loading quay: 150m

Small vessel repair facility (Phase 5)

Sub-contractor Facility

Warehouse

Client Offices

Machinery & Electrical workshop Piping workshop

Main Office Building Blasting & painting chamber

Steel workshopClinic & Fire station

Total Fabrication Area:

505,810sqm

Page 7: Shipyard’s Experience with BWMS Retrofits & Financing ... · Shipyard’s Experience with BWMS Retrofits & Financing Initiative ... BALLAST WATER MANAGEMENT SYSTEM (BWMS) a. IMO

Ship repair & conversion Refurbishment & construction Land rigs, Industrial Engineering

& Infrastructure

BWMS: TYPES OF SYSTEMSBWTS

Mechanical

Filtration

Magnetic

Separation

Hydro cyclone

Physical

Thermal

(heat)

Ultraviolet

Irradiation

Ultrasound

Cavitation

Inert Gas

DE oxygenation

Chemical

Disinfection

Biocides

Electrolysis/

Electro chlorination

Keppel Shipyards has completed three projects based on this system

Page 8: Shipyard’s Experience with BWMS Retrofits & Financing ... · Shipyard’s Experience with BWMS Retrofits & Financing Initiative ... BALLAST WATER MANAGEMENT SYSTEM (BWMS) a. IMO

N-KOM BWMS PROJECTS

SECTION WORKSCOPE DETAILS

PIPING Total 12 spools removed, modified and rubber

lined

6x24”, 2x16”, 1x14”, 1x12”, 2x6” spools

removed, modified and rubber-Lined

STEELWORKS 11 tons steel work 3 support platforms in engine room, 4 support frames in steering

room

ELECTRICAL Cable penetration and MCT Access for cable laying from C2E skid to engine room equipment

EQUIPMENT 13 pcs of equipment installed in engine room 2 main filter units, 2 C2E skids, 4 sludge pumps and 2 TRO panels

in engine room

1 C2E unit and 1 steam heater unit in steering room

LNG Carrier 1 (2013)

Vendor: Ocean Saver

Type: MARK II 3000m3/ hr capacity Electrolysis-based system

Shipyard Workscope:

Project Duration: 21 days (10 days in dock)

Note: This was the first BWTS project for N-KOM.

Page 9: Shipyard’s Experience with BWMS Retrofits & Financing ... · Shipyard’s Experience with BWMS Retrofits & Financing Initiative ... BALLAST WATER MANAGEMENT SYSTEM (BWMS) a. IMO

N-KOM BWMS PROJECTS

Installation of main filter and sludge pumps

Installation of C2E filters Installation of C2E filters

Installation of steam heater

LNG Carrier 1 (2013)

Page 10: Shipyard’s Experience with BWMS Retrofits & Financing ... · Shipyard’s Experience with BWMS Retrofits & Financing Initiative ... BALLAST WATER MANAGEMENT SYSTEM (BWMS) a. IMO

N-KOM BWMS PROJECTSLNG Carrier 2 (2015)

Vendor: Samsung Heavy Industries

Type: 6000 m3/hr SHI Purimar TM Electrolysis-based system

Shipyard Workscope:

SECTION WORKSCOPE DETAILS

PIPING 160 spools were installed for the system 80 * 24”, 51* 3”, 20* 8” spools in engine room

STEELWORKS No major steel work required except

foundation installation

4 support frames in steering room, 3 support platforms in engine

room bottom floor

ELECTRICAL Power cable & control cable laying Bus bar modification

2.6 kms cable laying

10 cable conduits opened for the same

EQUIPMENT 109 Spools lifted and shifted in location,

Total 120 lifts for spools and equipment

2 filter units

1 electrolysis unit

1 neutralization unit

2 booster pumps

Project Duration: 21 days (12 days in dock)

Note: This was a turn-key BWMS retrofit project for the ship owner.

Page 11: Shipyard’s Experience with BWMS Retrofits & Financing ... · Shipyard’s Experience with BWMS Retrofits & Financing Initiative ... BALLAST WATER MANAGEMENT SYSTEM (BWMS) a. IMO

N-KOM BWMS PROJECTSLNG Carrier 2 (2015)

Installation of Electrolysis Unit

Installation of 8” Vent Line

Installation of filter units

Installation of 24” Ballast line spool

Page 12: Shipyard’s Experience with BWMS Retrofits & Financing ... · Shipyard’s Experience with BWMS Retrofits & Financing Initiative ... BALLAST WATER MANAGEMENT SYSTEM (BWMS) a. IMO

N-KOM BWMS PROJECTS

SECTION WORKSCOPE DETAILS

PIPING Total 720 spools installed Out of 720, 600 spools fabricated by yard and 120 OFE

STEELWORKS No major steel work required except Foundation installation for most equipment

ELECTRICAL Power cable & control cable laying 950 mtrs of tubing run & installations

9.7 kms cable laying

EQUIPMENTS 34nos. new equipment & panel installation 3 filters installed

VLCC (2013)

Vendor: JFE Ballast ACE System

Shipyard Workscope:

Duration

Pre-fabrication: 1 month

Installation: 12 days

Note: The project was undertaken by our parent company Keppel Shipyard. This is also the first BWTS

retrofit project for a VLCC in Singapore.

Page 13: Shipyard’s Experience with BWMS Retrofits & Financing ... · Shipyard’s Experience with BWMS Retrofits & Financing Initiative ... BALLAST WATER MANAGEMENT SYSTEM (BWMS) a. IMO

N-KOM BWMS PROJECTSVLCC (2013)

Installation of new Filter in pump room Installation of NaClO tank

Installation of Na2So3 Tank Installation of new solenoid valve panel

Page 14: Shipyard’s Experience with BWMS Retrofits & Financing ... · Shipyard’s Experience with BWMS Retrofits & Financing Initiative ... BALLAST WATER MANAGEMENT SYSTEM (BWMS) a. IMO

OUR RECOMMENDATIONS Once the vendor/system and shipyard has been selected, the owner should establish

a communication channel between the shipyard and the vendor ASAP.

Depending the chosen execution strategy, a project manager, either from the

shipyard or from the vendor, should lead the execution. Our experience is that

vendors have difficulties managing retrofits outside their premises.

Our experience has shown that it is most efficient and economic to allow the shipyard

to produce the simple but bulky part of the equipment such as the pipe spools.

Clear demarcation list between yard, owner and vendor supplies.

Logistics and planning should be robust to ensure timely execution.

Page 15: Shipyard’s Experience with BWMS Retrofits & Financing ... · Shipyard’s Experience with BWMS Retrofits & Financing Initiative ... BALLAST WATER MANAGEMENT SYSTEM (BWMS) a. IMO

EXECUTION STRATEGIES

HOLISTIC PROJECT MANAGEMENT & EXECUTION

Close coordination with vendor during design layout stage

Equipment procurement, pre-fabrication, construction & modification

Co-commissioning with vendor

After sales service

Page 16: Shipyard’s Experience with BWMS Retrofits & Financing ... · Shipyard’s Experience with BWMS Retrofits & Financing Initiative ... BALLAST WATER MANAGEMENT SYSTEM (BWMS) a. IMO

EXECUTION STRATEGIESHOLISTIC PROJECT MANAGEMENT & EXECUTION

OWNER ENGAGEMENT VENDOR ENGAGEMENT SHIPYARD ENGAGEMENT

CHOOSE THE VENDOR FOR THE BWMS SYSTEM

DESIGN & ENGINEERING INPUTS FOR THE EQUIPMENT

COORDINATE WITH VENDOR DURING THE SYSTEM LAYOUT 3-D plan developments Site visits

PROCUREMENT OF EQUIPMENTS

LOGISTICS OF THE MATERIALS

PRE-FABRICATION OF MATERIALS

PROJECT MANAGEMENT Refit schedule Modification of the existing system Installation of the new system

CO-COMMISSIONING OF THE SYSTEM WITH THE VENDOR

AFTER -SALES SERVICE Post-maintenance / service

Page 17: Shipyard’s Experience with BWMS Retrofits & Financing ... · Shipyard’s Experience with BWMS Retrofits & Financing Initiative ... BALLAST WATER MANAGEMENT SYSTEM (BWMS) a. IMO

N-KOM’S BWMS FINANCING

SCHEME

NKOM

CLIENT

NKOM Project Account at QDB

CLIENT pays Advance Payment

against BG

QDB pays NKOM as per Discounting

Agreement over the Conversion

Period

CLIENT pays in N instalments as per

Conversion /Retrofit Agreement

over the agreed period of typically

12-24 months

ConversionRetrofit

Agreement

Financing Agreement

QDB

Conversion/Retrofit Agreement between

Client and N-KOM

Long Payment Terms Scheme based on

Guarantees. Form of guarantees to be

assessed and agreed.

Long Payment Clause in Agreement with

provisions (Sale, Loss etc.)

N-KOM raises the financing through QDB

against these guarantees

Typical Payment Period between 12 and 24

months

Project-specific account at QDB

*QDB: Qatar Development Bank

Page 18: Shipyard’s Experience with BWMS Retrofits & Financing ... · Shipyard’s Experience with BWMS Retrofits & Financing Initiative ... BALLAST WATER MANAGEMENT SYSTEM (BWMS) a. IMO

N-KOM’S BWMS FINANCING

SCHEME

Page 19: Shipyard’s Experience with BWMS Retrofits & Financing ... · Shipyard’s Experience with BWMS Retrofits & Financing Initiative ... BALLAST WATER MANAGEMENT SYSTEM (BWMS) a. IMO

THANK YOU!