PREFERRED SHIPYARD DELIVERING SOLUTIONSERHAMA BIN JABER AL JALAHMA SHIPYARD
Shipyard’s Experience with BWMS
Retrofits & Financing Initiative
Presented By: Chandru Sirumal Rajwani (CEO of N-KOM)
CONTENTSI. ABOUT N-KOM
II. BALLAST WATER MANAGEMENT SYSTEM (BWMS)
a. IMO Convention 2004
b. Types of BWMS
III. N-KOM BWMS PROJECTS
a. LNGC VESSEL 1 (2013)
b. LNGC VESSEL 2 (2015)
c. VLCC TANKER (2013)
IV. OUR RECOMMENDATIONS
V. EXECUTION STRATEGIES
VI. N-KOM’s BWMS FINANCING SCHEME
Ship repair & conversion Refurbishment & construction Land rigs, Industrial Engineering
& Infrastructure
Nakilat-Keppel Offshore & Marine (N-KOM) is a joint-venture between Qatar Gas Transport Company (NAKILAT), the
world’s leading transporter of liquefied natural gas (LNG), and Keppel Offshore & Marine, the global leader in ship repair,
ship conversion and construction of offshore drilling rigs. N-KOM offers a wide array of repair, conversion and
fabrication services for marine and offshore vessels as well as and onshore structures.
Some of our main clients:
ABOUT N-KOM
Ship repair & conversion Refurbishment & construction Land rigs, Industrial Engineering
& Infrastructure
Leveraging on Keppel Offshore & Marine (KOM)’s strengths and expertise as one of the most established
yards in the maritime industry, N-KOM offers a wide range of services such as:
Ship repair & conversion
Gas solutions (e.g. ME-GI conversion, ISO tank fabrication, etc.)
Green Shipping Solutions (e.g. BWTS installation, Scrubber systems, etc.)
Flying squad (voyage/anchorage repairs)
ABOUT N-KOM
ABOUT N-KOM
Handy-size Floating Dock (Future)
Q-Max Floating Dock (405m x 66m)
Quays & piers: 2,400m
Drydock 1360m x 66m
Drydock 2400m x 80m
Fabrication & Laydown Area
(Un)Loading quay: 150m
Small vessel repair facility (Phase 5)
Sub-contractor Facility
Warehouse
Client Offices
Machinery & Electrical workshop Piping workshop
Main Office Building Blasting & painting chamber
Steel workshopClinic & Fire station
Total Fabrication Area:
505,810sqm
BWMS: IMO CONVENTION 2004
Convention shall enter into force 12 months after the date on which not less
than 30 States, the combined merchant fleets of which constitute not less
than 35% of the gross tonnage of the world’s merchant shipping have
ratified it.
Not yet in force as 44 states of 32.89% of world gross tonnage have ratified
it.
Ship repair & conversion Refurbishment & construction Land rigs, Industrial Engineering
& Infrastructure
BWMS: TYPES OF SYSTEMSBWTS
Mechanical
Filtration
Magnetic
Separation
Hydro cyclone
Physical
Thermal
(heat)
Ultraviolet
Irradiation
Ultrasound
Cavitation
Inert Gas
DE oxygenation
Chemical
Disinfection
Biocides
Electrolysis/
Electro chlorination
Keppel Shipyards has completed three projects based on this system
N-KOM BWMS PROJECTS
SECTION WORKSCOPE DETAILS
PIPING Total 12 spools removed, modified and rubber
lined
6x24”, 2x16”, 1x14”, 1x12”, 2x6” spools
removed, modified and rubber-Lined
STEELWORKS 11 tons steel work 3 support platforms in engine room, 4 support frames in steering
room
ELECTRICAL Cable penetration and MCT Access for cable laying from C2E skid to engine room equipment
EQUIPMENT 13 pcs of equipment installed in engine room 2 main filter units, 2 C2E skids, 4 sludge pumps and 2 TRO panels
in engine room
1 C2E unit and 1 steam heater unit in steering room
LNG Carrier 1 (2013)
Vendor: Ocean Saver
Type: MARK II 3000m3/ hr capacity Electrolysis-based system
Shipyard Workscope:
Project Duration: 21 days (10 days in dock)
Note: This was the first BWTS project for N-KOM.
N-KOM BWMS PROJECTS
Installation of main filter and sludge pumps
Installation of C2E filters Installation of C2E filters
Installation of steam heater
LNG Carrier 1 (2013)
N-KOM BWMS PROJECTSLNG Carrier 2 (2015)
Vendor: Samsung Heavy Industries
Type: 6000 m3/hr SHI Purimar TM Electrolysis-based system
Shipyard Workscope:
SECTION WORKSCOPE DETAILS
PIPING 160 spools were installed for the system 80 * 24”, 51* 3”, 20* 8” spools in engine room
STEELWORKS No major steel work required except
foundation installation
4 support frames in steering room, 3 support platforms in engine
room bottom floor
ELECTRICAL Power cable & control cable laying Bus bar modification
2.6 kms cable laying
10 cable conduits opened for the same
EQUIPMENT 109 Spools lifted and shifted in location,
Total 120 lifts for spools and equipment
2 filter units
1 electrolysis unit
1 neutralization unit
2 booster pumps
Project Duration: 21 days (12 days in dock)
Note: This was a turn-key BWMS retrofit project for the ship owner.
N-KOM BWMS PROJECTSLNG Carrier 2 (2015)
Installation of Electrolysis Unit
Installation of 8” Vent Line
Installation of filter units
Installation of 24” Ballast line spool
N-KOM BWMS PROJECTS
SECTION WORKSCOPE DETAILS
PIPING Total 720 spools installed Out of 720, 600 spools fabricated by yard and 120 OFE
STEELWORKS No major steel work required except Foundation installation for most equipment
ELECTRICAL Power cable & control cable laying 950 mtrs of tubing run & installations
9.7 kms cable laying
EQUIPMENTS 34nos. new equipment & panel installation 3 filters installed
VLCC (2013)
Vendor: JFE Ballast ACE System
Shipyard Workscope:
Duration
Pre-fabrication: 1 month
Installation: 12 days
Note: The project was undertaken by our parent company Keppel Shipyard. This is also the first BWTS
retrofit project for a VLCC in Singapore.
N-KOM BWMS PROJECTSVLCC (2013)
Installation of new Filter in pump room Installation of NaClO tank
Installation of Na2So3 Tank Installation of new solenoid valve panel
OUR RECOMMENDATIONS Once the vendor/system and shipyard has been selected, the owner should establish
a communication channel between the shipyard and the vendor ASAP.
Depending the chosen execution strategy, a project manager, either from the
shipyard or from the vendor, should lead the execution. Our experience is that
vendors have difficulties managing retrofits outside their premises.
Our experience has shown that it is most efficient and economic to allow the shipyard
to produce the simple but bulky part of the equipment such as the pipe spools.
Clear demarcation list between yard, owner and vendor supplies.
Logistics and planning should be robust to ensure timely execution.
EXECUTION STRATEGIES
HOLISTIC PROJECT MANAGEMENT & EXECUTION
Close coordination with vendor during design layout stage
Equipment procurement, pre-fabrication, construction & modification
Co-commissioning with vendor
After sales service
EXECUTION STRATEGIESHOLISTIC PROJECT MANAGEMENT & EXECUTION
OWNER ENGAGEMENT VENDOR ENGAGEMENT SHIPYARD ENGAGEMENT
CHOOSE THE VENDOR FOR THE BWMS SYSTEM
DESIGN & ENGINEERING INPUTS FOR THE EQUIPMENT
COORDINATE WITH VENDOR DURING THE SYSTEM LAYOUT 3-D plan developments Site visits
PROCUREMENT OF EQUIPMENTS
LOGISTICS OF THE MATERIALS
PRE-FABRICATION OF MATERIALS
PROJECT MANAGEMENT Refit schedule Modification of the existing system Installation of the new system
CO-COMMISSIONING OF THE SYSTEM WITH THE VENDOR
AFTER -SALES SERVICE Post-maintenance / service
N-KOM’S BWMS FINANCING
SCHEME
NKOM
CLIENT
NKOM Project Account at QDB
CLIENT pays Advance Payment
against BG
QDB pays NKOM as per Discounting
Agreement over the Conversion
Period
CLIENT pays in N instalments as per
Conversion /Retrofit Agreement
over the agreed period of typically
12-24 months
ConversionRetrofit
Agreement
Financing Agreement
QDB
Conversion/Retrofit Agreement between
Client and N-KOM
Long Payment Terms Scheme based on
Guarantees. Form of guarantees to be
assessed and agreed.
Long Payment Clause in Agreement with
provisions (Sale, Loss etc.)
N-KOM raises the financing through QDB
against these guarantees
Typical Payment Period between 12 and 24
months
Project-specific account at QDB
*QDB: Qatar Development Bank
N-KOM’S BWMS FINANCING
SCHEME
THANK YOU!