+ All Categories
Home > Documents > St. Louis District Construction (FRM) · 2016-09-15 · Last Update: 1 September 2016 St. Louis...

St. Louis District Construction (FRM) · 2016-09-15 · Last Update: 1 September 2016 St. Louis...

Date post: 24-Apr-2020
Category:
Upload: others
View: 4 times
Download: 0 times
Share this document with a friend
2
Last Update: 1 September 2016 St. Louis District Construction (FRM) Location: The project is located on the right bank of the Mississippi River and is predominately in Perry County, Missouri, but has a small part in Randolph County, Illinois. The existing project consists of 33.1 miles of levee, 341 relief wells, and 4 pump stations. Description: The main deficiencies in the project are underseepage and inadequate levee grade (2 to 4 feet below net levee grade) along sections of the back levee. Until these are corrected, the levee is at an increased risk of failure during a flood at net levee grade. The deficiency correction project will provide additional underseepage control measures in the form of 297 relief wells, seepage berms, and a seepage cutoff trench; ditching and culvert improvements; three additional pump stations; and restoring the elevation of some parts of the back levee. One hundred fifteen relief wells have been constructed to date. Issues: The Energy and Water Development Appropriations Act of 2002 provided directive language to undertake design deficiency repairs and cost sharing consistent with the original project authorization. Construction is 100 percent Federal; the sponsor provides lands and relocations. Cost- sharing for the deficiency correction project is inconsistent with Administration policy of 65/35 cost share; therefore, it is unlikely that the Administration will include the project in future presidential budgets. Remaining benefit-remaining cost ratio is 2.7 to 1 at 7 percent. Importance: The Bois Brule Levee and Drainage District protects approximately 26,000 acres of primarily agricultural land, two industries, the Perryville airport and a highway connecting to the bridge crossing the Mississippi River to Chester, IL. Risk: Without correction of design deficiencies, the entire District has reduced levels of flood protection. With the existing underseepage issues, sudden failure of the levee can occur at several locations along the levee at a river stage below net levee grade, placing human life, vehicles, building, industrial equipment, livestock and agricultural production at risk. Consequence: The levee failed due to underseepage prior to the crest of the 1993 flood, flooding the entire levee district with to a depth of 20 feet. Failures due to underseepage can occur very rapidly with little warning. Missouri Chute Pump Station Activities for FY 16: Funds are being used to design and award construction contracts for the Jones Cutoff and Cinque Hommes pump stations and 52 relief wells and to initiate design of additional underseepage measures. Funds are also being used to continue storage of existing mechanical equipment for the Cinque Hommes and Jones Cutoff pump stations as well as to provide construction oversight of the Missouri Chute ditching/culvert/berm contract. Acquisition Strategy: Unrestricted. Amount That Could Be Used in FY 17: Funds will be used to oversee construction of the pump stations and relief wells awarded in FY16. An amount of $8,400,000 could be used for deficiency correction work to include additional relief wells, a seepage berms, a road and levee raise, and ditching and culverts drainage systems. Project Sponsor/Customer: Bois Brule Levee and Drainage District. Congressional Interest: Senate: Blunt (MO) and McCaskill (MO) House: Jason Smith (MO-8) Phase FY 16 Allocation FY 17 Budget FY 17 Total Capability Construction $13,000,000 $0 $8,400,000 Project Fact Sheet Bois Brule, MO (Deficiency Correction) Flood Control Acts of 1936 and 1965
Transcript
Page 1: St. Louis District Construction (FRM) · 2016-09-15 · Last Update: 1 September 2016 St. Louis District Construction (FRM) Location: The project is located on the right bank of the

Last Update: 1 September 2016

St. Louis District

Construction (FRM)

Location: The project is located on the right bank of the

Mississippi River and is predominately in Perry County,

Missouri, but has a small part in Randolph County, Illinois.

The existing project consists of 33.1 miles of levee, 341

relief wells, and 4 pump stations.

Description: The main deficiencies in the project are

underseepage and inadequate levee grade (2 to 4 feet below

net levee grade) along sections of the back levee. Until these

are corrected, the levee is at an increased risk of failure

during a flood at net levee grade. The deficiency correction

project will provide additional underseepage control

measures in the form of 297 relief wells, seepage berms, and

a seepage cutoff trench; ditching and culvert improvements;

three additional pump stations; and restoring the elevation of

some parts of the back levee. One hundred fifteen relief

wells have been constructed to date.

Issues: The Energy and Water Development Appropriations

Act of 2002 provided directive language to undertake design

deficiency repairs and cost sharing consistent with the

original project authorization. Construction is 100 percent

Federal; the sponsor provides lands and relocations. Cost-

sharing for the deficiency correction project is inconsistent

with Administration policy of 65/35 cost share; therefore, it

is unlikely that the Administration will include the project in

future presidential budgets. Remaining benefit-remaining

cost ratio is 2.7 to 1 at 7 percent.

Importance: The Bois Brule Levee and Drainage District

protects approximately 26,000 acres of primarily

agricultural land, two industries, the Perryville airport and a

highway connecting to the bridge crossing the Mississippi

River to Chester, IL.

Risk: Without correction of design deficiencies, the entire

District has reduced levels of flood protection. With the

existing underseepage issues, sudden failure of the levee can

occur at several locations along the levee at a river stage

below net levee grade, placing human life, vehicles,

building, industrial equipment, livestock and agricultural

production at risk.

Consequence: The levee failed due to underseepage prior

to the crest of the 1993 flood, flooding the entire levee

district with to a depth of 20 feet. Failures due to

underseepage can occur very rapidly with little warning.

Missouri Chute Pump Station

Activities for FY 16: Funds are being used to design and

award construction contracts for the Jones Cutoff and

Cinque Hommes pump stations and 52 relief wells and to

initiate design of additional underseepage measures. Funds

are also being used to continue storage of existing

mechanical equipment for the Cinque Hommes and Jones

Cutoff pump stations as well as to provide construction

oversight of the Missouri Chute ditching/culvert/berm

contract.

Acquisition Strategy: Unrestricted.

Amount That Could Be Used in FY 17: Funds will be

used to oversee construction of the pump stations and relief

wells awarded in FY16. An amount of $8,400,000 could be

used for deficiency correction work to include additional

relief wells, a seepage berms, a road and levee raise, and

ditching and culverts drainage systems.

Project Sponsor/Customer: Bois Brule Levee and

Drainage District.

Congressional Interest: Senate: Blunt (MO) and

McCaskill (MO) House: Jason Smith (MO-8)

Phase

FY 16

Allocation

FY 17

Budget

FY 17

Total Capability

Construction $13,000,000 $0 $8,400,000

Project Fact Sheet Bois Brule, MO – (Deficiency Correction)

Flood Control Acts of 1936 and 1965

Page 2: St. Louis District Construction (FRM) · 2016-09-15 · Last Update: 1 September 2016 St. Louis District Construction (FRM) Location: The project is located on the right bank of the

CB

CB

CB

CBCB

CB

CBCB

CBCB

CBCBCBCBCBCB

CBCB

CBCBCB

CB

CB

£¤61

¡¢55

MO

IL115

110

105

95

100

MISSISSIPPI

RIVER

MARYSRIVER

Randolph

Perry

Jackson

I

Legend Location in DistrictVicinity Map

MOIL IL

MO

9/6/2016 9:53:57 AM

0 2 41Miles

BOIS BRULE DRAINAGE & LEVEE DISTRICTCONSTRUCTION

Document Path: T:\Gis\PM\BudgetMaps\FY 2016 Budget EC-2-206 Final\mxd\New Map Standards\2016\Construction\Bois_Brule_Drainage and Levee.mxd

USACE: St. Louis District, Geospatial Engineering Branch

Pump Station

Cinque Holmes AreaSt Louis District BoundaryLevee Protected AreaState

Relief Well LineCut Off WallSeepage BermLevee Raise Road RelocationInterstate HighwayUS HighwayBoisBruleLevee

WORK PROPOSED WITH FUNDS REQUESTEDFOR THE BUDGET FISCAL YEAR.

WORK COMPLETED.

WORK UNDERWAY WITH FUNDS AVAILABLEFOR THE CURRENT FISCAL YEAR.

WORK REQUIRED TO COMPLETE THE PROJECTAFTER THE BUDGET FISCAL YEAR.

PROJECT AREA

BOIS BRULEDRAINAGE & LEVEE

LEVEE RAISESEEPAGE BERM

ADDITIONAL RELIEF WELLS PIEZOMETERS

JONES CUTOFF#2 PUMP STATION

CINQUES HOMMES#2 PUMP STATION


Recommended