2
System Start up 1. Turn the power strip (#1) next to the computer. 2. Start PC (#2) and WAIT until you get to the Windows desktop. 3. Turn on Ibidi 37 o C/CO 2 /O 2 environmental controller if needed (note: system requires ~30min to equilibrate) 4. Log in Windows using UIC User account. 5. Log in with UIC iLab account information. 6. Start NIS-Elements from desktop icon. Shutdown of System 1. Transfer saved files to removable media, or server. Do not leave your files on the computer. NEVER save any files to the C: drive. 2. Close all applications. Select Shutdown BEFORE logging out of iLab when done (if no one is waiting). 3. Clean up. 4. Become rich and famous! Startup and Shutdown Procedures for the UIC CCRB Nikon TiE Deconvolution Microscope
Transcript
Page 1: Startup and Shutdown Procedures for the UIC CCRB …uic.umn.edu/sites/uic.umn.edu/files/tie_startup.pdf · Shutdown of System! ... Startup and Shutdown Procedures for the ! UIC CCRB

System Start up 1.  Turn the power strip (#1) next to the

computer. 2.  Start PC (#2) and WAIT until you get to the

Windows desktop. 3.  Turn on Ibidi 37oC/CO2/O2 environmental

controller if needed (note: system requires ~30min to equilibrate)

4.  Log in Windows using UIC User account. 5.  Log in with UIC iLab account information. 6.  Start NIS-Elements from desktop icon. Shutdown of System 1. Transfer saved files to removable media, or server. Do

not leave your files on the computer. NEVER save any files to the C: drive.

2.  Close all applications. Select Shutdown BEFORE logging out of iLab when done (if no one is waiting).

3.  Clean up. 4.  Become rich and famous!

Startup and Shutdown Procedures for the UIC CCRB Nikon TiE Deconvolution Microscope

Page 2: Startup and Shutdown Procedures for the UIC CCRB …uic.umn.edu/sites/uic.umn.edu/files/tie_startup.pdf · Shutdown of System! ... Startup and Shutdown Procedures for the ! UIC CCRB

1.  Turn the power strip (Environmental

stage) next to the Ibidi controllers. Note: system requires ~30min to equilibrate

2.  Tilt transmitted light head back. 3.  Remove stage screws and stage.

4.  Install 96-well plate insert. 5.  Install correct insert for Ibidi stage

(slide or 35mm dish)

Procedure for the UIC CCRB Ibidi Slide/Dish Envirnonmental Chamber on

Nikon TiE Deconvolution Microscope