+ All Categories
Home > Documents > Status of LHC Operations

Status of LHC Operations

Date post: 19-Mar-2016
Category:
Upload: garron
View: 29 times
Download: 1 times
Share this document with a friend
Description:
Status of LHC Operations. R. Assmann for the LHC commissioning team and LHC teams & groups LPCC 23.7.2010. Outline. Stable beams for requested 100 nb-1 plus more Increasing intensity to > 10 12 p at injection Issues during stable beams Optimizing conditions in collision - PowerPoint PPT Presentation
Popular Tags:
35
Status of LHC Operations R. Assmann for the LHC commissioning team and LHC teams & groups LPCC 23.7.2010 23.7.2010 1 LPCC, R. Assmann
Transcript
Page 1: Status of LHC Operations

LPCC, R. Assmann 1

Status of LHC Operations

R. Assmannfor the LHC commissioning team and LHC teams & groups

LPCC 23.7.2010

23.7.2010

Page 2: Status of LHC Operations

LPCC, R. Assmann 2

Outline

Stable beams for requested 100 nb-1 plus more

Increasing intensity to > 1012 p at injection

Issues during stable beams

Optimizing conditions in collision

Analysis of record physics fill

Intensity outlook

Conclusion

23.7.2010

Page 3: Status of LHC Operations

LPCC, R. Assmann 3

Stable Beams for Requested 100 nb-1

23.7.2010

ca. 70 nb-1 in last fill!

Approach with high bunch intensity paid off (investment of commissioning time)

9e10 p per bunch up to 13 bunches

Page 4: Status of LHC Operations

LPCC, R. Assmann 4

Collision Scheme (LPC, M. Ferro-Luzzi)

23.7.2010

8 collisions per IP

Page 5: Status of LHC Operations

LPCC, R. Assmann 5

Increasing intensity to > 1012 p at injection

No interlock masking allowed at high intensities, even at injection.

Transfer line trajectories drifting away. Incoming tails from SPS. Improved setup of transfer lines, injection protection

and collimation required. B. Goddard, C. Bracco, M. Meddahi and team

23.7.2010

Page 6: Status of LHC Operations

LPCC, R. Assmann 6

Increasing intensity to > 1012 p at injection

23.7.2010

Wrong polarity BPM

Excellent agreement with model

Page 7: Status of LHC Operations

LPCC, R. Assmann 7

Increasing intensity to > 1012 p at injection

23.7.2010

Page 8: Status of LHC Operations

LPCC, R. Assmann 8

Tunnel View

Collimation Team

23.7.2010

Transfer line collimator

Ring magnets with beam loss monitors

Page 9: Status of LHC Operations

LPCC, R. Assmann 9

Increasing intensity to > 1012 p at injection

23.7.2010

With SPS scrapers

Page 10: Status of LHC Operations

LPCC, R. Assmann 10

Issues During Stable Beams

We are learning continually and solver issue after issue: Losses during stable beams Orbit Transverse damper RF noise

23.7.2010

Page 11: Status of LHC Operations

LPCC, R. Assmann 11

Losses during stable beams (9.7.)

23.7.2010

Intensity B1

Intensity B2

Page 12: Status of LHC Operations

LPCC, R. Assmann 12

Losses during stable beams (9.7.)

23.7.2010

Takes place at collimators in cleaning insertions OK

Page 13: Status of LHC Operations

LPCC, R. Assmann 13

Losses during stable beams (9.7.)

23.7.2010

Losses Peak at 0.315

All beams, all planes!

Page 14: Status of LHC Operations

LPCC, R. Assmann 14

Losses during stable beams (9.7.)

23.7.2010

HUMP

Tunes

R. Steinhagen

Page 15: Status of LHC Operations

LPCC, R. Assmann 15

Losses during stable beams (9.7.)

23.7.2010

Losses only in first 4 bunches from bucket 1 onwards!

Page 16: Status of LHC Operations

LPCC, R. Assmann 16

Lifetime 12.7. – “Regular” Drops

23.7.2010

crossingcollision

12.7.

Not easily avoidable losses in operation…

Page 17: Status of LHC Operations

LPCC, R. Assmann 17

Orbit control in IR: After normal correction

23.7.2010

Bumps in IR’s

Real?

YES Correct

NO Leave it in

Page 18: Status of LHC Operations

LPCC, R. Assmann 18

Orbit control in IR: H correction IR1

23.7.2010

30% of correction sent

Page 19: Status of LHC Operations

LPCC, R. Assmann 19

Orbit control in IR: Problem with Crossing Angle

23.7.2010

Non-closure when putting crossing angle…

Page 20: Status of LHC Operations

Orbit in the ramp fill 1232

20

Orbit correction became unstable – seemed to be coming from IR4.

Orbit FB switches off. Switch on worked, instability disappeared!

Very good stability

50 mm rms !!

LPCC, R. Assmann23.7.2010

Page 21: Status of LHC Operations

Ghost bunches

Small ghost bunches around main bunches reported by the experiments. Intensity at the level of 0.1% of the main bunch.

Ghost bunches confirmed measurements of the RF group. Bunches extend up to -80 ns. Spacing is 5 ns. Abort gap population isbelow 5E6 p/bucket (exceptfor messy 80 ns).

Problem: Collision ofghost bunches withone of nominal bunches

21 LPCC, R. Assmann23.7.2010

RF group

Page 22: Status of LHC Operations

LPCC, R. Assmann 22

Losses from RF bucket

23.7.2010

Page 23: Status of LHC Operations

LPCC, R. Assmann 23

Losses from RF bucket

23.7.2010

Use momentum-collimators (IR3) for cleaning uncaptured beam before beam dump!

Page 24: Status of LHC Operations

LPCC, R. Assmann 24

Losses from RF bucket

23.7.2010

Cleaning of uncaptured beam

Page 25: Status of LHC Operations

LPCC, R. Assmann 25

Transverse Damper in Stable Beams

23.7.2010

Damper off

Damper off

Damper noise reduction beam 2

Damper on

Damper on

W. Hoefle et al

Page 26: Status of LHC Operations

LPCC, R. Assmann 26

Optimizing conditions in collision

Various measures done in parallel… Beam-beam investigation ongoing. Equalize beam parameters:

Blow-up of longitudinal emittances to have nominal values. Blow-up of transverse emittances to have nominal values. Equalize bunch currents and B1/B2 currents by more stringent

injection process, good 450 GeV orbit correction. Minimize losses at flat top (crossing angle in steps, skip chromaticity

measurement for best fill, only manual IP scans, …). Use of transverse damper with reduced noise at 3.5 TeV. Increased B1/B2 tune split: 0.003 0.005

23.7.2010

Page 27: Status of LHC Operations

LPCC, R. Assmann 27

Record physics fill: Intensities

23.7.2010

only ~20 % loss of intensity over 19 h

~ 1% per hour excellent!

No lumi burn-off: 3.5 TeV, higher b*

19 hours stable beam

Page 28: Status of LHC Operations

LPCC, R. Assmann 28

Record physics fill: Peak luminosity

23.7.2010

Requested limit on peak lumi for LHC-b

Requested limit on peak lumi for ALICE

Page 29: Status of LHC Operations

LPCC, R. Assmann 29

Record physics fill: Bunch Specific Luminosity

23.7.2010

should be constant without emittance growth

Page 30: Status of LHC Operations

LPCC, R. Assmann 30

Record physics fill: Lumi Measured & Calculated

23.7.2010

calculated with measured bunch intensity, nominal ge = 3.75 mm and b*=3.5m

Emittance growth

ATLASCMS

CALCULATED

Machine parameters very well controlled!

Page 31: Status of LHC Operations

LPCC, R. Assmann 31

Effective Average Emittance Growth

23.7.2010

~ 0.13 mm rad per hour1.0 mm rad per hour at 450 GeV

Page 32: Status of LHC Operations

LPCC, R. Assmann 32

Beam-beam parameter

23.7.2010

Emittance growth

assuming nominal emittance

from measured charge and luminosity

~ design beam-beam parameter!

ξ =rp ⋅N4π ⋅ε n

Page 33: Status of LHC Operations

LPCC, R. Assmann 33

Intensity outlook LHC performs already outstanding… We are high already:

Presently we have established: ~ 0.7 MJ Remember: Beams are much smaller at LHC and 3.5 TeV! Transverse energy density is already ~ 7 MJ/mm2 at some relevant

locations. Far beyond previous CERN experience (ISR), HERA and Tevatron!

We want to increase from 0.7 MJ to 1.4 MJ the next days. Then plan for multi-week stable period without changes! What limits the increase in intensity?

No immediate danger, otherwise we would have to drop intensity. I have shown that we have still frequent non-conform issues. Use stable period to sort them out and then push ahead! Must always be prepared for infrequent problems (irregular dumps)!

23.7.2010

Page 34: Status of LHC Operations

LPCC, R. Assmann 34

Conclusion LHC operation has made significant progress:

Optimized working point for physics. All performance parameters well known and controlled! Record fill with expected luminosity, very small intensity losses and

very small emittance blow-up! Can run at design beam-beam parameter! LHC stored energy is at ~ 0.7 MJ: about 30% of world record! LHC stored energy density is at ~ 7 MJ/mm2 this is ~3 times world

record. Highly destructive beam! Push intensity up factor ~2 in next days/week. Still issues:

learning with highly destructive beams! Regularly see and solve non-conform issues (orbit, procedures, …). Want stable run period (~4 weeks) for solving them.

Then push into 10-30 MJ regime!

23.7.2010

Page 35: Status of LHC Operations

LPCC, R. Assmann 35

Thank you for your attention!

23.7.2010


Recommended