+ All Categories
Home > Documents > TEMELIN 1000 MW UNITS COMMISSIONING EXPERIENCE

TEMELIN 1000 MW UNITS COMMISSIONING EXPERIENCE

Date post: 21-Oct-2021
Category:
Upload: others
View: 5 times
Download: 0 times
Share this document with a friend
39
TEMELIN 1000 MW UNITS COMMISSIONING EXPERIENCE Olga Ubrá Škoda Praha, a.s. Milady Horákové 109, 160 41 Praha 6, Czech Republic [email protected] ABSTRACT There were three main stages of the NPP Temelin commissioning: The preparatory stage- individual tests of assembly and the first part of extended hydrotest, The non-active testing stage- the second part of extended hydrotest and inspection, The active testing stage- zero and low power testing, power ascension testing and plant performance test. The main objective of the start- up process stages and the testing procedures including some operational experience are described in the paper. 1. INTRODUCTION Temelin Nuclear Power Plant (NPP) is equipped with two VVER 1000 reactors, each with thermal output of 3000 MWt and two turbogenerator sets with electrical output 2x 1000 MW. The decision for construction of 4 units, type VVER 1000 in the Temelin location was made in 1980. The construction permit was issued in 1986. In the year 1990, the requirement of electrical output was revised and it was decided to complete only two 1000 MW units and substantially upgrade the design and the operational safety and flexibility of the NPP Temelin. In the course of the years 1990 to 1992, international audits and expertise and IAEA mission were carried out at the NPP Temelin. Based on the conclusion of IAEA mission, Halliburton NUS audit and the other expertise and in compliance with recommendation of the Czech nuclear regulatory body and of the Czech experts a modernisation program for NPP Temelin has been carried out. The following innovations have been implemented: Modernisation and upgrading of the safety and control systems, Fuel replacement and modification of the reactor core, Innovations of some components and subsystems of the primary and the secondary systems, replacement of the original cables with ones of higher fire rating, Design and construction of a full scope simulator, The improvement of safety documentation, elaboration of the Probabilistic Safety Assessment. The US Company Westinghouse Electric Corporation was selected to submit contract for the delivery of instrumentation and control system, primary side diagnostic system and for the delivery of nuclear fuel. The contract for the delivery of instrumentation and control system was signed in 1993 and the contract for the delivery of fuel including safety analyses was signed in 1994.
Transcript
Page 1: TEMELIN 1000 MW UNITS COMMISSIONING EXPERIENCE

TEMELIN 1000 MW UNITS COMMISSIONING EXPERIENCE

Olga Ubrá Škoda Praha, a.s.

Milady Horákové 109, 160 41 Praha 6, Czech Republic [email protected]

ABSTRACT There were three main stages of the NPP Temelin commissioning: • The preparatory stage- individual tests of assembly and the first part of extended

hydrotest, • The non-active testing stage- the second part of extended hydrotest and

inspection, • The active testing stage- zero and low power testing, power ascension testing and

plant performance test. • The main objective of the start- up process stages and the testing procedures

including some operational experience are described in the paper.

1. INTRODUCTION

Temelin Nuclear Power Plant (NPP) is equipped with two VVER 1000 reactors, each with thermal output of 3000 MWt and two turbogenerator sets with electrical output 2x 1000 MW. The decision for construction of 4 units, type VVER 1000 in the Temelin location was made in 1980. The construction permit was issued in 1986. In the year 1990, the requirement of electrical output was revised and it was decided to complete only two 1000 MW units and substantially upgrade the design and the operational safety and flexibility of the NPP Temelin.

In the course of the years 1990 to 1992, international audits and expertise and IAEA mission were carried out at the NPP Temelin. Based on the conclusion of IAEA mission, Halliburton NUS audit and the other expertise and in compliance with recommendation of the Czech nuclear regulatory body and of the Czech experts a modernisation program for NPP Temelin has been carried out. The following innovations have been implemented: • Modernisation and upgrading of the safety and control systems, • Fuel replacement and modification of the reactor core, • Innovations of some components and subsystems of the primary and the

secondary systems, replacement of the original cables with ones of higher fire rating,

• Design and construction of a full scope simulator, • The improvement of safety documentation, elaboration of the Probabilistic Safety

Assessment. The US Company Westinghouse Electric Corporation was selected to submit

contract for the delivery of instrumentation and control system, primary side diagnostic system and for the delivery of nuclear fuel. The contract for the delivery of instrumentation and control system was signed in 1993 and the contract for the delivery of fuel including safety analyses was signed in 1994.

Page 2: TEMELIN 1000 MW UNITS COMMISSIONING EXPERIENCE

2

Since 1995 after the completion of revisions and adjustment work and the finalisation of assembly, the preparation on NPP commissioning began. There were 3 main stages of the NPP Temelin commissioning: • Preparatory stage- individual tests of assembly and the first part of extended

hydrotest, • Non-active testing stage- the second part of extended hydrotest and REVISION, • Active testing stage- zero and low power testing, power ascension testing and

plant performance test. The summary of all stages and substages of the Temelin Units commissioning is on the Table 1. Some details are discussed in this paper. 2. PREPARATORY STAGE AND NON- ACTIVE TESTING STAGE

In 1999, all efforts of contractors were focused on the preparation of the first stage of extended hydrotest, which began on Unit 1 in October 1999 and on Unit 2 in July 2001. The purpose of the first stage of the extended hydrotest was to verify the tightness of the equipment and the primary circuit piping at a pressure 17.6 MPa and 24.5 MPa. More than 3000 individual tests were provided on the Unit 1 and 1576 tests on the Unit 2 from the start of testing to the end of the first stage of the extended hydrotest.

In February 2000 non- active testing stage on the Temelin NPP Unit 1 began. The second stage of extended hydrotest was completed successfully in April 2000 on the Unit 1 and in November 2001 on the Unit 2. After the second stage of the hydrotest a “REVISION” (inspection) was performed. During the REVISION all detected defects were fixed and pre- operational checks were performed.

After the REVISION substage active testing stage began. The first step of this process was transportation of the first container with fresh fuel from the fresh fuel area into Unit containment building. There were three basic stages of the Temelin Units active testing stage: • The zero and low power testing – Physics start- up tests (procedure of the basic

series F), • The power ascension testing – (procedures of the basic series E), • Plant Performance Test. 3. ACTIVE TESTING STAGE, PHYSICS START- UP TESTS

Physics start-up testing of Temelin NPP Unit 1 began in July 2000 and of Unit 2

in March 2002. The main objective of the physics start-up testing was to verify characteristics of the reactor core important for nuclear safety as well as for more accurate determination of neutron-physical characteristics, which are used in the course of unit operation.

Physics start-up tests of Temelin Units were divided in accordance with the approved “Program of Physics Start-up Tests F001” into the following three time periods. The first period of the physics start-up tests included: • fuel loading and reactor assembling • filling-in of the primary circuit by coolant • leak-tightness pressure tests of the primary and secondary system. • repeated containment integrity test

Page 3: TEMELIN 1000 MW UNITS COMMISSIONING EXPERIENCE

3

The second period included: • heating above the brittle fracture limit temperature • heating to semi-hot (Mode 4) and hot (Mode 3) state (280 °C) • performance of tests required by the operational procedures for reactor start-up • repeating some tests performed during Hot Functional Tests The third period included: • reaching initial reactor criticality • physics start-up tests

First stable criticality on the Unit 1 reactor was reached in October 11, 2000 and

on the Unit 2 reactor in May 31, 2002. The basic physics start-up tests, which started at the moment of the initial criticality were performed at zero or very low reactor power, when fission reaction had not yet heated the primary coolant. In compliance with the Physics start-up test phase program document the following test procedures were performed: - Initial core loading - Initial criticality - Determination of physics testing operational range of power - Source-term determination - Determination of physics testing operational range of power - Source-term determination - Reactivity computer check out - Verification of the control rods connection with their drive mechanism - Differential and integral control rod groups worth, and boron worth verification - Rod-drop measurement - Isothermal temperature reactivity coefficient and pressure reactivity coefficient

measurement - Incore thermocouples calibration - Reactivity power coefficient measurement - NIS calibration up to 1.5 % rated thermal power (RTP) - Reactor coolant system thermal capacity and heat loss determination - Reactor coolant system hydraulic characteristics measurement - Core symmetry verification - Boron injection system lag measurement determination - Reactor neutron noise characteristics measurement - Radiation monitoring - Measurements of the equilibrium Xenon worth Some of these procedures were performed not only during physics start-up tests, but also during power ascension testing.

Based on the results of physics start-up tests it was determined that reactor core of both Temelin Units meets safety and design requirements and the characteristics of the reactor core of both Temelin Units comply within acceptable allowance with predicted results. Besides basic physical tests several hundreds individual tests of equipment were provided in the course of the period of Physics start-up tests - on the Unit 1 about 1000 individual tests and on the Unit 2 about 600 tests. Based on acceptable results of all tests performed according “Program of Physics Start-up Tests” it was recommended to proceed into the power ascension test phase.

Page 4: TEMELIN 1000 MW UNITS COMMISSIONING EXPERIENCE

4

4. ACTIVE TESTING STAGE, POWER ASCENSION TESTING

Power ascension testing on Temelin Unit 1 began at the end of November 2000 and on the Unit 2 at June 2002. The main objective of the power ascension testing was to transfer the Unit from Mode 2 (power level <2% rated thermal power (RTP)) to Mode 1 (power level >2% RTP) and to bring it successfully to the rated plant power.

In the course of the process of the gradual power ascension, all basic design functions were tested. The Unit and its major components properties were verified in normal steady state as well as in non-steady state operation modes and in abnormal operation conditions. At the end of the stage, a safe and reliable Unit operation was demonstrated by the 144 hours trial run.

A binding scenario of the activities carried out during the power ascension testing was the “Program of Power Ascension Tests E001”. The process of the power ascension testing, from the transition into the MODE 1 till achieving of the rated power was divided into substages that followed both logically and in time. Power ascension testing of Temelin NPP Unit 1 per the approved program “E001” was divided into seven substages which were limited by the reactor power levels 5%, 12%, 30%, 55%, 75%, 90% and 100% of the RTP. The 144 hours Unit trial run was a part of the last substage. The process of the Unit 2 power ascension testing was subdivided into four substages limited by the power level 30%, 55%, 75% and 100%.

The performed commissioning and verifying activities were aimed in particular at the following areas: • Putting the secondary system into full operation including verification of the design

functions of the basic components and confirming of the thermal and mechanical properties of the new machine hall equipment as turbogenerator set, reheater and condenser,

• Verification of the unit operation in steady state operation modes at gradually increasing reactor power levels, in particular verification of the parameter stability and of the performance of the process equipment in connection with the control system,

• Verification of the unit operation under abnormal operation conditions and transients initiated by the trip of a major unit components including the verification of the control system performance,

• Demonstration of a reliable and safe unit operation in all other basic unit operational modes, i.e. during the heatup, criticality achieving, power ascension, shutdown, hot standby and during the cooldown.

• Verification of the neutron, thermo-hydraulic and mechanical properties of the reactor core,

• Verification of the performance, reliability and correct setup of all parts of the control system in connection with the process (control circuits, sequences, limitation and protection system), both in normal operation modes conditions and, in particular, from the point of view of mastering abnormal operation conditions and transients without violating the Plant Technical Specifications.

The units verification were provided for by the following tests: • in accordance with the test procedures of the basic series E- altogether 39

procedures covering partially or fully the basic areas of the unit verification, i.e. physics and thermo-hydraulic measurements, calibration, chemistry and health physics measurements, verification of the design functions of the equipment

Page 5: TEMELIN 1000 MW UNITS COMMISSIONING EXPERIENCE

5

including the control system and verification of normal and abnormal design modes,

• in accordance with the test procedures of the F series- 3 procedures that continue the activities performed in the course of the zero and low power testing stage,

• in accordance with the test procedures of the P series - these are in most cases tests of basic process equipment with the medium for which the proper conditions could not be set up before the power ascension stage. In addition to that, those are tests of the electric equipment connected with the power output and tests of secondary diagnostic system,

• in accordance with the test procedures of the V series - altogether 19 procedures that verify the properties of the new design and new structure elements and components of the secondary circuit. They are, in particular, aimed at the verification of thermal-hydraulic, aerodynamic and mechanical properties of the turbine, reheater and of the condenser.

Regarding the test procedures of the E, F, P series, there was only small difference between the first and the second Temelin NPP Units. The test procedures of the V-series were provided on the Unit 1 only, because of new design lot of Unit 1 secondary system components and elements. The Unit 1 turbine is the first 1000 MW saturated steam turbine (prototype) which was designed and manufactured by Škoda Company.

The Unit1 power ascension tests were successfully completed 24. 05. 2002 and 144 hour's trial run was finished 10. 6. 2002. In comparison with the 6 months assumed for the completion of the planned tests in the schedule of the stage testing procedure E001, the real duration was 19 months. The major impact on the duration of the power ascension testing stage had problems connected with turbogenerator set vibrations and intensive high frequency vibrations of the inlet steam piping between control valves and the high pressure part of the turbine. These phenomena were observed during the turbine operation in the range of low output of 0- 400MW. The turbine increased vibrations were caused partly due to imperfect counter balancing of the rotor system that was produced by the connection of separately balanced rotors. The counterbalancing in no load running and after turbogenerator grid connection and loading was performed, but the piping system vibration was not removed. Water draining lines and several tapping points of pressure and temperature measurement were cut off and serious leakage in the turbine control oil system was indicated.

Several forced outages of the turbogenerator occurred, mainly due to the vibration and the leakage in the turbine oil system. Due to forced turbine outages the low- pressure (LP) turbine rotor was damaged. It was obvious, that vibration was a complex problem, the solution of which was a necessary condition for Unit 1 commissioning to go on. An extensive program of special measurement on the turbine and piping system was implemented and the detailed analyses of the vibration were accomplished by a number of experts and specialised institutes. The experts came to the conclusion, that the main reason of the high frequency of the turbine and piping vibration was the flow of saturated steam through the control valves, where high velocities and dynamic exiting forces occurred due to high throttling at low power (high frequency pulsation in a steam flow).

During unplanned Unit outage the repair works and technical modification on non- nuclear part of the Unit were carried out. The following measures were materialised:

Page 6: TEMELIN 1000 MW UNITS COMMISSIONING EXPERIENCE

6

• Reconstruction of the main control valves. The most feasible way of pulsating flow reduction was to change the geometry of inner channels of original control valves. A redesign of the control valve was undertaken: the plug has a flat bot and newly developed muffler is located in the front of the seat. By the reconstruction of the main control valves the problems of pulsating pressure of the steam and vibrations were solved.

• Reconstruction of the oil hydraulic part of the turbine control system. The oil hydraulic control system was divided into two circuits, one for the actuation of the main control valves and the second for the check flap valves. The hydraulic actuators (servomotors) were improved and the nitrogen accumulators equipped the oil control system.

• Enlargement of the running radial clearance between turbine rotor and stator. All 3 LP turbine cylinders were equipped with measurement of the radial clearance between turbine rotor and stator by contactless path indicators. Turbine operator has permanent information about the LP cylinders operating condition.

Thanks to these measures all mentioned turbine diseases were successfully treated and removed. Power ascension testing started again and the process continued without any serious problem. More than 1500 individual tests were successfully performed.

Power ascension testing on Temelin Unit 2 began in June 2002 and was completed in April 2003. In comparison with the original schedule of the stage testing procedures the delay was 4 months. The Unit 2 stage testing procedures 2E001 divided power ascension testing into 4 substages. The substage up to 30% RTP of Unit 2 and its objectives corresponded to substages up to 5%, 12% and 30% RTP of Unit 1 and substage up to 100% RTP of Unit 2 a its objectives corresponded to the substages up to 90% and up to 100% RTP of Unit 1. The turbine of Unit 2 was operating successfully but serious problems of electrical generator occurred. The serious failure of the generator rotor occurred in the course of the primary test of the turbine generator, its exciter generator and its electrical protecting system. The Unit had to be shutdown and cooldown. The defective rotor was dismantled and sent to a manufacturing plant to identify the failure and to analyse the failure cause. It has been obvious, that the failure analyses would be a long- term matter, therefore it was decided to use a spare rotor and to continue the power ascension testing. But in the course of the primary tests of the turbine generator with spare rotor the same failure occurred. Power ascension testing had to be discontinued approximately for two months. The result of the manufacturer's investigation was that the exciting supply leads were damaged. The reason of the damage was probably combination of moisture condensed in the exciting supply leads and its copper abrasion which resulted into the short circuit between + and – pole of the exciting circuit. The manufacturer performed a set of measures including design improvement. The results of the measure corresponded to the expectation and the power ascension testing could be successfully completed. Nearly 1300 individual tests were carried out.

4. CONCLUSION

Since May 2003 both Temelin Units have been at trial operation. All completed stages of commissioning confirm that both Temelin Units meet or exceed all safety, design and operational requirements.

Page 7: TEMELIN 1000 MW UNITS COMMISSIONING EXPERIENCE

NPP TEMELIN 1000MW UNITS COMMISSIONING T1

UNIT1

UNIT2

START

COMPL. NUMBER OF TESTS

NOTE

START

COMPL. NUMBER OF TESTS

NOTE

PREPAR. STAGE

IHZ / CP,TZ

5.10.1999

20.10.1999

919

BEFORE MSKS3040 TESTS

IHZ / CP,TZ

13.7.2001

12.10.2001

308

BEFORE IHZ 1576 TESTS

IHZ / HHZ

25.2.2000

2.4.2000

608

IHZ / HHZ

12.10.2001

8.11.2001

325

NAV

REVISION

6.4.2000

16.6.2000

514

REVISION

8.11.2001

22.1.2002

896

BEFORE MSKS

5.7.2000

11.10.2000

930

INTERRUPTION23.9. - 4.10.

BEFORE MSKS

4.3.2002

31.5.2002

388

FS AFTER

MSKS

11.10.2000

25.10.2000

156

AFTER MSKS

31.5.2002

13.6.2002

235

5%

31.10.2000

11.11.2000

85

12%

14.11.2000

9.12.2000

180

INTERRUPTION27.11. - 6.12.

30%

15.12.2000

8.3.2001

153

OUTAGE + INTERRUPTION

30%

24.6.2002

3.9.2002

275

INTERRUPTION

(2)

55%

9.3.2001

2.10.2001

376

INTERRUPTION19.3. - 2.10.

55%

5.11.2002

31.1.2003

497

INTERRUPTION (2)

75%

19.10.2001

21.12.2001

250

INTERRUPTION1.11. - 1.12.

75%

6.2.2003

20.2.2003

218

90%

21.12.2001

3.1.2002

142

100%

10.1.2002

24.5.2002

377

INTERRUPTION25.2. - 28.4.

100%

25.2.2003

7.4.2003

279

SCHEDULED

OUTAGE 6.3. - 27.3.

ES

KV

26.5.2002

10.6.2002

INTERRUPTION1.6. - 10.6.

KV

12.4.2003

18.4.2003

AV

ZP

ZP

10.6.2002

ZP

18.4.2003

NAV NON- ACTIVE TESTING STAGE IHZ / CP,TZ THE FIRST STAGE OF EXTENDED HYDROTEST AV ACTIVE TESTING STAGE IHZ/HHZ THE SECOND (HOT) STAGE OF EXTENDED HYDROTEST FS PHYSICS START-UP TESTS KV UNIT TRIAL RUN ES POWER ASCENSION TESTING ZP TRIAL OPERATION MSKS FIRST STABIL CRITICALITY PKV INDIVIDUAL TESTS OF ASSEMBLY

Page 8: TEMELIN 1000 MW UNITS COMMISSIONING EXPERIENCE
Page 9: TEMELIN 1000 MW UNITS COMMISSIONING EXPERIENCE
Page 10: TEMELIN 1000 MW UNITS COMMISSIONING EXPERIENCE
Page 11: TEMELIN 1000 MW UNITS COMMISSIONING EXPERIENCE
Page 12: TEMELIN 1000 MW UNITS COMMISSIONING EXPERIENCE
Page 13: TEMELIN 1000 MW UNITS COMMISSIONING EXPERIENCE
Page 14: TEMELIN 1000 MW UNITS COMMISSIONING EXPERIENCE
Page 15: TEMELIN 1000 MW UNITS COMMISSIONING EXPERIENCE
Page 16: TEMELIN 1000 MW UNITS COMMISSIONING EXPERIENCE
Page 17: TEMELIN 1000 MW UNITS COMMISSIONING EXPERIENCE
Page 18: TEMELIN 1000 MW UNITS COMMISSIONING EXPERIENCE
Page 19: TEMELIN 1000 MW UNITS COMMISSIONING EXPERIENCE
Page 20: TEMELIN 1000 MW UNITS COMMISSIONING EXPERIENCE
Page 21: TEMELIN 1000 MW UNITS COMMISSIONING EXPERIENCE
Page 22: TEMELIN 1000 MW UNITS COMMISSIONING EXPERIENCE
Page 23: TEMELIN 1000 MW UNITS COMMISSIONING EXPERIENCE
Page 24: TEMELIN 1000 MW UNITS COMMISSIONING EXPERIENCE
Page 25: TEMELIN 1000 MW UNITS COMMISSIONING EXPERIENCE
Page 26: TEMELIN 1000 MW UNITS COMMISSIONING EXPERIENCE
Page 27: TEMELIN 1000 MW UNITS COMMISSIONING EXPERIENCE
Page 28: TEMELIN 1000 MW UNITS COMMISSIONING EXPERIENCE
Page 29: TEMELIN 1000 MW UNITS COMMISSIONING EXPERIENCE
Page 30: TEMELIN 1000 MW UNITS COMMISSIONING EXPERIENCE
Page 31: TEMELIN 1000 MW UNITS COMMISSIONING EXPERIENCE
Page 32: TEMELIN 1000 MW UNITS COMMISSIONING EXPERIENCE
Page 33: TEMELIN 1000 MW UNITS COMMISSIONING EXPERIENCE
Page 34: TEMELIN 1000 MW UNITS COMMISSIONING EXPERIENCE
Page 35: TEMELIN 1000 MW UNITS COMMISSIONING EXPERIENCE
Page 36: TEMELIN 1000 MW UNITS COMMISSIONING EXPERIENCE
Page 37: TEMELIN 1000 MW UNITS COMMISSIONING EXPERIENCE
Page 38: TEMELIN 1000 MW UNITS COMMISSIONING EXPERIENCE
Page 39: TEMELIN 1000 MW UNITS COMMISSIONING EXPERIENCE

Recommended