Tilahun Sarka (Eng.)DG, EDR.
CONTENT OF PRESENTATION
Introduction1
Standardization2
Technical and Financial challenges 3
Conclusion 411/25/2020 2
Introduction
EDR (Ethio-Djibouti railway share company)
Railway share company owned by Ethiopian and Djiboutiangovernment
Established on December 2017 for operation andmaintenance of railway line from Addis to Djibouti.
Currently under management contract with Chinesecompany for the operation and maintenance of the line.
Operation and maintenance is conducted by Chinesestandard usually known as Chinese Class II Standard.
11/25/2020 3
1
STANDARDIZATION
11/25/2020 4
2
• According to UIC guideline to standardization document,standards are defined as
“document, established by consensus and approved by arecognized body, that provides, for common and repeateduse, rule, guidelines or characteristics for activities or theirresults, aimed at the achievement of the optimum degreeof order in a given context”.
• Global practice
Standardization cont.
11/25/2020 5
• ISO (International Organization for Standardization)
• IEC (International Electro technical Commission)
• UIC
International Standards
• The European Committee for Standardization (CEN) and
• The European Committee for Electro technical Standardization (CENELEC)
Regional Standards
• U.S.A. ANSI
• U.K. BS
• Germany DIN
• France NF
National Standards
Standardization cont.
• African railway standard• So far Africa doesn’t have any significant union of
railways, however some railway lines operate crosscountry like, Sitarail, Tazara and EDR.
• African Union (AU) planned to construct railway linelinking African's major countries with AHSRN Vision2063.
• For that plan to be realized Africa needs one regionalrailway design, construction and operation standard.
11/25/2020 6
Ethiopian railway standard
11/25/2020 7
Design
Construction
Operation and
maintenance
Standard
Standardization cont.
Addis – Djibouti Overview from general Standards perispective.
Main technical standard
• Gauge: standard gauge 1435mm
• Railway class: national railway class II in China.
• Number of main line: double-track line from Sebeta-Adama; single-track line from Adama-Mieso- Djibouti
• Design speed: maximum travelling speed of 120km/h for passenger train; maximum travelling speed of 80km/hfor freight train
• Minimum curve radius: 1200m in normal segment, and 800m in difficult segment
• Centerline spacing: 4m
• Limiting slope: 9‰, and 18.5‰ for dual-locomotive traction
• Type of traction: electric traction
• Type of locomotive: HXD1C locomotive as main line locomotive; diesel DF7G type as shunting locomotive
• Traction mass: 3500t
• Effective length of receiving-departure line: 850m for single-locomotive, and 880m for dual-locomotive
• Type of block: automatic block between stations
• Number and type of existing locomotives and rolling stocks: 35×six-axle 7200 kW HXD1C type electric main linelocomotives; 6×six-axle 2200 kW DF7G type diesel shunting locomotives; 30×25G type passenger locomotives,including 20 hard-seat locomotives, 4 hard-berth locomotives, 4 soft-berth locomotives and 2 dining cars; 1100freight locomotives.
Guarantee of equipment
and facilities
Personnel Self-control of
personnelSafety
managementPersonnel
quality
Physical/
psychological health
Standardized operation
Equipment and
facilities
Technical standards
Input guaranteeMaintenance and
repair quality
Science and technology
Scientific and technical
guarantees
Guarantee of reinforcements
Control on unsafe behaviors
Monitoring of environmental
hazards
List of standards for all disciplines of the Addis Ababa-Djibouti Railway:
safety
Standardization cont.
• Generally Ethiopian government is developing national design,construction , operation and maintenance standard in collaborationwith Ethiopian standardization agency (EQSA).
• During Construction period, some efforts have been made todevelop Railway standardization in consultation with the RussianSaint Petersburg Transport University (PGUPS).
• EDR as a cross country railway operator is planning to developregional standard for the maintenance and operation of its railwayline.
• This can also be done in collaboration and with the support fromUIC.
11/25/2020 10
Technical and financial challenges
The two major challenges in railway industry are:-
1. Technical human capital
2. Financial resource
3
11/25/2020 11
Technical challenge
• To overcome the technical challenges EDR develops acapacity building model that will enable each keyposition in railway operation to be taken over with inthe shortest possible time.
• The capacity building model is the key element of ourmanagement contract with the Chinese company
11/25/2020 12
Financial challenge
• Basically the financial source of railway construction and operation are
11/25/2020 13
Loan
Private fund
Governmental budget
Joint gov’taland private
fund Financial source
Financial cont.
• Its known that railway line construction is highly capitalintensive and for a continent like Africa it has been amajor challenge for expanding railway infrastructurebecause of financial constraint.
• The major financial source for African railway lineconstruction is loan based.
• Looking at Ethiopian scenario and EDR all the financialsources are from different global loans and Grants sometimes.
11/25/2020 14
• For the construction and operation of cross country railwayline Africa should develop its own regional design,construction, operation and maintenance railway standardsfor a safe and effective implementation.
• Regarding technical human capital, all African countriesshould engage in capacity building programs specifically forrailway sector.
• With an effort of Railway Digitization by UIC, appliedstandards of continental Europe can easily be customizedand disseminated to African Railways.
Conclusion4
11/25/2020 15
Conclusion cont.
• And finally regarding financial issue AfricanDevelopment Bank (ADB) should invest in railwaysector for the development of railway infrastructureacross the continent.
11/25/2020 16
Let’s Standardize and make Two in One!
11/25/2020 Department of QSE 17