+ All Categories
Home > Documents > Training Report on Bsp

Training Report on Bsp

Date post: 02-Jun-2018
Category:
Upload: sanchay3090
View: 226 times
Download: 0 times
Share this document with a friend

of 14

Transcript
  • 8/10/2019 Training Report on Bsp

    1/14

    TRAINING REPORT ON

    BHILAI STEEL PLANT

    DURATION26.05.2014 - 07.06.2014

    REPORT SUBMITTED BY: -

    KUNAL SINGH (12119037)

    INSTITUTION:- NATIONAL INSTITUTE OF TECHNOLOGY RAIPUR

    DEPARTMENT OF MECHANICAL ENGINEERING

  • 8/10/2019 Training Report on Bsp

    2/14

    A Brief Introduction To Bhilai Steel Plant

    Bhilai Steel Plant, a unit of Steel Authority of India Ltd. is a

    public sector undertaking and was conceived under Indo-USSRTreaty in the 2nd Five year plan. This was in accordance with

    erstwhile government policy for strengthening economy and self

    reliance through development of core sector. The plant is located

    at the central position of India, which is one of the major iron belt

    of India, and it is about 40 kilometer from Raipur, capital of

    Chattisgarh. The captive mines of the plant located at Dalli-

    Rajahara supplies iron ore and lime stone used to be availablefrom Nandini captive mines. At present lime stone is procured

    from outside. The other major raw material, coal is purchased

    from outside either through import or from indigenous market.

    Bhilai Steel Plant, an integrated steel works, was commissioned

    in 1959 with production capacity of 1.0 million tonne of steel. Insuccessive phases, capacity was enhanced to 2.5 and 4.0 million

    tonne in the year 1962 and 1984 respectively. Figure depicts

    facilities available with Bhilai Steel Plant for 4.0 mt production.

    As of now this is the largest steel plant in India with present

    capacity utilisation more than 100% for three consecutive years.

    Bhilai Steel Plant, an integrated steel works, was commissioned

    in 1959 with production capacity of 1.0 million tonne of steel. In

    successive phases, capacity was enhanced to 2.5 and 4.0 million

    tonne in the year 1962 and 1984 respectively. Figure depicts

    facilities available with Bhilai Steel Plant for 4.0 mt production.

    As of now this is the largest steel plant in India with present

    capacity utilisation more than 100% for three consecutive years.

  • 8/10/2019 Training Report on Bsp

    3/14

    Bhilai Steel Plant - Major Landmarks

    Signing of Agreement for setting up of the plant Feb. 02, 1955

    Commencement of work at site May 06, 1956

    Commissioning of Coke Oven Battery # 1 Jan. 31, 1959

    Commissioning of Blast Furnace # 1 Feb. 04, 1959

    Commissioning of Power & Blowing Station Jun. 04, 1959

    Commissioning of Steel Melting Shop O.H. Fce # 1 Oct. 11, 1959

    Commissioning of Blooming Mill 1150 stand Nov. 12, 1959

    Commissioning of Billet Mill Dec. 24, 1959

    Commissioning of Rail & Structural Mill Oct.27, 1960

    Commissioning of Sintering Plant # 1 Jul. 03, 1961

    Commissioning of Merchant Mill Feb. 02, 1961

    Commissioning of Wire Rod Mill Sep. 01, 1967

    Commissioning of Sintering Plant #2 Aug. 01, 1979

    Commissioning of Plate Mill Mar. 31, 1983

    Commissioning of Converter #1 Jul. 29, 1984

    Commissioning of Continuous Casting Shop M/C #1 Mar. 15, 1986

    Commissioning of First Twin Hearth (at SMS-1) Sep. 12, 1986

    Commissioning of Blast Furnace #7 Aug. 30, 1987

    Commissioning of Coke Oven Battery Mar. 31, 1988

    Commissioning of Second Twin Hearth Jan. 01, 1990

    Commissioning of VAD unit at SMS-2 Jan. 17, 1991

    Commissioning of Third Twin Hearth Jun 29, 1992

  • 8/10/2019 Training Report on Bsp

    4/14

    Commissioning of Fourth Twin Hearth Jan 21, 1998

    Commissioning of Ladle Furnace at SMS-2 Dec 23, 1999

    Commissioning of RH Degasser Unit at SMS-2 Mar. 30, 2000

    Commissioning of Sintering Plant # 3 Dec. 12, 2001

    Only Steel Plant in India to cross 5 MT Mar 31, 2006

    Curde Steel Production in the financial year.

    Bhilai's expansion & modernisation to 7.5 MT Feb. 09, 2008

    capacity inaugurated

    Bhilai repeats 5 MT + performance Mar. 31, 2008

  • 8/10/2019 Training Report on Bsp

    5/14

    BSP FLOW PROCESS

  • 8/10/2019 Training Report on Bsp

    6/14

    PLANT OVERVIEW

    No. Department Unit Capacity

    Coke Oven 8 Batteries of 65 ovens and 4.3

    M high

    2 Batteries of 67 ovens and 7.0 M

    high

    3.3 million ton

    of BF Coke

    BLAST

    FURNACE

    3 Furnaces of 1033 Cum

    3 Furnaces of 1719 Cum1 Furnace of 2000 Cum

    4.71 mt of hot

    metal

    SMS-1 4 Twin Hearth Furnaces 2.5 mt of steel

    SMS-2 3 BOF of 100/130 T capacity 1.425 mt of steel

    CONCAST 1000/700/500 mm Cont. Billet

    Mill

    1.425 mt of steel

    BBM 3 BOF of 100/130 T capacity

    1000/700/500 mm Cont. Billet

    Mill

    2.15 mt of bloom

    RAIL ANDSTRUCTURAL

    MILL

    950/800 2 high reverseing Mill .75 mt of product

    WIRE ROD

    MILL

    4 strand continious Mill .4 mt of product

    MERCHANT

    MILL

    350 mm Cross Country Mill .5 mt of product

  • 8/10/2019 Training Report on Bsp

    7/14

    0 SINTERED

    PLANT

    1) 4 Machine of 50 Sq M hearth

    area

    2) 3 machine of 75 Sq M and 1

    Machine and 1 Machine of 80 Sq

    M hearth area3) 1 Machine of 320 Sq M hearth

    area

    8.3 mt of sinter

  • 8/10/2019 Training Report on Bsp

    8/14

    BLAST FURNACES

    What is a Blast Furnace? BF is a counter current heat and mass

    exchanger, inwhich solid raw materials are charged from the

    top of the furnace and hot blast is sent through the bottom via

    tuyeres. The heat is transferred from the gas to theburden and

    oxygen from the burden to the gas. Gas ascends up the furnace

    while burden and coke descend down through the furnace. The

    counter current nature of the reactions makes the overall

    process an extremely efficient one.

    In the blast furnace process iron ore and reducingagents (coke, coal) are transformed to hot metal, and slag is

    formed from the gangue of the ore burden and the ash of coke

    and coal. Hot metal and liquid slag do not mix and remain

    separate from each other with the slag floating on top of the

    denser iron. The iron can then be separated from the slag in the

    cast house. The other product from the Blast Furnace is dust

    laden blast furnace gas, which is further cleaned in the gas

    cleaning plant and is used as a fuel all over the plant.

    Blast Furnace constructional features:

    A blast furnace has a typical conical shape. The sections from top down are:

    > Throat, where the burden surface is.

    > The shaft or stack, where the ores are heated and reduction starts.

    > The bosh parallel or belly and

    > The bosh, where the reduction is completed and the ores are melted down. The

    hearth, where the molten material is collected and is cast via the tap hole

  • 8/10/2019 Training Report on Bsp

    9/14

    MACHINING ASSEMBLY & RE-ENGINEERING SERVICES-1

    ( MARS-1).

    MARS-1 has a vital role to play in maintaining the plant equipment so

    for as it supplies the bulk of spare parts required by the various units. It

    acquires an added significance by virtue of the finishing line of

    manufacturing activities of engineering shop . The product mix so

    arranged so as to meet the demand of both heavy and small spares. The

    shop is housed in three machining bays, 21 meters x182 meters each

    with an assembly bay of 24 meters x 96 meters .A total of 196 machine

    tools are engaged in direct production of spares, where- as the

    remaining contribute indi- rectly towards shop production. Apart from

    these, there are 12 Heat Treatment / Heating furnaces 22 material

    handling equipment (cranes,jib cranes transfer cars). The Annual

    production plan for MARS-1 during 2007-2008 is 6,40,000 credit

    hours.

    MAIN ACTIVITIES:-

    Function wise MARS-1 carries out the following activities:

    1. Manufacture of spares, changables, tools, tackles etc. Required for

    maintenance and operation of various departments.

    2. Overhauling and repair of equipment sub - assemblies to the extent

    of those that can be transported to MARS-1.

    3. Reclamation of worn-out spares .

    4. Repair of certain equipment at site-especially where machining atsite is required.

    5. Manufacturing and modification of equipment / spares for

    development work from the point of view of import substitution,cost

    reduction ,etc.

  • 8/10/2019 Training Report on Bsp

    10/14

    BLOOMING & BILLET MILL

    Blooming & Billet Mill popularly known as "Mother Mill", is a

    primary mill designed to roll 2.5 MT/ Annum of ingots into semies in

    the form of blooms & billets. A two high reversing blooming mill and

    12 stands continuous billet mill are part of this department. The

    1150mm two high reversing Blooming Mill is designed to roll steel

    ingots into blooms for Continuous Billet Mill and Rail & Structural

    Mill. Average weight of steel ingots which are used for rolling is 8 to 9

    Ton.

    BLOOMING MILL

    The heated ingot are placed on the ingot buggy (two ingots at a time)by means of tongs crane which delivers it on to the receiving roller

    table of Blooming Mill.The Blooming Mill is a 2-High horizontal

    stand, equipped with individually driven rolls. Each roll of the

    Blooming Mill is driven by 930 V, 8000 KW, 0-20-80 rpm motor.

    Length of Roll - 2800 mm

    Dia. of Roll - 1150 mm (Min.1100mm & Max.1180mm)

    The Mill can roll square and rectangular blooms and also narrow width

    slab. Common Sizes of Blooms and Narrow Width Slabs

    i) 320 x 320 mm

    ii) 265 x 340 mm

    iii) 260 x 300 mm

    iv) Shaped blooms for Beam-450mm & Beam-600mm

    v) Narrow Width Slab 200 x 320 mm

    vi) Narrow Width Slab 200 x 420 mm

  • 8/10/2019 Training Report on Bsp

    11/14

    BILLET MILL

    The Billet Mill has been designed to roll billets from blooms of cross

    section 325x325 sq.mm in 6 to 12 passes depending on cross section of

    billets to be produced in the Mill. The capacity of the Mill was

    designed to roll 15,01,000 Tonns/Year. But with modified output sizeof billets the mill is now capable of rolling to million tones per year.

    The Mill consists of 12 working stands arranged in three groups.

    a. The First group contains Two 2-High Horizontal stands with a 90

    deg. tilter in between. These stands are equipped with rolls of diameter

    1000mm and length 1200mm.

    b. The Second group called the roughing group contains 4 stand - 2

    each of Horizontal and Vertical stands arranged alternately. These

    stands are equipped with rolls of diameter 700mm.

    c. The Third group called the finishing group located after the transfer

    table contains 6 stands - 3 horizontal and 3 vertical stands arranged

    alternately. These stands are equipped with rolls of diameter 500mm.

    SECTION OF BILLETS ROLLED ARE

    1. 150 x 150 mm 2. 110 x 110 mm

    3. 105 x 105 mm 4. 100 x 100 mm

    5. 90 x 90 mm

  • 8/10/2019 Training Report on Bsp

    12/14

    WIRE ROD MILL

    The 4 strand 250mm continuous Wire Rod Mill, commissioned on

    September 1 1967, was designed to roll 6, 7, 8, 10mm diameter wire

    rods from square billets of 80mm x 80mm cross section (of length 11

    to 11.8 meters) with rated capacity of 4,00,000 T per annum. The billet

    size was further enhanced to 85 mm2, 90 mm2, 100 mm2, 105 mm2 to

    improve in coil weight from 540 Kgs. to 930 Kgs. After the revamping

    of Right Side, sections 5.5 - 12 mm dia. wire rods are rolled in B ,

    C&D strands, whereas 8mm & 10mm are rolled on left side (A strand).

    BRIEF DESCRIPTION OF THE MILL

    Inspected billets are fed on the charging grate of the furnace bymagnetic finger cranes. The billets are fed one by one to the furnace,

    through roll table and draw-in- roller mechanism. Billets are moved

    into the furnace by means of pushers at the charging end. Soaked

    billets are ejected out by means of Ejector Ram from the discharging

    end.

    The reheating furnace of the size 18Mx 12M is having 28

    burners, which includes 14 in the heating zone and 14 in the soaking

    zone. Mixed (Coke Oven & Blast Furnace) gas with calorific value of

    1800 K Cal/Cum is used in the furnace as fuel. Capacity of the furnace

    is 120T/Hr. Gas and air is preheated to 250c and 450c in metallic and

    ceramic recuperators respectively.

    The roughing group consists of nine horizontal stands in

    which combined drive is provided for stands 2-3 and 4-5; whereasstands 1, 6, 7, 8 and 9 are individually driven. All the drives are

    controlled by thyristor converter.

    Flying Shear is provided after stand no. 9 for front-end cutting

    & cobble cutting. First intermediate group has 6 horizontal stands, out

    of which stand No. 12 & 13 are not being used. Stand No. 10 & 11/14

    & 15 are used for rolling on all the strands. After stand No. 15, the Mill

    is divided in four strands, old line (A) and Modernised line (B,C&D).

  • 8/10/2019 Training Report on Bsp

    13/14

  • 8/10/2019 Training Report on Bsp

    14/14


Recommended