+ All Categories
Home > Documents > Unique Commissioning of EXMAR’s FLNG ODell_Black... · Unique Commissioning of EXMAR’s FLNG ......

Unique Commissioning of EXMAR’s FLNG ODell_Black... · Unique Commissioning of EXMAR’s FLNG ......

Date post: 25-Mar-2018
Category:
Upload: hoangnga
View: 219 times
Download: 3 times
Share this document with a friend
24
Unique Commissioning of EXMAR’s FLNG Frederik Van Nuffel – EXMAR Sara O’Dell – Black & Veatch
Transcript
Page 1: Unique Commissioning of EXMAR’s FLNG ODell_Black... · Unique Commissioning of EXMAR’s FLNG ... •GE LM2500+ gas turbine driver ... Actual Methane in Feed Gas (left axis) Design

Unique Commissioning of EXMAR’s FLNG

Frederik Van Nuffel – EXMAR

Sara O’Dell – Black & Veatch

Page 2: Unique Commissioning of EXMAR’s FLNG ODell_Black... · Unique Commissioning of EXMAR’s FLNG ... •GE LM2500+ gas turbine driver ... Actual Methane in Feed Gas (left axis) Design

AgendaIntroduction and History of the Project

Overview of LNG Commissioning

Temporary Regasification Skid

LNG Loading

Permitting for Operation on the Yangtze River

Safe Operations

Benefits of Commissioning in the Shipyard

Results of the LNG Commissioning

Page 3: Unique Commissioning of EXMAR’s FLNG ODell_Black... · Unique Commissioning of EXMAR’s FLNG ... •GE LM2500+ gas turbine driver ... Actual Methane in Feed Gas (left axis) Design

Introduction and History of the Project

• Fully self-sufficient floating liquefaction unit that produces 0.5 MTPA LNG

• Near-shore installation

• Black & Veatch’s patented PRICO® SMR technology

• GE LM2500+ gas turbine driver

• Dual fuel power generation with 12 MW capacity

• Contains 16,100 m³ LNG storage in three Type C cargo tanks

• LNG offloading via EXMAR STS technology to a FSU or LNGC

Page 4: Unique Commissioning of EXMAR’s FLNG ODell_Black... · Unique Commissioning of EXMAR’s FLNG ... •GE LM2500+ gas turbine driver ... Actual Methane in Feed Gas (left axis) Design

Introduction and History of the Project

Main process flow is as follows:

CO2 Removal Liquefaction

Refrigerant

Make-up

Boil-Off Gas

Handling

Boil-Off Gas

Reliquefaction

Hot Oil System

Inlet Facilities Dehydration LNG storage

Page 5: Unique Commissioning of EXMAR’s FLNG ODell_Black... · Unique Commissioning of EXMAR’s FLNG ... •GE LM2500+ gas turbine driver ... Actual Methane in Feed Gas (left axis) Design

Introduction and History of the Project

2009

Project Initiated

by Exmar

2010

B&V selected as

Liquefaction

technology provider

2011

B&V completes

FEED for topsides

2012

Wison selected as

EPCIC contractor

EPCIC phase kicks off!

2013

FLNG Construction

Begins

2014

Launching-

FLNG leaves

dry dock

2015

Design of

closed loop

commissioning

May 2016

Mechanical Completion

and pre-commissioning

achieved

September 2016

Successful Performance

Test completed!

Page 6: Unique Commissioning of EXMAR’s FLNG ODell_Black... · Unique Commissioning of EXMAR’s FLNG ... •GE LM2500+ gas turbine driver ... Actual Methane in Feed Gas (left axis) Design

Driver for Commissioning before Sail-Out

• Market turmoil changed project economics

• Pacific Exploration & Production canceled export project

• Construction of the FLNG near completion

• Last phase of EPCIC contract

• Proving the performance of world’s first FLNG

• Industry first

• Project stakeholders

• Operations team

Page 7: Unique Commissioning of EXMAR’s FLNG ODell_Black... · Unique Commissioning of EXMAR’s FLNG ... •GE LM2500+ gas turbine driver ... Actual Methane in Feed Gas (left axis) Design

Overview of the LNG Commissioning

Temporary Regasification Skid

(TRS) added to topsides units

CO2 Removal Liquefaction

Refrigerant

Make-up

Boil-Off Gas

Handling

Boil-Off Gas

Reliquefaction

Hot Oil System

Inlet Facilities Dehydration LNG storage

TRS

Page 8: Unique Commissioning of EXMAR’s FLNG ODell_Black... · Unique Commissioning of EXMAR’s FLNG ... •GE LM2500+ gas turbine driver ... Actual Methane in Feed Gas (left axis) Design

Overview of the LNG Commissioning

• Closed loop process

• Allowed for full performance test of entire FLNG

• Minimal changes made in order to maintain as

much of the original design/flow scheme as

possible

BOG recycle to warm up the BOG to

compression

Regen gas flow adjusted to balance fuel demand

of turbine

Process set points around mid-point

Page 9: Unique Commissioning of EXMAR’s FLNG ODell_Black... · Unique Commissioning of EXMAR’s FLNG ... •GE LM2500+ gas turbine driver ... Actual Methane in Feed Gas (left axis) Design

Temporary Regasification Skid

Single lift module including

• One HP sendout pump

• One HP LNG vaporizer

• One HIPPS skid

• Several control valves and other

instruments

Page 10: Unique Commissioning of EXMAR’s FLNG ODell_Black... · Unique Commissioning of EXMAR’s FLNG ... •GE LM2500+ gas turbine driver ... Actual Methane in Feed Gas (left axis) Design

Temporary Regasification Skid

• Designed and constructed as a stand-alone skid to reduce impacts to

schedules of both EXMAR projects

• Thorough safety, design and operational reviews by all parties

• All equipment and instruments borrowed from EXMAR FSRU project

• Capacity larger than required for liquefaction

• HIPPS skid protected downstream units from high pressure, low

temperature

Page 11: Unique Commissioning of EXMAR’s FLNG ODell_Black... · Unique Commissioning of EXMAR’s FLNG ... •GE LM2500+ gas turbine driver ... Actual Methane in Feed Gas (left axis) Design

Temporary Regasification Skid

All tie-ins to the FLNG systems were well considered:

• Power requirement of the HP pump

• Closed loop heating water demand of the HP vaporizer

• Instrument air and nitrogen consumption

All existing utility systems could handle the increased load

without modifications

Page 12: Unique Commissioning of EXMAR’s FLNG ODell_Black... · Unique Commissioning of EXMAR’s FLNG ... •GE LM2500+ gas turbine driver ... Actual Methane in Feed Gas (left axis) Design

LNG Loading

Since LNG transshipment was not allowed by the Yangtze river authorities,

LNG supply by truck was chosen

• LNG transport by truck is well established in China

• An LNG supply tender was organized

• Nantong Petrochina Kunlun Gas Co., Ltd was awarded with the entire

supply contract

Page 13: Unique Commissioning of EXMAR’s FLNG ODell_Black... · Unique Commissioning of EXMAR’s FLNG ... •GE LM2500+ gas turbine driver ... Actual Methane in Feed Gas (left axis) Design

LNG Loading

Dedicated pump skid and vaporizer skid designed and fabricated by Petrochina

• Allowing proper control of flow and pressure

• Increasing the discharge rate by pumping from two trucks simultaneously

• Ensure sufficient and stable vapor return to the trucks

• Redirect all safety valves to the FLNG flare stack

All connections made with LNG hoses, including breakaway couplings and QC/DC connections at the truck side.

Page 14: Unique Commissioning of EXMAR’s FLNG ODell_Black... · Unique Commissioning of EXMAR’s FLNG ... •GE LM2500+ gas turbine driver ... Actual Methane in Feed Gas (left axis) Design

LNG Loading

• All LNG came from Rudong LNG terminal, about 150 km away

• Proper LNG sampling and truck weighing procedures have been implemented

• An average rotation time of 4.5 hours for every two trucks has been reached

• A total of 12,000 m³ of LNG delivered for the commissioning

• 270 trucks have offloaded LNG without safety incidents

Page 15: Unique Commissioning of EXMAR’s FLNG ODell_Black... · Unique Commissioning of EXMAR’s FLNG ... •GE LM2500+ gas turbine driver ... Actual Methane in Feed Gas (left axis) Design

Permitting for Operation on the Yangtze River

Permitting was a tailor-made process as there was no previous experience

A stepped approach was followed:

Step 1. Development of an integrated Emergency Response Plan

Step 2. Detailed review by government appointed national experts of the ERP

Step 3. Assessment of yard and LNG terminal facilities by local authorities

Step 4. Implementation of Expert recommendations to the yard facilities and

operating procedures

Step 5. Monitoring of commissioning activities by local authorities

Page 16: Unique Commissioning of EXMAR’s FLNG ODell_Black... · Unique Commissioning of EXMAR’s FLNG ... •GE LM2500+ gas turbine driver ... Actual Methane in Feed Gas (left axis) Design

Permitting for Operation on the Yangtze River

Key upgrades implemented on yard facilities and procedures were:

• Upgrade of existing firefighting systems

• Firetruck, firefighting boats and tug boats kept on permanent standby

• Restricted marine traffic on Yangtze River during LNG bunkering

• Rigorous access control to the FLNG and bunkering station

• Advanced training of emergency and operations teams

A full permit was obtained well in time before the start of the

operations

Page 17: Unique Commissioning of EXMAR’s FLNG ODell_Black... · Unique Commissioning of EXMAR’s FLNG ... •GE LM2500+ gas turbine driver ... Actual Methane in Feed Gas (left axis) Design

Safe Operations

Ensuring that the LNG operations at a yard on the Yangtze

River were conducted in a safe manner required a thorough

safety review

• HAZID and HAZOP studies were caried out on both the

TRS design and the LNG loading operations

• Experienced staff from all parties were involved in the

safety studies

• The FERA study was updated for the specific operations

• Evacuation and escape ways were reassessed

• A detailed Emergency Response Plan was written

Page 18: Unique Commissioning of EXMAR’s FLNG ODell_Black... · Unique Commissioning of EXMAR’s FLNG ... •GE LM2500+ gas turbine driver ... Actual Methane in Feed Gas (left axis) Design

Safe Operations

• Several HSE audits were conducted

• Specific operational HSE procedures

were developed, including:

Permit to work system

Lockout and tag out procedures

Job safety assessments

Dedicated toolbox meetings

• Extensive training and drills on potential scenarios

• Daily meetings with all parties were held to monitor progress

Commissioning was completed without major HSE incident!

Page 19: Unique Commissioning of EXMAR’s FLNG ODell_Black... · Unique Commissioning of EXMAR’s FLNG ... •GE LM2500+ gas turbine driver ... Actual Methane in Feed Gas (left axis) Design

Benefits of Commissioning in the Shipyard

• Easy personnel logistics

• Resources readily available

Large labor pool at the shipyard

Quick access to local suppliers

• No hassle in bringing spare parts or special tools

on board

• Smooth delivery of all first fills and refrigerants

Page 20: Unique Commissioning of EXMAR’s FLNG ODell_Black... · Unique Commissioning of EXMAR’s FLNG ... •GE LM2500+ gas turbine driver ... Actual Methane in Feed Gas (left axis) Design

Results of the LNG Commissioning

• LNG composition changed rapidly over time

Lighter components used as fuel

Heavier components stayed in the closed loop process

• Heavier feed gas required changes to process

• Warmer mid-point temperature to match capacity of heavies system

Page 21: Unique Commissioning of EXMAR’s FLNG ODell_Black... · Unique Commissioning of EXMAR’s FLNG ... •GE LM2500+ gas turbine driver ... Actual Methane in Feed Gas (left axis) Design

Results of the LNG Commissioning

Feed gas used during commissioning was heavier than design

800

850

900

950

1000

1050

1100

1150

1200

70

75

80

85

90

95

100

0 5 10 15 20 25 30 35 40 45 50 55 60 65 70

Feed

Gas

Heati

ng V

alu

e, B

TU

/SC

F

Feed

Gas

Meth

an

e C

on

ten

t, m

ol%

Performance test time, hours

Actual Methane in Feed Gas (left axis)

Design Methane in Feed Gas (left axis)

Actual Feed Gas Heating Value (right axis)

Page 22: Unique Commissioning of EXMAR’s FLNG ODell_Black... · Unique Commissioning of EXMAR’s FLNG ... •GE LM2500+ gas turbine driver ... Actual Methane in Feed Gas (left axis) Design

Results of the LNG Commissioning

• Entire FLNG systems were run in automatic mode, fully DCS controlled

• Minimal operator interference during the performance test

• Black & Veatch PRICO® process easily dealt with changing process

conditions and off-spec design parameters

• Exmar Operations team became fully confident in running the FLNG

safely and successfully

Page 23: Unique Commissioning of EXMAR’s FLNG ODell_Black... · Unique Commissioning of EXMAR’s FLNG ... •GE LM2500+ gas turbine driver ... Actual Methane in Feed Gas (left axis) Design

Results of the LNG Commissioning

Actual performance was well above the guaranteed performance

over the 72-hour test

1 6 11 16 21 26 31 36 41 46 51 56 61 66 71

LN

G P

rod

ucti

on

Performance Test Time, hours

Actual Operating Point

Guarantee Point

Page 24: Unique Commissioning of EXMAR’s FLNG ODell_Black... · Unique Commissioning of EXMAR’s FLNG ... •GE LM2500+ gas turbine driver ... Actual Methane in Feed Gas (left axis) Design

Conclusion

This Project Achieved many industry firsts

• First Liquefaction operated on board a floating unit

• First Regas and Liquefaction used in a closed loop

• First Gas commissioning completed in a ship yard

• First LNG trucks loaded the floating unit

Project team’s innovation and hard work led to

success, achieving a major milestone for the

FLNG industry!


Recommended