+ All Categories
Home > Documents > U.S. Steel Superfund Site

U.S. Steel Superfund Site

Date post: 02-Jan-2017
Category:
Upload: leanh
View: 217 times
Download: 2 times
Share this document with a friend
64
US Steel/Spirit Lake Sediment Cleanup Update for River Corridor Coalition Erin Endsley, Project Manager Mike Bares, Technical Analyst Minnesota Pollution Control Agency August 26, 2015
Transcript
Page 1: U.S. Steel Superfund Site

US Steel/Spirit Lake Sediment Cleanup

Update for River Corridor Coalition

Erin Endsley, Project Manager Mike Bares, Technical Analyst

Minnesota Pollution Control Agency August 26, 2015

Page 2: U.S. Steel Superfund Site

Outline • Site history • SLR AOC and GLLA • Planned cleanup activities • Sediment Feasibility Study • Discussion of Alternatives • Remedy selection process • Project timelines/next steps • Questions and discussion

Page 3: U.S. Steel Superfund Site

US Steel Superfund Site

Page 4: U.S. Steel Superfund Site

USS and St. Louis River AOC

Page 5: U.S. Steel Superfund Site

Great Lakes Legacy Act (GLLA) • Provides funding for contaminated sediments

– “legacy” contamination • Goal: Accelerate the pace of sediment

remediation at Areas of Concern (AOCs) • US Steel: estuary sediments eligible for Legacy

Act funding as part of the SLR AOC • Mechanism: Use partnerships as an

innovative approach to conducting sediment remediation

• Opportunities for habitat restoration in conjunction with sediment remediation

Page 6: U.S. Steel Superfund Site

Completed or ongoing projects

Great Lakes Legacy Act Projects

Page 7: U.S. Steel Superfund Site

Program Involvement • Superfund site, listed on NPL in 1983 • 1995 - MPCA lead agency under deferral pilot

project with EPA • US Steel – responsible party • EPA-Great Lakes National Program Office –

administers Legacy Act program, voluntary program based on partnerships

• USS and GLNPO project agreement for contaminated sediments – feasibility study and remedial design

Page 8: U.S. Steel Superfund Site
Page 9: U.S. Steel Superfund Site

550 acres of land

approximately 300 acres of

impacted Estuary

sediments

USS Site Areas

Page 10: U.S. Steel Superfund Site

USS and EPA-GLNPO

USS

USS

USS

USS and DSPA

MPCA is overseeing all remedial work through Superfund, Voluntary and Petroleum Programs

USS Partnerships

Page 11: U.S. Steel Superfund Site

Upland Stream, Basin

& Wetland

Sediments

Unnamed Creek Corridor & Delta

Unnamed Pond

Wire Mill Pond

Tar Pits

Page 12: U.S. Steel Superfund Site
Page 13: U.S. Steel Superfund Site
Page 14: U.S. Steel Superfund Site
Page 15: U.S. Steel Superfund Site
Page 16: U.S. Steel Superfund Site
Page 17: U.S. Steel Superfund Site
Page 18: U.S. Steel Superfund Site
Page 19: U.S. Steel Superfund Site
Page 20: U.S. Steel Superfund Site

St. Louis River Estuary

Sediments

Steel Creek Delta

Wire Mill Delta

Page 21: U.S. Steel Superfund Site
Page 22: U.S. Steel Superfund Site
Page 23: U.S. Steel Superfund Site

1861

Page 24: U.S. Steel Superfund Site

1861

Page 25: U.S. Steel Superfund Site
Page 26: U.S. Steel Superfund Site
Page 27: U.S. Steel Superfund Site
Page 28: U.S. Steel Superfund Site

Remedial Cleanup Steps • Remedial Investigation - Develop understanding of

study area and determine magnitude and extent of contamination

• Feasibility Study - Develop alternatives for cleanup and evaluate the alternatives

• Proposed Plan - Document for the public that identifies MPCA’s preferred cleanup plan

• Design - Engineering design and plans for the cleanup • Construction - The physical work that is done to

complete the cleanup • Long-term Monitoring - The inspections and sampling

that make sure the cleanup was successful and continues to be protective

Page 29: U.S. Steel Superfund Site

Superfund Feasibility Study Goals and Considerations

1. The cleanup remedy will protect human health and the environment

2. FS must consider the estuary sediment remedial actions and Upland source control

3. FS must consider land ownership – current and anticipated future use

4. Other considerations: § Preserve upland for future economic redevelopment § GLNPO involvement will provide habitat betterment § Input from the resource managers (MNDNR, USFWS, Tribes,

City of Duluth, USACE, SLRA)

Page 30: U.S. Steel Superfund Site

Feasibility Study (FS) • Completed July 2015; approx. 2-yr process • 12 alternatives developed • Stakeholder input incorporated into

development of alternatives • 5 advanced through more detailed analysis • FS identifies USS and GLNPO’s preferred

alternative – Alternative #8 • Alternative #12 developed based on tribal

input

Page 31: U.S. Steel Superfund Site

Common Remedy Elements • Consolidation of contamination on Upland

units in confined disposal facilities (CDFs) • Dredging, excavation and capping • Natural cover and thin covers • Unnamed Creek will be reengineered to

control storm water • Wire Mill Pond and surrounding dredge spoil

piles will be completely removed creating 7-9 acres open water

• Habitat betterment considerations

Page 32: U.S. Steel Superfund Site

Alt 4: CDF on OU-M Delta

Page 33: U.S. Steel Superfund Site

Base

Page 34: U.S. Steel Superfund Site

Cap

Cap

Alt. 4

Total Removal Volume 354,000 yd3

Total Capping Area 181 acres

Net Change in Open Water +9 acres

Estimated Project Cost $61,000,000

8 feet

Reroute Steel Creek Outlet

Page 35: U.S. Steel Superfund Site

35 Alt 6: Shallow Sheltered Bay

w/Delta & Upland CDFs

Page 36: U.S. Steel Superfund Site

Base

Page 37: U.S. Steel Superfund Site

37 Alt. 6

CDF

Cap

CDF

6 feet

25 feet

19 feet

Cap

Total Removal Volume 648,000 yd3

Total Capping Area 196 acres

Net Change in Open Water +20 acres

Estimated Project Cost $68,000,000

Depth 3-6 feet

Page 38: U.S. Steel Superfund Site

38 Alt 7: Shallow Sheltered Bay; Delta Cap Area; Upland CDFs

Page 39: U.S. Steel Superfund Site

Base

Page 40: U.S. Steel Superfund Site

40 Alt. 7

Total Removal Volume 616,000 yd3

Total Capping Area 196 acres

Net Change in Open Water +20 acres

Estimated Project Cost $84,000,000

20 feet

20 feet

25 feet

0-3 feet

Depth 3-6 feet

Page 41: U.S. Steel Superfund Site

Alt 8: Shallow Sheltered Bay w/Delta & Upland CDFs

Page 42: U.S. Steel Superfund Site

Base

Page 43: U.S. Steel Superfund Site

Cap

CDF

CDF

CDF

Alt. 8

Total Removal Volume 648,000 yd3

Total Capping Area 196 acres

Net Change in Open Water +20 acres

Estimated Project Cost $66,000,000

9 feet

25 feet

6 feet Depth

3-6 feet

Page 44: U.S. Steel Superfund Site

Alt 12: Open Water Bay w/ Upland CDFs

Page 45: U.S. Steel Superfund Site

Base

Page 46: U.S. Steel Superfund Site

CDF

CDF

CDF

Cap

Alt. 12

20 feet

20 feet

25 feet

Total Removal Volume 716,000 yd3

Total Capping Area 207 acres

Net Change in Open Water +44 acres

Estimated Project Cost $77,000,000

Depth 1-2 feet

Page 47: U.S. Steel Superfund Site

SF Remedy Selection Criteria • Overall Protection of Human Health and the

Environment • Compliance with ARARs (applicable or

relevant and appropriate requirement) • Long Term Effectiveness and Permanence • Reduction of Toxicity, Mobility, or Volume • Short Term Effectiveness • Implementability • Cost • Community Acceptance • Support Agency Acceptance

Page 48: U.S. Steel Superfund Site

Resource Manager Concerns • Maximize removal of contaminated

sediment • Improve substrate for benthic communities • Increase area and density of aquatic

vegetation • Increase area of off-channel deep water • Improve habitat for fish, waterfowl,

songbirds • Maintain or increase recreational use • Protection of cultural heritage

Page 49: U.S. Steel Superfund Site

Conceptual Habitat Plan • Lower St. Louis River Habitat Plan

Project 2-7: Spirit Lake • Desired habitat elements:

• Saturated islands • Shallow and deep marsh • Shallow, open water • Mid-depth, open water • Deep, open water

• Objective – create “back bay” system with sheltered bays and shallow wetlands

Page 50: U.S. Steel Superfund Site
Page 51: U.S. Steel Superfund Site
Page 52: U.S. Steel Superfund Site

City of Duluth Concerns • Impacted property owner -

• City will negotiate with USS for compensation for impacts to their property

• USS will negotiate access agreement with City

• Limits on property use during construction • Impact of CDF berm heights on use of City-

owned property • Additional CDF limits land available for

redevelopment • Decision on post-cleanup land use

Page 53: U.S. Steel Superfund Site

City Owned Property

Significant Area of Future Land Use

Page 54: U.S. Steel Superfund Site
Page 55: U.S. Steel Superfund Site
Page 56: U.S. Steel Superfund Site
Page 57: U.S. Steel Superfund Site
Page 58: U.S. Steel Superfund Site

Tribal Concerns • Formal consultation with EPA under

Section 106 requirements (NHPA) • Stakeholder – input from tribes used to

develop Alternative #12 • Disposal of contaminated sediment in the estuary

considered a desecration of a sacred place • Open water for wild rice restoration • Similar habitat concerns as resource managers

• Legal ownership of Spirit Island • Viewsheds being considered in SHPO review

Page 59: U.S. Steel Superfund Site

169 acres of high potential area for wild rice restoration

Wild Rice Restoration Implementation Plan for the St. Louis River Estuary, 2012

Page 60: U.S. Steel Superfund Site

GLNPO Concerns • Timing/availability of funding • Habitat betterment is a priority • Priority to address contamination in AOC in

a timely manner • Legacy Act funding is a voluntary

partnership based program; SF is an enforcement based program

• Habitat improvements - during remediation vs. post-remediation

Page 61: U.S. Steel Superfund Site

Community Concerns • How can we be informed and provide input? • What will the impacts be to the neighborhood

during construction? • What will the area look like after the cleanup? • Will there be increased access or recreational

opportunities? • How will we know conditions will continue to be

safe after the cleanup?

Page 62: U.S. Steel Superfund Site

Next Steps • MPCA remedy selection Sept 2015 • Proposed Plan Sept 2015

• Public Comment Sept/Oct 2015 • Public Meeting Oct 1 2015

• Responsiveness Summary/Final Cleanup Plan • USS/GLNPO Project Agreement • Design/Permits: ongoing • Construction: Summer 2016-2018?

Page 63: U.S. Steel Superfund Site

More Info For more information: • Project Manager: Erin Endsley • Email: [email protected] • Phone: 218-302-6619 • Site information:

http://www.pca.state.mn.us/mvri83b • Sign up to be added to the email list

and/or the mailing list.


Recommended