Date post: | 20-Jan-2018 |
Category: |
Documents |
Upload: | ambrose-berry |
View: | 218 times |
Download: | 0 times |
W E S T E R N E L E C T R I C I T Y C O O R D I N A T I N G C OU N C I L
Use of EDWG Data by the LTPT
WECC StaffJanuary 15, 2016
2
W E S T E R N E L E C T R I C I T Y C O O R D I N A T I N G C OU N C I L
What is the LTPT?
The LTPT - Long Term Planning Tool:• Is a capital expansion tool • 20 year study horizon • Evaluating potential energy future
3
W E S T E R N E L E C T R I C I T Y C O O R D I N A T I N G C OU N C I L
LTPT
• LTPT comprised of:– SCDT-Study Case Development Tool– NXT-Network Expansion Tool
4
W E S T E R N E L E C T R I C I T Y C O O R D I N A T I N G C OU N C I L
SCDT
• SCDT - Study Case Development Tool– Produce Study Case– Optimized study case representing potential
“energy future”– Comprised of reduced nodal network model– Transmission expansion candidate lines– Transmission capital cost– Minimum cost generation optimization-decision
factors, constraints
5
W E S T E R N E L E C T R I C I T Y C O O R D I N A T I N G C OU N C I L
NXT
• NXT - Network Expansion Tool– Relieves candidate lines for four system conditions
Heavy Summer, Light Spring, Light Fall, Heavy Winter, oveloaded, loss of load etc
– Optimized transmission network expansion– Mitigating engineering constraints– Grid cost components applicable to study case
6
W E S T E R N E L E C T R I C I T Y C O O R D I N A T I N G C OU N C I L
LTPT Process Workflow
Perform Modeling
No
Yes
Define Scenarios to be examined in narrative
Parameterize Scenarios / Sensitivities
Does Parameterization affect
Scenario narrative?
Are results reasonable?
No Yes Select ‘no regrets’ investments; decide other
recommendations
Compare Scenario results based on pre-determined Metrics
Are sensitivities of Scenarios
required?
Yes
No
Define Metrics to be used to evaluate
Scenario/Sensitivity results
7
W E S T E R N E L E C T R I C I T Y C O O R D I N A T I N G C OU N C I L
10-Year & 20-Year Planning Comparison
Attribute 10-Year Studies 20-Year Studies
Tool Production Cost Model Capital Expansion Model
Objective Minimization Production Cost Capital CostFocus Capacity additions and specific
projects, planned and in progressUnderstanding potential “energy futures” and decisions needed to achieve those futures
Model decides to Dispatch Generation Build Gen and TransmissionLoad From balancing authorities w/
stakeholder adjustmentFrom balancing authorities w/ stakeholder adjustment
Resources Stakeholder specific Stakeholder specific and LTPT optimized
Transmission Stakeholder specific Stakeholder specific and LTPT optimized
Time Granularity Hourly / Sub-hourly Annual / Seasonal Load Durations
Interdependence Starting point of 20-Year Informs 10-Year
8
W E S T E R N E L E C T R I C I T Y C O O R D I N A T I N G C OU N C I L
EDWG Data in LTPT
• EDWG Data in LTPT– Transmission route finding input– No Siting– More realistic cost estimate– Environmental Risk– Line weighting-Financial Element
9
W E S T E R N E L E C T R I C I T Y C O O R D I N A T I N G C OU N C I L
Risk Weightings
• EDWG Risk Category Weightings– Think of the weighting similar to miles
• Staying in the fairway.• Avoiding hazards.• Minimizing strokes.
Traversing the geospatial landscape
11
W E S T E R N E L E C T R I C I T Y C O O R D I N A T I N G C OU N C I L
Overlay EDWG and Transmission Candidate Cooridors
12
W E S T E R N E L E C T R I C I T Y C O O R D I N A T I N G C OU N C I L
• Build cost surfaces• Bend corridor
routing to minimize environmental impact.
Optimize Corridors
13
W E S T E R N E L E C T R I C I T Y C O O R D I N A T I N G C OU N C I L
Transmission Models and Assumptions• Start with TEPPC 2024 Power Flow Model• Delineate load and generation hubs.• Perform Network Reduction, preserving interface and CCTA
transmission lines.• Define aggregation zones delineated by WECC Paths.• Define list of monitored lines based on aggregation zones.• Define transmission technology types and characteristics.• Define list of candidate corridors based on tiered rules.• Optimize corridor routing
14
W E S T E R N E L E C T R I C I T Y C O O R D I N A T I N G C OU N C I L
Economic Models and Assumptions• Fuel Prices
– Henry Hub per EIA Annual Energy Outlook (converted to 2014 dollars)
– Differentials by state– Progress multipliers per E3 Capital Cost Tool/Report
• Resource Types & Costs– Capital Cost: E3 Capital Cost Tool (“E3 Tool”),
TEPPC approved– Future types & Progress multipliers - 2027 Vintage
per E3 Tool– Simplified LCOE Model - E3 Tool
• Policy– CO2 Price: $37.11/MT
• Per stakeholder input – Metric Definition Task Force (MDTF)
– No PTC, Solar ITC reduced to 10%• Per E3 forecast of federal policy
– Coal constraints per stakeholder input
EIA – U.S. Energy Information AdministrationAEO – Annual Energy OutlookDG – Distributed GenerationRPS – Renewable Portfolio StandardNREL – National Renewable Energy Laboratory
• Transmission Costso Per TEPPC Capital Cost Update: B&V
analysis/report and tool, with stakeholder review/approval
o Includes Transmission and Substation Costs
o Cost Factors Include: EquipmentTerrain ROW AFUDC Breakers Transformers Voltage Compensation
o LCOE per E3 “levelization calculation”(E3 Captial Cost Tool)
PTC – Production Tax CreditITC – Investment Tax Credit
15
W E S T E R N E L E C T R I C I T Y C O O R D I N A T I N G C OU N C I L
Focus on Inter-regional needs
16
W E S T E R N E L E C T R I C I T Y C O O R D I N A T I N G C OU N C I L
Tool Enhancements
• Introduction of Corridor Library• Parameterized Goals• Parameterized Constraints• Co-optimization across seasonal and load level
conditions• Improved reduced network model