+ All Categories
Home > Documents > Utility Scale PV and CSP Solar Power Plants

Utility Scale PV and CSP Solar Power Plants

Date post: 03-Jun-2018
Category:
Upload: seawave
View: 230 times
Download: 0 times
Share this document with a friend

of 18

Transcript
  • 8/12/2019 Utility Scale PV and CSP Solar Power Plants

    1/18

    Utility Scale PV and CSP Solar Power PlantsPerformance, Impact on the Territory

    and Interaction with the Grid

    Authors:

    Martino BosatraFederico Fazi

    Pier Franco Lionetto

    Luca Travagnin

    Foster Wheeler Italiana Milan, Italy

    Presented at

    Power-Gen Europe 2010

    Rai, Amsterdam

    The Netherlands

    June 8 10, 2010

    TP_SOLAR_10_01

  • 8/12/2019 Utility Scale PV and CSP Solar Power Plants

    2/18

    Utility-Scale PV and CSP solar power plants

    Performance, impact on the territory and interaction with the grid

    Martino Bosatra, Federico Fazi, Pier Franco Lionetto, Luca Travagnin

    Foster Wheeler ItalianaCorsico (Milan- ITALY)

    1

    ABSTRACT

    PV and CSP Solar Power Plants represent today one of the most booming segments within renewable

    energy market. Both type of solar plants, boostered by favorable feed-in tariffs, are under

    construction in different countries covering a range of size (up to 100MW) commonly reserved to

    conventional technologies (thermal or combined cycle power plants). The report analyses the PV and

    CSP Plant technologies and compares them with respect to landscape impact, performance and

    impact on the grid (both in normal and transient condition). The relationship with the ancillary

    services needed by the Grid to ensure

    high service continuity and high quality level is investigated and possible future scenarios are

    discussed starting from the requests of Grid-Codes.

    2 INTRODUCTION

    Utility-Scale photovoltaic (PV) plants and Concentrated Solar Power (CSP) plants are becoming a reality.

    The uptake of such type of solar plant is expected to accelerate during the next decade especially in regions

    such as Southern Europe due to the presence of high solar irradiance and the continuous pressure for the

    implementation of numerous renewable energy generation technologies.

    The growth of such plant is granted only if unlimited access to the HV and EHV grid is allowed. Besides

    this issue, the higher penetration of renewable energies (especially wind and solar) harbors the risk of grid

    instability in case the generating plants are not able to properly support the Grid. Thus leads to the search for

    new developments with respect to the device design which should be armed with the task of supporting the

    grid operation and stability. New interconnection requirements, especially those are related to Utility-Scale

    PV plants, are coming into force in several European countries with the aim to serve as a planning document

    and decision guidance for the project designer and for the PV equipment Manufacturers.

    In the light of the above, a qualitative comparison has been carried out between an Utility-Scale PV plant

    and a CSP plant with nominal capacity of about 50 MW, reasonably assumed as reference size for both

    technologies (this size looks typical for most of the existing plants of both technologies). At once it has been

    necessary to define a specific region (Southern Italy) for which were known solar beam (i.e. irradiance level)

    and average ambient conditions, having these aspects huge influence on Plant design.

    Then it have been analyzed pros and cons of the two PV and CSP plants in terms of performance, i.e.

    efficiency and energy production, and impact on the territory, i.e. how many Hectares are needed and which

    is the impact on the regions where installation of such plants seem to be more probable.

  • 8/12/2019 Utility Scale PV and CSP Solar Power Plants

    3/18

    This report would also outline which one of these two different solar plants may be nowadays considered as

    less impacting on the Grid, which of them may or may not contribute to the grid stability during transients

    and finally which would be the technological improvements that may be required to make them compliant

    with the mandatory Grid Code requirements. The analysis do not refer to a specific Grid connection point

    but refers anyway to the European HV network because the majority of the existing Utility-Scale PV Plants

    and CSP plants are nowadays localized in Europe. Therefore the study refers to European Grid &

    Transmission Codes and in particular makes reference to the German Transmission Code [1], which was the

    first one, within the whole European Countries, had approached the topic of the renewable generating units

    and their impact on the Grid.

    3 SOLAR ENERGY RESOURCES GROWTH AND GLOBAL INSTALLED POWER

    3.1 PV installations overview [1] [2]

    The solar PV sector has been booming over the last decade and is forecast to confirm this trend in the

    coming years. By the end of 2009 the Global worldwide cumulative capacity was approaching 15 GW.

    Today, Europe is leading the way with more than 14 GW representing over 65% of the Global cumulative

    PV installed capacity equal to almost seven times the installed power in Japan and ten times that of USA,

    confirming as leader in the geographic area of PV installations. The growth in installations in Europe is even

    more interesting when compared with the rest of the world, because in terms of market dynamics there was a

    significant increase of so-called Utility-Scale PV plants.

    However, this Europe leadership is the result of strong inhomogeneous in the growth of the States

    composed, with some realities that are confirmed excellent market for PV, other that "marking time" and

    others that seem to be well placed to play an important role in the near future.

    These differences can be explained by the relative importance of plants segments (i.e. building installations,

    industrial installations and multi-megawatt installations), and by policy choices of national governments,

    resulting in rules and incentives to promote greater one segment respect to another and by the morphology

    of the national territory that might be a limitation especially for larger plants.

    3.2 CSP installations overview [3] [4] [5]

    After almost 20 years of silence, in the early years of the new millennium, CSP gained interest again and

    new plants have been built not only in USA but also in Europe.

    At the moment the total worldwide installed power is approximately 655 MW producing 1400 GWh of

    electric power in a year. Apart from USA and Spain, other countries where CSP plants are going to be built

    or at least in project, are Australia, India, Central Asia, Mexico and the Mediterranean countries like Italy,

    France, Greece, Turkey, Morocco, Libya, Algeria, Egypt and Israel.

  • 8/12/2019 Utility Scale PV and CSP Solar Power Plants

    4/18

    In contrast to the PV sector, the CSP industry is far less fragmented; with some of Europes best solar

    resources and a favorable tariff regime, Spains solar CSP sector is well positioned, 22 projects under

    construction for total 1,037 MWe out of the approximate 15 GW planned globally through 2014.

    Italy is the first country following Spain to make a significant move in support of CSP projects with FITs. In

    2008, Italian Government issued the legislative decree that set a new FIT for CSP; this decree requires that

    all CSP plants, including hybrid plants, have to include thermal storage while in Spain storage technology is

    allowed but not currently required for system approval.

    4 SOLAR POWER PLANT TECHNOLOGIES

    4.1 Utility-Scale PV plant

    Utility-scale PV plant, sometimes called central station PV, acts more like a concentrated power plant,

    producing energy and delivering it to the grid. Traditionally Utility-Scale PV plants use flat PV module

    technology of either crystalline silicon (mono or poly-crystalline silicon types) or thin film modules (mainly

    of cadmium tellurideCdTe type). Such PV modules are characterized by different sizes, i.e. 0.7 m2 to 1.7

    m2, by different peak power, i.e. 70Wp to 250Wp, and by different efficiency ranges which typically are

    lower for Thin Film PV modules, i.e. from 10% to 12%, than for crystalline silicon PV modules, whose

    typical efficiency is in the range of 11% to 16%.

    Another PV technology is represented by the concentrating photovoltaic (CPV) plant technology, which is

    based on reflection of concentrated sunlight onto highly efficient photovoltaic cells (such as copper indium

    gallium diselinide - CIGS, and thin film amorphous silicon). Nowadays such technology is used only in

    smaller or prototype PV installations and therefore cannot yet be considered as a viable alternative to other

    technologies for bigger Utility scale PV plant installations.

    Since the Utility-Scale PV concept is relatively new, so these different technologies are to date competing

    with no clear winners even if most ofthe biggest Utility Scale PV plants (i.e. within the range of 4060

    MWp) have been realized by fixed system. The cost of PV tracking system is usually greater than the cost of

    fixed PV system as well its performance is greater than the performance of the fixed PV system.

    PV modules are installed on fixed metallic support structures arranged in long rows, adequately spaced

    themselves, facing south (in the Northern Hemisphere) with an appropriate tilt, or deployed on tracking

    devices to follow the sun. PV modules are electrically connected together in series and parallel and then

    connected by DC cabling to the centralized inverters which convert DC power into AC power. Then the

    Inverter are connected together, on a.c. side, to the plant Medium Voltage network, and then the produced

    energy is delivered to the HV or EHV Grid by means of one or more step-up transformers.

    4.2 CSP plant

    All the CSP (Concentrating Solar Power) technologies produce heat or electricity using hundreds of mirrors

    to concentrate the suns rays to high temperature (typically between 400C and 1000C).

  • 8/12/2019 Utility Scale PV and CSP Solar Power Plants

    5/18

    There are four different main CSP technologies depending if the solar radiation is concentrated on a linear

    collector system (Parabolic trough and Linear Fresnell) or on a central focal point (Solar Tower and

    Parabolic Dish).

    Among the possible CSP Technologies the Parabolic Through seems to be the most commercially proven

    and it appears to be, at present time, the favored by CSP plants developers. Though Power Tower lacks in

    experience with few plants in operation, in medium to long term this configuration may produce electricity

    at a lower cost than parabolic trough plants. On the other hand, Parabolic Dish and Linear Fresnell

    systems have not progressed beyond their initial demonstration phase, though these technologies have the

    potentiality to produce energy with lower capital cost respect the other two.

    The CSP technology taken as reference for this study is based on Parabolic Through technology, mainly

    constituted by:

    the Solar Field, constituted by the Solar Collectors, which collect and concentrate the solar radiation,

    and the by the Solar Receivers, which absorb the concentrated solar energy and convert it to useable

    heat for the power block;

    the heat Storage, which stores solar energy from solar field and dispatch it to the power block in case

    of less solar radiation;

    the Power Block (and Grid connection) which uses the heat collected from the sun to produce

    electricity and it is constituted by a steam generator and a steam turbine coupled to a conventional

    electrical generator (i.e. synchronous generator and excitation system) that generates energy which is

    delivered to the HV or EHV Grid by means of its own step-up transformer.In a parabolic trough system, the solar field consists of hundred of linear solar collector assembly (SCA).

    The collectors are horizontal modular array of long rectangular, curved (U-shaped) highly reflective mirrors

    disposed in parallel rows. Each modular array are single-axis-tracking (typically North-South to be always

    tilted toward the sun during the day) that focus solar energy onto a central receiver tube located along the

    focal line of the mirrors where it is absorbed. The receiver tubes are particular high radiation absorbent

    devices where in the inside flows a working fluid called heat transfer fluid (HTF), which has the scope to

    exchange heat from the solar field to the power block. HTF is usually synthetic thermal oil (byphenil oil)

    and it is heated to temperatures of around 400C. HTF pumped through a series of heat exchangers to

    generate superheated steam for use in a conventional steam turbine generator or integrated in a combined

    steam and gas turbine cycle.

    To increase CSP Plant flexibility, the HTF can be stored in two tanks (hot and cold) that provides many

    advantages (avoid dumping of solar energy, reduce over-size of the power block, increase CSP plant

    operating hours, etc) as detailed in next section. Recent advanced researches are experimenting different

    kind of HTF and developing more efficient solar collector and more sophisticated sun-tracking systems in

    order to improve plant performance. In spite of solid experience in this technology and more than 500 MW

    operating plants, research and development continue to play an important role to drive plant cost further

    down.

  • 8/12/2019 Utility Scale PV and CSP Solar Power Plants

    6/18

    5 TECHNICAL COMPARISON

    The technical comparison between the two solar PV and CSP plants has been performed on the basis of the

    following main design bases:

    50 MW size, reasonably assumed as reference size for both technologies

    both Thin Film and Poly-crystalline PV module technologies, both fixed and tracker systems for

    Utility-Scale PV Plant

    Parabolic Through technology for CSP Plant

    Location: southern Italy.

    The main factors used for the comparison have been:

    Landscape impact

    performance

    interaction with the Grid in steady state and transient condition

    To compare a 50 MWp Utility-Scale grid connected PV plant with a 50 MWe CSP plant it is necessary to

    define common design bases by siting the plant in a specific area with defined irradiation level. For the case,

    this report localizes both plants in a southern region of Italy characterized by a yearly averaged Incident

    Global Irradiation of approx. 1900 kWh/m2 year and 2200 kWh/m2 year, as respectively estimated for a

    fixed PV field with an optimum tilt of 30C and for tracker PV s, and a yearly averaged Direct Normal

    Irradiation of approx. 1800 kWh/m2year.

    The yearly averaged Incident Global irradiation is the effective radiation reaching the tilted PV module

    plane and it is the sum of incident direct radiation, Incident diffuse radiation (from sky) and incident albedo

    radiation for a given reference year.

    The yearly averaged Direct Normal Irradiation is the yearly average amount of solar radiation incident on a

    surface oriented normal to the solar radiation for a given reference year

    5.1 Landscape impact

    5.1.1 Utility-Scale PV plant

    The key factor in designing the Utility Scale PV plant is to gain, for any specific site, the optimal groundarea occupation ratio (GAOR) without valuable reduction of expected performance ratio.

    The GAOR is calculated as ratio between the total surface of the PV modules used to realize the PV field

    and the ground area occupied by the PV field. The GAOR is affected by the shed disposition of PV arrays

    (i.e. by the distance between the rows of PV modules) which depends by PV array tilt angle and by limit

    shading angle. PV array tilt angle mainly depends by physical dimension of PV modules and by their ability

    to capture and transform as much as possible diffuse irradiance (thin film modules are usually better than

    crystalline silicon modules). As first approximation, the optimal limit shading angle for southern Italylatitudes corresponds to the angle (approximately around 20) needed to avoid shadows between 10 a.m. and

    2 p.m. on winter solstice. PV field performance slightly increased by increasing, for a given tilt angle, shed

  • 8/12/2019 Utility Scale PV and CSP Solar Power Plants

    7/18

    distance because thus reduces shadows (especially during winter time) and therefore helps to reduce

    mismatch losses.

    GAOR typical values, for a fixed installation localized in southern Italy, is in the range of 0.4 0.6, which

    corresponds to a tilt angle range of 35 25 (lower tilt are often used for thin-film PV modules arrays due

    to their better response to diffuse irradiance) while for the tracker system the GAOR is in the range of

    0.20.3.

    The corresponding ground area typically required for the same PV field, always localized in southern Italy,

    amounts approx. to 2.2 2.5 Ha/MWpif thin film PV modules are used, while amounts approx. to 1.7 2.1

    Ha/MWp if crystalline silicon PV modules are used (efficiency of crystalline silicon PV modules is better

    than the efficiency of thin film PV modules; typical values are respectively in the range of 14 16% and

    1012%).

    On the basis of the above figures, the estimated ground area needed to build a 50MWpUtilityScale PV

    plant amounts to approx. 120140Ha, for fixed PV field constituted by thin film PV arrays, and to

    90110Ha for fixed PV field constituted by crystalline silicon PV arrays.

    In case of a tracker PV field, the required ground area amounts approx. to 4 4.5 Ha/MWp , if thin film PV

    module are used, while amounts approx. to 3 3.5 Ha/MWpif crystalline silicon PV modules are used.

    Even if these different technologies and arrangements are nowadays competing with no clear winners, it

    can be observed that, in terms of land impact, fixed PV field requires about half of the area necessary for a

    Tracker PV system and as highlighted above the selection of PV modules may play an important role in

    determining the area required by the plant. Therefore it can be concluded that for bigger size of Utility-ScalePV plant, the fixed PV field arrangement should be preferable when compared in terms of land impact.

    5.1.2 CSP plant

    The Key factor that affects the CSP plant size, performance and thus land occupation, is the direct normal

    irradiation of the site which optimum value should be over than 1800 kWh/m2year.

    The CSP plants land occupation depends by the total installed collector surface and also by the space

    between each solar collector assembly required to minimize shadows and also to allow the maintenance of

    the big curved reflecting mirrors.

    Additional surface is required for the power block and heat storage, both usually located in the middle of the

    plant area and with an occupation much smaller respect to the solar field.

    Typical surface required by CSP plant localized in southern Italy as the PV plant above considered, with

    Direct Normal Irradiance of 1800 kWh/m2year, is in the range of 34 Ha/MW. However each plants solar

    field area, in a determinate location with a certain daily average direct normal irradiation, needs to be

    optimized respect to solar collector area and heat storage capacity in order to reach the minimum levelized

    cost of energy that is usually reached by installing an heat storage of approx. 6 hours.

    Therefore the estimated area required for a 50MW CSP plant hypothetically localized in southern Italy and

    based on Parabolic Through technology, amounts totally to approx. 160170 Ha

  • 8/12/2019 Utility Scale PV and CSP Solar Power Plants

    8/18

    5.2 Performance

    5.2.1 Utility-Scale PV plants

    To maximize sunlight exposition PV plants are designed by selecting the optimal tilt angle and the azimuth

    angle and thus by avoiding, as much as possible, shading between PV arrays. The energy produced by a PV

    system depends by:

    solar radiation incident on the modules plane, which depends on :

    latitude of the installation site

    front surface reflectance of photovoltaic modules

    exposure of modules: the tilt angle (angle between the horizontal plane and the plane of the

    module surface) and the angle of orientation (azimuth angle)

    any shade or fouling of photovoltaic modules

    ambient temperature

    the characteristics of the modules: power rating, temperature coefficient,

    mismatch losses, due to inverter mismatch and/or due to non homogeneous module

    characteristics connected in series and parallel, etc.;

    the characteristics of the BOS such as efficiency of inverter, losses in the cables and diodes,

    etc.

    Variations in solar radiation and ambient temperature from month-to-month and year-to-year influence the

    performance parameters.The electricity produced by the Utility-Scale PV plant can be determined according to the method defined

    by the EN 61724 standard which defines the PV overall system performance with respect to the energy

    production, solar resource, and overall effect of system losses. These parameters are the final PV system

    yield Yf, the reference yield Yr, and the performance ratio PF.

    The performance ratio PR (dimensionless) is the Yf divided by the Yr.

    Yf represents the number of hours that the PV arrays would need to operate at its rated power to provide the

    same energy and it is expressed in hours or kWh/kW while Yr represents an equivalent number of hours atthe reference irradiance.

    Yrdefines the solar radiation resource for the PV system and it is a function of the location, orientation of the

    PV array, and month-to-month and year-to-year weather variability.

    The expected performance of a 50 MWpUtility scale PV plant, localized in Southern Italy, is shown in the

    following table; the tracker PV system produces approximately 20% more energy than a fixed PV filed, on

    yearly basis with the same nominal installed power.

  • 8/12/2019 Utility Scale PV and CSP Solar Power Plants

    9/18

    Tab.1

    Utility Scale PV plant

    Performance table

    Fixed PV system Tracker PV system

    Thin film PV

    72.5 Wp

    Poly-crystalline

    220 Wp

    Thin film PV

    72.5 Wp

    Incident Global Irradiation ~1900 kWh/m2year ~2150 kWh/m2year

    Solar field total surface ~ 500000m2 ~ 370000 m2 ~ 500000 m2

    Total Plant area ~ 120 Ha ~ 85 Ha ~200 Ha

    Installed PV Peak Power 50 MWp

    Energy production

    (at inverter output terminals)~ 75 GWh/y ~ 90 GWh/y

    PR (yearly average) ~ 0.79 ~ 0.83

    5.2.2 CSP plant

    As per Utility-scale PV plant, performance of a CSP plant is affected by variations in solar radiation,characteristics of solar collectors, and by geometrical factors such as shadows, etc.

    For CSP plants it can be defined an efficiency factor so-called capacity factor of the plant. This is the ratio

    of the energy produced by the plant over the course of the year to the output had the system operated at its

    nameplate capacity (e.g. nominal size of the steam turbine for 8760 hours).

    The capacity factor strongly depends on the solar resource available in a certain location and on the solar

    field size, so on the mirrors area. Oversize the solar field allows the plant to provide more thermal energy to

    the power block and consequently results in a higher capacity factor but also leads to an increase ofinvestment cost. On the other hand, if the solar field area is reduced, a consistent part of the potentially

    available solar energy is dumped during high solar radiation days: the thermal energy to the power block is

    beyond the steam turbine maximum admissible thermal input.

    The expected performance of a CSP plant of this size, always localized in the same place of South Italy, is

    shown in the following table.

    Tab.2 - CSP Plant - Performance table Parabolic Trough

    Averaged Direct Normal Irradiation 1800 kWh/m2 year

    Solar field (collector surface) ~ 500000 m2

    Total Plant area ~ 165

    Thermal Storage 6 h

    Thermal input at power block 140 MWth

    Net Power Output 50 MWe

    Net Solar Electric Energy Production ~ 120 GWhe/y

    Capacity factor 27

  • 8/12/2019 Utility Scale PV and CSP Solar Power Plants

    10/18

    5.3 Interaction with the Grid in steady state and transient conditions

    5.3.1 Solar plants and Grid exploitation constraints

    The worldwide liberalization of the electrical power generation has brought the issue of market equilibrium

    into the electricity power industry and therefore all the generating firms have to compete by exercising

    market power trying to maximize their individual profit but the competition with solar power generation,

    especially with Utility Scale PV plants, may affect the bidding strategies of the conventional generating

    firms with potential impact on the nodal prices and profits.

    The presence of solar power generation gives incentives to the conventional generating firms to exercise

    market power in a different way than the case in which the entire generation output is based upon

    conventional power plants only, resulting in a different market outcome; in the presence of solar generation,

    the conventional generating firms would be forced to decrease their bidding parameters in order to cope with

    the increased availability of supply. Hence, since the solar plants are operated in a competitive manner, the

    market clearing price is reduced, thus the social welfare is increased. On the other hand, at the time whenthere is inadequate solar irradiance for the solar plants to generate power, the conventional generating firms

    may take advantage of the lack of supply and alter their bidding strategies in order to force the nodal prices

    to increase, thus increasing their profits. Considering that EU has set very ambitious targets regarding the

    penetration of renewable power generation, it can be anticipated that the implementation of multi-megawatt

    solar plants may cause some problems regarding the market prices.

    This issue may be more remarkable if the network to which the solar plants are connected present some

    bottle necks causing congestion (e.g. overload of lines that, due to safety reason, obliged connected solarplants to reduce their output). Furthermore, this effect would be more severe in Southern Europe regions (or

    islands without suitable interconnection with the continental Grid) where unfavorable weather conditions

    (especially for PV that is affected by temperature) and better irradiance can have a crucial impact on the

    produced power.

    Large-scale integration of multi-megawatt Solar Plants, especially Utility Scale PV plants, into Grid

    operation would therefore lead to new operation constraints (e.g. power is produced during the day, when

    the electricity demand is high, thus it is valuable peak current), for the entire HV distribution & transmission

    system, that could result unacceptable in the next years in terms of system performance (grid and generating

    plant). This fact would requires a rethinking of both the grid exploitation modality and of design of solar

    plants, by adding for instance appropriate storage system.

    a) CSP plant thermal Storage System

    The optimum solution to keep a high capacity factor and a constant power production is to adopt the heat

    storage technology.

    With the heat storage, the energy excess from the solar field can be stored and dispatch to the power block

    during solar radiation lack. Theoretically CSP plant with substantial heat storage can reach 100% capacity

    factor and may provide base-load electricity as the conventional fossil fuel plants. In other words if sky is

  • 8/12/2019 Utility Scale PV and CSP Solar Power Plants

    11/18

    momentarily clouded or even during first hours of night time, CSP plant may operates at its regime putting

    to use the solar energy previously stored.

    Depending on the storage medium, the heat storage systems can be either direct (storage medium is the

    same HTF circulating in the solar field concentrator, e.g. synthetic oil) or indirect (storage medium is

    different from the HTF, e.g. synthetic oil as HTF and molten salts as storage medium).

    Advanced heat storage systems are under development. Nowadays the most used and commercially

    available heat storage technology for parabolic trough is the two-tank indirect thermal storage.

    Two-tank indirect system is based on two tanks typically filled with molten salts (60% sodium nitrates and

    40% potassium nitrates): one hot tank and one cold tank. The excess of solar energy from the solar field is

    directed to a heat exchanger where cold molten salts are taken from the cold storage tank, heated from

    approximately 290C to 390C and then stored in the hot tank. When energy is needed, the system operates

    in reverse: the heated molten salts from the hot tank are pumped to the heat exchanger to reheat the HTF.

    In the following graph it may be appreciate how during high radiation hours the solar energy is delivered to

    the power block and to the heat storage. After filling the hot tank of the heat storage, the excess of energy

    has to be dumped. During the first hours of night, when there is obviously no solar radiation, the heat storage

    supplies energy to the power block.

    0

    100

    200

    300

    400

    500

    600

    700

    800

    900

    1000

    1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24

    Hour of Day [h]

    Direct Normal Irradiation

    To steam turbine

    Net electric output

    Dumped energy

    To heat storage

    From heat storage

    450

    300

    150

    50

    DirectNormalIrradiation[kWh/m2

    day]

    Power[MW]

    Fig.1typical summer day CSP plants performance with thermal storage

    b) PV plant battery storage System

    PV plants are intermittent resources especially because performances are strictly related to irradiance

    condition and ambient temperature which affect power output. Using battery storage which has the

    capability to be quickly started or changed from charging to discharging in millisecond time frame, may

    help to smooth spikes due to intermittent clouds over a PV system (which cause output to spike widely) and

    make them more dispatchable, increasing their capacity factors.

  • 8/12/2019 Utility Scale PV and CSP Solar Power Plants

    12/18

    Battery size will depend on the amount of peak shaving desired; if the load profile to be guaranteed doesnt

    allow peak shaving beyond a certain limit, the constraints being the depth of discharge limitations on the

    battery itself. Of course is not so easy to determine the required daily battery discharge capacity since

    producible energy is not constant all over the year and not easy to predict. Less storage may be required to

    shave the peak day load shape during summer then what is required for winter peak day load. Although the

    batteries have to be available to operate, they do not necessarily have to be operated on a daily

    charge/discharge cycle to enhance power output capacity. Thus, relatively inexpensive light-duty batteries

    would be adequate to enhance their capacity factors especially during the summer (cycling less than 50

    times per year vs. heavy-duty and more costly batteries cycling daily up to 250 times per year).

    0

    5

    10

    15

    20

    25

    30

    35

    0

    200

    400

    600

    800

    1000

    1200

    0 4 8 12 16 20 24

    Power[MW]

    GlobalincidentirradianceinPVmoduletiltedplane

    [kWh/m.day]

    Hour of Day [h]

    Global incident irradiance,

    clear sky model

    Global incident irradiance

    in PV module tilted plane

    Net Power at grid

    connection Point

    to battery storage

    from battery storage

    6

    6.5

    7

    7.5

    8

    8.5

    9

    Power[MW]

    Time of Day [hh:mm]

    Fig.2typical summer day Utility-Scale PV plants performance with battery storage system

    5.3.2 Solar plants and Grid Code rules

    Multi-megawatt solar plants have to be connected either to HV or EHV networks. The grid connection point

    and the voltage level to which the plant has or can be connected it depends by local network conditions and

    also by different rules adopted by different countries; in some cases this can only be determined by acalculation of the network operator.

    In the last couple of years, some new Directives and new Grid-Codes have been released by national

    Authorities and by Transmission System Operators; such guidelines are not harmonized and therefore

    inhomogeneous requirements are still required at national level (most probably due to the local Grid

    situation). Facing the growth of multi-megawatt solar plants (most of them are Utility scale PV plants rather

    than CSP) connected to the HV distribution systems, the year 2009 brings fundamental changes for new PV

    systems in a number of European countries. While in the past, renewable generating units connected to thenetwork were commonly not required to take over an active role and had to disconnect at the first sign of

    trouble, the new guidelines now require also the renewable generating units to actively support the grid

  • 8/12/2019 Utility Scale PV and CSP Solar Power Plants

    13/18

    during normal as well as disturbed conditions. This step is being regarded more and more as absolutely

    necessary to guarantee reliability and quality of supply in the mid- to long-term. This new approach has

    already been adopted in Germany and France and is being to be adopted also by other countries.

    Although the new Directives and new Grid Codes introduced specific requirements for wind and solar

    generating plants, CSP plants are not specifically mentioned. It is unclear whether they should be treated as

    renewable generating units or should be considered, especially the Parabolic Through technology, in all

    respects as conventional generating units (due to behavior of power block which is used to generate

    electrical power from the solar field) and therefore have to comply with the relevant specific requirements.

    Mandatory requirements specified by German Transmission Code [6] (German Operator is the first one,

    within the whole European Countries, that has approached the topic of the renewable generating units and

    their impact on the Grid) for renewable generating units are analyzed in the following chapters

    a) Active power control (dispatching) and Remote set point control.

    To avoid possible network congestion in case of line loss due to electrical fault any renewable generating

    unit, such as Utility-Scale PV plant or and CSP plant, shall be able to reduce its power. Therefore the TSO is

    in the position to require curtailment of the power output of solar power plants to face with the specific

    critical system conditions. Different requirements may be applied for the CSP plants rather than the Utility

    Scale PV plants because the CSP looks like a conventional generating plant using rotating synchronous

    generating unit, while PV is using static inverter.

    Power output of PV generating plants has to be reduced in steps of 10% per minute, under any operating

    condition and from any working point to a maximum power value (target value) which could correspond

    also to 100% power reduction, without disconnection of the plant from the network.

    Such requirement might be applied also to CSP plants if they are considered in all respect as renewable

    generating units, otherwise they have to fulfill requirements set for the conventional generating units, which

    are required to reduce or to increase - their output with different ramp-rate (e.g. 1%/min. as required by

    German Transmission [1]) between the minimum stable generation power and the continuous output.

    CSP plants may fulfill the requirement set for the PV generating units provided that the set-point given by

    TSO is compatible with the minimum operating load of the boiler and steam turbine. Being the

    characteristics of the CSP plant similar to the traditional thermal power plant, the load reduction can reach

    values around 40% of the nominal capacity, with limiting factor the stable operation of the heat exchangers.

    The advantage of CSP is that, in case of temporary reduction (limited to few hours), the solar energy

    captured by solar field is not loosen because could be stored in the thermal storage system (of course it

    depends on specific storage capacity, by the actual operating condition, by sun condition, etc).

    Also for the Utility Scale PV plants such requirement do not constitute an issue provided that an automatic

    power sharing management system is installed and it is capable to modulate the production of the entire

    plant, by acting on each inverter, through a communication based solution, by sending new power output set

  • 8/12/2019 Utility Scale PV and CSP Solar Power Plants

    14/18

    points or by sending shut down command to disconnect several inverters, or again, by combining the two

    controls. Of course if battery storage system is not installed, the amount of reduced power is definitely lost.

    So from technical point of view there are no barriers that may prevent CSP and utility Scale PV plants to be

    compliant with such specific Grid-Code requirements, while a cost increase it may be envisaged for the PV

    plants (rather than CSP plants) to implement the power sharing management system.

    b)

    Automatic reduction of active power generation according to active power droop characteristic in

    situations of over-frequency

    To avoid risk of unsafe system operation when the frequency rise over a certain value, any renewable

    generating unit, such as Utility-Scale PV plant or and CSP plant, shall have the capability to reduce its

    power generation when the grid frequency exceeds pre-set value. Reference value for the active power

    reduction P would be relative bigger percentage of the currently available power generation value at the

    point in time when the grid frequency is equal to 50.2Hz. This active power reference value must be reduced

    according to a coefficient of some output percentage per Hz when the grid frequency deviates from the pre-

    set value. The German Transmission Code requires, for all the renewable-based generating units, to reduce

    the active power with a gradient of 40% of the plants instantaneously available capacity per Hz as shows in

    the below fig.3. Requirements, in terms of power output adjustment and time duration, may be different

    country by country and mainly depends by local network conditions.

    Fig.3Active power reduction of renewable-based generating units in the case of overfrequency

    Furthermore the generating units have to remain connected to the grid (without tripping) if either the gridfrequency increases to values equal to 51.5Hz or decreases to values equal to 47.5Hz; above 51.5Hz and

    below 47.5Hz the plants can be disconnected.

    These requirements can fairly easily be fulfilled by the Utility scale PV system. A new control scheme has to

    be included in each inverter to control the operation point of the PV string and thus the power output. The

    inverter will automatically reduce the power output and stays constant until frequency is decreased below

    the pre-set value and after will increase automatically the power output switching to MPP (maximum power

    point) tracking control.

    CSP plants can easily fulfill such requirements and additionally could provide, since could be considered in

    all respect as conventional generating units, the primary frequency control, provided that the whole plant

    control (steam turbine, steam exchangers and thermal storage) is capable to operate in droop mode and with

  • 8/12/2019 Utility Scale PV and CSP Solar Power Plants

    15/18

    the required ramp rate. This coordinated regulation requires the contemporaneous reaction of steam turbine

    control system (that acts on the inlet steam control valves) and of steam exchangers control system (that acts

    on feed-water flow and hot fluid flow) to meet the fast response and wide variations required by the

    frequency control. CSP plant may also provide ancillary services, such as secondary frequency control and

    minute reserve, by means of appropriate thermal storage system.

    c) Minimum power factor at connection point, reactive power control and set point control for voltage

    stability, also remotely by network operator

    Slow changes in network voltage have to be kept within acceptable limits. In case of operation requirements

    and on demand of the system operator, any renewable generating unit, such as Utility-Scale PV plant or and

    CSP plant, has to support network voltage by injecting on the Grid appropriate amount of reactive power, in

    accordance with Network operator request.

    Utility-scale PV plants nowadays installed are designed to produce active power only. Reactive power is

    avoided due to losses in the inverter, lines and transformers. To meet the requirements of the grid codes, the

    inverters of the Utility-Scale PV plant have to be designed bigger or a centralized static VAR compensation

    system have to be installed. Reactive power has only to be provided during feed-in operation, so there is no

    need to provide reactive power during the night. Overall, an increase of PV installation system costs can be

    expected.

    CSP plants can fulfill the minimum power factor and/or the reactive power control because their generating

    units are constituted by synchronous generators equipped with excitation system capable to provide reactive

    power as required. Therefore the amount of reactive power that can be delivered to the Grid mainly depends

    by size of generator and relevant excitation system as for the conventional generating units.

    In addition, CSP plants may be requested, since could be considered in all respect as conventional

    generating units, to provide different amount of reactive power during different voltage situations. Apart

    from the requirements to provide reactive power supply in the nominal design point of the generating unit

    (P=Pn), there would be also requirements concerning operation at an active power output below the nominal

    active power (P

  • 8/12/2019 Utility Scale PV and CSP Solar Power Plants

    16/18

    all respect as conventional generating units, they should meet requirement set for the conventional

    generating units, while all the other renewable generating units, such as PV system, have to meet specific

    requirements as described below.

    In the event of network, with consequent voltage drop, any PV plant has to remain connected to the grid and

    to inject a certain amount of short-circuit current (agreed case-by case with the network Operator) into the

    network; furthermore it shall feed-in the same active power (and to absorb the same or less reactive power)

    as soon as the fault is cleared.

    The Code specifies the voltage drop that shall be ride through by any PV generating plant (Voltage through

    capability) as shown in the following fig.4. Above borderline 1 the generating units must be remained

    connected ; above borderline 2 and below borderline 1 generating units have to remain connected even if

    not capable to support voltage network. Below the borderline 2, the generating units are allowed to be

    disconnected.

    Fig.4Limiting curves of voltage at the Grid connection point in the event of network fault

    As shown in the next fig. 5, different fault-ride through capability requirementsare specified by different

    Grid Codes within European countries [7]. The fault-ride through capability curves are quite similar, but

    the dynamic requirements are different, mainly with respect to voltage support during the voltage drop.

    .

    Fig.5Comparison of fault-ride through capability required by different Grid Code in the event of network fault

  • 8/12/2019 Utility Scale PV and CSP Solar Power Plants

    17/18

  • 8/12/2019 Utility Scale PV and CSP Solar Power Plants

    18/18

    about 1416 months while to built a 50MWe CSP it would be required 2436 months. PV arrays are fairly

    easy and quick to install while CSP really look like as conventional power plant, mainly for the part relevant

    to the steam process part.

    On the other side, in terms of Grid impact, Utility-Scale PV plants are not naturally suitable to supply

    predictable energy and to provide network ancillary services unless special control features or additional

    equipment (such as inverters frequency and voltage response capability, battery storage system, etc.) are

    designed and installed, with consequent increase in capital cost.

    On the contrary CSP generation is highly predictable and since any CSP plant is intrinsically coupled with

    thermal storage this enables the CSP plant to easily meet, the load demand curve at any time, day and first

    hours of nighttime, and can cover peak hours demand if they are scheduled. Furthermore CSP plants can

    easily participate to primary and secondary grid frequency control so that they are able to support Grid

    exploitation both during steady state and transient condition.

    New grid-codes recently issued in some European countries have to be considered as an important step to

    allow a reliable interaction between renewable generating plants and the electrical network, even if these

    Grid Codes are not yet harmonized at European level. Different approaches are present with respect to

    minimum mandatory requirement and ancillary service, depending on technical needs of the specific

    power system, legal and organizational structure of different Transmission System Operator (TSO), which

    historically established grid management procedures.

    This fact is to day a barrier for the deployment of Utility Scale PV plants, that need, differently from CSP

    plants, special and costly design to comply with different grid needs.As a conclusion of this paper it should be recommended and that all he technical needs are deeply

    investigated inside CENELEC technical committees in order to achieve clearly defined and possibly

    harmonized rules, at least within the whole European market, capable to bring in line the different interests

    of manufacturers, power producers and network operators, minimizing capital costs.

    7 REFERENCES

    [1] EPIA, Annual Report 2009.[2] EPIA, Global Market outlook for Photovoltaic until 2013.

    [3] Global Concentrated Solar Power Markets and Strategies, 20092020; Emerging Energy Research; April

    2009.

    [4] Global Concentrated Solar Power: Markets and Strategies, 20092020; Politecnico di Milano; Ed. 2009.

    [5] Concentrating Solar Power, Global Outlook 09; ESTELA, IEA SolarPACES, Greenpeace International; Ed

    2009.

    [6] Transmission Code 2007Verband Der Netzbereiber VDN e.v. beim VDEW - Network and System Rules of

    the German Transmission System OperatorsAugust 2007[7] Utility Scale PV system: Grid Connection requirements, test procedures and European harmonisation T.

    Degner, G.Arnold, M.Braun, D.Geibel & W.Heckmann, Institut fr Solare Energieversorgungstechnick,

    Kassel, Germany; R.Brndlinger, arsenal research, Electric Energy System, Vienna, Austria


Recommended