FACTORS INFLUENCING INVESTORS’ PARTICIPATION IN PUBLIC ROAD INFRASTRUCTURE PROJECTS IN KENYA THROUGH PUBLIC PRIVATE PARTNERSHIP FRAMEWORK BY ALI SAHAL IDRIS UNITED STATES INTERNATIONAL UNIVERSITY - AFRICA SUMMER 2020
Transcript

FACTORS INFLUENCING INVESTORS’ PARTICIPATION

IN PUBLIC ROAD INFRASTRUCTURE PROJECTS IN

KENYA THROUGH PUBLIC PRIVATE PARTNERSHIP

FRAMEWORK

BY

ALI SAHAL IDRIS

UNITED STATES INTERNATIONAL UNIVERSITY - AFRICA

SUMMER 2020

i

FACTORS INFLUENCING INVESTORS’ PARTICIPATION IN PUBLIC ROAD

INFRASTRUCTURE PROJECTS IN KENYA THROUGH PUBLIC PRIVATE

PARTNERSHIP FRAMEWORK

BY

ALI SAHAL IDRIS

A Project Report Submitted to the Chandaria School of Business in Partial Fulfillment

of the Requirement for the Degree of Master of Business Administration (MBA) -

Global

UNITED STATES INTERNATIONAL UNIVERSITY - AFRICA

SUMMER 2020

ii

DECLARATION

I, the undersigned, declare that this Research Project is my original work and has not been

previously submitted for academic credit to any other college, institution, or university other

than this submission to the United State International University-Africa.

Signed: ________________________ Date: _____________________________

Ali Sahal Idris (Student ID: 660371)

This Research Project has been presented for examination with my approval as the Research

Supervisor.

Signed: ________________________ Date: _____________________________

Timothy Okech, PhD

Signed: ________________________ Date: _____________________________

Dean, Chandaria School of Business

iii

COPYRIGHT

© Copyright by Ali Idris, 2020

All rights reserved. No part of this proposal may be reproduced or transmitted in any form or

by any means, electronic, mechanical, including photocopying, recording or any information

storage without prior written permission from the author.

iv

ABSTRACT

The purpose of this study was to investigate the factors influencing private sector investors’

participation in public road infrastructure projects in Kenya through Public Private Partnership

framework. The study was guided by the following research questions: To what extent does

investor perception affect participation in the public private partnership projects in the roads

sector? To what extent does institutional capacity affect participation in the public private

partnership projects in the roads sector? Lastly, to what extent do procurement processes affect

participation in the public private partnership projects in the roads sector?

The study adopted a survey research design. The population of the study was the 192 road

projects that had been listed under the mandate of the Kenya National Highways Authority

(KeNHA) for the period 2007-2019. Using simple random sampling in determining the

participants in the survey, a sample size of 130 was selected for this study. The data collection

was done using survey questionnaires and the data collected was then analyzed using

descriptive and inferential statistical methods with the output of the analysis being presented

in the form of tables and figures.

Regarding research question one, the results show that a project’s financial feasibility, the

government’s political commitment and government policies, all had positive correlation with

investors’ participation in PPP road projects (Pearson Correlation, r = 0.614). This was

statistically significant at 5% (p =0.000). In terms of the second research question revealed that

the expertise of the investor, the investor’s technological capability and the financial capability

of the investor were significant to investors’ participation in PPP road projects (p = 0.000) at

5% level of statistical significance. Institutional capacity also positively affected investors’

participation in PPP road projects (Pearson Correlation, r = 0. 379), even though the level of

correlation remained low. The findings of the last research question were that the tendering

practices, the bidding and partner selection, and contract negotiation, were found to have a

slight positive influence on investors’ decision to participate in PPP road projects (Pearson

Correlation, r = 0. 496). Nonetheless, these findings remained significant (p= 0.000) at 5%

level of statistical significance.

v

On the basis of findings, it is concluded that private sector investors in the road sector in Kenya

have a weak perception on the viability of the proposed road PPP projects and have a low

confidence in the government’s political commitment towards PPPs. The study also concludes

that the capacity of the private sector players in the road sector in Kenya is still low to handle

large road infrastructure projects and a majority of the private sector players do not have the

internal technical and financial capacity to plan, negotiate, execute and manage such PPP

projects. The study further concludes that majority of investors feel that there is a lack of

transparency in the tendering and bidding processes which are plagued by conflict of interest,

meaning that selection and award of projects is driven by other external issues other than the

results of an open and competitive process. These gaps are therefore obstacles towards

investors’ participation in road PPP projects.

The study recommends concerted efforts at institutional level to enhance a common

understanding of the PPP concept, create sufficient awareness of PPP prospects among the

private actors, streamline the procurement procedures and legal framework surrounding PPP

road projects to boost private sector investors’ confidence. In addition, the study proposes

measures to build the financial capacity of private sector by developing local financial markets

in the country to boost the ability of financial institutions to fund road PPP projects. The study

further recommends the review of procurement practices around road PPP projects to improve

transparency of the bidder selection and proposes identifying an independent criterion to be

used in assessing the value-for-money for PPP projects. The study calls for information

symmetry in the procurement process for all interested stakeholders to reduce the chances of

favoritism and conflict of interest in bidder selection.

vi

ACKNOWLEDGEMENT

I sincerely appreciate and give thanks to my family, friends, faculty, and fellow students who

have supported and encouraged me in this academic journey. I particularly thank my research

supervisor for the tireless guidance and availability throughout this research study. I also thank

the management of the United States International University (USIU-A) for the academic

resources that were availed at my disposal to carry out this research.

vii

TABLE OF CONTENTS

DECLARATION.................................................................................................................... II

COPYRIGHT ........................................................................................................................ III

ABSTRACT ........................................................................................................................... IV

ACKNOWLEDGEMENT .................................................................................................... VI

TABLE OF CONTENTS ................................................................................................... VII

LIST OF TABLES ................................................................................................................ IX

LIST OF FIGURES ............................................................................................................... X

LIST OF ACRONYMS ........................................................................................................ XI

CHAPTER ONE ..................................................................................................................... 1

1.0 INTRODUCTION .................................................................................................... 1

1.1 Background of the Study ........................................................................................ 1

1.2 Statement of the Problem ....................................................................................... 5

1.3 Purpose of the Study ............................................................................................... 6

1.4 Research Questions................................................................................................. 6

1.5 Significance of the Study ........................................................................................ 6

1.6 Scope of the Study .................................................................................................. 7

1.7 Definition of Terms ................................................................................................ 7

1.8 Chapter Summary ................................................................................................... 8

CHAPTER TWO .................................................................................................................. 10

2.0 LITERATURE REVIEW ...................................................................................... 10

2.1 Introduction .......................................................................................................... 10

2.2 Investor Perception and Participation in PPP Projects ......................................... 10

2.3 Investor Capacity and Participation in PPP Projects ............................................ 15

2.4 Procurement Practices and Participation in PPP Projects .................................... 19

2.5 Chapter Summary ................................................................................................. 26

CHAPTER THREE .............................................................................................................. 27

3.0 RESEARCH METHODOLOGY .......................................................................... 27

3.1 Introduction .......................................................................................................... 27

3.2 Research Design ................................................................................................... 27

viii

3.3 Population and Sampling Design ......................................................................... 28

3.4 Data Collection Methods ...................................................................................... 30

3.5 Research Procedures ............................................................................................. 31

3.6 Data Analysis Methods ......................................................................................... 31

3.7 Chapter Summary ................................................................................................. 32

CHAPTER FOUR ................................................................................................................. 33

4.0 RESULTS AND FINDINGS .................................................................................. 33

4.1 Introduction .......................................................................................................... 33

4.2 Study Response and Respondents’ Background Information .............................. 33

4.3 Investor Perception and Participation in PPP Road Projects ................................ 38

4.4 Institutional Capacity and Participation in PPP Road Projects ............................ 44

4.5 Procurement Practices and Participation in PPP Projects .................................... 49

4.6 Investor Appetite for PPP Road Projects .............................................................. 55

4.7 Chapter Summary ................................................................................................. 55

CHAPTER FIVE .................................................................................................................. 57

5.0 DISCUSSION, CONCLUSION, AND RECOMMENDATIONS ...................... 57

5.1 Introduction .......................................................................................................... 57

5.2 Summary ............................................................................................................... 57

5.3 Discussion ............................................................................................................. 58

5.4 Conclusion ............................................................................................................ 64

5.5 Recommendation .................................................................................................. 66

REFERENCES ...................................................................................................................... 69

APPENDICES ....................................................................................................................... 83

Appendix I: Questionnaire ............................................................................................... 84

Appendix II: NACOSTI Research License ..................................................................... 90

Appendix III: USIU Research Letter ............................................................................... 91

Appendix IV: Letter of Introduction ............................................................................... 92

Appendix V: List of Road Projects .................................................................................. 93

ix

LIST OF TABLES

Table 4.1: Descriptive Findings on Investor Perception and Participation in Road PPP Projects

................................................................................................................................................. 40

Table 4.2: Correlation Between Investor Perception and Investor Participation .................... 42

Table 4.3: Regression Model Summary for Investor Perception ............................................ 43

Table 4.4: ANOVA for Investor Perception .......................................................................... 43

Table 4.5: Coefficients for Investor Perception ...................................................................... 44

Table 4.6: Institutional Capacity and Participation in Road PPP Projects ............................. 45

Table 4.7: Correlation Between Institutional Capacity and Investor Participation in Road PPP

Projects .................................................................................................................................... 47

Table 4.8: Regression Model Summary for Institutional Capacity ........................................ 48

Table 4.9: ANOVA for Institutional Capacity ........................................................................ 48

Table 4.10: Coefficients for Institutional Capacity ................................................................. 49

Table 4.11: Descriptive Statistics for Procurement Practices and Participation in Road PPP

Projects .................................................................................................................................... 51

Table 4.12: Correlation Between Procurement Practices and Investor Participation ............. 53

Table 4.13: Regression Model Summary for Procurement Practices ..................................... 53

Table 4.14: ANOVA for Procurement Practices .................................................................... 54

Table 4.15: Coefficients for Procurement Practices ............................................................... 54

Table 4.16: Level of Participation in Road PPP Projects ....................................................... 55

x

LIST OF FIGURES

Figure 4.1: Study Response Rate ............................................................................................ 34

Figure 4.2: Age Distribution of the Respondent Firms........................................................... 35

Figure 4.3: Workforce Size of the Respondent Firms ............................................................ 35

Figure 4.4: Scope of Operations of Respondent Firms ........................................................... 36

Figure 4.5: Respondent Firms’ Project Category ................................................................... 37

Figure 4.6: Figure 4.6: Primary Sources of Funding .............................................................. 37

Figure 4.7: Distribution of Major Lenders .............................................................................. 38

xi

LIST OF ACRONYMS

APIX The National Agency for the Promotion of Investments

CSF Critical Success Factors

DFID Department for International Development

EPC Engineering Procurement and Construction

KENHA Kenya National Highways Authority

KERRA Kenya Rural Roads Authority

KURA Kenya Urban Roads Authority

NPV Net Present Value

OECD Organization for Economic Co-operation and Development

PPIAF The Public Private Infrastructure Advisory Facility

PPP Public Private Partnership

RMLF Roads Maintenance Levy Fund (RMLF)

1

CHAPTER ONE

1.0 INTRODUCTION

1.1 Background of the Study

Public infrastructure is a fundamental prerequisite for economic growth and development and

its provision is a key mandate of governments worldwide (Kamau, 2016). According to

Kaldany, George and Lovasio (2019), the world is facing a $15 trillion infrastructure gap by

2040. As a mitigation strategy, the previous decade has witnessed the growing popularity of

Public Private Partnership (PPP) projects, both in the developed and the developing economies

to bridge this growing infrastructure gap (Xiong, Chen, Wang, and Zhu, 2018).

Public private partnership (PPP) is a formal contractual relationship, which is typically medium

to long term, between the public and the private sectors whereby some of the services that fall

under the responsibility of the public sector are provided by the private sector, with clear

agreement on shared objectives for delivery of public infrastructure or services (World Bank,

2018). Song, Song, and Sun (2013) further define PPP as a procurement model to deliver public

infrastructure and/or service across various sectors such as transportation, water treatment,

energy, environment, health, and education. As such, the benefits of PPPs are all-

encompassing, both for the private sector and the public sector, including the public

consumers. As Nyabira (2019) reinforces, PPP has been hailed as the antidote for the perennial

insufficiency of public funds to finance infrastructure projects. Moreover, PPP has the potential

of providing these gains by creating a convergence for government participation and private

financing initiatives (Yuan, Guang, and Wang, 2012).

PPPs are gradually becoming prominent within the development of road infrastructure projects

as governments the world over become increasingly aware of the association between an

underdeveloped road network with sub-optimal economic performance and quality of life

(World Bank Report, 2017). As a result of this realization, governments are seeking alternative

paths to develop their road networks in the pursuit of meeting their social, political, and

economic needs. Kaldany, George and Lovasio (2019) argue that PPP engineered roads can

significantly reduce delivery time for goods, lower costs for consumers, and speed through the

2

exports that propel growth in an economy. Mbego (2019) also notes that governments are

opting for PPP projects as ideal road sector financing mechanism that could cushion them from

the effects of escalating public debts. Rheki (2017) further observes that some governments

have effected incentives measures to encourage participation of the private sector in PPPs

through tax exemptions and duty waivers on the importation of road construction equipment.

A recent global survey Service Works (2019) revealed insights into the factors driving

successful PPP contracts and the risk factors that can compromise long-term project success.

At a global level, 40% of respondents stated that they spend more than half of their time on

implementation phase. The trend increases significantly to over 60% in the most developed

PPP markets, such as Canada and the United Kingdom. Differences in contract interpretation

were noted by the largest proportion of respondents (58%), followed by poor contract

documentation (43%) and difficulties in achieving the performance level set out in the contract

(43%) as key factors that impeded success of PPP projects.

Akbari and Gholamreza (2019) in their study on the success factors of PPPs in Iran showed

that private sector capability had a direct effect on project success during the construction

period and government capability is very effective during the project operation stage. In China,

Liang and Wang (2019) reveal that the private sector has developed a sense of achieving a

long-term financial return, which might have indeterminate results on the benefits of end users.

The increasing trend of sustainability concerns in the PPP project performance measurement

is confirmed, and it is partially due to the central government’s “High-Quality Development”

initiatives.

Vimlesh and Nandkishor (2018) in their report on PPPs in India noted that when using the

traditional Engineering Procurement and Construction (EPC) method of procurement,

governments usually award contracts to the lowest bidder, which encourages parties to use

cost-cutting measures at the cost of quality-enhancing measures. This practice of awarding the

lowest bidders, makes it less likely for the contract to be awarded to the party that delivers

highest quality products. In addition, state-owned infrastructure utilities have suffered

problems such as low labor productivity, poor service quality, thefts, revenue shortages,

inadequate investments, and deteriorating equipment, which have all resulted in a shift towards

3

the use of PPP model. Kang, Mulaphong, Hwang, and Chang (2019) have indicated that there

are political, economic, legislative, financial, and management factors that have driven the

ongoing adoption and implementation of PPP projects in the context of developing countries.

Sanni (2016) demonstrated that more developmental projects could be delivered through PPP

if the government could focus on these main factors in the implementation process. The study

identified seven critical success factors for PPP as projects feedback, leadership focus, risk

allocation and economic policy, good governance and political support, short construction

period, favorable socio-economic factors, and delivering publicly needed service. Otairua,

Umar, and Zawawi (2014) determined the reasons for the slow adoption of the PPP

procurement strategy in Nigeria through a survey of construction professionals. It was found

that corruption in government was the major problem. Factor analysis further revealed five

factors namely government policy on infrastructure, lack of consensus among policy makers,

political instability, lack of understanding of the PPP concept, and high participation costs.

A study of PPPs in Ethiopia showed that the five important attractive factors for pursuing PPP

in the Ethiopian road sector were: ‘solve the problem of public sector budget restraint’,

‘facilitate creative and innovative approaches’, ‘save time in delivering the project’, ‘improve

maintainability’ and ‘enhance government integrated solution capacity’ (Debela, 2019). In

Sudan, Khair, Mohamed and Mohammad, (2018) conducted a management framework to

reduce delays in road construction projects. The finance competence factors group was found

to be the main contributor towards delays in road construction projects in Sudan. Some

effective ways were proposed to overcome delays due to financing via use of strategic public

and private partnerships for large-scale projects, introduction of bank financing schemes for

medium-scale projects, and community-based partnership for small-scale projects.

Salih and Mohamed (2015) illustrated that there were three significant factors that had the most

impact for implementing PPP projects in Sudan. These were establishing new opportunities

for private sector, the qualification of contractor and consultant, and PPP supporting in

accelerating projects development. In Uganda, Alinaitwe and Ayesiga (2018) analyzed the

factors that affected the success of PPP projects. A competitive procurement process, a well-

4

organized private sector, the availability of competent personnel to participate in PPP project

implementation, and good governance are the most important cross-cutting factors identified.

In the recent years, the government in Kenya has made PPPs a key element of its development

strategy as reiterated in the government’s push for a deeper private sector participation in

public investment programmes (DFID, 2015). Carter and Claros (2016) in their report on

benchmarking PPP procurements show that Kenya has put in place comprehensive policy

framework and legal mechanisms on PPPs as evidenced in the Vision 2030, the country’s

development blueprint. The Vision 2030 which is focused on Kenya becoming a middle-

income economy by 2030 has set out a 10% per annum GDP growth target, and to realize these

high growth rates the Government has emphasized the importance of enabling private sector

participation in infrastructure in Vision 2030. To demonstrate the commitment to PPPs, the

Government of Kenya enacted the PPP Act in 2013 which together with the PPP Regulations

provide a robust PPP framework that is largely supportive of the PPP projects and provide

clarity on the PPP procurement process (Olotch, 2017). A DFID report of 2015 shows that

there has been a steady growth in the quality and size of the pipeline of PPP projects in Kenya.

As at 2015, there were a total of 70 projects in the National Priority List of PPPs planned for

the period 2018-2020, out of which, USD 4.202 billion was for the road sector.

Additionally, Kenya has emerged in the top 10 in Sub-Sahara Africa according to a World

Bank Group report of 2017 that evaluated 82 countries globally looking at their capacity to

prepare, procure and manage PPP projects. Adetona (2018) reports that the Kenyan

government took a big step in improving its business environment with the launch of the

Public-Private Partnership (PPP) Disclosure Portal in 2018. The PPP disclosure portal is an

online tool that makes all non-confidential information relating to PPP contracts available to

the public and is aimed at improving transparency and accountability in PPPs (Mwangasha,

2018).

Regardless of the foregoing, a report by Flynn and Rao (2019) shows that African countries

are finding it difficult to lure private sector into infrastructure-based PPP projects. The report

indicates that only 4% of the projects have been successfully accomplished through joint

5

ownership of governments and the private sector with most funding coming from development

finance institutions.

1.2 Statement of the Problem

According to the government of Kenya 2018-2019 budget policy statement, the country had

an allocation of KES. 115.9 billion in the budget to fund ongoing road construction projects

while at the same time planning for alternative funding through Public Private Partnership

arrangements to attain the country’s Vision 2030 development plan (The National Treasury,

2018). To attain this goal, the Kenyan government has been actively engaged in seeking private

investors for mega road projects around the country as evidenced by the list of 80 projects in

the national priority list of PPP projects (The National Treasury, 2018). Despite a push by the

government for the private sector to be actively involved in cash-intensive road infrastructure

projects, the pace of uptake by the private sector is still sluggish seeing that to date only one

road project is listed among the PPP projects that have attained project financial close

according to the data on the Kenya PPP Unit website (PPP Unit, 2018). Following the adoption

of PPP by the government, Anyanzwa and Muchira (2018) noted that only twenty-six (26%)

of the projects have been completed under the public private partnership framework.

Public sector bureaucracies have been blamed for the slow implementation of infrastructure

projects in the country even as it emerges that intricate procedure for the government to

approve projects is among the reasons many private investors stay away from State projects

(Anyanzwa and Muchira, 2018). In Thuo (2018), public and private partners’ capacity

deficiencies have been identified as a barrier to PPPs actualization in Kenya. Chami (2015)

points out a positive correlation between funding PPP road projects and budget deficits,

procurement procedure, project financial feasibility and project schedules. Kamau (2016) notes

that there is evidence to show most of the financing of such infrastructure in Kenya has been

through the Exchequer, Roads Maintenance Levy Fund (RMLF) and through multilateral

financial institutions such as the World Bank and Africa Development Bank. This is sufficient

evidence that the participation of private investors in road development remains insignificantly

low.

6

There is increasing disquiet about the slow progress of delivering PPP road projects and despite

the policy measures and the push by government for the private sector to be actively involved

in public infrastructure projects in Kenya, there is very little to show as far as actual rolled out

PPP projects are concerned based on road PPP projects at financial close stage (PPP Unit,

2018). Kisero (2018) in an article in the Business Daily newspaper titled “Why PPP model has

not succeeded here” states that more than six years since Kenya introduced a PPP law complete

with a bureaucracy to spearhead and roll out projects, not a single project has reached financial

close. It is against this background therefore that the current study aims to establish the factors

that affect private investors’ participation in public road PPP projects in Kenya.

1.3 Purpose of the Study

The purpose of this study is to investigate the factors influencing private sector investors’

participation in public road infrastructure projects in Kenya through Public Private Partnership

framework.

1.4 Research Questions

1.4.1 To what extent does investor perception of public projects affect participation in the

public private partnership projects in the roads sector?

1.4.2 To what extent does institutional capacity affect participation in the public private

partnership projects in the roads sector?

1.4.3 To what extent do procurement processes affect participation in the public private

partnership projects in the roads sector?

1.5 Significance of the Study

1.5.1 Potential Investors in PPP Projects

This study investigates the barriers that were encountered by investors who have attempted to

invest in road infrastructure projects in Kenya through the PPP model. As such, other similar

local and international investors, with interests in this sector, would utilize the findings of this

study to gain insights on how they can overcome these challenges during their investment

7

planning and execution. This study would also be beneficial to banks, financial institutions,

multi-lateral agencies, and other financiers involved in lending to private sector investors with

investment interests in the roads sector in Kenya. The study would help in their risk allocation

process and the resultant financial structuring of investment transactions involving road PPP

projects in Kenya.

1.5.2 Policy Makers

The findings of the study would be particularly valuable to the relevant government of Kenya

agencies in the roads sector including the National Treasury, Kenya National Highways

Authority (KeNHA), Kenya Rural Roads Authority (KeRRA), and Kenya Urban Roads

Authority (KURA) in formulating policies and putting in place mechanisms that would foster

the success of PPPs in the roads sector.

1.5.3 Researchers and academicians

Future researchers and academicians could utilize the findings of this study as a basis for their

further studies around PPPs in Kenya in general and road infrastructure projects in particular.

The study would also be helpful in identifying areas for further research for scholars and

contribute to the general body of knowledge on PPPs in Kenya.

1.6 Scope of the Study

This study focuses on the private sector investors, both local and international, who are

undertaking or who have undertaken the 192 road projects under the mandate of the Kenya

National Highways Authority (KeNHA) for the period 2007-2019, and seeks to identify the

challenges they faced in taking up these projects. The study respondents will be those with

offices located in Kenya and the study will be conducted between January and March 2020.

1.7 Definition of Terms

1.7.1 Public Private Partnership

PPPs, which are locally defined under the Public Private Partnership Act 2013 (PPP Act), are

arrangements between a contracting authority and a private party under which the private entity

8

undertakes to perform a public function or provide a service on behalf of the contracting

authority and is generally liable for risks arising from the performances of the function in

accordance with the terms of the project.

1.7.2 Road Projects

Infrastructural Road projects refers to the construction and development of road infrastructure;

rural, urban, and highway through private sector and government arrangement (Srivastava,

2014).

1.7.3 Investor Perception

An independent evaluation and insight into the benefits and risks associated with undertaking

Public Private Partnership Road projects. In this case, the investor considers the value attached

to PPP road projects (Bhargavi, 2014).

1.7.4 Institutional Capacity

Road sector related Institutional Capacity refers to investment in people, institutions and

practices that will enable the firms and agencies involved in the construction and development

of roads, achieve their objectives with high efficiency (Langaas, Odeck and Bjørvig, 2015).

1.7.5 Procurement Processes

A series of procedures and steps adhered to by the investors in the road development. It also

entails the acquisition of necessary materials, approvals, until the commissioning of the project

and effecting of payments (Bode and Padhi, 2016).

1.8 Chapter Summary

This chapter contains the background information on public private partnership (PPP) projects

in general, with emphasis on the roads sector. The chapter started by highlighting the trend of

PPP investments globally and regionally as an alternative to the use of scarce public resources

in creating win-win opportunities for both the public sector and the private sector investors.

The chapter also noted the desire of the government of Kenya to encourage the funding of road

9

infrastructure projects by the private sector through PPPs and the significance of investments

in road infrastructure for general economic growth. The chapter further brings into focus the

problem statement which shows that despite government efforts in Kenya to initiate PPPs and

the global trend in PPP investments, there has been little success of PPP initiatives in the road

sector in Kenya so far. It then notes the purpose of this study which is to investigate the factors

influencing private sector investors’ participation in public road infrastructure projects in

Kenya through Public Private Partnership framework, the significance of this study, the scope

of study and concludes with the definition of key terms used in the background of the study.

The next chapter presents a compressive review of literature on factors influencing low

participation of investors in PPP projects. The third chapter provides the research methodology

followed by results and findings in chapter four and finally, discussion, conclusion, and

recommendations in chapter five.

10

CHAPTER TWO

2.0 LITERATURE REVIEW

2.1 Introduction

The chapter presents the literature regarding the factors influencing investors’ participation in

the public private partnership projects. The literature is organized into three sections as

follows; the first section presents literature related to the effect of Investor Perception on the

participation level in the public private partnership projects. The second section divulges into

literature concerning the effect of institutional capacity on investors’ participation in the public

private partnership projects. The last section focuses on the effect of procurement practices on

investors’ participation in the in the public private partnership projects. The chapter closes with

a summary presenting a brief overview of the discussion.

2.2 Investor Perception and Participation in PPP Projects

The section discuses literature about investor perception and their participation in the public

private partnership projects. In the same vein, investor’s perception is assessed using three

factors: project financial feasibility, political commitment, and government policy towards the

intended project.

2.2.1 Project Financial Feasibility

According to Sarvari, Valipour, and Yahya (2019), financial and risk assessments of proposed

projects have become necessary for countries considering PPPs for infrastructure projects.

These assessments are essential to attracting private investors. Iqbal, Choudhry and

Holschemacher (2015) state that the principle behind risk management is to minimize

unfortunate effects by identifying and controlling threats and maximize). Nguyen, Mollik, and

Chih, (2018) identified critical risks in PPP toll road projects in Vietnam that affected the

projects’ financial viability. The study revealed risks either critically affecting toll road

projects’ financial viability in Vietnam, by inflating projects’ cash outflows or reducing

projects’ cash inflows in a commonly used net present value (NPV) analysis model. Eadie,

Tonar, and Millar (2013) argue that confidence in the PFI/PPP route had fallen due to the

11

recession and from the figures in the 2003 and 2008 reports indicated a negative trend in

perceptions of the route’s benefits.

Burger and Hawkesworth (2016) discuss how value for money is important both to the

government and the private investor. They argue that the choice between using a PPP or

traditional procurement should be simple: governments should prefer the method that creates

the most value for money. However, in practice the value-for-money objective is very often

blurred, and the choice between using a PPP and traditional infrastructure procurement may

be skewed by factors other than value for money. Research by Aslan and Duarte (2014) finds

that select countries that have taken the lead in PPP projects have also focused on sound

budgeting and accounting practices incorporating fiscal risks of all projects in the medium-

term and annual budgets. Credit enhancement through guarantees by Multilateral Development

Banks (MDBs) provide further assurance to private investors and cover any possibility of non-

fulfilment of sovereign guarantees, especially in emerging economies (Jet, 2018).

Budina, Polackova, and Irwin (2007) in their study concluded that economic stability,

institutional strengths, and soundness of legal and regulatory framework are crucial to the

success of PPP projects. On weighing on the benefits of PPP in road infrastructure. Flor (2018)

findings in construction risk in infrastructure project finance from EDHEC show that for a

large number of transport infrastructure PPP projects, (including roads), construction overruns

are significantly lower at 3.3 percent on average compared to public procurement projects,

with a 26.7 percent overrun average. There is no unlimited risk bearing– private firms (and

their lenders) will be cautious about accepting major risks beyond their control, such as

exchange rate risks/risk of existing assets. If they bear these risks, then their price for the

service will reflect this. Private firms will also want to know that the rules of the game are to

be respected by government as regards undertakings to increase tariffs/fair regulation, etc.

Private sector will also expect a significant level of control over operations if it is to accept

significant risks.

12

2.2.2 Political Commitment

Government support for PPP focuses on the extent to which national governments provide an

institutional framework that is either conducive or preventive for the introduction and diffusion

of PPPs within infrastructure (Koen, Ole Helby, and Murwantara, 2014). A report conducted

by Ruiz-Nunez, Fernanda, and Clive Harris (2016) reveal that payment guarantees comprise

91% of all indirect support provided by governments with revenue guarantees comprising only

7% of total indirect support. In India too, payment guarantees outweigh all other kinds of

guarantees. As noted above, a robust guarantee management system begins with designing

different types of guarantees. Through a number of case studies relating to government

finances of Indian states and other countries, Bhatia (2019) reveal that governments which

have checks and balances to issuance of guarantees and other forms of indirect support for PPP

projects are actually able to attract higher levels of PPP investment.

Osei-Kyei and Chan (2017) indicated that the three most critical factors in the success of PPPs

are the political support and acceptability for PPPs, government’s positive attitude towards

private sector investments and political stability. Węgrzyn (2016) reveals that public and

private parties do not share common perception of the PPP success. In general, the private

sector assigns lower values to the CSFs analyzed from the whole life perspective of a PPP

project. While seeking to respond to the question: Why is Senegal’s Dakar-Diamniadio toll

road, which opened on time and on budget in August 2013, so successful? Cartern (2015)

identifies political commitment as the key success driver. It was established that The

Government of Senegal set the project as a priority. The first driver on the road was the

President who paid the toll. However, the author cautions that political commitment alone is

not sufficient, it needs it needs to be turned into action by government agencies. Hence, the

Government of Senegal setup intra-agency coordinating committee. Furthermore, The

National Agency for the Promotion of Investments (APIX) oversaw the preparation of the

concession. The Public Private Infrastructure Advisory Facility (PPIAF) supported APIX with

technical assistance, including the design of a framework for the oversight of the project. Kwak

et al. (2009) argue that inadequate involvement and incapability of governments to manage

PPP projects lead to project failures in developing countries. Gibson and Davies, (2008) that

identified local political opposition as a barrier to PPPs in mature economies.

13

2.2.3 Government Policy

A clear legal and regulatory framework is crucial to achieving a sustainable infrastructural

solution through PPP (World Bank, 2016). It is mandatory for any serious government to first

articulate its PPP policy before embarking on establishing a PPP framework (Cui, Hope, and

Liu, 2018). Thiago and Thiago (2019) recall that the creation of the public-private partnership

(PPP) model in Brazil dates to 2003, with the publication of the PPP Law for the State of Minas

Gerais (State Law No. 14,868/2003). Subsequently, in 2004, the PPP Law for the State of São

Paulo (State Law No. 11,688) and Federal Law No. 11,079 (the Federal PPP Law) were also

published reinforcing this type of partnership. The PPP legislation was born of the need to

attract private investment in infrastructure projects in Brazil in the following areas: water and

sewage, health and hospitals, administrative facilities and logistics, including roads, urban

mobility, underground transportation and transportation in general.

Dey, Rahman and Dey (2016) sought to find out the implementation of the Public Private

Partnership (PPP) projects in Bangladesh. One of the key findings of this study was that lack

of institutional and legal framework for PPP in Bangladesh, which hindered the successful

implementation of such projects in the country. Kang, Mulaphong, Hwang, and Chang (2019)

explored the factors that affect the adoption and implementation of projects in the context of

developing countries. The results indicated five broad categories of political, economic,

legislative, financial, and management requisites.

Osei-Kyei and Chan (2017) explored the critical risk factors of PPP projects in Ghana, and

their findings indicated that, generally, country-risk factors are more critical in Ghana than

project-specific risks. Essentially, country-risk factors are risks, which relate to the political,

legal, and economic conditions of PPP (Ameyaw, 2015). The key critical country-risk factors,

which need attention in Ghana, include corruption, political/public opposition, exchange, and

interest rate fluctuations, poor public decision-making, political interference, and project

approvals and permit delays. On the other hand, some project-specific risks which are critical

and also need consideration include construction cost overruns, delay in project completion,

change in market demand, delay in land acquisition, high financing cost, construction changes,

poor quality of workman-ship, tariff change, environmental risk, and in experienced private

partner. For the case of Ethiopia, Debela (2019) revealed that for effective implementation of

14

PPP road projects, the government should ensure at least the presence of an enabling specific

PPP policy, well-organized and committed public agency, stable political and social

environment, favorable legal frameworks and good governance.

On 1st July 2015, the parliament of the Republic of Uganda passed the highly anticipated Public

Private Partnerships Bill; it was later assented to by the President of Uganda on 12th August

2015 (Ndandiko and Ibanda, 2016). The new law filled the gaping void for a legal framework

to regulate the development and implementation of PPPs in the country. Before the passing of

the new PPP's law, Uganda lacked a formative regulatory framework tailored to Public Private

Partnerships arrangements. Stakeholders would refer to the 2010 National PPP Framework

policy in conducting their operations. The PPP Unit's focus is to serve as the secretariat and

technical arm of the PPP Committee, which is mandated with assessing and approving PPP

projects in the country.

Li, Akintoye, Edwards, and Hardcastle (2005) established that identified lack of well-

established legal framework as one of barriers to PPPs project implementation. This indicates

that some governments in developing countries undertake PPPs without overall PPP policies,

which leads to ill-defined goals and a greater likelihood of problems with the projects

implementation. Bosire (2015) finds that all the counties in Kenya have PPP units which are

in line with the national governments initiative to encourage PPP funding for projects for

improving infrastructure levels across the counties. It also established that 70.73% of the

counties have in place PPP implementation guidelines which are instrumental in guiding the

process.

In Kenya, Muasya (2014) indicated that the ministry was very keen on quality services being

provided in set timeframes and within the set cost implications. The ministry is therefore

involved in PPP projects to help in the funding of required and necessary projects towards the

achievement of the vision 2030. The findings showed that the ministry had a team that forms

the committee responsible for these implementations. The results revealed that the ministry

had set procedures that had been laid down for implementation of PPP projects with the

ministry being responsible for the formulation and implementation. The results of the study

also found challenges such as; improper vetting procedures, political interests and interference,

15

political and socio-economic environment factors and internal vested interests are some of the

challenges encountered by the ministry in the implementation process a fact that fitted the

contextual argument.

2.3 Investor Capacity and Participation in PPP Projects

The public officials involved in PPP project teams need to have competencies to structure and

evaluate the project considering its financial, legal, and technical aspects. The areas of

expertise that they need to have in the five broad areas of project planning, financial, legal, and

technical and project management. However, the present study is limited to investor’s

expertise, investor’s technology capability, and the investor’s financial capability.

2.3.1 Investor Expertise

In the early stages of the process, the public sector should assess its institutional capacity to

act as a partner. Creating an entity to handle the partnerships, such as a redevelopment authority

or a quasigovernmental agency, may be necessary if such an agency does not exist. The public

partner needs to make sure it has the expertise to negotiate with the sophisticated private party

and the authority to retain the use of one or more consultants to assist in developing the

partnership. Jooste (2009) identifies organizations that enable PPP projects by supplementing

the necessary competencies. These organizations include private consultants, technical

specialists, non-governmental organizations, academic institutions, probity auditors, fairness

advisors, transaction advisors, PPP units, advocacy associations, and local, regional, and

multinational development agencies.

Devkar, Mahalingam and Kalidindi (2013) assessed the kinds of competencies that are

prevalent within ULBs in India, competencies that are often absent, strategies that are currently

used to bridge these competency gaps, and approaches that ULBs should follow in order to

create a more robust environment for PPPs. The case study analysis indicates that project

development competencies were supplemented through the engagement of PPP coordination

agencies. However, there were larger competency gaps around project governance.

Kamau (2016) indicate that most banks have limited participation in the road PPP projects in

Kenya. Out of the 71 PPP pipelines that were underway, none of the commercial banks

16

indicated as having participated in any activity. Knowledge about the PPP and opportunities

provided for the banking industry seems to be low. Those respondents with knowledge of the

annuity programme argued that the financing model was too complicated that it could lead to

increased non-performing loans. Okwaro, Chepkwony, and Boit (2017) found that the County

government of Uasin Gishu had not formulated policies and procedure on the implementation

of PPP procurement, thus has affected the adoption of PPP procurement; majority of the

investors have no confidence in the county procurement process which may have hindered

their interest in the adoption of PPP procurement; lack of confidence among the county

employees in PPP procurement decision making may have affected adoption of PPP

procurement negatively in the county.

2.3.2 Investor Technological Capability

Technological capability is a term that encompasses the system of activities, physical systems,

skills and knowledge bases, managerial systems of education and reward, and values that create

a special advantage for an organization or line of business (Nurazwa and Halim, 2019).

Technology is vital for road and infrastructure industry. As a result, technological innovation

is a key asset for strengthening competitiveness of a firm in construction industry. Quintana

(2017) posits that leveraging technology and innovation is essential to build capacity,

streamline programs, and further impact in successful public private partnerships (PPPs).

Technology can be leveraged in two ways: first using technical tools and platforms and second

using technical knowledge to ensure expertise and innovative practices are applied uniformly

and consistently to community investment strategies. Reichert and Zawislak (2014) seem to

hold a divergent perspective when they establish that technology alone cannot be used to assess

the competitiveness and positive performance of the firms. Based on 133 Brazilian firms, they

insist that there are other factors that impact firm competitiveness other than technology.

Kovalenko and Akhmetshin (2019) reports that experts and scientists agree that the use of

innovative materials becomes economically viable at the stage of construction and subsequent

operation of the road surface. It is new technologies that are designed to improve road safety

in our country of costly repairs. Since 2007 the use of macadam-mastic asphalt has begun to

cover roads, which has gained high popularity as a wear-resistant pavement material on roads

17

with a high degree of congestion, providing steady and increased flatness, roughness, cracking

resistance and adhesion during operation, reduces noise level from moving vehicles.

In the previous decade, many technological innovations have dominated the operations of road

construction industry (Lyovin, 2012). Since 2012, polymer-bitumen binder 60 has been used

as a binder in the composition of macadam-mastic asphalt concrete at the construction and

reconstruction of roads, which improves the performance properties of asphalt concrete and

extends the service life of the coating. Since 2014, the NOVACHIP technology has been

successfully applied, consisting in the installation of thin-layer coatings (wear layer) of a hot

bitumen-mineral mixture using a special paver for pre-applied bitumen-latex cationic

emulsion. This technology allows increasing the turnaround time of repair of the road and

improving the quality of the coating (evenness, noise absorption, coupling qualities).

Yates (2016) elucidates that the use of computerized expert system for construction

applications is on a growing spree. The existing examples include systems of to diagnose

vibration problems in rotating machinery and system to verify weld performance

qualifications. It is also predicted that the use of expert systems will probably be the most

important application of artificial intelligence techniques for construction over the next decade.

Vutsova (2014) argues that the role of technology in the public private partnership is to

eliminate the risks and weaknesses inherent in these projects. The problems involve: poor

infrastructure environment, lack of standards and quality processes, frequent cases of

reluctance to change and introduction of innovative solutions, and finally - a long and

cumbersome development.

2.3.3 Investor Financial Capability

Financial capability entails the inventors’ knowledge and skills to understand their own

financial strengths, projects needs along with utilizing the funds on available PPP projects

(Serido, Shim, and Tang, 2013). Bain (2009) and Regan, Smith, and Love (2011) opine that

international capital markets have experienced high levels of instability and adversely affected

the funding arrangements for social and economic infrastructure projects since 2008, leading

to limited availability of equity and debt capital and a higher cost of capital. Besides, the

market access has been difficult for both the public sector and the private sector, leading to

18

banks becoming the main source of funds for PPP projects (Bain, 2009). A study by KPMG

(2009) indicates that banks are unwilling to commit to lending terms for anything other than a

short period in some countries.

Experience and financial and technical capacity of the bidders should be included in pre-

qualification or qualification criteria when they exist and not be part of the bid evaluation

process. Criteria which are difficult to measure and allow for discretion, like quality of service

or safety, should be avoided. Rather, metrics and data collection requirements should be

specified in advance. Criteria or targets should be, whenever possible, pre-specified. If quality

targets differ across bids, such elements are difficult to evaluate and translate into cost

differences. Therefore, minimum quality requirements can be pre-specified as having to be met

by all the bidders, subject to ex-post verification.

In China, Zhu, and Chua (2018) reveal that political environment, economic environment,

shareholders’ credibility, financial market, legal system, public sector’s reliability, financial

structure, and regulatory framework were ranked as the top eight critical bankability criteria.

Despite all these lending preconditions, China had initiated 13,554 PPP projects costing 2,612

billion dollars until the end of June 2017 (Du, Wu, and Zhu, 2018). Sanni (2016) shows that

the five most important factors for PPP project success are economic viability of the project,

sound financial package, commitment and responsibility of public and private sectors,

thorough and realistic cost and benefit assessment, and good governance. Ye, Chong, and Shi

(2018) found that companies with more project experience, more political connections, and

higher profitability are more likely to be willing to participate in PPP projects.

Ojebode (2016) provides further evidence on constraints that are hindering the effectiveness

of PPP on affordable housing delivery in Nigeria. The study identifies, lack of regulation

guarantee, poor financial projections, poor feasibility assessments, poor communication,

inadequate financial resources, project cancellation and contract renegotiation etc. PPP needs

to develop a clear statement of objectives for affordable housing delivery, well-communicated

strategy, a clear institutional framework, independent oversight, sustainable financing

mechanisms and allow flexibility for implementation to mitigate these constraints. In addition

to providing the basis for more effective housing policy, the research develops a PPP model

19

for affordable housing delivery. In the Ghanaian context, Osei-Kyei, Chan, and Ayirebi (2017)

assert that the key issues that practitioners need to look at carefully in order to succeed include

transparency and competition, favorable legal framework, right project identification, capacity

building, extensive stakeholder engagement and appropriate risk allocation.

2.4 Procurement Practices and Participation in PPP Projects

Procurement means selection of the (highest ranked) bidder under a transparent, fair, and

accountable procurement system (United Nations Commission on International Trade Law,

2016) and signing a contract agreement with this partner. There are many factors that must be

considered when determining the best procurement approach for a given project, including

long-term costs, myriad uncertainties, risks both now and in the future, and complicated

funding and financing approaches (FHWA, 2012). In the current study, procurement is

assessed in the context of tendering practices employed in the PPP, the process of project

bidding and partner selection, and the effectiveness of contract negotiation during the

formulation of PPP agreements.

2.4.1 Tendering Practices

Tendering process takes various forms. The most common procedure is the open competitive

tendering, which involves the phases of a request for prequalification, prequalification,

invitation to tenders, tender evaluation and shortlisting, negotiation with shortlisted

tenders/bidders and selection of best bidding and award (Palcic, Palcic, and Reeves, 2019).

Even though calling for bidders to be prequalified and calling for tenders of qualified bidders

were simple tasks, Tiong and Alum (2017) have emphasized that there are three main phases

that can be distinguished in the tendering procedure of PPP, which are prequalification of

tenders, evaluation tenders, negotiation with preferred bidders, before PPP awarding.

Palcic, Palcic, and Reeves (2019) state that PPPs are often characterized by lengthy tendering

periods that have the potential to deter bidders for contracts and increase transaction costs.

They analyzed data on 877 PPP projects in seven countries and find considerable cross-country

variation in tendering periods in the United States. Using a duration analysis model, they found

that this variation persists even when we control for observable factors such as capital value.

The longest tendering periods were found in the housing, health and defense sectors and

20

tendering periods are positively related to project size. Indicators of institutional quality are

not found to be significant. However, these finds are contradicted by previous observation by

Khaderi (2019) who observes that most of the characteristics of the tender process will be the

same as in any public procurement process, but some stages and steps have specific aspects

and features. Hence, there are special considerations inherent to the complexities of PPPs.

However, all admit that a balance is needed so as not to endanger the legality of the process

and potentially suffer a challenge that may paralyze the process or require the government to

re-issue the tender.

Doni (2007) looked at three kinds of tendering procedures, which are the negotiation, the

auction, and the competitive negotiation procedure to provide contracting authorities with

guidelines to follow for designing PPP/PFI tenders. In the absence of consent between one

bidder and the public sector, the competitive negotiation will give a higher expected value to

the government compared to other methods. In Malaysia, Takim, Kharizamand and Rahman

(2009) and Shamsida and Ani Saifuza (2010) stated that the organizational structure of a

typical PPP in did not differ much from international best practice. The composition comprises

the government, the Special Purpose Vehicle (SPV), lenders, private investors, works

contractors, and facilities maintenance contractors. They further argued that the roles of the

parties in Malaysian PPP/PFI resembled their partners around the world.

2.4.2 Bidding and Partner Selection

This phase includes opening technical and financial bids and evaluating those bids in addition

to completing the financial model’s comparative (Fischer, 2012). The PPPCU then reviews the

Line Ministry’s financial model and compares it to the financial models of the bidders which

lead to the selection of the winning bidder (Norton Rose Fulbright, 2011). The bidding

processes differ depending on the nature and complexity of the project. There are two main

types of the PPP projects: concession projects and maintenance agreements, they define the

tender process since the first type requires large investments, complex or long activities

delegated to the private sector when maintenance contracts are not so complex and can be

signed on the basis of procurement rules for civil works.

21

For successful bidding, it is important to ensure competition and transparency. It will result in

choice of the partner that is able to deliver expected results at reasonable costs. If there is no

transparency, then the government might face such issues as protest that negatively affects the

project (Moszoro and Spiller, 2012). It is crucial to attract the best potential bidders who should

see benefits and feel rewarded for possible risks and protected by the existing regulations. In

addition, the country environment, and the commitment of government to accomplish the

project play a significant role in this case. Moreover, fair competition between bidders should

be supported by the means of providing information on the project and an evaluation procedure

which should not be biased. Furthermore, the rules of the game should be clear to the bidders

so that they understand the procurement process (PPIAF, 2009).

Casady, Flannery, and Geddes (2019) argues that PPP tendering periods in Canada are notably

shorter than in similar countries that have mature PPP markets, such as United Kingdom and

Ireland as observed from data on 160 PPP projects. From the analysis of the data on the PPP

tendering process duration, Casady et al. found that higher PPP contract values and greater risk

transfer were associated with longer tendering periods and that there were significant variations

in tendering periods across sectors. Other important success factors for PPPs identified from

the Canadian study include securing necessary approvals before commencing procurement,

creating specialized PPP procurement agencies, contract standardization, lower information

and design requirements, avoidance of additional bid stages, and the use of substantial

completion payments.

According to Marques (2010), one of the major advantages of PPPs is that in most situations

the government uses market prices (through bidding) to choose the private partner. These

savings provide the “value for money” for the project and are frequently the justification for

the PPP option. However, experience shows that failures of PPP contracts are often related to

the procurement procedure. In addition to transparency and fairness, which are essential in any

bidding process, thinking about appropriate procedures can reduce the likelihood of problems

arising in the future.

Marques (2010) adds that in a PPP, when selecting a private partner, a public tender is normally

compulsory, and the rule is to choose the most economically advantageous bid. When only one

22

criterion exists, usually the price (e.g. average tariff), the royalty paid, the level of subsidy, the

net present value (NPV), or the contract term, the winning bidder corresponds

straightforwardly to the bid which presents the lowest price, minimum subsidy, highest value

of royalty or net present value (NPV). However, when there are several criteria, the situation

is more complicated, and it is necessary to adopt a multi-criteria decision analysis to choose

the winner. In this case, the awarding authority should define the criteria (and eventually sub-

criteria) and the bid evaluation methodology before the tender call notice.

Zawawi (2017) conducted a case study on the Malaysian Public Private Partnership Unit, Unit

Kerjasama Awam Swasta (UKAS), to investigate the manner of competition incorporated

within PPP in Malaysia. Based on the empirical findings, in its effort to make the country’s

PPP programme a success, UKAS has been flexible in its implementation, with less emphasis

on incorporating competition within the procurement process. UKAS, however, still manages

to procure infrastructure using PPP for the reasons for adopting PPP. This result in

inconsistencies in UKAS governance on procurement process. Where the findings illustrate

that value for money can be achieved by other means, the researcher concludes that

competition involves more than achieving value for money; it can also be used as a procedural

barrier, hence achieving good governance.

Fischer (2012) elaborates the value of pre-qualification. He argues that pre-qualification is

needed to weed out firms that do not have the financial nor technical resources to carry out the

project. Responding to their questions distracts scarce qualified resources within government.

If they win the project, it will be delayed for years, before they can be taken away from the

project. Surety bonds can be used at different stages of the process, and they can exclude these

serious firms, as they will not obtain bank backing.

Jeppsen (2013) investigate how the public and private participants in the Danish PPP sector

perceive the relation between the choice of procurement procedure and PPPs and to what extent

the procurement procedure can be used as a an instrument that contributes to PPPs with higher

total welfare gains and lower total social costs. The analysis shows that central PPP aspects as

risk allocation and standardization are perceived differently from the perspective of the public

and the private sector. This difference might be explained by the different implied interest of

23

the actors. However, this could also indicate a conflict within the Danish PPP sector which is

interesting to investigate. In relation to procurement and PPP the findings indicate that the use

of competitive dialogue results in better final PPP offers compared to restricted procedure.

Olotch (2017) asserts that Kenya’s PPP framework is silent on the steps to be taken where a

procuring entity receives only one bid in response to a PPP tender. Would the bid be considered

non-responsive, thereby necessitating a fresh tender process? Should the procuring entity

proceed to carry out due diligence on the bidder, and award the tender if the bid meets the

tender requirements? How would the procuring entity ensure there is value for money?

Whichever the approach, the report aptly states: receiving a single bid may be problematic and

thus merits attention through the PPP regulatory framework.

2.4.3 Contract Negotiation

Managing PPP contracts differs from managing traditional government contracts. PPPs are

long term and complex, and contracts are necessarily incomplete that is, the requirements and

rules in all scenarios cannot be specified in the contract. Therefore, the management of PPP

contracts must be flexible in both available resources and skills to meet the whole-life

expectations of the contract. The aims of contract management for PPPs are to ensure dialogue

between the private and the public actors ensures that the project proposals are aligned with

expectation of the contracting authority (Berrone, Fageda, and Lluma, 2018).

Moving beyond the legal aspects of the contract, the process of negotiation also calls for

investigation. In PPPs, the private partner is often involved earlier in the decision-making

process, compared to traditional procurement (Klijn, 2010) and the contract is often more

extensive. The bundling of tasks entails that the contract often is negotiated with a consortium

or Special Purpose Vehicle (SPV), consisting of a number of private actors, which, by joining

expertise, can solve all the different tasks, integrated in the PPP (de Bettignies and Ross, 2010).

The drafting and negotiation of the contract is a complex and resource demanding process and

it is often argued that the private sector has an initial advantage as negotiation experience is

more established in the private sector (Parker and Figueira, 2010).

Amado (2012) notes that to enable the government to effectively manage the contract, certain

roles and responsibilities must be required of the private partner through the contract. It is very

24

important that the reporting system of the private partner complies with the government’s

requirements. In this context, the government will have clear policies and procedures with

respect to private partner reporting. These requirements must have been communicated in the

Tender Phase to ensure that the private partner has been given the opportunity to design and

implement a reporting process, and to allow for time to ensure that information management

systems are compliant with the needs of the government.

Contract signature or management of the contract signature process is more demanding for

both the public and private parties. According to Takim, Kharizamand and Rahman (2009) an

extended period is required to allow the private partner to prepare for signature, especially (in

some jurisdictions) the need to form an SPV that will sign the contract. It is essential that the

bidding process is transparent, clearly spelled out where the short-listed company is invited for

negotiation to get the project. But in Malaysia, the open tender is not fully applied, and there

are several companies which have already been awarded projects under the PPP procurement

without any competitive bidding (Khaderi and Aziz, 2010). It is crucial that open competitive

tender process is adapted to select the most qualified contractor based on their expertise and

experience.

According to APMG (2016), the risk of a challenge to the tender or award process is considered

higher in PPPs than in a conventional procurement. The procuring authority must have sound

preparation and procurement processes, and a legal team and relevant subject matter experts

prepared to handle potential challenges including the ability to resolve disputes in the interests

of moving the process forward. Problems may come after soft launch, or after award of the

contract. In Australia, Raisbeck et al. (2010) examined the issues of time and (capital) cost

performance by comparing actual and expected outcomes. They conclude that PPP

procurement delivers projects faster than TP and is between 11 and 31 per cent more cost-

efficient.

Using comparative approach, Habets (2010) makes several conclusions; in the UK PPP

projects offer an advantage in both time and costs, while in half of the projects, innovations

have taken place. On the other hand, are transaction costs high, mainly due to the long

tendering stage, which have also decreased potential benefits from competition. In Australia,

25

PPPs offer mainly a cost advantage as the projects offer a roughly similar time confidence level

as traditional procured projects, mainly due to the delays during the start-up of the project.

Negative outcome is the fact that innovations and design changes are very rare. These

outcomes are quite similar to the ones in the Netherlands. PPPs here are also subject to

extensive transactions costs during the tendering stage, offer too little possibilities for contract

changes leading to little use of innovations. Still these projects are expected to be delivered

with both cost and time advantages over traditional procured projects.

Dikmen and Birgonol (2006) about the importance of trust during contract negotiation. Trust

is reinforced through each partner’s realization of expected responsibilities. Reasonable

performance schedules for deliverables help document the commitments of parties and ensure

consistency in the implementation of the project. Partners can communicate more effectively

by building personal relationships with each other. According to Pelphrey (2015), formal and

informal forms of communication between entities create opportunities to build a more open

and trusting relationship. Parties must act honestly and in good faith and work under the

assumption that the other partners are doing the same. The practice of reciprocity also increases

the cooperative nature of the partnership. Finally, to overcome misperceptions and differences

impeding the emergence of trust, partners should work to understand the perspective and needs

of actors involved in the process. Hawkesworth and Burger (2011) opine that risk-sharing

arrangements uncovered ranged from deductible schemes to event mechanisms with the latter

employed quite frequently; hence, contract designers rely on ex post remedies to address risks

once an event, such as a change in law, occurs. Parametric analysis did not reveal any dominant

trends in risk allocation, but examination by the most active jurisdictions (Florida, Texas, and

Virginia) and source of risk (exogenous versus endogenous) illustrated that project context

influences risk allocation. Van Nguyen 2017 examines how Vietnamese laws should be

improved to facilitate successful PPP projects. It focuses on key PPP rules on project selection,

land acquisition, major entities in procurement, capital, and risk allocation of projects,

procurement procedures and dispute resolution. It was concluded that although PPP laws were

in force in Vietnam, there are many processes that could be improved.

26

2.5 Chapter Summary

The chapter focuses on the review of empirical findings concerning the factors influencing

participation or uptake of the private partnership projects. It emerges that PPP is influenced by

several factors among them: economic, political, social, cultural, and environmental factors.

The perception of investors is influenced by several factors. Financial viability, commitment

of the government, and government policy are key consideration for investors’ involvement in

the PPP. Secondly, institutional capacity of the investor as manifested in the technical

expertise, financial capability, and technological capability must match the needs and

requirements for undertaking the PPP projects. Lastly, procurement procedures and practices,

their flexibility and rigidity determine whether the investor takes up the PPP projects. In this

case, the tendering process, bidding process, and contract negotiation, all inform the final

decision by the investor to participate in the PPP. The proceeding chapter presents the

methodology and research strategy that the study shall embrace.

The following chapter describes the research methodology used in the study, followed by

results and findings in chapter four and finally, conclusion and recommendations in chapter

five.

27

CHAPTER THREE

3.0 RESEARCH METHODOLOGY

3.1 Introduction

This chapter therefore presents the research methodology to be used in the study. It starts with

the research design and the target population of the study, followed by the proposed sampling

design, and the data collection methods to be used in the study. The chapter also presents the

research procedures expected to be adopted and will conclude with the data analysis methods.

3.2 Research Design

Research design is defined as a framework for the generation of evidence that is chosen to

answer the research question in which the investigator is interested (Bryman, 2016). It is a

framework for the collection and analysis of data. Kothari and Garg (2014) describes research

design as the conceptual structure within which research would be conducted and aims to

provide for the collection of relevant evidence with minimal expenditure of effort, time, and

money. Research design may be categorized into the three main categories of descriptive

research, exploratory research, and causal research (Creswell and Poth, 2016). A Descriptive

research aims to describe a population, situation or phenomenon accurately and systematically

using any of the three main methods of case studies, observation, and surveys, to investigate

one or more variables. (Trochim, 2020). The descriptive research design was used in the study

in explaining the factors that influenced private sector investors’ participation in public road

infrastructure projects in Kenya through Public Private Partnership framework.

The method of descriptive research chose in this study is survey research design which

involves procedures in which the researcher administer brief interviews and discussions to a

sample or to the entire population to describe the attitudes, opinions, behaviors, or

characteristics of the population (Creswell and Poth, 2016). Surveys may be done through

questionnaires or interviews to collect data and statistically analyze the data to describe trends

abouts responses to questions and to test research questions or hypothesis. Survey design can

collect data from a large number of respondents and numerous questions can be asked about a

28

subject giving extensive flexibility in data analysis (Saudners, Lewis and Thornhill, 2019). In

this study, the use of questionnaire was employed which is a series of written questions where

the participants choses answers to the questions and supplies basic personal or demographic

information. To this end, survey questionnaires can be administered to the participants through

a variety of ways, such as through questionnaires sent via e-mail or fax, or can be administered

through the Internet (Roopa and Satya, 2012).

3.3 Population and Sampling Design

3.3.1 Population

Population refers to an aggregate or totality of all the objects, subjects or members that conform

to a set of specifications (Polit and Hungler 2013). Ary, Jacobs, Sorensen and Razavieh (2010)

defined population as all members of any well-defined class of people, events, or objects. The

target population for this study consists of the private sector investors, both local and

international, who are undertaking or who have undertaken the 192 road projects under the

mandate of the Kenya National Highways Authority (KeNHA) for the period 2007-2019. The

selection of road projects under KeNHA is based on the fact that this is the government of

Kenya road agency that is responsible for the development, management, rehabilitation and

maintenance of all roads classified under Class A, B and C totaling 18,101 kilometers as

outlined in KeNHA Strategic Plan 2018/19–2022/23. These are roads linking the international,

national, and provincial centers (KeNHA, 2018). The period used in the study of 2007-2019 is

from the date the KeNHA was established to the current government financial period. The

complete listing of such road projects numbering 192 roads has been obtained from data

available on KeNHA’s website.

3.3.2 Sampling Design

3.3.2.1 Sampling Frame

Sampling frame is the listing of all units in the population from which the sample will be

selected (Kothari and Garg, 2014). The sampling frame is defined by specific criteria and is

different from the population, which is every individual case that could be included in the study

29

(David and Sutton, 2016). Sampling is a specific principle used to select members of

population to be included in the study (Saunders, Lewis, and Thornhill, 2016). The sampling

frame for this study is the list of all the road projects under the mandate of Kenya National

Highways Authority for the period 2007-2019. This list totals to 192 road projects in three

different phases of production: Completed, On-Going, and Planned. The duration under study

is the twelve-year period covering 2007-2019 which is from the date of establishment of

KeNHA to current financial year. The sampling frame was sourced from the Kenya National

Highways Authority website.

3.3.2.2 Sampling Technique

Sampling design is a definite plan, which is determined before any data is collected, for

obtaining a sample from a given population (Kothari and Garg, 2014). Kothari and Garg (2014)

categorize samples broadly as being either probability samples or non-probability samples. In

this categorization, probability samples are those in which each element has a known

probability of being included in the sample as opposed to non-probability samples which do

not allow the researcher to determine the probability of inclusion. According to Kothari and

Garg (2014), probability samples can be carried out by way of: simple random sampling;

systematic sampling; stratified sampling; and cluster or area sampling. He goes on to state that

non-probability sampling can be done through convenience sampling; judgement sampling;

and quota sampling.

In this study, simple random probability sampling was used to select the sample. This allowed

for an equal chance of selection to every one of the 192 road projects in the population. From

the population of 192, the road projects will be listed and assigned numbers starting from

number 1 to number 192. Once the sample size was determined based on the sample size

calculation formula, random numbers totaling to the sample size was generated through

random numbers table. Thereafter, each number in the population corresponding to the random

numbers was selected.

30

3.3.2.3 Sample Size

A sample is the segment or subset of the population that is selected for investigation (Bryman,

2016). The sample size is therefore the number of units or elements that is selected for study

and is determined by the sampling technique and the size of the population.

The sample size for this study will be selected using the Yamane (1973) Formula. In the

formula, a 95% confidence level and P of .5 are assumed for the equation. The sample size

based on this formula was 130.

n = N / (1 + Ne2)

Where:

n = corrected sample size, N = population size, and e = Margin of error (MoE), e = 0.05 based

on the research condition.

With the study population of 192 and margin of error at 5%, the sample size would therefore

be:

n = 192 / [1 + 185*(0.05) *2]

n = 129.72972

n = 130 Road Project Investors

3.4 Data Collection Methods

There are two main traditional methods of data collection that are used in the quantitative

research, namely, self-completion surveys also known as social survey or questionnaire survey,

and structured interview (David and Sutton, 2016).

This study collected primary data using a structured questionnaire. The questionnaire

comprised of four sections. The first sections sought to capture demographic details of the

respondents. The second section focused on the effect of investor perception, the third on the

effect of institutional capacity, and the fourth and last section was on the effect of procurement

process as a factor of investor participation in public private partnership road projects in Kenya.

31

The questionnaire was administered directly to the respondents through drop and pick method

and this will give a control over the research process. This made data collected both reliable

and authoritative. The questionnaire had a combination of open ended and close ended

questions aimed at addressing the study objectives. The responses on the questionnaire were

based on a Five Point Likert Scale where 1- Strongly Disagree and 5- Strongly Agree.

3.5 Research Procedures

The study employed various research procedures to ensure that data collected was reliable and

valid. These research procedures included seeking a letter of introduction which facilitated the

application of research permit, pilot testing, self-administration of the questionnaires and

ethical considerations. Pilot testing was undertaken to ensure validity of data collected. After

the development of the questionnaire and data collection sheet, a pilot test was conducted to

test whether there are any errors and the data collected from the data collection instruments

was sufficient for data analysis and addressing the research objectives. Pilot testing was

undertaken with 10 respondents. and by use of Cronbach’s Alpha in SPSS a reliability analysis

was done to evaluate internal consistency of the variables. Findings of the pilot study informed

the refinement of the data collection instruments to ensure valid data is. Since all the variables

were reliable (α>0.7) the questionnaires were distributed to the respondents. To ensure a high

response self-administration of the questionnaire was done. The researcher administered the

questionnaire to the respondents and ample time was awarded for the respondent to complete.

3.6 Data Analysis Methods

Data analysis refers to the running of various statistical tests to infer findings and results from

the tests (Cooper and Schindler, 2014). Data collected was inspected for completeness and

errors. Errors and gaps identified was edited to ensure completeness in the data. Complete data

was coded and keyed into SPSS vs 22 for statistical analysis. Analysis of data was done for

descriptive statistics such as means, standard deviations and frequency distributions. This aid

in description of trends and patterns in the data. To infer relationships, Pearson’s correlation

and regression analysis was conducted using SPSS vs 22.

32

3.7 Chapter Summary

This chapter has highlighted the meaning of research methodology and shows that this is the

approach and rules by which the data for the study was collected, analyzed, and interpreted in

order to answer the research questions. The chapter shows that the key aspects of research

methodology are the research design, which is the structure and framework for undertaking the

research and the identification of the target population for the study. Specifically, the chapter

presents the research design used in the study as survey research design and identifies the

population of the study as the PPP road projects that have been listed in the pipeline by the

Ministry of Transport and Infrastructure. The chapter further describes the sample frame,

sampling technique and sample size for the study. The target population of the study is

identified as 192 road projects with a sample selected of 130. The chapter concludes by

presenting the data collection method using questionnaires and analysis using both descriptive

and inferential statistics. The next chapter presents the findings and results of the study and

finally discussion, conclusion, and recommendations in chapter five.

33

CHAPTER FOUR

4.0 RESULTS AND FINDINGS

4.1 Introduction

The chapter presents the results and findings of the study to investigate and analyze the factors

influencing private sector investors’ participation in public road infrastructure projects in

Kenya through Public Private Partnership framework. The results on each of the study

objectives are analyzed through descriptive and inferential statistics, with the findings being

presented in form of tables, figures, and charts.

4.2 Study Response and Respondents’ Background Information

The study established background profiles of the respondent firms either currently engaged or

with a potential to engage in road PPP projects in Kenya. The information collected on

respondents included the age of the firm, the size of the workforce, the geographical scope of

the firm’s operation, the road project category, the source of funding for road projects, and the

major lender to the investor.

4.2.1 Study Response Rate

The study recorded a response rate of 63%, with 82 questionnaires receiving responses, out of

the total 130 questionnaires administered as shown in Figure 4.1 below. According to

Finchman (2018), a response rate of 60% and above would be sufficient for a research study

and consequently, this research study has proceeded with the data analysis based on the 63%

response received.

34

Figure 4.1: Study Response Rate

4.2.2 Age Distribution of the Respondent Firms

The findings revealed that a majority of the respondents were firms established 6-10 years ago

at 36%, followed by firms established less than 5 years ago at 35%, firms established 11-15

years ago at 17%, and lastly those established more than 20 years ago at 4%. This age profile

of the respondents illustrates that a majority of the current players in the road sector in Kenya

have been in the road construction industry for more than 6 years, with a total of 65% of the

respondent firms being in the age bracket of 6 years or more. This denotes a high level of

maturity for the firms and adds confidence to the firms’ reliability on giving credible and

comprehensive information on the dynamics of the road construction sector in the Kenya. The

firms’ age distribution characteristics are summarized in Figure 4.2.

63%

37%

Study Response Rate

Response Rate Non-Responses

35

Figure 4.1: Age Distribution of the Respondent Firms

4.2.3 Workforce Size of the Respondent Firms

The study established the size of the workforce for the respondent firms with the assumption

that that firms with significant number of employees may have a higher experience and

accumulated knowledge that portends higher level of participation in PPP related projects. The

study showed that the majority of the firms surveyed had a workforce of less than 30 employees

at 51%, followed by firms with 30-59 employees at 25%, firms with 60-89 employees at 13%,

and with the least number of respondent firms being those with more than 90 employees, at

12%. The percentage distribution of respondent firms based on the size of the workforce is

illustrated in Figure 4.3.

Figure 4.2: Workforce Size of the Respondent Firms

35%

36%

17%

4%8%

Age of the Firm

Less Than 5 Years 6-10 Years 11-15 Years 16-20 Years Above 20 Years

Less than 30

employees

30-59

employees

60- 89

employees

More than 90

51%

25%13% 12%

Workforce Size

36

4.2.4 Scope of Operations of Respondent Firms

The study revealed that majority of the private sector investors surveyed in this study were

Kenyan or locally based at 59%, followed by those whose road construction operations are

within East Africa at 28%, with 9% having presence in Africa, and only 4% of the respondent

firms had global operations. Figure 4.4 indicates the distribution of geographical operation of

respondent firms involved in road sector in Kenya.

Figure 4.3: Scope of Operations of Respondent Firms

4.2.5 Road Project Category

The road project categories are classified based on the existing Kenya government road

category classification. A majority of the respondent firms, at 32%, indicated that they were

involved in the construction of Category A International Trunk Roads, followed by 24% for

Category C Primary Roads, 21% for Category D Secondary Roads, 15% for Category B

National Roads (B1, B3, & B8) and 9% for Special Purpose Roads. Figure 4.5 illustrates the

distribution of respondent firms based on the road project categories.

59%28%

9% 4%

Scope of Operation

Kenya East Africa Africa The Rest of the World

37

Figure 4.4: Respondent Firms’ Project Category

4.2.6 Source of Funding of Road Projects

The nature and availability of funding sources is a critical aspect in the ability of private sector

investors to participate in road PPP projects due to the capital-intensive nature of road PPP

projects. In this study, a majority of the respondent firms, at 73%, sourced their funding for

road construction projects locally, 15% of the firms sourced their funds from regional markets

while 12% of the firms sourced funding from international markets as reflected in Figure 4.6.

Figure 4.5: Primary Sources of Funding

32%15%

24% 21%9%

Project Category Distribution

Local Financing

Market

Regional

Financing

Market

International

Financing

Market

73%

15% 12%

Primary Sources of Funding

38

4.2.7 Major Lenders to Investors

The study findings showed the distribution of the major lenders to the investors in the road

construction sector to be as follows: Commercial Banks (61%), Development Banks (15%),

Pension Funds (14%), and Insurance Companies (11%). The role of development banks in

private sector financing has emerged in the wake of realization of sustainable development

goals, enhancing access to capital among PPP private investors as well as focusing on

providing technical assistance in matters of road and infrastructure development in the growing

economies (World Bank, 2018). Figure 4.7 illustrates the distribution of the major lenders of

the respondent firms.

Figure 4.6: Distribution of Major Lenders

4.3 Investor Perception and Participation in PPP Road Projects

The first research question in the study analyzed the extent to which investor perception of

public projects affects investors’ participation in the PPP road projects. The results from the

survey on respondent firms have been analyzed and presented using descriptive statistics

(mean, standard deviation, and percentages) as well as inferential (correlation and regression

analyses).

Commercial Bank

Development Bank

Pension Funds

Insurance Companies

61%

15%

14%

11%

Distribution of Major Lenders

39

4.3.1 Descriptive Statistics on Investor Perception

A descriptive analysis is the first step utilized in the study and has helped to describe the

relevant aspects of investor perception, providing a detailed information on each relevant

variable. The analysis of the different variables in this study has been done using SPSS Version

24.0 software. The descriptive statistics shows the percentages, mean and standard deviation

of the different variables used in the study. The findings demonstrate that investors perceived

that the appropriate risk assessment on PPP road projects was done to a low extent at 40%. In

addition, the study also showed that 36% of respondent investors perceived that the parties in

the PPP road project provided for detailed cost/benefits assessment. The study further showed

that to a very low extent, investors perceived that the capital markets, including the banking

institutions, had remained open to investment in road PPP projects. The study also showed

that 43% of the respondents perceived that increased political risks surrounding the PPP road

projects would result in a decrease in the Internal Rate of Return (IRR) on road projects. The

study has also revealed that a good number of investors at 41% perceived that the PPP road

projects reflected achievement for Value for Money (VFM) to both the public and the private

partner.

The study showed that to a lesser extent, 37%, investors perceived that the government had

been proactive in compensating landowners and communities affected by road PPP projects.

Moreover, 38% of the participants maintained neutrality when asked whether the government

was clear on its position in the implementation of the PPP road projects. Again, a good number

of respondents at 48%, remained neutral when asked whether the political regimes in the

country had remained stable for the last ten years. 53% of the participants surveyed indicated

that either the national government or the county government provided for sound guarantees

towards all PPP road projects. To a lower extent, 33% of the respondents agreed that the

government was actively involved in the road PPP project’s life cycle. To a great extent, 24%

of the participants agreed that there was weak sectorial public bidding legation, all PPP road

projects were anchored on the 2013 PPP Act. To a low extent, 44% of the respondents indicated

that there was strong sectorial public bidding legislation in all the PPP road projects.

Additionally, to a low extent, 38% of the participants indicated all the contract-bidding

procedures in PPP road projects are standardized. 47% of the respondents perceived a low

40

extent on the 2013 PPP Act’s clarity on government’s position and its objectives. However,

48% of the respondent acknowledged that to a great extent, with the appropriate support

mechanisms in place, the 2013 PPP Act had made it easier for public-private collaboration in

road projects.

Table 4.1: Descriptive Findings on Investor Perception and Participation in Road PPP

Projects

Investor Perception and

Participation in PPP Road

Projects

Very

Low

Extent

(%)

Low

Extent

(%)

Neutral

(%)

Great

Extent

(%)

Very

Great

Extent

(%)

Mean

StDev

Risk allocation on PPP road

projects is done in a more

appropriate manner.

15 40 33 10 3 2.99 0.77

The PPP road project parties

provide for detailed cost/benefits

assessment

11 32 36 16 5 3.31 0.82

The capital market including

banking institutions has remained

open to investment.

26 36 28 9 1 2.72 0.81

If the perceived political risks

increase, the expected Internal

Rate of Return (IRR) will decrease

1 6 28 43 23 4.62 0.96

The PPP road projects reflect

achievement for Value for Money

(VFM) to both the public and the

private partner.

1 9 30 41 19 4.49 0.94

The government has been

proactive in compensating

landowners and communities

within the project vicinity.

11 37 34 17 1 3.19 0.78

The government is less clear on its

position in the implementation of

the PPP road projects.

3 14 38 34 11 4.12 0.92

The political regimes have

remained stable for the last ten

years.

0 17 48 32 4 3.94 0.94

The state/county provides for

sound guarantees towards all PPP

road projects.

19 53 24 4 0 2.56 0.66

The government is actively

involved in the project life cycle.

22 33 27 15 3 2.97 0.82

41

Investor Perception and

Participation in PPP Road

Projects

Very

Low

Extent

(%)

Low

Extent

(%)

Neutral

(%)

Great

Extent

(%)

Very

Great

Extent

(%)

Mean

StDev

There is weak sectorial public

bidding legation, all PPP road

projects are anchored on the 2013

PPP Act.

4 32 24 24 16 3.75 0.81

There is strong sectorial public

bidding legislation in all the PPP

road projects.

13 44 32 7 4 2.98 0.73

All the contract-bidding

procedures in PPP road projects

are standardized.

13 38 31 17 1 3.12 0.78

The 2013 PPP Act is clear on

government’s position and its

objectives.

5 47 41 4 4 3.10 0.71

With the appropriate support

mechanisms in place, the 2013 PPP

Act has made it easier for public-

private collaboration in road

projects.

8 9 29 39 15 4.18 0.95

KEY: StDev-Standard Deviation

4.3.2 Correlation Analysis Between Investor Perception and Investor Participation in

PPP

The study used Pearson correlation to get the linear relationship between the various

independent and dependent variables. The independent variable is the variable that influences

the other, while the dependent variable is the one that is influenced. The correlation coefficient

indicates whether there is a linear relationship between two variables and whether the two

variables have a causal relationship. Pearson’s correlation is designated by (r) and it

symbolizes the correlation coefficient, which ranges between +1 to -1. The positive or negative

sign signifies the direction of the relationship while the statistical significance levels were

determined at alpha = 0.05 or alpha = 0.01.

The independent variables for this study were the investor perception which was correlated

with their consequent participation in PPP road projects, which was the dependent variable, to

find out if there was any relationship, association or correlation between investors’ perception

42

on these issues highlighted and their consequent participation in PPP road projects.

Additionally, the study established the sign of the coefficient indicating direction and

magnitude of the linear relationship as recommended by Orodho (2005). The findings are

presented in Table 4.2.

As indicated in Table 4.2 below, the study established that investors’ perceptions have an

overall positive correlation with participation in the PPP road projects, with Pearson’s

coefficient of r = 0.614 and was significant (p =0.000) at alpha = 0.005 level of significance.

This implies that investors’ perceptions have a linear relationship with the level of participation

in the PPP road projects and that for each unit increase in investor perception, the chances of

a private sector investor participating in PPP road projects increased by 61.4%.

Table 4.2: Correlations Between Investor Perception and Investor Participation

Correlations

Investor

Perception

Investor

Participation

Investor Perception

Pearson Correlation 1 .614**

Sig. (2-tailed) .000

N 82 82

Investor Participation

Pearson Correlation .614** 1

Sig. (2-tailed) .000

N 82 82

**. Correlation is significant at the 0.01 level (2-tailed).

4.3.3 Regression Analysis on Investor Perception Against Participation in PPP Projects

The research defined the long run relationship and formulated the test of significance on the

long run parameters(s). The study used Binary Logistic Regression analysis to determine the

linear statistical relationship between the independent and dependent variables for this

research. The output of the regression model for investor perception alongside its respective

probability value(s) is shown in Table 4.3. The coefficient of determination R-Square of 0.377

implies that 37.7% of the change in participation in PPP road projects was associated with

variation in investors’ perceptions, holding all other factors constant.

43

Table 4.3: Regression Model Summary for Investor Perception

Model Summaryb

Model R

R

Squar

e

Adjuste

d R

Square

Std.

Error of

the

Estimat

e

Change Statistics

Durbin

-

Watson

R

Square

Chang

e

F

Chang

e

df

1

df

2

Sig. F

Chang

e

1 .614

a .377 .369 .37987 .377 48.442 1 80 .000 1.797

a. Predictors: (Constant), Investor Perception

b. Dependent Variable: Investor Participation

Table 4.4 shows the Analysis of Variance (ANOVA) performed at 5% level of significance

which indicates that the variable investor perception had significant effect on investor level of

participation in PPPs. This implies that the regression model was a significant predictor of

investors’ participation PPP road projects.

Table 4.4: ANOVA for Investor Perception

ANOVAa

Model Sum of

Squares df Mean Square F Sig.

1

Regression 6.990 1 6.990 48.442 .000b

Residual 11.544 80 .144

Total 18.534 81

a. Dependent Variable: Investor Participation

b. Predictors: (Constant), Investor Perception

The normalized long run estimated co-integration results are shown in the following regression

equation:

Y = 1.33 + 0.597X1

Where: Y = Investor Participation

X1 = Investor Perception

This long-run equation shows that investor participation in PPP road projects is dependent on

investor perception.

44

Table 4.5: Coefficients for Investor Perception

Coefficientsa

Model

Unstandardized

Coefficients

Standardized

Coefficients t Sig.

95.0% Confidence

Interval for B

B Std.

Error Beta

Lower

Bound

Upper

Bound

1

(Constant) 1.333 .279 4.778 .000 .778 1.888

Investor

Perception .597 .086 .614 6.960 .000 .426 .767

a. Dependent Variable: Investor Participation

4.4 Institutional Capacity and Participation in PPP Road Projects

The second research question in the study analyzed the responses from the survey on the extent

to which institutional capacity affects participation in PPP road projects in the country. This

has been done and presented using descriptive statistics (mean, standard deviation, and

percentages) as well as inferential (correlation and regression analyses).

4.4.1 Descriptive Statistics on Institutional Capacity

The second research question of this study aimed at assessing the influence of investor’s

capacity on the level of participation in PPP Road Projects. Majority of the participants, 43%

remained neutral when asked whether their firms had established a fully equipped PPP team.

Nonetheless, to a very great extent 43% of the participants opined that their firms were yet to

establish a PPP team. To very low extent, participants indicated that the current public

governance permitted proper coordination among concerned road project PPP entities. To a

great extent, 29% of the respondents indicated their firms depended on external consultants for

technical capacity involving PPP road projects. In addition, 43% agreed to a great extent that

their firm had invested in experienced and highly technical expertise to undertake PPP projects.

33% of the participants, to a low extent indicated that the borrowing rate in the financial market

is sustainable in undertaking PPP road projects. 57% of the participants to a great extent agreed

that non-availability of affordable debt in the market made it difficult to participate in PPP road

projects. Half of the respondents admitted to great extent that whenever perceived political

45

risks increased, the insurance premium for private investors would increase. 52% of the

participants agreed to a very great extent that the availability of a budget plan enabled the

private investor to have better control of cost overruns in a project. 33% of the participants

indicated that to a low extent that the firm could access funding from foreign markets for PPP

road projects. 43% of the participants agreed to a low extent that the financial statements

regarding PPP road projects were published online through a working website platform while

38% of the respondents deemed to a low extent that all the necessary technological equipment

necessary for road PPP projects were available locally. 44% of the participants indicated that

to great extent, at times they were compelled to import special equipment for high quality road

construction. 54% of the participants, to very great extent indicated that the firm leveraged on

technology to facilitate knowledge sharing among PPP road project stakeholders. Lastly, to

very great extent, 54% of the participants indicated that their firms relied on technology in

making appropriate designs for roads that suited client needs.

Table 4.6: Institutional Capacity and Participation in Road PPP Projects

Variables

Very

Low

Extent

Low

Extent Neutral

Great

Extent

Very

Great

Extent

Mean StDev

The organization has a fully

equipped PPP team.

5 12 43 36 4 3.98 1.05

The organization is yet to establish

a PPP team.

1 4 31 43 21 4.62 0.97

The current public governance

permits proper coordination among

concerned road project PPP entities.

30.1 37 24.7 5.5 2.8 2.61 0.80

The organization depends on

external consultants for technical

capacity involving PPP road

projects.

5.1 8.9 29.1 29.1 27.8 4.46 0.95

The organization has invested in

experienced and highly technical

expertise to undertake PPP projects.

3.8 5.1 25.6 42.3 23.1 4.58 0.97

The borrowing rate in the financial

market is sustainable in undertaking

PPP road projects.

13 32.5 33.8 19.5 1.3 3.22 0.82

Non-availability of affordable debt

in the market makes it difficult to

implement PPP road projects.

0 0 16.2 56.8 27 4.01 0.99

46

Variables

Very

Low

Extent

Low

Extent Neutral

Great

Extent

Very

Great

Extent

Mean StDev

If the perceived political risks

increase, the insurance premium

will increase.

3.8 0 20 50 26.3 4.82 0.99

Availability of budget plan

enables the private partner to have

better control of cost overruns

0 1.3 5.2 41.6 51.9 5.42 0.97

The firm can access funding from

foreign markets for PPP road

projects.

21.8 33.3 32.1 10.3 2.6 2.91 0.82

All our financial statements

regarding PPP road projects are

published online through a working

website platform.

13.9 43 39.2 2.5 1.3 2.85 0.74

All the necessary technological

equipment are available locally

18.8 37.5 35 8.8 0 2.85 0.79

At times we are compelled to import

special equipment for high quality

road construction.

1.3 6.7 29.3 44 18.7 4.54 0.96

The firm leverages on technology to

facilitate knowledge sharing among

PPP road project stakeholders

0.0 0.0 3.8 41.8 54.4 4.50 0.98

The firm relies on technology to

make appropriate geometric design

for roads that suit client needs.

0 0 6.3 40 53.8 5.46 0.98

KEY: StDev-Standard Deviation

4.4.2 Correlations Between Institutional Capacity and Participation in Road Projects

The study used Pearson correlation to get the linear relationship between the various

independent and dependent variables. The independent variable is the variable that influences

the other, while the dependent variable is the one that is influenced. The correlation coefficient

indicates whether there is a linear relationship between two variables and whether the two

variables have a causal relationship. Pearson’s correlation is designated by (r) and it

symbolizes the correlation coefficient, which ranges between +1 to -1. The positive or negative

sign signifies the direction of the relationship while the statistical significance levels were

determined at alpha = 0.05 or alpha = 0.01.

47

For the second research question in the study, the institutional capacity was correlated with the

resultant participation in PPP road projects, which was the dependent variable, to find out if

there was any relationship, association or correlation between the variables. Further, the study

established the sign of the coefficient indicating direction and magnitude of the linear

relationship as recommended by Orodho (2005). The findings are presented in Table 4.7.

As indicated in Table 4.7, it was established that investors’ institutional capacity has a positive

correlation with their consequent level of participation in PPP road projects with a Pearson’s

coefficient of r = 0.379 and that this relationship was significant (p =0.000) at alpha = 0.005

level of significance. This implies that institutional capacity has a linear relationship with the

level of participation in the PPP road projects and that for each unit increase in institutional

capacity, the chances of participating in PPP road projects increased by 37.9%.

Table 4.7: Correlation Between Institutional Capacity and Investor Participation in

Road PPP Projects

Correlations

Investor

Participation

Institutional

Capacity

Investor Participation

Pearson Correlation 1 .379**

Sig. (2-tailed) .000

N 82 82

Institutional Capacity

Pearson Correlation .379** 1

Sig. (2-tailed) .000

N 82 82

**. Correlation is significant at the 0.01 level (2-tailed).

4.4.3 Regression Analysis of Institutional Capacity and Participation in PPP Road

Projects

The research defined the long run relationship and formulated the test of significance on the

long run parameters(s). The study used Binary Logistic Regression analysis to determine the

linear statistical relationship between the independent and dependent variables for this

research. The output of the regression model for institutional capacity alongside its respective

probability value(s) is reported in Table 4.8. As can be seen in Table 4.8, the variable

48

institutional capacity had a significant effect on the level of investor participation in PPP road

projects. The coefficient of determination R-Square implies that 14.3% of the change in the

level of participation in PPP road projects was associated with variation in institutional

capacity, holding all other factors constant.

Table 4.8: Regression Model Summary for Institutional Capacity

Model Summaryb

Model R

R

Squar

e

Adjuste

d R

Square

Std.

Error of

the

Estimat

e

Change Statistics

Durbin

-

Watson

R

Square

Chang

e

F

Chang

e

df

1

df

2

Sig. F

Chang

e

1 .379

a .143 .133 .44548 .143 13.394 1 80 .000 1.621

a. Predictors: (Constant), Institutional Capacity

b. Dependent Variable: Investor Participation

Table 4.9 shows the Analysis of Variance (ANOVA) performed at 5% level of significance

which indicates that the variable institutional capacity had significant effect on the investors

level of participation. This implies that the regression model for institutional capacity was a

significant predictor of the level of investors’ participation PPP road projects.

Table 4.9: ANOVA for Institutional Capacity

ANOVAa

Model Sum of

Squares df Mean Square F Sig.

1

Regression 2.658 1 2.658 13.394 .000b

Residual 15.876 80 .198

Total 18.534 81

a. Dependent Variable: Investor Participation

b. Predictors: (Constant), Institutional Capacity

49

The normalized long run estimated co-integration results are shown in the following regression

equation:

Y = 1.951 + 0.412X1

Where: Y = Investor Participation

X1 = Institutional Capacity

This long-run equation shows that the level of investor participation in PPP road projects is

dependent on institutional capacity of the investors.

Table 4.10: Coefficients for Institutional Capacity

Coefficientsa

Model

Unstandardized

Coefficients

Standardized

Coefficients t Sig.

95.0% Confidence

Interval for B

B Std.

Error Beta

Lower

Bound

Upper

Bound

1

(Constant) 1.951 .359 5.439 .000 1.237 2.665

Institutional

Capacity .412 .113 .379 3.660 .000 .188 .636

a. Dependent Variable: Investor Participation

4.5 Procurement Practices and Participation in PPP Projects

The third research question in the study analyzed the extent to which procurement processes

affect investors’ participation in the PPP road projects. The results from the survey on

respondent firms have been analyzed and presented using descriptive statistics (mean, standard

deviation, and percentages) as well as inferential (correlation and regression analyses).

4.5.1 Descriptive Statistics on Procurement Practices

The third research objective focused on evaluating the effectiveness of procurement practices

in facilitating investor participation in road PPP projects. 26% of the respondents indicated a

low extent of confidence in the tender evaluation process. 45% of the participants showed to a

very great extent their lack of confidence in the tender evaluation process. Furthermore,

majority of the respondents disagreed with the extent to which the PPP project partner bidding

50

process was transparent to all the stakeholders, with 34% indicating a very low extent and 26%

indicating a low extent. In addition, 47% of the participants indicated that to a great extent

there were some opaque practices in the partner bidding selection. On a positive note, 44% of

the participants revealed that to a great extent, the main information regarding tender

advertisement was made public through publications and online platforms. On the other hand,

36% of the participants revealed that the bidder selection was, to a low extent, solely dependent

on competitive exercise. 51% of the survey participants indicated that single sourcing was, to

a great extent, rampant in the selection of PPP projects. Majority of the participants disagreed

that instances of bribery were less prevalent during partner selection, with 47% indicating they

agreed with the statement to a low extent. 44% of the respondents agreed to a very great extent

that subversion of due process in the award and execution of PPP road projects. In addition,

46% of the participants indicated that to great extent, conflict of interest often arose during

bidder selection. Majority of the respondents, at 33%, were neutral on whether all contracts are

made public to the parties of interest. In addition, 46% of the participants were neutral on

whether the contracts were only restricted to the government and the selected bidder. Similarly,

40% of the participants remained neutral on whether there was room for renegotiation of PPP

road projects. Further, 37% of the respondents were neutral on whether contractual terms were

less explicit and some of the information needed further elaboration. Ultimately, 51% of the

participants agreed to a great extent that terms relating to payment mechanisms and distribution

of risks and benefits were well elaborated.

The detailed findings on the third research question on the effect of procurement practices are

presented in Table 4.11.

51

Table 4.11: Descriptive Statistics for Procurement Practices and Participation in Road

PPP Projects

Variable

Very

Low

Extent

Low

Extent Neutral

Great

Extent

Very

Great

Extent

Mean StDev

I have high confidence in the

tender evaluation process. 1.2 25.6 45.1 11 17.1 2.44 0.81

I have little confidence in the

tender evaluation process. 12.2 2.4 40.2 2.4 45.1 3.66 0.93

Partner bidding process is

transparent to all the

stakeholders.

34 26 11 22 7 2.33 0.72

There are some opaque practices

in the partner bidding selection. 0 9 29.5 47.4 14.1 3.67 0.83

Main information regarding

tender advertisement is made

public through publications and

online platforms.

0 3.8 23.1 43.6 29.5 3.99 0.83

Bidder selection is solely

dependent on competitive

exercise.

16.3 36.3 33.8 11.3 2.5 2.48 0.98

Single sourcing is rampant in the

PPP projects. 1.3 2.6 15.4 51.3 29.5 4.05 0.82

Instances of bribery are less

prevalent during partner

selection.

17.9 47.4 33.3 1.3 0 2.18 0.73

Subversion of due process in the

award and execution of PPP

road projects is common.

3.7 0 9.9 42 44.4 3.58 0.72

Conflict of interest often arises

during bidder selection. 1.3 3.9 17.1 46.1 31.6 4.03 0.88

All contracts are made public to

the parties of interest. 10 28.8 33.8 20 7.5 2.86 1.09

Contracts are only restricted to

the government and the selected

bidder.

1.2 13.6 45.7 30.9 8.6 3.32 0.86

There is room for renegotiation

of PPP road projects. 11.1 19.8 39.5 22.2 7.4 2.95 1.08

Contractual terms are less

explicit and some of the

information needs further

elaboration.

8.9 13.9 36.7 27.8 12.7 3.96 0.88

Terms relating to payment

mechanisms and distribution of 2.5 2.5 17.7 50.6 26.6 3.22 1.12

52

Variable

Very

Low

Extent

Low

Extent Neutral

Great

Extent

Very

Great

Extent

Mean StDev

risks/benefits are well

elaborated.

KEY: StDev-Standard Deviation

4.5.2 Correlations Between Procurement Practices and Investor Participation

The study used Pearson correlation to get the linear relationship between the various

independent and dependent variables. The independent variable is the variable that influences

the other, while the dependent variable is the one that is influenced. The correlation coefficient

indicates whether there is a linear relationship between two variables and whether the two

variables have a causal relationship. Pearson’s correlation is designated by (r) and it

symbolizes the correlation coefficient, which ranges between +1 to -1. The positive or negative

sign signifies the direction of the relationship while the statistical significance levels were

determined at alpha = 0.05 or alpha = 0.01.

The study’s third research question on the effect of procurement practices was correlated with

the investors’ level of participation in PPP road projects, which was the dependent variable, to

find out if there was any relationship, association or correlation between the variables. Further,

the study established the sign of the coefficient indicating direction and magnitude of the linear

relationship as recommended by Orodho (2005). The findings are presented in Table 4.12.

As indicated in Table 4.12 below, the study established that the procurement practices have a

positive correlation with the level of investors’ participation in PPP road projects with a

Pearson’s coefficient of r = 0.496 and this correlation was significant (p =0.000) at alpha 0.005

level of significance. This implies that procurement practices have a linear relationship with

the level of participation in the PPP road projects and that for each unit increase in procurement

practice variable, the chances of participating in PPP road projects increased by 49.6%.

53

Table 4.12: Correlation Between Procurement Practices and Investor Participation

Correlations

Investor

Participation

Procurement

Practices

Investor Participation

Pearson Correlation 1 .496**

Sig. (2-tailed) .000

N 82 82

Procurement Practices

Pearson Correlation .496** 1

Sig. (2-tailed) .000

N 82 82

**. Correlation is significant at the 0.01 level (2-tailed).

4.5.3 Regression Analysis of Procurement Practices Against Participation in PPP

Road Projects

The research defined the long run relationship and formulated the test of significance on the

long run parameters(s). The study used Binary Logistic Regression analysis to determine the

linear statistical relationship between the independent and dependent variables for this

research. The output of the regression model for procurement practices alongside its respective

probability value(s) is reported in Table 4.13. As can be seen in Table 4.13, the variable

procurement practices had a significant effect on the level of investor participation in PPP road

projects. The coefficient of determination R-Square of 0.246 implies that 24.6% of the change

in the level of participation in PPP road projects was associated with variation in procurement

practices, holding all other factors constant.

Table 4.13: Regression Model Summary for Procurement Practices

Model Summaryb

Model R

R

Squar

e

Adjuste

d R

Square

Std.

Error of

the

Estimat

e

Change Statistics

Durbin

-

Watson

R

Square

Chang

e

F

Chang

e

df

1

df

2

Sig. F

Chang

e

1 .496

a .246 .237 .41790 .246 26.131 1 80 .000 1.707

a. Predictors: (Constant), Procurement Practices

b. Dependent Variable: Investor Participation

54

Table 4.14 shows the Analysis of Variance (ANOVA) performed at 5% level of significance

which indicates that the variable procurement practices had significant effect on investor

participation. This implies that the regression model for procurement practices was a

significant predictor of the level of investors’ participation PPP road projects.

Table 4.14: ANOVA for Procurement Practices

ANOVAa

Model Sum of

Squares df Mean Square F Sig.

1

Regression 4.563 1 4.563 26.131 .000b

Residual 13.971 80 .175

Total 18.534 81

a. Dependent Variable: Investor Participation

b. Predictors: (Constant), Procurement Practices

The normalized long run estimated co-integration results are shown in the following regression

equation:

Y = 1.729 + 0.492X1

Where: Y = Investor Participation

X1 = Procurement Practices

This long-run equation shows that investor participation in PPP road projects is dependent on

procurement practices.

Table 4.15: Coefficients for Procurement Practices

Coefficientsa

Model

Unstandardized

Coefficients

Standardized

Coefficients t Sig.

95.0% Confidence

Interval for B

B Std.

Error Beta

Lower

Bound

Upper

Bound

1

(Constant) 1.729 .301 5.735 .000 1.129 2.329

Procurement

Practices .492 .096 .496 5.112 .000 .300 .683

a. Dependent Variable: Investor Participation

55

4.6 Investor Appetite for PPP Road Projects

The study also sought to establish the level of private sector investors’ participation in existing

PPP road projects in the country through a survey on a number of statements. The study

revealed that to great extent (36%), the road projects have been a true reflection of value for

money. 34% of the study respondents remained neutral when asked whether the satisfaction

level of the public towards completed PPP road projects was encouraging. 36% of respondents

surveyed disagreed that the progress completion rate for the PPP road projects was high.

Another, 36% of the respondents were neutral on whether the qualified rate of road project

quality was high. In addition, 41% of the respondents remained neutral when asked whether

the investment profit rate was motivating.

Table 4.16: Level of Participation in Road PPP Projects

Investor Appetite for PPP

Road Projects

Very

Low

Extent

Low

Extent Neutral

Great

Extent

Very

Great

Extent

Mean StDev

Road Projects’ are a true

reflection of value for money 1.3 8.8 36.3 36.3 17.5 4.40 0.95

The satisfaction level of the

public towards completed PPP

road projects is encouraging

7.8 26 33.8 27.3 5.2 3.61 0.85

The progress completion rate for

the PPP road projects is high. 13.4 36.1 30.9 2.1 82.5 7.31 1.10

The qualified rate of road project

quality is high. 3.8 17.9 35.9 32.1 10.3 3.99 0.90

The investment profit rate is

motivating. 12.3 27.2 40.7 17.3 2.5 3.30 0.85

KEY: StDev-Standard Deviation

4.7 Chapter Summary

The chapter presented the results and findings of the study to investigate and analyze the factors

affecting private sector investors’ participation in public road infrastructure projects in Kenya

through Public Private Partnership framework. The research results showed that investor

perception has a significant impact on investors’ decision to participate in PPP road projects.

In addition, the capacity of the investor had a significant influence on the level of participation

in PPP road projects. The research findings further revealed that procurement practices had a

56

positive and significant influence on the level of participation in PPP road projects. The next

chapter being the final chapter, presents the discussion of the findings, conclusion, and

recommendations arising from the study.

57

CHAPTER FIVE

5.0 DISCUSSION, CONCLUSION, AND RECOMMENDATIONS

5.1 Introduction

This chapter presents the summary of the results and findings of the study and discusses these

findings in the context of the existing literature on the subject. In addition, the chapter makes

conclusions of the study based on each of the study research questions. The chapter further

makes recommendations for improvements on the status of investor participation in PPP road

projects as well as recommendation for further studies.

5.2 Summary

The purpose of the study was to investigate and analyze the factors affecting private sector

investors’ participation in public road infrastructure projects in Kenya through Public Private

Partnership framework. The study was guided by the following research questions: To what

extent does investor perception affect participation in the public private partnership projects in

the roads sector? To what extent does institutional capacity affect participation in the public

private partnership projects in the roads sector? Lastly, to what extent do procurement

processes affect participation in the public private partnership projects in the roads sector?

The study adopted a survey research design. The population of the study was the 192 road

projects that had been listed under the mandate of the Kenya National Highways Authority

(KeNHA) for the period 2007-2019. Using simple random sampling in determining the

participants in the survey, a sample size of 130 was selected for this study. The data collection

was done using survey questionnaires and the data collected was then analyzed using

descriptive and inferential statistical methods with the output of the analysis being presented

in the form of tables and figures. The study was a survey targeting a population of 130 projects

listed in the pipeline by the Kenya National Highways Authority (KeNHA). Simple random

sampling was employed in establishing the survey participants. For data analysis, descriptive

statistics and inferential statistics were conducted. Analysis output was presented in the form

of tables and figures.

58

The first research question sought to answer the extent to which investor perception affected

participation in the public private partnership projects in the roads sector. The findings from

the first research question show that a project’s financial feasibility, the government’s political

commitment and government policies, all had positive correlation with investors’ participation

in PPP road projects (Pearson Correlation, r = 0.614). With a significance level at 5% (p

=0.000), the regression model results showed that investor perception variables had positive

and significant influence on the level of investor participation in road PPP projects.

The second research question focused on assessing the extent to which institutional capacity

of the investor affected the level of participation in PPP road projects. The findings on the

second research question revealed that the expertise of the investor, the investor’s

technological capability and the financial capability of the investor had a significant influence

on investor participation in PPP road projects with a (p = 0.000) 5% level of statistical

significance. As a result, institutional capacity therefore positively affected investors’

participation in PPP road projects, even though the level of correlation remained low (Pearson

Correlation, r = 0. 379).

The last research question of this study inquired into the influence of procurement practices on

investors’ decision to participate in PPP road projects. The findings of the last research

question were that the tendering practices, the bidding and partner selection, and contract

negotiation, were all found to have a slight positive influence on investors’ decision to

participate in PPP road projects (Pearson Correlation, r = 0. 496). Nonetheless, these findings

remained significant (p= 0.000) at 5% level of statistical significance, meaning that

procurement practices had a positive and significant influence on the level of investor

participation in road PPP projects.

5.3 Discussion

5.3.1 Investor Perception and Participation in PPP Road Projects

The study findings revealed that investor perception on PPP road projects had a positive and

significant effect on the level of participation in PPP road projects. The findings implied that

project financial feasibility, political commitment, government policy all had a positive

59

correlation with participation in PPP road projects (Pearson Correlation, r = 0.614). The

variables were found to be significant (p =0.000) at 5% significance level. Consequently, with

all other factors held constant, an increase in investor perception factors is expected to result

in an increase in private sector investors’ level of participation in PPP road projects. These

results are in line with studies by Chileshe, Njau, Kibichii, and Macharia (2020) who indicated

that perceptions on political stability and viability of the projects are highly valued by the

private sector in assessing whether or not to participate in PPP projects. In their findings,

factors such as acceptance and support given by the community, project feasibility, laws,

regulations and guidelines put in place, availability of a financial market and having a well-

organized and committed public agency, were the highly ranked critical success factors (CSFs)

in PPP projects. In addition, Chileshe et al (2020) also conclude that poor planning from public

and private sectors in managing PPP projects can lead to ineffective PPP project

implementation. They conclude that the private sector is motivated by quick profits, which

suggests that the sector is more attracted to invest in short-term projects that generate quick

returns rather than investing in transportation infrastructure whose returns are long-term and

associated with high risks. It is therefore necessary that both the public sector and private sector

parties understand their roles and responsibilities in the PPP project to achieve value for money

(VFM).

The study result is also in agreement with previous observations by Kenya Bankers Association

(2016) that infrastructure, especially transportation, projects are structurally exposed to market

risk. Certainly, below-estimate demand in road PPP projects may be the result of errors in

project preparation such as a defective cost-benefit analysis, inaccurate traffic projections,

unaffordable tariffs or may derive from factors such as unfavorable government action,

external factors, among others. Hashim (2017) further revealed that the asset risk in PPP

projects is among the challenges particularly where the risk is associated with the design and

construction. Nevertheless, the poor planning in designing and maintaining the assets at the

early stage of PPP projects will affect the operational phase. Bengesi, Mwesiga, and Mrema

(2016) also suggested that beyond the understanding of the concept of PPP, the investor

perceptions on political stability and the viability of the project in question may count more

towards private sector investor attraction to long term PPP projects which are typically

associated with huge capital investment and high risks.

60

The findings in this study on the effect of investor perceptions on project financial feasibility

also support findings by Lop, Ismail, & Isa (2017) that low level of end users’ satisfaction will

demonstrate the real situation of PPP project’s performance. One of the primary concerns that

investors have is inaccuracy of the data that leads to wrong projections as well as cost and

benefit analyses, thereby causing demand risk on the part of the investor and compromising

project sustainability. The government has also been slow in decision making towards potential

PPP projects. This is possibly attributed to lack of proper mechanism to transfer calculated risk

to the private sector. Another aspect of financial capability is the cost of capital which should

take into account the appropriate level of base tariff. Ideally, the internal rate of return (IRR)

of a project should be equal to its cost of capital. If the IRR is greater than the cost of capital,

the investor makes excess profit, while if IRR is less than the cost of capital, the investor loses

money. Pricing should thus ideally be set at levels that allow fair rates of return on investment

to cover the cost of financing and to meet contractual obligations (United Nations Economic

and Social Commission for Asia and the Pacific, 2009).

The high number of pending or incomplete projects also gives credence to investors’ low

perception on the financial feasibility of PPP road projects. In Kenya, for instance, the

Government is facing the uphill task of clearing a backlog of road projects that have been

delayed and it is estimated that it will take 10 years and an additional KShs.650 billion in

budgetary allocations to complete the delayed ongoing projects (Owino 2020). Mwende (2019)

further asserts that the time and cost overruns on projects are deliberately orchestrated by

corrupt public officials who ensure that timelines are breached through delayed payments,

which allows contractors to ask for compensation for the delays originating from the

government. Patil, Gupta, Desai, and Sajane (2013) identify five important causes of

construction delays in transportation infrastructure projects namely; land acquisition,

environmental impact assessment, financial closure, change orders by the client, and poor site

management and supervision by the contractor.

Furthermore, the outcome of this study’s research question on the investor perception resonates

well with Debel (2019) who revealed that for effective implementation of PPP road projects,

the government should ensure at least the presence of an enabling specific PPP policy, well

organized and committed public agency, stable political and social environment, favorable

61

legal frameworks and good governance. However, the study findings contradict with

conclusions drawn by Minjie (2012) in a study on health PPPs which indicate that there was a

strong governance for health PPP projects the ministry was committed to PPP projects goals.

5.3.2 Institutional Capacity and Participation in PPP Road Projects

The study findings from the research question on institutional capacity of private sectors

investor in road projects in Kenya revealed that the institutional capacity of the investors which

was assessed through variables such as financial, technical, marketing, management

capabilities, play a significant role in predicting the likelihood of private sector investors

participating in road PPP projects. The research findings in this study show that the investor

expertise, technical capability, and financial capability have a positive and significant effect

on participation in PPP projects. These study findings on investor expertise are closely linked

to the Agrawal (2010) assertion that a strong and capable project team is crucial for the success

of PPP project implementation. The findings can also be related to findings that the efficiency

of PPP project success is directly impacted by the shortage of staff in monitoring the projects

performance as revealed by Bannan (2012). This is further supported by studies on

implementing PPP projects as discussed by Carrillo (2006) that conclude that different level

of experience between individuals from private concessionaires and public sectors also

contributed to the poor projects implementation.

The findings on the technical capability of the private sector investors is also associated with

the level of dependency of the private sector party on the government agencies. This is

supported by Carrillo (2006) who shows evidence that private concessionaires whose project

teams are highly dependent on the government, despite the project being private sector driven,

are not capable of successful implementing PPP projects. Unfortunately, in the local context,

many firms within the construction sector struggle with deficiency in various capability

endowments. Thus, the research findings on institutional capacity supports the argument by

Lop, Ismail, Isa, and Khalil (2017) who identified eight factors contributing to poor project

performance. These include institutional capacity factors namely; lack of competency among

staff or person in charge of the PPP, service delivery failure, lack of strategy in assessing

performance, lack of monitoring, lack of experience and understanding of PPP among

62

stakeholders, and poor management. Further studies supporting the research findings on the

effect of institutional capacity on the level of participation in PPP projects show that inadequate

capacity by the investor can act as a cause of project delays; resulting in time and cost overruns

in infrastructure projects (Deeppa and Krishnamurthy, 2014). These findings by Deeppa and

Krishnamurthy (2014) manage to group these institutional capacity factors into contractor

related factors, professional management related factors, material related factors, labour and

equipment, government related factors, external factors, project related factors, owner related

factors, contractual responsibilities, and design and documentation factors. Other institutional

capacity factors affecting the ability of private sector investors to undertake successful PPPs

include inadequate negotiation skills among those engaged in negotiation of PPP contracts and

the lack of a PPP coordination team (Msafiri, 2015).

The research findings on institutional capacity of investors is further supported by assessments

of the financial capability of private sector investors in less developed capital markets who

mainly depend on commercial banks and similar lenders in the industry (Kamau, 2016). The

possibility of commercial banks forming a consortium to fund such projects is disrupted by the

varying views of each potential partner. Typically, banks examine the feasibility of projects

based on the available information. A positive evaluation of one of the banks may not

necessarily match with that of another bank due to variation on priorities. In assessing the

financial capability as far as collateral is involved, Nifula (2009) reports that for PPP projects,

in contrast with other commercial lending agreements that pledge property or assets in case of

default, the project lenders will instead seek to secure “step-in” rights to use the assets in order

to continue to operate the utility until its debt obligations have been repaid. This sort of

potential constraint on management is not present, or is limited, in other forms of corporate

lending and is another consideration for the internal financial sustainability of a PPP.

The financial capability of private sector investors is further affected by the financial capacity

of government institutions tasked with overseeing implementation of PPP projects which are

often under-funded as demonstrated through the Kenya government 2019/2020 financial year

budgetary allocations which show that as of January 2019 there were pending bills totaling

KES. 36.8 billion (Owino, 2020). In addition, (Wanzala, 2019) reports that the KES. 65 billion

allocated by the Kenya government for road projects for the fiscal year ended June 2019 was

63

far much lower than the KES. 94.8 billion required to complete the proposed road works,

including land compensation. Owino (2020) further reports that it will take at least 10 years

and a further KES. 650 billion in budgetary allocations to complete the pending road projects.

5.3.3 Procurement Practices and Participation in PPP Projects

The study findings also assessed the relation between procurement practices and the level of

investor participation in road PPP projects. Procurement is probably the most critical aspect

and perhaps the most demanding phase of PPP project, other than the actual implementation

of the road project. The study revealed that tendering process, bidding process and bidder

selection, and contract negotiation process as critical factors for consideration by private sector

investors in their decision to participate in PPP road projects. The analysis established a

positive and significant relationship between procurement practices and the level of investor

participation in PPP projects. The study echoes the findings by Subaizah and Azzahra (2014)

that factors such as lengthy delays in negotiations, lack of government guidelines and

procedures on PPP, higher charge to direct users, delays because of political debate and

confusion over government objectives and evaluation criteria as the top five constraints for

adopting PPP in Malaysia. The study findings are also in line with other research conclusions

by Agrawal (2010) that in poorly regulated PPP markets, procurement is highly characterized

by high opaqueness, lengthy procedures, corruption and rent seeking behavior, among other

factors which weaken the private investors’ confidence in PPP projects. Dolla and Laishra

(2019) have shown that despite the dire need for MSW services in India, the stakeholders

perceived that the MSW services procured through the PPP mode had unfavorable results such

as failed projects, high transaction costs, and over-exploitation by the private sector. They

attributed this negativity to inappropriate procurement process.

The study results are also supported by the findings from a study by Dabarera, Perera, and

Rodrigo (2019) on road construction PPP in Sri Lanka which found that the public procurement

process was too bureaucratic and opened up an avenue for corrupt transactions by some

dishonest public officials, who normally inflate costs. Their study showed that lack of

transparency on PPP contracts, creating an avenue for corrupt transactions by some dishonest

public officials. Chami (2015) also revealed that it was also clear that there was a positive

64

correlation between funding PPP road projects and procurement procedure, financial

feasibility, funding PPP road projects and project schedules. The findings from this study

reveal that the fundamental justification for adopting PPP would significantly reduce the

upfront costs for the government in providing and maintaining public facilities and that it

allows for improvement in the public facilities and services because PPP encourages

innovation by the private sector. Where established procurement procedures have not been

followed there may be an opportunity for interested parties such as other disappointed bidders

to challenge the award of the project in the courts. Some countries also have freedom of

information laws that require details of the winning bid be available and so an awarding

authority may be required to disclose any post bid amendments to the contract that have been

made.

However, the study findings contradict with conclusions drawn from India by Nallathiga,

Shaikh, Shaikh, and Sheik (2017) that there was a greater convergence across the different

procurement methods and that there was greater consensus among project stakeholder on the

critical success/ failure factors of road PPP projects. Sobják (2018) further observes that

potential private investors in public-private infrastructure projects in Sub-Saharan Africa do

not regard the tender process as the highest corruption risk. Rather, they are highly concerned

about the transparency environment of the project origination (project appraisal, selection,

design, and budgeting), because misconduct at this initial phase gives leeway for corruption at

later project stages. This therefore concludes that project origination may be more important

than the traditional focus on promoting procurement reform.

5.4 Conclusion

5.4.1 Investor Perception and Participation in PPP Road Projects

The private sector investors in the road sector in Kenya have a weak perception on the viability

of the road PPP projects proposed by the government. In addition, the investors have a low

confidence towards the government’s level of political commitment in carrying out effective

partnering with the private sector in road PPP projects. The investors further perceive that there

are gaps in the adequacy of the existing government policies that are aimed in promoting road

65

PPPs. Despite the acknowledgement that PPP is essentially a new approach to risk allocation

in public road infrastructure development, investors still hold a low perception towards the

current model, resulting in the evidently low participation of the private sector in road PPP

projects.

5.4.2 Institutional Capacity and Participation in PPP Road Projects

The study concludes capacity of the private sector players in the road sector in Kenya is still

low to handle large road infrastructure projects. Such projects typically require highly

specialized technical and project management skills and with huge capital requirements.

Majority of the private sector players in the road sector do not have the internal technical

capacity to plan, negotiate, execute and manage such PPP projects which also run over long

periods, as compared to the traditional government funded projects. The investors also do not

have a dedicated PPP project management team. In addition, one of the biggest hinderances to

investor participation in road PPP projects in Kenya is the financial capacity of the investors,

with a very limited access to funded sources for such ventures locally. Therefore, most PPP

projects are undertaken by foreign based investors leaving locals for sub-contracting

opportunities.

5.4.3 Procurement Practices and Participation in PPP Projects

The study concludes that there was a lack of transparency in the tendering and bidding

processes, which is a major obstacle towards investors’ participation in PPP road projects.

There is poor planning in the contract preparation and negotiation process which is affected by

delays that impedes the successful implementation of the planned PPP projects. Most investors

are of the opinion that the procurement processes are plagued by conflict of interest and that

selection and award of projects is driven by other external issues other than the results of the

open and competitive process. Consequently, there are instances where entities with limited

capacities are awarded tenders and this directly affects value for money for the pursued project.

However, most of the investors agreed that information on the pipeline of PPP projects and

other tender information was easily accessible by all interested parties.

66

5.5 Recommendation

5.5.1 Recommendation for Improvement

5.5.1.1 Investor Perception and Participation in PPP Road Projects

In view of the findings, this study calls for concerted efforts at institutional level to enhance a

common understanding of the PPP concept, create sufficient awareness of PPP prospects

among the private sector investors, and streamline the procedures and legal framework

surrounding PPP projects to boost private investors’ confidence. There is an urgent need to

review existing government policies and regulations on PPP, in particular, the PPP Act and

other current legal obstacles, to bring about an alignment of the interests of the public and

private sector. This should be aimed to result in appropriate risk-reward allocation between the

public sector and potential private investors in PPP projects.

There is also need to carry out early stage assessment of the viability of proposed projects

through a thorough feasibility studies and financial modelling which factors in the long-term

financing implications of a PPP project. This may be done by the government dedicating a

special fund to finance the early stage project viability studies so that only projects that are

considered attractive for partnership with private sector investors are then pushed forward the

next stage of procurement to promote the uptake of such projects by private investors.

Ultimately, there should be clear measures taken by government to support local private

investors in the road sector which will show a strong government commitment to actualize

infrastructure PPP projects. This would best be done by facilitating to close a few pilot projects

with local investors that can act as the blueprint for future road sector PPP projects.

5.5.1.2 Institutional Capacity and Participation in PPP Road Projects

There is need to strengthen the institutional capacity of both the public sector players and

private investors in the road sector for effective PPP implementation. This can be done by

building the financial capacity of potential investors through measures to develop the local

financial markets in the country to boost the ability of financial institutions to fund road PPP

projects. The government may utilize credit enhancement programs for lenders funding PPP

67

projects and may also use legislative measures that promote flexibility of financial markets to

raise funds for such infrastructure projects. This will provide opportunities for the private

investors to engage in PPP at competitive and even subsidized funding cost.

In addition, the technical capacity of local investors may be improved by making it mandatory

for foreign investors in the road infrastructure sector to have minimum percentage of local

content by forming consortia with local partners in bidding for PPP projects. This facilitates

knowledge transfer and the building of technical and project management capacity for local

players in the road sector. Besides this, the government agencies such as the Construction

Authority, KeNHA and other stakeholders should conduct multi-stakeholder seminars and

training workshops on PPP for local private sector.

5.5.1.3 Procurement Practices and Participation in PPP Projects

The procurement practices around road PPP projects should be reviewed to improve

transparency of the bidder selection criteria. This selection criteria should be available to all

interested parties in advance of the bidding process. A critical component of this criteria would

be a cost-benefit analysis report which identifies a public sector comparator for all road PPP

projects which shows the value of an equivalent project undertaken through normal

government funded procurement process so that the investor selection is based on the

additional value brought about by the PPP option. This ensures there is an independent criterion

to assess value-for-money for PPP projects.

The procurement process timeliness including contract negotiations and signoffs of all relevant

government approvals should be enshrined in regulations to avoid unnecessary delays

occasioned by public officials. This allows private investors and public agencies to prepare in

advance and commit resources within the well-planned timelines. In addition, the central

repository on PPP should be kept well updated, timely, and easily accessible to all the

stakeholders. Information on all selected bidders and their qualifications for the project

awarded should also be published in accessible platforms for public scrutiny. This ensures that

there is information symmetry for all interested stakeholders and reduces the chances of

favoritism and conflict of interest in bidder selection.

68

5.5.2 Recommendation for Further Study

The study was limited to road projects under the management of the Kenya National Highway

Authority (KeNHA). It is necessary to conduct other studies that evaluate the uptake of PPP in

urban and rural road projects. Additionally, the county governments in Kenya are also

mandated to undertake PPP projects. It is therefore recommended to assess the effectiveness

of road PPP adoption in various counties across the country. Lastly, a comparative study should

be undertaken in other sub-Saharan Africa countries which have reported success stories in

road PPPs to identify the factors behind their successful experience with PPP funded road

projects.

69

REFERENCES

Adetona, A. (2018). Kenya's PPP deal information: now open to the public. Procurement and

Supply Chain Management, 3(9); 47-54

Agrawal, R. (2010). Successful Delivery of Public Private Partnerships for Infrastructure

Development. International Journal of Public Sector Management, 27(4); 192-205

Akbari, A. & Gholamreza, H. (2019). The effect of critical success factors on project success

in Public-Private Partnership projects: A case study of highway projects in Iran. Transport

Policy, Elsevier, 73(3); 152-161

Alinaitwe, H. & Ayesiga, R. (2018). Success factors for the implementation of public-private

partnerships in the construction industry in Uganda. Strategic Journal of Business &

Change Management, 3(1); 18-29

Amado, M., Ashton, K., Ashton, S., Bostwick, J., Clements, G., Drysdale, J., & Francis, J.,

(2012). Project Management for Instructional Designers. Public Works Management &

Policy, 22(9);321-330

Ameyaw, E. E, & Chan, A. P. (2015) Evaluation and ranking of risk factors in public–private

partnership water supply projects in developing countries using fuzzy synthetic evaluation

approach. Expert Systems Applied 42(12):5102–5116

Anyanzwa, J. & Muchira, N. (2018). Kenya in major policy shift on support for PPPs.

International Journal of Public Policy 5 (2): 179-183

Ary, D., Jacobs, L. C., Sorensen, C., & Razavieh, A. (2010). Introduction to research in

education eight edition. Wadsworth: Cengage Learning.

Aslan, C. & Duarte, D. (2014). How do countries measure, manage, and monitor fiscal risks

generated by public-private partnerships? Chile, Peru, South Africa, Turkey (English).

Policy Research working paper; no. WPS 7041. Washington, DC: World Bank Group.

Bengesi, K.M.., Mwesiga, P., & Mrema, M. (2016). Assessment of Public Private Partnership

70

(PPP) in Transportation Infrastructure in Tanzania: The Way PPP is Understood,

Challenges and the Way Forward. Economic and Social Research Foundation. Transport

Reviews, 35(3); 1091-1102

Bengesi, K.M. (2016). Public Private Partnership in Tanzania's Transportation Infrastructure:

The Way PPP is Understood, Challenges and the way Forward. Economic and Social

Research Foundation, 3(22); 108-125

Berrone, P., Fageda, X. & Lluma, E. (2018). Public-Private Partnership In Latin America: A

Guide For Regional and Local Governments, Development Bank of Latin America, 3(1),

2-44.

Bhargavi, P. (2014). Investors’ Perception Towards Investment. Global Journal of Finance and

Management 6(2); 185-190

Bhatia, S. (2019) Public Sector Finances as Determinants of Private Investment in PPP Projects

– Experiences from Select Countries. Journal of Economics, Management and Trade.

23(6): 1-17,

Bode, V. & Padhi, A. (2016). The Procurement Process. International Journal of Information,

Business and Management, 8(2); 181-187

Bryman, A. (2016). Social Research Methods (5th ed.). London: Oxford University Press.

Budina, N., Polackova, H. & Irwin. B. T. (2017). Public-Private Partnerships in the New EU

Member States Managing Fiscal Risks in the New EU Member States Managing Fiscal

Risks. World Bank Working Paper No. 114.

Burger, P. & Hawkesworth, I. (2016) How to Attain Value for Money: Comparing PPP and

Traditional Infrastructure Public Procurement. International Journal of Public

Administration, 37(8) 506 -513

Carter, L. (2015). Five secrets of success of Sub-Saharan Africa’s first road PPP. International

Journal of Financial Studies, 5(1);1-28,

71

Casady, C., Flannery, D., & Reeves, E. (2019) Understanding PPP Tendering Periods in

Canada: A Duration Analysis, Public Performance & Management Review, 42(6) 1259-

1278,

Chami, N.S. (2015). Factors Influencing Funding of Public Private Partnership Road Projects:

The Case of Infrastructural Development of Thika Road in Kenya. Journal of Project

Management, 17(9); 411-419

Chileshe, N., Njau, C.W., Kibichii, B.P., & Macharia, L.N. (2020) Critical success factors for

Public-Private Partnership (PPP) infrastructure and housing projects in Kenya.

International Journal of Construction Management, 24(9); 3491-3498

Cooper, D. R., & Schindler, P. S. (2014). Business Research Methods. The McGraw− Hill

Companies.

Creswell, J. W., & Poth, C. N. (2016). Qualitative inquiry and research design: Choosing

among five approaches. Sage publications.

Cui, C. Hope, A. & Liu, Y. (2018) Review of studies on the public–private partnerships (PPP)

for infrastructure projects, International Journal of Project Management ·, 30(30); 1-11.

Dabarera, G., Perera, B. & Rodrigo, M. (2019). Suitability of public-private-partnership

procurement method for road projects in Sri Lanka. Built Environment Project and Asset

Management, 9(2); 199-213.

David, M. & Sutton, C. D. (2016). Social Research: The Basics.

De Bettignies, J.-E., & Ross, T. W. (2010). The Economics of Public-Private Partnerships:

Some Theoretical Contributions. Cheltenham; Northampton, MA: Edward Elgar

Publishing Limited.

Debela, Y.G. (2019) Critical success factors (CSFs) of Public–Private Partnership (PPP) Road

Projects in Ethiopia, International Journal of Construction Management, 18(2); 1782-

1791

72

Devkar, G.A., Mahalingam, A. & Kalidindi, N.S. (2013) Competencies and urban Public

Private Partnership projects in India: A case study analysis, Policy and Society, 32(5)

Dey, S., Rahman, S., Dey, M. (2016). Public Private Partnerships: A Study on the Power

Sector of Bangladesh. SIU Journal of Management, 6(2); 181-200

Dolla, T. & Laishram, B. (2019) Factors Affecting Public-Private Partnership Preference in

Indian Municipal Waste Sector, International Journal of Construction Management,

25(1); 349-355

Doni, N. (2007). A Comparison of Alternative Procedures for the Selection of the Private

Partner in PPP Projects. Working Paper UniversitadegliStudi di Firenze.,

Du, J., Wu, H., & Zhu, L. (2018). Research on the participation mode selection of construction

enterprises in PPP projects in Proceedings of Construction Research Congress. Public

Administration Review, 87(21); 1054-1067

Eadie, R., Tonar, L., & Millar, P. (2013). Public Private Partnerships, reevaluating value for

money. International Journal of Procurement Management 6(2):152-169

Eadie, R. (2013) Re-evaluating value for money. International Journal of Financial Studies,

5(1);1-28,

Elika, B. (2013). Complex transportation project management: An in-depth look at process

integration, alternative financing, and sustainability. World Applied Sciences Journal,

35(6); 456-471

Fincham J. E. (2008). Response rates and responsiveness for surveys, standards, and the

Journal. American Journal of Pharmaceutical education, 72(2), 43-55

Fischer, R. (2012) The PPP bidding process, CEA-DIIU. Journal of Public Procurement, 13(4);

221-230

Flor, L. (2018). Using guarantees to drive efficiency gains in road PPPs by reducing costs,

International Journal of Financial Studies, 8(3); 105-122

73

Flynn, M. & Rao, K. (2019) Smart Cities Funding and Financing in Developing Economies,

including South African insights, Developing Economies Review, 4(1); 3-24.

Gibson, H. and Davies, B. (2008). The Impact of Public Private Partnerships on Education: A

Case Study of Sewell Group Plc. and Victoria Dock Primary School. International Journal

of Educational Management, 22(1): 74-89.

Gifford, J., & Transue, M. (2012) OECD Multi-level Governance Studies, Subnational Public-

Private Partnerships. Meeting Infrastructure Challenges. Public Money & Management,

29(3); 166-181

Guest, C. (2019). Advantages and Disadvantages of Census Surveys. Journal of Business

Statistics, 23(5): 91-95

Habets, J. (2010). Incomplete Contracts and Public-Private-Partnerships; A case study of the

Dutch Infrastructure policy. National Contract Management Journal, 48(3) ;721-729

Iqbal, Shahid, Rafiq M. Choudhry, Klaus Holschemacher, Ahsan Ali, and Jolanta

Tamošaitiene. (2015). Risk management in construction projects. Technological and

Economic Development of Economy 21: 65–78.

Jeppesen, J.J. (2013). Procurement of Public-Private Partnerships: Does the procedure matter?

An analysis of public-private partnerships in Denmark and the role of procurement

procedures. Journal of International Business and Politics, 5(5); 201-213

Jooste, S.F. & Scott, R.W. (2009). Organizations Enabling Public Private Partnerships: An

Organization Field Approach. Working Paper. No. 49

Kaldany, R. & Losavio, J. (2019). The world is facing a $15 trillion infrastructure gap by

2040. Here's how to bridge it. [Online] Available:

https://www.weforum.org/agenda/2019/04/infrastructure-gap-heres-how-to-solve-it/

Kamau, P. (2016) Commercial Banks and Economic Infrastructure PPP Projects in Kenya:

Experience and Prospects, KBA Centre for Research on Financial Markets and Policy®

Working Paper Series WPS/01/16

74

Kang, S., Mulaphong, D., Hwang, E. & Chang, C. (2019). Public-private partnerships in

developing countries. International Journal of Public Sector Management, 32(4); 334-351

Khaderi, S., & Aziz A R, (2010) Adoption of PFI in Malaysian public works projects: Are we

ready? CIB World Congress, 2(1) ;1-16

Kisero, J. (2018, May 17). Why PPP Model has not Succeeded Here. The Business Daily

[Online] Available: https://www.businessdailyafrica.com/analysis/columnists/Why-PPP-

model-has-not-succeeded-here/4259356-4567166-14moqcyz/index.html

Klijn, E.-H. (2010). Public-Private Partnerships: Deciphering Meaning, Message and

Phenomenon. Edward Elgar Publishing Limited.

Koen, V., Ole Helby, P., Walter, S., & Murwantara, R. (2014). Policy commitment, legal and

regulatory framework, and institutional support for PPP in international comparison:

Indexing countries' readiness for taking up PPP PDF Logo. Working Papers in Economics

and Finance, L32

Kothari, C.R. & Garg, G. (2014). Research Methodology, Third Edition, New Age

International Publishers, New Delhi

Kovalenko, E. & Akhmetshin, K. (2019) The introduction of new technologies in the

development and production of roads. MATEC Web of Conferences 265, 02015 (2019)

Langaas, M., Odeck, J. &Bjørvig, K. (2015). The Concept of Institutional Capacity Building

and Review of Road Sector Projects. Journal of Facilities Management, 16(2); 355-364

Leigland, J. (2018). Public-Private Partnerships in Developing Countries: The Emerging

Evidence-based Critique. The World Bank Research Observer, 33(1); 103–134

Leiringer, R. (2006). Technological innovation in the context of PPPs: incentives,

opportunities, and actions. Construction Management and Economics, 24(3), 301-308.

[Copyright Taylor & Francis]

Li, B., Akintoye, A., Edwards, P. J., &Hardcastle, C. (2005) “Perceptions of Positive and

75

Negative Factors Influencing the Attractiveness of PPP/PFI Procurement for Construction

Projects in the UK: Findings from a Questionnaire Survey”. Engineering, Construction

and Architectural Management, 12(2): 125-148.

Liang, Y. & Wang, H. (2019). Sustainable Performance Measurements for Public–Private

Partnership Projects: Empirical Evidence from China. Sustainability, MDPI, Open

Access Journal, 11(13);1-15

Lop, N.S., Ismail, K., Isa, M., & Khalil, N. (2017) Factors Affecting the Operational

Performance of Public Private Partnership (PPP) Projects: Cases in Malaysia.

International Journal of Academic Research in Business and Social Sciences, 27(11); 445-

472

Lyovin, B.A. (20120 Innovation in scientific ensuring transport safety. The World of

Transport, 1 (1); 1-5.

Marques, R.C. (2010). How should the private partner be selected in a PPP? Construction

Management and Economics, 27(4); 567-561

Mbego, S. (2019). Government partners private companies to build roads, evade debts.

[Online]Available:https://www.standardmedia.co.ke/business/article/2001322509/gover

nment-partners-private-companies-to-build-roads-evade-debts

Ministry of Finance, Kenya (2018). Public Private Partnerships in Kenya [Online] Available:

http://trademission.kenyagreece.com/wp-content/uploads/Public-Private-Partnership-in-

Kenya.pdf

Mohamed, K. & Mohammad, H. (2018) A Management Framework To Reduce Delays In

Road Construction Projects. Arabian Journal for Science and Engineering 43(4); 1925–

1940

Moszoro, M. W., & Spiller, P. T. (2012). Third-party opportunism and the nature of public

contracts. Policy Paradigm. Policy Studies,35(2); 79-96.

Muasya, N.S. (2014). Implementation of Public Private Partnerships by The Ministry of

76

Transport and Infrastructure in Kenya, International Journal of Project Management,

31(7); 289-301

Mwangasha, J. (2018). Why private investors stay away from State projects, Mega Projects.

International Journal of Public Policy 5(3); 202-220

Mwende, J. (2020). Mega Projects: How cartels disrupt Kenya’s mega projects to make a

killing. [Online] Available: https://www.constructionkenya.com/6926/cartels-disrupt-

kenya-projects/

Nallathiga, R., Shaikh, D., Shaikh, T.F., & Sheik, F. A. (2017) Factors Affecting the

Success/Failure of Road Infrastructure Projects Under PPP in India. Journal of

Construction Engineering and Project Management, 7(4);1-12.

National Treasury (2018) Budget Policy Statement (2018). [Online] Available:

http://www.treasury.go.ke/media-centre/news-updates/436-2018-budget-policy-

statement.html

Ndandiko, C., Ibanda, S.J. (2013). Public Private Partnerships (PPP) Act, 2013

Nelson, R. M. (2018). Multilateral Development Banks: Overview and Issues for Congress.

Congressional Research Service. International Trade and Finance, 5(18); 783-796

Nguyen, A., Mollik, A., & Chih, Y. (2018). (2018) Government investment in PPP. Journal of

Construction Engineering and Management, 23(14); 567-577

Nifula, A. K., (2009). Conceptual Issues in Defining Public Private Partnerships (PPPs).

International Review of Business Research Papers; 6(2); 150 -163

Norton Rose Fulbright (2019). Basic principles of procurement. [Online] Available:

https://www.nortonrosefulbright.com/en/knowledge/events/60cbc108/basic-principles-

of-procurement

Nurazwa, A. & Halim, H. (2019). The Relationship between Technological Capability and

Manufacturing Performance. International Journal of Recent Technology and

77

Engineering, 7(6);432-438

Nyabira, B. (2019). The long journey towards a favourable PPP framework in Kenya [Online]

Available:http://www.ikm.co.ke/news/articles/2019/The-long-journey-towards-a-

favourable-PPP-framework-in-Kenya.html

Ojebode, A.J. (2016). Public-Private Partnership (PPP) as a Mechanism for the Provision of

Affordable Housing Delivery in Nigeria. Engineering, Construction and Architectural

Management, 22(2) ;401-411

Olotch, C. (2017). Public-Private Partnerships: How does Kenya fare? [Online] Available:

https://blogs.worldbank.org/ppps/public-private-partnerships-how-does-kenya-fare

Osei-Kyei R, Dansoh A, Ofori-Kuragu JK (2014). Reasons for adopting public–private

partnership (PPP) for construction projects in Ghana. International Journal of

Construction Management, 14(4):227–238.

Osei-Kyei, R, & Chan, A.P.C (2016). Implementing public- private partnership (PPP) policy

for public construction projects in Ghana: critical success factors and policy implications.

International journal of construction management, 31(4); 592-597

Osei-Kyei, R, & Chan A. P. C (2017). Implementation constraints in public-private

partnership: empirical comparison between developing and developed countries. Journal

of Facility Management 15(1) 356-361

Osei-Kyei1, R., Chan, A.P.C., & Ayirebi, D. (2017). Public-Private Partnership in Ghana.

Otairua, A., Umar, N. & Zawawi, A. (2014). Slow Adoption of PPPs in Developing Countries:

Survey of Nigerian Construction Professionals. Procedia Engineering, 77(10), 188-195

Owino, S. (2020). It will take 10 years, Sh650bn to finish ongoing road projects [Online]

Available:https://www.nation.co.ke/news/10-years-Sh650bn-to-complete-road-

projects/1056-5482496-140xtg3/index.html

Palcic, D., Palcic, D., & Reeves, E. (2019). Public-Private Partnership Tendering Periods: An

78

International Comparative Analysis. Journal of Strategic Property Management, 1(4) 1-9

Parker, D., & Figueira, C. (2010). PPPs in developed and developing economies: what lessons

can be learned? Northampton, MA: Edward Elgar Publishing Limited.

Patil, S.K., Gupta, A.K., Desai, D. B. & Sajane, A.S. (2014). Time Performance of Different

Types of Construction Projects. Journal of Public Participation, 6(1); 391-400

Pelphrey, M. (2015). Directing the ERP Implementation. A Best Practice Guide to Avoiding

Program Failure Traps While Tuning System Performance. Series on Resource

Management, London, CRC Press.

Polit, D.F. &Hungler, B.P. (2013). Essentials of Nursing Research: Methods, Appraisal, and

Utilization (8th Edition ed.). Philadelphia: Wolters Kluwer/Lippincott Williams and

Wilkins

PPP Unit (2018). Post-procurement PPP Projects. [Online] Available:

http://portal.pppunit.go.ke/project-info/stage/Post-procurement

Proctor, R.W. (2005). Methodology is more than research design and technology. Behavior

Research Methods (2005) 37(2); 197–201

Quintana, L. (2017). Implementing a Successful Public-Private Partnership: Leveraging

Technology and Innovation. Corporate Social Responsibility, 16(4); 339-445

Raisbeck, P., Duffield, C., & Xu, M. (2010). Comparative Performance of PPPs and

Traditional Procurement in Australia. Construction Management and Economics 28(2):

345-359.

Rajan, T. A., Gopinath, G. & Behere, M. (2014). PPPs and Project overruns: Evidence from

Road Projects in India. Journal of Construction Engineering and Management 68(140):

267-279,

Regan, M. (2005). Capital Markets, Infrastructure Investment and Growth in the Asia Pacific

Region. Review, 17(2); 489-497

79

Reichert, F. & Zawislak, P. (2014) Technology Capability and Firm Performance. Journal of

Technology Management & Innovation.9(4); 121-130

Roopa, S. & Satya, R. (2012). Questionnaire Designing for a Survey. The Journal of Indian

Orthodontic Society 46(4):37-41

Ruiz-Nunez, F. & Clive, H, (2016). The State of PPPs: Infrastructure Public-Private

Partnerships in Emerging Markets and Developing Economies 1991-2015. World Bank

Group and PPIAF. Working Paper No. 108

Sanni, A.O. (2016). Factors determining the success of public private partnership projects in

Nigeria. Construction Economics and Building, 16(2), 42-55

Saruchera, F. & Phiri, M.A. (2016). Technological Innovations Performance And Public-

Private-partnerships. Corporate Ownership & Control; 13(4);549-557

Sarvari, H., Valipour, A., & Yahya, N. (2019), Approaches to Risk Identification in Public–

Private Partnership Projects: Malaysian Private Partners’ Overview. Administrative

Sciences, 9(17);1-18

Saunders, M., Lewis, P., & Thornhill, A. (2019). Research Methods for Business Students"

Chapter 4: Understanding research philosophy and approaches to theory development.

8th ed. Harlow. Pearson Education Limited

Seboru, M.A. (2015) An Investigation into Factors Causing Delays in Road Construction

Projects in Kenya. American Journal of Civil Engineering. 3(3); 51-63.

Semple, A. & Turley, L. (2013). Public-private partnerships health check: Managing

partnerships during their lifetime. Winnipeg, MB: IISD.

Semple, A. & Turley, L. (2013). Public-private partnerships health check: Managing

partnerships during their lifetime. International Journal of Public Sector Management,

28(14); 216-234

Serido, J., Shim, S., & Tang, C. (2013). A developmental model of financial capability.

80

International Journal of Behavioral Development 37(4):287-297

Service Works Global (2019). New International Survey Reveals Trends in Operational PPP

Projects. [Online] Available: https://www.swg.com/new-survey-reveals-trends-ppp-

projects/

Sobják, A. (2018). Corruption Risks in Infrastructure Investments in Sub-Saharan Africa

Anita. 2018 OECD Global Anti-Corruption & Integrity Forum, 3(15);1-14.

Song, J., Song, D., Zhang, X. & Sun, Y. (2013). “Risk identification for PPP waste-to-energy

incineration projects in China,” Energy Policy, 61(2); 953–962,

Soomro, M.A. & Zhang. X. (2019) Failure Links between Public and Private Sector Partners

in Transportation Public Private Partnerships. Journal of Traffic and Logistics

Engineering, 1(1); 2-6

Srivastava, A. (2014). Village Road Construction. Journal of the Eastern Asia Society for

Transportation Studies, 6(2); 1313 – 1328

Subaizah, F. & Azzahra, H. (2014). Challenges in Implementing Public Private Partnership

(PPP) in Malaysia. Procedia - Social and Behavioral Sciences, 164(31); 5-10

Takim, R., Kharizamand R. & Rahman, R. (2009). The acceptability of PFI Scheme in

Malaysia. Asian Social Science. 4 (12), pp 71-82, 2009

Thiago, F.M., Thiago L.S. (2019). The Public-Private Partnership. Law Review, 5,1; 1-3

Thuo, D. (2018). Public Private Partnerships Model in Kenya: Opportunities and Challenges.

Construction Management and Economics, 27(5); 516-531

Trochim, W. M. (2020). Research Methods Knowledge Base. [Online] Available:

https://conjointly.com/kb/descriptive-statistics/

United Nations Commission On International Trade Law (2016) UNCITRAL Model Law on

Procurement of Goods, Construction and Services with Guide to Enactment. [Online]

Available:https://www.uncitral.org/pdf/english/texts/procurem/ml-procurement/ml-

81

procure.pdf

Van Nguyen, H. (2017) Making Public-Private Partnerships In Infrastructure Successful In

Vietnam: A Need For A Better Procurement Legal Mechanism. Journal of Construction

Management, 8(22); 811-820

Vimlesh, P. & Nandkishor, S. (2018) Critical Success Factors of Public-Private Partnership for

Road Sector Development in India: A Private Sector Perspective. IUP Journal of Business

Strategy, 5(21); 821-827

Vutsova, A. (2014). The role of public-private partnership for effective technology transfer.

ATI - Applied Technologies & Innovations, 10(3); 83-90

Wanzala, O. (2019). Budget Shortfall Risks Stalling Road Projects. [Online] Available:

https://www.nation.co.ke/news/Budget-shortfall-risks-stalling-road-projects/1056-

4943716-gwima/index.html

Węgrzyn, J. (2016). The Perception of Critical Success Factors for PPP Projects in Different

Stakeholder Groups. Entrepreneurial Business and Economics Review, 4(2), 81-92,

World Bank, (2017). Procuring Infrastructure Public-Private Partnerships (PPPs) 2017

[Online] Available: http://bpp.worldbank.org/

World Bank, (2016). Government Objectives: Benefits and Risks of PPPs [Online] Available:

https://ppp.worldbank.org/public-private-partnership/overview/ppp-objectives

World Bank, (2018). Procuring Infrastructure Public-Private Partnerships (PPPs) 2018

[Online] Available: http://bpp.worldbank.org/

Xiong, Z., Wang, H., Chen, B. & Zhu, D. (2018). Governing public–private partnerships: A

systematic review of case study literature. Australian Journal of Public Administration,

1(4);1-16.

Yamane, T. (1973). Statistics: an introductory analysis. New York: Harper & Row.

Ye, X. Shi, S., Chong, H. & Fu, X. (2018). Empirical Analysis of Firms’ Willingness to

82

Participate in Infrastructure PPP Projects. Journal of Construction Engineering and

Management, 144(1);498-506

Zawawi, M, Kulatunga, U, & Thayaparan, M. 2017, 'Malaysian experience with Public Private

Partnerships (PPP) – managing unsolicited proposals’, Built Environment Project and

Asset Management, 6 (5), 508-520

Zhu , L. & Chua, D. (2018). Identifying Critical Bankability Criteria for PPP Projects: The

Case of China. Advanced Management in Civil Engineering Projects, 11(2); 235-246

83

APPENDICES

84

Appendix I: Questionnaire

SECTION I: DEMOGRAPHIC FACTORS

Kindly fill out your company information in the spaces below. Please tick only one response

for each question.

1. Age of the company (Years): Less Than 5 [ ] 6-10 [ ] 11-15 [ ] 16-20 [ ] Above 20 [ ]

2. Number of Employees: Less than 30 [ ] 30-59 [ ] 60- 89 [ ] more than 90 [ ]

3. Scope of company’s operations: Kenya [ ] East Africa [ ] Africa [ ] Global [ ]

4. Road Project Category: International Trunk (A) [ ] National (B1, B3, & B8) [ ]

Primary (C) [ ] Secondary (D) [ ] Special Purpose Roads [ ] Other [ ]

5. Source of Financing: Local Market [ ] Regional Market [ ] International market [ ]

6. Form of financing: Equity [ ] Debt [ ] Equity & Debt [ ]

7. Major Lender: Commercial Banks [ ] Development Banks [ ] Pension Funds [ ]

Insurance Companies [ ] Other [ ]

SECTION II: INVESTOR PERCEPTION AND PARTICIPATION IN THE PUBLIC

PRIVATE PARTNERSHIP

Indicate the extent to which your perception of each of the factors below affected your decision

to participate or not to participate in the PPP road projects. Use a scale of 1-5, where 1 =

very low extent, 2 = low extent, 3 = neutral, 4 = great extent, 5 = very great extent.

85

Project Financial Viability

FV1 Risk allocation on PPP road projects is done in a more

appropriate manner.

1 2 3 4 5

FV2 The PPP road project parties provide for detailed

cost/benefits assessment

1 2 3 4 5

FV3 The capital market including banking institutions has

remained open to investment.

1 2 3 4 5

FV4 If the perceived political risks increase, the expected

Internal Rate of Return (IRR) will increase.

1 2 3 4 5

FV5 The PPP road projects reflect achievement for Value for

Money (VFM) to both the public and the private partner.

1 2 3 4 5

Political Commitment

PC1 The government has been proactive in compensating

landowners and communities within the project vicinity.

1 2 3 4 5

PC2 The government is less clear on its position in the

implementation of the PPP road projects.

1 2 3 4 5

PC3 The political regimes have remained stable for the last ten

years.

1 2 3 4 5

PC4 The state/county provides for sound guarantees towards all

PPP road projects.

1 2 3 4 5

PC5 The government is actively involved in the project life

cycle.

1 2 3 4 5

Government Policy

GP1 There is weak sectorial public bidding legation, all PPP road

projects are anchored on the 2013 PPP Act.

1 2 3 4 5

GP2 There is strong sectorial public bidding legislation in all the

PPP road projects.

1 2 3 4 5

86

GP3 All the contract bidding procedures in PPP road projects are

standardized.

1 2 3 4 5

GP4 The 2013 PPP Act is clear on government’s position and its

objectives.

1 2 3 4 5

GP5 With the appropriate support mechanisms in place,

The 2013 has made it easier for public-private collaboration

in road projects.

1 2 3 4 5

SECTION III: INSTITUTIONAL CAPACITY AND PARTICIPATION IN THE

PUBLIC PRIVATE PARTNERSHIP

Indicate the extent to which each of the following aspects of institutional capacity affected

your decision to participate or not to participate in the PPP road projects. Use a scale of 1-5,

where 1 = very low extent, 2 = low extent, 3 = neutral, 4 = great extent, 5 = very great

extent.

Investor Expertise

IE1 The organization has a fully equipped PPP unit. 1 2 3 4 5

EI2 The organization is yet to establish a PPP unit. 1 2 3 4 5

EI3 The current public governance permits proper coordination

among concerned road project PPP entities.

1 2 3 4 5

EI4 The organization depends on external consultants for

technical capacity involving PPP road projects.

1 2 3 4 5

EI5 The organization has invested in experienced and highly

technical expertise to undertake PPP projects.

1 2 3 4 5

87

Financial Capability

FC1 The borrowing rate in the financial market is sustainable in

undertaking PPP road projects.

1 2 3 4 5

FC2 Non-availability of affordable debt in the market makes it

difficult to implement PPP road projects.

1 2 3 4 5

FC3 If the perceived political risks increase, the insurance

premium will increase.

1 2 3 4 5

FC4 Availability of budget plan enables the private partner

to have better control of cost overruns

1 2 3 4 5

FC5 The firm can access funding from foreign markets for PPP

road projects.

1 2 3 4 5

Technological Capability

TC1 All our financial statements regarding PPP road projects are

published online through a working website platform.

1 2 3 4 5

TC2 All the necessary technological equipment are available

locally

1 2 3 4 5

TC3 At times we are compelled to import special equipment for

high quality road construction.

1 2 3 4 5

TC4 The firm leverages on technology to facilitate knowledge

sharing among PPP road project stakeholders

1 2 3 4 5

TC5 The firm relies on technology to make appropriate geometric

design for roads that suit client needs.

1 2 3 4 5

88

SECTION IV: PROCUREMENT PRACTICES AND PARTICIPATION IN THE

PUBLIC PRIVATE PARTNERSHIP

Indicate the extent to which each of the following aspects of the procurement practices affected

your decision to participate or not to participate in the PPP road projects. Use a scale of 1-5,

where 1 = very low extent, 2 = low extent, 3 = neutral, 4 = great extent, 5 = very great

extent.

Tendering Practices

TP1 I have high confidence in the tender evaluation process. 1 2 3 4 5

TP2 I have little confidence in the tender evaluation process. 1 2 3 4 5

TP3 Partner bidding process is transparent to all the

stakeholders.

1 2 3 4 5

TP4 There are some opaque practices in the partner bidding

selection.

1 2 3 4 5

TP5 Main information regarding tender advertisement is made

public through publications and online platforms.

1 2 3 4 5

Bidder Selection

BS1 Bidder selection is solely dependent on competitive

exercise.

1 2 3 4 5

BS2 Single sourcing is rampant in the PPP projects. 1 2 3 4 5

BS3 Instances of bribery are less prevalent during partner

selection.

1 2 3 4 5

BS4 Subversion of due process in the award and execution of

PPP road projects.

1 2 3 4 5

BS5 Conflict of interest often arises during bidder selection. 1 2 3 4 5

89

Contractual Negotiation

CN1 All contracts are made public to the parties of interest. 1 2 3 4 5

CN2 Contracts are only restricted to the government and the

selected bidder.

1 2 3 4 5

CN3 There is room for renegotiation of PPP road projects. 1 2 3 4 5

CN4 Contractual terms are less explicit and some of the

information needs further elaboration.

1 2 3 4 5

CN5 Terms relating to payment mechanisms and distribution of

risks/benefits are well elaborated.

1 2 3 4 5

SECTION V: LEVEL OF INVESTOR PARTICIPATION IN PPP

Indicate the extent to which you agree with the following aspects of the level of participation

and the success of the PPP road projects in Kenya. Use a scale of 1-5, where 1 = very low

extent, 2 = low extent, 3 = neutral, 4 = great extent, 5 = very great extent.

Investor Participation in PPP

IP1 Road Projects’ are a true reflection of value for money 1 2 3 4 5

IP2 The satisfaction level of the public towards completed PPP

road projects is encouraging

1 2 3 4 5

IP3 The progress completion rate for the PPP road projects is

high.

1 2 3 4 5

IP4 The qualified rate of road project quality is high. 1 2 3 4 5

IP5 The investment profit rate is motivating. 1 2 3 4 5

90

Appendix II: NACOSTI Research License

91

Appendix III: USIU Research Letter

92

Appendix IV: Letter of Introduction

Date

Address

Dear Respondent,

RE: Research Questionnaire

I am a student at the United States International University Africa (USIU-Africa) pursuing a

Master of Business Administration degree. As part of the course work, I am conducting a

research titled “Factors Affecting Investors’ Participation in Road Infrastructure through

Public Private Partnership Framework in Kenya”.

As an organization that is involved in the road construction sector, the findings of this research

will be of interest to your organization and would help enhance the organization’s future

involvement in road sector PPP projects. Your voluntary participation in this research will

therefore go a long way in helping this outcome.

In this regard, kindly take a few minutes to complete the attached questionnaire with accurate

information that will be used solely for this research while observing utmost confidentiality.

The findings of the study will be also be shared with your organization at the end of the

research.

Your assistance is in this project is highly valued and appreciated.

Yours faithfully,

Ali Idris

Research Student

93

Appendix V: List of Road Projects

Project Title Length (Km) Project Value

1 Magumu - Njambini Road 22 820,320,126

2 Rumuruti - Mararal Road (phase I) 35 3,989,211,846

3 Londiani-Fort Tenan-Muhoroni Road 63 5,468,960,786

4 Maumau - Ruambwa - Nyadorera - Siaya

Road 31 2,596,902,092

5 Mbita cause way Bridge 1 1,065,976,165

6 Kehancha-Suna - Masara Road 68 5,903,140,601

7 Marsarbit- Turbi Road 122 -

8 Turbi - Moyale Road 121 14,046,896,920

9 Timboroa - Eldoret Road 76 5,434,860,652

10 Athi River - Namanga Road including

Namanga One Stop Border Post 135 9,012,901,788

11 Jn. A109 (Changamwe round about) - Moi

International Airport Access Road & Port

Reitz Road

6 5,897,089,231

12 NCTIP: Rehabilitation of Njoro Turnoff -

Timboroa Road 84 6,077,153,674

13 NCTIP: Rehabiliation of Nyamasaria -

Kisian Road 22 8,140,437,887

14 KTSSP: Rehabilitation Kisumu -

Kakamega Road 47 9,219,020,496

15 KTSSP: Rehabilitation Webuye - Kitale

Road 58 5,908,571,071

16 KTSSP: Rehabilitation MajiyaChumvi -

Bachuma Gate Road 53 5,798,508,016

17 MPARD Package 1: Miritini- Mwache

Road including Kipevu Link Road 10 18,756,435,483

18 Mariakani - Kaloleni - Kilifi Road: Phase I

& II 54 4,203,590,934

19 Thua Bridge 1 652,586,968

20 Sotik - Ndanai Road 20 2,149,591,972

21 Ndanai - Gorgor Road 13 1,100,714,249

22 Enjinja - Bumala Road 37 2,356,506,338

23 Rangala-Siaya-Bondo Road 42 1,793,573,075

24 Homa Bay-Mbita Road 41 4,106,551,858

25 Ndori- Ng'iya&Kogelo Access Road 20 1,532,719,990

26 RodiKopany - Ndhiwa - Karungu Road 50 1,344,076,590

27 Ena-Ishiara - Chiakariga Road 57 3,298,061,109

94

Project Title Length (Km) Project Value

28 Thika - Magumu Road 85 1,304,912,086

29 Lomut - Lokori Road – Design 100 38,541,000

30 Lanet- Ndundori Road 30 1,148,837,797

31 Merille- Marsarbit Road 121 5,793,916,618

32 Mwatate - Taveta Road 99 2,256,667,327

33 Eldoret - Webuye Road 60 2,310,244,146

34 Webuye - Malaba Road 59 2,165,717,280

35 Kapsoit - Sondu Road – Design 34 69,984,300

36 EATTFP: One Stop Border Post at Taveta

Border Crossing-DFID N/A 178,928,335

37 Kitui Turn Off- Mwingi- Garissa Road –

Design 300 141,017,300

38 NCTIP: Rehabiliation of Mau Summit -

Kericho Road (B1) 58 4,668,839,660

39 NCTIP: Rehabiliation of Kericho -

Nyamasaria Road 76 6,968,218,886

40 NCTIP: Rehabiliation of Kisumu-Airport-

Kisian Road 9 3,556,343,009

41 NCTIP: Rehabiliation of Machakos

Turnoff - JKIA Road 33 2,743,293,266

42 Kisian -Busia Road – Design 95 98,670,227

43 Modika - Nuno Road (phase II) 12 1,491,606,238

44 LAPSSET Garissa-Isiolo Road – Design 263 29,411,434

45 LAPSSET Lamu - Garissa Road – Design 305 35,346,101

46 Ndori-Owimbi 22 700,002,484

47 Owimbi - Luanda Kotieno 26 1,049,472,915

48 Kisii - Chemosit (C21) 72 465,748,822

49 Emergency Maintenance of Kisumu –

Kakamega N/a 355,433,874

50 Wakor Bridge N/a 172,722,966

51 Wargadud–Bambo 42 659,360,000

52 Ngewa - Kibichoi - Jn D397 (Ichaweri)

(RUIRU) Road – Design 50 55,000,000

53 Nginyang - Lokori - Lokichar Road –

Design 200 74,000,000

54 Stand Khisa-Khumsalaba Road -

EATTFP: Construction of Axle Load

Stations at Mariakani NA 559,669,074

56 EATTFP: Construction of Axle Load

Stations at Athi River N/A 406,578,765

95

Project Title Length (Km) Project Value

57 EATTFP: Busia OBP N/A 293,491,748

58 KTSSP: Mombasa Northern Bypass –

Design 38 -

59 KTSSP: Nakuru-Nyahururu-Nyeri -

Marua– Design 170

NCTIP: NBI URBAN TOLL

CONCESSIONING

60 N/A 120,480,360

61 NCTIP: ASSORTED EQUIPMENT-

MATERIALS DEPARTMENT N/A 67,940,001

62 NCTIP: Rehabiliation of Sultan Hamud -

Machakos Turnoff Road (A109) 55 4,869,594,403

63 NCTIP: Construction of Road Over Rail at

Makutano 2 582,774,315

64 Emergency Restoration of Public Assets at

Kisumu N/A 128,626,629

65 Emergency Restoration of Public Assets

Homa Bay &Oyugis N/A 95,801,364

66 Leseru-Kitale (B2/A1) (Lot No. 1) 60 429,657,181

67 Mariakani–Kilifi 450,000,000

68 Kanyonyo-Embu 108,000,000

69 Mwabungu - Mamba (c108) 50,000,000

70 Ndenderu-Banana-Kanungo 50,000,000

71 Sagana - Kutus-Kianjiru 80,000,000

72 Karen Roundabout 3 695,229,299

73 Muranga-Sagana - Marua (A2) 800,000,000

74 EATTFP: One Stop Border Post at Isebania

Border Crossing N/A 165,938,799

75 Nairobi Southern Bypass 26 10,997,431,030

76 Wajir - Buna –Moyale 205,854,445

77 Chepterit - Baraton University - Kimondi

Road 12 1,779,541,653

78 EATTFP: One Stop Border Post at

Lungalunga Border Crossing N/A 199,170,192

79 Naivasha–Njabini

80 Kangundo-Mwala

81 Road over rail bridge along Mau Summit -

Timboroa Road

82 Dundori-Olkalau-Njambini 614,920

83 Kendu Bay-Homa Bay Road 38

96

Project Title Length (Km) Project Value

84 Nairobi - Thika Highway Improvement

Project Lot 1 & 2 27 15,950,835,648

85 Nairobi - Thika Highway Improvement

Project Lot 3 24 1,439,970,518

86 Emali- Oloitoktok Road 3,589,395,155

87 Isiolo - Merille Road 120 49,472,500

88 Kangema - Gacharage Road 35 4,467,528,083

89 Northern Corridor Rehabilitation-III N/a

90 Moiben - Kapcherop–Kitale

91 Loruk - Barpelo Road 62 6,442,295,046

92 KTSSP: Technical Support Programmes N/a 85,000,000

93 Oljororok - Ndundori Road 35 2,359,865,914

94 Chebilat - Ikonge - Chabera Road 45 3,352,376,396

95 KTSSP: Interchanges at Nyahururu, Njoro,

& Mau Summit Turnoffs N/A 907,212,442

96 Chiakariga - Meru Road 56 5,143,165,666

97 EATTFP: One Stop Border Post at Malaba

Border Crossing N/A 169,811,274

98 Voi - Mwatate - Wundanyi (phase I&II)

Road 45 3,395,448,358

99 Bambo–Rhamu 59 878,898,778

100 KTSSP: Access roads to HQ (Barabara)

and EASA N/A 51,840,000

101 KTSSP: HQ Complex for the Road

subsector Instituitions (Barabara Plaza) 3 4,118,605,891

102 NUTRIP: Capacity building and Technical

Assistance Programme N/a 150,000,000

103 SS-EARTTDFP Capacity building and

Technical Assistance Programme N/a 3,400,000,000

104 Jn A1 (Makutano) - Todonyang Road

(C47) – Design 187 280,000,000

105 Kenol - Muranga - Sagana Road

(C71/C73)– Design 45 164,857,840

106 Support to Road Sector: Capacity Building

Component N/a

107 LAPSSET Isiolo - Nginyang Road –

Design 330 178,198,572

108 KTSSP: Malindi-Madogo-Garissa– Design 330 280,797,868

109 KTSSP: Nakuru-Loruk-Marich Pass –

Design 280 270,533,738

97

Project Title Length (Km) Project Value

110 KTSSP: Lake Victoria Ring Road – Design 450 335,000,552

111 NETIP: Lot 1_Isiolo – Kula Mawe 77 94,510,967

112 NETIP: Lot 2_Kula Mawe–Modogashe 113 74,222,398

113 NETIP: Lot 3_Modogashe –Samatar 90 245,508,411

114 NETIP: Lot 4_Wajir – Wargetut 119 109,988,532

115 NETIP: Lot 6_Wargetut – Elwak 56 101,841,805

116 NETIP: Lot 7_Elwak - Rhamu 142 100,000,000

117 Kutus -Kerugoya -Karatina Road 702,856,828

118 KTSSP: Rehabilitation Kakamega -

Webuye Road 40 4,595,344,294

119 Road Reserves Mapping, protection &

Network Management N/a 550,000,000

120 Development Projects Monitoring and

Evaluation, P&E, Quality Assurance &

Safety Audits

N/a 550,000,000

121 Elwak–Wargadud 60 704,099,750

122 Nuno - Modogashe Road Project 135 8,638,797,574

123 KTSSP: Construction of Kisumu Boys -

Mambo Leo Road 5 3,170,394,481

124 Narok - Sekenani Road (C12) 75 2,214,834,126

125 Installation of Automatic Trafficc counters

and Classifiers and development of

Highway Traffic Database

N/A 585,904,016

126 Kitale -Endebes - Suam Road 45 5,997,717,511

127 Changamwe-Magongo - KwaJomvu

(A109L) Road dualling 4 2,420,327,530

128 Garsen - Witu - Lamu Road(C112) 135 11,006,148,294

129 Dualling of Mombasa –Mariakani 11 10,338,947,803

130 Wei Wei Bridge N/a 500,000,000

131 Mpard Package 3 - Mteza – Kibundani

Section 7 5,000,000,000

132 NUTRIP: James Gichuru junction – Rironi

(Uhuru Highway) (26 km) 26 23,478,371,181

133 KTSSP: DuallingAthi River - Machakos

Turnoff Road 21 10,314,694,165

134 KTSSP: Interchange at KerichoJn B1/C23 N/A 1,007,993,814

135 KTSSP: Interchange at Ahero Turnoff (Jn

A1/B1) N/A 348,072,108

136 SS-EARTTDFP: Upgrading of Kalobeiyei

River — Nadapal (88 km) road section 88 1,690,000,000

98

Project Title Length (Km) Project Value

137 SS-EARTTDFP: Upgrading of Lokitaung

Junction to Kalobeiyei River (80 km) road

section

80 1,750,000,000

138 SS-EARTTDFP: Upgrading of Lokitaung

Junction to Lodwar (80 km) road section 80 1,786,704,730

139 SS-EARTTDFP: Replacement of Kainuk

Bridge N/A 329,260,690

140 SS-EARTTDFP: Upgrading of Lodwar-

Loichangamatak (50 km) road section 50 1,361,992,326

141 Malaba–Busia 28 986,360,266

142 Kitale-Morpus (A1) (Lot No. 2) 65 531,265,894

143 MorpusJunc b4- Marich Pass (A1) (Lot no.

3) 32 308,743,512

144 Marich Pass - Kainuk (KWS Gate) Lot 4 40 526,370,976

145 KWS Gate - Kalemingorok (A1) (lot No. 5) 37 452,860,526

146 Kalemingorok - Lokichar (jn C46/A1) (Lot

No. 6) 33 498,358,098

147 Lokichar (JN A1/C46) - Amosing (C46)

(Lot No. 7) 36 835,779,557

148 Nyaru–Iten 64 2,466,639,639

149 Dhohoye Bridge on Kisian–Usenge N/A 1,200,000,000

150 Ugunja-Ukwala-Ruambwa (C92) 27 1,372,951,628

151 Mau Narok - Kisiriri (B18) 34 1,232,217,429

152 Ruiru – Githunguri - Uplands (C560) 47 4,167,691,617

153 Posta (Naibor) – Kisima–Maralal 65 2,932,425,645

154 Marigat Bridge N/a 950,000,000

155 Endau Bridge N/a 950,000,000

156 Lomut Bridge N/a 500,000,000

157 Dualling of Eldoret Town N/a 18,200,000,000

Isebania - Mukuyu - Kisii - Ahero Road

(A1) Lot 1 & 2

158 170 28,726,650,000

159 Kibwezi - Mutomo - Kitui Road (B7) 192 19,994,154,918

160 MPARD Package 2 - Mwache – Tsunza –

Mteza 9 25,000,000,000

161 Dualling of Nairobi - Nakuru Road (Land

Acquisition) 180 49,250,000,000

162 Kitale - Morpus (KFW) 68

163 Dualling of Mombasa - Nairobi Road

(Land Acquisition) 450 39,100,000,000

164 EXIM: Nairobi Western Bypass 17 19,900,000,000

99

Project Title Length (Km) Project Value

165 Dualling of Nakuru - Mau Summit Road

(Land Acquisition) 175 6,200,000,000

166 Bomas - OngataRongai - Kiserian Road

Dualling– Design 17 100,000,000

167 NUTRIP: Kisumu Northern Bypass Road

(9km) 9 2,245,009,781

168 SS-EARTTDFP: Upgrading of

Loichangamatak - Lokichar (40 km) road

section

40 5,210,000,000

169 Maralal - North Horr Road (C77) – Design 320 103,000,000

170 North Horr - Marsabit Road (C82) –

Design 185 325,000,000

171 Dualling of Mombasa - Mariakani Road

(Lot 2: KwaJomvu - Mariakani) 30 1,000,000,000

172 Eldoret Town Bypass Road 35 11,557,686,237

173 Mombasa Gate Bridge (Likoni Bridge) N/a 500,000,000

174 DuallingMeru Town Roads - (B66/A9) 200,000,000

175 DuallingThika - Kenol - Marua (A2-R) 96 200,000,000

176 Bypass Rds Development Project (Nbi

greater southern, Nbi Western, Aberdare

ranges)

100,000,000

177 NUTRIP: Southern Bypass junction-James

Gichuru road junction (Mombasa road -

Uhuru Highway) (12km)

12 1,174,267,739

178 NUTRIP: JKIA junction-Southern Bypass

junction and ICD Access Roads (Mombasa

Road) (8km)

8 974,267,739

179 Dualling Muthaiga - Kiambu (C32) Design 25 200,000,000

180 Muthaiga - Kiambu - Ngewa Bypass (B30)

Design 62 200,000,000

181 Athi River – Machakos Turnoff Phase 1A 300,000,000

182 Malaba One Stop Border Post 400,000,000

183 Busia One Stop Border Post 400,000,000

184 BRT on Thika Road to KNH

(Superhighway) 8,000,000,000

185 Annuity Programmes 4,000,000,000

186 Construction of 3 interchanges at Nakuru 2,700,000,000

187 JKIA – Likoni Road – James Gichuru 18 65,000,000,000

188 Malindi – Mombasa – Lunga lunga

(B8/A14)-Phase 1: Mombasa-Mtwapa 13 45,000,000,000

100

Project Title Length (Km) Project Value

189 Dualling of Kenol - Sagana –Marua 84 30,000,000,000

190 Upgrading of Loichangamatak – Lokichar

40 50,000,000,000

191 OljoOrok - Dundori (B20) 35 1,900,000,000

192 Mombasa - Mariakani Contract 2: Kwa 30

Jomvu - Mariakani (A8) 28,209,069,850


Recommended