+ All Categories
Home > Documents > 30917947 Reactive Power Compensation Using Capacitor Banks

30917947 Reactive Power Compensation Using Capacitor Banks

Date post: 07-Apr-2018
Category:
Upload: weikotorc
View: 223 times
Download: 0 times
Share this document with a friend

of 82

Transcript
  • 8/6/2019 30917947 Reactive Power Compensation Using Capacitor Banks

    1/82

    INTRODUCTION

    In this chapter we are going to discuss about power system in short and about A.P

    TRANSCO and its role in maintaining power in state from buying and selling the power.

    1.1 INTRODUCTION TO POWER SYSTEM

    Electrical power is a little bit like the air one breathes. One doesn't really think

    about it until it is missing. Power is just "there," meeting ones daily needs, constantly. It

    is only during a power failure, when one walks into a dark room and instinctively hits the

    useless light switch, that one realizes how important power is in our daily life. Without it,

    life can get somewhat cumbersome.

    Electric Energy is the most popular form of energy, because it can be transported

    easily at high efficiency and reasonable cost. The power system of today is a complex

    interconnected network as shown in fig. 1.

    1Figure 1 Power System interconnected

  • 8/6/2019 30917947 Reactive Power Compensation Using Capacitor Banks

    2/82

    A Power System can be subdivided into four major parts:

    i. Generation.

    ii. Transmission and Sub transmission.

    iii. Distribution.

    iv. Loads.

    Power is generated at generating stations, usually located away from the actual

    users. The generated voltage is then stepped up to a higher voltage for transmission,

    as transmission losses are lower at higher voltages. The transmitted electric power is then

    stepped down at grid stations.

    The modern distribution system begins as the primary circuit, leaves the sub-

    station and ends as the secondary service enters the customer's meter socket. First, the

    energy leaves the sub-station in a primary circuit, usually with all three phases.

    The most common type of primary is known as a wye configuration.The wye

    configuration includes 3 phases and a neutral (represented by the center of the "Y".) The

    neutral is grounded both at the substation and at every power pole. The primary and

    secondary (low voltage) neutrals are bonded (connected) together to provide a path to

    blow the primary fuse if any fault occurs that allows primary voltage to enter the

    secondary lines. An example of this type of fault would be a primary phase falling across

    the secondary lines. Another example would be some type of fault in the transformer

    itself.

    The other type of primary configuration is known as delta. This method is older

    and less common. In delta there is only a single voltage, between two phases (phase to

    phase), while in wye there are two voltages, between two phases and between a phase

    and neutral (phase to neutral). Wye primary is safer because if one phase becomes2

  • 8/6/2019 30917947 Reactive Power Compensation Using Capacitor Banks

    3/82

    grounded, that is, makes connection to the ground through a person, tree, or other object,

    it should trip out the fused cutout similar to a household circuit breaker tripping. In delta,

    if a phase makes connection to ground it will continue to function normally. It takes two

    or three phases to make connection to ground before the fused cutouts will open the

    circuit. The voltage for this configuration is usually 4800 volts.

    Transformers are sometimes used to step down from 7200 or 7600 volts to 4800

    volts or to step up from 4800 volts to 7200 or 7600 volts. When the voltage is stepped up,

    a neutral is created by bonding one leg of the 7200/7600 side to ground. This is

    commonly used to power single phase underground services or whole housing

    developments that are built in 4800 volt delta distribution areas. Step downs are used in

    areas that have been upgraded to a 7200/12500Y or 7600/13200Y and the power

    company chooses to leave a section as a 4800 volt setup. Sometimes power companies

    choose to leave sections of a distribution grid as 4800 volts because this setup is less

    likely to trip fuses or reclosers in heavily wooded areas where trees come into contact

    with lines.

    For power to be useful in a home or business, it comes off the transmission grid

    and is stepped-down to the distribution grid. This may happen in several phases. The

    place where the conversion from "transmission" to "distribution" occurs is in a power

    substation. A power substation typically does two or three things:

    i. It has transformers that step transmission voltages down to distribution voltages

    ii. It has a "bus" that can split the distribution power off in multiple directions.

    3

  • 8/6/2019 30917947 Reactive Power Compensation Using Capacitor Banks

    4/82

    iii. It often has circuit breakers and switches so that the substation can be

    disconnected from the transmission grid or separate distribution lines can be

    disconnected from the substation when necessary.

    It often has circuit breakers and switches so that the substation can be

    disconnected from the transmission grid or separate distribution lines can be disconnected

    from the substation when necessary. The primary distribution lines are usually in the

    range of 4 to 34.5 KV and supply load in well defined geographical area. Some small

    industrial customers are served directly by the primary feeders.

    1.3 APTRANSCO

    Government of Andhra Pradesh enacted the AP Electricity REFORMS ACT in

    1998.As a sequel the APSEB was unbundled into Andhra Pradesh Power Generation

    Corporation Limited (APGENCO) & Transmission Corporation of Andhra Pradesh

    Limited (APTRANSCO) on 01.02.99. APTRANSCO was further unbundled w.e.f.

    01.04.2000 into "Transmission Corporation" and four "Distribution Companies"

    (DISCOMS).

    a.)CURRENT ROLE

    From Feb 1999 to June 2005 APTRANSCO remained as Single buyer in the state

    -purchasing power from various Generators and selling it to DISCOMs in accordance

    with the terms and conditions of the individual PPAs at Bulk Supply Tariff (BST) rates.

    Subsequently, in accordance with the Third Transfer Scheme notified by Go AP,

    4

  • 8/6/2019 30917947 Reactive Power Compensation Using Capacitor Banks

    5/82

    APTRANSCO has ceased to do power trading and has retained with powers of

    controlling system operations of Power Transmission.

    1.4 CONCLUSION

    In this chapter we discussed about the power system and role of A.P TRANSCO

    in the state of A.P.

    In next chapter we are going to discuss about the salient features of

    A.PTRANSCO.

    5

  • 8/6/2019 30917947 Reactive Power Compensation Using Capacitor Banks

    6/82

    INTRODUCTION

    In this chapter, we are going to discuss about the salient feature of A.P

    TRANSCO/A.PGENCO/DISCOMS.

    The object of reform and restructure of power sector in the state is to create

    conditions for sustainable development of the sector through promoting competition,

    efficiency, transparency and attracting the much needed private finances into power

    sector. The ultimate goal of the reform program is to ensure that power will be supplied

    under the most efficient conditions in terms of cost and quantity to support the economic

    development of the state and power sector ceases to be a burden on the States budget and

    eventually becomes a net generator of resources.

    A key element of the reform process is that the government will withdraw from

    its earlier role as a regulator of the industry and will be limiting its role to one of policy

    formulation and providing directions.

    In accordance with Reform Policy, the Government of A.P entacted the A.P

    Electricity Reforms Act 1998 and made effective from 1.2.1999. Transmission

    Corporation of A.P Ltd (APTRANSCO and APGENCO) were incorporated under

    Companies Act, 1956. The assets, liabilities and personnel were allocated to these

    companies. Distribution companies have been incorporated under Companies Act as

    subsidiaries to distribution to APTRANSCO and the assets, liabilities and personnel have

    been allocated to distribution companies through notification of a second transfer scheme

    by the Govt. on 31.3.2000.

    The Government of A.P established the A.P Electricity Regulatory Commission

    (APERC) as per the provision of the act and the Commission started functioning from

    3.4.1999. Regular licenses have been issued to APTRANSCO by APERC for

    Transmission and Bulk supply and Distribution and Retail supply from 31.1.2000. The

    commission has been issuing yearly Tariff orders since then based on Annual Revenue

    Requirement (ARR) and tariff proposals of these companies.

    6

  • 8/6/2019 30917947 Reactive Power Compensation Using Capacitor Banks

    7/82

    2.2 SALIENT FEATURES OF A.P TRANSCO/A.PGENCO/DISCOMS

    Table 2.2 (a) features of A.P power system

    PARAMETER UNITS 2008-09

    (UPTO

    MARCH

    09)

    31.03.09

    (PROVL)

    2009-10

    (UPTO

    MARCH

    10)

    31.03.10

    (PROVL)

    Energy generated (cumulative) MU - - -

    1. Thermal MU - 23325.67 - 24180.38

    2. Hydel MU - 7785 - 5510.46

    3. Wind MU - - - -

    Total MU - 31110.67 - 29690.84

    Energy purchased and imported

    (includingothers energy handled)

    MU - 36511.56 - 45075.68

    Energy available for use (2+3) MU - 67622.23 - 74766.52

    Maximum demand during the year

    (at generation terminal) MW

    ME - 9997

    (27-03-

    2009)

    - 10880

    (21-03-2010)

    PercpaitaConsumption (includes

    captive generation)

    KWH - 746 - -

    APTRANSCO LINE (EHT) - - - - -

    400kv CKM 21.44 3008.20 24 3032.79

    220kv CKM 265.88 1250.25 19068 12693.18

    132kv CKM 233.02 14938.57 164.88 15103.45

    DISCOMS Lines # - - - - -

    33kv Km 1421.78 38628 1230 39858

    11kv Km 19521.82 248670 10596 259266

    LT km 10166.53 527852 4212 532064

    TOTAL - 26630.14 845599.15 6418.17 862017.32

    Table 2.2 (b) load generation and sharing of A.P with other state

    7

  • 8/6/2019 30917947 Reactive Power Compensation Using Capacitor Banks

    8/82

  • 8/6/2019 30917947 Reactive Power Compensation Using Capacitor Banks

    9/82

    2.3 CONCLUSION

    In this chapter, we discussed about the salient features of

    A.PTRANSCO / A.PGENCO / DISCOMS.

    In next chapter we are going to discuss about the need for compensation and types

    of compensations used.

    3.1 INTRODUCTION

    In this chapter, reactive power compensation, mainly in transmission systems

    installed at substations is discussed. Reactive power compensation in power systems can

    be either shunt or series.

    Except in a very few special situations, electrical energy is generated, transmitted,

    distributed, and utilized as alternating current (AC). However, alternating current has

    several distinct disadvantages. One of these is the necessity of reactive power that needs

    to be supplied along with active power. Reactive power can be leading or lagging. While

    it is the active power that contributes to the energy consumed, or transmitted, reactive

    power does not contribute to the energy. Reactive power is an inherent part of the total

    9

  • 8/6/2019 30917947 Reactive Power Compensation Using Capacitor Banks

    10/82

    power. Reactive power is either generated or consumed in almost every component of

    the system, generation, transmission, and distribution and eventually by the loads. The

    impedance of a branch of a circuit in an AC system consists of two components,

    resistance and reactance. Reactance can be either inductive or capacitive, which

    contribute to reactive power in the circuit. Most of the loads are inductive, and must be

    supplied with lagging reactive power. It is economical to supply this reactive power

    closer to the load in the distribution system.

    3.2 TYPES OF COMPENSATION

    Shunt and series reactive compensation using capacitors has been 3 widely

    recognized and powerful methods to combat the problems of voltage drops, power losses,

    and voltage flicker in power distribution networks. The importance of compensation

    schemes has gone up in recent years due to the increased awareness on energy

    conservation and quality of supply on the part of the Power Utility as well as power

    consumers. This amplifies on the advantages that accrue from using shunt and series

    capacitor compensation. It also tries to answer the twin questions of how much to

    compensate and where to locate the compensation capacitors.

    i.) SHUNT CAPACITOR COMPENSATION

    Since most loads are inductive and consume lagging reactive power, the

    compensation required is usually supplied by leading reactive power. Shunt

    compensation of reactive power can be employed either at load level, substation level, or

    at transmission level. It can be capacitive (leading) or inductive (lagging) reactive power,

    10

  • 8/6/2019 30917947 Reactive Power Compensation Using Capacitor Banks

    11/82

    although in most cases as explained before, compensation is capacitive. The most

    common form of leading reactive power compensation is by connecting shunt capacitors

    to the line.

    Fig. 3.2(i) represents an A.C generator supplying a load through a line of series

    impedance (R+jX) ohms, fig.3.2(ii) shows the phasor diagram when the line is delivering

    a complex power of (P+jQ) VA and Fig. 3.2(iii) shows the phasor diagram when the line

    is delivering a complex power of (P+jO) VA i.e. with the load fully compensated. A

    thorough examination of these phasor diagrams will reveal the following facts which are

    higher by a factor of2

    Cos

    1

    compared to the minimum power loss attainable in the

    system.

    11

  • 8/6/2019 30917947 Reactive Power Compensation Using Capacitor Banks

    12/82

    Figure 3.2 (i) represents an A.C generator supplying a load through a line of

    series.

    Figure.3.2 (ii) shows the phasor diagram when the line is delivering a complex

    power of (P+jQ)

    Figure. 3.2 (iii) shows the phasor diagram when the line is delivering a complex

    power of (P+jQ)

    The loading on generator, transformers, line etc is decided by the current flow.

    i. The higher current flow in the case of uncompensated load necessitated by the

    reactive demand results in a tie up of capacity in this equipment by a factor of

    12

  • 8/6/2019 30917947 Reactive Power Compensation Using Capacitor Banks

    13/82

    Cos

    1i.e. compensating the load to UPF will release a capacity of (load VA

    rating X Cos ) in all these equipment.

    ii. The sending-end voltage to be maintained for a specified receiving-end voltage is

    higher in the case of uncompensated load. The line has bad regulation with

    uncompensated load.

    iii. The sending-end power factor is less in the case of an uncompensated one. This is

    due to the higher reactive absorption taking place in the line reactance.

    iv. The excitation requirements on the generator are severe in the case of

    uncompensated load. Under this condition, the generator is required to maintain a

    higher terminal voltage with a greater current flowing in the armature at a lower

    lagging power factor compared to the situation with the same load fully

    compensated. It is entirely possible that the required excitation is much beyond

    the maximum excitation current capacity of the machine and in that case further

    voltage drop at receiving-end will take place due to the inability of the generator

    to maintain the required sending-end voltage. It is also clear that the increased

    excitation requirement results in considerable increase in losses in the excitation

    system.

    It is abundantly clear from the above that compensating a lagging load by using

    shunt capacitors will result in

    i. Lesser power loss everywhere upto the location of capacitor and hence a more

    efficient system.

    13

  • 8/6/2019 30917947 Reactive Power Compensation Using Capacitor Banks

    14/82

    ii. Releasing of tied-up capacity in all the system equipments thereby enabling a

    postponement of the capital intensive capacity enhancement programs to a later

    date.

    iii. Increased life of equipments due to optimum loading on them.

    iv. Lesser voltage drops in the system and better regulation.

    v. Less strain on the excitation system of generators and lesser excitation losses.

    vi. Increase in the ability of the generators to meet the system peak demand thanks to

    the released capacity and lesser power losses.

    Shunt capacitive compensation delivers maximum benefit when employed right

    across the load. And employing compensation in HT & LT distribution network is the

    closest one can get to the load in a power network. However, various considerations like

    ease of operation end control, economy achievable by lumping shunt compensation at

    EHV stations etc will tend to shift a portion of shunt compensation to EHV & HV

    substations. Power utilities in most countries employ about 60% capacitors on feeders,

    30% capacitors on the substation buses and the remaining 10% on the transmission

    system. Application of capacitors on the LT side is not usually resorted to by the utilities.

    Just as a lagging system power factor is detrimental to the system on various

    counts, a leading system pf is also undesirable. It tends to result in over-voltages, higher

    losses, lesser capacity utilization, and reduced stability margin in the generators. The

    reduced stability margin makes a leading power factor operation of the system much

    more undesirable than the lagging p.f operation. This fact has to be given due to

    14

  • 8/6/2019 30917947 Reactive Power Compensation Using Capacitor Banks

    15/82

    consideration in designing shunt compensation in view of changing reactive load levels in

    a power network.

    Shunt compensation is successful in reducing voltage drop and power loss

    problems in the network under steady load conditions. But the voltage dips produced by

    DOL starting of large motors, motors driving sharply fluctuating or periodically varying

    loads, arc furnaces, welding units etc can not be improved by shunt capacitors since it

    would require a rapidly varying compensation level. The voltage dips, especially in the

    case of a low short circuit capacity system can result in annoying lamp-flicker, dropping

    out of motor contactors due to U/V pick up, stalling of loaded motors etc. and fixed or

    switched shunt capacitors are powerless against these voltage dips. But thyristor

    controlled Static VAR compensators with a fast response will be able to alleviate the

    voltage dip problem effectively.

    a.) SHUNT CAPACITORS

    Shunt capacitors are employed at substation level for the following reasons:

    i. Voltage regulation: The main reason that shunt capacitors are installed at

    substations is to control the voltage within required levels. Load varies over the

    day, with very low load from midnight to early morning and peak values

    occurring in the evening between 4 PM and 7 PM. Shape of the load curve also

    varies from weekday to weekend, with weekend load typically low. As the load

    varies, voltage at the substation bus and at the load bus varies. Since the load

    power factor is always lagging, a shunt connected capacitor bank at the substation

    15

  • 8/6/2019 30917947 Reactive Power Compensation Using Capacitor Banks

    16/82

    can raise voltage when the load is high. The shunt capacitor banks can be

    permanently connected to the bus (fixed capacitor bank) or can be switched as

    needed. Switching can be based on time, if load variation is predictable, or can be

    based on voltage, power factor, or line current.

    ii. Reducing power losses: Compensating the load lagging power factor with the

    bus connected shunt capacitor bank improves the power factor and reduces

    current flow through the transmission lines, transformers, generators, etc. This

    will reduce power losses (I2R losses) in this equipment.

    iii. Increased utilization of equipment: Shunt compensation with capacitor banks

    reduces KVA loading of lines, transformers, and generators, which means with

    compensation they can be used for delivering more power without overloading

    the equipment.

    Reactive power compensation in a power system is of two typesshunt and series.

    Shunt compensation can be installed near the load, in a distribution substation, along the

    distribution feeder, or in a transmission substation. Each application has different

    purposes. Shunt reactive compensation can be inductive or capacitive. At load level, at

    the distribution substation, and along the distribution feeder, compensation is usually

    capacitive. In a transmission substation, both inductive and capacitve reactive

    compensation are installed.

    b.) SHUNT CAPACITOR INSTALLATION TYPES:

    16

  • 8/6/2019 30917947 Reactive Power Compensation Using Capacitor Banks

    17/82

    The capacitor installation types and types of control for switched capacitor are

    best understood by considering a long feeder supplying a concentrated load at feeder end.

    This is usually a valid approximation for some of the city feeders, which emanate from

    substations, located 4 to 8 Kms away from the heart of the city.

    Absolute minimum power loss in this case will result when the concentrated load

    is compensated to up by locating capacitors across the load or nearby on the feeder. But

    the optimum value of compensation can be arrived at only by considering a cost benefit

    analysis.

    Figure 3.2 (iv) long distribution feeder supplying a concentrated load

    It is evident from fig. 3.2 (v) that it will require a continuously variable capacitor

    to keep the compensation at economically optimum level throughout the day. However,

    17

  • 8/6/2019 30917947 Reactive Power Compensation Using Capacitor Banks

    18/82

    this can only be approximated by switched capacitor banks. Usually one fixed capacitor

    and two or three switched units will be employed to match the compensation to the

    reactive demand of the load over a day. The value of fixed capacitor is decided by

    minimum reactive demand as shown in Fig 3.2 (v)

    Figure. 3.2 (v) reactive demand

    Automatic control of switching is required for capacitors located at the load end

    or on the feeder. Automatic switching is done usually by a time switch or voltage

    controlled switch as shown in Fig 3.2(v). The time switch is used to switch on the

    capacitor bank required to meet the day time reactive load and another capacitor bank

    switched on by a low voltage signal during evening peak along with the other two banks

    will maintain the required compensation during night peak hours.

    ii) SERIES CAPACITOR COMPENSATION

    18

  • 8/6/2019 30917947 Reactive Power Compensation Using Capacitor Banks

    19/82

    Shunt compensation essentially reduces the current flow everywhere upto the

    point where capacitors are located and all other advantages follow from this fact. But

    series compensation acts directly on the series reactance of the line. It reduces the transfer

    reactance between supply point and the load and thereby reduces the voltage drop. Series

    capacitor can be thought of as a voltage regulator, which adds a voltage proportional to

    the load current and there by improves the load voltage.

    Figure 3.2 (vi) Aerial view of 500-kV series capacitor installation

    Series compensation is employed in EHV lines to

    i. Improve the power transfer capability

    ii. Improve voltage regulation

    iii. Improve the load sharing between parallel lines.

    19

  • 8/6/2019 30917947 Reactive Power Compensation Using Capacitor Banks

    20/82

    Economic factors along with the possible occurrence of sub-synchronous

    resonance in the system will decide the extent of compensation employed.

    Series capacitors, with their inherent ability to add a voltage proportional to load

    current, will be the ideal solution for handling the voltage dip problem brought about by

    motor starting, arc furnaces, welders etc. And, usually the application of series

    compensation in distribution system is limited to this due to the complex protection

    required for the capacitors and the consequent high cost. Also, some problems like self-

    excitation of motors during starting, ferro resonance, steady hunting of synchronous

    motors etc discourages wide spread use of series compensation in distribution systems.

    3.3 ECONOMIC JUSTIFICATION FOR USE OF CAPACITORS:

    Increase in benefits for 1KVAR of additional compensation decrease rapidly as

    the system power factor reaches close to unity. This fact prompts an economic analysis to

    arrive at the optimum compensation level. Different economic criteria can be used for

    this purpose. The annual financial benefit obtained by using capacitors can be compared

    against the annual equivalent of the total cost involved in the capacitor installation. The

    decision also can be based on the number of years it will take to recover the cost involved

    in the Capacitor installation. A more sophisticated method would be able to calculate the

    present value of future benefits and compare it against the present cost of capacitor

    installation.

    When reactive power is provided only by generators, each system component

    (generators, transformers, transmission and distribution lines, switch gear and protective

    equipment etc) has to be increased in size accordingly. Capacitors reduce losses and

    loading in all these equipments, thereby effecting savings through powerless reduction

    20

  • 8/6/2019 30917947 Reactive Power Compensation Using Capacitor Banks

    21/82

    and increase in generator, line and substation capacity for additional load. Depending on

    the initial power factor, capacitor installations can release at least 30% additional

    capacity in generators, lines and transformers. Also they can increase the distribution

    feeder load capability by about 30% in the case of feeders which were limited by voltage

    drop considerations earlier. Improvement in system voltage profile will usually result in

    increased power consumption thereby enhancing the revenue from energy sales.

    Thus, the following benefits are to be considered in an economic analysis of

    compensation requirements.

    a) Benefits due to released generation capacity.

    b) Benefits due to released transmission capacity.

    c) Benefits due to released distribution substation capacity.

    d) Benefits due to reduced energy loss.

    e) Benefits due to reduced voltage drop.

    f) Benefits due to released feeder capacity.

    g) Financial Benefits due to voltage improvement.

    Capacitors in distribution system will indeed release generation and transmission

    capacities. But when individual distribution feeder compensation is in question, the value

    of released capacities in generation and transmission system is likely to be too small to

    warrant inclusion in economic analysis. Moreover, due to the tightly inter-connected

    nature of the system, the exact benefit due to capacity release in these areas is quite

    difficult to compute. Capacity release in generation and transmission system is probably

    more relevant in compensation studies at transmission and sub-transmission levels and

    21

  • 8/6/2019 30917947 Reactive Power Compensation Using Capacitor Banks

    22/82

    hence are left out from the economic analysis of capacitor application in distribution

    systems.

    a.) BENEFITS DUE TO RELEASED DISTRIBUTION SUBSTATIONCAPACITY:

    The released distribution substation capacity due to installation of capacitors

    which deliver Qc MVARs of compensation at peak load conditions may be shown to be

    equal to

    c2c

    c

    2/1

    2c

    22cc S1

    S

    SinQ

    S

    CosQ1S

    +

    =

    In general and SinQS cc when10

    SQ CC


Recommended