Activity ID Activity Description c y Orig Dur Early Start Early Finish Budgeted Cost 1 LCLS PROJECT - PED & CONSTRUCTION 1.09 CONVENTIONAL FACILITIES 1.09.01 System Management & Integration 1.09.01.01 Management CFMGT_1018 Management - PED (remaining) 107 05/02/05 09/30/05 79,177 CFMGT_1040 Construction Management Consulting - PED 107 05/02/05 09/30/05 109,000 CFMGT_1105 Consumable Supplies - PED (remaining) 107 05/02/05 09/30/05 4,690 CFMGT_1110 Student Research Analyst - PED 107 05/02/05 09/30/05 8,458 CFMGT_1134 Travel - FY05 (remaining) 107 05/02/05 09/30/05 11,466 CF13013210 Independent Cost Estimate (ICE) - 30% Review 40 08/15/05* 10/10/05 100,700 CFMGT_2000 Reproduction - 30% Design 164 08/22/05* 04/28/06 15,900 CF13013100 RY - CLOC Seismic Peer Review 120 09/06/05* 03/13/06 86,504 CFMGT_1230 Geotechnical Baseline Report 130 09/12/05* 03/31/06 117,237 CFMGT_1070 AWARD: Construction Management Consulting - FY06 1 10/03/05 10/03/05 185,500 CFMGT_1020 Management - FY06 242 10/03/05 09/29/06 184,087 CFMGT_1090 Construction Management Consulting - FY06 242 10/03/05 09/29/06 185,500 CFMGT_1100 Consumable Supplies - FY06 242 10/03/05 09/29/06 7,840 CFMGT_1125 Travel - FY06 242 10/03/05 09/29/06 25,400 CF13013220 Independent Cost Estimate (ICE) - 60% Review 40 11/08/05 01/20/06 47,700 CFMGT_2010 Additional ICE - 60% Review 20 01/03/06* 01/31/06 63,600 CF10012010 TCCo Modification - 30% Estimate 5 02/06/06* 02/10/06 53,000 CFMGT_1115 Student Research Analyst - LLP 651 02/06/06* 09/30/08 0 CF13013230 Independent Cost Estimate (ICE) - 90% Review 30 02/21/06 04/03/06 0 FY05 FY06 FY07 FY08 FY09 Management - PED (remaining) Construction Management Consulting - PED Consumable Supplies - PED (remaining) Student Research Analyst - PED Travel - FY05 (remaining) Independent Cost Estimate (ICE) - 30% Review Reproduction - 30% Design RY - CLOC Seismic Peer Review Geotechnical Baseline Report AWARD: Construction Management Consulting - FY06 Management - FY06 Construction Management Consulting - F Consumable Supplies - FY06 Travel - FY06 Independent Cost Estimate (ICE) - 60% Review Additional ICE - 60% Review TCCo Modification - 30% Estimate Student R Independent Cost Estimate (ICE) - 90% Review © Primavera Systems, Inc. Start Date 06/01/01 Finish Date 03/31/09 Data Date 05/02/05 LCLS PROJECT Integrated Master Schedule Conventional Facilities
Transcript
Page 1: Activity cOrig Early Budgeted FY05 FY06 FY07 FY08 FY09 ID ... · CFMGT_1175 CF Controls Liaison FY05Q2-Q4 (remaining) 107 05/02/05* 09/30/05 24,077 CFMGT_1045 Cost Account Managers-Phase

ActivityID

ActivityDescription

cy

OrigDur

EarlyStart

EarlyFinish

BudgetedCost

1 LCLS PROJECT - PED & CONSTRUCTION1.09 CONVENTIONAL FACILITIES1.09.01 System Management & Integration1.09.01.01 ManagementCFMGT_1018 Management - PED (remaining) 107 05/02/05 09/30/05 79,177

CFMGT_1040 Construction Management Consulting - PED 107 05/02/05 09/30/05 109,000

CFMGT_1105 Consumable Supplies - PED (remaining) 107 05/02/05 09/30/05 4,690

CFMGT_1110 Student Research Analyst - PED 107 05/02/05 09/30/05 8,458

CFMGT_1134 Travel - FY05 (remaining) 107 05/02/05 09/30/05 11,466

CF13013210 Independent Cost Estimate (ICE) - 30% Review 40 08/15/05* 10/10/05 100,700

CFMGT_2000 Reproduction - 30% Design 164 08/22/05* 04/28/06 15,900

CF13013100 RY - CLOC Seismic Peer Review 120 09/06/05* 03/13/06 86,504

CFMGT_1230 Geotechnical Baseline Report 130 09/12/05* 03/31/06 117,237

CFMGT_1070 AWARD: Construction Management Consulting -FY06

1 10/03/05 10/03/05 185,500

CFMGT_1020 Management - FY06 242 10/03/05 09/29/06 184,087

CFMGT_1090 Construction Management Consulting - FY06 242 10/03/05 09/29/06 185,500

CFMGT_1100 Consumable Supplies - FY06 242 10/03/05 09/29/06 7,840

CFMGT_1125 Travel - FY06 242 10/03/05 09/29/06 25,400

CF13013220 Independent Cost Estimate (ICE) - 60% Review 40 11/08/05 01/20/06 47,700

CFMGT_2010 Additional ICE - 60% Review 20 01/03/06* 01/31/06 63,600

CF10012010 TCCo Modification - 30% Estimate 5 02/06/06* 02/10/06 53,000

CFMGT_1115 Student Research Analyst - LLP 651 02/06/06* 09/30/08 0

CF13013230 Independent Cost Estimate (ICE) - 90% Review 30 02/21/06 04/03/06 0

FY05 FY06 FY07 FY08 FY09

Management - PED (remaining)

Construction Management Consulting - PED

Consumable Supplies - PED (remaining)

Student Research Analyst - PED

Travel - FY05 (remaining)

Independent Cost Estimate (ICE) - 30% Review

Reproduction - 30% Design

RY - CLOC Seismic Peer Review

Geotechnical Baseline Report

AWARD: Construction Management Consulting - FY06

Management - FY06

Construction Management Consulting - F

Consumable Supplies - FY06

Travel - FY06

Independent Cost Estimate (ICE) - 60% Review

Additional ICE - 60% Review

TCCo Modification - 30% Estimate

Student R

Independent Cost Estimate (ICE) - 90% Review

© Primavera Systems, Inc.

Start Date 06/01/01Finish Date 03/31/09Data Date 05/02/05

LCLS PROJECTIntegrated Master Schedule

Conventional Facilities

Page 2: Activity cOrig Early Budgeted FY05 FY06 FY07 FY08 FY09 ID ... · CFMGT_1175 CF Controls Liaison FY05Q2-Q4 (remaining) 107 05/02/05* 09/30/05 24,077 CFMGT_1045 Cost Account Managers-Phase

Sheet 2 of 28

ActivityID

ActivityDescription

cy

OrigDur

EarlyStart

EarlyFinish

BudgetedCost

1.09.01.01 ManagementCFMGT_2022 CF Management & Integration 40 03/01/06* 04/25/06 68,900

CFMGT_2020 Additional ICE - 100% Review 20 03/02/06 03/29/06 0

CFMGT_2005 Reproduction - 60% and 100% Design 164 03/06/06* 10/24/06 26,500

CFMGT_1330 AWARD: Construction Management Consulting -FY07

1 10/02/06* 10/02/06 185,500

CFMGT_1120 Management - FY07 242 10/02/06 09/28/07 195,888

CFMGT_1145 Travel - FY07 242 10/02/06 09/28/07 26,000

CFMGT_1160 Construction Management Consulting - FY07 242 10/02/06 09/28/07 185,500

CFMGT_1190 Consumable Supplies - FY07 242 10/02/06 09/28/07 8,050

CFMGT_1340 AWARD: Construction Management Consulting -FY08

1 10/01/07* 10/01/07 185,500

CFMGT_1180 Construction Management Consulting - FY08 242 10/01/07 09/29/08 185,500

CFMGT_1155 Travel - FY08 243 10/01/07 09/30/08 26,800

CFMGT_1200 Consumable Supplies - FY08 243 10/01/07 09/30/08 6,594

CFMGT_1130 Management - FY08 and Beyond 362 10/01/07 03/31/09 285,070

CFMGT_LOE CF LOE Complete 0 03/31/09 0

CFMGT_1170 COMP: Conventional Facilities 0 04/01/09 0

1.09.01.02 Cost Account ManagersCFMGT_1051 Cost Account Managers-Phase 2 (remaining) 107 05/02/05 09/30/05 158,354

CFMGT_1175 CF Controls Liaison FY05Q2-Q4 (remaining) 107 05/02/05* 09/30/05 24,077

CFMGT_1045 Cost Account Managers-Phase 2 (add) 86 06/01/05* 09/30/05 63,637

CFMGT_1210 Electrical Engineer - PED 21 09/01/05* 09/30/05 11,100

CFMGT_1050 Cost Account Managers - FY06 242 10/03/05 09/29/06 420,770

CFMGT_1220 Electrical Engineer - FY06 242 10/03/05 09/29/06 190,933

CFMGT_1250 Cost Account Managers - FY07 242 10/02/06 09/28/07 587,664

CFMGT_1270 Electrical Engineer - FY07 242 10/02/06 09/28/07 188,864

FY05 FY06 FY07 FY08 FY09

CF Management & Integration

Additional ICE - 100% Review

Reproduction - 60% and 100% Design

AWARD: Construction Management Cons

Management - FY07

Travel - FY07

Construction Managemen

Consumable Supplies - FY07

AWARD: Construction Ma

Construction Management Consulting - FY08

Travel - FY08

Consumable Supplies - FY08

Management - FY08 and Beyond

CF LOE Complete

COMP: Conventional Facilities

Cost Account Managers-Phase 2 (remaining)

CF Controls Liaison FY05Q2-Q4 (remaining)

Cost Account Managers-Phase 2 (add)

Electrical Engineer - PED

Cost Account Managers - FY06

Electrical Engineer - FY06

Cost Account Managers - FY07

Electrical Engineer - FY07

Sheet 2 of 28

Page 3: Activity cOrig Early Budgeted FY05 FY06 FY07 FY08 FY09 ID ... · CFMGT_1175 CF Controls Liaison FY05Q2-Q4 (remaining) 107 05/02/05* 09/30/05 24,077 CFMGT_1045 Cost Account Managers-Phase

Sheet 3 of 28

ActivityID

ActivityDescription

cy

OrigDur

EarlyStart

EarlyFinish

BudgetedCost

1.09.01.02 Cost Account ManagersCFMGT_1260 Cost Account Managers - FY08 and Beyond 362 10/01/07 03/31/09 855,211

CFMGT_1280 Electrical Engineer - FY08 and Beyond 362 10/01/07 03/31/09 0

1.09.01.03 Construction Management & AE SupportCFMGT_2001 EP Produce Sampling Plan (remaining) 13 05/02/05 05/18/05 3,911

CFMGT_2006 EP Develop Statement of Work (remaining) 13 05/02/05 05/18/05 1,586

CFMGT_2240 A&E Title 1 Reimbursables (cost growth) 20 06/06/05* 07/01/05 56,680

CFMMF_3075 AE Engineering Support Title 3 - MMF 118 08/01/05* 02/01/06 27,720

CFS20_3070 AE Engineering Support Title 3 - Alcove/RF Hut 118 08/01/05* 02/01/06 36,181

CFMGT_2025 Review Bids for EP Site Analysis 5 08/02/05* 08/08/05 2,537

CFMGT_2230 A&E Interim Support (cost growth) 15 08/08/05* 08/26/05 28,340

CFMGT_1500 UTR Support for Construction 87 08/15/05* 12/16/05 23,760

CFMGT_1510 UTR Support for Construction 257 08/15/05* 09/01/06 97,451

CFMGT_1520 UTR Support for Construction 319 08/15/05* 12/01/06 121,457

CFMGT_1076 AWARD: Construction Management Pkg -FY06(LLP)

1 10/17/05* 10/17/05 630,000

CFRYC_2745 Kickoff Meeting - CM/GC 1 10/19/05 10/19/05 0

CFMGT_1077 Phase 1 Construction Management 101 10/21/05 03/31/06 630,000

CFMGT_2030 AWARD: Contract for EP Site Analysis 1 11/14/05* 11/14/05 69,440

CFMGT_1600 Fire Protection Engineer 49 12/05/05* 02/28/06 21,200

CFMGT_1530 UTR Support for Construction 53 01/09/06* 03/24/06 23,038

CFMGT_2035 EP Site Analysis/Site Characterization 80 01/09/06* 05/02/06 69,440

CFMGT_1540 UTR Support for Construction 214 01/09/06* 11/09/06 93,349

CFMGT_1550 UTR Support for Construction 276 01/09/06* 02/26/07 120,998

CFMGT_1084 AWARD: A&E Title 3 Support for RSY-CLOC 1 02/07/06 02/07/06 0

CFMGT_2040 EP Excavated Material Disposition Plan 20 02/22/06 03/21/06 0

FY05 FY06 FY07 FY08 FY09

Cost Account Managers - FY08 and Beyond

Electrical Engineer - FY08 and Beyond

EP Produce Sampling Plan (remaining)

EP Develop Statement of Work (remaining)

A&E Title 1 Reimbursables (cost growth)

AE Engineering Support Title 3 - MMF

AE Engineering Support Title 3 - Alcove/RF Hut

Review Bids for EP Site Analysis

A&E Interim Support (cost growth)

UTR Support for Construction

UTR Support for Construction

UTR Support for Construction

AWARD: Construction Management Pkg - FY06(LLP)

Kickoff Meeting - CM/GC

Phase 1 Construction Management

AWARD: Contract for EP Site Analysis

Fire Protection Engineer

UTR Support for Construction

EP Site Analysis/Site Characterization

UTR Support for Construction

UTR Support for Construction

AWARD: A&E Title 3 Support for RSY-CLOC

EP Excavated Material Disposition Plan

Sheet 3 of 28

Page 4: Activity cOrig Early Budgeted FY05 FY06 FY07 FY08 FY09 ID ... · CFMGT_1175 CF Controls Liaison FY05Q2-Q4 (remaining) 107 05/02/05* 09/30/05 24,077 CFMGT_1045 Cost Account Managers-Phase

Sheet 4 of 28

ActivityID

ActivityDescription

cy

OrigDur

EarlyStart

EarlyFinish

BudgetedCost

1.09.01.03 Construction Management & AE SupportCFBID1560 Start Bid Package Phase 1 0 02/28/06* 0

CF05034005 UTR Support for Construction 193 03/27/06 01/11/07 123,476

CFMGT_1078 AWARD: Construction Management Pkg - FY06 (C) 1 04/03/06* 04/03/06 3,186,846

CFMGT_1087 A&E Support for Title 3 RSY-CLOC 400 04/03/06* 11/12/07 400,628

CFMGT_1088 A&E Title 3 Support for RSY-CLOC (reimbursables) 400 04/03/06* 11/12/07 137,265

CFMGT_1089 A&E Title 3 Support for RSY-CLOC (Mod 2) 400 04/03/06* 11/12/07 114,280

CFMGT_1080 Phase 2 Construction Management + Fee - FY06 127 04/04/06 10/02/06 3,186,846

CFBID2200 Start Bid Package Phase 2 0 04/18/06* 0

CFBID1640 Phase 1 Subcontract Execution 0 05/23/06* 0

CFMOB1000 Commence Sitework 0 05/24/06* 0

CFMOB1040 Mobilization 0 05/24/06* 0

CFMOB1100 SWPP & Site Construction Fencing 0 05/24/06* 0

CFRY102020 Start Research Yard Modifications 0 05/24/06* 0

CFNEH1100 Start Near Experimental Hall 0 07/13/06* 0

CFCLS2000 Start Central Laboratory Office Complex 0 07/17/06* 0

CFCUP1120 Start Central Utility Plant 0 07/17/06* 0

CFBTH2000 Start FFTB Removal 0 07/21/06* 0

CFACC1100 Start Access Tunnel 0 07/25/06* 0

CFBOD2260 Phase 2 Subcontract Execution 0 07/28/06* 0

CFFEE1100 Start Front End Enclosure 0 08/23/06* 0

CFUH01020 Start Undulator Hall 0 08/25/06* 0

CFBD1320 Start Electron Beam Dump 0 09/08/06* 0

CFMGT_1305 AWARD: Phase 2 CM + Fee - FY07 1 10/02/06* 10/02/06 5,180,255

CFMGT_1310 Phase 2 Construction Management + Fee - FY07 242 10/03/06 10/01/07 5,180,255

FY05 FY06 FY07 FY08 FY09

Start Bid Package Phase 1

UTR Support for Construction

AWARD: Construction Management Pkg - FY06 (C

A&E Support for Title 3

A&E Title 3 Support for

A&E Title 3 Support for

Phase 2 Construction Management + Fee

Start Bid Package Phase 2

Phase 1 Subcontract Execution

Commence Sitework

Mobilization

SWPP & Site Construction Fencing

Start Research Yard Modifications

Start Near Experimental Hall

Start Central Laboratory Office Complex

Start Central Utility Plant

Start FFTB Removal

Start Access Tunnel

Phase 2 Subcontract Execution

Start Front End Enclosure

Start Undulator Hall

Start Electron Beam Dump

AWARD: Phase 2 CM + Fee - FY07

Phase 2 Construction Man

Sheet 4 of 28

Page 5: Activity cOrig Early Budgeted FY05 FY06 FY07 FY08 FY09 ID ... · CFMGT_1175 CF Controls Liaison FY05Q2-Q4 (remaining) 107 05/02/05* 09/30/05 24,077 CFMGT_1045 Cost Account Managers-Phase

Sheet 5 of 28

ActivityID

ActivityDescription

cy

OrigDur

EarlyStart

EarlyFinish

BudgetedCost

1.09.01.03 Construction Management & AE SupportCF04034005 UTR Support for Construction 293 11/10/06 02/08/08 330,894

CFFEH1180 Start FEH Cavern 0 11/22/06* 0

CFXRY1220 Start X-Ray Transport & Diagnostic 0 01/04/07* 0

CF13014005 UTR Support for Construction 312 02/27/07 06/04/08 257,044

CFMGT_1315 AWARD: Phase 2 CM + Fee - FY08 1 10/01/07* 10/01/07 3,450,208

CFMGT_1320 Phase 2 Construction Management + Fee - FY08 297 10/02/07 12/18/08 4,210,255

CFCLC5000 Start Commissioning 0 06/04/08* 0

CFMGT_1317 AWARD: Phase 2 CM + Fee - FY09 1 10/01/08* 10/01/08 760,046

CFPC8020 Start Project As-Builts & O/M Manuals 0 11/13/08* 0

1.09.01.04 Mechanical Design (MD)1.09.01.04.02 Mechanical Design T1 Linac FacilitiesCFLNF_0070 MD Support Title 1 Linac Facility 109 06/13/05* 11/14/05 12,142

CFLNF_0075 Additional MD Support Title 1 Linac Facility 63 01/03/06* 04/03/06 19,347

1.09.01.04.03 Mechanical Design Title 2 (Linac not included)CFRYB_2215 MD Support For Title 2 Design (remaining) 85 05/02/05 08/30/05 15,560

CF10010230 MD Support For Title 2 Design 56 09/12/05* 11/30/05 18,630

CF10010240 Additional MD Support Title 2 Design -Non LINAC 138 12/01/05 06/30/06 38,694

1.09.01.04.04 Mechanical Design T2 Linac FacilitiesCFLNF_2145 Additional MD Support Title 2 Linac Facility 16 11/07/05* 11/30/05 22,443

CFLNF_2150 MD Support Title 2 Linac Facility 60 05/02/06* 07/26/06 22,443

1.09.01.04.05 Mechanical Design Title 3 Linac FacilityCFLNF_3030 MD Title 3 Support - Linac 91 10/03/06 02/27/07 24,528

1.09.01.04.06 Mechanical Design Title 3 (Linac not Included)CF13013085 MD Title 3 Support - Non Linac 243 05/01/06* 04/30/07 21,265

FY05 FY06 FY07 FY08 FY09

UTR Support for Construction

Start FEH Cavern

Start X-Ray Transport & Diagnostic

UTR Support for Construction

AWARD: Phase 2 CM + Fee - FY08

Phase 2 Construction Management + Fee - FY08

Start Commissioning

AWARD: Phase 2 CM + Fee - FY09

Start Project As-Builts & O/M Manuals

MD Support Title 1 Linac Facility

Additional MD Support Title 1 Linac Facility

MD Support For Title 2 Design (remaining)

MD Support For Title 2 Design

Additional MD Support Title 2 Design -Non LI

Additional MD Support Title 2 Linac Facility

MD Support Title 2 Linac Facility

MD Title 3 Support - Linac

MD Title 3 Support - Non Linac

Sheet 5 of 28

Page 6: Activity cOrig Early Budgeted FY05 FY06 FY07 FY08 FY09 ID ... · CFMGT_1175 CF Controls Liaison FY05Q2-Q4 (remaining) 107 05/02/05* 09/30/05 24,077 CFMGT_1045 Cost Account Managers-Phase

Sheet 6 of 28

ActivityID

ActivityDescription

cy

OrigDur

EarlyStart

EarlyFinish

BudgetedCost

1.09.01.05 Conventional Experiment Facility (CEF)1.09.01.05.02 CEF Engineering Title 1 Linac FacilityCFLNF_0010 Develop as-built package Linac Facilitiy 60 08/08/05* 10/31/05 8,540

CFLNF_0020 Utility investigation Linac Facility 27 11/01/05 12/09/05 19,561

CFLNF_0230 Additional Utility Investigation Linac Fac 44 01/09/06* 03/13/06 10,867

CFLNF_1130 COMP: Title 1 Linac Facility 0 03/13/06 0

1.09.01.05.03 CEF Engineering Title 2 (Linac Not Included)CF10010210 CEF Title 2 Support 15 05/02/05 05/20/05 1,586

CFMGT_1056 HVAC Specialist (remaining) 21 05/02/05* 05/31/05 10,497

CF0410000 CEF Title 2 Design Support (Non Linac) 83 06/06/05* 09/30/05 27,848

CF13013110 In-House Conventional Facility Peer Review 145 06/06/05* 01/13/06 35,302

CF0410010 Additional CEF Title 2 Design - Non LINAC 138 12/01/05* 06/30/06 50,858

1.09.01.05.04 CEF Design Linac Facility Title 2CFLNF_1510 User mtg.-interior layout details Linac Facility 20 03/14/06 04/10/06 4,347

CFLNF_1520 User Review and Approval Linac Facility 15 04/11/06 05/01/06 4,347

CFLNF_2010 Multi-Discipline Developmt Phase Linac Facility 40 05/02/06 06/27/06 12,606

CFLNF_2020 User Review and Approval Linac Facility 20 06/28/06 07/26/06 4,347

CFLNF_2030 Consultant Modify drwgs as necessary Linac Facil 20 07/27/06 08/23/06 8,694

CFLNF_2040 Consultants provide 100% dwgs Linac Facility 20 08/24/06 09/21/06 6,955

CFLNF_2050 COMP: Title 2 Linac Facility 0 09/21/06 0

1.09.02 Title 1 & Title 2 Conventional Facilities1.09.02.02 A & E Services (S20, MMF, MMC not Incl)1.09.02.02.02 Title 2 DesignCF04012013 30% Title 2 Design Review - RY - CLOC (Apr Accr) 5 05/02/05* 05/06/05 231,750

CFMGT_1082 A&E Title 2 Support RSY-CLOC (Reimb Apr Accr) 5 05/02/05* 05/06/05 17,440

CF04012015 30% Title 2 Design Review - RY through CLOC 83 05/02/05 08/26/05 708,500

CFMGT_1086 A&E Title 2 Support RSY-CLOC (Reimbursables) 184 05/02/05 02/06/06 118,737

FY05 FY06 FY07 FY08 FY09

Develop as-built package Linac Facilitiy

Utility investigation Linac Facility

Additional Utility Investigation Linac Fac

COMP: Title 1 Linac Facility

CEF Title 2 Support

HVAC Specialist (remaining)

CEF Title 2 Design Support (Non Linac)

In-House Conventional Facility Peer Review

Additional CEF Title 2 Design - Non LINAC

User mtg.-interior layout details Linac Facility

User Review and Approval Linac Facility

Multi-Discipline Developmt Phase Linac Facili

User Review and Approval Linac Facility

Consultant Modify drwgs as necessary Lina

Consultants provide 100% dwgs Linac Fac

COMP: Title 2 Linac Facility

30% Title 2 Design Review - RY - CLOC (Apr Accr)

A&E Title 2 Support RSY-CLOC (Reimb Apr Accr)

30% Title 2 Design Review - RY through CLOC

A&E Title 2 Support RSY-CLOC (Reimbursables)

Sheet 6 of 28

Page 7: Activity cOrig Early Budgeted FY05 FY06 FY07 FY08 FY09 ID ... · CFMGT_1175 CF Controls Liaison FY05Q2-Q4 (remaining) 107 05/02/05* 09/30/05 24,077 CFMGT_1045 Cost Account Managers-Phase

Sheet 7 of 28

ActivityID

ActivityDescription

cy

OrigDur

EarlyStart

EarlyFinish

BudgetedCost

1.09.02.02.02 Title 2 DesignCFMGT_2070 MTH - Structural & Electrical Design (LLP) 197 05/17/05* 03/13/06 55,269

CFLNF_1150 Sector 24 - Stairwells Design 67 06/07/05* 09/09/05 13,058

CF04012095 Far Hall A&E Title 2 Design Changes 116 08/08/05* 02/06/06 64,375

CF04012025 60% Title 2 Design Review - RY through CLOC 62 08/29/05 11/23/05 1,153,226

CF04012105 A&E Title 2 Design Changes - DCNs 98 09/01/05* 02/06/06 356,639

CF04012115 A&E Title 2 Design Changes - Committed 98 09/01/05* 02/06/06 147,182

CFMGT_2090 Mechanical Design Consultancy 120 09/26/05* 03/31/06 18,020

CF04012125 A&E Title 2 Design Changes - DCNs 77 10/03/05* 02/06/06 217,392

CF04012040 90% Title 2 Design Review - RY through CLOC 15 11/28/05 12/16/05 394,320

CF04012135 A&E Title 2 Design Changes - DCNs 49 12/05/05* 02/28/06 211,350

CF04012055 100% Title 2 Design Review 17 01/12/06 02/06/06 122,708

CF04012060 LCLS Review 100% Title 2 Design/Bid Documents 10 01/24/06 02/06/06 0

CF04012065 SLAC Commitee Review 100% Title 2 Design 9 02/07/06 02/17/06 0

CFMGT_2093 AWARD: Structural & Electrical Design for LCLS 1 02/13/06* 02/13/06 107,042

CF10012015 Monte Carlo Analysis 5 02/13/06* 02/17/06 8,480

CFMGT_2095 Structural & Electrical Design for LCLS 120 02/14/06 08/03/06 107,042

CF04012070 COMP: LCLS Review 100% Design (RY-CLOC) 0 02/17/06 0

CF04012075 DOE Review 100% Title 2 Design ( RY - CLOC) 20 02/21/06 03/20/06 0

CF04012101 REQD:Obtain Seismic Rvw Committee Appr(T2) 0 03/14/06 0

CF04012085 RCV: DOE Approval 100% Title 2 ( RY - CLOC) 0 03/20/06 0

CF04012023 AWARD: Arch Flash Calculation 1 05/19/06* 05/19/06 0

CF04012033 Arc Flash Calculation 97 05/22/06 10/06/06 0

CF10010215 AWARD: 12kv Design (MH 48 to CUP Substation) 1 06/05/06* 06/05/06 197,160

CF10012025 12 kv Design (MH 48 to CUP Substation) 60 06/06/06 08/29/06 197,160

FY05 FY06 FY07 FY08 FY09

MTH - Structural & Electrical Design (LLP)

Sector 24 - Stairwells Design

Far Hall A&E Title 2 Design Changes

60% Title 2 Design Review - RY through CLOC

A&E Title 2 Design Changes - DCNs

A&E Title 2 Design Changes - Committed

Mechanical Design Consultancy

A&E Title 2 Design Changes - DCNs

90% Title 2 Design Review - RY through CLOC

A&E Title 2 Design Changes - DCNs

100% Title 2 Design Review

LCLS Review 100% Title 2 Design/Bid Documents

SLAC Commitee Review 100% Title 2 Design

AWARD: Structural & Electrical Design for LCLS

Monte Carlo Analysis

Structural & Electrical Design for LCLS

COMP: LCLS Review 100% Design (RY-CLOC)

DOE Review 100% Title 2 Design ( RY - CLOC)

REQD:Obtain Seismic Rvw Committee Appr(T2)

RCV: DOE Approval 100% Title 2 ( RY - CLOC)

AWARD: Arch Flash Calculation

Arc Flash Calculation

AWARD: 12kv Design (MH 48 to CUP Substatio

12 kv Design (MH 48 to CUP Substation)

Sheet 7 of 28

Page 8: Activity cOrig Early Budgeted FY05 FY06 FY07 FY08 FY09 ID ... · CFMGT_1175 CF Controls Liaison FY05Q2-Q4 (remaining) 107 05/02/05* 09/30/05 24,077 CFMGT_1045 Cost Account Managers-Phase

Sheet 8 of 28

ActivityID

ActivityDescription

cy

OrigDur

EarlyStart

EarlyFinish

BudgetedCost

1.09.02.03 A & E Services - (S20, MMF,MCC)1.09.02.03.02 Title 2 Design (Sector 20)CFS20_2196 MTH Engineering Services for S 20 LLP (Commit) 21 05/02/05* 05/31/05 23,353

CFS20_2206 Additional A&E Title 2 Design for S20 39 08/08/05* 09/30/05 18,017

CFS20_2198 Additional MTH Engineering Services for S-20 LLP 80 08/08/05* 11/30/05 33,920

1.09.02.03.04 Title 2 Design (MMF)CFMMF_2096 MTH Engineering Design for MMF LLP (Committed) 20 05/02/05* 05/27/05 17,811

CFMMF_2116 MTH Electrical Engrg Svc - Feeder B081 82 06/07/05* 09/30/05 22,890

CFMMF_2095 Additional A&E Title 2 Design for MMF 39 08/08/05* 09/30/05 6,436

1.09.03 Construction-T3 Conventional Facilities1.09.03.01 Sector 20 Injector Facilities1.09.03.01.01 S20 - Site Preparation/General RequirementsCFS20_3002 Remove Alcove Pump Room (remaining) 73 05/02/05* 08/12/05 5,748

CFS20_3015 RF Hut Clear Area (remaining) 73 05/02/05 08/12/05 12,170

CFS20_3016 Receive S20 MtrCntlCntr - Hardware 1 08/15/05* 08/15/05 42,806

CFS20_3040 Kick off - Alcove/RF Hut 1 08/23/05* 08/23/05 0

CFS20_4005 Site Mobilization 4 08/30/05* 09/02/05 21,200

CFS20_3003 Temporary Power & Phone 74 09/01/05* 12/16/05 23,058

CFS20_4000 S20 - General Requirement 111 09/01/05* 02/14/06 251,611

CFS20_4002 K10B - General Requirement 55 09/13/05* 11/30/05 17,784

CFS20_3017 Receive S20 SubStation - Hardware 1 09/27/05* 09/27/05 123,444

CFS20_3013 Relocate RF Hut Piping 21 10/03/05* 10/31/05 5,000

1.09.03.01.02 S20 - Site ConstructionCFS20_4010 Site Construction - Demolition 25 09/06/05 10/10/05 75,912

CFS20_4410 K10B - Demolition 4 09/13/05 09/16/05 8,269

CFS20_4360 Equipment Yard - Demolition 3 10/11/05 10/13/05 8,700

CFS20_4530 Injector Housing - Layout & Concrete Demo 6 11/04/05 11/11/05 3,000

FY05 FY06 FY07 FY08 FY09

MTH Engineering Services for S 20 LLP (Commit)

Additional A&E Title 2 Design for S20

Additional MTH Engineering Services for S-20 LLP

MTH Engineering Design for MMF LLP (Committed)

MTH Electrical Engrg Svc - Feeder B081

Additional A&E Title 2 Design for MMF

Remove Alcove Pump Room (remaining)

RF Hut Clear Area (remaining)

Receive S20 MtrCntlCntr - Hardware

Kick off - Alcove/RF Hut

Site Mobilization

Temporary Power & Phone

S20 - General Requirement

K10B - General Requirement

Receive S20 SubStation - Hardware

Relocate RF Hut Piping

Site Construction - Demolition

K10B - Demolition

Equipment Yard - Demolition

Injector Housing - Layout & Concrete Demo

Sheet 8 of 28

Page 9: Activity cOrig Early Budgeted FY05 FY06 FY07 FY08 FY09 ID ... · CFMGT_1175 CF Controls Liaison FY05Q2-Q4 (remaining) 107 05/02/05* 09/30/05 24,077 CFMGT_1045 Cost Account Managers-Phase

Sheet 9 of 28

ActivityID

ActivityDescription

cy

OrigDur

EarlyStart

EarlyFinish

BudgetedCost

1.09.03.01.02 S20 - Site ConstructionCFS20_4400 Equipment Yard - Patch AC 1 11/11/05 11/11/05 2,800

CFS20_4450 K10B - Fencing & Grating 5 11/21/05 11/29/05 2,000

CFS20_4535 Change Order Requests 34 01/09/06* 02/27/06 21,780

1.09.03.01.03 S20 - ConcreteCFS20_4430 K10B - Concrete Foundations & SOG 9 09/13/05 09/23/05 30,181

CFS20_4040 Structural - Footings & Grade Beams 15 10/11/05 10/31/05 40,284

CFS20_4370 Structural - Equipment Pads/Footings 15 10/14/05 11/03/05 14,950

CFS20_4050 Structural - SOG 10 11/08/05 11/21/05 53,572

CFS20_4435 Change Order Requests 34 01/09/06* 02/27/06 4,240

1.09.03.01.05 S20 - MetalsCFS20_4540 K10B - Set Equipment 10 09/26/05 10/07/05 22,815

CFS20_4380 Structural - Structural Support 3 11/04/05 11/08/05 20,000

CFS20_4060 Structural - Erect Struct Steel (Emerg Access) 10 11/08/05 11/21/05 169,609

CFS20_4548 Change order Requests 34 01/09/06* 02/27/06 15,600

1.09.03.01.06 S20 - Woods & PlasticsCFS20_4545 Injector Housing - Modify Stairs 10 11/14/05 11/29/05 14,450

1.09.03.01.07 S20 - Thermal & Moisture ProtectionCFS20_4070 Building Encl - Roof Decking/Insulate Ceiling 12 11/22/05 12/09/05 123,980

CFS20_4140 Wall Construction - Insulate Walls 2 12/12/05 12/13/05 7,700

CFS20_4290 RF Hut - Install Insulation 1 01/03/06 01/03/06 1,300

1.09.03.01.08 S20 - Doors & WindowsCFS20_4080 Building Enclosure - Door Frames 1 11/29/05 11/29/05 11,834

CFS20_4270 RF Hut - Set Door Frame 1 12/20/05 12/20/05 1,000

CFS20_4130 Wall Construction - Install Door Frames 2 12/20/05 12/21/05 9,800

CFS20_4315 Change Order Requests 34 01/09/06* 02/27/06 5,300

CFS20_4310 RF Hut - Install Door Hardware 1 01/19/06 01/19/06 1,000

FY05 FY06 FY07 FY08 FY09

Equipment Yard - Patch AC

K10B - Fencing & Grating

Change Order Requests

K10B - Concrete Foundations & SOG

Structural - Footings & Grade Beams

Structural - Equipment Pads/Footings

Structural - SOG

Change Order Requests

K10B - Set Equipment

Structural - Structural Support

Structural - Erect Struct Steel (Emerg Access)

Change order Requests

Injector Housing - Modify Stairs

Building Encl - Roof Decking/Insulate Ceiling

Wall Construction - Insulate Walls

RF Hut - Install Insulation

Building Enclosure - Door Frames

RF Hut - Set Door Frame

Wall Construction - Install Door Frames

Change Order Requests

RF Hut - Install Door Hardware

Sheet 9 of 28

Page 10: Activity cOrig Early Budgeted FY05 FY06 FY07 FY08 FY09 ID ... · CFMGT_1175 CF Controls Liaison FY05Q2-Q4 (remaining) 107 05/02/05* 09/30/05 24,077 CFMGT_1045 Cost Account Managers-Phase

Sheet 10 of 28

ActivityID

ActivityDescription

cy

OrigDur

EarlyStart

EarlyFinish

BudgetedCost

1.09.03.01.08 S20 - Doors & WindowsCFS20_4240 Finishes - Install Doors & Hardware 2 01/25/06 01/26/06 8,000

1.09.03.01.09 S20 - FinishesCFS20_4542 K10B - Install Finishes 1 11/30/05 11/30/05 1,314

CFS20_4110 Wall Construction - Frame Walls 5 12/13/05 12/19/05 18,430

CFS20_4260 RF Hut - Install Frame Walls/Ceiling 5 12/13/05 12/19/05 4,000

CFS20_4570 Injector Housing - Paint Surfaces 8 12/15/05 12/28/05 8,000

CFS20_4150 Wall Construction - Rock Walls & Finish Walls 5 12/22/05 01/03/06 23,700

CFS20_4160 T-Bar Ceiling - Install T-Bar Ceiling 5 01/04/06 01/10/06 13,400

CFS20_4300 RF Hut - Install Finishes 10 01/04/06 01/18/06 16,200

CFS20_4575 Change Order Requests 34 01/09/06* 02/27/06 5,300

CFS20_4200 T-Bar Ceiling - Drop Tile 2 01/18/06 01/19/06 3,200

CFS20_4210 Finishes - Paint Walls 5 01/18/06 01/24/06 17,227

CFS20_4230 Finishes - Install Floor Treatment 3 01/27/06 01/31/06 5,000

1.09.03.01.14 S20 - Conveying SystemsCFS20_4250 Finishes - Install Overhead Crane 2 01/25/06 01/26/06 2,929

1.09.03.01.15 S20 - MechanicalCFS20_4095 Overhead MEP - Mechanical - LLP 45 10/03/05* 12/06/05 135,000

CFS20_4030 Demolition - Mechanical 17 10/11/05 11/02/05 47,611

CFS20_4550 Injector Housing - Install Sump 5 11/14/05 11/18/05 5,200

CFS20_4340 Klystron Gallery - Chilled Water Piping 24 11/14/05 12/19/05 29,700

CFS20_4480 Install Chilled Water System - Mechanical 17 11/21/05 12/15/05 42,200

CFS20_4460 Install HVAC System - Mechanical 28 11/21/05 01/05/06 139,947

CFS20_4500 Install Hot Water System - Mechanical 17 11/23/05 12/19/05 23,000

CFS20_4520 Install Compressed Air & City Water 6 11/29/05 12/06/05 10,320

CFS20_4555 Injector Housing - Install LCWS & R Piping 5 11/30/05 12/06/05 11,000

FY05 FY06 FY07 FY08 FY09

Finishes - Install Doors & Hardware

K10B - Install Finishes

Wall Construction - Frame Walls

RF Hut - Install Frame Walls/Ceiling

Injector Housing - Paint Surfaces

Wall Construction - Rock Walls & Finish Walls

T-Bar Ceiling - Install T-Bar Ceiling

RF Hut - Install Finishes

Change Order Requests

T-Bar Ceiling - Drop Tile

Finishes - Paint Walls

Finishes - Install Floor Treatment

Finishes - Install Overhead Crane

Overhead MEP - Mechanical - LLP

Demolition - Mechanical

Injector Housing - Install Sump

Klystron Gallery - Chilled Water Piping

Install Chilled Water System - Mechanical

Install HVAC System - Mechanical

Install Hot Water System - Mechanical

Install Compressed Air & City Water

Injector Housing - Install LCWS & R Piping

Sheet 10 of 28

Page 11: Activity cOrig Early Budgeted FY05 FY06 FY07 FY08 FY09 ID ... · CFMGT_1175 CF Controls Liaison FY05Q2-Q4 (remaining) 107 05/02/05* 09/30/05 24,077 CFMGT_1045 Cost Account Managers-Phase

Sheet 11 of 28

ActivityID

ActivityDescription

cy

OrigDur

EarlyStart

EarlyFinish

BudgetedCost

1.09.03.01.15 S20 - MechanicalCFS20_4090 Overhead MEP - Mechanical 10 12/12/05 12/27/05 80,500

CFS20_4120 Wall Construction - MEP Rough-In 5 12/20/05 12/28/05 93,260

CFS20_4577 DCC Controls Installation 34 01/09/06* 02/27/06 135,619

CFS20_4578 Change Order Requests 34 01/09/06* 02/27/06 30,753

CFS20_4180 T-Bar Ceiling - Install Diffusers & Fire Sprinkl 6 01/11/06 01/19/06 19,400

CFS20_4330 RF Hut - Set Fan Coil & connect Piping 4 01/24/06 01/27/06 11,300

CFS20_4220 Finishes - Install Trim MEP 2 01/25/06 01/26/06 21,000

CFS20_4580 Start-up & Commissioning - Mechanical 5 02/07/06 02/13/06 15,200

CFS20_4600 Start-up & Commissioning - HVAC Balancing 11 02/14/06 03/01/06 6,000

1.09.03.01.16 S20 - ElectricalCFS20_4420 K10B - Underground Electrical 25 09/13/05 10/17/05 70,782

CFS20_4440 K10B - Install Equipment 30 10/10/05 11/18/05 148,329

CFS20_4020 Demolition - Electrical 2 10/11/05 10/12/05 10,600

CFS20_4390 Equipment Yard - Install Groundiing 5 11/04/05 11/10/05 5,000

CFS20_4100 Overhead MEP - Electrical 22 11/09/05 12/12/05 165,953

CFS20_4350 Klystron Gallery - Cable Trays 30 11/14/05 12/29/05 19,500

CFS20_4560 Injector Housing - Install Electrical 10 12/01/05 12/14/05 22,000

CFS20_4490 Chilled Water System - Install Electrical 5 12/06/05 12/12/05 6,500

CFS20_4470 HVAC System - Install Electrical 10 12/19/05 01/05/06 19,000

CFS20_4510 Hot Water System - Install Electrical 5 12/20/05 12/28/05 4,000

CFS20_4280 RF Hut - MEP Wall Rough-In 5 12/21/05 12/29/05 8,000

CFS20_4565 K10B - Change Order Requests 34 01/09/06* 02/27/06 13,780

CFS20_4170 T-Bar Ceiling - Install Fixtures 3 01/11/06 01/13/06 53,000

CFS20_4190 T-Bar Ceiling - Trim Vesda 2 01/13/06 01/17/06 3,500

FY05 FY06 FY07 FY08 FY09

Overhead MEP - Mechanical

Wall Construction - MEP Rough-In

DCC Controls Installation

Change Order Requests

T-Bar Ceiling - Install Diffusers & Fire Sprinkl

RF Hut - Set Fan Coil & connect Piping

Finishes - Install Trim MEP

Start-up & Commissioning - Mechanical

Start-up & Commissioning - HVAC Balancing

K10B - Underground Electrical

K10B - Install Equipment

Demolition - Electrical

Equipment Yard - Install Groundiing

Overhead MEP - Electrical

Klystron Gallery - Cable Trays

Injector Housing - Install Electrical

Chilled Water System - Install Electrical

HVAC System - Install Electrical

Hot Water System - Install Electrical

RF Hut - MEP Wall Rough-In

K10B - Change Order Requests

T-Bar Ceiling - Install Fixtures

T-Bar Ceiling - Trim Vesda

Sheet 11 of 28

Page 12: Activity cOrig Early Budgeted FY05 FY06 FY07 FY08 FY09 ID ... · CFMGT_1175 CF Controls Liaison FY05Q2-Q4 (remaining) 107 05/02/05* 09/30/05 24,077 CFMGT_1045 Cost Account Managers-Phase

Sheet 12 of 28

ActivityID

ActivityDescription

cy

OrigDur

EarlyStart

EarlyFinish

BudgetedCost

1.09.03.01.16 S20 - ElectricalCFS20_4320 RF Hut - Install Light Fixtures & Vesda 3 01/19/06 01/23/06 9,000

CFS20_4590 Start-up & Commissioning - Electrical 11 01/24/06 02/07/06 11,000

1.09.03.01.20 S20 - Project Close OutCFS20_3225 AWARD: Building Commissioning Alcove 1 01/17/06* 01/17/06 63,600

CFS20_3230 CF Building Commissioning Alcove 55 01/24/06 04/11/06 63,600

CFS20_3195 AVAIL: RF Hut Shell Beneficial Occupancy 0 01/27/06 0

CFS20_2800 Drawing Implementation to SLAC System- S20 56 02/22/06 05/10/06 1,290

CFS20_4455 COMP: K10B Stubstation 0 02/27/06 0

CFS20_3260 AVAIL: Alcove Beneficial Occupancy 0 03/01/06 0

CFS20_4610 COMP: Sector 20 Certificate of Occupancy 0 03/01/06 0

CFS20_3250 COMP: Alcove Title 3 0 05/10/06 0

1.09.03.02 Magnetic Measurement Facility1.09.03.02.01 MMF - Site Preparation/General RequirementsCFMMF_3005 MMF Relocate Stores - SLAC 69 05/09/05* 08/15/05 14,834

CFMMF_3110 MMF - Kickoff Meeting 1 08/23/05* 08/23/05 0

CFMMF_3045 Receive B81 Transformer (LLP) 1 08/30/05* 08/30/05 37,100

CFMMF_4060 MMF - Site Mobilization 5 08/30/05* 09/06/05 44,308

CFMMF_3165 CF - Site Preparation 40 09/01/05* 10/27/05 12,902

CFMMF_3060 CF - MMF Modify Bldg Lighting & Power 88 09/01/05* 01/11/06 35,408

CFMMF_4000 MMF - General Requirements 101 09/01/05* 01/31/06 228,239

CFMMF_3047 Receive B81 MCC (LLP) 1 11/07/05* 11/07/05 32,860

1.09.03.02.02 MMF - Site ConstructionCFMMF_4070 MMF - Site Demolition 23 09/07/05 10/07/05 40,710

CFMMF_4140 Building Shell - Underground Utilities 3 10/25/05 10/27/05 16,000

CFMMF_4145 Change Order Requests 34 01/09/06* 02/27/06 19,080

FY05 FY06 FY07 FY08 FY09

RF Hut - Install Light Fixtures & Vesda

Start-up & Commissioning - Electrical

AWARD: Building Commissioning Alcove

CF Building Commissioning Alcove

AVAIL: RF Hut Shell Beneficial Occupancy

Drawing Implementation to SLAC System- S20

COMP: K10B Stubstation

AVAIL: Alcove Beneficial Occupancy

COMP: Sector 20 Certificate of Occupancy

COMP: Alcove Title 3

MMF Relocate Stores - SLAC

MMF - Kickoff Meeting

Receive B81 Transformer (LLP)

MMF - Site Mobilization

CF - Site Preparation

CF - MMF Modify Bldg Lighting & Power

MMF - General Requirements

Receive B81 MCC (LLP)

MMF - Site Demolition

Building Shell - Underground Utilities

Change Order Requests

Sheet 12 of 28

Page 13: Activity cOrig Early Budgeted FY05 FY06 FY07 FY08 FY09 ID ... · CFMGT_1175 CF Controls Liaison FY05Q2-Q4 (remaining) 107 05/02/05* 09/30/05 24,077 CFMGT_1045 Cost Account Managers-Phase

Sheet 13 of 28

ActivityID

ActivityDescription

cy

OrigDur

EarlyStart

EarlyFinish

BudgetedCost

1.09.03.02.03 MMF - ConcreteCFMMF_4080 Building Shell - Footings 11 10/10/05 10/24/05 102,502

CFMMF_4170 Building Shell - SOG Concrete Patch 3 11/11/05 11/15/05 49,873

CFMMF_4175 Fill void under concrete slab 34 01/09/06* 02/27/06 22,790

CFMMF_4178 Change Order Requests 34 01/09/06* 02/27/06 8,480

1.09.03.02.05 MMF - MetalsCFMMF_4005 LLP - Structural Steel 38 09/01/05* 10/25/05 0

CFMMF_4150 Building Shell - Erect Steel 15 10/26/05 11/15/05 138,375

1.09.03.02.06 MMF - Woods & PlasticsCFMMF_4075 MMF - Install protection @ Carousel 5 09/06/05* 09/12/05 12,114

1.09.03.02.07 MMF - Thermal & Moisture ProtectionCFMMF_4180 Building Shell - Install GV / Flashing 3 11/04/05 11/08/05 28,000

CFMMF_4190 Building Shell - Install Metal Panels 3 11/04/05 11/08/05 43,264

1.09.03.02.08 MMF - Doors & WindowsCFMMF_4050 LLP - Doors, Frames & Hardware 20 09/01/05* 09/29/05 0

CFMMF_4200 Building Shell - Install Exterior Door Frames 3 11/09/05 11/11/05 28,818

1.09.03.02.09 MMF - FinishesCFMMF_4078 MMF - Build New Demising Walls 16 09/13/05 10/04/05 27,560

CFMMF_4220 LAB TI - Frame Walls 4 11/04/05 11/09/05 47,000

CFMMF_4240 LAB TI - Install Finishes 11 11/10/05 11/28/05 70,000

CFMMF_4255 LAB TI - Install T-Bar Ceiling 5 11/22/05 11/30/05 14,000

CFMMF_4280 LAB TI - Install Ceiling Tile 3 12/14/05 12/16/05 8,000

CFMMF_4290 LAB TI - Seal Floors / Epoxy Floors 5 12/19/05 12/27/05 950

CFMMF_4295 Change Order Requests 34 01/09/06* 02/27/06 9,540

1.09.03.02.10 MMF - SpecialitiesCFMMF_4250 LAB TI - Wall Construction 1 11/28/05 11/28/05 745

FY05 FY06 FY07 FY08 FY09

Building Shell - Footings

Building Shell - SOG Concrete Patch

Fill void under concrete slab

Change Order Requests

LLP - Structural Steel

Building Shell - Erect Steel

MMF - Install protection @ Carousel

Building Shell - Install GV / Flashing

Building Shell - Install Metal Panels

LLP - Doors, Frames & Hardware

Building Shell - Install Exterior Door Frames

MMF - Build New Demising Walls

LAB TI - Frame Walls

LAB TI - Install Finishes

LAB TI - Install T-Bar Ceiling

LAB TI - Install Ceiling Tile

LAB TI - Seal Floors / Epoxy Floors

Change Order Requests

LAB TI - Wall Construction

Sheet 13 of 28

Page 14: Activity cOrig Early Budgeted FY05 FY06 FY07 FY08 FY09 ID ... · CFMGT_1175 CF Controls Liaison FY05Q2-Q4 (remaining) 107 05/02/05* 09/30/05 24,077 CFMGT_1045 Cost Account Managers-Phase

Sheet 14 of 28

ActivityID

ActivityDescription

cy

OrigDur

EarlyStart

EarlyFinish

BudgetedCost

1.09.03.02.14 MMF - Conveying SystemsCFMMF_4030 LLP - Crane Equipment 75 09/12/05* 12/29/05 180,000

CFMMF_4160 Building Shell - Install Crane Support 14 01/03/06 01/23/06 62,097

1.09.03.02.15 MMF - MechanicalCFMMF_4040 LLP - Mechanical EFs 39 09/12/05* 11/03/05 0

CFMMF_4020 LLP - Mechanical AHUs 51 09/26/05* 12/07/05 500,000

CFMMF_4100 Building Shell - MEP - install & layout 20 10/04/05* 10/31/05 23,320

CFMMF_4120 Building Shell - MEP - install OH Piping 20 10/06/05 11/02/05 198,229

CFMMF_4110 Building Shell - MEP -Insulate High Bays 3 10/21/05 10/25/05 9,540

CFMMF_4260 LAB TI - Install Registers & Trim Fire Sprinkler 6 12/01/05 12/08/05 24,400

CFMMF_4210 Building Shell - Install AHU & MAU/Ducting-Mech 15 12/08/05 01/03/06 145,334

CFMMF_4010 LLP - Fire Sprinkler 26 12/09/05* 01/20/06 0

CFMMF_4300 LAB TI - Finish ProcessPiping 5 12/28/05 01/05/06 65,000

CFMMF_4305 Change Order Requests 34 01/09/06* 02/27/06 5,300

CFMMF_4320 HVAC Startup & Commissioning 6 01/24/06 01/31/06 20,800

1.09.03.02.16 MMF - ElectricalCFMMF_4073 MMF - Site Demolition - Safe-Off Gas 1 10/10/05* 10/10/05 2,332

CFMMF_4130 Building Shell - MEP - Install Conduit 36 10/11/05 12/01/05 65,333

CFMMF_4230 LAB TI - In Wall MEP Rough-In 5 11/07/05 11/11/05 87,000

CFMMF_4215 Building Shell - Install AHU & MAU/Ducting-Elect 15 12/08/05 01/03/06 44,540

CFMMF_4270 LAB TI - Install Light Fixtures 3 12/09/05 12/13/05 32,000

CFMMF_4310 LAB TI - Finish MEP Trim 5 01/06/06 01/12/06 34,000

CFMMF_4315 Relocate Electrical Conduit 34 01/09/06* 02/27/06 26,500

CFMMF_4318 Change Order Requests 34 01/09/06* 02/27/06 10,600

CFMMF_3040 AWARD: MMF Major Electrical Equip (LLP) 1 01/17/06* 01/17/06 0

CFMMF_3055 SLAC - Install MMF Major Elec Equip (LLP) 34 01/25/06 03/14/06 356,160

FY05 FY06 FY07 FY08 FY09

LLP - Crane Equipment

Building Shell - Install Crane Support

LLP - Mechanical EFs

LLP - Mechanical AHUs

Building Shell - MEP - install & layout

Building Shell - MEP - install OH Piping

Building Shell - MEP -Insulate High Bays

LAB TI - Install Registers & Trim Fire Sprinkler

Building Shell - Install AHU & MAU/Ducting-Mech

LLP - Fire Sprinkler

LAB TI - Finish ProcessPiping

Change Order Requests

HVAC Startup & Commissioning

MMF - Site Demolition - Safe-Off Gas

Building Shell - MEP - Install Conduit

LAB TI - In Wall MEP Rough-In

Building Shell - Install AHU & MAU/Ducting-Elect

LAB TI - Install Light Fixtures

LAB TI - Finish MEP Trim

Relocate Electrical Conduit

Change Order Requests

AWARD: MMF Major Electrical Equip (LLP)

SLAC - Install MMF Major Elec Equip (LLP)

Sheet 14 of 28

Page 15: Activity cOrig Early Budgeted FY05 FY06 FY07 FY08 FY09 ID ... · CFMGT_1175 CF Controls Liaison FY05Q2-Q4 (remaining) 107 05/02/05* 09/30/05 24,077 CFMGT_1045 Cost Account Managers-Phase

Sheet 15 of 28

ActivityID

ActivityDescription

cy

OrigDur

EarlyStart

EarlyFinish

BudgetedCost

1.09.03.02.16 MMF - ElectricalCFMMF_3050 SLAC - MMF Major Elec Equipment 10 03/15/06 03/28/06 81,620

1.09.03.02.20 MMF - Project Close OutCFMMF_5010 CF - Data & Voice Cabling 40 01/03/06* 03/01/06 33,799

CFMMF_3173 AWARD: Building Commissioning MMF 1 01/17/06* 01/17/06 63,600

CFMMF_3175 CF Building Commissioning MMF 45 02/07/06 04/11/06 63,600

CFMMF_5020 CF - Testing and Balancing 10 02/15/06 03/01/06 6,106

CFMMF_4500 COMP: MMF Certificate of Occupancy 0 02/27/06 0

CFMMF_3200 AVAIL: Beneficial Occupancy MMF 0 03/01/06 0

CFMMF_2700 CF - Drawing Implementation to SLAC System- MMF 46 03/08/06 05/10/06 2,580

CFMMF_3195 COMP: Magnetic Measure Facility Title 3 0 05/10/06 0

1.09.03.04 Linac Facility Upgrade (LN)1.09.03.04.03 ElectricalCFLNF_3020 AWARD: T3 Construction Package (Linac) 1 10/02/06* 10/02/06 746,706

CFLNF_3010 Start Construction Linac Facility 0 10/03/06 0

CFLNF_3050 Install Interior Utilities Electrical 91 10/03/06 02/27/07 323,720

1.09.03.04.04 UtilitiesCFLNF_3040 Install Utilities Linac Facility 91 10/03/06 02/27/07 620,110

1.09.03.04.05 Linac - MetalsCFLNF_1170 Fabricate Sector 24 Stairwells 20 09/02/05* 09/30/05 42,400

CFLNF_1180 Fabricate Sector 24 Stairwells Enclosure 20 09/12/05* 10/07/05 24,486

CFLNF_1210 Install Sector 24 Stairwells 11 10/10/05 10/24/05 26,299

CFLNF_1230 COMP: Sector 24 Stairwells Installation 0 10/24/05 0

1.09.03.04.20 LN - Project Close OutCFLNF_3070 Building Commissioning Linac Facility 10 02/13/07 02/27/07 57,500

CFLNF_3080 Project Punch List Linac Facility 10 02/21/07 03/06/07 57,500

CFLNF_3060 Building Complete Linac Facility 0 02/27/07 0

FY05 FY06 FY07 FY08 FY09

SLAC - MMF Major Elec Equipment

CF - Data & Voice Cabling

AWARD: Building Commissioning MMF

CF Building Commissioning MMF

CF - Testing and Balancing

COMP: MMF Certificate of Occupancy

AVAIL: Beneficial Occupancy MMF

CF - Drawing Implementation to SLAC System-

COMP: Magnetic Measure Facility Title 3

AWARD: T3 Construction Package (Linac)

Start Construction Linac Facility

Install Interior Utilities Electrical

Install Utilities Linac Facility

Fabricate Sector 24 Stairwells

Fabricate Sector 24 Stairwells Enclosure

Install Sector 24 Stairwells

COMP: Sector 24 Stairwells Installation

Building Commissioning Linac Fac

Project Punch List Linac Facility

Building Complete Linac Facility

Sheet 15 of 28

Page 16: Activity cOrig Early Budgeted FY05 FY06 FY07 FY08 FY09 ID ... · CFMGT_1175 CF Controls Liaison FY05Q2-Q4 (remaining) 107 05/02/05* 09/30/05 24,077 CFMGT_1045 Cost Account Managers-Phase

Sheet 16 of 28

ActivityID

ActivityDescription

cy

OrigDur

EarlyStart

EarlyFinish

BudgetedCost

1.09.03.04.20 LN - Project Close OutCFLNF_3100 AVAIL: Beneficial Occupancy Linac Facility 0 02/27/07 0

CFLNF_3090 Drawing Implementation to SLAC System 10 02/28/07 03/13/07 2,647

CFLNF_3110 COMP: Linac Facility Title 3 0 03/13/07 0

CFLNF_3120 COMP: Linac Facility Final Acceptance 0 03/13/07 0

1.09.03.05 Research Yard/B102,B211,B113 & Storage Trailers1.09.03.05.01 RY - Site PreparationCF05012900 Research Yard Site Preparation 40 11/07/05* 01/19/06 30,874

CF05033063 AWARD: Tunnel Rescue Team 1 03/06/06* 03/06/06 106,000

CF05033065 Tunnel Rescue Team 100 03/06/06* 07/25/06 106,000

CF05010 AWARD: Research Yard Construction Pkg - FY06 1 04/17/06* 04/17/06 1,673,977

CF05033054 AWARD: Construction Power for Tunnelling - FY06 1 05/22/06* 05/22/06 50,692

CF05033073 AWARD: Sales Tax - FY06 1 05/24/06* 05/24/06 196,843

CF05033075 Sales Tax 591 05/24/06* 09/29/08 1,356,897

CF05033055 SLAC - Construction Power for Tunnelling 629 06/21/06 12/19/08 493,509

CF05015 AWARD: Research Yard Construction Pkg - FY07 1 10/02/06* 10/02/06 19,153

CF05033064 AWARD: Construction Power for Tunnelling - FY07 1 10/02/06* 10/02/06 187,424

CF05033083 AWARD: Sales Tax - FY07 1 10/02/06* 10/02/06 563,102

CF05033074 AWARD: Construction Power for Tunnelling - FY08 1 10/01/07* 10/01/07 205,509

CF05033093 AWARD: Sales Tax - FY08 1 10/01/07* 10/01/07 596,952

CF05033084 AWARD: Construction Power for Tunnelling - FY08 1 10/01/08* 10/01/08 49,885

1.09.03.05.02 RY - FFTB/BSY & Site ConstructionCF05012920 Construction of FFTB/BSY Vertical Wall 20 10/03/05* 10/28/05 137,800

CF05012925 Construction FFTB/BSY - cost increased 30 10/03/05* 11/11/05 47,700

CF05012930 COMP: FFTB/BSY Vertical Wall 0 11/11/05 0

CF05033020 LCLS Site Construction 177 04/03/06* 12/12/06 241,103

FY05 FY06 FY07 FY08 FY09

AVAIL: Beneficial Occupancy Lina

Drawing Implementation to SLAC S

COMP: Linac Facility Title 3

COMP: Linac Facility Final Accep

Research Yard Site Preparation

AWARD: Tunnel Rescue Team

Tunnel Rescue Team

AWARD: Research Yard Construction Pkg - FY06

AWARD: Construction Power for Tunnelling - F

AWARD: Sales Tax - FY06

Sales Tax

SLAC

AWARD: Research Yard Construction Pkg

AWARD: Construction Power for Tunnelli

AWARD: Sales Tax - FY07

AWARD: Construction Po

AWARD: Sales Tax - FY08

AWARD: Construction Power for Tunnelling - FY08

Construction of FFTB/BSY Vertical Wall

Construction FFTB/BSY - cost increased

COMP: FFTB/BSY Vertical Wall

LCLS Site Construction

Sheet 16 of 28

Page 17: Activity cOrig Early Budgeted FY05 FY06 FY07 FY08 FY09 ID ... · CFMGT_1175 CF Controls Liaison FY05Q2-Q4 (remaining) 107 05/02/05* 09/30/05 24,077 CFMGT_1045 Cost Account Managers-Phase

Sheet 17 of 28

ActivityID

ActivityDescription

cy

OrigDur

EarlyStart

EarlyFinish

BudgetedCost

1.09.03.05.02 RY - FFTB/BSY & Site ConstructionCF05020 Sitework 91 05/24/06 10/02/06 1,685,298

1.09.03.05.05 RY - MetalsCF05030 Metals 91 05/24/06 10/02/06 7,832

1.09.03.05.20 RY - Project Close OutCF05033030 AWARD: Testing RY through CLOC 1 10/02/06* 10/02/06 115,000

CF05040 COMP: Research Yard Mods Construction 0 10/02/06 0

CF05033050 AVAIL: Beneficial Occupancy Research Yard Mods 0 10/03/06 10/02/06 0

CF05033053 RY Project Close Out 40 10/03/06 11/29/06 3,970

CF05033035 Testing - RY through CLOC 200 10/24/06 08/09/07 115,000

CF05033200 COMP: Research Yard Mods Final Acceptance 0 12/13/06 12/12/06 0

CF05033500 AWARD: Furnishing - RY through CLOC 1 10/01/07* 10/01/07 1,180,000

CF05033510 Furnishing - RY through CLOC 200 11/29/07 09/16/08 1,180,000

1.09.03.06 Access Road Construction (AR)1.09.03.06.02 AR - Site ConstructionCF06100 AWARD: Access Road Construction Package 1 04/17/06* 04/17/06 157,035

CF06110 Sitework 80 05/09/06 08/30/06 123,843

1.09.03.06.03 AR - ConcreteCF06120 Concrete 60 06/07/06 08/30/06 33,192

1.09.03.06.20 AR - Project Close OutCF06130 Access Road - Project Close Out 20 08/31/06 09/28/06 0

CF06140 COMP: Access Road Construction 0 09/28/06 0

1.09.03.08 Beam Transport Hall (BTH)1.09.03.08.01 BTH - Site Preparation/General RequirementsCF08000 START: FFTB - Shut Down 0 04/10/06* 0

CF04012910 SLAC - FFTB Remove Utilities - Safe-Off 10 04/10/06 04/21/06 61,661

CF04012930 SLAC - FFTB Technical Equipment Removal 50 04/24/06 07/03/06 0

FY05 FY06 FY07 FY08 FY09

Sitework

Metals

AWARD: Testing RY through CLOC

COMP: Research Yard Mods Constructio

AVAIL: Beneficial Occupancy Research Y

RY Project Close Out

Testing - RY through CLOC

COMP: Research Yard Mods Final Acc

AWARD: Furnishing - RY through CLOC

Furnishing - RY through CLOC

AWARD: Access Road Construction Package

Sitework

Concrete

Access Road - Project Close Out

COMP: Access Road Construction

START: FFTB - Shut Down

SLAC - FFTB Remove Utilities - Safe-Off

SLAC - FFTB Technical Equipment Removal

Sheet 17 of 28

Page 18: Activity cOrig Early Budgeted FY05 FY06 FY07 FY08 FY09 ID ... · CFMGT_1175 CF Controls Liaison FY05Q2-Q4 (remaining) 107 05/02/05* 09/30/05 24,077 CFMGT_1045 Cost Account Managers-Phase

Sheet 18 of 28

ActivityID

ActivityDescription

cy

OrigDur

EarlyStart

EarlyFinish

BudgetedCost

1.09.03.08.01 BTH - Site Preparation/General RequirementsCF04012940 SLAC - FFTB Shielding Block Removal 50 04/24/06 07/03/06 0

CF08100 AWARD: BTH Construction Package - FY06 1 05/22/06* 05/22/06 1,030,000

CF04012920 REQD: Ready for Construction*** 0 07/20/06* 0

CF08105 AWARD: BTH Construction Package - FY07 1 10/02/06* 10/02/06 5,811,185

1.09.03.08.02 BTH - Site ConstructionCF08110 Sitework 213 07/21/06 05/24/07 96,823

1.09.03.08.03 BTH - ConcreteCF08120 Concrete 180 08/18/06 05/07/07 5,414,780

1.09.03.08.05 BTH - MetalsCF08130 Metals 180 08/18/06 05/07/07 75,853

1.09.03.08.15 BTH - MechanicalCF08140 Mechanical 180 08/18/06 05/07/07 138,998

1.09.03.08.16 BTH - ElectricalCF08150 Electrical 180 08/18/06 05/07/07 684,358

1.09.03.08.17 BTH - Others (include Div 4, and 6 through 14)CF08160 Other Construction 180 08/18/06 05/07/07 426,892

1.09.03.08.20 BTH - Project Close OutCF08170 COMP: Beam Transport Hall Construction 0 05/24/07 0

CF0833050 AVAIL: Beneficial Occupancy Beam Transport Hall 0 05/24/07 0

CF0833100 BTH - Project Close Out 40 05/25/07 07/23/07 2,647

CF0833200 COMP: Beam Transport Hall Final Acceptance 0 07/23/07 0

1.09.03.09 Front End Enclosure (FEE)1.09.03.09.01 FEE - Site Preparation/General RequirementsCF09100 AWARD: Front End Enclosure Construction Pkg - FY 1 08/01/06* 08/01/06 41,605

CF09105 AWARD: Front End Enclosure Construction Pkg - FY 1 10/02/06* 10/02/06 1,214,933

1.09.03.09.02 FEE - Site ConstructionCF09110 Sitework 163 08/23/06 04/17/07 261,339

FY05 FY06 FY07 FY08 FY09

SLAC - FFTB Shielding Block Removal

AWARD: BTH Construction Package - FY06

REQD: Ready for Construction***

AWARD: BTH Construction Package - FY

Sitework

Concrete

Metals

Mechanical

Electrical

Other Construction

COMP: Beam Transport Hall Construction

AVAIL: Beneficial Occupancy B

BTH - Project Close Out

COMP: Beam Transport Hall

AWARD: Front End Enclosure Construction

AWARD: Front End Enclosure Constructi

Sitework

Sheet 18 of 28

Page 19: Activity cOrig Early Budgeted FY05 FY06 FY07 FY08 FY09 ID ... · CFMGT_1175 CF Controls Liaison FY05Q2-Q4 (remaining) 107 05/02/05* 09/30/05 24,077 CFMGT_1045 Cost Account Managers-Phase

Sheet 19 of 28

ActivityID

ActivityDescription

cy

OrigDur

EarlyStart

EarlyFinish

BudgetedCost

1.09.03.09.03 FEE - ConcreteCF09120 Concrete 120 10/19/06 04/12/07 661,949

1.09.03.09.15 FEE - MechanicalCF09130 Mechanical 120 10/19/06 04/12/07 93,613

1.09.03.09.16 FEE - ElectricalCF09140 Electrical 120 10/19/06 04/12/07 133,525

1.09.03.09.17 FEE - Others (include Div 4, and 6 through 14)CF09150 Other Construction 120 10/19/06 04/12/07 106,110

1.09.03.09.20 FEE - Project Close OutCF09160 COMP: FEE Construction 0 04/17/07 0

CF0933050 AVAIL: Beneficial Occupancy Front End Enclosure 0 04/17/07 0

CF0933100 FEE - CF Project Close Out 40 04/18/07 06/13/07 2,647

CF0933200 COMP: Front End Enclosure Final Acceptance 0 06/13/07 0

1.09.03.10 Electron Beam Dump (EBD)1.09.03.10.01 EBD - Site Preparation/General RequirementsCF10100 AWARD: Electron Beam Dump Construction

Package1 08/16/06* 08/16/06 13,327

CF10170 AWARD: Electron Beam Dump Constr. Pkg - FY07 1 10/02/06* 10/02/06 1,287,106

1.09.03.10.02 EBD - Site ConstructionCF10110 Sitework 175 09/08/06 05/18/07 152,200

1.09.03.10.03 EBD - ConcreteCF10120 Concrete 135 11/03/06 05/18/07 516,230

1.09.03.10.15 EBD - MechanicalCF10130 Mechanical 135 11/03/06 05/18/07 228,842

1.09.03.10.16 EBD - ElectricalCF10073055 AWARD: EBD Steel Shielding - FY06 1 07/10/06* 07/10/06 75,967

CF10073060 SLAC Install EBD Steel Shielding 120 08/01/06 01/23/07 212,000

CF10073057 AWARD: EBD Steel Shielding - FY07 1 10/02/06* 10/02/06 136,033

CF10140 Electrical 135 11/03/06 05/18/07 179,696

FY05 FY06 FY07 FY08 FY09

Concrete

Mechanical

Electrical

Other Construction

COMP: FEE Construction

AVAIL: Beneficial Occupancy Fr

FEE - CF Project Close Out

COMP: Front End Enclosure F

AWARD: Electron Beam Dump Constructio

AWARD: Electron Beam Dump Constr. Pk

Sitework

Concrete

Mechanical

AWARD: EBD Steel Shielding - FY06

SLAC Install EBD Steel Shielding

AWARD: EBD Steel Shielding - FY07

Electrical

Sheet 19 of 28

Page 20: Activity cOrig Early Budgeted FY05 FY06 FY07 FY08 FY09 ID ... · CFMGT_1175 CF Controls Liaison FY05Q2-Q4 (remaining) 107 05/02/05* 09/30/05 24,077 CFMGT_1045 Cost Account Managers-Phase

Sheet 20 of 28

ActivityID

ActivityDescription

cy

OrigDur

EarlyStart

EarlyFinish

BudgetedCost

1.09.03.10.17 EBD - Others (include Div 4, and 6 through 14)CF10150 Other Construction 135 11/03/06 05/18/07 223,465

1.09.03.10.20 EBD - Project Close OutCF10160 COMP: Electron Beam Dump Construction 0 05/18/07 0

CF1033050 AVAIL: Beneficial Occupancy Beam Dump 0 05/18/07 0

CF1033100 EBD - Project Close Out 40 05/21/07 07/17/07 2,647

CF1033200 COMP: Electron Beam Dump Final Acceptance 0 07/17/07 0

1.09.03.11 Near Experimental Hall (NEH)1.09.03.11.01 NEH - Site Preparation/General RequirementsCF11100 AWARD: Near Experimental Hall Constr Pkg - FY06 1 06/20/06* 06/20/06 1,249,437

CF1103010 SLAC Site Preparation 80 07/10/06* 10/30/06 41,388

CF11105 AWARD: Near Experimental Hall Constr Pkg - FY076 1 10/02/06* 10/02/06 6,292,796

1.09.03.11.02 NEH - Site ConstructionCF11110 Sitework including Demo Gas Pad 235 07/13/06 06/18/07 713,949

1.09.03.11.03 NEH - ConcreteCF11120 Concrete 140 08/10/06 03/02/07 2,948,571

1.09.03.11.05 NEH - MetalsCF11130 Metals 140 08/10/06 03/02/07 142,886

1.09.03.11.15 NEH - MechanicalCF11140 Mechanical 180 09/08/06 05/25/07 1,357,187

1.09.03.11.16 NEH - ElectricalCF11150 Electrical 180 09/08/06 05/25/07 1,099,210

1.09.03.11.17 NEH - Others (include Div 4, and 6 through 14)CF11160 Other Construction 180 09/08/06 05/25/07 1,280,432

1.09.03.11.20 NEH - Project Close OutCF11170 COMP: Near Experimental Hall Construction 0 06/18/07 0

CF1133050 AVAIL: Beneficial Occupancy NEH 0 06/18/07 0

CF1133100 NEH - CF Project Close Out 40 06/19/07 08/14/07 2,647

FY05 FY06 FY07 FY08 FY09

Other Construction

COMP: Electron Beam Dump C

AVAIL: Beneficial Occupancy B

EBD - Project Close Out

COMP: Electron Beam Dump

AWARD: Near Experimental Hall Constr Pkg -

SLAC Site Preparation

AWARD: Near Experimental Hall Constr P

Sitework including Demo Gas

Concrete

Metals

Mechanical

Electrical

Other Construction

COMP: Near Experimental Ha

AVAIL: Beneficial Occupancy NEH

NEH - CF Project Close Out

Sheet 20 of 28

Page 21: Activity cOrig Early Budgeted FY05 FY06 FY07 FY08 FY09 ID ... · CFMGT_1175 CF Controls Liaison FY05Q2-Q4 (remaining) 107 05/02/05* 09/30/05 24,077 CFMGT_1045 Cost Account Managers-Phase

Sheet 21 of 28

ActivityID

ActivityDescription

cy

OrigDur

EarlyStart

EarlyFinish

BudgetedCost

1.09.03.11.20 NEH - Project Close OutCF1133200 COMP: Near Experimental Hall Final Acceptance 0 08/14/07 0

1.09.03.12 Undulator Hall (UH)1.09.03.12.01 UH - Site Preparation/General RequirementsCF12100 AWARD: Undulator Hall Construction Pkg - FY06 1 08/07/06* 08/07/06 640,541

CF12105 AWARD: Undulator Hall Construction Pkg - FY07 1 10/02/06* 10/02/06 5,341,721

1.09.03.12.02 UH - Site ConstructionCF12110 Sitework 168 08/29/06 04/30/07 252,187

CF05033006 AWARD: EP Soil Disposal Contract 1 10/23/06* 10/23/06 507,150

CF05033007 EP Soil Disposal 160 11/21/06 07/25/07 507,150

1.09.03.12.05 HVACCF12120 Metals 120 10/25/06 04/18/07 6,072

1.09.03.12.15 UH - MechanicalCF12130 Mechanical 120 10/25/06 04/18/07 592,947

1.09.03.12.16 UH - ElectricalCF12140 Electrical 120 10/25/06 04/18/07 347,802

1.09.03.12.17 UH - Others (include Div 4, and 6 through 14)CF12150 Other Construction 120 10/25/06 04/18/07 160,683

1.09.03.12.19 UH - Tunnel ConstructionCF12160 UH Tunnel Construction 168 08/29/06 04/30/07 4,622,570

1.09.03.12.20 UH - Project Close OutCF12170 COMP: Undulator Hall Construction 0 04/30/07 0

CF1233050 AVAIL: Beneficial Occupancy Undulator Facility 0 04/30/07 0

CF1233100 UH - CF Project Close Out 40 05/01/07 06/26/07 2,647

CF1233200 COMP: Undulator Facility Final Acceptance 0 06/26/07 0

1.09.03.13 X-Ray - Transport & Diagnostic Hall (XRTD)1.09.03.13.01 XRTD - Site Preparation/General RequirementsCF13100 AWARD: XRTD Construction Package 1 12/14/06* 12/14/06 5,859,129

FY05 FY06 FY07 FY08 FY09

COMP: Near Experimental H

AWARD: Undulator Hall Construction Pkg -

AWARD: Undulator Hall Construction Pkg

Sitework

AWARD: EP Soil Disposal Contract

EP Soil Disposal

Metals

Mechanical

Electrical

Other Construction

UH Tunnel Construction

COMP: Undulator Hall Construction

AVAIL: Beneficial Occupancy U

UH - CF Project Close Out

COMP: Undulator Facility Final Acceptance

AWARD: XRTD Construction Package

Sheet 21 of 28

Page 22: Activity cOrig Early Budgeted FY05 FY06 FY07 FY08 FY09 ID ... · CFMGT_1175 CF Controls Liaison FY05Q2-Q4 (remaining) 107 05/02/05* 09/30/05 24,077 CFMGT_1045 Cost Account Managers-Phase

Sheet 22 of 28

ActivityID

ActivityDescription

cy

OrigDur

EarlyStart

EarlyFinish

BudgetedCost

1.09.03.13.02 XRTD - Site ConstructionCF13110 Sitework 147 01/04/07 08/02/07 252,508

1.09.03.13.03 XRTD - ConcreteCF13120 Concrete 100 03/05/07 07/24/07 73,048

1.09.03.13.05 HVACCF13130 Metals 100 03/05/07 07/24/07 7,195

1.09.03.13.15 XRTD - MechanicalCF13140 Mechanical 100 03/05/07 07/24/07 543,682

1.09.03.13.16 XRTD - ElectricalCF13150 Electrical 100 03/05/07 07/24/07 527,784

1.09.03.13.17 XRTD - Others (include Div 4, and 6 through 14)CF13160 Other Construction 100 03/05/07 07/24/07 128,080

1.09.03.13.19 XRTD - Tunnel ConstructionCF13170 XRTD Tunnel Construction 147 01/04/07 08/02/07 4,326,831

1.09.03.13.20 XRTD - Project Close OutCF13180 COMP: X-Ray Transport & Diagnostics Construction 0 08/02/07 0

CF1333050 AVAIL: Beneficial Occupancy X-Ray Transport 0 08/02/07 0

CF1333100 XRTD - CF Project Close Out 40 08/03/07 09/28/07 2,647

CF1333200 COMP: X-Ray Transpt & Diag Hall Final Acceptance 0 09/28/07 0

1.09.03.14 Far Experimental Hall (FEH)1.09.03.14.01 FEH - Site Preparation/General RequirementsCF14100 AWARD: Far Experimental Hall Construction Pkg 1 10/31/06* 10/31/06 6,868,189

1.09.03.14.02 FEH - Site ConstructionCF14110 Sitework 185 11/22/06 08/17/07 121,901

1.09.03.14.05 FEH - MetalsCF14120 Metals 140 01/24/07 08/10/07 185,809

1.09.03.14.15 FEH - MechanicalCF14130 Mechanical 140 01/24/07 08/10/07 376,274

FY05 FY06 FY07 FY08 FY09

Sitework

Concrete

Metals

Mechanical

Electrical

Other Construction

XRTD Tunnel Construction

COMP: X-Ray Transport & D

AVAIL: Beneficial Occupanc

XRTD - CF Project Close Out

COMP: X-Ray Transpt & D

AWARD: Far Experimental Hall Construc

Sitework

Metals

Mechanical

Sheet 22 of 28

Page 23: Activity cOrig Early Budgeted FY05 FY06 FY07 FY08 FY09 ID ... · CFMGT_1175 CF Controls Liaison FY05Q2-Q4 (remaining) 107 05/02/05* 09/30/05 24,077 CFMGT_1045 Cost Account Managers-Phase

Sheet 23 of 28

ActivityID

ActivityDescription

cy

OrigDur

EarlyStart

EarlyFinish

BudgetedCost

1.09.03.14.16 FEH - ElectricalCF14140 Electrical 140 01/24/07 08/10/07 571,764

1.09.03.14.17 FEH - Others (include Div 4, and 6 through 14)CF14150 Other Construction 140 01/24/07 08/10/07 307,085

1.09.03.14.18 FEH - Access TunnelCF14180 AWARD: Access Tunnel Construction Pkg - FY06 1 06/30/06* 06/30/06 473,554

CF14190 Access Tunnel Constructionn 261 07/25/06 08/06/07 2,676,957

CF14185 AWARD: Access Tunnel Construction Pkg - FY07 1 10/02/06* 10/02/06 2,203,403

1.09.03.14.19 FEH - Tunnel ConstructionCF14160 FEH Tunnel Construction 170 11/22/06 07/27/07 5,305,356

1.09.03.14.20 FEH - Project Close OutCF14200 COMP: Access Tunnel Constructionn 0 08/06/07 0

CF14170 COMP: Far Experimental Hall Construction 0 08/17/07 0

CF1433050 AVAIL:Beneficial Occupancy Far Experimental Hall 0 08/17/07 0

CF1433100 FEH - CF Project Close Out 40 08/20/07 10/15/07 2,666

CF1433200 COMP: Far Experimental Hall Final Acceptance 0 10/15/07 0

1.09.03.15 BTH Service Buildings 2.1, 2.2, and 2.3 (SB BTH)1.09.03.15.03 SB BTH - ConcreteCF15100 AWARD: BTH Service Building Construction Pkg 1 10/16/06* 10/16/06 1,807,685

CF15110 Concrete 137 11/07/06 05/24/07 50,909

1.09.03.15.05 SB BTH - MetalsCF15120 Metals 137 11/07/06 05/24/07 99,098

1.09.03.15.15 SB BTH - MechanicalCF15130 Mechanical 137 11/07/06 05/24/07 563,220

1.09.03.15.16 SB BTH - ElectricalCF15140 Electrical 137 11/07/06 05/24/07 811,977

1.09.03.15.17 SB BTH - Others (include Div 4, and 6 through 14CF15150 Other Construction 137 11/07/06 05/24/07 282,480

FY05 FY06 FY07 FY08 FY09

Electrical

Other Construction

AWARD: Access Tunnel Construction Pkg - F

Access Tunnel Construction

AWARD: Access Tunnel Construction Pk

FEH Tunnel Construction

COMP: Access Tunnel Constructionn

COMP: Far Experimental Hall Construction

AVAIL:Beneficial Occupanc

FEH - CF Project Close Out

COMP: Far Experimental Hall Final Acceptance

AWARD: BTH Service Building Construc

Concrete

Metals

Mechanical

Electrical

Other Construction

Sheet 23 of 28

Page 24: Activity cOrig Early Budgeted FY05 FY06 FY07 FY08 FY09 ID ... · CFMGT_1175 CF Controls Liaison FY05Q2-Q4 (remaining) 107 05/02/05* 09/30/05 24,077 CFMGT_1045 Cost Account Managers-Phase

Sheet 24 of 28

ActivityID

ActivityDescription

cy

OrigDur

EarlyStart

EarlyFinish

BudgetedCost

1.09.03.15.20 SB BTH - Project Close OutCF15160 COMP: BTH Service Buildings Construction 0 05/24/07 0

1.09.03.16 UH Service Building 3.1 (SB UH)1.09.03.16.01 SB UH - Site PreparationCF16100 AWARD: UH Service Building Construction Pkg 1 10/20/06* 10/20/06 1,224,417

1.09.03.16.03 SB UH - ConcreteCF16110 Concrete 115 11/13/06 04/30/07 209,971

1.09.03.16.05 SB UH - MetalsCF16120 Metals 115 11/13/06 04/30/07 49,236

1.09.03.16.15 SB UH - MechanicalCF16130 Mechanical 115 11/13/06 04/30/07 391,289

1.09.03.16.16 SB UH - ElectricalCF16140 Electrical 115 11/13/06 04/30/07 433,193

1.09.03.16.17 SB UH - Others (include Div 4, and 6 through 14)CF16150 Other Construction 115 11/13/06 04/30/07 140,726

1.09.03.16.20 SB UH - Project Close OutCF16160 COMP: UH Service Building Construction 0 04/30/07 0

1.09.03.17 FEH Service Building 8.1 (FEH SB)1.09.03.17.01 SB FEH - Site PreparationCF17100 AWARD: FEH Service Building Construction Pkg 1 04/05/07* 04/05/07 935,232

1.09.03.17.03 SB FEH - ConcreteCF17110 Concrete 79 04/27/07 08/17/07 224,063

1.09.03.17.05 SB FEH - MetalsCF17120 Metals 79 04/27/07 08/17/07 62,811

1.09.03.17.15 SB FEH - MechanicalCF17130 Mechanical 49 06/11/07 08/17/07 287,677

1.09.03.17.16 SB FEH - ElectricalCF17140 Electrical 49 06/11/07 08/17/07 251,503

1.09.03.17.17 SB FEH - Others (include Div 4, and 6 through 14CF17150 Other Construction 49 06/11/07 08/17/07 109,178

FY05 FY06 FY07 FY08 FY09

COMP: BTH Service Buildings

AWARD: UH Service Building Constructi

Concrete

Metals

Mechanical

Electrical

Other Construction

COMP: UH Service Building Con

AWARD: FEH Service Building Co

Concrete

Metals

Mechanical

Electrical

Other Construction

Sheet 24 of 28

Page 25: Activity cOrig Early Budgeted FY05 FY06 FY07 FY08 FY09 ID ... · CFMGT_1175 CF Controls Liaison FY05Q2-Q4 (remaining) 107 05/02/05* 09/30/05 24,077 CFMGT_1045 Cost Account Managers-Phase

Sheet 25 of 28

ActivityID

ActivityDescription

cy

OrigDur

EarlyStart

EarlyFinish

BudgetedCost

1.09.03.17.20 SB FEH - Project Close OutCF17160 COMP: FEH Service Building Construction 0 08/17/07 0

1.09.03.18 NEH Central Utility Plant (CUP)1.09.03.18.01 CUP - Site Preparation/General RequirementsCF18100 AWARD: Central Utility Plant Construction - FY06 1 06/22/06* 06/22/06 557,749

CF18102 AWARD: Central Utility Plant Construction - FY07 1 10/02/06* 10/02/06 2,338,541

CF18103 AWARD: Natural Gas Line (Guest House to CUP) 1 12/11/06* 12/11/06 108,000

CF18105 AWARD: 12 kv Construction (MH48 to CUP Substat) 1 12/11/06* 12/11/06 1,218,000

1.09.03.18.02 CUP - Site ConstructionCF18110 Sitework 216 07/17/06 05/23/07 2,999

CF18115 Natural Gas Line (Guest House to CUP) 40 01/18/07 03/15/07 108,000

1.09.03.18.03 CUP - ConcreteCF18120 Concrete 170 08/14/06 04/17/07 120,721

1.09.03.18.05 CUP - MetalsCF18130 Metals 170 08/14/06 04/17/07 111,552

1.09.03.18.15 CUP - MechanicalCF18140 Mechanical 170 08/14/06 04/17/07 1,347,462

1.09.03.18.16 CUP - ElectricalCF18150 Electrical 170 08/14/06 04/17/07 1,061,746

CF18155 12 kv Construction (MH48 to CUP Substat) 80 01/18/07 05/10/07 1,218,000

1.09.03.18.17 CUP - Others (include Div 4, and 6 through 14)CF18160 Other Construction 170 08/14/06 04/17/07 251,812

1.09.03.18.20 CUP - Project Close OutCF18170 Start Up & Commissioning 30 04/12/07 05/23/07 0

CF18180 COMP: Central Utility Plant Construction 0 05/23/07 0

CF1833200 COMP: Central Utility Plant Final Acceptance 0 05/23/07 0

CF18090300 COMP: All Areas Except CLOC 0 12/19/08 0

FY05 FY06 FY07 FY08 FY09

COMP: FEH Service Building Construction

AWARD: Central Utility Plant Construction - F

AWARD: Central Utility Plant Constructio

AWARD: Natural Gas Line (Guest Hous

AWARD: 12 kv Construction (MH48 to

Sitework

Natural Gas Line (Guest House to

Concrete

Metals

Mechanical

Electrical

12 kv Construction (MH48 to CU

Other Construction

Start Up & Commissioning

COMP: Central Utility Plant Construction

COMP: Central Utility Plant Fin

COMP: All Areas Except CLOC

Sheet 25 of 28

Page 26: Activity cOrig Early Budgeted FY05 FY06 FY07 FY08 FY09 ID ... · CFMGT_1175 CF Controls Liaison FY05Q2-Q4 (remaining) 107 05/02/05* 09/30/05 24,077 CFMGT_1045 Cost Account Managers-Phase

Sheet 26 of 28

ActivityID

ActivityDescription

cy

OrigDur

EarlyStart

EarlyFinish

BudgetedCost

1.09.03.19 Central Laboratory Office Complex (CLOC)1.09.03.19.01 CLOC - Site Preparation/General RequirementsCF19100 AWARD: CLOC Contruction Package - FY06 1 06/22/06* 06/22/06 101,584

CF19110 AWARD: CLOC SITEWORK, Landscape & Parking -FY06

1 06/22/06* 06/22/06 342,481

CF19103 AWARD: CLOC Contruction Package - FY07 1 10/02/06* 10/02/06 6,666,305

CF19113 AWARD: CLOC SITEWORK, Landscape & Parking -FY07

1 10/02/06* 10/02/06 1,669,179

CF19106 AWARD: CLOC Contruction Package - FY08 1 10/01/07* 10/01/07 7,814,655

CF19116 AWARD: CLOC SITEWORK, Landscape & Parking -FY08

1 10/01/07* 10/01/07 1,809,878

1.09.03.19.02 CLOC - Site ConstructionCF19120 SITEWORK, Landscape and Parking 552 07/17/06 09/24/08 3,821,538

1.09.03.19.03 CLOC - ConcreteCF19130 Concrete 450 09/12/06 06/26/08 2,059,773

1.09.03.19.04 CLOC - MasonryCF19140 Masonry 450 09/12/06 06/26/08 47,887

1.09.03.19.05 CLOC - MetalsCF19150 Metals 450 09/12/06 06/26/08 1,454,454

1.09.03.19.06 CLOC - Woods & PlasticsCF19160 Wood and Plastics 450 12/07/06 09/22/08 190,705

1.09.03.19.07 CLOC - Thermal & Moisture ProtectionCF19170 Thermal & Moisture Protection 450 12/07/06 09/22/08 2,363,894

1.09.03.19.08 CLOC - Doors & WindowsCF19180 Doors & Windows 450 12/07/06 09/22/08 1,226,010

1.09.03.19.09 CLOC - FinishesCF19190 Finishes 450 12/07/06 09/22/08 1,842,282

1.09.03.19.10 CLOC - SpecialtiesCF19200 Specialtieis 450 12/07/06 09/22/08 85,300

1.09.03.19.11 CLOC - EquipmentCF19210 Equipment 450 12/07/06 09/22/08 0

FY05 FY06 FY07 FY08 FY09

AWARD: CLOC Contruction Package - FY06

AWARD: CLOC SITEWORK, Landscape & Par

AWARD: CLOC Contruction Package - FY

AWARD: CLOC SITEWORK, Landscape &

AWARD: CLOC Contruction Package - FY08

AWARD: CLOC SITEWOR

SITEWOR

Concrete

Masonry

Metals

Wood and Plastics

Thermal & Moisture Protection

Doors & Windows

Finishes

Specialtieis

Equipment

Sheet 26 of 28

Page 27: Activity cOrig Early Budgeted FY05 FY06 FY07 FY08 FY09 ID ... · CFMGT_1175 CF Controls Liaison FY05Q2-Q4 (remaining) 107 05/02/05* 09/30/05 24,077 CFMGT_1045 Cost Account Managers-Phase

Sheet 27 of 28

ActivityID

ActivityDescription

cy

OrigDur

EarlyStart

EarlyFinish

BudgetedCost

1.09.03.19.12 CLOC - FurnishingsCF19220 Furnishings 450 12/07/06 09/22/08 0

1.09.03.19.13 CLOC - Special ConstructionCF19230 Special Construction 450 12/07/06 09/22/08 0

1.09.03.19.14 CLOC - Conveying SystemsCF19240 Conveying Systems 450 12/07/06 09/22/08 171,656

1.09.03.19.15 CLOC - MechanicalCF19250 Mechanical 450 12/07/06 09/22/08 2,514,515

1.09.03.19.16 CLOC - ElectricalCF19260 Electrical 450 12/07/06 09/22/08 2,626,071

1.09.03.19.20 CLOC - Project Close OutCF19270 Commissioning & Punchlist 80 06/03/08 09/24/08 0

CF19280 Testing and Certification 10 09/25/08 10/08/08 0

CF19290 COMP: CLOC Construction 0 10/08/08 0

CF1933050 AVAIL: Beneficial Occupancy CLOC 0 10/08/08 0

CF1933100 CLOC - CF Project Close Out 48 10/09/08 12/17/08 2,786

CF1933200 COMP: Central Lab Office Ctr Final Acceptance 0 12/19/08 0

2 LCLS PROJECT - R&D, SPARES, COMMISSIONING2.09 Conventional Facility Commissioning2.09.032.09.03.05 CF RSY through CLOC CommissioningCFMGT_1099 AWARD: Dispute Resolution Board - FY06 1 05/08/06* 05/08/06 14,502

CFMGT_1109 Dispute Resolution Board (FY06) 251 05/09/06 05/07/07 36,040

CF05033040 AWARD: Commissioning RY through CLOC - FY07 1 10/02/06* 10/02/06 106,000

CFMGT_1001 AWARD: Dispute Resolution Board - FY07 1 10/02/06* 10/02/06 54,557

CF05033045 Commissioning - RSY-CLOC (FY07) 250 10/03/06 09/28/07 105,400

CFMGT_1119 Dispute Resolution Board (FY07) 107 05/08/07* 10/08/07 34,980

FY05 FY06 FY07 FY08 FY09

Furnishings

Special Construction

Conveying Systems

Mechanical

Electrical

Commissioning & Punchlist

Testing and Certification

COMP: CLOC Construction

AVAIL: Beneficial Occupancy CLOC

CLOC - CF Project Close Out

COMP: Central Lab Office Ctr Final Acceptance

AWARD: Dispute Resolution Board - FY06

Dispute Resolution Board (FY06

AWARD: Commissioning RY through CLO

AWARD: Dispute Resolution Board - FY07

Commissioning - RSY-CL

Dispute Resolution Board (FY07)

Sheet 27 of 28

Page 28: Activity cOrig Early Budgeted FY05 FY06 FY07 FY08 FY09 ID ... · CFMGT_1175 CF Controls Liaison FY05Q2-Q4 (remaining) 107 05/02/05* 09/30/05 24,077 CFMGT_1045 Cost Account Managers-Phase

Sheet 28 of 28

ActivityID

ActivityDescription

cy

OrigDur

EarlyStart

EarlyFinish

BudgetedCost

2.09.03.05 CF RSY through CLOC CommissioningCF05033041 AWARD: Commissioning RY through CLOC - FY08 1 10/01/07* 10/01/07 331,600

CFMGT_1005 AWARD: Dispute Resolution Board - FY08 1 10/01/07* 10/01/07 36,941

CF05033085 Commissioning - RSY-CLOC (FY08) 251 10/01/07 09/30/08 327,700

CFMGT_1129 Dispute Resolution Board (FY08) 251 10/09/07 10/08/08 34,980

CF05033042 AWARD: Commissioning RY through CLOC - FY09 1 10/01/08* 10/01/08 75,000

CF05033095 Commissioning - RSY-CLOC (FY09) 63 10/01/08 12/31/08 79,500

FY05 FY06 FY07 FY08 FY09

AWARD: Commissioning

AWARD: Dispute Resolution Board - FY08

Commissioning - RSY-CLOC (FY08)

Dispute Resolution Board (FY08)

AWARD: Commissioning RY through CLOC - FY09

Commissioning - RSY-CLOC (FY09)