Board PresentationBoard Presentation
Mobile Work Mobile Work ManagementManagementPilot ProjectPilot Project
Mike Beardslee, PMP, GISPMike Beardslee, PMP, GISPOctober 14, 2010
22
Agenda
Strategic Plan/CIP Background Scope and Architecture Spending Plan/Procurement ROI Future Steps Recommended Board Action
33
Mobile Work Management Program
Loudoun Water Strategic Plan Goal– Leverage technology to optimize business Leverage technology to optimize business
practicespractices Part of 2010 CIP
44
Background
Current use of laptops in field– Clumsy, slow, require connectivityClumsy, slow, require connectivity
Need for more efficient mobile platform– Automate data entry/managementAutomate data entry/management– Boost data integrityBoost data integrity– Mapping and routing functionsMapping and routing functions– Decrease windshield time, increase time on Decrease windshield time, increase time on
tasktask– Improve customer serviceImprove customer service
55
Background
Initial task order $48,036 to Gannett Fleming for Implementation Plan– Define phased approachDefine phased approach– Recommend technical solutionsRecommend technical solutions– Foundation for new task orderFoundation for new task order
66
Task Order #3
Pilot Project, $186,600 Establish framework for mobile work
management platform– Back office ‘middle-ware’Back office ‘middle-ware’
Two mobile applications on iPhones/iPads– Hydrant FlushingHydrant Flushing– Meter Service WorkMeter Service Work
Completion in Q2, 2011
77
HansenWork Orders
MUNISService Requests
GISMaps
MobileMiddleware
MobileUser Applications
MobileFramework Middleware
BusinessApplications
Hydrant FlushingMeter Service
88
Mobile – CIP
2010 2011 2012 Total
2010 CIP $500,000 $400,000 $200,000 $1,100,000
Revised 2011 CIP Projection
$150,000 $500,000 $450,000 $1,100,000
99
Procurement Actions
Task Order #1Implementation
Plan(Complete)
2010 2011 2012
Task Order #3Pilot Project
Possible Future Mobile Implementation
Phases - Separate Procurement(s)
Today
Timeline
$48k
$186k
$866k
1010
ROI
20% gain in efficiency through reduced mileage and associated costs
Hydrant flushing– $20k - $40k in labor savings$20k - $40k in labor savings– Intangible benefits (data integrity, etc.)Intangible benefits (data integrity, etc.)
1111
Future
ROI Analysis Procurement for additional mobile
apps– Cross connection/backflowCross connection/backflow– Manhole checksManhole checks– Easement maintenanceEasement maintenance
1212
Recommended Board Action
I move the Board approve Task Order No. 3 with Gannett Fleming for an estimated not to exceed cost of $186,600 and authorize an approximate 10 percent contingency to be controlled by the General Manager, for an authorized budget ceiling not to exceed $205,000 without further Board approval.
1313
Questions?