sLH
C-P
roje
ct-N
ote-
0026
24/0
1/20
11
This is an internal CERN publication and does not necessarily reflect the views of the CERN management.
sLHC Project Note 0026
2011-01-24
Cleanroom refurbishment in SM18 within the SPL project frame, feasibility
study.
Janic Chambrillon / BE-RF
Keywords: SPL, cleanroom, cleanroom upgrade, SRF cavity, high gradient cavity, cavity rinsing,
cavity assembling, ultra pure water, UPW, high pressure rinsing, HPR, optical inspection, SM18.
Summary
Manufacturing of SRF cavities with high gradient (>25 MV/m) requires a good control of the
cleaning and assembling procedure. To do so, it has been recommended to update the CERN
cleanroom facility in SM18. Improvement of the existing cleanroom class, construction of a new
clean space and acquisition of a new high pressure rinsing system are the essential parts of the
upgrade. New control procedures and new instrumentations will help to monitor each step of the
cleaning and assembling procedure.
1. Introduction
Cleanrooms are an essential part of the manufacturing process for a superconducting accelerator.
CERN cleanroom facilities are now 15 years old, and even if they are sufficient for the LHC cavity
gradient (5 MV/m), they are not sufficient to reach the 25 MV/m gradient needed by proton drivers
as the SPL. In fact, with high gradient resonators cleanliness becomes a key parameter and
additional controls of the manufacturing and assembling process should be established to obtain
good performance. Therefore, improvements of the facilities have to be done.
2. SM18 area current infrastructure
With the approval by the management of the SPL study, CERN decided to refurbish the existing
SM18 test facility to comply with the required gradients of 25 MV/m. In March 2010, a visit at
CERN of power coupler experts from different institutes confirmed that the actual facilities had to
be refurbished. The SM18 cleanroom facility is composed of three parts, each measuring 15 meters
long; an outside working place, a Class 10’000/ISO7 cleanroom and a Class 10/ISO4 cleanroom,
used as an assembly area for LHC cavities (Figure 1). However, because of the door opening the
actual useful space is around 13 meters long by 2.10 meters high. The useful height can be extended
to 2.60 meters thanks to a small door on top of the main door. It was designed to let LHC power
coupler pass the doors after the final assembling. Finally, an additional Class 100/ISO5 softwall
cleanroom (baldaquin) is located outside of the main facility. According to the coupler experts’
recommendations, the SM18 cleanroom has a good potential for the SPL coupler work1. The Class
2
10/ISO4 area provided by the facility is the best place to reach gradients greater than 25 MV/m. The
final coupler assembling should be done in such room as well as niobium cavity rinsing2.
3. SM18 cleanroom facility upgrade
To achieve the manufacturing of such high voltage gradient components, carrying operations
between different cleanroom facilities should be avoided. They are time consuming and they
introduce additional risks in terms of particle contamination (ripping of plastic bag when moving
the equipment, possible contamination at unpacking). The philosophy should be to control as much
as possible the manufacturing process, and therefore remove any hazardous operations. Thus, the
SM18 facility needs an upgrade of its cleanliness class.
Within this scope, experts recommended to provide additional Class 100 and Class 1’000 clean
rooms1 (Figure 2). A new Class 1’000 room should be built for the personnel dressing and be
ideally equipped with an air shower to access to the working area. The actual Class 10’000 rooms
can be upgraded to provide the new Class 100 area, used as a preparation area before entering into
the class 10 cleanroom. In addition, other projects with lower cleanliness needs could use this new
class 100 space as an assembling area. The actual air shower should be replaced by an ionized air
shower to access to the Class 10 area. Finally, an additional baldaquin (n°2 on Figure 2) could be
installed for long term storage of components.
Nevertheless, the cleaning processes must be done in dedicated rooms, to avoid contamination of
the assembling areas. Thus a new Class 100 cleanroom, dedicated to power coupler elements
rinsing and degreasing, should be built in direct connection with the future class 100 one. Moreover,
an additional Class 10 cabinet is needed for installing the high pressure rinsing (HPR) system to
clean the cavities. This cabinet will be connected from outside (for maintenance reason) to the
rinsing room and will constitute a local class 10 space. Likewise, an Ultra Pure Water (UPW)
supply system must be installed next to the cleanroom to limit the size of the UPW circulation
circuit. An additional water tank may be considered, if needed, to buffer the ultra pure water
consumption during the rinsing operations.
4. Quality control
To guarantee a good control of the manufacturing and assembling process, the monitoring of
critical parameters has to be done as much as possible. Thanks to CERN and DESY’s
experience3,4,5,6
we are able to define a list of control procedures and therefore a list of the
equipment to be obtained (Table 1, Table 2, Table 3).
Ultra Pure Water quality
Controls are mainly done on the Ultra Pure Water quality; particle counting, bacteria analysis,
water resistivity measurement and Total Organic Carbon (TOC) test (Table 1, Table 2). Such
controls must be done at the inlet and if possible at the outlet of the rinsing systems to check the
rinsing efficiency. In fact, the rinsing water contains many bubbles that lead to unstable and non
relevant measurements of the particle content. An alternative solution used at DESY3 consists of
filtering a relevant sample of the rinsing water with a mechanical filter. This filter is then analysed
under a light microscope to determine the numbers and the size of the particles. However this
counting operation has to be done manually and can take up two hours. For that reason it should be
3
considered as an optional method to check the outlet water. Water resistivity measurements at the
outlet were used at CERN to minimize the time needed for conditioning of the LEP SC cavity6.
This method is still used at CERN to validate the rinsing with the HPR system. Measurements at
inlet, outlet and filter analysis will then be reported in a database which will be used to detect
failures in the process and thus improve it.
Cleanroom class 10 / ISO4:
Name - Description: Comment:
High pressure cavity rinsing system Nozzle moving through a rotating cavity
Online liquid particle counter At inlet of the cavity rinsing system
Online Ohm-meters Check water resistivity at inlet
Bacteria analysis system Check water quality at rinsing system inlet
Mechanical filter Validate the rinsing at rinsing system outlet
Optical microscope Analysis of the mechanical filter
Online TOC analyser Check carbon presence in UPW
Drying system Accelerate cavities' drying
Air monitoring system / Particle counter Control air quality
Leak detection system He test
Online O2 monitoring system Survey of the O2 level
Air tight boxes & cabinet Storage of clean component, have to be in stainless
steel
Fog generator Study and check air flow movement
Optical cavity inspection system Study cavity surface defects
Spray gun Removal of dust
Ultrasound cleaning bath Removal of dust
Table 1: equipment needed for the class 10 areas, in blue are the UPW related equipment
4
Air quality
Monitoring of the air quality is necessary. Temperature and humidity are easy to monitor and are
already in place in the current cleanroom facility. To guarantee the laminar flow conditions, air flow
velocity measurement should be done on each filter regularly along the year. Once assembling,
rinsing and carrying procedures will be defined, a first verification with handheld particle counter
must be done to validate them. A global operation pattern will appear, and lead to the definition of
specific measurement point for an online particle density monitoring. Moreover, specific checking
should be considered before any critical operation3. Within the same scope, cleanliness of a
component could be validated by blowing with filtered and dry gas7. Particle measurement is done
in the blowing direction.
Optical inspection of cavities
Finally, the control process could be completed by the acquisition of an optical inspection system
for SRF cavities. It is composed of a cylinder fitting the iris of the cavity, on which an illumination
system and a CCD camera are installed. It allows the characterization of surface defects. A
correlation between data from T-map or quench location measurements, obtained during RF test,
and surface aspect is done to locate defects produced when manufacturing the cavities. This system,
originally developed at KEK/Kyoto University, has proven its efficiency8 and has been delivered to
other institutes such as DESY9, where it is still in development.
Cleanroom class 100 / ISO5:
Name - Description: Comment:
Power Coupler & HOM rinsing system Low pressure rinsing
Online liquid particle counter At inlet & outlet of the cavity rinsing system
Online Ohm-meters Check water resistivity at inlet & at outlet
Bacteria analysis system Check water quality at rinsing system inlet
Mechanical filter Validate the rinsing at rinsing system outlet
Optical microscope Analysis of the mechanical filter
Online TOC analyser Check carbon presence in UPW
Air monitoring system / Particle counter Control air quality
Leak detection system He test
Online O2 monitoring system Survey of the O2 level
Air tight boxes & cabinet For storage of clean component, have to be in stainless
steal
Table 2: equipment needed for class 100 areas, in blue are the UPW related equipment
5
5. Upgrade priority
To spread over time the total cost of the refurbishment, the project can be divided into steps with
different priority levels (Appendix I, Appendix II Appendix III). However the first step represents
itself 90% (Appendix IVAppendix III) of the total amount of the refurbishment. In fact, it includes
the upgrade of the cleanroom facility, the installation of a new HPR associated to a new UPW
production unit and its monitoring instrumentation. A way to reduce the cost of the first step could
be achieved if the HPR system from CERN gives good result on SPL cavity. A first rinsing on a
one cell SPL prototype cavity is planned by the end of December 2010. In case of good
performances when rinsing the cavities with CERN’s HPR, the installation of a new HPR can be
postponed. In that case, the cost of the first step drops to 58% of the total refurbishment cost.
As a second step of the upgrade, we should focus equipments which will lead to the improvement of
the working procedure and reinforce the quality control: fog generator, cavity optical inspection
system, bacteria analysis in UPW and O2 survey system if needed.
Finally, the two last steps will focus on dedicated equipment for the cleanroom like pumping
equipment, cleanroom monitoring equipment, and storage equipment for clean components.
6. Conclusion
The aim of this upgrade is not only to provide a cleaner environment for high gradient component,
but also, thanks to new control procedure, to provide a real follow-up of the manufacturing process
for each element needing a high degree of cleanliness. Moreover, the upgrade will benefit other
projects such as LHC spare cavities, by upgrading their manufacturing and assembling process.
Additional external equipment:
Name - Description: Comment:
UPW production unit Production of UPW
UPW tank Buffer UPW use
High pressure pump 100 bars needed
Primary vacuum pump Oil free
Secondary vacuum pump Oil free
Table 3: cleanroom upgrade, additional equipment, in blue are the UPW related equipment
6
Figure 1: Cleanroom at SM18, present configuration
7
Figure 2: Cleanroom at SM18, configuration proposal.
8
Appendix I: Equipment table 1 (Priority A1). Light blue rows are elements of the equipment described in the dark blue row on top of them.
Name - Description: Qty: Cleanliness
class:
Price/unit chf
(ExW):
Total prices
chf (Exw): Providers: Manufacturers: Comments: Priority:
Low Pressure Rinsing
Equipment 1 Class 100
Nan CERN CERN
A1
SM18 clean room upgrade 1 Class 100
to 10 640 000,00 640 000,00 Company 1 Company 1
1st estimate. On site
works should not
exceed 6 weeks
A1
New Personnel Access
Class 1000
Company 1 Company 1
A1
New Cleaning Area
Class 100
Company 1 Company 1
A1
Upgrade of the Class 10 000
Area Class 100
Company 1 Company 1
A1
Ionised aire shower
(upgrade) Class 10
Company 1 Company 1
A1
Upgrade of the Class 10 Area
Class 10
Company 1 Company 1
A1
Ultra Pure Water
Production Unit 1 Type 1+ 230 000,00 230 000,00 Company 2 Company 2
A1
Pre-treatment unit 1 grey 80 000,00 80 000,00 Company 2 Company 2 water softener A1
Main system 1 grey 150 000,00 150 000,00 Company 2 Company 2
deionisation + tank +
pump + UV light +
monitoring at 1400 L/h
available in 900 L/h for
130 000,00 CHF
A1
Liquid Particle Counter 1 Class 10 30 650,00 30 650,00 Company 3 Company 4 remote LPC A1
Spray Gun 2 Class 10 250,00 500,00
A1
Total Organic Carbon TOC
& Ohm meter 1
Type1+ &
Class 10 47 000,00 47 000,00 Company 5 Company 5
A1
Ultrasound Cleaning bath 1 Class 100 1 000,00 1 000,00 CERN
magasin CERN
A1
9
Appendix II: Equipment table 2 (Priority A2 to C). Light blue rows are elements of the equipment described in the dark blue row on top of them.
Name - Description: Qty: Cleanliness
class:
Prices / unit
chf (ExW):
Total prices
chf (Exw): Providers: Manufacturers: Comments: Priority:
High Pressure Rinsing
System 1 Class 10 522 000,00 522 000,00 To be defined To be defined
Based on DESY's new
HPR, some
modifications could be
necessary to adapt it
at CERN
A2
Stainless Steel Cabinet 1 Nan To be defined To be defined A2
Rinsing System 1 Nan To be defined To be defined A2
Touch Control Device 1 Nan To be defined To be defined Optional A2
High Pressure Pump 1 Grey 80 000,00 80 000,00 To be defined To be defined
Too big for the system,
a smaller compressor
will reduce the cost of
the system
A2
Bacteria Analysis Procedure 1 Class 100 Nan To be defined To be defined Should be done by an
external company B
Fog Generator 1 Class 100 to
10 12 700,00 12 700,00 Company 3 Company 6 B
O2 survey system
Class 100 to
10 Nan To be defined To be defined
To be define when the
new cleanroom air
condition will be known
B
Optical inspection system for
Cavities 1 Class 100 68 000,00 68 000,00 Company 7 Company 7
Raw estimation from
DESY, their system
was loan by KEK
B
Air monitoring system 1 Class 100
to 10 22 990,00 Company 3 Company 4 C
Air Partcile Counter 3 Class 10 3 665,00 10 995,00 Company 3 Company 4 R2014 C
Air Partcile Counter 3 Class 100 3 665,00 10 995,00 Company 3 Company 4 R2014 C
Vacuum pump for Particle
counter 1 Grey 1 000,00 1 000,00 Company 3 Company 4 C
10
Appendix III : Equipment table 3 (Priority C to D). Light blue rows are elements of the equipment described in the dark blue row on top of them.
Name - Description: Qty: Cleanliness
class:
Prices / unit
chf (ExW):
Total prices
chf (Exw): Providers: Manufacturers: Comments: Priority:
Ionic Pumping system 1 Class 100
to 10 7 000,00 7 000,00 Company 8 Company 8 C
Ionic Pump 1 Class 100 Nan Company 8 Company 8 VacIon Plus 75 C
Power Supply 1 Grey Nan Company 8 Company 8 C
Controller 1 Class 100 Nan Company 8 Company 8 Dual unit single channel C
Leak Detection system 1 Class 100 30 262,50 30 262,50 Company 9 Company 9 SmartTest HLT 570 C
He leak detection system
(dry pump) 1 Class 100 27 795,00 27 795,00 Company 9 Company 9 C
Wireless remote 1 Class 100 2 467,50 2 467,50 Company 9 Company 9 C
Pumping Group 1 Grey 17 234,00 17 234,00 Company 9 Company 9 HiCube Turbo
pumping station C
Primary Pump 1 Grey
Nan Company 9 Company 9 C
Secondary Pump 1 Grey Nan Nan Company 9 Company 9 C
Air tight boxes & Cabinets Class 100 Nan To be defined To be defined D
Anemometer Probe 1 Class 100 to
10 720,00 720,00 Company 3 Company 4 D
Differential Pressure Probe 3 Class 100 to
10 480,00 1 440,00 Company 3 Company 4 D
11
Appendix IV: Prices for each steps and its percentage over the total cost.
Total: 1 631 496,50 CHF 100,00 %
A1 + A2 1 471 150,00 CHF 90,20 %
A1 949 150,00 CHF 58,20 %
A2 522 000,00 CHF 32,00 %
B 80 700,00 CHF 5,00 %
C 77 486,50 CHF 4.70 %
D 2 160,00 CHF 0,10 %
12
1 E. Montesinos, SPL Main power Coupler (SPL-MC) Cleanroom requirements, May 17th, 2010.
2 O. Capatina, Fabrication of Nb and Cu SPL cavities and required tools CERN Satus, SPL Cavity Working Group
Meeting, February 8th, 2010.
3 N. Krupka, T. Ebeling, K. Escherich, A. Matheisen, Morales Zimmermann, B. Petersen, D. Reschke, N. Steinhau-
Kuehl, F. Zhu, Quality control at the TTF-Cleanroom infrastructure for cavity-processing.
4 N. Krupka, K. Escherich, M. Habermann, K. Harries, A. Matheisen, B. Petersen, Quality control update of the
cleanroom for superconducting multi cell cavities at DESY, contribution to the SRF2005, Ithaca, New-York, USA
5 K.Escherich, A.Matheisen, N.Krupka, B.Petersen, M.Schmökel, Clean-room facilities for high gradient resonator
preparation, contribution to the SRF2005, Ithaca, New-York, USA
6 C. Benvenuti, P. Bernard, D. Bloess, G. Cavallari, E. Chiaveri, E. Haebel, N. Hilleret, J. Tückmantel and W.
Weingarten, Superconducting niobium sputter-coated copper cavity modules for the LEP energy upgrade, CERN
7 A. Matheisen, Feng Zhu, Preparation of the RF power couplers for the tesla test facility, TESLA
collaboration 8 Y. Iwashita, H. Hayano, Y. Tajima, Development of a high resolution camera and observations of superconducting
cavities, Proceeding of EPAC08, Genoa, Italy
9S. Aderhold, Optical inspection of SRF cavities at Desy, Proceedings of IPAC’10, Kyoto, Japan