LIFE Project Number
LIFE12 ENV/FI/597
Progress Report Covering the project activities from 01/01/2015 to 31/12/2015
Reporting Date
31/03/2016
Reduction of wastewater nutrient load: demonstrations and modelling
N-SINK
Data Project
Project location Hämeenlinna, Finland
Project start date: 01/08/2013
Project end date: 31/07/2017
Total budget 1 118 260€
EC contribution: 594 130€
(%) of eligible costs 50%
Data Beneficiary
Name Beneficiary University of Helsinki, Lammi Biological Station
Contact person Mr Jussi Huotari
Postal address Pääjärventie 320, FI-16900 Lammi, FINLAND
Telephone +358 50 415 4405
Fax: Fax: +358 2941 40746
E-mail [email protected]
Project Website http://www.helsinki.fi/lammi/NSINK/
Progress report LIFE+ 2
1. Table of contents.
1. Table of contents ........................................................................................................... 2
2. List of key words and abbreviations ........................................................................... 2
3. Executive summary ...................................................................................................... 3
3.1. General progress ................................................................................................... 3
3.2. Assessment as to whether the project objectives and work plan are still
viable ...................................................................................................................... 3
3.3. Problems encountered .......................................................................................... 3
4. Administrative part ...................................................................................................... 3
5. Technical part ............................................................................................................... 5
5.1. Actions .................................................................................................................... 5
5.1.1. Action A ...................................................................................................... 5
5.1.2. Action B ....................................................................................................... 5
5.1.3. Action C ...................................................................................................... 8
5.1.4. Action D .................................................................................................... 13
5.2. Envisaged progress until next report ................................................................ 14
5.3. Impact .................................................................................................................. 16
5.4. Outside LIFE ....................................................................................................... 16
6. Financial part .............................................................................................................. 17
6.1. Costs incurred ..................................................................................................... 17
7. Annexes ....................................................................................................................... 19
7.1. Deliverables ......................................................................................................... 19
7.2. Dissemination material ....................................................................................... 19
2. List of key-words and abbreviations (when appropriate).
CH4 Methane gas
CO2 Carbon dioxide gas
Denitrification Reduction of nitrate to dinitrogen gas
DNRA Dissimilatory nitrate reduction to ammonium
DPHYS Department of Physics, University of Helsinki
FIWA Finnish Water Utilities Association
IPT Isotope pairing technique
LBS Lammi Biological Station, University of Helsinki
Luke Natural Resources Institute Finland
N2 Dinitrogen gas
N2O Nitrous oxide gas
SYKE Finnish Environment Institute
UJ University of Jyväskylä
WWTP Waste water treatment plant
Progress report LIFE+ 3
3. Executive summary
3.1. General progress.
The project has generally progressed according to the proposal. All the set milestones
have been accomplished as planned. Sediment filtration demonstration in Keuruu is
ready for more detailed analysis of the results and demonstrations in Vanajavesi and
Lammi will be ready in spring 2016. A modelling framework for the integration of
ecological and economic models for the spatial optimization of cost effective
nitrogen abatement measures is ready and first model runs done. Final calibrations of
the ecological models and improvement of the economic model with additional
abatement measures are in progress. We expect a full scale economic model
including all relevant abatement measures to be ready in the autumn 2016.
3.2. Assessment as to whether the project objectives and work plan are still viable.
The proposal is still valid and we foresee no obstacles preventing us to achieve the
goals of the project.
3.3. Problems encountered
Keuruu demonstration exceeded budgeted costs, which compromised the
implementation of the demonstration in Petäjävesi. However, municipality of
Petäjävesi has promised to cover the costs of the sediment filtration system and
demonstration will start in spring 2016. It is somewhat later than foreseen in the
project plan but the results will be ready to the final report.
Unexpected problems with nitrification at Paroinen WWTP have postponed the
planned third and last demonstration period in autumn 2105. The demonstration will
be implemented in spring 2016 after ice melt. The delay will not have an effect on
other actions.
4. Administrative part
According to the project plan steering and advisory board (SAB) assembled twice in 2015
(12 May and 17 November). One coordination/science meeting was organized on 7
October 2015 and one SKYPE meeting 25 November 2015 for planning of stakeholder
workshop held on 2 December 2015. LBS and UJ met in Jyväskylä 12 March 2015 to
look at the results of sediment filtration demonstrations as well as to plan related
forthcoming actions and SYKE and LUKE (former MTT) together organized data sharing
and integration of the models. The meetings and workshops were organized in
cooperation between beneficiaries. Additionally partners communicated by e-mail and
telephone whenever necessary.
Since 1 January 2015 legal status of MTT changed due to integration of several
governmental research institutes to form LUKE and thus, we prepared a request of an
Amendment to the project. The Amendment has already been signed by the Commission
and the coordinating beneficiary.
One sab member, Timo Heinonen, the managing director of HS-vesi Oy started in a new
job and his replacement, Jukka Meriluoto, will join the SAB. Saara Kukkonen (MTK
Häme) replace Kari Aikio in SAB during his leave of absence (18 May 2015 – 11 May
2016).
There is a discrepancy in the project plan between the proposed deadlines of the final
reports of Actions B.2 (D3.4, deadline 31 May 2016), B.3 (D4.3, deadline 30 April 2017)
Progress report LIFE+ 4
and C.3 (D 7.4, deadline 31 December 2016). Action B.2 and C.3 produces input data
about the effects of the abatement measures on water quality to the Action B.3, which in
turn produces input data of the required abatement measures to modelling in Actions B.2
and C.3. In this iterative modelling process (see D 7.1) final results of the different
actions will be ready about the same time. Thus, we request new deadlines for
Deliverables D3.4, Final report of the model demonstrations (31 May 2016 → 31 April
2017) and D7.4, the Final report of the Action C.3 (31 December 2016 → 31 April
2017).
At present any extension of the project duration seems unnecessary.
The following reports have been delivered since the start of the project:
-Inception report
-Midterm Report
-Amendment
Figure 1. Schematic figure of the project management and team structure. Team
blocks (bottom row) represent also team responsibilities as well as involvement (in
parentheses) of the actions. Team members in parentheses are crucial to the project
due to their expertise but they get their salary from other sources.
Progress report LIFE+ 5
5. Technical part
5.1. Action A
5.1.1. Action A: Preparation of the study sites for the N-SINK demonstration action
ACTION A.1: Choosing the study and monitoring sites based on the
hydrological and technical survey
Besides Hämeenlinna/Paroinen, Keuruu and Petäjävesi, we added Lammi
WWTP to the sediment filtration demonstration sites to get another variety of
approaches to the N removal by denitrification in the sediments (see Action B.1).
Additional measurements of waste water flow with CTD were conducted in
Keuruu and Vanajavesi by DPHYS in January and February 2015 to check the
waste water flow and representativeness of the sampling points during
demonstration. In winter 2015 the quality of ice and snow meltwater and water
beneath the ice was examined in Lake Vanajavesi by the UH geophysics team
(DPHYS; Matti Leppäranta, Ioanna Merkouriadi and Fang Yang). Also
hydrographic soundings were made to cover a larger area, and the growth and
melting of ice was examined. The data will be used in implementation of an ice
model to cover the all-year physical behaviour of the lake.
ACTION A.2: Drafting the environmental permit for the N-SINK sediment
filtration in the medium-size wastewater treatment
It came evident that sediment filtration demonstration in Petäjävesi does not need
water permit, as it is done by the WWTP itself, and does not cause changes in the
original permit of the WWTP. Also demonstration in Lammi (see Action B.1)
does not change conditions set in the existing water permit of Lammi WWTP.
Action A is now completed.
5.1.2. Action B
ACTION B.1: N-SINK sediment filtration demonstrations
Construction plans of the filtration systems of Keuruu and Petäjävesi are based
on the hydraulic modelling provided by Pöyry PLC. Clean Waters-project of
Vapo Oy was chosen to construct, install and disassemble the filtration system.
The length of the filtration system of Keuruu was 30 meters, built from a PE-pipe
(diameter 630 mm), and had 50 holes (diameter 30 mm) on each side. The
filtration system was constructed and installed between 15 and 16 October 2014
and disassembled on 2 November 2015. A group of scuba divers (Päijänteen
Sukelluspalvelu) took care of the installation and disassembling. The total costs
of the Keuruu filtration system were higher than expected in the budget. It is not
reasonable to use the same filtration system in Petäjävesi as the WWTP outflow
is much smaller and the size of the pipe is 1/3 of the size of the Keuruu pipe.
Moreover, even installation of the same system in Petäjävesi would be costly. In
the negotiations with Petäjävesi municipality on 11 November 2015, however,
they promised to take care of the expenses on the installation of new filtration
system. In Petäjävesi, the demonstration will start in spring 2016.
Progress report LIFE+ 6
The filtration system tested in Keuruu did not interrupt the waste water treatment
processes in Keuruu WWTP and the new technology did not increase phosphorus
release from the sediments. Filtration system increased the actual and potential
rates of denitrification near the waste water discharge pipe and did not increase
N2O emissions or DNRA rates.
Water discharge from Paroinen WWTP is different from that in Keuruu and
Paroinen, because the treated wastewater is released to a ditch (Rautamonoja)
draining into a shallow bay of Lake Vanajavesi, instead of being led through a
discharge pipe deeper in the lake. As the waste water flow is already spatially
optimized on sediment surface it allowed us to assess a different approach in this
N-SINK demonstration. Depart from the plan we did not use the filtration fabric
or plastic pipeline, but instead we study the overall denitrification at this specific
site in the original conditions. To be able to estimate the effectiveness of this
ecosystem service, we constructed large mesocosm demonstration in summer
2015. We used watertight fencing around the sediment and the overlying water,
replaced the water inside the fencing with the treated waste water from
Rautamonoja and monitored changes in nitrogen species inside “boxes”. The
demonstration construction resembles one outlined in report “N-SINK sediment
filtration demonstrations: Progress report” (M 2.1), except flow-through
approach could not be used due to high concentration of suspended solids in the
water, which clogged the tubing resulting inaccurate flow rate control crucial to
the approach. The demonstration was implemented twice within two week
periods in 2015, but the third and last period had to be postponed until spring
2016 due to problems in nitrification processes in Paroinen WWTP. This is not
be causing delays to related actions but the results can be applied as soon they are
attained. Land owners in Keuruu and Paroinen were informed of the
demonstrations, and the public opinion supported the actions.
With support by FIWA, a student of Häme University of Applied Sciences
conducted, as a practical part of a thesis, a factorial experiment on response of
denitrification rate on temperature by using treated waste water from Paroinen
WWTP and sediment from Rautamonoja mouth. Results of this experiment will
support our determination of overall denitrification in front of Rautamonoja
mouth in Lake Vanajavesi.
In spring 2015 we included another approach in our demonstration varieties as
Sari Uusheimo (Maj and Tor Nessling Foundation stipendiate) started to study
denitrification activity of the post settling pond at Lammi WWTP. Since March
2015 water quality of inlet and outlet of the pond has been sampled in 3-4 week
interval and denitrification activity has been measured three times in the pond by 15NO3 labelling and IPT-method. Sampling will last until spring 2016 to
complete a full year. Preliminary results indicate retention of >20% of total P and
60% of total N in the pond between March and December, denitrification being
responsible of about 10% of the N retention during open water period.
Progress report LIFE+ 7
ACTION B.2. Long term and model demonstrations of catchment scale N
retention
Demonstration of long term changes in the water quality due to the protection
actions in heavily loaded river basins in southern Finland. Development of
scenarios of nutrient purification in waste water treatment and in agricultural
production to mitigate nutrient losses to waters and air.
B.2.1. Empirical analysis of lake water quality in the Vanajavesi drainage basin
In this task, we analyse the reasons for long term changes in water quality of
eight lakes in the Vanajavesi drainage basin. The preliminary results of the
analysis were shown in the Midterm report. In 2015, we planned further
processing and analyses of the data. For that we applied additional funding. The
funding granted allows this work to be carried out in 2016.
B.2.2. Model demonstrations of the N retention
We used the semi-distributed catchment scale N model INCA to analyse in detail
the process rates. The INCA models are distributed, dynamic process-based
models, which can take into account in detail the variability of agricultural
management practices, soil types and point sources (see D3.3 and M7.2). Further,
the INCA model allows also running of agricultural and waste water treatment
scenarios in connection to an economical model. This is also essential for a cost-
effective allocation of abatement measures (see D 7.1). The next step then is to
upscale INCA model scenario results as export coefficients to a larger river basin
by using the river basin scale model WSFS-VEMALA in the Kokemäenjoki
basin (Action C.3).
We selected one sub-basin (Mustajoki) in the Vanajavesi drainage basin and the
whole Porvoonjoki river basin to be modelled by the INCA model. We produced
preliminary model applications to both sub-basins, as well as simulated the effect
of different fertilization levels on the crop yield and nutrient leaching on
agricultural fields, and as effluents from sewage treatments plants as point
sources. In 2015, the calibration was improved by comparing the simulated
denitrification fluxes against measured ones. Further, the simulated vegetation
uptake was calibrated against measured N balances of typical crops. That data
was provided as input to economical optimization model in Action B3 to make
preliminary runs. We established an interactive map tool on the project web-page
to present some of the project results, where the preliminary results of nitrogen
sources in Mustajoki and Porvoonjoki are shown. The preliminary results of the
INCA modelling were presented for stake holders on 2.12.2015 (report annexed,
M 3.4).
The INCA modelling is done by Kirsti Granlund and Katri Rankinen (SYKE).
The modelling work will continue in 2016. We request a new deadline for
Deliverable 3.4, the Final report of model demonstrations (31 May 2016 → 31
April 2017).
Progress report LIFE+ 8
ACTION B.3: Demonstration of spatially cost-effective allocation of nutrient
abatement measures at watershed level
The main purpose of Action B.3 is to address the economic viability of sediment
filtering approach relative to other potential nutrient abatement measures that
could be implemented in Finland to reduce nitrogen loading to lakes and the
Baltic Sea. To this end, this action aims to build a model to analyse cost-
efficiency of different abatement measures numerically, the main attention and
the biggest contribution being on the optimal spatial distribution of abatement
measures.
In the first modelling phase, we only introduced a single potential abatement
measure, reducing inorganic nitrogen fertilization that could be applied in
different sub-catchments of Lake Vanajavesi. After the first model results
introduced in the report “First model results, up-scaling and scenario building”
(M 7.2), we have focused on other abatement measures. In 2015, we included in
the model several additional abatement measures, namely restoring wetlands,
improving the level of wastewater treatment in treatment plants, extending the
coverage of waste water network, and introducing reduced tillage. This work has
been done in close cooperation with other actions, so that the yield function and
leaching parameters are based on the calibrations of INCA-N –model and the
retention parameter, depicting the movement of nutrients in the catchment area,
is based on VEMALA –model. The extended model version is now in operation
and the project is progressing as scheduled. According to preliminary results the
total cost of reducing 100 tons of nitrogen load to Lake Vanajavesi is 380 000
Euros per year. The costs increase substantially if the target is increased: The
cost of reaching the target of 200 tons of nitrogen is 1.2 million Euros annually.
The most cost-efficient abatement measures are reduced tillage and improving
the effectiveness of wastewater treatment plant.
In addition to the modelling work, we carried out an extensive literature review
on the Baltic Sea scale on other models, the set of measures they include, their
results, and the differences between our modelling approach and theirs. In the
next stage, we will consider new abatement measures, including sediment
filtration, to be included to the model and we will extend the results to
Porvoonjoki catchment.
This literature review and the work to introduce these new abatement measures
as a part of the economic model are now ongoing.
Lassi Ahlvik, Heini Toikkanen and Pekka Kinnunen (LUKE) have been
responsible for the economic modelling. Tiina Kituniemi has been the office
secretary of the project, responsible for the financial management at LUKE.
5.1.3. Action C
ACTION C.1: Monitoring the ecosystem effects of sediment filtering in Lake
Keurusselkä
Progress report LIFE+ 9
C.1.1: Monitoring denitrification and DNRA (unfavoured reduction of NO3 to
NH4) rates in the recipient lakes
In Keuruu, sediment samples were taken four times in 2015. In Petäjävesi,
samples were taken two times in 2015 (Table 1). Sanni Aalto (UJ), Anu Karvinen
(UJ; Maj and Tor Nessling Foundation stipendiate), Eveliina Kinnunen (UJ) and
Olli Nousiainen (UJ) were responsible of the field sampling. Sampling was done
from the points described in report “Description of the flow directions and
monitoring points of demonstration sites” (M 1.1). For measurement of
denitrification and DNRA, 21-27 sediment cores were taken per sampling trip.
Cores were incubated with 15NO3 in laboratory, following IPT-method and
produced N2 gas was later measured with isotope ratio mass spectrometer
[Isoprime IRMS (Isotope-Ratio Mass Spectrometry)]. To measure DNRA,
additional acid trapping was done and the concentrations of labelled ammonium
(15NH4) were measured with IRMS (Thermo). Sanni Aalto (UJ) has analysed and
calculated all N2 results for 2015, except the results from the last sampling
occasion (21 October 2015). Sanni Aalto (UJ), Anu Karvinen (UJ; Maj and Tor
Nessling Foundation stipendiate) and Eveliina Kinnunen (UJ) have prepared and
calculated the final results of all DNRA samples. Monitoring will continue in
Petäjävesi when the sediment filtering system is installed.
C.1.2: Monitoring N2O production rates in the recipient lakes and wastewater
treatment plants
For Keuruu and Petäjävesi, N2O production rates were measured from the same
sediment core samples than denitrification and DNRA (Table 1). Sanni Aalto,
and Anu Karvinen collected gas samples from IPT-incubations and measured
them with Isoprime IRMS. The amount of samples is shown below (Table 1). All
N2O samples were analysed and results calculated during 2015. N2O production
rates were measured from nitrification pool and discharge three times in Keuruu
WWTP in 2015 (13 Apr 2015, 22 June 2015, 3 Sept 2015) and one time in
Petäjävesi WWTP (3 Sep 2015). In addition, N2O production was measured from
clarification pool in Keuruu and in Petäjävesi on 3 Sept 2015.
Table 1. Details on the field sampling done in Keuruu and Petäjävesi in 2015.
Date
Number of
sampling points
No of Denitrification
samples
No of DNRA
samples
No of N2O
samples
No of NO2+3
samples
No of PO4/NH
4 samples
Keuruu 19.1.2015 9 9 5 9 9 5
19.5.2015 7 7 5 7 7 5
11.8.2015 7 7 5 7 7 7
20.10.2015 7 7 5 7 7 7
Petäjävesi 28.1.2015 7 7 5 7 7 5
28.5.2015 7 7 5 7 7 5
Progress report LIFE+ 10
C.1.3: Monitoring other physical and biological parameters in the recipient lake
and wastewater treatment processes
Oxygen, pH, conductivity and temperature were measured at one meter vertical
intervals from each sampling point in every sampling occasion. Nitrate
concentration was measured from each sampling point and phosphate and
ammonium from the first five to seven points (Table 1). UJ was responsible of
the monitoring of physical and biological parameters.
ACTION C.2: Monitoring the ecosystem effects of sediment filtering in Lake
Vanajavesi
C.2.1: Monitoring denitrification and DNRA (unfavored reduction of NO3 to
NH4) rates in the recipient lakes
Denitrification activity was measured five times in 2015. Samples also for
DNRA determinations were collected in 2015. Denitrification activity is clearly
increased in the sediments under the influence of treated waste water from
Paroinen WWTP. The determinations will be continued 2-3 times until summer
2016.
C.2.2: Monitoring N2O production rates in the recipient lakes and wastewater
treatment plants
Approximately monthly sampling of N2O as well as CH4 and CO2 was conducted
during the ice covered seasons continuing with a three weeks interval after the
ice-off in Lake Vanajavesi in 2015. Areal N2O production rate will be estimated
from dissolved gas concentrations in situ and flux estimations instead of
sediment core incubations. The measurements will be continued 5 times until
summer 2016.
We started N2O measurements at Paroinen WWTP on 19 January 2015 and
sampled 11 times within 3-10 weeks interval. All type of process waters were
sampled from altogether 21 sampling points on 26 February and 11 March 2015.
Based on that survey we selected seven points for monitoring including process
waters where highest N2O concentrations were found, as well as those pools
where we expect N2O production to occur, i.e. denitrification and nitrification
pools. In addition to dissolved gas samples, we measured gas flux between
process waters and the atmosphere with floating chamber technique seven times
from those seven sampling points to determine gas exchange rate, which is
required for determination of N2O production rates of WWTP. We will continue
2-3 times until summer 2016. For reference we made similar measurements at
Janakkala and Valkeakoski WWTPs on 7 September 2015.
C.2.3: Monitoring other physical and biological parameters in the recipient lake
and wastewater treatment processes
Water quality measurements were conducted at the same time with the N2O
measurements in Lake Vanajavesi. Monitored parameters included
concentrations of nitrite and nitrate, ammonium, total nitrogen, phosphate, total
Progress report LIFE+ 11
phosphorus, chl-a, dissolved organic carbon and dissolved oxygen as well as
measurements of pH, conductivity and water temperature. The measurements
will be continued 5 times until summer 2016.
ACTION C.3: Verification of catchment scale N retention models
In this action, the INCA model scenario results are up-scaled to the larger
Kokemäenjoki river basin (Figure 2; 27046 km2, lake percentage 11%) by using
the river basin scale model VEMALA. The Kokemäenjoki river discharges to the
Bothnian Sea, which is regarded largely as nitrogen limited. VEMALA is an
especially useful model when large river systems are considered.
Figure 2. Map of Finland with highlighted Kokemäenjoki and Vanajavesi
subcatchments.
The up-scaling of INCA-N with VEMALA v.3 was tested over the Vanajavesi
drainage basin (M 7.2) in correlation with the INCA model and the economic
model. The nitrogen load reduction estimate from the economic model was used
as an input for the nutrient retention simulation with VEMALA. The VEMALA
model was then able to simulate the impact of the load reduction on the water
quality of Lake Vanajanselkä. Furthermore, VEMALA v.3 was tested in the
Kokemäenjoki river basin. The preliminary results of the simulations, under
present conditions, using the terrestrial model VEMALA-N as a nitrogen input to
the river rather than the INCA-N up-scaled results, were presented at the
stakeholders meeting on 2.12.2015. The nitrogen retention simulated in the
Kokemäenjoki catchment was too high (around 50%, Figure 3) as mineralisation
and denitrification rates were too high. The simulations will be improved before
the final results are published.
Progress report LIFE+ 12
Figure 3. Total nitrogen loading into rivers and into the Sea with nitrogen
retention in the river network.
Markus Huttunen and Marie Korppoo (SYKE) have been responsible for this
action. The preliminary results of the Kokemäenjoki results with VEMALA were
presented at the stakeholders meeting on 2 December 2015.
We request a new deadline for Deliverable 7.4, the Final report of the Action C.3
(31 December 2016 → 31 April 2017).
Lake Keurusselkä 3-D flow model
Determining the contact time between waste water effluent and the lake bottom
in dynamic real world conditions, requires either direct field measurements or the
use of a 3-D hydrodynamic model. In this task we build a high-resolution 3-D
model of Lake Keurusselkä around the wastewater outlet using the open source,
European Union Public License (EUPL) COHERENS code. The results will be
used as part of a denitrification model in estimation of the effects of sediment
filtration system in Keurusselkä in Action B.1.
Necessary preparatory work for Lake Keurusselkä 3-D model has been done in
2015. We gathered available input/measurement data and made additional ADCP
measurements over a period of 1 April – 22 June 2015. We processed the data,
introduced a new version of COHERENS codebase into service (V2.9) and
developed Lake Keurusselkä specific high resolution model codes. We also
produced preliminary simulations to test individual parts of the model. Next we
will integrate the modelling components together and produce the 3-D flow and
contact time conditions needed by the denitrification study model.
The hydrodynamic modelling work is done by Janne Juntunen and Janne
Ropponen (SYKE) and will continue in 2016. The denitrification model work is
done by Sanni Aalto (UJ). Modelling results are expected before 06/2016.
Progress report LIFE+ 13
5.1.4. Action D
ACTION D.1: Communication and dissemination
For communication and dissemination, project documentation is put in project
www –pages: http://www.helsinki.fi/lammi/NSINK/.
Dissemination activity has still been intended to increase the general awareness
of the project and to a greater extent also to present the preliminary results.
Presentations have been given in international workshops and meetings (ASLO,
Granada, Spain; DTU, Copenhagen, Denmark; iCoN4, Edmonton, Canada; NJF,
Moss, Norway) as well as locally. The project and its results have been presented
also in university courses.
Workshops and Meetings
- 12 – 13 January 2015, Maaperätieteenpäivät, Helsinki (Katri Rankinen, SYKE)
Annex
- 24 February, ASLO meeting, Granada, Spain (Sanni Aalto, UJ) Annex
- 26 May, DTU project meeting, Technical University of Denmark, Copenhagen,
Denmark (Sanni Aalto, UJ)
- 29 June 2015, iCoN4, Edmonton, Canada (Sanni Aalto, UJ) Annex
- 27 – 29 October 2015, NJF seminar and workshop The Water Framework
Directive and Agriculture, Moss, Norway (Katri Rankinen, SYKE)
- 1 October 2015, meeting with Vapo CleanWaters, Jyväskylä (Sanni Aalto,
Marja Tiirola, UJ)
- 18 August 2016, Regional council of Häme, Hämeenlinna (Jussi Huotari, Lauri
Arvola, LBS)
- 10 November 2015, Vanajavesikeskus, Vesijaosto, Hämeenlinna (Lauri Arvola,
LBS)
- 11 November 2015, meeting with technical director, environmental engineer
and secretary, Petäjävesi, Finland (Sanni Aalto, Marja Tiirola, UJ)
- 12 December 2015, Stakeholder workshop, Helsinki, Annex
Courses
- 12 – 13 August 2015, Helsinki Summer School, Lammi Biological Station
(Jussi Huotari, Lauri Arvola, LBS)
- 23 November 2015, Lappeenranta University of Technology (Katri Rankinen,
SYKE)
Progress report LIFE+ 14
Table 2. List of milestones.
Name of the Milestone Action Deadline Completion
M 8.1 www-pages opened D 1 30/09/2013 20/09/2013
M 9.1 Selection of project coordinator
and advisory board
E 1 31/10/2013 07/10/2013
01/11/2013
M 8.2 Starting seminar organized D 1 30/11/2013 01/11/2013
M 9.2 First annual meeting of SAB E 1 30/12/2013 12/12/2013
M 4.1 Workshop 1 organized and
reported
B 3 31/12/2013 19/12/2013
M 1.1 Sites and monitoring points
described
A 1 31/01/2014 31/12/2014
M 3.2 Workshop 1 organized and
reported
B 2 31/05/2014 27/05/2014
M 1.2 Environmental permit applied
drafted
A 1 30/06/2014 25/02/2014
M 9.3 Second half-year meeting of SAB E 1 30/06/2014 14/05/2014
M 7.2 First scenarios ready C 3 30/11/2014 30/11/2014
M 9.4 Second year meeting of SAB E 1 31/12/2014 12/11/2014
M 2.1 Progress report 1 ready B 1 28/02/2015 28/02/2015
M 9.3 Third half-year meeting of SAB E 1 30/06/2015 12/05/2015
M 3.4 Workshop 2 organized and
reported
B 2 31/12/2015 02/12/2015
M 7.3 Workshop will be organized C 3 31/12/2015 02/12/2015
M 9.6 Third annual meeting of SAB E 1 31/12/2015 17/11/2015
M 3.5 Final report ready B 2 31/05/2016 →
31/04/2017*
M 5.2 Publications submitted C 1 30/06/2016
M 6.2 Publications submitted C 2 30/06/2016
M 9.7 Fourth half-year meeting of SAB E 1 30/06/2016
M 4.4 Workshop 2 organized and
reported
B 3 30/11/2016
M 8.3 Workshops organized D 1 30/11/2016
M 7.5 Final report ready C 3 31/12/2016 →
31/04/2017**
M 9.8 Fourth annual meeting of SAB E 1 31/12/2016
M 2.2 Final report ready B 1 28/02/2017
M 4.5 Report 5 ready (D 4.3) B 3 30/04/2017
M 8.4 Final seminar organized D 1 31/05/2017
M 9.11 Final annual meeting of the
project
E 1 31/05/2017
M 5.3 Final Report ready C 1 30/06/2017
M 6.3 Final Report ready C 2 30/06/2017 * We request a new deadline for Deliverable 3.4 (M 3.5), the Final report of the Action B.2 (31
December 2016 → 31 April 2017). See section 4. Administrative part.
** We request a new deadline for Deliverable 7.4 (M 7.5), the Final report of the Action C.3 (31
December 2016 → 31 April 2017). See section 4. Administrative part.
5.2. Envisaged progress until next report.
The next report will be the Final report and we expect all actions to be completed by then.
Progress report LIFE+ 15
Table 3. Gantt chart illustrating the proposed and actual progress of the planned actions. Tasks/
Activities
2013 2014 2015 2016 2017
1T 2T 3T 4T 1T 2T 3T 4T 1T 2T 3T 4T 1T 2T 3T 4T 1T 2T 3T 4T
Overall project schedule
Proposed
O
O
X
O
Actual
Action A1 Proposed
Actual
Action B1
Action B2
Proposed
Actual
Action B3
Action C1
Proposed
Actual
Action C2
Action C3
Action D Proposed
Actual
Action E Proposed
Actual
Start date Mid-Term End date
X=Progress reports
Progress report LIFE+ 16
5.3. Impact:
Environmental Policy & Governance Clear interest has been indicated towards the project and its results of what would be the
appropriate way of discharging treated waste waters from WWTPs to recipient waters. Our
preliminary results indicate that nitrogen removal can be enhanced by optimising the spatial
allocation of the treated waste water discharge on inland water sediment surfaces.
Demonstration in Keuruu indicated that there are no technical obstacles to sediment filtering
technique and nitrogen removal by denitrification can be enhanced without harmful side
effects on the bottom sediment of a lake. Demonstrations in Paroinen and Lammi show that
denitrification is increased also in the sediments of shallow areas although there nutrients can
be available to primary producers as well. There is intention to apply funding to study the
possibilities of harvesting algal biomass as well as increasing the algal growth in post-
treatment ponds such as in Lammi WWTP. Preliminary results from cost-efficiency analysis,
not yet including all abatement measures, imply that the most cost-efficient abatement
measures are reduced tillage and improving the effectiveness of the wastewater treatment
plant.
We estimate that if our results and suggestions are taken into practice it has an effect on
nitrogen load to inland waters and the Baltic Sea. How much N load can be reduced is still to
be estimated.
5.4. Outside LIFE
Parallel actions outside LIFE to support the objectives of N-SINK have been funded
by Maj and Tor Nessling Foundation, FIWA and the Academy of Finland. For this
support we have been able to analyse samples, include additional site to the
demonstrations and conduct a laboratory experiment to complement demonstration in
Paroinen. These support has been crucial to the project due to the fact that EC
substantially cut the proposed budget in the late phase of the application process.
Progress report LIFE+ 17
6. Financial part
6.1. Costs incurred
Budget breakdown categories Total cost in € Costs incurred from the start
date to 31.12.2015 in €
% of total costs
1. Personnel 1 053 941 529 660 50.3
2. Travel and subsistence 25 000 12 604 50.4
3. External assistance 21 000 11 334 54.0
4. Durable goods
Infrastructure
Equipment
Prototype 25 000 29 300 117.2
5. Land purchase / long-term lease
6. Consumables 20 101 6 126 30.5
7. Other Costs 0 4 515
8. Overheads 43 218 22 338 51.7
TOTAL 1 188 260 615 876 51.8
Prototype costs exceeded the budgeted. There are costs included also in external
assistance, such as prototype construction plan, which were originally included in
prototype costs.
Other costs include expenses, such as participation fees, thought to be included in
travel costs in the original budget. It also includes some costs not foreseen in the
budget, such as hepatitis vaccines due to working in WWTPs.
Progress report LIFE+ 18
Action number and name Foreseen costs
Spent so far Remaining Projected final cost
A1. Preparation of the study sites for the N-SINK demonstration action
66 345 40 275 26 070 66 345
B1. N-SINK sediment filtration demonstrations
113 752
88 799 24 953 113 752
B2. Long-term and model demonstrations of catchment scale N retention
184 083 90 251 93 832 184 083
B3. Demonstration of spatially costeffective allocation of nutrient abatement measures at watershed level
146 400 60 561 85 839 146 400
C1. Monitoring the ecosystem effects of sediment filtering in Lake Keurusselkä
124 326 63 946 60 380 124 326
C2. Monitoring the ecosystem effects of sediment filtering in Lake Vanajavesi
46 014 33 689 12 325 46 014
C3. Verification of catchment scale N retention models
180 665 32 787 147 878 180 665
D1. Communication and dissemination
67 205 6 514 60 691
67 205
D2. Development of after Life communication plan
225 0 225 225
E1. Project management and monitoring of the project progress
216 027 176 716 39 311 216 027
TOTAL 1 145 042 593 538 551 504 1 145 042
Progress report LIFE+ 19
7. Annexes
7.1. Deliverables
No deliverables were due in the reporting period.
7.2. Dissemination materials
Poster_Maaperätieteenpäivät2015
Poster_ASLO2015
Poster_iCoN2015
M3.4_Workshop_report