+ All Categories
Home > Documents > LIFE12 ENV/FI/597 Progress Report Covering the project ... · In this iterative modelling process...

LIFE12 ENV/FI/597 Progress Report Covering the project ... · In this iterative modelling process...

Date post: 14-Aug-2020
Category:
Upload: others
View: 5 times
Download: 0 times
Share this document with a friend
19
LIFE Project Number LIFE12 ENV/FI/597 Progress Report Covering the project activities from 01/01/2015 to 31/12/2015 Reporting Date 31/03/2016 Reduction of wastewater nutrient load: demonstrations and modelling N-SINK Data Project Project location Hämeenlinna, Finland Project start date: 01/08/2013 Project end date: 31/07/2017 Total budget 1 118 260EC contribution: 594 130(%) of eligible costs 50% Data Beneficiary Name Beneficiary University of Helsinki, Lammi Biological Station Contact person Mr Jussi Huotari Postal address Pääjärventie 320, FI-16900 Lammi, FINLAND Telephone +358 50 415 4405 Fax: Fax: +358 2941 40746 E-mail [email protected] Project Website http://www.helsinki.fi/lammi/NSINK/
Transcript
Page 1: LIFE12 ENV/FI/597 Progress Report Covering the project ... · In this iterative modelling process (see D 7.1) final results of the different actions will be ready about the same time.

LIFE Project Number

LIFE12 ENV/FI/597

Progress Report Covering the project activities from 01/01/2015 to 31/12/2015

Reporting Date

31/03/2016

Reduction of wastewater nutrient load: demonstrations and modelling

N-SINK

Data Project

Project location Hämeenlinna, Finland

Project start date: 01/08/2013

Project end date: 31/07/2017

Total budget 1 118 260€

EC contribution: 594 130€

(%) of eligible costs 50%

Data Beneficiary

Name Beneficiary University of Helsinki, Lammi Biological Station

Contact person Mr Jussi Huotari

Postal address Pääjärventie 320, FI-16900 Lammi, FINLAND

Telephone +358 50 415 4405

Fax: Fax: +358 2941 40746

E-mail [email protected]

Project Website http://www.helsinki.fi/lammi/NSINK/

Page 2: LIFE12 ENV/FI/597 Progress Report Covering the project ... · In this iterative modelling process (see D 7.1) final results of the different actions will be ready about the same time.

Progress report LIFE+ 2

1. Table of contents.

1. Table of contents ........................................................................................................... 2

2. List of key words and abbreviations ........................................................................... 2

3. Executive summary ...................................................................................................... 3

3.1. General progress ................................................................................................... 3

3.2. Assessment as to whether the project objectives and work plan are still

viable ...................................................................................................................... 3

3.3. Problems encountered .......................................................................................... 3

4. Administrative part ...................................................................................................... 3

5. Technical part ............................................................................................................... 5

5.1. Actions .................................................................................................................... 5

5.1.1. Action A ...................................................................................................... 5

5.1.2. Action B ....................................................................................................... 5

5.1.3. Action C ...................................................................................................... 8

5.1.4. Action D .................................................................................................... 13

5.2. Envisaged progress until next report ................................................................ 14

5.3. Impact .................................................................................................................. 16

5.4. Outside LIFE ....................................................................................................... 16

6. Financial part .............................................................................................................. 17

6.1. Costs incurred ..................................................................................................... 17

7. Annexes ....................................................................................................................... 19

7.1. Deliverables ......................................................................................................... 19

7.2. Dissemination material ....................................................................................... 19

2. List of key-words and abbreviations (when appropriate).

CH4 Methane gas

CO2 Carbon dioxide gas

Denitrification Reduction of nitrate to dinitrogen gas

DNRA Dissimilatory nitrate reduction to ammonium

DPHYS Department of Physics, University of Helsinki

FIWA Finnish Water Utilities Association

IPT Isotope pairing technique

LBS Lammi Biological Station, University of Helsinki

Luke Natural Resources Institute Finland

N2 Dinitrogen gas

N2O Nitrous oxide gas

SYKE Finnish Environment Institute

UJ University of Jyväskylä

WWTP Waste water treatment plant

Page 3: LIFE12 ENV/FI/597 Progress Report Covering the project ... · In this iterative modelling process (see D 7.1) final results of the different actions will be ready about the same time.

Progress report LIFE+ 3

3. Executive summary

3.1. General progress.

The project has generally progressed according to the proposal. All the set milestones

have been accomplished as planned. Sediment filtration demonstration in Keuruu is

ready for more detailed analysis of the results and demonstrations in Vanajavesi and

Lammi will be ready in spring 2016. A modelling framework for the integration of

ecological and economic models for the spatial optimization of cost effective

nitrogen abatement measures is ready and first model runs done. Final calibrations of

the ecological models and improvement of the economic model with additional

abatement measures are in progress. We expect a full scale economic model

including all relevant abatement measures to be ready in the autumn 2016.

3.2. Assessment as to whether the project objectives and work plan are still viable.

The proposal is still valid and we foresee no obstacles preventing us to achieve the

goals of the project.

3.3. Problems encountered

Keuruu demonstration exceeded budgeted costs, which compromised the

implementation of the demonstration in Petäjävesi. However, municipality of

Petäjävesi has promised to cover the costs of the sediment filtration system and

demonstration will start in spring 2016. It is somewhat later than foreseen in the

project plan but the results will be ready to the final report.

Unexpected problems with nitrification at Paroinen WWTP have postponed the

planned third and last demonstration period in autumn 2105. The demonstration will

be implemented in spring 2016 after ice melt. The delay will not have an effect on

other actions.

4. Administrative part

According to the project plan steering and advisory board (SAB) assembled twice in 2015

(12 May and 17 November). One coordination/science meeting was organized on 7

October 2015 and one SKYPE meeting 25 November 2015 for planning of stakeholder

workshop held on 2 December 2015. LBS and UJ met in Jyväskylä 12 March 2015 to

look at the results of sediment filtration demonstrations as well as to plan related

forthcoming actions and SYKE and LUKE (former MTT) together organized data sharing

and integration of the models. The meetings and workshops were organized in

cooperation between beneficiaries. Additionally partners communicated by e-mail and

telephone whenever necessary.

Since 1 January 2015 legal status of MTT changed due to integration of several

governmental research institutes to form LUKE and thus, we prepared a request of an

Amendment to the project. The Amendment has already been signed by the Commission

and the coordinating beneficiary.

One sab member, Timo Heinonen, the managing director of HS-vesi Oy started in a new

job and his replacement, Jukka Meriluoto, will join the SAB. Saara Kukkonen (MTK

Häme) replace Kari Aikio in SAB during his leave of absence (18 May 2015 – 11 May

2016).

There is a discrepancy in the project plan between the proposed deadlines of the final

reports of Actions B.2 (D3.4, deadline 31 May 2016), B.3 (D4.3, deadline 30 April 2017)

Page 4: LIFE12 ENV/FI/597 Progress Report Covering the project ... · In this iterative modelling process (see D 7.1) final results of the different actions will be ready about the same time.

Progress report LIFE+ 4

and C.3 (D 7.4, deadline 31 December 2016). Action B.2 and C.3 produces input data

about the effects of the abatement measures on water quality to the Action B.3, which in

turn produces input data of the required abatement measures to modelling in Actions B.2

and C.3. In this iterative modelling process (see D 7.1) final results of the different

actions will be ready about the same time. Thus, we request new deadlines for

Deliverables D3.4, Final report of the model demonstrations (31 May 2016 → 31 April

2017) and D7.4, the Final report of the Action C.3 (31 December 2016 → 31 April

2017).

At present any extension of the project duration seems unnecessary.

The following reports have been delivered since the start of the project:

-Inception report

-Midterm Report

-Amendment

Figure 1. Schematic figure of the project management and team structure. Team

blocks (bottom row) represent also team responsibilities as well as involvement (in

parentheses) of the actions. Team members in parentheses are crucial to the project

due to their expertise but they get their salary from other sources.

Page 5: LIFE12 ENV/FI/597 Progress Report Covering the project ... · In this iterative modelling process (see D 7.1) final results of the different actions will be ready about the same time.

Progress report LIFE+ 5

5. Technical part

5.1. Action A

5.1.1. Action A: Preparation of the study sites for the N-SINK demonstration action

ACTION A.1: Choosing the study and monitoring sites based on the

hydrological and technical survey

Besides Hämeenlinna/Paroinen, Keuruu and Petäjävesi, we added Lammi

WWTP to the sediment filtration demonstration sites to get another variety of

approaches to the N removal by denitrification in the sediments (see Action B.1).

Additional measurements of waste water flow with CTD were conducted in

Keuruu and Vanajavesi by DPHYS in January and February 2015 to check the

waste water flow and representativeness of the sampling points during

demonstration. In winter 2015 the quality of ice and snow meltwater and water

beneath the ice was examined in Lake Vanajavesi by the UH geophysics team

(DPHYS; Matti Leppäranta, Ioanna Merkouriadi and Fang Yang). Also

hydrographic soundings were made to cover a larger area, and the growth and

melting of ice was examined. The data will be used in implementation of an ice

model to cover the all-year physical behaviour of the lake.

ACTION A.2: Drafting the environmental permit for the N-SINK sediment

filtration in the medium-size wastewater treatment

It came evident that sediment filtration demonstration in Petäjävesi does not need

water permit, as it is done by the WWTP itself, and does not cause changes in the

original permit of the WWTP. Also demonstration in Lammi (see Action B.1)

does not change conditions set in the existing water permit of Lammi WWTP.

Action A is now completed.

5.1.2. Action B

ACTION B.1: N-SINK sediment filtration demonstrations

Construction plans of the filtration systems of Keuruu and Petäjävesi are based

on the hydraulic modelling provided by Pöyry PLC. Clean Waters-project of

Vapo Oy was chosen to construct, install and disassemble the filtration system.

The length of the filtration system of Keuruu was 30 meters, built from a PE-pipe

(diameter 630 mm), and had 50 holes (diameter 30 mm) on each side. The

filtration system was constructed and installed between 15 and 16 October 2014

and disassembled on 2 November 2015. A group of scuba divers (Päijänteen

Sukelluspalvelu) took care of the installation and disassembling. The total costs

of the Keuruu filtration system were higher than expected in the budget. It is not

reasonable to use the same filtration system in Petäjävesi as the WWTP outflow

is much smaller and the size of the pipe is 1/3 of the size of the Keuruu pipe.

Moreover, even installation of the same system in Petäjävesi would be costly. In

the negotiations with Petäjävesi municipality on 11 November 2015, however,

they promised to take care of the expenses on the installation of new filtration

system. In Petäjävesi, the demonstration will start in spring 2016.

Page 6: LIFE12 ENV/FI/597 Progress Report Covering the project ... · In this iterative modelling process (see D 7.1) final results of the different actions will be ready about the same time.

Progress report LIFE+ 6

The filtration system tested in Keuruu did not interrupt the waste water treatment

processes in Keuruu WWTP and the new technology did not increase phosphorus

release from the sediments. Filtration system increased the actual and potential

rates of denitrification near the waste water discharge pipe and did not increase

N2O emissions or DNRA rates.

Water discharge from Paroinen WWTP is different from that in Keuruu and

Paroinen, because the treated wastewater is released to a ditch (Rautamonoja)

draining into a shallow bay of Lake Vanajavesi, instead of being led through a

discharge pipe deeper in the lake. As the waste water flow is already spatially

optimized on sediment surface it allowed us to assess a different approach in this

N-SINK demonstration. Depart from the plan we did not use the filtration fabric

or plastic pipeline, but instead we study the overall denitrification at this specific

site in the original conditions. To be able to estimate the effectiveness of this

ecosystem service, we constructed large mesocosm demonstration in summer

2015. We used watertight fencing around the sediment and the overlying water,

replaced the water inside the fencing with the treated waste water from

Rautamonoja and monitored changes in nitrogen species inside “boxes”. The

demonstration construction resembles one outlined in report “N-SINK sediment

filtration demonstrations: Progress report” (M 2.1), except flow-through

approach could not be used due to high concentration of suspended solids in the

water, which clogged the tubing resulting inaccurate flow rate control crucial to

the approach. The demonstration was implemented twice within two week

periods in 2015, but the third and last period had to be postponed until spring

2016 due to problems in nitrification processes in Paroinen WWTP. This is not

be causing delays to related actions but the results can be applied as soon they are

attained. Land owners in Keuruu and Paroinen were informed of the

demonstrations, and the public opinion supported the actions.

With support by FIWA, a student of Häme University of Applied Sciences

conducted, as a practical part of a thesis, a factorial experiment on response of

denitrification rate on temperature by using treated waste water from Paroinen

WWTP and sediment from Rautamonoja mouth. Results of this experiment will

support our determination of overall denitrification in front of Rautamonoja

mouth in Lake Vanajavesi.

In spring 2015 we included another approach in our demonstration varieties as

Sari Uusheimo (Maj and Tor Nessling Foundation stipendiate) started to study

denitrification activity of the post settling pond at Lammi WWTP. Since March

2015 water quality of inlet and outlet of the pond has been sampled in 3-4 week

interval and denitrification activity has been measured three times in the pond by 15NO3 labelling and IPT-method. Sampling will last until spring 2016 to

complete a full year. Preliminary results indicate retention of >20% of total P and

60% of total N in the pond between March and December, denitrification being

responsible of about 10% of the N retention during open water period.

Page 7: LIFE12 ENV/FI/597 Progress Report Covering the project ... · In this iterative modelling process (see D 7.1) final results of the different actions will be ready about the same time.

Progress report LIFE+ 7

ACTION B.2. Long term and model demonstrations of catchment scale N

retention

Demonstration of long term changes in the water quality due to the protection

actions in heavily loaded river basins in southern Finland. Development of

scenarios of nutrient purification in waste water treatment and in agricultural

production to mitigate nutrient losses to waters and air.

B.2.1. Empirical analysis of lake water quality in the Vanajavesi drainage basin

In this task, we analyse the reasons for long term changes in water quality of

eight lakes in the Vanajavesi drainage basin. The preliminary results of the

analysis were shown in the Midterm report. In 2015, we planned further

processing and analyses of the data. For that we applied additional funding. The

funding granted allows this work to be carried out in 2016.

B.2.2. Model demonstrations of the N retention

We used the semi-distributed catchment scale N model INCA to analyse in detail

the process rates. The INCA models are distributed, dynamic process-based

models, which can take into account in detail the variability of agricultural

management practices, soil types and point sources (see D3.3 and M7.2). Further,

the INCA model allows also running of agricultural and waste water treatment

scenarios in connection to an economical model. This is also essential for a cost-

effective allocation of abatement measures (see D 7.1). The next step then is to

upscale INCA model scenario results as export coefficients to a larger river basin

by using the river basin scale model WSFS-VEMALA in the Kokemäenjoki

basin (Action C.3).

We selected one sub-basin (Mustajoki) in the Vanajavesi drainage basin and the

whole Porvoonjoki river basin to be modelled by the INCA model. We produced

preliminary model applications to both sub-basins, as well as simulated the effect

of different fertilization levels on the crop yield and nutrient leaching on

agricultural fields, and as effluents from sewage treatments plants as point

sources. In 2015, the calibration was improved by comparing the simulated

denitrification fluxes against measured ones. Further, the simulated vegetation

uptake was calibrated against measured N balances of typical crops. That data

was provided as input to economical optimization model in Action B3 to make

preliminary runs. We established an interactive map tool on the project web-page

to present some of the project results, where the preliminary results of nitrogen

sources in Mustajoki and Porvoonjoki are shown. The preliminary results of the

INCA modelling were presented for stake holders on 2.12.2015 (report annexed,

M 3.4).

The INCA modelling is done by Kirsti Granlund and Katri Rankinen (SYKE).

The modelling work will continue in 2016. We request a new deadline for

Deliverable 3.4, the Final report of model demonstrations (31 May 2016 → 31

April 2017).

Page 8: LIFE12 ENV/FI/597 Progress Report Covering the project ... · In this iterative modelling process (see D 7.1) final results of the different actions will be ready about the same time.

Progress report LIFE+ 8

ACTION B.3: Demonstration of spatially cost-effective allocation of nutrient

abatement measures at watershed level

The main purpose of Action B.3 is to address the economic viability of sediment

filtering approach relative to other potential nutrient abatement measures that

could be implemented in Finland to reduce nitrogen loading to lakes and the

Baltic Sea. To this end, this action aims to build a model to analyse cost-

efficiency of different abatement measures numerically, the main attention and

the biggest contribution being on the optimal spatial distribution of abatement

measures.

In the first modelling phase, we only introduced a single potential abatement

measure, reducing inorganic nitrogen fertilization that could be applied in

different sub-catchments of Lake Vanajavesi. After the first model results

introduced in the report “First model results, up-scaling and scenario building”

(M 7.2), we have focused on other abatement measures. In 2015, we included in

the model several additional abatement measures, namely restoring wetlands,

improving the level of wastewater treatment in treatment plants, extending the

coverage of waste water network, and introducing reduced tillage. This work has

been done in close cooperation with other actions, so that the yield function and

leaching parameters are based on the calibrations of INCA-N –model and the

retention parameter, depicting the movement of nutrients in the catchment area,

is based on VEMALA –model. The extended model version is now in operation

and the project is progressing as scheduled. According to preliminary results the

total cost of reducing 100 tons of nitrogen load to Lake Vanajavesi is 380 000

Euros per year. The costs increase substantially if the target is increased: The

cost of reaching the target of 200 tons of nitrogen is 1.2 million Euros annually.

The most cost-efficient abatement measures are reduced tillage and improving

the effectiveness of wastewater treatment plant.

In addition to the modelling work, we carried out an extensive literature review

on the Baltic Sea scale on other models, the set of measures they include, their

results, and the differences between our modelling approach and theirs. In the

next stage, we will consider new abatement measures, including sediment

filtration, to be included to the model and we will extend the results to

Porvoonjoki catchment.

This literature review and the work to introduce these new abatement measures

as a part of the economic model are now ongoing.

Lassi Ahlvik, Heini Toikkanen and Pekka Kinnunen (LUKE) have been

responsible for the economic modelling. Tiina Kituniemi has been the office

secretary of the project, responsible for the financial management at LUKE.

5.1.3. Action C

ACTION C.1: Monitoring the ecosystem effects of sediment filtering in Lake

Keurusselkä

Page 9: LIFE12 ENV/FI/597 Progress Report Covering the project ... · In this iterative modelling process (see D 7.1) final results of the different actions will be ready about the same time.

Progress report LIFE+ 9

C.1.1: Monitoring denitrification and DNRA (unfavoured reduction of NO3 to

NH4) rates in the recipient lakes

In Keuruu, sediment samples were taken four times in 2015. In Petäjävesi,

samples were taken two times in 2015 (Table 1). Sanni Aalto (UJ), Anu Karvinen

(UJ; Maj and Tor Nessling Foundation stipendiate), Eveliina Kinnunen (UJ) and

Olli Nousiainen (UJ) were responsible of the field sampling. Sampling was done

from the points described in report “Description of the flow directions and

monitoring points of demonstration sites” (M 1.1). For measurement of

denitrification and DNRA, 21-27 sediment cores were taken per sampling trip.

Cores were incubated with 15NO3 in laboratory, following IPT-method and

produced N2 gas was later measured with isotope ratio mass spectrometer

[Isoprime IRMS (Isotope-Ratio Mass Spectrometry)]. To measure DNRA,

additional acid trapping was done and the concentrations of labelled ammonium

(15NH4) were measured with IRMS (Thermo). Sanni Aalto (UJ) has analysed and

calculated all N2 results for 2015, except the results from the last sampling

occasion (21 October 2015). Sanni Aalto (UJ), Anu Karvinen (UJ; Maj and Tor

Nessling Foundation stipendiate) and Eveliina Kinnunen (UJ) have prepared and

calculated the final results of all DNRA samples. Monitoring will continue in

Petäjävesi when the sediment filtering system is installed.

C.1.2: Monitoring N2O production rates in the recipient lakes and wastewater

treatment plants

For Keuruu and Petäjävesi, N2O production rates were measured from the same

sediment core samples than denitrification and DNRA (Table 1). Sanni Aalto,

and Anu Karvinen collected gas samples from IPT-incubations and measured

them with Isoprime IRMS. The amount of samples is shown below (Table 1). All

N2O samples were analysed and results calculated during 2015. N2O production

rates were measured from nitrification pool and discharge three times in Keuruu

WWTP in 2015 (13 Apr 2015, 22 June 2015, 3 Sept 2015) and one time in

Petäjävesi WWTP (3 Sep 2015). In addition, N2O production was measured from

clarification pool in Keuruu and in Petäjävesi on 3 Sept 2015.

Table 1. Details on the field sampling done in Keuruu and Petäjävesi in 2015.

Date

Number of

sampling points

No of Denitrification

samples

No of DNRA

samples

No of N2O

samples

No of NO2+3

samples

No of PO4/NH

4 samples

Keuruu 19.1.2015 9 9 5 9 9 5

19.5.2015 7 7 5 7 7 5

11.8.2015 7 7 5 7 7 7

20.10.2015 7 7 5 7 7 7

Petäjävesi 28.1.2015 7 7 5 7 7 5

28.5.2015 7 7 5 7 7 5

Page 10: LIFE12 ENV/FI/597 Progress Report Covering the project ... · In this iterative modelling process (see D 7.1) final results of the different actions will be ready about the same time.

Progress report LIFE+ 10

C.1.3: Monitoring other physical and biological parameters in the recipient lake

and wastewater treatment processes

Oxygen, pH, conductivity and temperature were measured at one meter vertical

intervals from each sampling point in every sampling occasion. Nitrate

concentration was measured from each sampling point and phosphate and

ammonium from the first five to seven points (Table 1). UJ was responsible of

the monitoring of physical and biological parameters.

ACTION C.2: Monitoring the ecosystem effects of sediment filtering in Lake

Vanajavesi

C.2.1: Monitoring denitrification and DNRA (unfavored reduction of NO3 to

NH4) rates in the recipient lakes

Denitrification activity was measured five times in 2015. Samples also for

DNRA determinations were collected in 2015. Denitrification activity is clearly

increased in the sediments under the influence of treated waste water from

Paroinen WWTP. The determinations will be continued 2-3 times until summer

2016.

C.2.2: Monitoring N2O production rates in the recipient lakes and wastewater

treatment plants

Approximately monthly sampling of N2O as well as CH4 and CO2 was conducted

during the ice covered seasons continuing with a three weeks interval after the

ice-off in Lake Vanajavesi in 2015. Areal N2O production rate will be estimated

from dissolved gas concentrations in situ and flux estimations instead of

sediment core incubations. The measurements will be continued 5 times until

summer 2016.

We started N2O measurements at Paroinen WWTP on 19 January 2015 and

sampled 11 times within 3-10 weeks interval. All type of process waters were

sampled from altogether 21 sampling points on 26 February and 11 March 2015.

Based on that survey we selected seven points for monitoring including process

waters where highest N2O concentrations were found, as well as those pools

where we expect N2O production to occur, i.e. denitrification and nitrification

pools. In addition to dissolved gas samples, we measured gas flux between

process waters and the atmosphere with floating chamber technique seven times

from those seven sampling points to determine gas exchange rate, which is

required for determination of N2O production rates of WWTP. We will continue

2-3 times until summer 2016. For reference we made similar measurements at

Janakkala and Valkeakoski WWTPs on 7 September 2015.

C.2.3: Monitoring other physical and biological parameters in the recipient lake

and wastewater treatment processes

Water quality measurements were conducted at the same time with the N2O

measurements in Lake Vanajavesi. Monitored parameters included

concentrations of nitrite and nitrate, ammonium, total nitrogen, phosphate, total

Page 11: LIFE12 ENV/FI/597 Progress Report Covering the project ... · In this iterative modelling process (see D 7.1) final results of the different actions will be ready about the same time.

Progress report LIFE+ 11

phosphorus, chl-a, dissolved organic carbon and dissolved oxygen as well as

measurements of pH, conductivity and water temperature. The measurements

will be continued 5 times until summer 2016.

ACTION C.3: Verification of catchment scale N retention models

In this action, the INCA model scenario results are up-scaled to the larger

Kokemäenjoki river basin (Figure 2; 27046 km2, lake percentage 11%) by using

the river basin scale model VEMALA. The Kokemäenjoki river discharges to the

Bothnian Sea, which is regarded largely as nitrogen limited. VEMALA is an

especially useful model when large river systems are considered.

Figure 2. Map of Finland with highlighted Kokemäenjoki and Vanajavesi

subcatchments.

The up-scaling of INCA-N with VEMALA v.3 was tested over the Vanajavesi

drainage basin (M 7.2) in correlation with the INCA model and the economic

model. The nitrogen load reduction estimate from the economic model was used

as an input for the nutrient retention simulation with VEMALA. The VEMALA

model was then able to simulate the impact of the load reduction on the water

quality of Lake Vanajanselkä. Furthermore, VEMALA v.3 was tested in the

Kokemäenjoki river basin. The preliminary results of the simulations, under

present conditions, using the terrestrial model VEMALA-N as a nitrogen input to

the river rather than the INCA-N up-scaled results, were presented at the

stakeholders meeting on 2.12.2015. The nitrogen retention simulated in the

Kokemäenjoki catchment was too high (around 50%, Figure 3) as mineralisation

and denitrification rates were too high. The simulations will be improved before

the final results are published.

Page 12: LIFE12 ENV/FI/597 Progress Report Covering the project ... · In this iterative modelling process (see D 7.1) final results of the different actions will be ready about the same time.

Progress report LIFE+ 12

Figure 3. Total nitrogen loading into rivers and into the Sea with nitrogen

retention in the river network.

Markus Huttunen and Marie Korppoo (SYKE) have been responsible for this

action. The preliminary results of the Kokemäenjoki results with VEMALA were

presented at the stakeholders meeting on 2 December 2015.

We request a new deadline for Deliverable 7.4, the Final report of the Action C.3

(31 December 2016 → 31 April 2017).

Lake Keurusselkä 3-D flow model

Determining the contact time between waste water effluent and the lake bottom

in dynamic real world conditions, requires either direct field measurements or the

use of a 3-D hydrodynamic model. In this task we build a high-resolution 3-D

model of Lake Keurusselkä around the wastewater outlet using the open source,

European Union Public License (EUPL) COHERENS code. The results will be

used as part of a denitrification model in estimation of the effects of sediment

filtration system in Keurusselkä in Action B.1.

Necessary preparatory work for Lake Keurusselkä 3-D model has been done in

2015. We gathered available input/measurement data and made additional ADCP

measurements over a period of 1 April – 22 June 2015. We processed the data,

introduced a new version of COHERENS codebase into service (V2.9) and

developed Lake Keurusselkä specific high resolution model codes. We also

produced preliminary simulations to test individual parts of the model. Next we

will integrate the modelling components together and produce the 3-D flow and

contact time conditions needed by the denitrification study model.

The hydrodynamic modelling work is done by Janne Juntunen and Janne

Ropponen (SYKE) and will continue in 2016. The denitrification model work is

done by Sanni Aalto (UJ). Modelling results are expected before 06/2016.

Page 13: LIFE12 ENV/FI/597 Progress Report Covering the project ... · In this iterative modelling process (see D 7.1) final results of the different actions will be ready about the same time.

Progress report LIFE+ 13

5.1.4. Action D

ACTION D.1: Communication and dissemination

For communication and dissemination, project documentation is put in project

www –pages: http://www.helsinki.fi/lammi/NSINK/.

Dissemination activity has still been intended to increase the general awareness

of the project and to a greater extent also to present the preliminary results.

Presentations have been given in international workshops and meetings (ASLO,

Granada, Spain; DTU, Copenhagen, Denmark; iCoN4, Edmonton, Canada; NJF,

Moss, Norway) as well as locally. The project and its results have been presented

also in university courses.

Workshops and Meetings

- 12 – 13 January 2015, Maaperätieteenpäivät, Helsinki (Katri Rankinen, SYKE)

Annex

- 24 February, ASLO meeting, Granada, Spain (Sanni Aalto, UJ) Annex

- 26 May, DTU project meeting, Technical University of Denmark, Copenhagen,

Denmark (Sanni Aalto, UJ)

- 29 June 2015, iCoN4, Edmonton, Canada (Sanni Aalto, UJ) Annex

- 27 – 29 October 2015, NJF seminar and workshop The Water Framework

Directive and Agriculture, Moss, Norway (Katri Rankinen, SYKE)

- 1 October 2015, meeting with Vapo CleanWaters, Jyväskylä (Sanni Aalto,

Marja Tiirola, UJ)

- 18 August 2016, Regional council of Häme, Hämeenlinna (Jussi Huotari, Lauri

Arvola, LBS)

- 10 November 2015, Vanajavesikeskus, Vesijaosto, Hämeenlinna (Lauri Arvola,

LBS)

- 11 November 2015, meeting with technical director, environmental engineer

and secretary, Petäjävesi, Finland (Sanni Aalto, Marja Tiirola, UJ)

- 12 December 2015, Stakeholder workshop, Helsinki, Annex

Courses

- 12 – 13 August 2015, Helsinki Summer School, Lammi Biological Station

(Jussi Huotari, Lauri Arvola, LBS)

- 23 November 2015, Lappeenranta University of Technology (Katri Rankinen,

SYKE)

Page 14: LIFE12 ENV/FI/597 Progress Report Covering the project ... · In this iterative modelling process (see D 7.1) final results of the different actions will be ready about the same time.

Progress report LIFE+ 14

Table 2. List of milestones.

Name of the Milestone Action Deadline Completion

M 8.1 www-pages opened D 1 30/09/2013 20/09/2013

M 9.1 Selection of project coordinator

and advisory board

E 1 31/10/2013 07/10/2013

01/11/2013

M 8.2 Starting seminar organized D 1 30/11/2013 01/11/2013

M 9.2 First annual meeting of SAB E 1 30/12/2013 12/12/2013

M 4.1 Workshop 1 organized and

reported

B 3 31/12/2013 19/12/2013

M 1.1 Sites and monitoring points

described

A 1 31/01/2014 31/12/2014

M 3.2 Workshop 1 organized and

reported

B 2 31/05/2014 27/05/2014

M 1.2 Environmental permit applied

drafted

A 1 30/06/2014 25/02/2014

M 9.3 Second half-year meeting of SAB E 1 30/06/2014 14/05/2014

M 7.2 First scenarios ready C 3 30/11/2014 30/11/2014

M 9.4 Second year meeting of SAB E 1 31/12/2014 12/11/2014

M 2.1 Progress report 1 ready B 1 28/02/2015 28/02/2015

M 9.3 Third half-year meeting of SAB E 1 30/06/2015 12/05/2015

M 3.4 Workshop 2 organized and

reported

B 2 31/12/2015 02/12/2015

M 7.3 Workshop will be organized C 3 31/12/2015 02/12/2015

M 9.6 Third annual meeting of SAB E 1 31/12/2015 17/11/2015

M 3.5 Final report ready B 2 31/05/2016 →

31/04/2017*

M 5.2 Publications submitted C 1 30/06/2016

M 6.2 Publications submitted C 2 30/06/2016

M 9.7 Fourth half-year meeting of SAB E 1 30/06/2016

M 4.4 Workshop 2 organized and

reported

B 3 30/11/2016

M 8.3 Workshops organized D 1 30/11/2016

M 7.5 Final report ready C 3 31/12/2016 →

31/04/2017**

M 9.8 Fourth annual meeting of SAB E 1 31/12/2016

M 2.2 Final report ready B 1 28/02/2017

M 4.5 Report 5 ready (D 4.3) B 3 30/04/2017

M 8.4 Final seminar organized D 1 31/05/2017

M 9.11 Final annual meeting of the

project

E 1 31/05/2017

M 5.3 Final Report ready C 1 30/06/2017

M 6.3 Final Report ready C 2 30/06/2017 * We request a new deadline for Deliverable 3.4 (M 3.5), the Final report of the Action B.2 (31

December 2016 → 31 April 2017). See section 4. Administrative part.

** We request a new deadline for Deliverable 7.4 (M 7.5), the Final report of the Action C.3 (31

December 2016 → 31 April 2017). See section 4. Administrative part.

5.2. Envisaged progress until next report.

The next report will be the Final report and we expect all actions to be completed by then.

Page 15: LIFE12 ENV/FI/597 Progress Report Covering the project ... · In this iterative modelling process (see D 7.1) final results of the different actions will be ready about the same time.

Progress report LIFE+ 15

Table 3. Gantt chart illustrating the proposed and actual progress of the planned actions. Tasks/

Activities

2013 2014 2015 2016 2017

1T 2T 3T 4T 1T 2T 3T 4T 1T 2T 3T 4T 1T 2T 3T 4T 1T 2T 3T 4T

Overall project schedule

Proposed

O

O

X

O

Actual

Action A1 Proposed

Actual

Action B1

Action B2

Proposed

Actual

Action B3

Action C1

Proposed

Actual

Action C2

Action C3

Action D Proposed

Actual

Action E Proposed

Actual

Start date Mid-Term End date

X=Progress reports

Page 16: LIFE12 ENV/FI/597 Progress Report Covering the project ... · In this iterative modelling process (see D 7.1) final results of the different actions will be ready about the same time.

Progress report LIFE+ 16

5.3. Impact:

Environmental Policy & Governance Clear interest has been indicated towards the project and its results of what would be the

appropriate way of discharging treated waste waters from WWTPs to recipient waters. Our

preliminary results indicate that nitrogen removal can be enhanced by optimising the spatial

allocation of the treated waste water discharge on inland water sediment surfaces.

Demonstration in Keuruu indicated that there are no technical obstacles to sediment filtering

technique and nitrogen removal by denitrification can be enhanced without harmful side

effects on the bottom sediment of a lake. Demonstrations in Paroinen and Lammi show that

denitrification is increased also in the sediments of shallow areas although there nutrients can

be available to primary producers as well. There is intention to apply funding to study the

possibilities of harvesting algal biomass as well as increasing the algal growth in post-

treatment ponds such as in Lammi WWTP. Preliminary results from cost-efficiency analysis,

not yet including all abatement measures, imply that the most cost-efficient abatement

measures are reduced tillage and improving the effectiveness of the wastewater treatment

plant.

We estimate that if our results and suggestions are taken into practice it has an effect on

nitrogen load to inland waters and the Baltic Sea. How much N load can be reduced is still to

be estimated.

5.4. Outside LIFE

Parallel actions outside LIFE to support the objectives of N-SINK have been funded

by Maj and Tor Nessling Foundation, FIWA and the Academy of Finland. For this

support we have been able to analyse samples, include additional site to the

demonstrations and conduct a laboratory experiment to complement demonstration in

Paroinen. These support has been crucial to the project due to the fact that EC

substantially cut the proposed budget in the late phase of the application process.

Page 17: LIFE12 ENV/FI/597 Progress Report Covering the project ... · In this iterative modelling process (see D 7.1) final results of the different actions will be ready about the same time.

Progress report LIFE+ 17

6. Financial part

6.1. Costs incurred

Budget breakdown categories Total cost in € Costs incurred from the start

date to 31.12.2015 in €

% of total costs

1. Personnel 1 053 941 529 660 50.3

2. Travel and subsistence 25 000 12 604 50.4

3. External assistance 21 000 11 334 54.0

4. Durable goods

Infrastructure

Equipment

Prototype 25 000 29 300 117.2

5. Land purchase / long-term lease

6. Consumables 20 101 6 126 30.5

7. Other Costs 0 4 515

8. Overheads 43 218 22 338 51.7

TOTAL 1 188 260 615 876 51.8

Prototype costs exceeded the budgeted. There are costs included also in external

assistance, such as prototype construction plan, which were originally included in

prototype costs.

Other costs include expenses, such as participation fees, thought to be included in

travel costs in the original budget. It also includes some costs not foreseen in the

budget, such as hepatitis vaccines due to working in WWTPs.

Page 18: LIFE12 ENV/FI/597 Progress Report Covering the project ... · In this iterative modelling process (see D 7.1) final results of the different actions will be ready about the same time.

Progress report LIFE+ 18

Action number and name Foreseen costs

Spent so far Remaining Projected final cost

A1. Preparation of the study sites for the N-SINK demonstration action

66 345 40 275 26 070 66 345

B1. N-SINK sediment filtration demonstrations

113 752

88 799 24 953 113 752

B2. Long-term and model demonstrations of catchment scale N retention

184 083 90 251 93 832 184 083

B3. Demonstration of spatially costeffective allocation of nutrient abatement measures at watershed level

146 400 60 561 85 839 146 400

C1. Monitoring the ecosystem effects of sediment filtering in Lake Keurusselkä

124 326 63 946 60 380 124 326

C2. Monitoring the ecosystem effects of sediment filtering in Lake Vanajavesi

46 014 33 689 12 325 46 014

C3. Verification of catchment scale N retention models

180 665 32 787 147 878 180 665

D1. Communication and dissemination

67 205 6 514 60 691

67 205

D2. Development of after Life communication plan

225 0 225 225

E1. Project management and monitoring of the project progress

216 027 176 716 39 311 216 027

TOTAL 1 145 042 593 538 551 504 1 145 042

Page 19: LIFE12 ENV/FI/597 Progress Report Covering the project ... · In this iterative modelling process (see D 7.1) final results of the different actions will be ready about the same time.

Progress report LIFE+ 19

7. Annexes

7.1. Deliverables

No deliverables were due in the reporting period.

7.2. Dissemination materials

Poster_Maaperätieteenpäivät2015

Poster_ASLO2015

Poster_iCoN2015

M3.4_Workshop_report


Recommended