INTRODUCTION TO RAILWAY ENGINEERING
Transcript
Page 1: My Railway Engg. Ppt

INTRODUCTION TO

RAILWAY ENGINEERING

Page 2: My Railway Engg. Ppt

RAILWAY ENGINEERING

The branch of Civil Engineering which deals with the design, construction and maintenance of the railway tracks for safe and efficient movements of trains is called Railway Engineering.

2

Page 3: My Railway Engg. Ppt

As per scope of this book, we shall study here only about construction and maintenance of railway tracks and not with the design of tracks.

SCOPE OF RAILWAY ENGINEERINGA part from design, construction and maintenance of tracks, Railway engineering also includes the study of the following important topics :-

3

Page 4: My Railway Engg. Ppt

Contents

• Introduction to railway• Classification of railways (on the basis of

gauge)• Components of railway track (rails, sleeper,

ballast)

Page 5: My Railway Engg. Ppt

• Geometric design of railway track (cross section, gradient, super elevation)

• Maximum permissible speed• Railway points and crossings• Stations and yards• Platforms

Contents

Page 6: My Railway Engg. Ppt

• Rail transport is where a train runs along a set of two parallel steel rails, known as a railway or railroad. The rails are anchored perpendicular to ties (or sleepers) of timber, concrete or steel, to maintain a consistent distance apart, or gauge. The rails and perpendicular beams are placed on a foundation made of concrete, or compressed earth and gravel in a bed of ballast.

Page 7: My Railway Engg. Ppt

Components of a railway track (Permanent Way)

Rails

Sleepers (Ties)

Ballast

Page 8: My Railway Engg. Ppt
Page 9: My Railway Engg. Ppt
Page 10: My Railway Engg. Ppt

What are the advantages of rail transport?

• It facilitate long distance travel and transport of bulky goods which are not easily transported through motor vehicles.

• It is a quick and more regular form of transport because it helps in the transportation of goods with speed and certainty.

• It helps in the industrialization process of a country by easy transportation of coal and raw-materials at a cheaper rate.

Page 11: My Railway Engg. Ppt

• It encourages mobility of labour ad thereby provides a great scope for employment.

• Railway is the safest form of transport. The chances of accidents and breakdown of railways are minimum as compared to other modes of transport.

• The carrying capacity of the railways is extremely large. • It is the largest public undertaking in the country. Their

charges are based on charge what the traffic can bear principles which helps the poor. In fact, it is a national necessity.

Page 12: My Railway Engg. Ppt

Disadvantages

• The railway requires a large investment of capital.• Another disadvantages of railway transport is its

inflexibility. It routes and timings cannot be adjusted to individual requirements.

• Rail transport cannot provide door to door service as it is tied to a particular track. Intermediate loading or unloading involves greater cost, more wear and tear and wastage of time. The time cost of terminal operations are a great disadvantage of rail transport.

Page 13: My Railway Engg. Ppt

• Railway transport is unsuitable and uneconomical for short distances and small traffic of goods.

Page 14: My Railway Engg. Ppt

. SYSTEMS OF RAILWAYSThe Railways can be provided on, above the below the ground surface, suiting to the area. Further, the Railways below the ground surface can be constructed just below the ground surface can be constructed just below the ground level or at greater depths.

14

Page 15: My Railway Engg. Ppt

There are, therefore, the following four systems of Railways :-

1. Surface railways;2. Elevated railways;3. Under ground railways;4. Tube railways.

1) Surface railways :-The railways provided over the ground surface are known as surface railways.

Suitability :-This system is Railways is most extensively used throughout the world

15

Page 16: My Railway Engg. Ppt

because this is the best system for transporting people and goods. In

surface railways, the various means like*level crossings,**over-bridge or***under-bridge are to be provided for crossing of the railway

and road traffic safely and efficiently.

2) Elevated railways :-The railways provided at higher or

elevated portion, above the ground surface are called “high level” or

“elevated railways”.In this system of Railways, a

16

Page 17: My Railway Engg. Ppt

continuous viaduct supported on piers, columns, etc. is constructed and the track is carried on its steel deck. This system is very costly because buildings like stations, waiting halls, offices are to be constructed at high levels requiring stair cases, escalators, etc. but elevated railways cause little obstruction due to piers, columns supporting the track. Suitability :- Elevated railways are suitable in the heavily congested urban areas where the under ground railways cannot be

17

Page 18: My Railway Engg. Ppt

constructed.3) Under ground railways :- The railways

provided just below ground level are called “low level or underground railways”.

In this system of Railways, tunnels are constructed for carrying tracks through them and a over - bridge is necessary at every road crossing to carry the road traffic over the railway traffic. Due to ventilation problems in tunnels, electricity is the only source of power for traction in under ground railways.

18

Page 19: My Railway Engg. Ppt

Advantages :-i. This system provides rapid and unobstructed

transportation.ii. This system helps in reducing traffic

congestion problems.iii. This system provides safety during aerial

attack in war. Suitability :- Under ground railways are suitable

in the heavily congested urban areas where the traffic intensity on roads is heavy.

19

Page 20: My Railway Engg. Ppt

Tube railways :- The railway provided underground at a greater depth of about 18

m or more (up to 52 m) are called tube railways.

This system of railways is so called as the section of the underground tunnels,

carrying the track, is to avoid the interference of the tracks with water and gas pipes,

sewerage systems and oil or drainage pipes, etc

Some important features of the tube railways are given below :-

20

Page 21: My Railway Engg. Ppt

i. The railways stations have to be of cylindrical form.

ii. Escalators or moving stair cases are to be constructed to reach the tube railways.

iii. Only electric traction to be used to avoid the smoke and ventilation problems.

iv. Automatic signaling system is to be used.

21

Page 22: My Railway Engg. Ppt

V. Such a mechanism of the train is to be used that it cannot start until all the doors are closed, and it automatically stops, if the signal is at ‘STOP’ position.

This system of railways is used by the London Post Office in transporting mails through a small diameter tunnel with automatic control without any driver.

22

Page 23: My Railway Engg. Ppt

REQUIREMENTS OF A GOOD TRACK

• Gauge should be correct and uniform• Alignment of track should be correct• Transition curves should provided wherever

required• Perfect cross levels between rails• Gradient should be as gentle as possible• Points and crossings (turnouts) should be

designed and maintained properly

Page 25: My Railway Engg. Ppt

COMPONENT PARTS OF A PERMANENT WAY :-

The following are the component parts of a permanent way or a railway track :-

• Formation or sub grade ;• Ballast ;• Sleepers ;• Rails ;• Fixtures and fastenings.All these component parts of a permanent way

are illustrated in Fig given below :-

25

Page 26: My Railway Engg. Ppt

26

Page 27: My Railway Engg. Ppt

REQUIREMENTS OF AN IDEAL PERMANENT WAY

The following are the principal requirements of an ideal permanent way or of a good railway track :-

i. The gauge of the permanent way should be uniform, correct and it should not get altered.

ii. Both the rails should be at the same level on tangent (straight) portion of the track.

iii. Proper amount of *superelevation should

27

Page 28: My Railway Engg. Ppt

be provided to the outer rail above the inner rail on curved portion of the track.

iv. The permanent way should be sufficiently strong against lateral forces.

v. The curves, provided in the track, should be properly designed.

vi. An even and uniform gradient should be provided through out the length of the track.

vii. The **tractive resistance of the track should be minimum.

viii. The design of the permanent way should be such that the load of the train is

28

Page 29: My Railway Engg. Ppt

uniformly distributed on both the rails so as to prevent unequal settlement of the track.

ix. It Should provide adequate elasticity in order to prevent the harshness of impacts between the rails and the moving wheel loads of a train.

x. It should be free from excessive rail joints and all the joining should be properly designed and constructed.

xi. All the components parts such as rails, sleepers, ballast, fixtures and

29

Page 30: My Railway Engg. Ppt

fastenings, etc. should satisfy the design requirements.

xii. All the fixtures and fastenings such as chairs, bearing plates, fish plates, fish bolts, spikes etc. should be strong enough to withstand the stresses occurring in the track.

xiii.All the *points and crossings, laid in the permanent way, should be properly designed and carefully constructed.

xiv. It should be provided with fence near30

Page 31: My Railway Engg. Ppt

level crossings and also in urban areas.xv. It should be provided with proper drainage

facilities so as to drain off the rain water quickly away from the track.

xvi. It should be provided with safe and strong bridges coming in the alignment of the track.

xvii.It should be provided with safe and strong bridges coming in the alignment of the track.

xviii.It should be so constructed that 31

Page 32: My Railway Engg. Ppt

Elements of Railway tracks• The track on a railway or railroad, also known as the

permanent way, is the structure consisting of the rails, fasteners, sleepers and ballast (or slab track), plus the underlying sub grade.

• For clarity it is often referred to as railway track or railroad track.

Page 33: My Railway Engg. Ppt

33

Page 34: My Railway Engg. Ppt

Track Formation

Requirements for Choosing a Track System:Trains running on Track do not cause excessive environmental pollution in the form

of noise and ground vibration.

1. Costs of the total service life of the track must be as low as possible.

2. Maintenance should be low and as inexpensive as possible

The purpose of track is to transfer train loads to the formation.

Page 35: My Railway Engg. Ppt
Page 36: My Railway Engg. Ppt

Running Rails

Page 37: My Railway Engg. Ppt

Track gauge (Rail gauge)

• The distance between the inner sides of the

heads of the two load bearing rails that make up a single railway line.

Page 38: My Railway Engg. Ppt

Various gauges used worldwide

Page 39: My Railway Engg. Ppt

Various gauges used worldwideGauge Width (mm) Used in

Standard Gauge 1435 England, USA, Canada, China, Australia

Broad Gauge (BG) 16761670

India, Brazil, ArgentinaSpain, Portugal

Broad Gauge (Russian Gauge)

1524 Russia, Finland

Cape Gauge 1067 Japan, Newzealand

Meter Gauge (MG) 1000915

India, FranceIreland

Narrow Gauge 672610

India, PakistanS. Africa

Page 40: My Railway Engg. Ppt

TYPES OF GAUGES PREVALENT IN INDIA

The different gauges prevalent in India are of the following these types :-

1. Broad gauge (1676),2. Metre gauge (1000),3. Narrow gauge (762 mm & 610 mm).

40

Page 41: My Railway Engg. Ppt

41

1. Broad Gauge :- When the clear horizontal distance between the inner faces of two parallel rails forming a track is 1676mm the gauge is called Broad Gauge (B.G)

This gauge is also known as standard gauge of India and is the broadest gauge of the world.

The Other countries using the Broad Gauge are Pakistan, Bangladesh, SriLanka, Brazil, Argentine,etc.50% India’s railway tracks have been laid to this gauge.

Page 42: My Railway Engg. Ppt

Suitability :- Broad gauge is suitable under the following Conditions :-(i) When sufficient funds are available for the railway project.(ii) When the prospects of revenue are very bright.This gauge is, therefore, used for tracks in plain areas which are densely populated i.e. for routes of maximum traffic, intensities and at places which are centers of industry and commerce.2. Metre Gauge :- When the clear horizontal distance between the inner faces of two

42

Page 43: My Railway Engg. Ppt

parallel rails forming a track is 1000mm, the gauge is known as Metre Gauge (M.G)The other countries using Metre gauge are France, Switzerland, Argentine, etc. 40% of India’s railway tracks have been laid to this gauge.Suitability :- Metre Gauge is suitable under the following conditions:-(i) When the funds available for the railway project are inadequate.(ii) When the prospects of revenue are not very bright.This gauge is, therefore, used for tracks in under-developed areas and in interior areas 43

Page 44: My Railway Engg. Ppt

Where traffic intensity is small and prospects for future development are not very bright.3.Narrow Gauge :- When the clear horizontal distance between the inner faces of two parallel rails forming a track is either 762mm or 610mm, the gauge is known as Narrow gauge (N.G)The other countries using narrow gauge are Britain, South Africa, etc. 10% of India’s railway tracks have been laid to this gauge.Suitability :- Narrow gauge is suitable under the following conditions :-

44

Page 45: My Railway Engg. Ppt

( i) When the construction of a track with wider gauge is prohibited due to the provision of sharp curves, steep gradients, narrow bridges and tunnels etc.(ii) When the prospects of revenue are not very bright.This gauge is, therefore, used in hilly and very thinly populated areas. The feeder gauge is commonly used for feeding raw materials to big government manufacturing concerns as well as to private factories such as steel plants, oil refineries, sugar factories, etc.

45

Page 46: My Railway Engg. Ppt

Factors Affecting the Adoption of a Particular Gauge

The following are the factors which affect the adoption of a particular gauge for the track :-

I. Intensity of Population.II. Intensity of Traffic.III. Industrial and Commercial development of the

Locality.IV. Prospects of future development of the area.

46

Page 47: My Railway Engg. Ppt

V. Funds available for th railway project.VI. Topographical and Geological Features of the

country.

Effects of Breaking the GaugeOne country should have only one gauge

throughout its various parts. But the policy of India and its Topographical, Geological and Financial conditions have led to adopt various gauges in its different parts. The various effects of breaking or change of gauge are discussed below :-

47

Page 48: My Railway Engg. Ppt

1. Advantages of Breaking the Gauge :-i). The most effective advantage of breaking the

gauge is to render the railway an economical and profitable concern.

ii). It facilitates the provision of a steeper gradient, sharp curves and narrow tunnels by adopting a less wide gauge in hilly and rocky areas.

2. Disadvantages of Breaking the Gauge :-i). It causes much inconvenience to the passengers

while changing the train at station, with change of gauge.

48

Page 49: My Railway Engg. Ppt

ii). It causes delay in movement of people and goods.iii). It results in wastage of time.iv). It involves extra labour for unloading and reloading the goods. The goods are also likely to be damaged or dislocated at the junction station, having change of gauge.v). It requires the provision of extra and costly transshipment yards, godowns, sheds, etc. at every junction station having change of gauge.vi). It causes extreme difficulty in quick movement of military and ammunition during war days. 49

Page 50: My Railway Engg. Ppt

Which gauge is the best?• Historically…..

the choice of gauge was partly arbitrary and partly a response to local conditions

• Narrow-gauges - cheaper to build and can negotiate sharper curves

• Broad-gauges - give greater stability and permit higher speeds.

Page 51: My Railway Engg. Ppt

Coning of Wheels Coning of wheels is a method of beveling the wheels to avoid depreciation to the

wheels and rims. Normally the wheels are conned by a cone of semi-angle. It is based on the theorem of coning.

• Introduction Railway wheels are usually beveled by means of a cone semi-angle of the

arrangement of 1/20 (rad.). The rails are also fixed at this identical angle to the perpendicular. The width of the wheel is generally 140 mm and the rail top is approximately 80 mm. The proportions of the region of liaison between an encumbered wheel and rail reckon on the exact shapes of the wheel pace and rail head. It also depends on the extent of the load occupied.

51

Page 52: My Railway Engg. Ppt
Page 53: My Railway Engg. Ppt
Page 54: My Railway Engg. Ppt

Coning of Wheels

• The space between the inner borders of wheel rims is by and large kept less than the measurement of the track. This results in a gap between the wheel rims and running ends of the rails which is approximately equal to 1 cm, (3/8) on both side. More often than not, the tread of wheels is perfectly the dead centre of the beginning of the rail, since the wheel is chamfered to keep it in this middle position involuntarily. Thus the wheels are beveled at an inclination of 1 in 20.

• Advantages of coning the wheels• (i) Coning the wheels reduces the depreciation of the wheel rims and rails.

Depreciation is caused because of the friction action of rims with inner faces of the rail top.

• (ii) Coning also gives an option of lateral drift of the hinge with is wheels.• (iii) Coning also prevents, to some extent, the slipping of the wheels.

54

Page 55: My Railway Engg. Ppt

Theory of Coning

• On a railway level track, the moment the hinge loco motes towards one rail, the wheel tread width above the rail steps-up but reduces over the other rail. This forbids the auxiliary movement and hinge pulls back to its original position. This is possible only if the diameters on both rails are equal and the pressure on both the rails is also equal.

• On a coiled path, because of rigidity of the wheel bottom either of the wheels has to slip by a measure equal to the differentiation of length or else the axle has to move outward a bit so that a tread with longer diameter is formed over the outer rail whereas a slighter diameter tread is formed over the inner rail.

55

Page 56: My Railway Engg. Ppt

FISH PLATE AND FISH BOLTS

Page 57: My Railway Engg. Ppt

BEARING PLATE (BENEATH THE SLEEPER)

Page 58: My Railway Engg. Ppt

HIGH SPEED RAILS

• Passenger rail transport that operates significantly faster than the normal speed of rail traffic.

• The U.S. Department of Transportation's reasonably expected to reach sustained speeds of more than 125 mph (201 km/h)

Page 59: My Railway Engg. Ppt

WORLD RECORD

• The world record for conventional high-speed rail is held by the V150 of France, a specially configured and heavily modified train which clocked 574.8 km/h (357.2 mph) on a test run.

• Aerodynamic designs (to reduce drag, lift, and noise), air brakes, regenerative braking, stronger engines, dynamic weight shifting, etc

• High Speed train in France (> 574 Kmph)

Page 60: My Railway Engg. Ppt

RAILWAY POINTS AND CROSSINGS

Page 61: My Railway Engg. Ppt

POINTS AND CROSSINGS• To divert trains from one track to another, a

special arrangement is made….so that

…the inside flange of the wheel can move on the diverted track.

• Such arrangement is called “POINTS AND CROSSINGS”

Page 62: My Railway Engg. Ppt

A Right Hand Diversion

Page 63: My Railway Engg. Ppt

• Points + crossings =

TURNOUT

Page 64: My Railway Engg. Ppt

POINTS AND SWITCHES

• A railroad switch or points is a mechanical installation enabling railway trains to be guided from one track to another at a railway junction.

Page 65: My Railway Engg. Ppt
Page 66: My Railway Engg. Ppt

POINTS AND SWITCHES

Electric, Hydraulic or Manual

Page 67: My Railway Engg. Ppt

CROSSINGS

• It is a special form of construction to provide flange way clearance between two rails to be crossed.

• To achieve this, a gap is provided from throat to nose of crossing over which the wheel jumps.

Page 68: My Railway Engg. Ppt

Components of CROSSING of a Right Hand Turnout

Throat

Page 69: My Railway Engg. Ppt
Page 70: My Railway Engg. Ppt
Page 71: My Railway Engg. Ppt

• To ensure that the wheel negotiates the gap properly and doesn’t strike the nose, the outer rail is guided with the help of CHECK RAILS.

CROSSINGS

Page 72: My Railway Engg. Ppt

Characteristics of a good crossing:

• Should be rigid• Frog and wing rails should be protected

against damage so that the wheels do not bump into the gap.

• Frog should be of sufficient thickness.

Page 73: My Railway Engg. Ppt

Types of crossings

• Acute angle (V-Crossing)• Obtuse angle crossing• Square Crossing

Page 74: My Railway Engg. Ppt

CAPACITY OF RAILWAY TRACK

• Maximum number of trains that can run safely on any length of track per hour.

• Maximum number of trains that can be handled in a yard …TERMINAL CAPACITY.

Page 75: My Railway Engg. Ppt

Specification of Indian Railways1. Sleeper density = no. of sleepers per rail

length.Generally, 1 sleeper in every meter length.Depends on: axle load, speed, strength of

sleeper, depth of ballast.Sleeper density = n+ x (x = 7 usually)

n = length of each rail2. Rails: 13 m long (for BG track)

Page 76: My Railway Engg. Ppt

• Example: If sleeper density is n + 6 for a BG track, calculate the number of sleepers in 960 m length of railway.

Length of each rail = 13 mTotal no. of rails in 960 m = 960/13 = 74No. of sleeper in each rail = 13 + 6 = 19So, no. of sleeper in 74 rails = 74 x 19 = 1406

Page 77: My Railway Engg. Ppt

3. Materials required per KM length of track

1. No. of rails per km = (1000/13) x 2 = 1542. Weight of rail per km = (154 x 13) x 60 = 120,120

kg (@ 60 kg/m)3. No. of sleepers per km = (154/2) x (13 + 7) = 15404. No. of fish plates per km = 77 x 2 = 1545. No. of bolts per km = 154 x 4 = 6066. No. of bearing plates per km = 1540 x 2 = 30807. No. of fasteners = (1540 x 12)8. Quantity of ballast per km = (0.2 x 3.35 x 1000)

cubic meter