OPERATIONAL PERFORMANCE MAY’13
Month Carried Tonnage Monthly Traffic projection based
on ATP
Variation % (Over 2012 – 13)2013-14 2012-13
For May’13
0.45 0.35 0.38 30%
Cumulative – till May’13
0.93 0.74 0.79 26%
Tonnage - MT
COMMODITY-WISE LOADING – FOR THE MONTH OF MAY’13
Particulars Carried Tonnage 2013-14
Carried Tonnage 2012-13
Variation Over
Commodity May’13 Apr’13 -May’13
May’12 Apr’12- May’12
Las t Yr May’12
Last Yr
Apr’12-May’13
Iron Ore/ Export
Domestic
Total
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0%
0%
0%
0%
0%
0%
Cement 0.74 1.76 0.96 1.89 -23% -7%
Fertilizer 0.60 1.09 0.30 0.50 98% 118%
Food Grains 0.57 1.58 0.11 0.40 405% 291%
LPG/POL 0.18 0.37 0.30 0.50 -40% -26%
Coal 2.21 3.89 1.64 3.84 34% 1%
Gypsum 0.15 0.46 0.16 0.27 -1% 71%
Iron Sheet/Wood 0.00 0.00 0.00 0.00 0% 0%
Cont 0.08 0.16 0.00207 0.00488 3776% 3128%
Total 4.54 9.32 3.48 7.41 30% 26%
Tonnage in Lakhs
COMMODITY-WISE REVENUE – FOR THE MONTH OF MAY’13
Particulars Gross Revenue
2013-14
Gross Revenue
2012-13
Variation % Over
Commodity May’13 Apr’13-May’13
May’12 Apr’12- May’12
Las t Yr May’12
Last Yr
Apr’12-May’12
Iron Ore/ Export
Domestic
Total
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0%
0%
0%
0%
0%
0%
Cement 2.18 5.18 2.71 5.32 -20% -3%
Fertilizer 1.41 2.56 0.67 1.09 111% 134%
Food Grains 1.23 3.06 0.23 0.72 438% 323%
LPG/POL 0.71 1.43 1.10 1.80 -35% -20%
Coal 6.32 11.10 4.33 10.12 46% 10%
Gypsum 0.46 1.38 0.43 0.75 7% 85%
Iron Sheet/Wood 0.00 0.00 0.00 0.00 0% 0%
Cont 0.10 0.17 0.01 0.04 625% 341%
Total 12.41 24.89 9.49 19.84 31% 25%
` - Crores
Commodity wise Net Revenue Including OH
Particular May 2013 May 2012 Net Rev
Commodity Gross Reve
O&M Cost `. 149/T
* Net Reve
Gross Reve
O&M Cost `.140/T
Net Reve
Variation %
Iron Ore/ Export
Domestic0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0%
0%
Cement 2.18 1.10 1.08 2.71 1.48 1.23 -12%
Fertilizer 1.41 0.89 0.52 0.67 0.46 0.21 150%
Food Grains
1.23 0.85 0.38 0.23 0.17 0.06 550%
LPG/POL 0.71 0.27 0.44 1.10 0.47 0.63 -30%
Coal 6.32 3.27 3.05 4.33 2.52 1.81 68%
Gypsum 0.46 0.23 0.23 0.43 0.24 0.19 20%
Iron Sheet/ Wood
0.00 0.00 0.00 0.00 0.00 0.00 0%
Auto/Cont 0.10 0.12 -0.02 0.01 0.01 0.00 0%
TOTAL 12.41 6.73 5.68 9.49 5.35 4.14 37%
` - Crores
•May’13 -Net Revenue Includes Def OH of ` 110 Lakhs ,O&M Cost Inclusive of Def OH- ` 173/T•May’12 –Net Revenue Includes Def OH of ` 90 Lakhs,O&M Cost Inclusive of Def OH- ` 179/T
Commodity wise Gross & Net Revenue Including OH (Per Tonne)
Particular May 2013 May 2012 Net Rev
Commodity Gross Rev
O&M Cost /T
Net Rev
Gross Rev
O&M Cost /T
Net Rev Variation %
Iron Ore
Export
Domestic
0
0
0
0
0
0
0
0
0
0
0
0
0%
0%
Cement 295 148 146 281 154 127 15%
Fertilizer 236 148 87 222 154 68 29%
Food Grains 214 148 65 201 154 47 39%
LPG/POL 390 148 242 362 154 208 16%
Coal 286 148 138 264 154 110 25%
Gypsum 296 148 147 275 154 121 22%
Iron Sheet /Wood
0 0 0 0 0 0 0%
Cont 127 148 -21 0 0 0 0%
Amt - `
•May’13 - Net Revenue Includes Def OH of ` 24/T , O&M Cost Inclusive of Def OH - ` 173/T•May’12 – Net Revenue Includes Def OH of ` 26/T, O&M Cost Inclusive of Def OH - ` 179/T
Operating Ratio for the month of May 2013For May
2013To End of May 2013
Gross Revenue 12.41 24.89
Total Income 12.41 24.89
Operating Expenses
O&M Costs (Inc of Def. OH) 9.15 14.46
Administrative Expenses 0.07 0.14
Depreciation 2.83 5.66
Total Expenses (i) 12.05 20.26
Operating Ratio (%) 97% 81%
Cost of Maintenance works (ii) 0.00 0.31
Total Expenses (I) + (II) 12.05 21
Operating Ratio (Cumulative) 97% 83%
Surplus/Deficit 0.36 4.31
Surplus % 3% 17%
` - Crores
NOTE : In O&M costs, cost of fuel is calculated as per service & direction wise
COST OF FUEL (SERVICE WISE/ DIRECTION WISE) for May’13
Cost of Fuel From April ’13 – May’13 – 7.90 Cr
Particulars No of Wagons Cost of Fuel ` - Crores
Total ` - Crores
Wagon Type UP DN UP DN UP + DN
BCN Load 1233 1585 0.72 0.33 1.05
BOXN Load 3579 0 1.66 0 0.16
BTPG Load 379 0 0.21 0.00 0.21
BTPN Load 104 0 0.05 0.00 0.05
BLCA/BFKN Load 131 90 0.06 0.01 0.07
BCNHL Ld 348 58 0.15 0.01 0.16
BOXN Empty 0 3751 0.00 0.24 0.24
BTPG Empty 0 483 0.00 0.10 0.10
BTPN Empty 0 675 0.00 0.10 0.10
BLCA/BFKN Empty 0 0 0.00 0.00 0.00
BRN Empty 0 0 0.00 0.00 0.00
Cost of Fuel of CLE + Other (UP+DN) 0.01
TOTAL 5774 6642 2.85 0.79 3.65
Cost of Lube Oil + Others 0.24
TOTAL 3.89
Line Capacity Utilization for the month of May’13 :
Direction Loaded Empties Total No of Trains
*CLE *Others Total
UP Trains 115 0 115 54
(68)
3
(13) 306Down Trains 42 92 134
157 92 249 54 3 306
Permissible Capacity : 340
Utilized : 306
Percentage of Utilization : 90%
Percentage of Utilization Loaded : 46%
Engine Hour Cost : 84.36 Lakhs
NOTE:
* Moved between SKLR-SBHR-SKLR
WAGON DAYS – MAY 2013
No of Days
TotalUP Down
Actual 3791 3045 6836
Abnormal Detention
744 177 921
Rate per Day in terms of 8 wheeler : ` 1038.30
Wagon Hire Charges (Actual) : ` 71.01 Lakhs
Wagon Hire Charges for Abnormal : ` 9.56 Lakhs
Detention (Avoidable)
*Abnormal Detention : Time taken for completing the journey > 15 Hrs
Details of Payments Received from Mysore Division after adjusting O&M Costs
Months Due Date Actual date of Receipt
Amount Rs - Cr
Prov. Pay Final Pay (Prov Pay)
April ’13 05.05.13 31.05.13 04.06.13 5.55
May ’13 05.06.13 30.06.13
Details of Payments made by HMRDC to SWR
Particulars For the month of May’13
To the End
(Crores)
Contractual payment for maintenance works (Provisional bill from --)
0.00 0.31