+ All Categories
Home > Documents > SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK...

SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK...

Date post: 14-Jun-2020
Category:
Upload: others
View: 0 times
Download: 0 times
Share this document with a friend
176
SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK RECONFIGURATION AND ENERGY MANAGEMENT by FEI DING Submitted in partial fulfillment of the requirements for the degree of Doctor of Philosophy Dissertation Advisor: Dr. Kenneth A. Loparo Department of Electrical Engineering and Computer Science CASE WESTERN RESERVE UNIVERSITY January, 2015
Transcript
Page 1: SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK ...read.pudn.com/downloads799/sourcecode/math/3153436/Thesis_fin… · SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK RECONFIGURATION

SMART DISTRIBUTION SYSTEM AUTOMATION:

NETWORK RECONFIGURATION AND ENERGY

MANAGEMENT

by

FEI DING

Submitted in partial fulfillment of the requirements

for the degree of Doctor of Philosophy

Dissertation Advisor: Dr. Kenneth A. Loparo

Department of Electrical Engineering and Computer Science

CASE WESTERN RESERVE UNIVERSITY

January, 2015

Page 2: SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK ...read.pudn.com/downloads799/sourcecode/math/3153436/Thesis_fin… · SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK RECONFIGURATION

CASE WESTERN RESERVE UNIVERSITY

SCHOOL OF GRADUATE STUDIES

We hereby approve the thesis/dissertation of

Fei Ding

candidate for the degree of Doctor of Philosophy

Committee Chair

Kenneth A. Loparo

Committee Member

Marija Prica

Committee Member

Mingguo Hong

Committee Member

Vira Chankong

Date of Defense

Nov.11, 2014

* We also certify that written approval has been obtained

for any proprietary material contained therein.

Page 3: SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK ...read.pudn.com/downloads799/sourcecode/math/3153436/Thesis_fin… · SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK RECONFIGURATION

iii

Table of Contents

SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK RECONFIGURATION

AND ENERGY MANAGEMENT .................................................................................................. 1

Table of Contents ............................................................................................................................ iii

List of Figures ................................................................................................................................. vi

List of Tables ................................................................................................................................... ix

Chapter 1 Introduction .................................................................................................................. 1

Chapter 2 A Review on Existing Approaches for Reconfiguring Distribution Systems .............. 8

Chapter 3 Three Methods Proposed for Reconfiguring Distribution Systems ........................... 18

3.1 Problem Formulation .......................................................................................................... 18

3.2 Heuristic Method ................................................................................................................ 22

3.3 Hybrid Method .................................................................................................................... 25

3.3.1 Hybrid Method ............................................................................................................. 25

3.3.2 Sensitivity Analysis Based on OPF Solutions ............................................................. 28

3.4 Genetic Algorithm .............................................................................................................. 31

3.5 Case Studies ........................................................................................................................ 34

3.5.1 Case I : Three-Feeder Test System .............................................................................. 34

3.5.2 Case II : 33-Bus Test System ....................................................................................... 38

3.6 Comparison of Three Methods ........................................................................................... 41

Chapter 4 Hierarchical Decentralized Network Reconfiguration Study .................................... 43

4.1 Decentralized Structure ....................................................................................................... 44

4.2 Operational Rules ................................................................................................................ 49

4.3 Multi-Agent Technique ....................................................................................................... 51

4.4 Dynamic Network Reconfiguration .................................................................................... 55

4.5 Case Study .......................................................................................................................... 58

4.5.1 Case I : 118-Bus Test System ...................................................................................... 61

4.5.2 Case II : 69-Bus Test System ....................................................................................... 64

4.5.3 Case III : 216-Bus Test System.................................................................................... 66

4.5.4 Result Discussion and Remark .................................................................................... 68

4.5.5 Dynamic Network Reconfiguration .............................................................................. 71

Chapter 5 Modeling and Primary Control for Distributed Generation Systems ......................... 79

Page 4: SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK ...read.pudn.com/downloads799/sourcecode/math/3153436/Thesis_fin… · SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK RECONFIGURATION

iv

5.1 Wind Power Generation Unit .............................................................................................. 79

5.1.1 Mathematical Model .................................................................................................... 81

5.1.2 Control System ............................................................................................................. 83

5.2 Micro-Gas-Turbine Generation Unit .................................................................................. 85

5.2.1 Mathematical Model .................................................................................................... 86

5.2.2 Control System ............................................................................................................. 89

5.3 Photovoltaic Generation Unit ............................................................................................. 90

5.3.1 Mathematical Model .................................................................................................... 90

5.3.2 Control System ............................................................................................................. 92

5.4 Fuel Cell Generation Unit ................................................................................................... 95

5.4.1 Mathematical Model .................................................................................................... 95

5.4.2 Control System ........................................................................................................... 100

5.5 Super-Capacitor Energy Storage System .......................................................................... 101

5.5.1 Mathematical Model .................................................................................................. 101

5.5.2 Control System ........................................................................................................... 102

5.6 Operation of Grid-Connected / Islanded Distributed Generation Systems ....................... 104

5.6.1 Control System for Grid-Tie Inverter ........................................................................ 106

5.6.2 Control System for Islanded Inverter ......................................................................... 107

5.6.3 Small-Signal Stability Analysis ................................................................................. 108

5.7 Case Study ........................................................................................................................ 111

5.7.1 Grid-Connected Operation ......................................................................................... 112

5.7.2 Islanded Operation ..................................................................................................... 117

Chapter 6 Distribution Network Reconfiguration and Energy Management of Distributed

Generation Systems ..................................................................................................................... 121

6.1 Three-Phase Power Flow and Power Loss Minimization ................................................. 121

6.1.1 Three-Phase Unbalanced System Modeling .............................................................. 121

6.1.2 Power Flow Equations ............................................................................................... 123

6.1.3 Power Loss Minimization .......................................................................................... 125

6.2 Optimal Planning of DG Units.......................................................................................... 127

6.2.1 Optimal Locations of DG Units ................................................................................. 128

6.2.2 Optimal Capacity of DG Units................................................................................... 129

6.3 Network Reconfiguration and Optimal Operation of DG Units ....................................... 131

Page 5: SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK ...read.pudn.com/downloads799/sourcecode/math/3153436/Thesis_fin… · SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK RECONFIGURATION

v

6.4 Case Study ........................................................................................................................ 137

6.4.1 Gaussian-Mixture Load Modeling ............................................................................. 137

6.4.2 Case I: 25-Bus Unbalanced Distribution System ....................................................... 138

6.4.3 Case II: Revised IEEE 123-Bus Unbalanced Distribution System ............................ 143

Chapter 7 Conclusions and Future Work .................................................................................. 149

Reference ..................................................................................................................................... 157

Page 6: SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK ...read.pudn.com/downloads799/sourcecode/math/3153436/Thesis_fin… · SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK RECONFIGURATION

vi

List of Figures

Figure 3.1 Structure of the switches. ......................................................................................... 22

Figure 3.2 Flowchart of the heuristic algorithm based on branch-exchange and single-loop

optimization. ................................................................................................................................. 25

Figure 3.3 Flowchart of the proposed hybrid method. ............................................................ 27

Figure 3.4 Flowchart of the proposed genetic algorithm. ........................................................ 32

Figure 3.5 The genes included in each chromosome. ............................................................... 32

Figure 3.6 Three-feeder test system. .......................................................................................... 34

Figure 3.7 Results of sensitivity of power loss with respect to S9, S10, S16 and S17

respectively. .................................................................................................................................. 37

Figure 3.8 Results of power loss changes for shifting S9, S10, S16 and S17 from their OPF

solutions to 0/1 respectively. ........................................................................................................ 38

Figure 3.9 Iterative results of the revised GA for the 3-feeder test system. ........................... 38

Figure 3.10 Single-line diagram of 33-bus test system. ............................................................ 38

Figure 3.11 Voltage magnitudes of all nodes before and after the reconfiguration. ............. 39

Figure 3.12 Sensitivity of the power loss with respect to different switch states. .................. 40

Figure 3.13 Iterative results of the revised GA for the 33-bus test system. ........................... 41

Figure 4.1 118-bus radial distribution system. ......................................................................... 44

Figure 4.2 The graph for zone-1. ............................................................................................... 48

Figure 4.3 Components of G1-U1................................................................................................ 48

Figure 4.4 Decomposition with fictitious loads and fictitious generators representing power

flows through the interconnecting lines. .................................................................................... 49

Figure 4.5 Operation procedures for the 118-bus distribution system. ................................. 51

Figure 4.6 The framework of two intelligent agents. ............................................................... 52

Figure 4.7 Coordination between two agents. .......................................................................... 53

Figure 4.8 Framework of dynamic network reconfiguration. ................................................ 56

Figure 4.9 Dynamic network reconfiguration with time-ahead planning. ............................ 57

Figure 4.10 The demonstration system built using MATLAB. ............................................... 59

Figure 4.11 Node voltages of the 118-bus system before and after reconfiguration. ............ 63

Figure 4.12 Power losses in the 118-bus system before and after reconfiguration. .............. 63

Figure 4.13 Single-line diagram of the 69-bus test system. ..................................................... 64

Figure 4.14 Decomposed systems and hierarchical agents for the 69-bus system. ................ 65

Figure 4.15 Single-line diagram of the 216-bus test system. ................................................... 66

Figure 4.16 Decomposed systems for the 216-bus system. ...................................................... 67

Figure 4.17 Voltage results of the 216-bus system before and after the reconfiguration. .... 68

Figure 4.18 Ten load shapes. ...................................................................................................... 71

Figure 4.19 Hourly solar radiation and temperature profiles. ............................................... 72

Figure 4.20 Two faults happened in the 118-bus system. ........................................................ 77

Figure 5.1 Three types of wind energy conversion system. ..................................................... 81

Figure 5.2 Two-mass model for the shaft system of WTG. ..................................................... 81

Page 7: SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK ...read.pudn.com/downloads799/sourcecode/math/3153436/Thesis_fin… · SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK RECONFIGURATION

vii

Figure 5.3 Electrical circuit for the induction machine in d-q frame. ................................... 82

Figure 5.4 Conventional pitch angle control system. ............................................................... 83

Figure 5.5 Control for rotor-side converter. ............................................................................. 85

Figure 5.6 Single-shaft MT model. ............................................................................................ 86

Figure 5.7 Electrical circuit of PMSG in d-q frame. ................................................................ 89

Figure 5.8 Configuration of a micro-turbine generation system. ........................................... 89

Figure 5.9 The physics of a PV cell. ........................................................................................... 90

Figure 5.10 Single-diode equivalent circuit for a PV cell. ....................................................... 91

Figure 5.11 Characteristics curves for the PV array model. ................................................... 92

Figure 5.12 Flow-chart for variable-step P&O method. ......................................................... 94

Figure 5.13 Block diagram of the MPPT controller. ............................................................... 95

Figure 5.14 Equivalent electric model for the fuel cell. ........................................................... 95

Figure 5.15 Medium-term dynamic fuel cell model. ................................................................ 98

Figure 5.16 Configuration and control for fuel cell generation system................................ 100

Figure 5.17 Typical charge/discharge characteristic curves of the super-capacitor and

battery. ........................................................................................................................................ 101

Figure 5.18 Classic equivalent circuit for ultra-capacitor. .................................................... 102

Figure 5.19 Control for the bi-directional DC/DC converter. .............................................. 103

Figure 5.20 A sketch of multiple distributed generation systems. ........................................ 104

Figure 5.21 The configuration of a distributed generation unit for grid-connected and

islanded operations. ................................................................................................................... 105

Figure 5.22 Three-level controller block diagram in d-axis for the grid-tie inverter. ........ 107

Figure 5.23 The complete controller for the grid-tie inverter. .............................................. 107

Figure 5.24 Three-level controller block diagram in d-axis for the autonomous inverter. 108

Figure 5.25 Block diagram of the state-space model for the grid-connected DG system. .. 111

Figure 5.26 Configuration of the distribution system with multiple distributed energy

resources. .................................................................................................................................... 112

Figure 5.27 Two faults occurred at the system. ...................................................................... 113

Figure 5.28 Simulation results for the system at steady-state. .............................................. 115

Figure 5.29 Changes in wind speed and solar irradiance. ..................................................... 116

Figure 5.30 Simulation results for wind power unit and DC generation unit. .................... 116

Figure 5.31 Simulation results of the microgrid. .................................................................... 118

Figure 5.32 Designed scheme of the synchronization. ........................................................... 119

Figure 5.33 Simulation results of the synchronization process. ............................................ 120

Figure 6.1 Components between two buses in an unbalanced distribution system. ........... 122

Figure 6.2 The framework of the strategy. ............................................................................. 127

Figure 6.3 The flowchart of the proposed methodology. ....................................................... 133

Figure 6.4 The genes included in each chromosome. ............................................................. 135

Figure 6.5 GMM approximations of load pdfs. ...................................................................... 138

Figure 6.6 Single-line diagram of the 25-bus unbalanced distribution system.................... 138

Figure 6.7 Power loss in the system with DG units installed at different locations. ........... 139

Page 8: SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK ...read.pudn.com/downloads799/sourcecode/math/3153436/Thesis_fin… · SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK RECONFIGURATION

viii

Figure 6.8 Decomposed systems and hierarchical reconfiguration agents for the 25-bus

system. ......................................................................................................................................... 141

Figure 6.9 Four groups of load shapes. ................................................................................... 141

Figure 6.10 Optimal outputs of two DG units in the 25-bus system for 24 hours. .............. 142

Figure 6.11 System power losses for different scenarios during 24 hours. .......................... 143

Figure 6.12 The configuration of the revised IEEE 123-bus test system. ............................ 143

Figure 6.13 The graph of 123-bus system. ............................................................................... 146

Figure 6.14 Decomposed systems and hierarchical reconfiguration agents for the 123-bus

system. ......................................................................................................................................... 146

Figure 6.15 The optimal outputs of three DG units in the revised 123-bus system for 24

hours. ........................................................................................................................................... 148

Figure 6.16 System power losses for different scenarios during 24 hours. .......................... 148

Figure 6.17 Maximum voltage unbalance and line loading level in the revised 123-bus

system during 24 hours. ............................................................................................................. 148

Figure 7.1 The conceived framework. ..................................................................................... 154

Page 9: SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK ...read.pudn.com/downloads799/sourcecode/math/3153436/Thesis_fin… · SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK RECONFIGURATION

ix

List of Tables

Table 3.1 Simulation Results of Centralized Method For Three-Feeder Test System ......... 35

Table 3.2 Solutions of OPF for Three-Feeder Test System ..................................................... 35

Table 3.3 Power Losses for Different “0-State” Switch in Loop-1 ......................................... 36

Table 3.4 Power Losses for Different “0-State” Switch in Loop-2 ......................................... 36

Table 3.5 Simulation Results Of Centralized Method For 33-Bus System ............................ 39

Table 3.6 Solutions of OPF for 33-Bus Test System ................................................................ 40

Table 3.7 Results of “0-State” Switches for 33-Bus Test System ............................................ 40

Table 3.8 Comparison of Three Methods ................................................................................. 42

Table 4.1 Fifteen Loops and Associated Buses in the 118-bus System ................................... 45

Table 4.2 Decentralized Structure for the 118-bus System ..................................................... 48

Table 4.3 Simulation Results of 118-Bus System ..................................................................... 61

Table 4.4 Simulation Results of 69-Bus System ....................................................................... 65

Table 4.5 Simulation Results of 216-Bus System ..................................................................... 67

Table 4.6 Capacity of Each PV Unit During 24 Hour Period ................................................. 72

Table 4.7 Simulation Results of The Dynamic Reconfiguration ............................................. 74

Table 4.8 Simulation Results When Fault Occurs ................................................................... 78

Table 5.1 Comparisons of Two Types of Microturbines ......................................................... 85

Table 5.2 Parameters of A PV Array ........................................................................................ 92

Table 5.3 Comparisons of Different Types of MPPT Algorithm. ........................................... 93

Table 6.1 Optimal Capacity of DG Units for Three Scenarios ............................................. 140

Table 6.2 Simulation Results of The Optimal Switching Plan .............................................. 141

Table 6.3 Optimal Capacity of DG Units for Three Scenarios ............................................. 145

Table 6.4 Simulation Results of The Optimal Switching Plan .............................................. 147

Page 10: SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK ...read.pudn.com/downloads799/sourcecode/math/3153436/Thesis_fin… · SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK RECONFIGURATION

x

ACKNOWLEDGEMENTS

First of all, I am profoundly grateful to my research advisor, Professor Kenneth A.

Loparo. He has persuasively provided the guidance for my research topic, critical

thinking and problem solving. His invaluable help is indispensable for my accomplished

research work during the past four years. Besides, professor Loparo is a successfully

researcher and has made great contributions to different research areas, and he is really

my role model of academic career.

Then, I would like to thank Professors Marija Prica, Vira Chankong and Mingguo

Hong for serving as my advisory committee and reviewing my dissertation. Their

comments are of great importance for me to improve my dissertation.

Besides, I would like to extend my thanks to all colleagues in the lab. I believe that the

support and encouragement received from each other are important for us, and I will

treasure the time that we shared together. Also, many thanks are due to my friends who

had given numerous help while I studied at CWRU.

Finally and importantly, I would like to express my gratitude to my beloved parents for

their unconditionally spiritual supports and understandings. They always provide their

love to me without any reservation. I hope that they will be proud of their loving daughter

who has already grown up and become a real Ph.D.. Besides, I would like to use this

dissertation in memory of my passed grandfather whom I didn’t have a chance to

accompany at the last moment due to the long distance from the United States to China.

In sum, the past more than four years have recorded an important and treasured

experience in my life journey. I will keep on doing my best in the following career life.

Page 11: SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK ...read.pudn.com/downloads799/sourcecode/math/3153436/Thesis_fin… · SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK RECONFIGURATION

xi

Smart Distribution System Automation: Network Reconfiguration

and Energy Management

Abstract

by

FEI DING

Smart distribution system automation is the key to realizing a highly reconfigurable,

reliable, flexible and active distribution system. Automated network reconfiguration

including restoration is the most studied area in distribution automation, and it

contributes to power loss minimization, voltage improvement and also can enable the

distribution network to respond to contingencies and changes happened in the grid.

Distributed energy resources at the customer premises, energy storage systems and plug-

in electric vehicles are indispensable parts of future smart distribution systems. Their

participations have brought more dynamics and uncertainties into the grid, and hence new

technologies at both planning and operation levels must be developed to manage the

energy dispatched from distributed energy resources and energy storage units, the

charging and discharging behaviors of electric vehicles so that the entire power

distribution system could operate stably and efficiently. Meantime, due to the intermittent,

imperfectly predicted renewable energy and more complicated, uncertain load patterns,

two challenges have arisen on network reconfiguration study, including more frequent

reconfiguration actions and more complicated optimization problems for determining the

Page 12: SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK ...read.pudn.com/downloads799/sourcecode/math/3153436/Thesis_fin… · SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK RECONFIGURATION

xii

optimal network topology. Thus, new approaches for reconfiguring distribution networks

must be developed to overcome these challenges.

In order to address the above challenges which distribution systems are facing to and

develop new technologies for realizing smart distribution automation, a comprehensive

study on network reconfiguration and energy management of distributed generation

systems was studied. The contributions of this dissertation include: (1) proposed a novel

problem formulation for network reconfiguration problem based on “switch states”; (2)

developed three new methods to solve the optimization problem including heuristic

algorithm, hybrid algorithm and revised genetic algorithm; (3) proposed a hierarchical,

decentralized network reconfiguration approach that has been proved to have significant

computational advantage compared with other existing methods; (4) proposed the

concept of “dynamic network reconfiguration” in which the impact of time-varying load

demands, renewable energy generation and other contingencies on the optimal

distribution network topology were fully addressed and analyzed. (5) Since DG has

become one of the most important parts in distribution systems. The mechanism of

distributed generation itself and the impact of distributed generation on distribution

system analysis must be studied. This dissertation has studied the modeling and reactive

control of multiple DG systems, and also studied the unbalanced distribution feeder

reconfiguration and proposed energy management strategy for controlling all grid-

connected DGs in order to optimize distribution system operation.

Page 13: SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK ...read.pudn.com/downloads799/sourcecode/math/3153436/Thesis_fin… · SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK RECONFIGURATION

1

Chapter 1 Introduction

The traditional electric power system is designed for unidirectional power flow with

very limited observability, intelligence and autonomous response. Electricity users are

simply waiting for the electric power transferred from power plants through transmission

lines and distribution feeders, without any active interaction or demand response. The

limited one-way interaction makes it difficult for the grid to respond to the ever changing

and rising energy demands of the 21st century. Besides, concerns about global climate

change have increased the penetration of renewable energy resources worldwide. As a

result, in order to build a more secure, reliable, efficient and greener power grid, the

concept of “smart grid” has been proposed. Generally speaking, there is no specific or

unique definition of smart grid. Smart grid technology includes the application of

automation and intelligent controls to power systems, and it includes several significant

characteristics [1], including: 1) increased use of digital control and information

technology with real-time availability; 2) dynamic optimization relating to grid

operability; 3) inclusion of demand side response; 4) demand side management

strategies; 5) integration of distributed resources including renewables and energy

storage; 6) deployment of smart metering; 7) distribution system automation; 8) smart

appliances and customer devices at the point of end use.

With the emphasis on the distribution level, distribution systems are facing the

challenge of evolving from passive networks with unidirectional flow supplied by the

transmission grid to active distribution networks highly involved with distributed

generation (DG) requiring bidirectional power flows. Such a transition requires a

paradigm shift in both system design and operations. It is noted that both planning and

Page 14: SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK ...read.pudn.com/downloads799/sourcecode/math/3153436/Thesis_fin… · SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK RECONFIGURATION

2

operation depends on two basic parameters: technical constraints (equipment capacity,

voltage drop, radial network structure, reliability indices, etc.) and economical targets

such as minimizing investment and operating costs, minimizing energy imported from

transmission, energy loss and reliability costs, etc. Distributed generation at customer

premises, self-healing protection mechanisms, and distribution automation are three

crucial aspects for future (smart) distribution systems. According to the statistics released

by US Department of Energy in 2011 [2], transmission and distribution losses associated

with the delivery of electricity for residential, commercial, and industrial consumption

accounts for 7% of gross generation, or 246 B kilowatt hours. Besides, with the transition

to electric vehicles, their fueling will become part of the electricity generation

infrastructure, thereby adding significantly to the transmission and distribution costs of

centralized generation. By contrast with conventional coal fuel power stations that are

centralized and often require electricity to be transmitted over long distances, distributed

energy resources (DER) are decentralized, modular and more flexible technologies, and

are usually located close to the loads they serve. Due to these significant advantages, DG

has emerged as an alternative to supply electric power and DG technologies have been

widely developed [3].

DG systems typically use renewable energy resources, including, but not limited to,

wind, solar, hydro, biomass and geothermal power. Based on REN21’s 2014 report [4],

worldwide renewable energy contributed 19% to energy consumption and 22% to

electricity generation in 2012 and 2013, respectively. In the United States, President

Obama has called to secure 25% of electricity from clean, renewable resources by 2025.

According to [5], renewable energy in the United States accounted for 12.9% of the

Page 15: SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK ...read.pudn.com/downloads799/sourcecode/math/3153436/Thesis_fin… · SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK RECONFIGURATION

3

domestically produced electricity in 2013, and 11.2% of total energy generation. Among

all renewable energy, wind and solar are two important types. Until now U.S. wind power

installed capacity has exceeded 60,000 MW and the installed photovoltaic capacity has

passed 10.5 GW.

Fuel cells also show great potential to work as distributed energy resources because of

they are highly efficienct and environmentally friendly. The efficiency of low

temperature proton exchange membrane fuel cells is around 35~45% [6], and the

efficiency of high temperature solid oxide fuel cells can be as high as 65% [7]. Fuel cells

are considered as clean energy resources because there is zero or very low pollutant

emission. Microturbines are touted to become widespread in distributed generation and

combined heat and power applications [8]. They are one of the most promising

technologies for powering hybrid electric vehicles. The capacity of a commercial size

microturbine usually ranges from tens to hundreds of kilowatts [9].

The outputs of renewable energy based DG systems are intermittent and unpredictable.

In addition, electrical energy demand is set to rise with the electrification of

transportation and heat, putting additional strains on distribution networks [10], [11], [12].

A plug-in hybrid electric vehicle is a hybrid vehicle that utilizes rechargeable batteries

that can be fully charged by connecting to an external electric power source. Compared to

conventional vehicles, plug-in hybrid electric vehicles (PHEVs) reduce air pollution and

the reliance on petroleum [13]. The penetration of PHEVs in the power grid is increasing,

as of September 2014 about 248,000 highway-capable plug-in hybrid electric cars have

been sold worldwide since December 2008 [14], about 41.3% of the total 600,000 plug-in

electric cars sold worldwide until Oct. 2014. However, all these changes will result in

Page 16: SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK ...read.pudn.com/downloads799/sourcecode/math/3153436/Thesis_fin… · SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK RECONFIGURATION

4

more stochastic and dynamic behaviors that the distribution system has not experienced

nor been designed for. It is indispensable to develop flexible and intelligent planning

methodologies in order to properly exploit the integration of DG and manage changing

load patterns caused by PHEVs, while still satisfying both power quality and reliability

constraints. Besides, the stochastic representation of generation and load is a must for

these methodologies in order to plan a safe and reliable system. In order to realize all

these objectives, the first step is to understand the mechanisms of distributed generation

by building appropriate simulation models and developing stable control methods.

From the perspective of the distribution network, a reliable distribution automation

system is the key to enable autonomous smart distribution system operation to any

changes, such as time-varying load demands, unexpected faults and planned actions, and

to ensure the efficiency, reliability and optimality during distribution network operations.

Distribution automation refers simply to greater automation of processes within the

distribution system. A relatively short-term vision for distribution automation is a

distribution system that, through automation, has a more flexible electrical system

architecture that is supported by open-architecture communication networks [15].

Distribution automation should result in a system that is multifunctional and takes

advantage of new capabilities in power electronics, cyber technology and system

simulation. Real-time state-estimation tools should be used to perform predictive

simulations and to continuously optimize performance, including real-time demand-side

management, efficiency, reliability, and power quality to help bridge the communication-

power architectures.

Page 17: SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK ...read.pudn.com/downloads799/sourcecode/math/3153436/Thesis_fin… · SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK RECONFIGURATION

5

Automated network reconfiguration including restoration is the most studied area in

distribution automation, which is a promising option because it uses existing assets to

achieve important and timely goals. Importantly, network reconfiguration is generally

referred to, but not limited to, distribution feeder reconfiguration. In transmission systems,

network topology optimization or reconfiguration has also been studied widely [16], [17],

[18], [19]. However, the objectives and methods of reconfiguration problems in

transmission and distribution systems are totally different. Switching actions in

transmission systems are mainly used to avoid overloads, reduce operation costs and

improve system security, while switching actions in distribution systems are used to

reduce power losses, improve voltage profiles and improve system reliability. Besides,

transmission networks are meshed and balanced, while distribution networks are radial

and unbalanced, so the constraints and methodologies for reconfiguring transmission and

distribution systems are totally different. This dissertation is focused on smart distribution

automation and thus the terminology of network reconfiguration always indicates

distribution feeder reconfiguration.

A distribution network can change its topology by opening or closing switches to

optimize system operation, isolate faults, and to restore the supply during outages due to

contingencies. In addition, the change of topology can improve load balancing between

feeders by transferring loads from heavily loaded feeders to other feeders, thus improving

voltage levels, reducing losses and increasing levels of reliability. It is also possible to

reduce average customer outage times, annual unavailability and expected unserved

energy by distribution system automation. In recent years, new methodologies of

distribution network reconfiguration have been presented, exploring the greater capacity

Page 18: SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK ...read.pudn.com/downloads799/sourcecode/math/3153436/Thesis_fin… · SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK RECONFIGURATION

6

and speed of computer systems, the increased availability of system-wide data, and the

advancement of automation, in particular supervisory control and data acquisition

(SCADA). With the increased use of SCADA and distribution automation using switches

and remote controlled equipment, distribution network reconfiguration becomes more

viable as a tool for real-time planning and control.

As the operating conditions vary, network reconfiguration can be used to minimize

power losses provided that technical operational limits are not violated and protective

devices remain properly coordinated. This distribution automation functionality is highly

desirable given the deployment of remotely controlled switches in smart distribution

networks that are expected to facilitate the integration of power from distributed energy

sources and to serve varying load patterns, for instance, from electric vehicle charging. It

must be noted that network reconfiguration is a short-term problem that tries to find the

optimal network configuration for a specific operating period, and the switching plan

obtained for the reconfigured system will achieve the desired operations within the

current operating period. Due to the high level of uncertainty regarding future network

conditions, it is extremely unlikely that a single network topology is optimal for all

periods over a long time horizon. Thus, it is necessary to reconfigure the distribution

network from time to time.

Although many approaches have been proposed to solve the reconfiguration problem,

one of the main remaining challenges with network topology optimization is the required

computational time and resources. Network reconfiguration is a complicated non-convex

optimization problem with binary decision variables and operational constraints.

Heuristic approaches have been shown to perform most quickly with satisfying

Page 19: SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK ...read.pudn.com/downloads799/sourcecode/math/3153436/Thesis_fin… · SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK RECONFIGURATION

7

approximations, but they are still not efficient enough when dealing with large-scale

networks with thousands of buses. The occurrence of intermittent renewable energy,

uncertain load demands for charging electric vehicles and more complicated demand

responses have changed the traditional static network into a highly dynamic one. It is

necessary to more frequently reconfigure the network in response to changes that occur in

the grid. Thus, a highly efficient and effective approach to reconfigure distribution

feeders to improve system operation is highly desired.

This dissertation is organized as follows. Chapter II gives a review of existing

approaches for distribution system reconfiguration. Chapter III gives the optimization

problem formulation for the network reconfiguration problem and also presents three new

methods to solve the reconfiguration problem. Each method is tested on different

distribution systems, and the performance of each of these methods is discussed and

compared. As mentioned earlier, a highly efficient and effective approach to solve the

reconfiguration problem is significant and necessary for future smart distribution systems.

A hierarchical, decentralized reconfiguration approach is given in Chapter IV, and this

approach has been shown to be very efficient and have good accuracy. In order to study

the impact of DG network reconfiguration and develop appropriate energy management

strategies, dynamic modeling and primary control of multiple DG units are studied in

Chapter V. Then, a comprehensive study of reconfiguring unbalanced distribution

systems with distributed generation is presented in Chapter VI. Finally, Chapter VII

concludes the dissertation and discusses possible future work.

Page 20: SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK ...read.pudn.com/downloads799/sourcecode/math/3153436/Thesis_fin… · SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK RECONFIGURATION

8

Chapter 2 A Review on Existing Approaches for

Reconfiguring Distribution Systems

Network reconfiguration in distribution systems is realized by changing the status of

sectionalizing switches (normally closed) and tie-switches (normally open). It can be

used to reduce power losses by transferring loads from heavily loaded feeders to lightly

loaded feeders without violating system security and stability constraints, and it can also

be used to restore loads in response to the problems that have occurred in the system.

Distribution feeder reconfiguration can be used for system planning as well as real-time

control and operation. From an optimization perspective, network reconfiguration is a

mixed-binary nonlinear optimization problem where binary variables represent the switch

states and continuous variables model the electric network. However, even for a

distribution system of moderate size the number of switching options is so large that

conducting load-flow studies for all the possible options is computationally inefficient

and impractical as a real-time feeder reconfiguration strategy. As a result, during the past

decades, numerous approaches have been proposed to solve reconfiguration problems.

The first publication about network reconfiguration problem by Merlin and Back [20]

determined the network configuration with minimum or near-minimum line losses using

a branch-and-bound type heuristic technique. According to their proposed method, all

network switches are initially closed to obtain a meshed network. Then, network switches

are opened one at a time until a new radial structure is reached, and the switch selected to

open at each time minimized the losses of the resulting network. Merlin and Back’s work

has been the foundation for all other network reconfiguration studies that have followed.

However, there are several major drawbacks of the methodology including the

Page 21: SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK ...read.pudn.com/downloads799/sourcecode/math/3153436/Thesis_fin… · SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK RECONFIGURATION

9

assumption of purely active loads represented by current sources, neglecting voltage

angles and network constraints. As a result, Shirmohammadi and Hong [21] modified

Merlin’s methodology to avoid these drawbacks and their approach also starts by closing

all network switches which are then opened one-by-one another by determining the

optimum flow pattern in the network. They also developed an efficient power flow

method suitable for both radial and weekly meshed distribution networks. Accordingly,

Gaswami and Basu [22] used the concept of optimum flow pattern assuming that only

one switch was closed each time to form one loop, and improved configurations were

obtained by successively conducting single-loop switch exchange until no further

improvements are obtained. [20] - [22] start by switches to obtain a meshed network, and

then switches are opened successively to obtain the radial structure. This implementation

pattern can be considered as a “sequential switch opening method”, and most

reconfiguration approaches follow this pattern. On the contrary, McDermott et al. [23]

developed a reconfiguration algorithm starting with all network switches open, and a list

of candidate switches is built at each step and the candidate with minimum loss increment

is closed at that step. This proposed reconstruction procedure is repeated until a

connected, radial network is achieved. Because the number of normally closed switches

is much larger than the number of normally opened switches, more load flow calculations

are needed in this approach than other sequential opening methods.

A branch-exchange type heuristic algorithm has been suggested by Civanlar and

Grainger [24], and a formula to estimate loss reduction caused by transferring load

between two feeders was also derived. According to their work, loss reduction can be

attained only if there is a significant voltage difference across the normally open tie-

Page 22: SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK ...read.pudn.com/downloads799/sourcecode/math/3153436/Thesis_fin… · SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK RECONFIGURATION

10

switch and if the loads on the higher voltage side of the tie-switch are transferred to the

other side. This conclusion is quite significant because the number of switches that need

to be studied can be greatly reduced. Based on their work, Baran and Wu [25] introduced

two different methods to approximate power flow in the system after a load transfer, and

these approximate power flow methods are then used to estimate both loss reduction and

load balance in the system. Since there are generally multiple tie-switches existing in a

system, it is important to determine the implementation scheme of multiple loops. Fan et

al. [26] provided an analytical description and a systematic understanding about the

single-loop optimization approach. Each time a loop is selected, and the best switch to be

opened is determined by finding the minimum loss increment associated with a particular

switch in the loop. The evaluation procedure starts from the original open switch and then

goes up in one direction toward the source node by one switch at a time until the

minimum loss increment is reached.

Recently, more new heuristic approaches are proposed on the basis of the above classic

algorithms. Gomes et al. [27] proposed a two-stage reconfiguration algorithm. The

computation also starts from a meshed network with all switches closed. The first-stage

requires finding all maneuverable switches and computing the power loss if a

maneuverable switch is opened; the open switch the minimum power loss is identified.

The selected maneuverable switches are revised and this procedure is repeated until a

radial network is achieved. The second-stage is used to improve the solution obtained at

the first stage. For each opened switch selected from the first stage, two exchange

operations are performed involving pairs of switch neighbors. If a reduction in power loss

can be achieved, replace the opened switch with its neighbor switch. This algorithm is

Page 23: SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK ...read.pudn.com/downloads799/sourcecode/math/3153436/Thesis_fin… · SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK RECONFIGURATION

11

quite simple and effective, but many load flow computations are needed so it can be

computationally expensive. As a result, Raju and Bijwe [28] developed a reconfiguration

approach that included sensitivity analysis to supplement the two-stage heuristic

approach. The sensitivity of power loss with respect to the impedance magnitude of each

branch is computed and only the top ranked switches are investigated to determine the

one that provides the minimum power loss when opened. The loss sensitivity of the new

system with the selected switch opened is computed and the procedure is repeated until

the radial network structure is obtained. Finally, the power loss reduction for exchanging

opened switches with their neighbors is also checked to determine if the solution can be

improved. Besides, optimum power flows were considered in many reconfiguration

studies before conducting the heuristic algorithms. Gomes et al. [29] developed a refined

heuristic algorithm by including optimum power flow (OPF) where the status of all

maneuverable switches are represented as continuous values. The OPF is solved for the

meshed network to obtain the switch status results for all maneuverable switches. Instead

of studying the power loss reduction by opening each of the maneuverable switches, only

six switches with the smallest values are studied to reduce the computational time. The

switch with minimum power loss is selected as the opened switch and the list of

maneuverable switches is updated. The OPF and heuristic checking are repeated for the

remaining maneuverable switches until the radial structure is achieved. Schmidt et al.

[30]formulated the reconfiguration problem as a mixed integer nonlinear optimization

problem with integer variables representing the status of switches and continuous

variables representing the current flowing through all branches. The Newton method was

used to compute the branch currents within the integer best-first search.

Page 24: SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK ...read.pudn.com/downloads799/sourcecode/math/3153436/Thesis_fin… · SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK RECONFIGURATION

12

Heuristic algorithms are generally simple and fast, but optimality of the global solution

can not be guaranteed. Another type of reconfiguration approaches uses meta-heuristics

or artificial intelligent techniques. In a two-part paper presented by Chiang and Jean-

Jumeau [31], [32], a two-stage solution methodology based on a modified simulated

annealing technique and the ε-constraint method was proposed for solving network

reconfiguration problems with the objective of reducing losses and balancing the load.

Simulated annealing is a generic probabilistic meta-heuristic for locating a good

approximation to the global optimum of a given objective function in a large search space.

The name and inspiration come from annealing in metallurgy, a technique involving

heating and controlled cooling of a material to increase the size of its crystals and reduce

their defects. Chang and Kuo [33] also applied simulated annealing to the network

reconfiguration problem for loss minimization. They presented a set of simplified line

flow equations to compute the line loss and developed an efficient perturbation scheme

and initialization procedure for dynamically determining a better starting temperature for

the simulated annealing so that the entire computation could be sped up. Ant algorithms

are another class of artificial intelligence techniques inspired by the foraging behavior of

real ant colonies using a population-based approach with exploration for positive

feedback. Through a collection of cooperative agents called “ants”, the near-optimal

solution to the optimization problem can be effectively achieved. Su et al. [34] proposed

a method employing an ant colony search algorithm to solve network reconfiguration

problems using artificial ants. State transition rules along with global and local updating

techniques were introduced to ensure near optimal solutions. Recently, Chang [35] used

the ant colony search algorithm to solve the combinatorial optimization problem of

Page 25: SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK ...read.pudn.com/downloads799/sourcecode/math/3153436/Thesis_fin… · SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK RECONFIGURATION

13

network reconfiguration and capacitor placement. Particle swarm optimization (PSO)

algorithm was first proposed by Kennedy and Eberhart [36] to solve optimization

problems by simulating the migration and aggregation of bird flocks when seeking food

to determine a search path according to the velocity and current position of particle

without more complicated evolutionary operations. PSO algorithms have also been used

by many literatures to solve network reconfiguration problems [37]-[38]. In [39] a

discrete PSO algorithm was applied to two test systems but it was found to be inefficient

because large numbers of infeasible non-radial solutions that appeared at each generation

significantly increased the computation time before reaching a desired solution. Then

Abdelaziz et al. [40] revised this discrete PSO algorithm to overcome the drawbacks of

the proposed algorithm in [39]. The Tabu search is another popular approach in network

reconfiguration studies [41], [42].

Besides the above-mentioned approaches, genetic algorithms (GAs) that mimic the

process of natural selection and genetics are popular artificial intelligence techniques. GA

was first applied to the loss minimum reconfiguration problem by Nara et al. [43]. In the

proposed GA, the genetic strings are defined to represent the arc (branch) numbers and

the switch position on each arc, and an approximated fitness function was used to

represent the system power loss. The principle disadvantage of this basic GA is that such

binary codification problems can require very long string lengths that grow in proportion

to the number of the switches. To improve the performance of the GA, Zhu [44] modified

the string structure and fitness function to reduce the string depending on the number of

open switches. The fitness function also considered system constraints and an adaptive

mutation process that was used to change the mutation probability. Similarly, a refined

Page 26: SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK ...read.pudn.com/downloads799/sourcecode/math/3153436/Thesis_fin… · SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK RECONFIGURATION

14

GA was proposed by Lin et al. [45] to take advantage of the optimum flow pattern,

genetic algorithm and tabu search method Real number codifications were used instead of

binary codification, and the genes in each chromosome represented the open switches in

the network. A competition mechanism based on the fitness value was implemented in

the search process to decide whether crossover or mutation was needed for the next step.

A tabu list was introduced to define forbidden moves in the searching process. Recently,

a large number of literatures have been published to present their contributions on

improving genetic algorithm for solving network reconfiguration problems [46], [47],

[48], [49], [50]. The improvements include new codification methods, adaptive operators,

and changes in fitness functions.

In addition to these classic meta-heuristics or artificial intelligence techniques, some

new approaches have also been introduced in network reconfiguration studies. The

harmony search algorithm (HSA) is a new meta-heuristic population search algorithm

proposed by Geem et al. [51], which is developed by mimicking the process of searching

for better harmony in musical performance. The significant terms used in HSA include

harmony memory (HM), harmony memory size (HMS), harmony memory considering

rate (HMCR), pitch adjusting rate (PAR) and the number of improvisations (NI). HSA

was introduced to solve network reconfiguration problem by Rao et al. [52], and its

performance was well compared with GA and tabu search approaches. Compared to

heuristic methods, meta-heuristics or artificial intelligence techniques are well suited for

solving mixed-binary optimization problems and are more likely to achieve solutions that

are near the global optimal. However, these methods are generally not repeatable and

may require several executions to obtain the best solution.

Page 27: SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK ...read.pudn.com/downloads799/sourcecode/math/3153436/Thesis_fin… · SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK RECONFIGURATION

15

Different from heuristics and artificial intelligence techniques, mixed-integer

programming methods can also be used to solve network reconfiguration problems. This

type of approach can acquire global optimal solutions but is much more complicated than

the other two approaches, and often requires commercial numerical solvers to obtain a

solution. However, with the aid of advanced high-performance computers, mixed-integer

programming methods are becoming more and more popular for solving network

reconfiguration problems. Ramos et al. [53] linearized the problem and then solved the

linearized optimization problem using mixed-integer linear programming, however the

solution does not represent losses exactly. In order to overcome such a drawback,

Romero-Ramos et al. [54] presented a nonlinear formulation using a nonconventional

group of variables to be solved using a mixed-integer nonlinear optimizer. Khodr et al.

[55] also employed an exact model of losses in a Benders decomposition solution

apporach. However, the optimization problem models in [54] and [55] are both non-

convex so there is no assurance of convergence to the global optimal solution. Thus, Jabr

et al. [56] presented an exact mixed-integer conic programming model using convex

continuous relaxation, so the solution obtained was guaranteed to be globally optimal.

The study of network reconfiguration traces back to 1970’s, with thousands of related

papers published in the past 40 years, and many of the solution approaches are quite

mature. However, the distribution system infrastructure is faced with many new changes

including more remotely controlled maneuverable switches, the integration of distributed

energy resources and highly uncertain, time-varying load patterns, for instance, from

electric vehicle charging, requiring new approaches to the reconfiguration problem. In [1],

[57] and [58], the opportunities and new challenges for the design and implementation of

Page 28: SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK ...read.pudn.com/downloads799/sourcecode/math/3153436/Thesis_fin… · SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK RECONFIGURATION

16

reconfiguration algorithms are discussed within the context of “smart grid” development

efforts. With the development of the “smart grid” comes increased numbers of smart

meters, advanced monitoring technology, intelligent control agents with better

communication capabilities, and well-developed demand response strategies and self-

response capabilities. All these new developments will enable faster and more accurate

reconfiguration of distribution feeders. However, stricter power quality constraints, new

topologies including meshed structures and islanding, and the increase in operating data

present challenges to the development of efficient reconfiguration strategies. The authors

in [58] conceived a system for automatic reconfiguration of distribution networks based

on a heuristic method to determine the best network topology, and some preliminary

results were also given. In [59], studies of time-domain three-phase transient behaviors of

large-scale distribution networks were conducted, which have been proven to be of great

importance for implementation of smart grid reconfiguration principles. With the

increased penetration of distributed energy resources, the effects of distributed generation

are included in most recent network reconfiguration studies. Wu et al. [60] proposed a

reconfiguration methodology based on an ant colony algorithm that is aimed at achieving

the minimum power loss and incremental load balance factor for radial distribution

networks with distributed generators, and it was shown that lower system losses and

better load balancing results would be achieved with the help of distributed generation.

Rao et al. [61] presented their study based on harmony search to determine the optimal

network reconfiguration and optimal outputs of grid-connected distributed energy

resources at the same time in order to minimize power losses in distribution systems.

Song et al. [62] proposed both operation and integration schemes of distributed energy

Page 29: SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK ...read.pudn.com/downloads799/sourcecode/math/3153436/Thesis_fin… · SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK RECONFIGURATION

17

resources in network reconfiguration for loss reduction and service restoration, for both

radial and meshed network structures. Network reconfiguration is indeed an important

feature of active distribution network management at both planning and operation levels,

and thus comprehensive studies including network reconfiguration as only one part have

been presented. Martins and Borges [63] gave a model for active distribution system

expansion planning based on a genetic algorithm, and distributed generation was

considered together with conventional alternatives for expansion including rewiring,

network reconfiguration, and the installation of new protection devices. Two different

methods for uncertainties incorporation through the use of multiple scenario analysis

were also proposed and compared. In [64], a multi-objective optimization model for the

operation of distribution systems with large numbers of single-phase solar generators was

proposed, which was used to minimize phase imbalances and energy losses in three-

phase unbalanced distribution systems by controlling switched capacitors, voltage

regulators and reconfiguration switches. The genetic algorithm with a decision-making

process was used for solving this multi-objective optimization problem and stochastic

data of solar generators was also included.

Page 30: SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK ...read.pudn.com/downloads799/sourcecode/math/3153436/Thesis_fin… · SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK RECONFIGURATION

18

Chapter 3 Three Methods Proposed for Reconfiguring

Distribution Systems

Network reconfiguration involves determining the optimal open or close switch states

in the distribution network. In this Chapter, the network reconfiguration problem is

formulated as a nonlinear optimization problem with an objective that is a function of the

switch states. Three new solution methods are proposed, including a revised heuristic

algorithm based on branch-exchange and single-loop optimization, a hybrid method

based on optimal power flow and heuristics and a revised genetic algorithm.

3.1 Problem Formulation

Network reconfiguration is mostly used to reduce power losses in distribution systems,

and thus the objective function is defined as

2

1

min minM

loss i i

i

f P I r

(3.1)

where, M is the total number of branches in the system. Ii is the ith

branch current. ri is the

ith

branch resistance.

Line reactance is constant regardless of the structure, so the power loss only depends

on line currents that can be calculated using nodal voltages. Suppose A is the node branch

incidence matrix for the system, then

(3.2)

where Vbus is the nodal voltage vector, Ibranch is the branch current vector, and Zbranch is

the branch reactance (diagonal) matrix.

Total power losses in the system are computed as

Tbus branch branchA V Z I

Page 31: SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK ...read.pudn.com/downloads799/sourcecode/math/3153436/Thesis_fin… · SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK RECONFIGURATION

19

lossP T * T -T -* T *branch branch branch bus branch branch branch busI R I V A Z R Z A V (3.3)

Let -T -* Tbranch branch branchT A Z R Z A , and

21 1 2 1

2 2 21 1 1

22 1 2 2

2 2 21 1 1

21 2

2 2 21 1 1

M M Mi i i i i i Ni i

i i ii i i

M M Mi i i i i i Ni i

i i ii i i

M M MNi i i Ni i i Ni i

i i ii i i

a r a a r a a r

Z Z Z

a a r a r a a r

Z Z Z

a a r a a r a r

Z Z Z

T (3.4)

where, N is the total number of buses, aij is the ij-th element of matrix A, Zi = ri + j∙xi is

the reactance for the ith

branch.

Except the substation node, all nodes are considered as PQ nodes, and the nodal

voltages can be obtained from

1 1

1 1

N N

i i ij j ij j i ij j ij j

j j

N N

i i ij j ij j i ij j ij j

j j

P e G e B f f G f B e

Q f G e B f e G f B e

(3.5)

where Vi = ei +j fi is the ith

node voltage. Yij = Gij+jBij is the ij-th element of the node

admittance matrix, which is defined by

(3.6)

and, Ybranch=Z-1

is the (diagonal) branch admittance matrix. The nodal branch incidence

matrix (A) is constant for a fixed topology, but changes when the network is reconfigured.

Network reconfiguration is essentially an optimal decision to open or close switches,

so the states of switches are the primary parameters in the reconfiguration study. It is

assumed that each branch is equipped with a remotely controlled switch, and the state of

×

T

branchY = A Y A

Page 32: SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK ...read.pudn.com/downloads799/sourcecode/math/3153436/Thesis_fin… · SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK RECONFIGURATION

20

each switch is defined as

1,

0,

1,

j

switch j isclosed and directionis sameastheinitial

S switch j isopen

switch j isclosed and directionisopposite

(3.7)

where, the direction refers to the direction of current flow.

The calculation starts from the assumption that all switches are initially closed, and the

node branch incidence matrix for this network is A0, which is constant for a specific

system. Then the node branch incidence matrix (A) for any other topology of the system

can be determined by the initial node branch incidence matrix and the switch states, as

(3.8)

where aij =A(i, j) is the matrix element and aij0 =A0(i, j), and Sj is the state of switch j.

Substituting (3.4) and (3.8) into (3.3), the power loss becomes

0 0 2

*

21 1 1

N N Mik jk k k

loss j i

j i k k

a a r SP V V

Z

(3.9)

Substituting (3.8) into (3.6), Gij and Bij can be represented as

0 0 2 0 0 2

2 2 2 21 1

M Mik jk k k ik jk k k

ij ij

k kk k k k

a a r S a a x SG B

r x r x

(3.10)

Besides, several constraints must be considered when solving the optimization problem:

(1) System Structure Constraint

The distribution network is radial without meshes before and after reconfigurations, so

(3.11)

where, d is the total number of slack buses.

A(i, j) = A0(i, j) ×S

j

1

M

k

k

S N d

Page 33: SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK ...read.pudn.com/downloads799/sourcecode/math/3153436/Thesis_fin… · SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK RECONFIGURATION

21

All loads are served without disconnections, so

rank(A) = N – d (3.12)

In addition, at least one branch is open in each loop, so

(3.13)

where, Mk is the amount of branches in the kth

loop.

(2) Voltage Limit

ANSI C84.1 [65] recommends voltage magnitudes be within 5% of the norminal

value. No overvoltage (>1.1 pu) or undervoltage (<0.9 pu ) is allowed [66]. In the

following study, the ±5% limit is considered as “strict” and “excellent”, and ±10% limit

is considered as “loose” and “fair”.

0.9 ∙ 𝑉𝑛𝑜𝑟𝑚 ≤ |𝑉𝑖| ≤ 1.1 ∙ 𝑉𝑛𝑜𝑟𝑚 (3.14)

(3) Current Limit

Each line is loaded within its capacity. And, branch currents are limited by

|𝐼𝑏𝑟𝑎𝑛𝑐ℎ,𝑖| ≤ 𝐼𝑏𝑟𝑎𝑛𝑐ℎ,𝑖𝑚𝑎𝑥 (3.15)

In summary, according to the above analysis the network reconfiguration problem can

be finally formulated as

0 0 2*

21 1 1

min min

. . (3.5),(3.7),(3.11) ~ (3.15).

N N Mik jk k k

j i

j i k k

a a r Sf V V

Z

s t

(3.16)

All the parameters except the switch states are constant for a specific system. Thus the

above formula is a function of switch states and because the switch states are discrete

variables, network reconfiguration is a constrained, interger, nonlinear optimization

1

1kM

i ki

S M

Page 34: SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK ...read.pudn.com/downloads799/sourcecode/math/3153436/Thesis_fin… · SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK RECONFIGURATION

22

problem.

3.2 Heuristic Method

The heuristic algorithm is developed based on branch-exchange and single-loop

optimization. Generally multiple tie-switches exist in a distribution network, and the

closures of these switches will lead to a meshed network with multiple loops. Single-loop

optimization indicates that each time only a loop is studied, and this loop is the one with

the largest voltage difference between two sides of the initially opened tie-switch. In

order to regain radial system structure, a switch must be selected from the studied loop to

open, and this switch is determined using branch-exchange method.

Suppose the sectionalizing switches 1 ~ k-1 are at one side of the initially opened tie-

switch n, and sectionalizing switches k ~ n-1 are at the other side, shown in Fig. 3.1. All

other switches are represented as the set C.

……

n

1 2 k-1… ...

k k+1 n-1…...

b1 b2bk-1

bk bk+1 bn-1…

b0 bk-2…

bn-2

Figure 3.1 Structure of the switches.

Then, the total power losses can be calculated as

1 1

(0) 2 2 2

1

k n

i i i i j jlossi i k j C

P I R I R I R

(3.17)

where, Ii and Ri are respectively the magnitude of the current and the resistance at branch

i.

If the tie-switch is closed and its adjacent sectionalizing switch n-1 is opened, the load

at bus bn-1 is transferred to the other side. Because all the network loads can be modeled

Page 35: SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK ...read.pudn.com/downloads799/sourcecode/math/3153436/Thesis_fin… · SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK RECONFIGURATION

23

as constant current injections, the switching operation in a loop only changes the flow

pattern of the loop itself. Thus, the new branch currents can be defined as

, 1,2,..., 1,

, , 1,..., 1

,

i

i i

i

I I i k n

I I I i k k n

I i C

(3.18)

The new power loss can be evaluated using new currents, and the changes in power

loss are

1 1(1) (0) 2

1 1

2n k n

loss i i i i iloss lossi i i k

P P P I R I I R I R

(3.19)

Bus voltages Vk-1 and Vn-1 for the initial network can be respectively calculated as

1 1

1 0 1 01 1

k n

k i i n i ii i

V V I R V V I R

(3.20)

If Vk-1≤Vn-1, 1 1

1

k n

i i i i

i i k

I R I R

and ∆Ploss is always greater than zero. For opening of

the next switch n-2, the new power loss is compared with Ploss(1)

using the same method,

and it is easily proved that the power losses increase. Besides, opening all of the other

switches in the same direction will produce more power losses. Thus, the power loss

reduction cannot be achieved by opening the sectionalizing switches in the higher-voltage

side. Instead, power loss reduction could only be achieved if Vk-1>Vn-1, i.e. opening the

switch at the lower-voltage side of the initially opened tie-switch.

Besides, according to (3.9), power loss is a function of switch states, and it can be

easily calculated if the switch states are known. Thus, the power losses in the system after

reconfiguration are calculated using the exact power flow results instead of approximate

formulas that are used in [22] and [24] so that the algorithm is able to get closer to the

Page 36: SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK ...read.pudn.com/downloads799/sourcecode/math/3153436/Thesis_fin… · SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK RECONFIGURATION

24

true optimal solution.

In summary, the flowchart of the proposed heuristic algorithm is given as Fig. 3.2.

First, number all buses and branches, and identify all tie-switches in the subsystem being

studied. Divide all other sectionalizing switches into two groups according to their

locations at the left or right side of the tie-switch. Solve the power flow for the initial

system. Then, determine the optimal switch-pair to minimize power losses according to

the following steps.

(1) Each time, the tie-switch with the biggest voltage difference across it is chosen.

Then the initially closed switch will be selected from the sectionalizing switches in the

loop that is formed if the studied tie-switch is closed. The location of candidate switches

at two directions makes it necessary to determine the opening of switches at the side that

can lead to power loss reduction. It is proved that power loss reduction can only be

achieved by opening the switch at the lower voltage side of the initially opened tie-switch

and closing the tie-switch.

(2) Start the search from the adjacent switch of the tie-switch. Let the states of the

adjacent switch and tie-switch be zero and 1/-1 (dependent on the current direction)

respectively.

(3) Calculate power losses using the new switch states. If the power losses are not

reduced, exchanging the switch states in this loop cannot attain power loss reduction, so

keep the switch states at their initial values. Otherwise, keep checking the power loss

reduction by letting the state of the next switch in the same side be zero instead. Repeat

until no further power loss reductions occur.

(4) Check whether the system with the new switch states satisfies all constraints. If so,

Page 37: SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK ...read.pudn.com/downloads799/sourcecode/math/3153436/Thesis_fin… · SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK RECONFIGURATION

25

record the results and refine the switch states for the system. Otherwise, choose the

switch states with the minimal power loss that satisfies all constraints.

(5) Repeat procedures (1)~(4) until finishing all loops and no more reduction occurs.

The final switch states are taken as the “optimal” solution for the reconfiguration problem.

Number all buses and branches. Identify all tie-switches and divide left / right side sectionalizing switches.

Conduct a load flow.

Number all buses and branches. Identify all tie-switches and divide left / right side sectionalizing switches.

Conduct a load flow.

Choose the tie-switch with the biggest voltage differenceChoose the tie-switch with the biggest voltage difference

Decide search directionDecide search direction

V(left-side)-V(right-side)<0?V(left-side)-V(right-side)<0?

Revise switch statesRevise switch states

Calculate power losses using (3.9)Calculate power losses using (3.9)

Power Loss Reduced?Power Loss Reduced?

Continue with the next switch in the same side Continue with the next switch in the same side

Power Loss Reduced?Power Loss Reduced?

Back to the result obtained at last iterationBack to the result obtained at last iteration

All constraints satisfied?All constraints satisfied?

Record the new switch states, and prepare for next iteration.

Record the new switch states, and prepare for next iteration.

Finish all possible branch-exchanges?Finish all possible branch-exchanges?

Get the optimal solutionGet the optimal solution

Choose the

feasible, secondary

optimal switch

states instead.

Choose the

feasible, secondary

optimal switch

states instead.

STOPSTOP

Right-sideNOYESLeft-side

NO

YES

YES

NO

NO

YES

YES

NO

Figure 3.2 Flowchart of the heuristic algorithm based on branch-exchange and single-loop

optimization.

3.3 Hybrid Method

3.3.1 Hybrid Method

The second method is called hybrid because it is a combination of optimal power flow

(OPF) and heuristic method. From (3.16), it is known that network reconfiguration can be

Page 38: SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK ...read.pudn.com/downloads799/sourcecode/math/3153436/Thesis_fin… · SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK RECONFIGURATION

26

considered as an OPF problem. If we relax the discrete switch states into continuous

values between -1 and 1, the new and continuous OPF problem can be solved using

conventional nonlinear programming techniques.

After solving OPF, the solutions are continuous values between -1 and 1. In order to

obtain the finally feasible results, it is necessary to determine the integer values based on

OPF solutions. Thus, the proposed hybrid method is composed of two stages: the first

stage is to solve OPF using interior-point method; and the second stage is to revise OPF

solutions into integer switch states using heuristic corrections. The flowchart of the entire

algorithm is given as Fig. 3.3.

(1) Number all the buses and branches at first.

(2) Determine the infeasible switches. Those switches that must be always closed are

defined as “infeasible” switches because their openings will lead to disconnected network,

and the states of these switches are deleted from the decision variables in the objective

function so that the order of the matrix formed during computation is reduced.

(3) Determine the loops possibly formed by the closures of tie-switches. A loop is

defined by the closing of an initially opened tie-switch and other initially closed

sectionalizing switches.

(4) Form the OPF problem as (3.16) and use the interior-point algorithm to solve the

optimization problem.

Page 39: SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK ...read.pudn.com/downloads799/sourcecode/math/3153436/Thesis_fin… · SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK RECONFIGURATION

27

1. Number the buses and branches

2. Determine the infeasible switches, and delete the states of

them from the decision variables in the objective function

3. Determine the loops formed by the closures of tie-switches

4. Form the OPF problem and then solve the

optimization problem

5.2 Acquire candidate switches waiting for recovery and divide

them into groups according to the loops which they belong to.

Choose the unsolved group with the least number of

candidate switches to study.

Open a switch k and close all other switches in the

studied group, then compute the new power loss dPk.

5.1 Obtain the final results for those switches if their

OPF solutions are already integers

Recover integer values

from the OPF solutions.

All switches in the studied group tested?

Decide the “0-state” switch that leads to the smallest dPk and revise

the switch states in the studied group into integer values.

Update the candidate switches in the remaining groups.

All groups solved?

STOP

YES

NO

YES

NO

Figure 3.3 Flowchart of the proposed hybrid method.

(5) Decide the opened switch for each loop based on OPF solutions. After the first four

steps, the relaxed OPF problem is solved and the solutions of continuous switch states are

obtained. In order to determine the integer states (0, 1 or -1) of all switches, the following

procedures are conducted:

(5.1) Obtain the results for parts of switches based on the OPF solutions: the OPF

solutions of all decision variables can be divided into integers and decimal numbers. The

Page 40: SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK ...read.pudn.com/downloads799/sourcecode/math/3153436/Thesis_fin… · SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK RECONFIGURATION

28

switches with the integer solutions (0, -1 and 1) are marked as finally solved and their

states are exactly the OPF solutions. Then, on the basis of these solved switches, new

infeasible switches could be induced. Thus find the infeasible switches from the

remaining ones, and revise the states of these switches into 1/-1 (the positive/negative

sign is decided according to the current direction).

(5.2) After (5.1), the remaining switches are considered as candidate switches, and

their states need to be revised into integers using the following heuristic method.

(5.2.1) Divide the candidate switches into groups according to the loops which they

belong to.

(5.2.2) Study the unsolved group with the least number of candidate switches and

decide the “0-state” switch. The “0-state” switch is selected provided the power loss

increment is least if its state is changed from OPF solution to 0 and the states of all other

candidate switches in the same group are changed from OPF solutions to 1/-1.

(5.2.3) Update the candidate switches in all unsolved groups and repeat (5.2.2) until

finishing all groups. Before moving to the next group, the candidate switches in all other

groups are checked again to find the infeasible switches on the basis of the new switch

states solved in (5.2.2). The infeasible switches are deleted from the candidated switches

and their states are revised into 1/-1.

3.3.2 Sensitivity Analysis Based on OPF Solutions

As illustrated in the above study, power loss is the function of switch states. The

optimal solution (S*) of the relaxed OPF problem minimizes the power losses (Ploss*) by

neglecting the constraint that switch states can only be three integer values. Any

Page 41: SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK ...read.pudn.com/downloads799/sourcecode/math/3153436/Thesis_fin… · SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK RECONFIGURATION

29

deviations of switch states from S* will cause changes in power losses. Thus, the

sensitivity of power loss with respect to switch states is evaluated.

From (3.9), the power loss can be represented as

0 0 2

*

21 1 1

( ( ), )N N M

ik jk k kloss j i

j i k k

a a r SP V V f V S S

Z

(3.21)

If a small change S is added into the switch state vector S, then the new power loss is

loss loss

f fP P f

VV,S S S

V S S (3.22)

where Ploss is the power loss change due to the change of switch states.

Thus, the sensitivity value around the operating point S0 can be calculated as

( )( )

lossP f f

0 00 0 0

V S ,SS V S ,S

V

S V S S (3.23)

The representations of the three matrices in (3.23) could be acquired from (3.5)~(3.10)

and the results are given in (3.24)~(3.26).

1 2

, , ,loss loss loss

M

P P Pf

S S S

S (3.24)

where, * 0 0

21 1

2 , 1,2,..., .N N

loss loss hj jh i ih

h h j i h

P P rV a V a h M

S S z

1 1

, , , ,loss loss loss loss

N N

P P P Pf

e f e f

V (3.25)

where,

1 1 2 2 0 0 2

21

1 1 2 2

2 2 2

,

2 2 2

lossi i N iN

Mi ik jk k k

ij

kloss ki i N iN

i

Pe t e t e t

e a a r St

P zf t f t f t

f

.

Page 42: SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK ...read.pudn.com/downloads799/sourcecode/math/3153436/Thesis_fin… · SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK RECONFIGURATION

30

1

1 1 1 1 1 1

2 2 1

1 1 1 1 1 1

2 2 1

2 2 1

2 2

P P P P P P

N N M

Q Q Q Q Q Q

N N M

Ph Ph Ph Ph Ph

N N

Qh Qh Qh Qh

N N

y y y y y y

e f e f S S

y y y y y y

e f e f S SV

y y y y y

e f e f S

y y y y

e f e f

S

1

Ph

M

Qh Qh

M

y

S

y y

S S

(3.26)

where,

1 1

1 1

N N

i ij j ij j i ij j ij j i

j jPi

N NQi

i ij j ij j i ij j ij j i

j j

e G e B f f G f B e Py

yf G e B f e G f B e Q

,

(0) (0) (0)

,

1 1

2 2 2 2

(0) (0) (0)

,

1 1

2

, ,

2

n nPh

h k h k i ik h k h k i ik h k k

i ik k kk kn n

Qh k k k k

h k h k i ik h k h k i ik h k k

i ik

ye f e a e f f a a S

S r x

y r x r xe f e a e f f a a S

S

,

As a result, the sensitivity is solved and it is a 1´m row vector. Thus the power loss

change for shifting switch states from OPF solutions to the extreme integer values is

evaluated by solving (3.27) iteratively with a small step.

(0) (0) (0)

,

1 1

2 2 2 2

(0) (0) (0)

,

1 1

2

, ,

2

n nPh

h k h k i ik h k h k i ik h k k

i ik k kk k

n nQh k k k k

h k h k i ik h k h k i ik h k k

i ik

ye f e a e f f a a S

S r x

y r x r xe f e a e f f a a S

S

, , ,

, , , , , , ,

1 1

, ,

, ,

,

,

h h j h hj h h j h h j

Ph Phn n

j jh h j h hj h i i h i i h h j h h j h i i h i i

i i

h hj h hj

Qh

j h hj h hj hi i hi i

i

e l f h j h e h f l j hy y

ande fe l f h l e h f j h e h f l l f h e j h

e h f l j hy

e e h f l l f h e j h

1 1

0 0 2 0 0 2

2 2 2 21 1

,

,

, .

h hj h hj

Qhn n

j h hj h hj hi i hi i

i

m mik jk k k ik jk k k

ij ij

k kk k k k

e l f h j hy

andf e l f h l e h f j h

a a r S a a x Sand l h

r x r x

, , ,

, , , , , , ,

1 1

, ,

, ,

,

,

h h j h hj h h j h h j

Ph Phn n

j jh h j h hj h i i h i i h h j h h j h i i h i i

i i

h hj h hj

Qh

j h hj h hj hi i hi i

i

e l f h j h e h f l j hy y

ande fe l f h l e h f j h e h f l l f h e j h

e h f l j hy

e e h f l l f h e j h

1 1

0 0 2 0 0 2

2 2 2 21 1

,

,

, .

h hj h hj

Qhn n

j h hj h hj hi i hi i

i

m mik jk k k ik jk k k

ij ij

k kk k k k

e l f h j hy

andf e l f h l e h f j h

a a r S a a x Sand l h

r x r x

, , ,

, , , , , , ,

1 1

, ,

, ,

,

,

h h j h hj h h j h h j

Ph Phn n

j jh h j h hj h i i h i i h h j h h j h i i h i i

i i

h hj h hj

Qh

j h hj h hj hi i hi i

i

e l f h j h e h f l j hy y

ande fe l f h l e h f j h e h f l l f h e j h

e h f l j hy

e e h f l l f h e j h

1 1

0 0 2 0 0 2

2 2 2 21 1

,

,

, .

h hj h hj

Qhn n

j h hj h hj hi i hi i

i

m mik jk k k ik jk k k

ij ij

k kk k k k

e l f h j hy

andf e l f h l e h f j h

a a r S a a x Sand l h

r x r x

Page 43: SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK ...read.pudn.com/downloads799/sourcecode/math/3153436/Thesis_fin… · SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK RECONFIGURATION

31

* ** *

*

( )( )

loss

f fP

V S ,SV S ,S

VS S

V S S (3.27)

3.4 Genetic Algorithm

Compared with the existing GAs used in network reconfiguration studies, both

encodings and operators in the algorithm are improved in order to better solve the

reconfiguration problem for distribution systems with the consideration of distributed

generation. Fig. 3.4 shows the flowchart of the revised genetic algorithm.

(1) Encoding and Initialization

The size of the population and the maximal allowed generations are defined first. In

the first generation, all chromosomes in the population are required to be feasible, i.e.

satisfying all defined constraints. The great majority of the existing GA applications to

the reconfiguration problem are done using binary codifications to represent the locations

and status of switches, and thus the string is quite long even without the inclusion of DG

parameters. In this thesis, the real-valued string is used instead of the binary codification

to reduce the number of bits. Each chromosome in a population is defined as Fig. 3.5 and

it has T+2K genes in total:

(a) Suppose there are totally T initially opened tie-switches in the system. The first T

genes represent the opened switches.

(b) The following 2K genes are the active power and reactive power generated from K

grid-connected DG units.

Page 44: SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK ...read.pudn.com/downloads799/sourcecode/math/3153436/Thesis_fin… · SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK RECONFIGURATION

32

k=1. Define 1st generation and each

chromosome must be feasible.

k=1. Define 1st generation and each

chromosome must be feasible.

Initialization: pop_ size, max_ genInitialization: pop_ size, max_ gen

System Structure Constraints System Structure Constraints

Voltage and Current ConstraintsVoltage and Current Constraints

Satisfy all constraints

Select an offspringSelect an offspring

Delete this

offspring from

the population

Delete this

offspring from

the population

Violate any constraint

Violate any

constraint

Satisfy all constraints

Keep this offspring in the population

and compute its operating costs

Keep this offspring in the population

and compute its operating costs

Elitism selection from the remained

feasible population

Elitism selection from the remained

feasible population

All offsprings are evaluated?All offsprings are evaluated?

YES

NO

k=k+1k=k+1

k>max generationk>max generation STOPSTOPYES

NO

i=1i=1

rand<0.5 ?rand<0.5 ?

Cross-Over

after_co=pop_ size+1

Cross-Over

after_co=pop_ size+1

i=i+1 i=i+1

i>pop_size ?i>pop_size ?

j=1j=1

rand<0.5 ?rand<0.5 ?

Mutation

after_mu=after_co+1

Mutation

after_mu=after_co+1

j=j+1 j=j+1

j>after_co ?j>after_co ?

NO

YES

YES

NO

YES

NO

NO

YES

Figure 3.4 Flowchart of the proposed genetic algorithm.

OS1~OST PDG1 QDG1 ... PDG,K QDG,K

Figure 3.5 The genes included in each chromosome.

Page 45: SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK ...read.pudn.com/downloads799/sourcecode/math/3153436/Thesis_fin… · SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK RECONFIGURATION

33

(2) Cross-Over

Based on the above encodings, each string is mixed of integers and continuous values.

It is assumed that there are both half chance to apply the cross-over and mutation

operators. The cross-over operator randomly selects two chromosomes (A, B) and then

exchanges their information to create two new chromosomes (C, D) following the rule

based on one-point technique and arithmetical operator:

(a) Select a gene i from T+2K genes randomly.

(b) If i ≤ T, C (1: i ) = A (1: i ), C(i+1: T) = B (i+1: T), and C(T+1 : T+2K ) = 0.2 ∙

A(T+1: T+2K ) + 0.8 ∙ B( T+1: T+2K ).

(c) If i >T, C (1: T) = A (1:T), C(T+1: i ) = 0.8 ∙ A(T+1: i ) + 0.2 ∙ B( T+1: i ), and

C(i+1: T+2K ) = 0.2 ∙ A(i+1: T+2K ) + 0.8∙B( i+1: T+2K).

The other chromosome D is obtained in the opposite way to C by reversing A and B in

the above equations.

(3) Mutation

The mutation operator randomly changes one bit in the string to introduce new

information into the offspring, and suppose the jth

gene is selected. If

(a) j ≤ T, this gene is replaced by another value in its domain, i.e. another switch in

the corresponding loop.

(b) j > T, this gene is replaced by another feasible value within the capacity of DG

units.

(4) Elitism Selection

Before evaluating the fitness values of the new population, all repeated chromosomes

are deleted and the feasibility of each offspring is evaluated by checking the system

Page 46: SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK ...read.pudn.com/downloads799/sourcecode/math/3153436/Thesis_fin… · SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK RECONFIGURATION

34

structure constraints and voltage/current constraints in turn. Then, the operating costs of

all feasible offsprings are computed and the elitism is used to select the best population.

3.5 Case Studies

In order to test the performance of the proposed three methods, they are applied to

reconfigure two test systems, respectively. The first test system is a three-feeder

distribution system [24] and the second test system is a 33-bus distribution system [25].

3.5.1 Case I : Three-Feeder Test System

Fig. 3.6 shows the topology of the three-feeder test system, which includes three

feeders, three tie-switches and sixteen buses. The numbers with circles denote the

numbers of switches and branches. The nominal voltage is 13.8 kV and system frequency

is 60 Hz. Total power losses are 710.1 kW and the minimal nodal voltage is 0.9675 p.u.

at bus 12.

Figure 3.6 Three-feeder test system.

First, all branches and buses are numbered in the figure. There are three loops formed

after closing all tie-switches ○16 , ○17 , ○18 , which are respectively: 1) ○1 -○3 -○4 -○16 -○10 -

1 2 3

4

5

67

8

9

11

10

12

13

14

1516

1 2

3

4

5

6

7

8 9

10

11

12

13

14

15

16

17

18

Page 47: SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK ...read.pudn.com/downloads799/sourcecode/math/3153436/Thesis_fin… · SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK RECONFIGURATION

35

○8 -○7 (loop-1); 2) ○7 -○9 -○17 -○13 -○12 -○2 (loop-2); 3) ○3 -○5 -○6 -○18 -○15 -○14 -○12 -

○2 -○1 (loop-3).

(1) Heuristic Algorithm

The voltage differences across three tie-switches are 323.29 V, -342.43 V and -120.92

V, respectively. Thus, loop-2 is first studied and switches ○7 and ○9 are the candidate

open switches. In summary, the finally optimal results of the centralized approach are

obtained after five iterations. Table 3.1 gives the simulation results and only the iterations

with power loss reductions are shown. The final opened switches are ○9 , ○10 and ○18 .

The power loss is reduced to 645.65 kW by 9.08%, and the minimum voltage is 0.96 p.u.

at bus 12. CPU computing time is only 0.041 seconds.

Table 3.1 Simulation Results of Centralized Method For Three-Feeder Test System

Iterations Switch Pair Power loss after

reconfiguration Close Open

0 --- --- 710.1 kW

1 ○17 ○9 670.62 kW

2 ○16 ○10 645.65 kW

(2) Hybrid Method

In the system, the infeasible switches are ○1 , ○2 , ○3 , ○7 , ○11 , ○12 , and the values of

their states are: S1 = S2 = 0, and S3 = S7 = S11 = S12 = 1.The OPF problem is formed as

(3.16), and then solved using interior-point algorithm. Table 3.2 shows the OPF solutions.

Table 3.2 Solutions of OPF for Three-Feeder Test System

Objective Function fmin

(minimal power loss) Solutions of Switch States

620.0 kW S18=0, S9=-0.3232, S16=0.4773, S10=0.5227,

S17=0.6768, All others = 1.

Page 48: SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK ...read.pudn.com/downloads799/sourcecode/math/3153436/Thesis_fin… · SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK RECONFIGURATION

36

After solving the relaxed OPF problem, the solutions of most switch states are integers

and these values are exactly the final results. Because S18=0, switch ○18 will be opened

for removing loop-3. Thus, the switch states that need revise are S9, S16, S10 and S17,

only 4/18 of total switches. These four candidate switches are divided into two groups: 1)

S10 and S16 (at loop-1); 2) S9 and S17 (at loop-2). Because the states of all other

switches in loop-1 and loop-2 are 1, the state of one candidate switches in each group has

to be revised to 0 and the other one is revised to 1/-1.

Since each of two groups have two candidate switches, the selection of “0-state”

switch can start from any group and group-1 is chosen randomly. S16 and S10 are

selected to be 0 in turn, and the power losses for two scenarios are compared in Table 3.3.

Finally, the states of switches ○10 and ○16 are respectively revised to 0 and 1.

Table 3.3 Power Losses for Different “0-State” Switch in Loop-1

“0-state” Switch States of the Switches in

the Same Group Power Losses Selected Opened Switch

16 S10=1, S16=0 667.03 kW 10

10 S10=0, S16=1 642.79 kW

Because the opening of ○10 doesn’t affect the connection of loop-2, no infeasible

switch is deleted from group-2. S9 and S17 are respectively chosen to be 0, and the

power losses for two scenarios are compared in Table 3.4. Similarly, the states of

switches ○9 and ○17 are respectively revised to 0 and -1 based on the comparison.

Table 3.4 Power Losses for Different “0-State” Switch in Loop-2

“0-state” Switch States of the Switches in

the Same Group Power Losses Selected Opened Switch

9 S9=0, S17=1 645.65 kW 9

17 S17=1, S9=0 684.26 kW

Page 49: SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK ...read.pudn.com/downloads799/sourcecode/math/3153436/Thesis_fin… · SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK RECONFIGURATION

37

Finally the states of all candidate switches are revised and the optimal opened switches

for the system are ○9 ,○10 and ○18 . The power loss for the new structure is 645.65 kW,

9.08% reduction from the initial power loss. The entire computation costs 1.9 s.

The results of sensitivity around different switch states changing from the OPF

solution to 0 and 1 are solved using (3.23). Fig. 3.7 shows the sensitivity of power loss to

S9, S10, S16 and S17 respectively, and the difference of switch state between two points

is chosen as 0.03. Then the results of power loss changes for shifting S9, S10, S16 and

S17 from their OPF solutions to 0 and 1 are obtained, shown as Fig. 3.8. Because the

values of sensitivity are all negative, reducing switch states will lead to power loss

increment and increasing switch states will lead to power loss reduction on the contrary.

The results have shown that system power loss is more sensitive if switch states are

reducing to 0 than increasing to 1. And the power loss is more sensitive to S17 than S9,

and more sensitive to S16 than S10 when the switch states are close to 0. Consequently,

the best choice would be opening S9, S10 and closing S16, S17, which is same as the

result obtained using the hybrid method.

Figure 3.7 Results of sensitivity of power loss with respect to S9, S10, S16 and S17 respectively.

-260000

-160000

-60000

40000

0 0.2 0.4 0.6 0.8 1

Sen

siti

vit

y

Switch States

S9

S17

S10

S16

Page 50: SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK ...read.pudn.com/downloads799/sourcecode/math/3153436/Thesis_fin… · SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK RECONFIGURATION

38

Figure 3.8 Results of power loss changes for shifting S9, S10, S16 and S17 from their OPF solutions

to 0/1 respectively.

(3) Revised Genetic Algorithm

Fig. 3.9 gives the iterative results of the revised GA, and it finally converges to the

optimal result 645.65 kW after 1.64 s. The optimal opened switches are ○9 ,○10 and ○18 .

Figure 3.9 Iterative results of the revised GA for the 3-feeder test system.

3.5.2 Case II : 33-Bus Test System

Fig. 3.10 shows the topology of the 33-bus test system, which includes 33 buses and 5

tie-switches (○33 -○37 ). Total loads are 3715 kW and 2300 kVar. For the initial structure,

system power losses are 202.68 kW and the minimal voltage is 0.9131 p.u. at bus 18.

1 2 3 4 5 6 7 8 9 1010 1111 1212 1313 1414 1515 1616 1717

2626 2727 2828 2929 3030 31312222 2323 2424

1818 1919 2020 2121

2525 3232

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18

19 20 21 22

23 24 2526 27 28 29 30 31 32 33

3737

3636

3434

35353333

Figure 3.10 Single-line diagram of 33-bus test system.

-20000

0

20000

40000

60000

80000

0 0.2 0.4 0.6 0.8 1

Po

wer

Lo

ss

Ch

an

ges

/ W

Switch States

S9

S17

S10

S16

Page 51: SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK ...read.pudn.com/downloads799/sourcecode/math/3153436/Thesis_fin… · SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK RECONFIGURATION

39

(1) Heuristic Algorithm

The algorithm stops after 23 iterations. Table 3.5 gives the simulation results and only

the iterations with power loss reductions are shown. The final opened switches are ○7 ,

○9 , ○14 , ○32 and ○37 . System power loss is reduced to 139.55 kW by 31.15%, and the

minimum voltage is 0.94 p.u. at bus 32. CPU computing time is only 1.65 seconds. Fig.

3.11 shows the voltage magnitudes of all nodes before and after the reconfiguration. It

shows that voltages at most buses have increased a lot after the reconfiguration.

Figure 3.11 Voltage magnitudes of all nodes before and after the reconfiguration.

Table 3.5 Simulation Results Of Centralized Method For 33-Bus System

Iterations with Power Loss

Reduction

Switch Pair Power loss after

reconfiguration Close Open

0 --- --- 202.68 kW

1 ○35 ○8 153.49 kW

2 ○37 ○28 147.44 kW

4 ○8 ○10 145.92 kW

6 ○36 ○32 143.93 kW

9 ○10 ○11 143.71 kW

12 ○33 ○7 143.19 kW

13 ○28 ○37 142.76 kW

15 ○34 ○14 141.2 kW

18 ○11 ○9 139.55 kW

(2) Hybrid Method

Page 52: SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK ...read.pudn.com/downloads799/sourcecode/math/3153436/Thesis_fin… · SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK RECONFIGURATION

40

Solutions of the relaxed OPF are given in Table 3.6 and the results of opened switches

obtained after heuristic revision are given in Table 3.7. Finally, the optimal configuration

of the system is the one with switches ○7 , ○14 , ○9 , ○32 , ○37 opened and all other

switches closed. Sensitivity of the power loss with respect to each candidate switch is

studied and the result is shown as Fig. 3.12. The first three sensitive switches are S25,

S26 and S37. The entire computation time is 15.1 seconds.

Table 3.6 Solutions of OPF for 33-Bus Test System

Objective Function fmin

(minimal power loss) Solutions of Switch States

126.74 kW

S9=0, S10=0.391, S7=0.469, S32=-0.4939, S14=0.53,

S6=0.531, S25=0.6582, S26=0.688, S11=0.7275, S28=0.8218,

S37=0.8552, S36=0.8577, S27=0.9768. All others=1.

Table 3.7 Results of “0-State” Switches for 33-Bus Test System

Studied Group Candidate

“0-State” Switch Power Losses

Selected Opened

Switch

1 7 127.38 kW

7 6 132.39 kW

2 32 127.76 kW

32 36 128.2 kW

3

25 151.64 kW

37

26 147.25 kW

28 139.98 kW

37 139.55 kW

27 143.3 kW

Figure 3.12 Sensitivity of the power loss with respect to different switch states.

Page 53: SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK ...read.pudn.com/downloads799/sourcecode/math/3153436/Thesis_fin… · SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK RECONFIGURATION

41

(3) Revised Genetic Algorithm

Fig. 3.13 gives the iterative results of the revised GA, and it finally converges to the

optimal result 139.55 kW after 8.1 s. The optimal opened switches are ○7 , ○14 , ○9 , ○32 ,

○37 .

Figure 3.13 Iterative results of the revised GA for the 33-bus test system.

3.6 Comparison of Three Methods

According to the above simulation results, the performances of three proposed

methods are compared as Table 3.8. All three methods can help reduce power losses in

distribution systems, but their performances are quite different. The heuristic algorithm

based on branch-exchange and single-loop optimization always converges very quickly.

Because the OPF is first solved in the hybrid method, its solution and convergence speed

depends on the initial value chosen to solve OPF and also depends on the size of the

studied system. The number of loops determines the size of each gene in the GA in the

system, so the computational speed of GA could be slow for reconfiguring large systems,

with computation times most probably in tens of seconds. Further, because of the

mechanism of heuristics, both heuristic method and hybrid method are not guaranteed the

reach the global optimal, instead, the revised GA is able to reach the global optimal

solution after a sufficient number of evolutions.

Because the three methods perform differently, the method that is preferred depends on

Page 54: SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK ...read.pudn.com/downloads799/sourcecode/math/3153436/Thesis_fin… · SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK RECONFIGURATION

42

the characteristics of the system being studied. For small-scale systems, the revised GA is

chosen to get the optimal topology with fast computational speed. For large-scale

distribution systems, the heuristic method is chosen to reduce power loss with high

computational efficiency.

Table 3.8 Comparison of Three Methods

Solve

Problem?

Global

Optimal? Speed Implementation

Heuristic

Algorithm Yes No Fast Very Easy

Hybrid

Method Yes No

Depends on the initial

value and could be slow

for large system.

Medium

Revised GA Yes Close to Might be slow for large

system. Easy

Page 55: SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK ...read.pudn.com/downloads799/sourcecode/math/3153436/Thesis_fin… · SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK RECONFIGURATION

43

Chapter 4 Hierarchical Decentralized Network

Reconfiguration Study

Traditional distribution systems are designed for unidirectional power flow with very

limited dynamics. Distributed generation, energy storage and plug-in electric vehicles are

being integrated into the grid and all these will bring more dynamics, uncertainties and

stochastic behaviors into distribution systems. Reconfiguring such new, dynamic

distribution networks with high efficiency and reliability will be very challenging.

Three methods are proposed in Chapter III, and they can solve the reconfiguration

problem successfully. However, all these methods are implemented in a centralized

manner and the burden of excessive computational complexity is inevitable. Past research

on power systems has considered a variety of decentralized approaches [67], [68], [69],

[70]. Further, multi-agent systems have been used in power system studies in order to

deal with the problems of complexity and large-scale distribution systems [71], [72], [73].

A proximal message passing method was presented to solve security constrained

optimum power flow by Chakrabarti et al. [74], and it can minimize the cost of operation

of all devices, over a given time horizon, across all scenarios subject to all constraints.

Inspired by past work, a hierarchical decentralized methodology for network

reconfiguration is proposed in this chapter, which decomposes the network into sub-

networks within a multi-agent architecture where agents are responsible for the

reconfigurations of sub-networks based on the two-stage operating principle. It can help

reduce operational and computational difficulties because local control agents are

responsible for collecting local information and for controlling local switches.

Page 56: SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK ...read.pudn.com/downloads799/sourcecode/math/3153436/Thesis_fin… · SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK RECONFIGURATION

44

Simultaneous computations of various agents are used for reconfiguring the decomposed

systems, and thus the total computation time is greatly reduced compared with

centralized methods. Because real-time information exchange is necessary, this scheme

will require the deployment of appropriate sensor and communication networks.

In order to explain the proposed hierarchical decentralized approach, a standard 118-

bus distribution system [42] is used as the example, and its initial topology is shown as

Fig. 4.1.

1-substation2

3

4

567

8

9

1011

12131415

16

17

181920212223

24

25

26

27

2829

30313233

34

35

36

3738394041

4243

4445

464748

49

50

51

52

55

5657

5859

60

61

62

5354

636465

6667

68

69

70

71727374

75

76

77

7879

808182

83

8485

86

87

88

89

9091

9293

94

95

96

9798

99

100

101102103104

105

106107108

109

110

111112

114115

116

117

118

113

TS-1

TS

-2

TS-3

TS-4

TS

-5

TS

-6

TS

-7

TS-8

TS-9

TS-10

TS

-11

TS-12

TS-13

TS-14

TS

-15

Figure 4.1 118-bus radial distribution system.

4.1 Decentralized Structure

A loop is defined by the closing of an initially opened tie-switch and other initially

closed sectionalizing switches. The loops defined in the manner are easily recognized and

are unique regardless of switching operations.

Fifteen loops (loop1~loop15) exist in the 118-bus system and Table 4.1 shows the buses

included in each loop. These fifteen loops cannot be solved totally independently because

they share common branches and the status of the same switch states solved in different

loops can be different. A feasible approach is to decompose the entire system into several

Page 57: SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK ...read.pudn.com/downloads799/sourcecode/math/3153436/Thesis_fin… · SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK RECONFIGURATION

45

relatively independent clusters in which highly dependent loops are studied together.

Table 4.1 Fifteen Loops and Associated Buses in the 118-bus System

Loop No. Buses included in the loop

1 2,4,5,6,7,8,24,23,22,21,20,19,18,11,10

2 11,12,13,14,15,16,17,27,26,25,24,23,22,21,20,19,18

3 2,10,11,18,19,20,21,22,23,24,25,26,27,52,51,50,49,48,47,46, 45,44,29,28,4

4 2,10,11,18,19,20,21,22,23,24,25,35,34,33,32,31,30,29,28,4

5 4,5,6,7,8,9,46,45,44,29,28

6 29,30,31,32,33,34,35,36,37,38,39,40,41,42,43,49,48,47,46,45,44

7 29,30,53,54,62,61,60,59,58,57,56,55

8 29,30,31,32,33,34,35,36,37,38,62,61,60,59,58,57,56,55

9 1,2,4,28,29,55,56,57,58,96,91,90,89,65,64,63

10 65,66,67,68,69,70,71,72,73,74,75,76,77,99,98,97,96,91,90,89

11 65,66,67,68,69,70,71,72,91,90,89

12 64,65,66,67,68,69,70,71,72,73,74,75,88,87,86,79,78

13 1,63,64,78,79,86,105,104,103,102,101,100

14 1,63,64,78,79,80,81,82,83,108,107,106,105,104, 103,102,101,100

15 100,101,102,103,104,105,106,107,108,109,110,118,117,116,115,114

In order to facilitate differentiating the tightly connected and loosely connected areas,

the notion of “connectivity degree” of two areas is defined:

(4.1)

If D(A,B) = 0, areas A and B are relatively independent. For a given threshold δ, if

D(A,B) ≤ δ, A and B are loosely connected and if D(A,B) > δ, A and B are tightly

connected. If δ is small, very few loosely connected areas will be identified, and if δ is

large the number of loosely connected areas can be over-estimated. For the sake of

illustration, 0.2 is chosen as the threshold value.

A systematic procedure for decomposing the system using the “cut vertex set” concept,

similar to the cut set in graph theory, is described next. A cut vertex set of the connected

graph G=(V, E) is a vertex set U V such that

(a) G-U (remove all the vertices in U and delete all related edges connecting the

vertices in U) is not connected, and

D(A,B) =Total number of the common buses

min total number of buses in A,total number of buses in B( )

Í

Page 58: SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK ...read.pudn.com/downloads799/sourcecode/math/3153436/Thesis_fin… · SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK RECONFIGURATION

46

(b) G-K is connected whenever K U, and

(c) Each vertex u in U is connected with at least one vertex in each component of G-

U in graph G.

Specially, a cut vertex set is a cut vertex if only one vertex exists in the cut vertex set.

Then, the procedure consists of

(1) Obtain the modified adjacency matrix C. Let m be the amount of loops. The

modified adjacency matrix is a m-by-m matrix where the ij-th element is D(loopi, loopj).

(2) If there are separate areas that have no common buses except for the source node of

the system, these areas are named as fundamental decomposed zones. The tie-switches

between two fundamental decomposed zones are their connections. The steps that follow

are conducted for all fundamental decomposed zones, respectively.

(3) Draw the graph. In the graph G=(V,E), the vertices V ={v1,…,vn} represent loops

1~n, and the edges E connecting the vertices indicate the loops are coupled. Draw

vertices to represent all the loops in the studied zone. Add an edge connecting vi and vj if

C(i, j) is not zero. If loopi and loopj are loosely connected, write “L” on the edge.

Otherwise, write “T” on the edge.

(4) Check whether the graph G is connected. If not, find the isolated vertices, denoted

by S. The corresponding loops for the isolated vertices consist of the first members of

decomposed systems.

(5) Determine the cut vertex sets of G-S. Start the search from the first vertex (parent)

and look for the cut vertex set from all the vertices (child) that are incident to the parent

node. If the cut vertex set is empty, turn to the vertices incident to the child nodes to

search. If a cut vertex set is found, delete the cut vertex set and related edges defines two

Page 59: SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK ...read.pudn.com/downloads799/sourcecode/math/3153436/Thesis_fin… · SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK RECONFIGURATION

47

separate components. Continue to find the cut vertex sets for each component until no

more cut vertex sets exist. The separate components represent the decomposed systems,

and the tie-switches corresponding to the cut vertex sets represent the connections among

the decomposed systems.

(6) Obtain additional decomposed systems based on the components obtained in (5). If

two vertices are connected with an edge labeled by “L”, their corresponding loops are

decomposed into two subsystems. If two loosely connected vertices are tightly

connecting with another vertex, the corresponding tie-switch of this vertex is the

interconnection between two subsystems. If all vertices in a component are tightly

connected, no extra decomposition is needed.

(7) Arrange all decomposed systems layer by layer such that the upper layers include

the lower layers.

Consider the 118-bus system, three fundamental decomposed zones are divided: zone-

1 including tie-switches 1~8, zone-2 including tie-switches 10~12, and zone-3 including

tie-switch 15. The former two zones are connected by tie-switch 9, and the latter two are

connected by tie-switches 13 and 14. Each zone is further decomposed according to the

above steps (3)~(6). Zone-1, studied as the example, includes loops 1~8 and its graph G1

is connected, as shown in Fig. 4.2. The cut vertex set U1 is {3,4,5} and the two induced

components of G1-U1 are given in Fig. 4.3. Then, cluster-I comprising loop1~loop2 and

cluster-II comprising loop6~loop8 are thus decomposed. Tie-switches 3~5 are the

connections between two clusters and if they are initially open, these two clusters are

independent of each other. According to step (6), the first component in Fig. 4.3 cannot

be separated. In the second component, vertices 6 and 7 are loosely connected so cluster-

Page 60: SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK ...read.pudn.com/downloads799/sourcecode/math/3153436/Thesis_fin… · SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK RECONFIGURATION

48

II can be decomposed further into two subsystems - loop6 and loop7, which are related by

tie-switch 8.

Similarly, the graphs of zone-2 and zone-3 can be obtained and both are not separable,

so zone-2 and zone-3 cannot be decomposed further. Finally, after arranging the

decomposed systems layer by layer, the 118-bus system is decomposed into hierarchical

layers with multiple systems as shown in Table 4.2.

Figure 4.2 The graph for zone-1.

Figure 4.3 Components of G1-U1.

Table 4.2 Decentralized Structure for the 118-bus System

Layer-0 118-bus distribution system

Layer-1Zone-1 Zone-2 Zone-3

*1 tie-switches1~8

tie-switches10~12 tie-switch 15

*2 913,14

Layer-2 System-1 System-23,4,5

tie-switches1,2

tie-switches6~8

Layer-3 Sub-1 Sub-28

tie-switch 6 tie-switch 7

*1- The tie-switches included in its zone/system *2- The tie-switches shared by two zones/system

(Buses 1~62) (Buses 1,63~99) (Buses 1,100~118)

(Buses 1~28) (Buses 29~62)

(Buses 29~52)

(Buses 29,30,53~62)

When decomposing the system, interconnecting lines are disconnected and fictitious

loads and fictitious generators representing power flows through the interconnecting lines,

as depicted in Fig. 4.4, are used for the analysis. The fictitious load is the accumulation of

all the loads supplied by the interconnecting line. The bus connecting to the fictitious

1

2 3 4 5

6 7 8

T T TT

T T LT T

TT T TL

TTL

1

2

T 6 7 8T

T

L

Page 61: SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK ...read.pudn.com/downloads799/sourcecode/math/3153436/Thesis_fin… · SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK RECONFIGURATION

49

generator is a slack bus with voltage = 1.0 p.u.. This paper aims at finding the optimal

configuration with the minimal power losses, and although bus voltages can affect the

value of the power losses they cannot change the optimality of the configuration, so using

a slack bus is appropriate.

P, QP, Q

Fictitious Generator

Fictitious Load

Figure 4.4 Decomposition with fictitious loads and fictitious generators representing power flows

through the interconnecting lines.

4.2 Operational Rules

The principle for solving the optimization problem is from small to large: first solve

the optimization problem for the lowest layer and then proceed to higher layers. This is

because the switch states solved in the lower layer are used as fixed values in higher

layers. At each layer, two stages are defined and each stage is essentially a

reconfiguration problem, so any of three proposed method including heuristic method,

hybrid method and GA could be used to solve each optimization problem. Because the

heuristic method has best computational efficiency, it is used in the decentralized

approach so that more computation time could be saved.

Stage-1: Begin from the lowest layer. Keep the switch states of all the tie-switches

shared by two of the subsystems at their initial values (=0). Solve the following

optimization problems individually to acquire the states of switches (Si) that are exclusive

to each subsystem.

Page 62: SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK ...read.pudn.com/downloads799/sourcecode/math/3153436/Thesis_fin… · SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK RECONFIGURATION

50

1 1min

min

i switch set only in subsystem

T i switch set only in subsystem T

f g S

f g S

(4.2)

where, f1, f2, …, fT are respectively the problem formulations in (3.16) for subsystem 1,

2, …, T.

Stage-2: Let the solutions of (4.2) be S11..., Sk

1, solve for the states of the shared tie-

switches using (4.3). Record the results of all switch states, and use these as fixed

(constant) values for the upper layer.

min f =g(Sjshared tie-switch set, Si =1,2,...,k = Si1) (4.3)

where f is the formulation given in (3.16) and two subsystems with interconnections in

the same layer are treated together, and Sj is the state of tie-switch j shared by two

subsystems.

Considering the 118-bus distribution system, the entire operation consists of ten

procedures to finish all layers, as shown in Fig. 4.5. The exact load flow result is obtained

at procedure ○10 . Procedures ○1 ~ ○5 can be solved simultaneously by different

computational agents, and ○8 can be solved simultaneously with ○6 -○7 -○9 . Hence the

entire computing time is tdecentralized = max(T1,T2,T3,T4,T5) + max(T8, T6+T7+T9) + T10

provided that the communication among agents is negligible. If the system is

reconfigured in a centralized manner, the necessary computing time depends on the

iteration times which will certainly be larger than the sum of T1~T10. Thus, tdecentralized is

always smaller than the computational time of the centralized method. In summary, the

entire network reconfiguration is realized by combining parallel computations

Page 63: SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK ...read.pudn.com/downloads799/sourcecode/math/3153436/Thesis_fin… · SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK RECONFIGURATION

51

implemented simultaneously and hierarchical computations taken sequentially. Due to the

simultaneous operations of multiple agents, the overall operation time can be greatly

reduced.

Reconfigure Loop-6

Reconfigure Loop-7

Reconfigure Loop-8

Reconfigure Loops 1, 2

Reconfigure Loops 3, 4, 5

Reconfigure Loops 10,11,12

Reconfigure Loop -15

Reconfigure Loop 9Reconfigure Loop 13,14

Optimal Configuration for 118-bus distribution system

14 5 2 3

6

7

98

10

Figure 4.5 Operation procedures for the 118-bus distribution system.

4.3 Multi-Agent Technique

Network reconfiguration problem is solved in a decentralized manner with the

decomposed sub-problems given in (4.2) and (4.3). Separate agents, organized in a

hierarchical structure, are assigned to the sub-problems and parallel computations are

implemented. Fig. 4.6 shows the framework of two intelligent agents. Each agent is

composed of three units: data unit that collects its local information and communicates

with other agents, computation unit that implements the heuristic algorithm given in

Chapter III to solve the local reconfiguration problem, and the decision unit for

control/coordination. The computational results of the lower-layer agents are sent to the

data units of the agents in the upper-layer. The final optimal configuration is decided

based on collaboration/coordination among the multiple agents.

Page 64: SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK ...read.pudn.com/downloads799/sourcecode/math/3153436/Thesis_fin… · SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK RECONFIGURATION

52

Figure 4.6 The framework of two intelligent agents.

Communication and coordination among agents are of great importance. For the

decomposed systems at different layers in the same fundamental decomposed zone, the

communication between agents involves sending switch states from the lower-layer

system and no coordination is needed. However, agents within the same layer affect each

other in the form of fictitious loads. Denoting these two systems as I and II, there are two

different scenarios:

(1) I and II are relatively uncoupled. Thus the structure of II has no effect on the

fictitious load in I, and vice versa. The constant fictitious load is the sum of loads that are

supplied by the initial interconnecting line. Any two of zone-1, zone-2 and zone-3 in

Table II are examples of such systems, and system-1 and system-2 are as well. Thus, each

agent of these two systems obtains the value of the constant fictitious load from another

agent in the beginning, but no coordination is needed.

(2) I and II share branches/buses in common, i.e. the connectivity degree is nonzero. In

this scenario, various structures of II alter the values of fictitious loads in I and vice versa.

Page 65: SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK ...read.pudn.com/downloads799/sourcecode/math/3153436/Thesis_fin… · SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK RECONFIGURATION

53

Sub-1(loop6) and sub-2(loop7) in Table II are examples of such systems. Coordination

between agents is indispensable and the coordination strategy is presented in Fig. 4.7.

Figure 4.7 Coordination between two agents.

Ag

ent-

ID

ata

Un

it

Com

pu

tati

on

Un

it

Lo

cal

Info

rma

tio

nT

he

rela

tio

n b

etw

een

fic

titi

ou

s lo

ads

and

sw

itch

sta

tes

in a

gen

t I.

S(m

in)=

S(m

ax)?

YES

NO

flag

1=

1fl

ag1=

0

flag

1

Da

ta U

nit

Com

pu

tati

on

Un

it

Dec

isio

n U

nit

flag

2S

(I) k

Sto

p2

flag

1∙f

lag2=

1?

YE

S

NO

k=

k+

1

S(I

) 0|S

(II)

init

Do

ne.

S

(I) f

inal

= S

(I) 0

flag

1fl

ag2

S(I

) k

k =

0, S

(I) k

= 0

, S

(II)

K =

S(I

I)in

it,

S(I

) k+

1|S

(II)

K =

S(I

) 0

flag

2

S(I

) k+

1|S

(II)

k =

S(I

) k ?

NO

Do

ne.

S

(I) f

inal

= S

(I) k

+1

YES

S(m

in)=

S(m

ax)?

YES

NO

flag

2=

1fl

ag2

=0

flag

1∙f

lag2 =

1?

YE

SN

O

Do

ne.

S

(II)

final

= S

(II)

0

flag

1

S(I

I)0|S

(I) i

nit

S(I

I)k

Do

ne.

S

(II)

final=

S(I

I)k

Sto

p2=

1

Sto

p2=

1?

YE

S

Lo

cal

Info

rma

tio

n

Agent-II

S(I

) k+

1|S

(II)

k=

S(I

) 1~

k-1

?NO

YE

S Do

ne.

S

(I) f

inal

= S

(I) k

Sto

p2=

2

Do

ne.

S

(II)

final

= S

(II)

k-1

YE

SSto

p2=

2?

Th

e re

lati

on

bet

wee

n f

icti

tio

us

load

s an

d s

wit

ch s

tate

s in

ag

ent

II.

S(I

I)k

Dec

isio

n U

nit

S(I

I)k|S

(I) k

S(I

) k

S(I

) k+

1|S

(II)

k

Page 66: SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK ...read.pudn.com/downloads799/sourcecode/math/3153436/Thesis_fin… · SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK RECONFIGURATION

54

(2.a) In the beginning, the maximal, minimal and initial values of the fictitious loads in

I and II are computed based on the relationship between fictitious loads and switch states.

Then, the optimal switch states of each system are solved independently, given that the

fictitious load is maximal, minimal and at the initial value respectively, and the results are

denoted as S(max), S(min) and S0. If S(max) = S(min), it means that the optimal result is

independent of values of the fictitious load. This condition is checked in the decision unit

in each agent, and if true, no further coordination is needed and the optimal solution of

each agent is the value of S(max), S(min) or S0 (S(max)=S(min)=S0). The grey lines with

arrows represent the inputs and outputs used in the above procedure.

(2.b) If any of the two conditions is false, coordination is activated. During

coordination, the agent for the system with more loads is the master agent (agent-I) and

the other is the slave agent (agent-II). S(X)k denotes the solution of switch states for

agent-X at the kth

iteration. S(X)i |S(Y)j denotes the solution of switch states for agent-X

computed at the ith

iteration given that the switch states in agent-Y is S(Y)j.

The first iteration starts with the master agent. Let k=0, S(I)0=0, S(II)0=initial switch

states of II, and thus S(I)k+1| S(II)k is the value of S0 solved by agent-I in (2.a). Then, let

k=k+1 and send new S(I)k to the data unit that will communicate with the data unit in

agent-II. Thus iteration in the master agent is finished, and the inputs/outputs are denoted

by dash dot lines.

(2.c) With the new value of S(I)k, the fictitious load in agent-II is updated, and the

optimal switch states for area II are determined by the computation unit. The result is

denoted by S(II)k|S(I)k, which is sent to agent-I via the communication channel between

Page 67: SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK ...read.pudn.com/downloads799/sourcecode/math/3153436/Thesis_fin… · SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK RECONFIGURATION

55

two data units. Dashed lines with arrows represent the inputs and outputs in the slave

agent.

(2.d) The iteration repeats by computing S(I)k+1 based on the new fictitious load

calculated using S(II)k. The stopping criterion that S(I)k+1 is same as the results of S(I)

obtained in the former iterations is checked in the master agent, and if it is true, a

stopping signal “stop 2” is sent to agent-2 via the communications channel between data

units. There are two different scenarios: 1) if S(I)k+1=S(I)k, the final solutions for agent-I

and agent-II are respectively S(I)k+1 and S(II)k, and both agents achieve optimality. 2) if

S(I)k+1 is the same as former results, additional iteration will cause endless loops. Thus

we choose the final solutions as S(I)k and S(II)k-1 in order to make sure the master agent is

optimal. Note, coordination occurs between the agents of the two decomposed systems,

corresponding to stage-1, and a third agent is responsible for solving the stage-2 problem

after receiving the coordinated results from agents I and II.

4.4 Dynamic Network Reconfiguration

Renewable energy resources, energy storage and plug-in electric vehicles are being

integrated into the power grid, and they will play important roles at both transmission and

distribution levels. Many renewable energy resources, such as wind and solar, depend on

environmental conditions, and their power generations are intermittent. The increasing

penetration level of plug-in electric vehicles will add more uncertainties on the system

operation. All these changes lead to more stochastic behaviors and dynamics happened in

distribution systems, and it is necessary to alter system topology from time to time so that

the grid could respond to changes and the system operation could be improved. Thus, in

response to time-varying loads, fluctuating generation of renewable energy resources and

Page 68: SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK ...read.pudn.com/downloads799/sourcecode/math/3153436/Thesis_fin… · SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK RECONFIGURATION

56

unexpected situations (such as faults), the application of “dynamic” network

reconfiguration is proposed, and its framework is shown as Fig. 4.8.

Figure 4.8 Framework of dynamic network reconfiguration.

Let the starting time be T0 and the operating period be ΔT, and the decentralized

network reconfiguration algorithm is conducted based on the operating data at the

beginning of each operating window. At T0, the optimal switching plan is solved using

the proposed hierarchical decentralized approach, and the studied distribution network is

thus reconfigured and this new topology is kept same for the remaining time in the

current operation period. At T0+ ΔT, the new operation period starts, and the real-time

system data is collected again and also compared with former data to check whether

changes occur. If there are no changes, the reconfiguration is not needed so the system

topology is kept same until next time window arrives. Instead, if there are changes, the

lowest-layer agent corresponding to the subsystem where the change happens is activated,

and its computation unit resolves the local optimization problem. If the solution is same

as the former operation period, the happened changes do not alter the optimal system

topology, so there is no need to reconfigure the network. Otherwise, the new solution is

transmitted to the corresponding upper-layer agents where the reconfiguration problems

are resolved. Finally, the new switching plan is obtained, and the distribution network

T0+∆T

T0 Read the Real-time System

Data

Use the proposed

decentralized approach to

solve the reconfiguration

problem.

Plan-0

Check whether there are changes: if so, activate the lowest-layer agent

and resolve the optimization problem. If the result is different from the last time window, activate the upper-layer agent.

Read the Real-

time System Data

Page 69: SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK ...read.pudn.com/downloads799/sourcecode/math/3153436/Thesis_fin… · SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK RECONFIGURATION

57

will be reconfigured again and the new topology is kept consistent until the next period

arrives.

Further, in order to avoid neglecting important changes in the system, a time-ahead

planning approach is implemented in the agents of the lowest-layer systems. At the

midpoint of each operating period, the data units of the lowest-layer agents get data from

their local systems. If there have been no changes, all agents wait for the next operation

period to begin. Otherwise, any agent that detects important changes in its local load

power or DER generation levels activates its computation agent to resolve the

reconfiguration problem based on the new data, and if the result is different, it will send

the new result to its upper-layer agents to “inform” them to re-compute. After all agents

complete their work, the distribution network is reconfigured based on new switch states

and the current time becomes the new starting point for the following period T. Fig. 4.9

shows the implementation of the dynamic network reconfiguration with time-ahead

planning. At T1, the dynamic network reconfiguration for the system with new optimal

topology is rescheduled. There is a small time lag of t between T1 and the time when

changes are detected, which is the time required for executing the hierarchical

decentralized reconfiguration.

Figure 4.9 Dynamic network reconfiguration with time-ahead planning.

T1

T1+T

T1+2T…

Important

changes detected

and the problem

solution is

differnt

Initially Planned Operation

t

Enable upper-

layer agents to

re-compute the

optimal switch

states…...

0

T

2T

3T

nT

0.5T

1.5T

2.5T

New Planned

Operation

Page 70: SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK ...read.pudn.com/downloads799/sourcecode/math/3153436/Thesis_fin… · SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK RECONFIGURATION

58

If a fault occurs in the system, the agent of the subsystem where the fault is located

removes the affected buses/ branches/ loads from its system information before re-

evaluating the optimal system topology. After the fault is cleared, the agent will detect

the change at the beginning of the next planning period, and then resolve the problem by

revising the system information.

4.5 Case Study

The proposed hierarchical decentralized network reconfiguration approach is applied

to three test systems: 69-bus distribution system, 118-bus distribution system and 216-bus

distribution system. The simulations are conducted on a computer with the Intel 2.53

GHz processor and 3 GB RAM. Despite of the application of decentralized method,

simulation results obtained by using two centralized approaches are also given to

compare the performance of different methods. These two centralized approaches are the

heuristic algorithm based on branch-exchange and single-loop optimization proposed in

Chapter III and the harmony search algorithm (HSA). HSA is recently introduced to

solve distribution network reconfiguration problems and its performance is proved to be

better that GA and Tabu search in [51], so it is chosen to compare with the proposed

hierarchical decentralized approach.

At first, a simulation system, shown in Fig. 4.10, is implemented using

Matlab/Simulink in order to demonstrate the hierarchical, decentralized reconfiguration

approach. The demonstration system consists of the distribution system being studied and

includes distributed control agents. The distribution system is modeled using Simulink

elements, and each branch includes a R-L line and an initially closed switch. Distributed

agents control the switches in their own subsystems remotely, based on the switch state

Page 71: SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK ...read.pudn.com/downloads799/sourcecode/math/3153436/Thesis_fin… · SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK RECONFIGURATION

59

results obtained by computational units. Each block with the dashed-line rectangular

frame represents an agent modeled using “S-Functions” [75], which includes a data unit

(orange block), computational unit (blue block) and decision unit (grey block).

Figure 4.10 The demonstration system built using MATLAB.

Page 72: SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK ...read.pudn.com/downloads799/sourcecode/math/3153436/Thesis_fin… · SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK RECONFIGURATION

60

The operation of multiple agents is guided by the operational rules for the

decentralized approach. All the computational agents are initially disabled and enabled

when reconfiguration is required. The first input to the data unit of each agent is the

enable (1) or disable (0) signal. Each computational unit or decision unit has two outputs:

the first output is the switch to be opened obtained from the heuristic algorithm that is

written to a data file for access by upper-layer agents, and the second output is the signal

used to enable/disable upper-layer agents. The demo system is a general computational

utility that can be used to reconfigure the network structure of any distribution system by

changing the model and updating the system information.

The 118-bus system has control agents 1~10 that implement the procedures ○2 , ○3 , ○1 ,

○6 , ○7 , ○4 , ○5 , ○9 , ○8 , ○10 given in Fig. 4.5, respectively. Coordination is only required

for agents 1 and 2, so decision units are only modeled for these two agents. Agents 1, 2, 3,

6, 7 are associated with lowest-layer systems in the three fundamental decomposed zones,

and are enabled immediately by setting their first inputs to 1 when reconfiguration is

needed. The enable signals in agents 1 and 2 are both transmitted to agent 4 to initiate

procedure-○6 based on the switch states determined by the lower-layer agents. The outputs

from agents 3 and 4 are transmitted to agent 5 to activate the higher-level computation.

Outputs from agents 6, 7 and 5 are then transmitted to agents 8 and 9 to compute the final

switch states. Agent 10 then calculates the load flow results for the entire system, and the

two outputs are displayed. The first output is all the opened switches, which are sent to

the distribution system so that the network structure is changed appropriately, and the

second output is the minimal power loss.

Page 73: SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK ...read.pudn.com/downloads799/sourcecode/math/3153436/Thesis_fin… · SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK RECONFIGURATION

61

To simulate the dynamic network reconfiguration, periodic pulse signals are used as

the inputs to the data units of the lowest-layer agents and the second input to the data unit

of each upper-layer agent. For the upper-layer agents, the period of the pulse signals is

the operating period scheduled for the dynamic network reconfiguration. For the lowest-

layer agents, the period of the pulse signals is half the operating period because time-

ahead planning is done in the lowest-layer agents at the mid-point of each operating

window.

4.5.1 Case I : 118-Bus Test System

Fig. 4.1 has given the topology of 118-bus test system, and Total loads are 22709.7 kW

and 17041.1 kVar. For the initial network, the minimum voltage is 0.869 pu at bus 77,

which is well beyond the recommended range (5% deviation from the nominal value).

Total power losses are 1298.1 kW, 5.7% of the total load power.

The parameters used in HSA include harmony memory (HM), harmony memory size

(HMS), harmony memory considering rate (HMCR), pitch adjusting rate (PAR) and the

number of improvisations (NI). In the following case studies, these parameters are given

as: HMS = 10, NI = 250, HMCR=0.85 and PAR=0.3.

The results of the hierarchical decentralized approach, centralized approach and HSA

are shown in Table 4.3. The power loss reduction of the decentralized approach is 1.3%

less than the centralized approach and 2.7% more than HSA. The computing time of the

decentralized approach is 28.5% of the computing time needed for the centralized

approach and only 1.33% of the computing time needed for HSA.

Table 4.3 Simulation Results of 118-Bus System

Proposed Decentralized

Approach

Centralized

Approach HSA

Open Switches 21, 25, 48, 32, 45, 40, 60, 23, 26, 48, 34, 45, 40, 23, 25, 50, TS-4, 44,

Page 74: SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK ...read.pudn.com/downloads799/sourcecode/math/3153436/Thesis_fin… · SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK RECONFIGURATION

62

37, TS-9, 76, 71, 73, TS-

13, 82, 109

58, TS-8, 95, 97, 71,

74, TS-13, TS-14, 109

42, 61, 37, TS-9, 97,

70, 73, TS-13, 82, 109

Power Loss

Reduction 31.4 % 32.7 % 28.7 %

Minimum Voltage 0.932 pu 0.932 pu 0.93 pu

Voltages

≥0.95 pu 88 buses 104 buses 84 buses

CPU Time 3.2 s 7.82 s 180.2 s

When reconfiguring the network using the decentralized approach, the coordination

between agents 1 and 2 results in both agents obtaining the true optimal results. The

demonstration system is used to simulate the decentralized reconfiguration process, and

the results for different switch states are observable from green blocks in Fig. 4.10. The

solver is “discrete” with “fixed step size” 0.0005 s and the simulation time is set to be

0.001 s. The total computation time required is 5.3 seconds. If only one agent is used to

reconfigure the distribution system, i.e. using the centralized approach, the total

computation time is 29.5 s, or about 5.6 times that of the decentralized approach.

The results of nodal voltages for the initial network, the centralized method, HSA and

the hierarchical decentralized method are compared in Fig. 4.11. Most voltages are

increased after reconfiguration, especially for buses 29~43, 65~77 and 101~113. Fig.

4.12 compares the power losses distributed at 132 branches before and after

reconfiguration. It is observed that the power losses at branches 29~38, 64~69 and

100~109 are reduced greatly after reconfiguration. Power losses at branches 113~132 are

increased instead, which is due to the closure of TS-15 and the loads at buses 110~113

being transferred to the feeder 114-115-116-117-118. However, even though the power

losses for some branches are increased, the total power losses are significantly reduced

after reconfiguration.

Page 75: SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK ...read.pudn.com/downloads799/sourcecode/math/3153436/Thesis_fin… · SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK RECONFIGURATION

63

Figure 4.11 Node voltages of the 118-bus system before and after reconfiguration.

Figure 4.12 Power losses in the 118-bus system before and after reconfiguration.

0.85

0.9

0.95

1

1 7

13

19

25

31

37

43

49

55

61

67

73

79

85

91

97

10

3

10

9

11

5

p.u

.

Bus Number

Initial System

Centralized Approach

HSA Approach

Page 76: SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK ...read.pudn.com/downloads799/sourcecode/math/3153436/Thesis_fin… · SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK RECONFIGURATION

64

4.5.2 Case II : 69-Bus Test System

Figure 4.13 Single-line diagram of the 69-bus test system.

Fig. 4.13 shows the single-line diagram of a 69-bus test system, and system data can

refer to [76]. There are five tie-switches in total, and total load powers are 3801.89 kW

and 2694.1 kVar. For the initial topology, system power losses are 225.0 kW and the

minimum voltage is 0.91 pu.

Fig. 4.14 gives the structure of the decomposed subsystems and the hierarchical

arrangement of the computational agents. The results of decentralized approach,

centralized approach and HSA are given in Table 4.4. The centralized and HSA

approaches both reduce the power losses to 98.59 kW, but HSA needs 5.8 s more time

Page 77: SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK ...read.pudn.com/downloads799/sourcecode/math/3153436/Thesis_fin… · SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK RECONFIGURATION

65

than the centralized approach. For the decentralized approach proposed, final power

losses are 108 kW and the computation time is the least.

Buses 1~46, 51, 52, 66~69

System-1

(Tie-switches 1~3)

Layer-1

Layer-0

Buses 4~9, 47~50, 53~65

System-2

(Tie-switch 4)

TS-5

Buses 1~11, 28~46, 51, 52,

66, 67

System-1.1

(Tie-switch 1)

Buses 12~27, 68, 69

System-1.2

(Tie-switch 2)

69- Bus Distribution System

TS-3

Layer-2

Agent-1

Reconfigure 1.1

Agent-2

Reconfigure 1.2

Agent-3

Reconfigure 2

Agent-4

Whether close TS-3?

Agent-5

Whether close TS-5?

Negotiate to Coordinate the Results

1 2 3

4

5

Decomposed Subsystems Hierarchical Computation Agents

Figure 4.14 Decomposed systems and hierarchical agents for the 69-bus system.

Table 4.4 Simulation Results of 69-Bus System

Decentralized

Approach

Centralized

Approach HSA

Opened Switches 10, 17, 12, 58, 63 69, 70, 14, 58, 61 69, 70, 14, 58, 61

Power Loss

Reduction 52 % 56.2 % 56.2 %

Minimum Voltage 0.948 pu 0.95 pu 0.95 pu

Voltages ≥ 0.95 pu 67 buses 69 buses 69 buses

CPU Time 0.39 s 0.5 s 6.3 s

Page 78: SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK ...read.pudn.com/downloads799/sourcecode/math/3153436/Thesis_fin… · SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK RECONFIGURATION

66

4.5.3 Case III : 216-Bus Test System

Figure 4.15 Single-line diagram of the 216-bus test system.

Fig. 4.15 shows the single-line diagram of a 216-bus system with 25 tie-switches. This

system is constructed by enlarging the system given in [77]. Nominal voltage is 20 kV

and total load is 33.153 MW and 24.369 MVar. For the initial network structure, total

power losses are 2386.817 kW and the minimum node voltage is 0.8463 p.u. at bus 143.

Based on the “cut-vertex set” concept, the 216-bus test system is decomposed into

multiple subsystems, illustrated as Fig. 4.16. Table 4.5 gives the results obtained using

the three methods. It shows that the power loss reduction of the decentralized approach is

4.2% less than the centralized approach and 8.8% more than HSA. The computation time

of the decentralized approach is only 6.14% of the computational time of the centralized

1

1

2

3 4 5 6 7 8

19

9 12 1310 11 14 15 16 17

21

2223 24 25

28 29

26

2730 31

18

20

2

3

38 39 40 41

42 43 46

47

44 45 4837 49 50 51 52

55 5654 5763 6462 65

5859

60 61

5 6

7

6768

66

69

8570

77 79 80 81 827883

84 86 87

88

89

90

7172

8

73 74 75 76

9

10

91

92 93

97

94 95

96

9899

104 105

108 109102

103 106 107

100 101

110

111

128 129

132127

133

130

131

134

33

34 35 36

114 115

119112

113 117 118

116120 121 122 123

124125 126

136

137 140 143135 138 139146 147

142

144

145

148

141

4

22

24

11

12

13

15 16

23

14

32

53

150

151 152 153

154 155

156 159 160157 158 161 162163 164165

178

177

176

175

179 180

183

149166 167 168169 170 171172 173 174

181 182

184 185186

187

188

189190 191 192 193 195 196 197194

198 199200 201

202 203 204 205 206 207 208 209 210 211 212 213 214

215 216

17

18

19

20

21

25

Page 79: SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK ...read.pudn.com/downloads799/sourcecode/math/3153436/Thesis_fin… · SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK RECONFIGURATION

67

approach and 0.45% that of HSA. Besides, the voltage results for the initial network, the

centralized method, HSA and the hierarchical decentralized method are given in Fig. 4.17.

It shows that system voltage magnitudes have increased a lot after the reconfiguration for

all three methods.

216-bus distribution system

(Buses 1~65)

Zone-1

TS 1~7

(Buses 1, 66~148)

Zone-2

TS 8~16

(Buses 1, 149~216)

Zone-3

TS 17~21

(Buses 1~36)

System-1

TS 1~3

(Buses 37~65)

System-2

TS 5~7

(Buses 1~10,

19,33~36)

System-1.1

TS-1

(Buses 11~18,

20~32)

System-1.2

TS-3

(Buses 37~44,

54~57)

System-2.1

TS-5

(Buses 45~53,

58~65)

System-2.2

TS 6~7

(Buses 1,66~97)

System-3

TS 8~10

(Buses 98~148)

System-4

TS 11~16

(Buses 98~126)

System-4.1

TS 11~14

(Buses 127~148)

System-4.2

TS 15~16

(Buses 127~135,

145~148)

System-4.2.1

TS-15

(Buses 136~144)

System-4.2.2

TS-16

(Buses 98~104,110~112)

System-4.1.1

TS-11

(Buses 105~109,

113~126)

System-4.1.2

TS 12~14

(Buses 105~109, 113~118)

System-4.1.2.1

TS-13

(Buses 119~126)

System-4.1.2.2

TS 14

TS-4

TS-2

TS-12

TS 22~23 TS 24~25Layer-1

Layer-0

Layer-2

Layer-3

Layer-4

Layer-5

Figure 4.16 Decomposed systems for the 216-bus system.

Table 4.5 Simulation Results of 216-Bus System

Decentralized Approach Centralized Approach HSA

Open Switches

43, 49, 51, 9, TS-3, 22,

TS-4, 87, 83, TS-14, 116,

122, 111, 134, 141, TS-9,

207, 210, 161, TS-21,

TS-19, 118, 81, 144, 130

9, 22, 23, TS-4, 43, 51, 49,

83, TS-9, 87, 111, 121,

117, TS-14, 134, 141, 207,

171, 167, 160, TS-21, TS-

22, TS-23, 144, 129

8, 26, 25, 52, 42, 50, TS-7,

TS-8, TS-9, 86, 109, TS-12,

116, 122, 134, 140, 207, TS-

18, 165, 159, TS-21, 118,

81,147, 128

Power Loss

Reduction 35.4% 39.6% 26.6%

Minimum

Voltage 0.92 pu 0.929 pu 0.90 pu

Voltages

≥0.95 pu 165 buses 173 buses 148 buses

CPU Time 2.165 s 33.7 s 477 s

Page 80: SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK ...read.pudn.com/downloads799/sourcecode/math/3153436/Thesis_fin… · SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK RECONFIGURATION

68

Figure 4.17 Voltage results of the 216-bus system before and after the reconfiguration.

4.5.4 Result Discussion and Remark

(1) System Improvement and Optimal Result

According to the simulation results of 69-bus system, 118-bus system and 216-bus

system, both the proposed decentralized approach and two other approaches can reduce

power losses. The power loss reductions and voltage improvements made by the

hierarchical decentralized approach are always very close to those made by the

centralized approach with less than 5% difference. The performance of HSA is quite

different for the different test systems, and the solution of HSA can deviate considerably

from the solutions of the decentralized and centralized approaches depending on the

choices of initial HM parameters and the number of allowed improvisations. It is

remarkable that preference to the hierarchical decentralized approach increases with the

size of the system, indicating that our proposed approach have significant potential for

applications.

The heuristic approach cannot guarantee global optimality of a solution even in a

centralized implementation, and can only ensure that a solution is optimal during the

operation of a given loop. For the decentralized method, each decomposed system is

reconfigured using the heuristic approach based on a two-stage methodology, and the

Page 81: SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK ...read.pudn.com/downloads799/sourcecode/math/3153436/Thesis_fin… · SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK RECONFIGURATION

69

solution obtained for each system is locally optimal, not necessarily globally optimal.

Also, the agents for the decomposed systems only have local information, so it is not

possible to achieve the same solution as the centralized method without information

about the rest of the system. However, each decomposed system reduces the local power

losses, and these solutions are optimal for each decomposed sub-network.

Further, the hierarchical decentralized approach has the best numerical stability

compared with two other methods. Because the buses involved in the computation for

each subsystem are quite few, the occurrence of infeasible solutions is reduced and also

the convergence speed is greatly increased.

(2) Computation Time

The hierarchical decentralized approach can have significant computational time

advantages, particularly as the size of the system increases. The proposed decentralized

approach uses system decomposition to reduce the total number of iterations and the

order of the matrices formed at each iteration, which results in reductions in the

computational time. In the 118-bus system, the orders of the matrices for the centralized

and HSA approaches are 132, and the load flow is solved 143 times in the centralized

approach. However, for the decentralized approach, the order of the matrix for each sub-

problem is only around 10~20, and the most the load flow needs to be computed is only

15 iterations. For the 216-bus system, the reduction is even greater.

Although multiple iterations might occur because of the coordination between agents,

the computation time of each agent is quite short. The largest computing time of all

agents in the 118-bus system is 2.76s, with the smallest only 0.343s. The longest and

shortest computing time for the 216-bus system is respectively 4.715s and 0.095s. Further,

Page 82: SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK ...read.pudn.com/downloads799/sourcecode/math/3153436/Thesis_fin… · SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK RECONFIGURATION

70

because multiple agents are processing in parallel, the final computational time of the

decentralized approach is not the sum of the computational times of all agents, but

instead depends on the maximal computing time of all the agents in the same layer. As a

result, the computational time for the decentralized approach is much shorter than the

other approaches.

Besides, although multiple agents are cooperating to solve the problem, the data that

need to be exchanged among agents are restricted to the switch states. Thus with limited

data being exchanged, the time needed for transferring data is small compared to the

computational time.

(3) Simulation Environment

All algorithms and the demo system are developed using Matlab and Simulink. The

implementation of the proposed decentralized network reconfiguration on real

distribution systems will need much more effort other than developing new approaches.

At present, a demo system built using Matlab is mainly used to illustrate how the

decentralized approach is developed and conducted. The hierarchical decentralized

reconfiguration approach will be definitely demonstrated using an agent-based software

platform. Besides, in the future, this approach will be test using hardware in the loop

simulation (HILS) and then finally implemented in hardware using a laboratory

demonstration system [78] available at Case Western Reserve University.

(4) Remark

Based on the simulation results provided, it can be concluded that the computational

time of HSA and centralized approach for reconfiguring larger systems will increase

significantly, and hence these centralized algorithms might become infeasible for real

applications if the system scale is large enough. Instead, the proposed decentralized

Page 83: SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK ...read.pudn.com/downloads799/sourcecode/math/3153436/Thesis_fin… · SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK RECONFIGURATION

71

approach has no such drawback. Although currently there is no explicit time limitation

for network reconfiguration, as we move to modernization of the distributions system

with more complex network topologies that include DER, demand response, etc. with a

focus on increasing the reliability, resiliency, and efficiency of the system,

reconfiguration approaches with fast computing capability will be necessary to achieve

the desired levels of real-time operation and automation.

4.5.5 Dynamic Network Reconfiguration

Taking the 118-bus distribution system as the example, dynamic network

reconfiguration is implemented using the demonstration system to study the impacts of

time-varying loads, fluctuating generation from distributed energy resources and

permanent faults on the optimal topology. As shown in Fig. 4.18, ten groups of load

profiles are extracted from load measurements of different areas on the same day. Each

load shape covers 24 hours and the time interval between two points is 15-min. The per

unit values are obtained by dividing the instantaneous power by the maximal value in

each load group. In order to simulate time-varying loads, each load in the 118-bus system

is selected from ten shapes randomly, with actual instantaneous power computed as the

product of the initial value and the per unit value at the current time.

Figure 4.18 Ten load shapes.

0.25

0.35

0.45

0.55

0.65

0.75

0.85

0.95

1.05

0:0

0

1 h

2 h

3 h

4 h

5 h

6 h

7 h

8 h

9 h

10 h

11 h

12 h

13 h

14 h

15 h

16 h

17 h

18 h

19 h

20 h

21 h

22 h

23 h

p.u

.

Time

Page 84: SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK ...read.pudn.com/downloads799/sourcecode/math/3153436/Thesis_fin… · SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK RECONFIGURATION

72

The effects of distributed energy resources are studied by integrating six photovoltaic

(PV) generation units into the grid. Each PV unit is of same type and its simulation model

will be explained in the next chapter. The maximal PV output power is 970.0 kW at the

reference condition when the temperature is 298 K and solar irradiance is 1000 W/m2. Fig.

4.19 shows the profiles of hourly solar radiation and temperature for a 24 hour period

based on ten years of measured data [79]. The corresponding PV output power for each

hour is obtained as shown in Table 4.6. For the network reconfiguration study, distributed

energy resources can be considered as time-varying negative loads. The placement and

sizing of a DG unit affect the value of power losses, and Chapter VI will give detailed

analysis about optimal placement and sizing plan. Here, we arbitrarily suppose six PV

units are locating at buses 27, 43, 62, 76, 77, 113 respectively.

Figure 4.19 Hourly solar radiation and temperature profiles.

Table 4.6 Capacity of Each PV Unit During 24 Hour Period

Time (h) 0~1 1~2 2~3 3~4 4~5 5~6

Capacity (kW) 0 0 0 0 0 0

Time (h) 6~7 7~8 8~9 9~10 10~11 11~12

Capacity (kW) 22.87 129.3 430.92 553.11 757.58 842.8

Time (h) 12~13 13~14 14~15 15~16 16~17 17~18

Capacity (kW) 793.3 640.0 437.0 286.6 174.7 66.4

Page 85: SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK ...read.pudn.com/downloads799/sourcecode/math/3153436/Thesis_fin… · SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK RECONFIGURATION

73

Time (h) 18~19 19~20 20~21 21~22 22~23 23~24

Capacity (kW) 0 0 0 0 0 0

Because only hourly PV power data is available, the operating period for the dynamic

network reconfiguration is set to be 1 h and the starting point is at 0 h. The entire study

time is 24 hours. Table 4.7 shows the simulation results of the final time windows

adjusted after the time-ahead planning, the opened switches scheduled for each operating

window and the minimal power losses calculated at the beginning of each operating

window. The fifth column shows the power losses of the system without any

reconfiguration operation. In order to verify the positive effects of the selected PV buses

on reducing power losses, the power losses of the system without any reconfigurations

are also computed for the case when PV units are connected to six randomly selected

buses (25, 48, 61, 84, 95, 110), and the results are given in the sixth column. The

comparison between the fifth and the six columns has proved that the power losses are

reduced when the PV units are connected to the buses with the largest positive

sensitivities.

It has been shown previously that the computational time of the hierarchical

decentralized network reconfiguration is relatively short, so the time lag between two

operating windows isn't shown. It is seen that the operating window is first adjusted at

t=0.5 h when the switch states solved by one lower-layer agent (agent-1) changes. The

network is then reconfigured and 0.5 h becomes the starting time for the next operating

window. Similarly, the operating windows are also adjusted at 1 h, 16.5 h and 17 h.

During the entire 24-hour period, the system topology is changed at 0, 0.5 h, 1 h, 8 h, 9 h,

10 h, 12 h, 15 h, 16 h, 16.5 h, 17 h and 18 h.

Page 86: SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK ...read.pudn.com/downloads799/sourcecode/math/3153436/Thesis_fin… · SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK RECONFIGURATION

74

Suppose the power losses for each hour are constant, the total energy losses for 24-

hour period are 16671 kWh if no reconfiguration is implemented. If the dynamic network

reconfiguration is implemented without time-ahead planning, the total energy losses are

computed to be 11913 kWh for a 32.2% reduction, and total energy losses for dynamic

reconfiguration with the time-ahead planning are only 10954.4 kWh for a 37.7%

reduction.

The simulation is implemented in Simulink, and 0.02 s is used to mimic an operating

period, and the entire simulation time is 0.46 s for an entire day. It took 41 seconds to

complete the simulation using decentralized reconfiguration, and more than 100 s using

centralized reconfiguration.

Table 4.7 Simulation Results of The Dynamic Reconfiguration

Time

Window Opened Switches

Power

Losses (kW)

Initial Power

Losses (kW) (kW)

0 Initial TS-1~TS-15 644.45 644.45 644.45

1 0~0.5 h

21, TS-2, 48, TS-4, 45, 39,

TS-7, TS-8, TS-9, 75, 71,

73, TS-13, TS-14, 109

435.94

644.45 644.45

2 0.5~1 h

21, TS-2, 49, 34, 45, 40,

TS-7, TS-8, TS-9, 75, 71,

73, TS-13, TS-14, 109

414.3

3 1~ 2 h

21, TS-2, 49, 34, 45, 40,

TS-7, TS-8, TS-9, 76, 71,

73, TS-13, 82, 109

399.37 588.68 588.68

4 2~3 h

21, TS-2, 49, 34, 45, 40,

TS-7, TS-8, TS-9, 76, 71,

73, TS-13, 82, 109

371.25 551.35 551.35

5 3~4 h

21, TS-2, 49, 34, 45, 40,

TS-7, TS-8, TS-9, 76, 71,

73, TS-13, 82, 109

352.15 524.1 524.1

6 4~5 h

21, TS-2, 49, 34, 45, 40,

TS-7, TS-8, TS-9, 76, 71,

73, TS-13, 82, 109

359.28 529.77 529.77

7 5~6 h

21, TS-2, 49, 34, 45, 40,

TS-7, TS-8, TS-9, 76, 71,

73, TS-13, 82, 109

368.5 541.0 541.0

8 6~7 h 21, TS-2, 49, 34, 45, 40,

TS-7, TS-8, TS-9, 76, 71, 410.5 599.59 599.59

Page 87: SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK ...read.pudn.com/downloads799/sourcecode/math/3153436/Thesis_fin… · SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK RECONFIGURATION

75

73, TS-13, 82, 109

9 7~8 h

21, TS-2, 49, 34, 45, 40,

TS-7, TS-8, TS-9, 76, 71,

73, TS-13, 82, 109

478.9 681.9 688.9

10 8~9 h

21, TS-2, 49, 34, 45, 40,

TS-7, TS-8, 95, TS-10, 70,

72, TS-13, 82, 109

433.13 598.8 631.88

11 9~10 h

21, 15, 49, 34, 45, 40, TS-

7, TS-8, 95, TS-10, 70, 72,

TS-13, 82, 109

392.33 509.1 592.7

12 10~11 h

21, 15, 49, 34, 45, 40, TS-

7, TS-8, 95, TS-10, 70, 73,

TS-13, 82, 109

395.9 513.2 614.77

13 11~12 h

21, 15, 49, 34, 45, 40, TS-

7, TS-8, 95, TS-10, 70, 73,

TS-13, 82, 109

393.0 509.1 625.2

14 12~13 h

20, 15, 49, 34, 45, 40,

TS-7, TS-8, 95, TS-10, 70,

73, TS-13, 82, 109

399.9 518.0 640.5

15 13~14 h

20, 15, 49, 34, 45, 40, TS-

7, TS-8, 95, TS-10, 70, 73,

TS-13, 82, 109

400.43 517.8 634.1

16 14~15 h

20, 15, 49, 34, 45, 40, TS-

7, TS-8, 95, TS-10, 70, 73,

TS-13, 82, 109

426.8 549.2 654.48

17 15~16 h

21, 15, 49, 34, 45, 40, TS-

7, TS-8, 95, TS-10, 70, 72,

TS-13, 82, 109

462.11 599.0 682.1

18 16~16.5 h

21, TS-2, 49, 34, 45, 40,

TS-7, TS-8, 95, TS-10, 70,

72, TS-13, 82, 109

522.7

688.0 751.5

19 16.5~17 h

21, TS-2, 49, 34, 45, 41,

TS-7, TS-8, 95, TS-10, 70,

73, TS-13, 82, 109

547.7

20 17~18 h

21, 26, 49, 34, 45, 41, TS-

7, TS-8, TS-9, TS-10, 71,

73, TS-13, 82, 109

621.2 831.6 878.05

21 18~19 h

21, 26, 49, 33, 45, 41, 59,

37, TS-9, TS-10, 71, 73,

TS-13, 82, 109

772.8 1089.7 1113.5

22 19~20 h

21, 26, 49, 33, 45, 41, 59,

37, TS-9, TS-10, 71, 73,

TS-13, 82, 109

834.22 1201.2 1201.2

23 20~21 h

21, 26, 49, 33, 45, 41, 59,

37, TS-9, TS-10, 71, 73,

TS-13, 82, 109

784.1 1129.2 1129.2

24 21~22 h 21, 26, 49, 33, 45, 41, 59,

37, TS-9, TS-10, 71, 73, 729.1 1053.8 1053.8

Page 88: SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK ...read.pudn.com/downloads799/sourcecode/math/3153436/Thesis_fin… · SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK RECONFIGURATION

76

TS-13, 82, 109

25 22~23 h

21, 26, 49, 33, 45, 41, 59,

37, TS-9, TS-10, 71, 73,

TS-13, 82, 109

638.6 928.78 928.78

26 23~24 h

21, 26, 49, 33, 45, 41, 59,

37, TS-9, TS-10, 71, 73,

TS-13, 82, 109

530.6 773.4 773.4

If a fault occurs in the system and is not cleared before the operating window arrives,

the agent of the subsystem where the fault is located will detect the fault and the optimal

system topology is re-computed. The procedure is as follows:

1) The computational unit starts to resolve the reconfiguration problem by first

revising the system data to delete the infeasible buses/branches/loads affected by the fault.

2) Check whether DG units exist in the isolated areas. If not, go to step-3. Otherwise,

the DG unit will work as a back-up energy resource for restoring the loads isolated during

the outage. The principle for the load restoration is to maximize the restored loads as well

as keep the power losses in the induced microgrid to be minimal using a the formulation

as an optimization problem:

22

1 , 21 1

22

, ,max1 1

min

. .

M N

MG L i i ii i

M N

L i i i DGi i

f w P w I r

s t P I r P

(4.4)

where N2 is the amount of connected branches in the microgrid after restoration, M is

the amount of restored loads in the microgrid, PL,i is the active power of the restored load

i, w1 and w2 are weighting coefficients, and PDG,max is the maximum output power of the

DG. Both PL,i and PDG,max are for the current time window. All voltages and currents after

the restoration should be within acceptable operating limits.

Page 89: SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK ...read.pudn.com/downloads799/sourcecode/math/3153436/Thesis_fin… · SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK RECONFIGURATION

77

3) This agent then reports to its upper-layer agents about the new switch states together

with the infeasible branches so that re-computations in the upper-layer agents are

activated to obtain the new switches that are to be opened.

4) Wait for next operating time or planning time, if the lowest-layer agent detects the

fault has been cleared, it will add the deleted system information before resolving the

optimization problem. All other agents are working normally to resolve their optimization

problems.

Fig. 4.20 shows the case where two faults occurred in the 118-bus system at times 6:15

and 14:30 respectively, and each fault is cleared after 1 hour. All other system

information is the same as the former case, so the results of switch states for the periods

0~6.5 h and 16~24 h are the same as given in Table 4.7, and the results for other periods

are given in Table 4.8. The optimal opened switches for the distribution system are

solved for the two faults respectively. During the second fault, two time windows are

split because the results of the optimal opened switches calculated at the planning time

are different.

1-substation2

34

567

8

9

10

11

121314

15

16

17

181920212223

24

25

2627

2829

3031323334

35

36

37383940414243

444546474849

50

51

52

55

56575859

60

61

62

53

54

1

2

3

4

5

6

7

8

9

Zone-2Zone-3

6364

Fault-2

Fault-1

Figure 4.20 Two faults happened in the 118-bus system.

Page 90: SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK ...read.pudn.com/downloads799/sourcecode/math/3153436/Thesis_fin… · SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK RECONFIGURATION

78

Before fault-1 occurs, the configuration is that tie-switch 6 is closed and branch 40-41

is open, so buses 37~40 are isolated and no DG exists in the outage area when fault-1

occurs. On the contrary, buses 56~62 form a microgrid that includes a PV unit connected

at bus-62 when fault-2 occurs. Thus the optimization problem (4.4) is solved for two

windows with different load power and PV output power data, and the loads at buses

59~62 are restored.

Table 4.8 Simulation Results When Fault Occurs

Time

Window Opened Switches

Power

Losses (kW)

6.5 ~ 7.5 h 21, TS-2, 48, 34, 45, 59, 95, 76, 71, 73, TS-13, 82, 109 413.6

7.5 ~ 8 h 21, TS-2, 49, 34, 45, 40, TS-7, TS-8, TS-9, 76, 71, 73,

TS-13, 82, 109 441.7

8 ~ 14.5 h Same as table VI

14.5~15 h 20, 15, 49, 34, 45, 39, TS-10, 70, 73, TS-13, 82, 109 464.5

Restore loads connecting at buses 59~62.

15~15.5 h 21,15, 48, 34, 45, 39, TS-10, 70, 72, TS-13, 82, 109 492.3

Restore loads connecting at buses 59~62.

15.5~16 21, 15, 49, 34, 45, 40, TS-7, TS-8, 95,

TS-10, 70, 72, TS-13, 82, 109 466.6

Page 91: SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK ...read.pudn.com/downloads799/sourcecode/math/3153436/Thesis_fin… · SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK RECONFIGURATION

79

Chapter 5 Modeling and Primary Control for Distributed

Generation Systems

Wind power and solar power are two most important types of renewable energy. By

the end of year 2013, wind power capacity has been over 60,000 MW and the installation

PV capacity has been over 10 GW. Fuel cells also show great potential to be green power

sources of the future because of many merits they have, such as high efficiency, zero or

low pollution, and flexible modular structure. Micro-gas-turbine (MT) has been widely

used in distributed generation and combined heat and power applications. Besides,

energy storage device is extremely useful to cooperate with intermittent renewable

energy. Super-capacitor, also known as ultra-capacitor, is widely used in many

applications because of its high power density and ability to store and release power

within short time periods. In order to study the performance of distributed energy

resources and optimize their interactions with power grids, it is primarily necessary to

develop appropriate mathematical models, controllers and conduct multiple scenario

simulation tests.

Considerable effort has gone into modeling energy generation sources and storage

systems, but very often these models are simplified to reduce computational complexity

for long-term simulation. However, for short-term dynamic simulation, detailed dynamic

modeling of the energy resources, storage systems, power electronic devices, and

controllers are required.

5.1 Wind Power Generation Unit

Generally there are two types of wind energy conversion system including constant

Page 92: SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK ...read.pudn.com/downloads799/sourcecode/math/3153436/Thesis_fin… · SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK RECONFIGURATION

80

speed system and variable speed system. Fig. 5.1(a) shows the configuration of a constant

speed wind energy conversion system, in which the generator is a squirrel cage induction

generator that is connected to the utility grid or load directly. Since the generator is

directly coupled with the grid or load, the wind turbine rotates at a constant speed

governed by the utility frequency and the number of poles of the generator. Fig. 5.1(b)

and Fig. 5.1(c) show two different types of variable wind energy conversion system. In

the former type, the permanent magnet synchronous machine is usually used as the

generator, and it is directly connected with the power converter that is then connecting

with load or grid. The latter one is a double-fed induction generator, and the rotor of the

generator is fed by a back-to-back voltage source converter. The stator of the generator is

directly connected load or grid. While the generator in the latter system is usually a

permanent magnet synchronous machine, and it is directly connected with the power

converter that is then connecting with load or grid. The variable-speed and pitch-

controlled double-fed wind energy system widely exist because it can convert wind

energy with high efficiency, control both active and reactive power, reduce power

fluctuations and generate high quality power [80], [81], [82].

Gear

Box GGrid/

Load

(a)

Gear

Box GGrid/

Load

(b)Converter

Page 93: SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK ...read.pudn.com/downloads799/sourcecode/math/3153436/Thesis_fin… · SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK RECONFIGURATION

81

Gear

Box DFIG Grid

(c) Figure 5.1 Three types of wind energy conversion system.

Figure 5.2 Two-mass model for the shaft system of WTG.

5.1.1 Mathematical Model

(1) Wind Turbine Model

The mechanical power that wind turbine extracts from wind can be computed as

30.5 ( , )m p wP A C v (5.1)

where 𝜌 is air density in kg/m3, 𝐴 = 𝜋 ∙ 𝑅2 is the turbine swept area in m

2, vw is wind

speed in m/s, Cp is the power coefficient which is a function of tip-speed-ratio λ and

blade pitch angle β.

The specific representation of power coefficient curve depends on the blade design

and will be given by wind turbine manufacturers. In this thesis, it is modeled using

equation (5.2), as

3

21

0.0068116 4.06

, 0.5176 0.4 50.08 1

p eC

(5.2)

(2) Model for Shaft System

Jwt Jgen

Twt Tgen

H

D

Wind Turbine Induction Generator

Page 94: SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK ...read.pudn.com/downloads799/sourcecode/math/3153436/Thesis_fin… · SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK RECONFIGURATION

82

Fig 5.2 shows a two-mass model for the shaft system. It consists of a low-speed wind

turbine mass and a high-speed generator mass, neglecting the gearbox mass because of its

relatively small inertia.

The electromechanical dynamic equations are

wtwt wt wt wt gen wt wt gen

wtwt

gengen gen gen gen wt gen gen wt

gengen

dT J D H

dt

d

dt

dT J D H

dt

d

dt

(5.3)

where, wt and gen are turbine rotational speed and generator rotational speed in rad/s,

Twt and Tgen are turbine torque and generator torque, Jwt and Jgen are moments of inertia of

the turbine and generator respectively, Dwt and Dgen are linear damping coefficients of the

turbine and the generator, Hwt and Hgen are stiffness coefficients of the turbine and the

generator.

(3) Induction Generator Model

Generally, all stator and rotor parameters are transformed into a two-axis reference

frame (d-q frame). Its electric system is depicted as Fig. 5.3.

d-axis q-axis

Figure 5.3 Electrical circuit for the induction machine in d-q frame.

The voltage equations are

+ +

- -

Rsd+- + -

RrdLlsd Llrd

Lmdisd irdvsd vrd

ωλsq (ω-ωr)λrq

+ +

- -

Rsq+ - +-

RrqLlsq Llrq

Lmqisq irqvsq vrq

ωλsd (ω-ωr)λrd

Page 95: SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK ...read.pudn.com/downloads799/sourcecode/math/3153436/Thesis_fin… · SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK RECONFIGURATION

83

( ) ( ) ( ) ( ) ( )

( ) ( ) ( ) ( ) ( )

( ) ( ) ( )( ) ( ) ( )

( ) ( ) ( ) ( ) ( )

sd sd sd sdsd

sqsq sq sq sq

r rdrd rd rdrd

rqrq rq rq r r

v t i t t t tR d

Rv t i t t t tdt

t t tv t i t tR d

Rv t i t tdt t t

( )q t

(5.4)

The flux equations are

(5.5)

5.1.2 Control System

Control of the wind generation system consists of control for the wind turbine, control

for the rotor-side converter and control for grid-side converter [83], [84], [85], [86]. Wind

turbine control is aimed at extracting mechanical power from wind. Rotor-side converter

control manages active and reactive power at the stator terminal. Grid-side converter

control maintains the dc-link voltage constant regardless of the magnitude and direction

of rotor power. The grid-side converter is actually a grid-tie inverter, and its control

strategy will be given later.

Figure 5.4 Conventional pitch angle control system.

At a specified wind speed, there exists a unique rotational speed to achieve the

maximum power coefficient Cp,max and thus obtain the maximum mechanical power from

( ) ( ) ( ) ( ) ( )

( ) ( ) ( ) ( ) ( )

( ) ( ) ( )( ) ( ) ( )

( ) ( ) ( ) ( ) ( )

sd sd sd sdsd

sqsq sq sq sq

r rdrd rd rdrd

rqrq rq rq r r

v t i t t t tR d

Rv t i t t t tdt

t t tv t i t tR d

Rv t i t tdt t t

( )q t

lsdsd sd rd sd mds m

lsqsq sq rq sq mqs m

Lt i t i t i t tL L

Lt i t i t i t tL L

lrdrd rd sd rd mdmr

lrqrq rq sq rq mqmr

Lt i t i t i t tLL

Lt i t i t i t tLL

+

-

p ik s k

s

Pitch

angle

0

max

Pelec

Pref

Page 96: SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK ...read.pudn.com/downloads799/sourcecode/math/3153436/Thesis_fin… · SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK RECONFIGURATION

84

the available wind power. If wind speed is below the rated value the rotational speed is

adjusted so that power coefficient remains max when the pitch angle is zero. Meanwhile,

if wind speed increases above the rated value pitch angle control is activated to increase

the pitch angle to limit the mechanical power. Fig 5.4 shows the pitch angle control

system.

The stator-voltage oriented reference frame, in which q-axis is aligned with stator

voltage vector vs is used in rotor-side converter control. For constant stator flux the

voltage at the stator resistance is small compared to the grid, thus

0, 0, 0, 0,sd sq s sd sq s

d dR v v v

dt dt (5.6)

Substituting (6) into stator voltage and flux equations yields,

Lm isq rqLs

v Ls m isd rdL Ls s

i

i

(5.7)

Then, active power and reactive power injected into the grid from the stator terminal

are

3 3

2 2

3 3

2 2

ms sd sd sq sq s rq

s

s ms sq sd sd sq s rd

s s

LP v i v i v i

L

v LQ v i v i v i

L L

(5.8)

Consequently, from equation (5.8) Ps and Qs are proportional to –irq and –ird

respectively.

Substituting (5.5) and (5.7) into rotor voltage equations, yields

Page 97: SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK ...read.pudn.com/downloads799/sourcecode/math/3153436/Thesis_fin… · SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK RECONFIGURATION

85

(5.9)

Using a proportional-integral (PI) control algorithm and combining (5.8) and (5.9) the

block diagram of the rotor-side converter is given in Fig. 5.5, which includes an external

power loop and an internal current loop.

Figure 5.5 Control for rotor-side converter.

5.2 Micro-Gas-Turbine Generation Unit

Microturbines are small and simple-cycle gas turbines with outputs ranging from

around 25 to 300 kW. There are essentially two types of microturbines: one is the high-

speed single-shaft unit and the other one is the low-speed split-shaft unit. The

comparisons of two types are listed as Table 5.1.

Table 5.1 Comparisons of Two Types of Microturbines

2 2

2 2

m mrd r rd r rd r r rq

s s

m m m srq r rq r rq r r rd r

s s s

L Ldv R i L i L i

L dt L

L L L vdv R i L i L i

L dt L L

,rd refI

,rq refI

max

rqI

rdI

+

+

-

-

min

,rd refV

,rq refV

1rqV

-

+

+

+

,s refP

P

,maxrqI

+ -

,

,

rq i

rq p

kk

s

sQ

Q

,maxrdI

+-

,

,

rd i

rd p

kk

s

sP ,minrqI

,s refQ

,minrdI

dq-> abc PWM,abc refV

Rotor-side converter

control signal

max

min

1rdV

,

,

rq i

rq p

kk

s

,

,

rd i

rd p

kk

s

2

mr r rq

s

LL I

L

2

mr r rd

s

LL I

L

+ m

s r s

s s

Lv

L

Configuration Features

Single-Shaft Compressor and Turbine are

mounted on the same shaft as

the electrical alternator.

• High-speed turbine: ~50000 to ~120000 rpm

• Permanent magnet machine

• Power converter is needed to convert high

frequency signals into 60 Hz.

Page 98: SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK ...read.pudn.com/downloads799/sourcecode/math/3153436/Thesis_fin… · SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK RECONFIGURATION

86

5.2.1 Mathematical Model

Single-shaft microturbine is studied as the example. Its model is composed of four

parts including speed and acceleration control, fuel control, temperature control and gas

turbine. Fig. 5.6 shows the block diagram for the mathematical model.

W(Xs+1)

Ys+Z

LV

G

++

speed control

DF ceV

g

g

mP2fW

3K

refP

2f

sTe

6K

fK

fWCRsE

e

1f1fW

cbs

a

1

1

sT f

TDsEe

1

1

sTCD

13

54

sT

KK

CT

DTF

sT

sT

t

15

1

1

4 sT

maxF

minF

maxF

minF

Acceleration

Control

Speed Control

RT

T

Temperature Control

Turbine

n

Fuel Control

Figure 5.6 Single-shaft MT model.

(1) Speed and acceleration control

Speed control is to control the rotational speed almost constant within a range of loads

changing. It is realized by regulating fuel demands of the micro-gas-turbine. In Fig. 5.6,

Pref is the load reference; △ωg is the speed deviation of the generator; FD is fuel demand;

Z represents the governor mode (droop or isochronous); W is the controller gain; X and Y

are lead and lag constants of the controller respectively (s).

Acceleration control is used primarily to limit the turbine acceleration rate during the

process of startup. If the rotate speed of the turbine is closed to its rated speed,

acceleration control will be automatically closed.

Split-Shaft Power turbine and the

conventional generator are

connected via a gearbox

• Low speed: 3600 rpm

• Induction or synchronous machine

• Power converter is not needed.

Page 99: SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK ...read.pudn.com/downloads799/sourcecode/math/3153436/Thesis_fin… · SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK RECONFIGURATION

87

(2) Fuel control

Fuel control part includes fuel limiter, valve and actuator. The fuel flow dynamics is

dominated by the inertia of the fuel system actuator and the valve positioner. In the

figure, Vce represents the least amount of fuel needed for the particular operating point;

ωn is the rated rotated speed of the generator; ωg is the real rotated speed; speed deviation

is △ωg=ωg-ωn;K3 is the gain of the delay; T is fuel limiter constant (s); a, c are known

valve parameters; b is the time constant of the valve(s);Tf is time constant of the

actuator (s);Kf is the feedback efficient of the valve and actuator;Wf is the fuel demand

signal in per unit (p.u); K6 is the fuel flow coefficient when the turbine operates at rated

speed without loads. At steady state, the signal Vce generated from low-value gate and the

fuel flow signal Wf have the following relationship:

(5.10)

(3) Gas Turbine

The compressor-turbine is the heart of the system, and it is composed of combustion

system, compressor and turbine. The compressor is a dynamic device with a time lag

associated with the compressor discharge volume. There is also a small time delay (ECR)

associated with the combustion reaction and a transport delay (ETD) associated with

transport or gas from the combustion system through the turbine. In the figure, Wf1 is the

output signal of fuel control system; Wf2 is the output signal of the compressor. TCD is the

compressor discharge time constant (s). The torque and the exhaust temperature

characteristic of the single-shaft gas turbine are linear with regard to fuel flow, turbine

speed and turbine rotor speed.

6

3

1KWKW

a

c

KV fffce

Page 100: SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK ...read.pudn.com/downloads799/sourcecode/math/3153436/Thesis_fin… · SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK RECONFIGURATION

88

Exhaust temperature function (5.11)

Torque function (5.12)

where, TR is the actual temperature of the turbine (K); af1、bf1、af2、bf2、cf2 are

constants. So the output mechanical power is

(5.13)

At steady state, △ωg=0, ωg=1.0,so

(5.14)

Since s = 0, so

(5.15)

Then,

(5.16)

Thus, load power reference Pref in speed control system has the following relationship

with the output mechanical power Pm:

(5.17)

(4) Temperature control

Temperature control is in command whenever the exhaust temperature exceeds the

exhaust temperature reference, or when the unit is picking up load faster than the turbine

dynamics can handle, which is due to the fact that the exhaust temperature responds

faster because of the increases in fuel flow before the moderating action of air flow with

1 1 11 (1 )R f f f gf T a W b

2 2 2 2 2f f f f gf a b W c

2 2 2 2 2m m g g f f f f g gP T f a b W c

2

2

2

f

fm

fb

aPW

2ff WW

6

2

2

3

6

3

11K

b

aPK

a

c

KKWKW

a

c

KV

f

fm

ffffce

2

6

3 2

m f

ref ce f

f

P aZ Z cP V K K

W WK a b

Page 101: SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK ...read.pudn.com/downloads799/sourcecode/math/3153436/Thesis_fin… · SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK RECONFIGURATION

89

increase in engine speed.

Figure 5.7 Electrical circuit of PMSG in d-q frame.

The generator is a two-pole PMSG with a non-salient rotor. Fig. 5.7 shows the

equivalent electrical circuit of the PMSG in synchronous rotational (d-q) frame. Rs is the

stator armature resistance, Lls is the leakage inductance, Lm is the mutual inductance, total

inductance L=Lls+Lm. PMSG generates a constant d-axis flux m, which is represented by

an inductance in parallel with a constant current source im, as

L i

m m m (5.18)

Voltage equations for the electrical part in d-q frame are

(5.19)

The mechanical part of PMSG is a single-mass model, as

(5.20)

5.2.2 Control System

Figure 5.8 Configuration of a micro-turbine generation system.

dv

sR dlsLr q

mimLdi qv

sR qlsLr d

mLqi

d s d d r q

q s q q r d

dv R i

dt

dv R i

dt

re r m

dJ T F T

dt

PMSG

Micro-

Turbine

G

Grid/Load

Page 102: SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK ...read.pudn.com/downloads799/sourcecode/math/3153436/Thesis_fin… · SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK RECONFIGURATION

90

Fig. 5.8 shows the configuration of a micro-turbine generation system. PMSG is

connecting with the single-shaft micro-turbine. Because the rotational speed of single-

shaft micro-turbines are usually at 50000 to 120000 rpm, power converter is necessary to

convert high frequency outputs from PMSG into utility frequency.

To simplify the control system, uncontrolled diode rectifier is used. The universal

bridge inverter is used to manage the outputs at its terminal, and its control strategy is

different for grid-connected and island operations, which will be explained in the

following.

5.3 Photovoltaic Generation Unit

Photovoltaic effect is a basic physical process through which solar energy is converted

into electrical energy directly. The physics of a PV cell is similar to the classical p-n

junction diode, shown in Fig. 5.9. At night, a PV cell can basically be considered as a

diode. When the cell is illuminated, the energy of photons is transferred to the

semiconductor material, resulting in the creation of electron-hole pairs.

Figure 5.9 The physics of a PV cell.

5.3.1 Mathematical Model

There are several equivalent circuits widely used for modeling a PV cell, including the

ideal model, single-diode model and double-diode model. Single-diode equivalent model

Page 103: SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK ...read.pudn.com/downloads799/sourcecode/math/3153436/Thesis_fin… · SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK RECONFIGURATION

91

has been proved to have great performance on mimicking the characteristics of the PV

cell, and it is used in the thesis. Fig. 5.10 shows the single-diode equivalent circuit, which

is composed of a photocurrent Iph, a nonlinear diode D, a series resistance Rs and a

parallel resistance Rsh.

Figure 5.10 Single-diode equivalent circuit for a PV cell.

The output current and voltage are related by

(5.21)

where, Iph is photocurrent; Is is diode saturation current; q is coulomb constant; k is

Boltzman’s constant; T is cell absolute temperature (K); A is P-N junction ideality factor.

Photocurrent is the function of solar radiation and cell temperature, described as

(5.22)

where, S is the real solar radiation (W/m2); Sref , Tref , Iph,ref is the solar radiation, cell

absolute temperature, photocurrent in standard test conditions respectively; CT is the

temperature coefficient (A/K).

Diode saturation current varies with the cell temperature

(5.23)

where, Is,ref is the diode saturation current in standard test conditions;Eg is the band-gap

energy of the cell semiconductor (eV),depending on the cell material.

phIsR

shRD

I

V

+

_

( )

( 1)sq V IR

sAkTph s

sh

V IRI I I e

R

, ( )ph ph ref T ref

ref

SI I C T T

S

3 1 1

,

g

ref

qE

Ak T T

s s ref

ref

TI I e

T

Page 104: SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK ...read.pudn.com/downloads799/sourcecode/math/3153436/Thesis_fin… · SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK RECONFIGURATION

92

The output power of a PV cell is less than 2 W at ~0.5 volts DC output voltage, so a

group of PV cells are usually connected in series and parallels to form a PV array for

practical application. The output voltage and current of a PV array can be formulated as

(5.24)

where, Ns and Np are cell numbers of the series and parallel cells respectively.

Fig. 5.11 shows current versus voltage and power versus voltage curves for a PV array

model at the reference condition ( T = 298 K and S = 1000 W/m2

) based on the

parameters given in Table 5.2. The maximum output power is 970.0 kW when the

voltage is 2400 V and current is 404.2 A.

Table 5.2 Parameters of A PV Array

A Tref Sref Is,ref Rs Ns Np 1.7687 298 1000 3.35 0.312 140 130

Figure 5.11 Characteristics curves for the PV array model.

5.3.2 Control System

As indicated in Fig. 5.11, there exists a maximum value for the output power of a PV

array under the given temperature and solar irradiance. Besides, the maximum output

power will be different for variant environmental conditions. Maximum Power Point

Tracking (MPPT) is a way to help a PV array extract maximum power under different

)

( 1) )

s

S P

IRq V

AkT N N sPP ph P S

sh S P

IRN VI N I N I e

R N N

Page 105: SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK ...read.pudn.com/downloads799/sourcecode/math/3153436/Thesis_fin… · SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK RECONFIGURATION

93

operating conditions. A large number of MPPT methods have been proposed in

literatures, and Esram and Chapman [87] gave a detailed comparison of these methods,

summarized as Table 5.3.

Perturbation and Observation (P&O) method is one of the most used MPPT methods

because of its simplicity and requirements for fewer measured variables. P&O algorithm

operates by constantly measuring the terminal voltage and current of the PV array,

constantly perturbing the voltage by adding a small disturbance, and then observing

changes in the output power to determine next control signal. If the output power

increases the perturbation will continue in the same direction in the following step,

otherwise the perturbation direction will be reversed. To improve tracking speed and

algorithm accuracy, the perturbation needs be continuously adjusted.

Table 5.3 Comparisons of Different Types of MPPT Algorithm.

By observing the characteristic curves of PV cells, the power increment dP and voltage

Page 106: SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK ...read.pudn.com/downloads799/sourcecode/math/3153436/Thesis_fin… · SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK RECONFIGURATION

94

increment dV satisfy:

At the left of MPP: dP / dV > 0

At the right of MPP: dP / dV < 0

At the MPP: dP / dV =0

As the operating point gets closer to the MPP the value of |dP/dV| is smaller, and the

perturbation can be chosen small and tracking is slow but accurate. When the operating

point is far from MPP the perturbation is large and tracking is fast. In sum, the variable-

step P&O algorithm is given as Fig. 5.12.

Measure ,k k

V I

k k kP V I

10

k kP P

1 1,k k k kV V I I

Yes

Yes

Yes

Yes

No

No

No No

10

k kV V

1

1

k kref ref

k k

P PV V

V V

10

k kV V

10

k kP P

1

1

k kref ref

k k

P PV V

V V

1

1

k kref ref

k k

P PV V

V V

1

1

k kref ref

k k

P PV V

V V

Figure 5.12 Flow-chart for variable-step P&O method.

MPPT can be realized by regulating the duty cycle of IGBTs in the boost converter

connected to the PV array, and the control block diagram is shown as Fig. 5.13. By

detecting the present voltage and current, the MPPT algorithm can determine the optimal

output voltage that leads to the maximum output power, and PI controllers are used for

tracking the voltage reference signal.

Page 107: SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK ...read.pudn.com/downloads799/sourcecode/math/3153436/Thesis_fin… · SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK RECONFIGURATION

95

MPPT

pvI

Voltage

Control

refV Current

Control

pvV

+

-

+

-

PWM IGBT

Figure 5.13 Block diagram of the MPPT controller.

5.4 Fuel Cell Generation Unit

Fuel cells (FCs) are static energy conversion devices that convert the chemical energy

of fuel directly into DC electrical energy. Fuel cells have a wide variety of potential

applications including micro-power, auxiliary power, transportation power, stationary

power for buildings and other distributed generation applications, and central power. At

present, mostly used fuel cells mainly include five kinds, which are alkaline fuel cells

(AFC), proton exchange membrane fuel cells (PEMFC), phosphoric acid fuel cells

(PAFC), molten carbonate fuel cells (MCFC) and solid oxide fuel cells (SOFC). Amongst

these types, polymer electrolyte membrane fuel cells (PEMFC) and solid oxide fuel cells

(SOFC) both show great potentials in transportation and DG applications.

5.4.1 Mathematical Model

stack

nernstE

+

- stack

FCV

stackactR

stackconRstack

ohmR

C

Figure 5.14 Equivalent electric model for the fuel cell.

Fig. 5.14 shows the equivalent electric model of a fuel cell [88]. It is noted that this

equivalent model could be used for both SOFC and PEMFC, but the representations for

the elements are different. The capacitor simulates the double-layer effect of the cell, and

it can be considered as a first-order delay existing in the activation and concentration

Page 108: SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK ...read.pudn.com/downloads799/sourcecode/math/3153436/Thesis_fin… · SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK RECONFIGURATION

96

voltages, as

(5.25)

and Ra is given as

act cona

FC

V VR

I

(5.26)

where, IFC is the operating current; Vact is the activation over-voltage, Vcon is the

concentration over-voltage.

There are three nonlinear resistances and an internal Nernst voltage. These four parts

all depend on the cell temperature and the partial pressure of hydrogen, oxygen and

water. Nernst voltage (Enernst) represents the open-circuit voltage of the single fuel cell at

the particular temperature and gas partial pressure. SOFC is studied as the example, and

its Nernst voltage is given as

2 2 20

1ln( ) ln( ) ln( )

2 2nernst H O H O

RTE E p p p

F

(5.27)

where, E0 is the standard referenced voltage at 1 atm pressure (V), F is Faraday

constant (96485 C/mol), R is the universal constant of the gas (8.314 J/(K mol)), 𝑝𝐻2,

𝑝𝑂2 and 𝑝𝐻2𝑂 are partial pressures of hydrogen, water vapor and oxygen (atm), T is cell

absolute temperature (K), Tref is the referenced temperature (K).

Activation over-voltage equivalent resistance (Ract) represents the losses of the

activation of anode and cathode in the fuel cell. For SOFC, the activation over-voltage

can be represented using Butler-Volmer equation, as

0

(1 )[exp( ) exp( )]act actzFV zFV

J JRT RT

(5.28)

where, 𝛼 is the transmitting coefficient, z is the number of electrons transferred by

every molecule fuel, J0 is the exchange current density (A/m2),J is the actual current

aCR

Page 109: SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK ...read.pudn.com/downloads799/sourcecode/math/3153436/Thesis_fin… · SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK RECONFIGURATION

97

density (A/m2).

The activation over-voltages of the anode and cathode are described as

(5.29)

Then, activation over-voltage equivalent resistance can be represented as

(5.30)

Ohmic over-voltage resistance (Rohm) is decided by the resistances of the anode,

cathode, electrolyte and the connecting parts, and it can be expressed as

(5.31)

where, is the flowing distance when the current is flowing through resistances (cm),

is the flowing area when the current is flowing through resistances (cm2), is the

resistivity of the the anode, cathode, electrolyte and the connecting parts ( ), which

is affected much by the temperature.

Concentration over-voltage equivalent resistance (Rcon) represents the effects of the

concentration of the reactant on the surface of the electrodes on the cell. The anodic and

cathodic concentration overvoltages can be expressed as

(5.32)

Then, the concentration over-voltage equivalent resistance is

1 2

.

0. 0. 0.

sinh ( ) ln[ ( ) 1] ,2 2 2

act i

i i i

RT J RT J JV i a c

F J F J J

. .act a act cact

FC

V VR

I

i iohm

i

lR

A

il

iA i

cm

2 2

2 2

2

2

.

.

ln( )2

ln( )4

r

H H O

con c r

H H O

r

O

con a

O

p pRTV

F p p

pRTV

F p

Page 110: SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK ...read.pudn.com/downloads799/sourcecode/math/3153436/Thesis_fin… · SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK RECONFIGURATION

98

(5.33)

During the simulation study, it is noticed that the time constants of double-layer effect,

changes in partial pressure and temperature differ a lot [89]: the time constant of double-

layer effect is usually less than 1 second and the changes in partial pressure are usually at

tens of seconds to minutes, while the changes in temperature only appear after minutes to

hours. Thus, during the short-term simulation study, we only consider the double-layer

effect and assume partial pressures and temperature constant. Instead, for medium-term

study, besides of double-layer effect the dynamics of partial pressure changes are also

considered [90], and the fuel cell model is demonstrated as Fig. 5.15. The changes in

temperature are only considered when the simulation time is long enough.

fN

rK2 rK

s

K

H

H

2

2

1

/1

s

K

OH

OH

2

2

1

/1

s

K

O

O

2

2

1

/1

stack

nernstE

+-

2Hp2H Op

2Op

in

ON2 + -

in

HN2 + -

Fuel

processor

delay

sf1

1

opt

r

u

K2

OHr _

1

1

1 es

2max

2

in

H

r

u N

K

2min

2

inH

r

u N

K

r

FCI

Fuel valve

control

function

Electric

response delay

stack

FCV

Fuel Control

Current Measurement

Electrochemical Dynamic

Electric Part

stackactR

stackconR

stackohm

R

2 2 2

1

20 ln( / )

2H O H O

RTN E p p p

F

stack

FCI

C

Figure 5.15 Medium-term dynamic fuel cell model.

Current measure part is to control the circuit current of the fuel cell stack 𝐼𝐹𝐶𝑠𝑡𝑎𝑐𝑘. Fuel

utilization u is the ratio between the fuel flow that reacts and the fuel flow injected into

the stack, described as

. .con a con ccon

FC

V VR

I

Page 111: SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK ...read.pudn.com/downloads799/sourcecode/math/3153436/Thesis_fin… · SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK RECONFIGURATION

99

(5.34)

where, and represents the hydrogen input flow rates and hydrogen reactive flow

rates respectively (mol/s), the constant , N is the number of the series cells,

is the fuel cell feedback current (A). is the electric response constant.

Fuel control part is to control gas input flow rate Nf (mol/s). The fuel valve is regulated

by adjusting the operating current, and the control function is

(5.35)

where, uopt is the given optimal utilization value.

Electrochemical dynamic part is most important in the medium-term dynamic model,

which is to simulate the changing of gas partial pressure in the stack. The calculation

methods of H2, O2 and H2O are similar. Taking H2 as an example, the calculation process

is introduced.

Changes of the hydrogen partial pressure can be expressed as

(5.36)

where, is the hydrogen partial pressure (atm), is the anode volume (m3), is

the number of moles of the hydrogen in the anode (mol), is gas constant (8.314 J/(K

mol)).

Then, it can be derived as

(5.37)

where, , , are the input, output and reacting flow rates of the hydrogen

2

2 2

2FC

rr

rH

in in

H H

K INu

N N

2

in

HN2

r

HN

FNKr 4

r

FCIe

2

2in rrH FC

opt

KN I

u

2 2H an Hp V n RT

2HpanV

2Hn

R

2 2 2 2 2

in out r

H H H H H

an an

d RT d RTp n N N N

dt V dt V

2

in

HN2

out

HN2

r

HN

Page 112: SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK ...read.pudn.com/downloads799/sourcecode/math/3153436/Thesis_fin… · SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK RECONFIGURATION

100

(mol/s)。

Since there is a proportional relation between the output rate of the reactants and the

partial pressure of the reactants, shown as

(5.38)

Substituting (5.38) into (5.37) and taking Laplace transform, we obtain

(5.39)

where, .

5.4.2 Control System

A DC/DC converter is generally connected to the fuel cell stack in order to increase the

output voltage and thus reduce the number of fuel cells required. The output voltage and

current at the terminal of the boost circuit are controlled, and the control system is similar

to the one used for PV system, as shown in Fig. 5.16.

PI

PI

PWM

Vdc,ref

Ifc

Voltage

Control

fuel cell

stack

Current

Control

Boost

Vdc

Vdc

Figure 5.16 Configuration and control for fuel cell generation system.

2 2 2

out

H H HN p K

2

2 2

2

1/( ) 2

1 FC

H in r

H H r

H

Kp s N K I

s

2 2H an HV RTK

Page 113: SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK ...read.pudn.com/downloads799/sourcecode/math/3153436/Thesis_fin… · SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK RECONFIGURATION

101

5.5 Super-Capacitor Energy Storage System

Super-capacitors are electrochemical capacitors that have unusually high energy

density when compared with common capacitors, and they are widely used as energy

storage device in DG applications. Fig. 5.17 shows the typical charging/discharging

characteristic curves of the super-capacitor, as well as the curves of the battery [91].

Compared with batteries which are also widely used for energy storage applications,

super-capacitors have energy densities that are approximately 10% of conventional

batteries, while their power density is generally 10 to 100 times greater. Thus, super-

capacitors have much shorter charge/discharge cycles and are more suitable for short-

term dynamic studies. Besides, the cycle life of super-capacitors is quite long, over

100,000 times.

Figure 5.17 Typical charge/discharge characteristic curves of the super-capacitor and battery.

5.5.1 Mathematical Model

Many equivalent circuits exist for modeling super-capacitors, such as classic

equivalent circuit model, three branches model and ladder circuit model, etc. Classic

equivalent circuit [92] is widely used because it is simple and effective, and it is shown as

Fig. 5.18. The model consists of an ideal capacitor, a series resistance ESR and a parallel

resistance EPR. ESR is very small, and simulates heat losses and charge/discharge

Page 114: SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK ...read.pudn.com/downloads799/sourcecode/math/3153436/Thesis_fin… · SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK RECONFIGURATION

102

voltage transient mutation in the process of charging and discharging. EPR is a large

resistance, which represents the current leakage effect and impact on long-term energy

storage performance.

Figure 5.18 Classic equivalent circuit for ultra-capacitor.

The three parameters in the model are formulated as

(5.40)

(5.41)

(5.42)

where, is the initial self-discharge at ; is the final self-discharge at ; C is the

rated capacitance; V is the change in voltage at turn on of load; I is the change in

current at turn on of load; is the initial capacitor voltage; is the capacitor current.

5.5.2 Control System

Super-capacitor energy storage system is composed of the super-capacitor, a bi-

directional DC/DC converter and controllers, and it can be charged by the grid to store

extra electric energy, and can also discharge electricity to the external grid. Super-

capacitor energy storage system can operate as a compensation for some intermittent

sources, such as wind farms or solar sources. In this manner, super-capacitors can be

ESR

EPR

C

VESR

I

2 1

2 1ln /

t tEPR

V V C

2

1_

1 tC

C C C C initt

ev ESR i i d V

C EPR

1V 1t 2V 2t

_C initVCi

Page 115: SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK ...read.pudn.com/downloads799/sourcecode/math/3153436/Thesis_fin… · SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK RECONFIGURATION

103

considered as transition sources to maintain the DG system stable.

Figure 5.19 gives the control system for the bi-directional converter [93]. The primary

objective of the converter is to maintain the common dc-link voltage constant. In this

way, no matter the ultra-capacitor is charging or discharging, the voltage at the dc bus can

be stable and thus the ripple in the capacitor voltage is much less. When the voltage at

DC bus is lower than the referenced voltage, switch S2 is activated, and the converter

works as a boost circuit; when the DC bus voltage is higher than the referenced voltage,

switch S1 is activated, and the converter works as a buck circuit. For both situations, the

control scheme still includes two loops-external voltage control and internal current

control.

Figure 5.19 Control for the bi-directional DC/DC converter.

Ultra-

capacitor

ucIucL

dcC

2S

1S

dcV

ucVPI PI

>=

AND

ANDNOT

2S

1S

dcV

,dc refV

,uc refI

ucI

PWM

dcV

,dc refV

signal

Page 116: SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK ...read.pudn.com/downloads799/sourcecode/math/3153436/Thesis_fin… · SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK RECONFIGURATION

104

Figure 5.20 A sketch of multiple distributed generation systems.

5.6 Operation of Grid-Connected / Islanded Distributed Generation

Systems

Fig. 5.20 shows a sketch of multiple distributed generation systems: each DG unit

could operate separately, or work with other DG units under appropriate energy

management strategy. All DG units can be integrated into the utility grid by

implementing stable control strategy on the grid-tie inverter, and can also operate

autonomously to supply electric power to loads directly. In general, during the grid-

connected operation the output power from the DG unit is controlled, while during the

islanded operation the voltage and frequency in the isolated network are regulated to be

nominal. Detailed control strategy is discussed in the following.

Gear

Box DFIG

PMSG

Micro-

Turbine

G

PV

Array

Fuel

Cell

Ultra-

capacitor

AC Bus

Page 117: SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK ...read.pudn.com/downloads799/sourcecode/math/3153436/Thesis_fin… · SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK RECONFIGURATION

105

Three-phase PWM inverter

AC

Bus

Grid

AC Loads

Isolating

Switches

+

-

Vdc

va

vb

vc

Lf

Lf

Lf

Cf

Rline

Rline

Rline

Lline

Lline

Lline

Cf Cf

ifiline

vfa

vfb

vfc

vLa

vLb

vLc

Rg

Rg

Rg

Lg

Lg

Lg

ig

vga

vgb

vgc

Figure 5.21 The configuration of a distributed generation unit for grid-connected and islanded

operations.

In order to illustrate the development of the inverter controller, a general configuration

of a distributed generation unit for both grid-connected and islanded operations is given

as Fig. 5.21. The mathematic relations of the three-phase voltages and currents can be

first obtained at the abc frame. The synchronous rotating frame (dq0 frame) with q-axis

aligned to the grid voltage vector is used to design controllers. Applying the frame

transformation, the relations of voltages and currents are written as (5.43)~(5.45), which

provide the basis for designing the controllers for both grid-connected and autonomous

systems.

fdf d fd f fq

fqf q fq f fd

diL v v L i

dt

diL v v L i

dt

(5.43)

,

,

fdf fd line d f fq

fqf fq line q f fd

dvC i i C v

dt

dvC i i C v

dt

(5.44)

,, ,

,, ,

line dline fd Ld line line d line line q

line qLqline fq line line q line line d

diL v v R i L i

dt

diL v v R i L i

dt

(5.45)

Page 118: SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK ...read.pudn.com/downloads799/sourcecode/math/3153436/Thesis_fin… · SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK RECONFIGURATION

106

5.6.1 Control System for Grid-Tie Inverter

During grid-connected operation, the isolating switches are closed and vL is determined

by the grid voltage as

gdg Ld gd g gd g gq

gqg Lq gq g gq g gd

diL v v R i L i

dt

diL v v R i L i

dt

(5.46)

where,

* *

1 1

* *

, ,

*

2 , ,

*

2 , ,

* *

3 3

d d fd f fq q q fq f fd

d fd line d f fq q fq line q f fd

d fd Ld line line d line line q

q fq Lq line line q line line d

d Ld gd g gd g gq q Lq gq g g

v v v L i v v v L i

i i i C v i i i C v

v v v R i L i

v v v R i L i

v v v R i L i v v v R i

q g gdL i

(5.47)

Applying Laplace transformation to (5.43)~(5.45), then

* * * *

1 1

,,

* * * *

2 2 3 3

( ) ( ) ( ) ( )1 1

( ) ( ) ( )( ) 1 1

fd fq fd fq

d q f d q f

line q gd gqline d

d q line line d q g g

i s i s v s v s

v v sL i i sC

i s i s i si s

v v sL R v v sL R

(5.48)

During grid-connected operation, the ac load impedance is much larger than the line

impedance, so iline ig. Thus,

,,

* *

4 4

1line qline d

d q line g line g

ii

v v s L L R R

(5.49)

where,

*

4 ,

*

4 ,

d fd gd line g line q

q fq gq line g line d

v v v L L i

v v v L L i

(5.50)

Page 119: SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK ...read.pudn.com/downloads799/sourcecode/math/3153436/Thesis_fin… · SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK RECONFIGURATION

107

pc ick s k

s

1

fsL

1

*

dv fd

i*

fdi +

-

*

di

+

pv ivk s k

s

,line di

f fq

C v

*

fdv

+

fdv

-

1

fsC

+-+

- +

f fq

C v

,line di

2

*

dv

+

p i

k s k

s

gdv

,line g line q

L L i

*

,line di

+-

+

-

1

line g line g

R R s L L

,line di

+

gdv

+

-

,line g line q

L L i

Inner-LevelMiddle-Level

Outer-Level

Figure 5.22 Three-level controller block diagram in d-axis for the grid-tie inverter.

From (5.48) and (5.49), the control system can be decomposed into three levels, with

PI controllers used in each level. Fig. 5.22 shows the block diagram of the control system

for d-axis components with the control variables if, vf and iline. The control system for the

q-axis components is designed using the same method. For the grid-tie inverter, the

objective is to manage the active and reactive power outputs of the DG system, and the

reference values for the line current are given by (5.51). In sum, the entire controller for

the grid-tie inverter is given as Fig. 5.23.

*

, 2 2

*

, 2 2

1.5

1.5

ref fd ref fq

line d

fd fq

ref fq ref fd

line q

fd fq

P v Q vi

v v

P v Q vi

v v

(5.51)

1+

-

-

line gL L

+

+

++

- 2 21.5

ref fd ref fq

fd fq

P v Q v

v v

iline,d

ip

kk

s

vgd

vgq

*

,line di

Qref

Pref

2 21.5

ref fq ref fd

fd fq

P v Q v

v v

*

,line qi

Qref

Pref

iline,q

ip

kk

s

2

++

*

fdv

*

fqv

3+

-

-

fC

fC

+

+

++

-vfd

ivpv

kk

s

iline,d

iline,q

4

++

*

fdi

*

fqi

vfq

ivpv

kk

s

5+

-

-

fL

fL

+

+

++

-ifd

icpc

kk

s

vfd

vfq

6

++

*

dv

ifq

icpc

kk

s

*

qv

line gL L

Figure 5.23 The complete controller for the grid-tie inverter.

5.6.2 Control System for Islanded Inverter

When the isolating switches are opened, the DG system is operating autonomously as a

microgrid. Different from grid-connected operation, the line current is determined by

Page 120: SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK ...read.pudn.com/downloads799/sourcecode/math/3153436/Thesis_fin… · SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK RECONFIGURATION

108

(5.52) assuming the AC loads are constant-impedance loads.

,

, ,

,

, ,

line d

load Ld load line d load line q

line q

load Lq load line q load line d

diL v R i L i

dt

diL v R i L i

dt

(5.52)

where, Rload and Lload represent the accumulated load impedance.

Similarly, the control system for the islanded inverter can be designed as three levels.

During the islanded operation, the voltage and frequency of the isolated system are

controlled based on the frequency/active power droop and voltage/reactive power droop,

as

* *

* *

P inv

Q inv

f f m P P

V V m Q Q

(5.53)

Thus, both the middle and inner levels are similar to the grid-tie inverter, but the

outmost level is changed to the droop controller. The outputs form the droop controller

are used to compute the reference values of voltages at d-q frame. Fig. 5.24 gives the

complete controller for the autonomous inverter during islanded operation.

*

fdv

*

fqv

3+

-

-

fC

fC

+

+

++

-

vfd

ivpv

kk

s

iline,d

iline,q

4

++

*

fdi

*

fqivfq

ivpv

kk

s

5+

-

-

fL

fL

+

+

++

-ifd

icpc

kk

s

vfd

vfq

6

++

*

dv

ifq

icpc

kk

s

*

qv

invP

3+

-

-

+

+

P*

mP

4

+mQ

-f*

-V*

f

V

invQ

Q*

Figure 5.24 Three-level controller block diagram in d-axis for the autonomous inverter.

5.6.3 Small-Signal Stability Analysis

Based on the above analysis, the state-space model of an entire distributed generation

system including the three-level control system can be obtained for both grid-connected

Page 121: SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK ...read.pudn.com/downloads799/sourcecode/math/3153436/Thesis_fin… · SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK RECONFIGURATION

109

and autonomously operating systems. The grid-connected operation is studied as the

example .

For the outer-level, let 𝜑1 = 𝑖𝑙𝑖𝑛𝑒,𝑑∗ − 𝑖𝑙𝑖𝑛𝑒,𝑑 , 𝜑2 = 𝑖𝑙𝑖𝑛𝑒,𝑞

∗ − 𝑖𝑙𝑖𝑛𝑒,𝑞 and define the state

vector x = [1 2, ]

T, input vectors u1 = [Pref, Qref, vgd, vgq]

T and u2 = [vfd, vfq, iline,d, iline,q]

T,

and output vector y = [𝑣𝑓𝑑∗ , 𝑣𝑓𝑞

∗ ]T, then the state-space model is given as

1 1 1 1 2

1 1 1 1 2

x A x B u B u

y C x D u D u

(5.54)

The representations of the state matrix A1, input matrix B1 and B2, output matrix C1 and

feedforward matrices D1', D1'' can be easily obtained from (5.46)~(5.50). Similarly, the

state-space representations of the middle-level and inner-level controllers are obtained as

(5.55) and (5.56).

2 2 1 2 2

2 2 1 2 2

x A x B u B u

y C x D u D u

(5.55)

where, 𝜑3 = 𝑣𝑓𝑑∗ − 𝑣𝑓𝑑, 𝜑4 = 𝑣𝑓𝑞

∗ − 𝑣𝑓𝑞, 𝑥 = [𝜑3, 𝜑4]𝑇, 𝑦 = [𝑖𝑓𝑑∗ , 𝑖𝑓𝑞

∗ ]𝑇

, 𝑢1 = [𝑣𝑓𝑑∗ , 𝑣𝑓𝑞

∗ ]𝑇

and 𝑢2 = [𝑣𝑓𝑑 , 𝑣𝑓𝑞 , 𝑖𝑙𝑖𝑛𝑒,𝑑 , 𝑖𝑙𝑖𝑛𝑒,𝑞]𝑇.

3 3 1 3 2

3 3 1 3 2

x A x B u B u

y C x D u D u

(5.56)

where, 𝜑5 = 𝑖𝑓𝑑∗ − 𝑖𝑓𝑑 , 𝜑6 = 𝑖𝑓𝑞

∗ − 𝑖𝑓𝑞 , 𝑥 = [𝜑5, 𝜑6]𝑇 , 𝑦 = [𝑣𝑑∗ , 𝑣𝑞

∗]𝑇

, 𝑢1 = [𝑖𝑓𝑑∗ , 𝑖𝑓𝑞

∗ ]𝑇

,

𝑢2 = [𝑖𝑓𝑑 , 𝑖𝑓𝑞 , 𝑣𝑓𝑑 , 𝑣𝑓𝑞]𝑇.

For the ac-side system from the inverter terminal to the grid, we consider the filter

inductance currents ifd, ifq, line currents iline,d, iline,q, and the PCC voltages vfd, vfq as both

states and outputs. Two input vectors are defined as u1 = [𝑣𝑑∗ , 𝑣𝑞

∗]T and u2 = [vgd,vgq]

T.

Page 122: SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK ...read.pudn.com/downloads799/sourcecode/math/3153436/Thesis_fin… · SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK RECONFIGURATION

110

Then the state-space model is

4 4 1 4 2

4 4 1 4 2

x A x B u B u

y C x D u D u

(5.57)

Based on (5.54)~(5.57), the state-space model of the entire system is concluded as

(5.58) with the state vector, input vector, output vector are respectively defined as

1 2 3 4 5 6 , ,

, ,

, , , , , , , , , , ,

, , ,

, , , , ,

T

fd fq fd fq line d line q

T

ref ref gd gq

T

fd fq fd fq line d line q

x i i v v i i

u P Q v v

y i i v v i i

x A x B u

y C x D u

(5.58)

where,

1 1 1 4

2 1 2 2 1 1 4 2 2 4

3 2 1 3 2 3 3 2 1 1 4 3 2 2 4 3 3 4

4 3 2 1 4 3 2 4 3 4 4 3 2 1 1 3 2 2 3 3 4

0 0

0

A B M C

B C A B D M C B M CA

B D C B C A B D D M C B D M C B M C

B D D C B D C B C A B D D D M D D M D M C

,

M1 = M2 =

0 0 1 0 0 0

0 0 0 1 0 0

0 0 0 0 1 0

0 0 0 0 0 1

, M3=

1 0 0 0 0 0

0 1 0 0 0 0

0 0 1 0 0 0

0 0 0 1 0 0

,

1 2 3 2 4 3 2 1 4

TB B B D B D D B D D D B N , C=[0 0 0 C4], D=0.

Finally, the block diagram for the state-space model of the grid-connected DG system

can be concluded as Fig. 5.25. The state-space model for the islanded system can be

obtained in the same way as the above procedures, and also its block diagram has the

same form as Fig. 5.25, but the parameters of inputs, states and outputs are different.

Page 123: SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK ...read.pudn.com/downloads799/sourcecode/math/3153436/Thesis_fin… · SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK RECONFIGURATION

111

B1'

B1''

u1'

u1''s-1

A1

D1'

D1''

C1

x1

y1B2'

B2''

(u2')

u2''s-1

A2

D2'

D2''

C2

x2

y2B3'

B3''

(u3')

u3'' s-1

A3

D3'

D3''

C3

x3

y3B4'

B4''

(u4')

u2'' s-1

A4

D4'

D4''

C4

x4

y4

M3

M2M1

Figure 5.25 Block diagram of the state-space model for the grid-connected DG system.

5.7 Case Study

Fig. 5.26 shows the configuration of a distribution system with multiple grid-connected

distributed energy resources, including wind turbine, microturbine, PV cells, fuel cells

and supercapacitor energy storage. System voltage is 400 V. There are fifteen nodes in

the network, with five different loads connected to nodes 11-15. A MT generation unit

and a wind farm are located at nodes 12 and 13, respectively. The PV generation unit,

fuel cell generation unit and energy storage are all connected to node 14 via a mutual

inverter. Each distributed energy resource can also be disconnected from the grid and the

control strategy should be changed from the grid-connected operation control to islanded

operation control. PV generation unit, fuel cell generation unit and supercapacitor energy

storage are accumulated together, which finally consists of a DC generation system.

At first, the grid-connected operation of multiple distributed generation systems is

simulated, and different scenarios are studied, including steady state, faults on the line,

Page 124: SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK ...read.pudn.com/downloads799/sourcecode/math/3153436/Thesis_fin… · SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK RECONFIGURATION

112

changes in wind speed and solar irradiance. For each scenario, the dynamic behaviors of

all DG units are analyzed. Then, the islanded operation of the DC generation system, i.e.

DC microgrid is studied with the implementation of the autonomous inverter control.

40

40

40

40

40

10

40

40

40

40

3+N

3

20kV

0.4kV

1

2

3

4

5

6

7

8

9

10 11 12

Load 1

Load 3

Load 4

Load 5

Load 6

Line 4

Line 6

Line 2

Line 1

Line 5

Line 6

Line 3

30m

30m

30m

30m

30m

35m 35m 35m

35m

13

15

16

17

18

10Load 2

Line 3

30m

14

PV

CellsAC

DC

MT

PV System

DC Micro-grid

Micro-Gas-Turbine System

30 kW

Wind

Farm

90 kW

Wind Power System

DC

DC

Ultra-

Capacitor

DCDC

Fuel

Cells

DC

DC

Electro

-lyzer

Fuel Cell Generation System

Figure 5.26 Configuration of the distribution system with multiple distributed energy resources.

5.7.1 Grid-Connected Operation

The model of the complete grid-connected hybrid AC/DC microgrid system is built

Page 125: SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK ...read.pudn.com/downloads799/sourcecode/math/3153436/Thesis_fin… · SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK RECONFIGURATION

113

using MATLAB/Simulink. The capacities of wind power unit and MT generation unit are

90 kW and 30 kW, respectively. The wind turbine operates at a nominal wind speed of 15

m/s, with a generator rotor speed of 1.2 pu. SOFC is used as the energy resource in the

fuel cell generation unit and its capacity is 18 kW. PV generation unit has a maximum

power rating of 9.8 kW with solar irradiance of 1000 W/m2 and an operating temperature

of 298K.

(1) Steady State Operation and Line Faults

At steady state, all distributed generation units are controlled to operate under their

rated conditions, and supply power to loads and grid. Then, two faults respectively occur

at 5 s and 9 s, and both last for 1 second. Fig. 5.27 gives the types and locations of two

faults. All simulation results are given in Fig. 5.28.

40

10

40

2

3

4

5

8 9 10

Load 3

30m

35m 35m 35m

12

30m

Fault-1: 4s-5s phase-a

line grounding fault

Fault-2: 9s-10s 3-phase

line grounding fault

Figure 5.27 Two faults occurred at the system.

All distributed generating units reach steady-state operation after a short period of

transient time. At steady state, since the PV generation system and fuel cell system can

supply sufficient power for the load demands, the super-capacitor energy storage system

is inactive, i.e. neither charging nor discharging. The pitch angle controller maintains the

pitch angle to fix at eight degree so that the rotational speed of wind generator is 1.2 p.u..

The rotational speed of MT generator finally stays at 0.96 p.u. during steady-state

Page 126: SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK ...read.pudn.com/downloads799/sourcecode/math/3153436/Thesis_fin… · SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK RECONFIGURATION

114

operation. Two line faults both affect all bus voltages and currents. Single-phase fault has

little influence on the side of each distributed generation unit because of the isolation

effect from the power electronics. During 3-phase grounding fault, WT and MT system

are significantly affected by fluctuations in rotational speed, and the DC microgrid is not

stable since it is actually disconnected from the grid by the fault. After clearing the fault,

the entire system regains stability gradually.

Page 127: SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK ...read.pudn.com/downloads799/sourcecode/math/3153436/Thesis_fin… · SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK RECONFIGURATION

115

Figure 5.28 Simulation results for the system at steady-state.

(2) Changes in Wind Speed and Solar Irradiance

Fig. 5.29 shows the changes happened in both wind speed and solar irradiance. At t=5s

wind speed has a step change from 15m/s to 20m/s, and then at t=12s wind speed changes

again from 20m/s to 12m/s. Solar irradiance increases from 1000 W/m2 to 1500 W/m

2 at

t=8s, and then decreases greatly to 500 W/m2 at t=15s. Total simulation time is 20 s. Fig.

5.30 gives simulation results for the wind power unit and DC generation unit.

Page 128: SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK ...read.pudn.com/downloads799/sourcecode/math/3153436/Thesis_fin… · SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK RECONFIGURATION

116

Figure 5.29 Changes in wind speed and solar irradiance.

Figure 5.30 Simulation results for wind power unit and DC generation unit.

When the wind speed jumps to 20 m/s, the pitch angle controller increases pitch angle

to about 19 degrees to limit output power to ~90 kW; when wind speed decreases to 12

m/s, the pitch angle is kept at 0 to allow the wind turbine to extract maximum power, ~70

time solar irradiance wind speed

0-5s 1000 15

5s-8s 1000 20

8s-12s 1500 20

12s-15s 1500 12

15s-20s 500 12

Page 129: SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK ...read.pudn.com/downloads799/sourcecode/math/3153436/Thesis_fin… · SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK RECONFIGURATION

117

kW. In the DC generation system, MPPT controller enables the PV system to work at its

MPPs for various environmental conditions. Super-capacitor energy storage system can

track the power difference between sources and load demands by charging and

discharging.

5.7.2 Islanded Operation

DC generation unit can be disconnected from the grid and work as a microgrid to

supply power for “Load 5”, which is 25 kVA with 0.9 power factor. Now the control

strategy for the islanded inverter is switched to droop control so that system voltage and

frequency in the microgrid could be maintained to be nominal as 400 V and 60 Hz,

respectively. Fig. 5.31 shows simulation results of the microgrid. It proves that the

proposed droop controller can maintain the entire microgrid operate stably: voltage and

frequency are maintained nominal; all DC energy resources operate stably and generate

constant power; voltages and currents at the terminal of the autonomous inverter are

three-phase sinusoidal; and the ac load gets fully served by the microgrid with enough

generation.

Page 130: SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK ...read.pudn.com/downloads799/sourcecode/math/3153436/Thesis_fin… · SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK RECONFIGURATION

118

Figure 5.31 Simulation results of the microgrid.

Page 131: SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK ...read.pudn.com/downloads799/sourcecode/math/3153436/Thesis_fin… · SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK RECONFIGURATION

119

invP Pm

*f

+

-

+

-*P

invQ Qm

*V

+

-

+

-

+

+

+

+

2

mV

refV

ref

*Q

Figure 5.32 Designed scheme of the synchronization.

Besides, the disconnected microgrid can be reconnected to the grid. But before

conducting the reconnection, the magnitudes and phases of the voltages at the point of

common coupling (PCC) in both microgrid and the grid should be synchronized. Fig.

5.32 shows a simple scheme of synchronization: detect the grid-side voltage and

microgrid voltage, and compute both voltage magnitude difference ∆𝑉𝑚 and phase

difference ∆𝜃, which are then added into the reference values of the controller for the

autonomous inverter. When both voltage magnitudes and phase angles of the microgrid

and bulk grid are exactly same, the connecting switch between the microgird and grid is

closed so that the microgrid is reconnected to the distribution grid. Fig. 5.33 shows the

simulation results of the synchronization process. At the beginning, there are slight

magnitude difference and significant phase difference between microgrid voltage and

grid voltage. When t = 2 s, the synchronization is implemented, and after about 1 second

the magnitudes and phases of the voltages in the microgrid and the grid get exactly

synchronized with zero difference.

Page 132: SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK ...read.pudn.com/downloads799/sourcecode/math/3153436/Thesis_fin… · SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK RECONFIGURATION

120

Figure 5.33 Simulation results of the synchronization process.

Page 133: SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK ...read.pudn.com/downloads799/sourcecode/math/3153436/Thesis_fin… · SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK RECONFIGURATION

121

Chapter 6 Distribution Network Reconfiguration and

Energy Management of Distributed Generation Systems

The mathematical modeling, primary control and simulation studies of multiple

distributed generation (DG) units were studied in chapter 5. From the perspective of a

distribution system, the integration of these DGs can help improve the voltage profile,

provide uninterrupted power supply and also reduce power losses. The locations and

outputs of DERs also affect system voltages and power losses directly, and it is necessary

to choose the optimal locations and to determine the capacity of DG units first in order to

improve voltages and reduce losses during distribution system operation. All previous

studies on network reconfiguration are based on balanced system assumption with the

application of single-phase equivalents. However, distribution systems are generally

unbalanced because of non-uniform load distribution and nonsymmetrical conductor

spacing on three-phase lines. With the expected growth in the numbers and sizes of

single-phase DERs integrated into the grid and the increasing power demands for

charging plug-in electric vehicles, unbalance issues, developing efficient and robust

algorithms for reconfiguration of unbalanced distribution networks is essential.

6.1 Three-Phase Power Flow and Power Loss Minimization

6.1.1 Three-Phase Unbalanced System Modeling

Fig. 6.1 shows the components between two buses in an unbalanced distribution

system, and voltages and currents are related as (6.1).

Page 134: SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK ...read.pudn.com/downloads799/sourcecode/math/3153436/Thesis_fin… · SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK RECONFIGURATION

122

Figure 6.1 Components between two buses in an unbalanced distribution system.

(6.1)

Loads can be modeled as negative current injections at buses for both Wye and Delta

connections. Each load is assumed to be a linear combination of constant power

component, constant impedance component and constant current component, thus the

three-phase current injection at bus-i is computed as

(6.2)

where, [IP,i]abc, [IZ,i]abc, [II,i]abc are three-phase current injections of the constant power,

constant impedance and constant current loads connecting at bus-i, respectively.

The DG unit locating at bus-i can be modeled as positive current injection, as

(6.3)

where, 𝑃𝐷𝐺,𝑖𝑝

, 𝑄𝐷𝐺,𝑖𝑝

are phase-p active and reactive power generated from the DG unit

locating at bus i. 𝑉𝑖𝑝=𝑒𝑖

𝑝+ 𝑗𝑓𝑖

𝑝 is phase-p voltage at bus i.

If a DG unit works at constant power mode, the equivalent current injection could be

computed directly as (6.3) because the values of active and reactive power are specified.

However, if a DG unit works at constant voltage mode, a two-loop computation is needed

to obtain the equivalent current injection. The inner-loop calculates the reactive power

output of the DG unit that is necessary to keep the bus voltage magnitude at the specified

Bus-i zaaVi

a

Vib

Vic

Vja

Vjb

Vjc

Bus-j

zbb

zcc

zab

zbc

zca

Iic

Iib

Iia

IL,ia

IL,ib

IL,ic

aa aji iaa ab ac

b b bi j ba bb bc i

c cc ca cb cc ii ij

VV Iz z z

V V z z z I

z z zV IV

1, 2, 3,i i i L,i P,i Z,i I,iabc abc abc abcI I I I

, , , , , ,

* * *

Ta a b b c c

DG i DG i DG i DG i DG i DG i

a b ci i i

P jQ P jQ P jQ

V V V

DG,i abc

I

Page 135: SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK ...read.pudn.com/downloads799/sourcecode/math/3153436/Thesis_fin… · SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK RECONFIGURATION

123

value, and the outer-loop calculates the current injection with the initially specified active

power and the solved reactive power.

It is noted that although two-phase or single-phase branches usually exist in the

unbalanced network, (6.1) is still true while the values of the corresponding phase

impedances for the missing phases become zeros, and the voltages and currents for the

missing phases are then deleted from the results. Similarly, for the single-phase or two-

phase loads and DG units, the output power of the missing phase is set to zero without

changing the formulations of (6.2) and (6.3).

6.1.2 Power Flow Equations

Network reconfiguration is generally indicated as feeder reconfiguration, thus it is

supposed that only three-phase feeder branches are reconfigurable. Besides, it is assumed

that each feeder branch is equipped with a three-phase switch, and the state of the switch

is defined as

1,

0,

1,

j

switch j isclosed and directionis sameastheinitial

S switch j isopen

switch j isclosed and directionisopposite

(6.4)

where, direction refers to the direction of current flow.

The connectivity of a network can be represented using node-branch incidence matrix.

If the system is ideally three-phase balanced, single-phase equivalents are adopted and

the node-branch incidence matrix is denoted as Abalanced, which varies for different

system structures. The calculation starts from the assumption that all switches are initially

closed, and the node-branch incidence matrix for the closed-loop system is A0

balanced,

which is constant for a specific system. Then Abalanced can be computed using A0

balanced

and switch states, as

Page 136: SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK ...read.pudn.com/downloads799/sourcecode/math/3153436/Thesis_fin… · SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK RECONFIGURATION

124

(6.5)

where, aij, aij0

are the ij-th elements of Abalanced and A0

balanced respectively.

If the system is unbalanced, three-phase representations of the node-branch incidence

matrix must be used, which can be acquired by multiplying each element in Abalanced with

a 3×3 unit matrix, as

(6.6)

It is known that

(6.7)

where, Vbus is bus voltage vector. Ibranch and Ibus are branch current vector and node

injection current vector, respectively. Zbranch is branch reactance diagonal matrix. Ybranch

and Ybus are branch admittance diagonal matrix and node admittance matrix, respectively.

And, it is known that

(6.8)

where, IDG and IL are DG injection current vector and load injection current vector,

respectively.

According to (6.7) and (6.8), power flow algorithm is developed as: with initial voltage

𝐕𝐛𝐮𝐬(𝑘−1)

(k is the iteration time) given, node injection current 𝐈𝐛𝐮𝐬(𝑘)

is computed from (6.8),

and the results are used to compute new bus voltages 𝐕𝐛𝐮𝐬(𝑘)

using (6.7). The iteration goes

on until meeting the stop criteria, and finally system voltages and currents are solved

iteratively.

Further, from (6.7) the current injection at bus-i is given as

aij = aij0 ×S j

0

0

0

0 00 0

( , ) 0 0 0 0

0 0 0 0

ijij

ij ij j

ij ij

aa

A i j a a S

a a

Tbus branch bus bus busI = A Y A V Y V

bus DG LI = I I

Page 137: SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK ...read.pudn.com/downloads799/sourcecode/math/3153436/Thesis_fin… · SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK RECONFIGURATION

125

(6.9)

where, 𝑡𝑖𝑘𝑙𝑝

= ∑ (𝑎𝑖𝑗0 𝑎𝑘𝑗

0 𝑦𝑗𝑙𝑝

) ∙ 𝑆𝑗2 ≜ 𝑔𝑖𝑘

𝑙𝑝+ 𝑗𝑏𝑖𝑘

𝑙𝑝𝑚𝑗=1 .

[𝑦𝑗𝑎𝑎, 𝑦𝑗

𝑎𝑏, 𝑦𝑗𝑎𝑐; 𝑦𝑗

𝑏𝑎, 𝑦𝑗𝑏𝑏, 𝑦𝑗

𝑏𝑐; 𝑦𝑗𝑐𝑎, 𝑦𝑗

𝑐𝑏 , 𝑦𝑗𝑐𝑐] is the conjugate inverse matrix of the phase

impedance matrix for the jth

branch. Besides, since

, ,

,

l linject i inject il

bus i l li i

P j QI

e j f

(6.10)

where, 𝑃𝑖𝑛𝑗𝑒𝑐𝑡,𝑖𝑝

, 𝑄𝑖𝑛𝑗𝑒𝑐𝑡,𝑖𝑝

are actual phase-p active and reactive power injections at bus i.

Finally, we can obtain power flow equations as

(6.11)

6.1.3 Power Loss Minimization

In unbalanced systems, the power loss at a branch is computed as the difference (by

phase) of the input power minus the output power. Because

(6.12)

According to (6.1), (6.6) and (6.12), total active power losses in the system is obtained

as

(6.13)

,

1

, , , .n c

l lp pbus i ik k

k p a

I t V l phase a b c

,

,

1

1

inject i

inject i

n cl l lp p lp p l lp p lp p

i iik k ik k ik k ik kk p a

n cl l lp p lp p l lp p lp p

i iik k ik k ik k ik kk p a

P e g e b f f g f b e

Q f g e b f e g f b e

Tbus branch branchA V Z I

1 1

* 0 0 2

1 11

Re

n c n ck p pk p pk k p pk p pkj i ij i ij j i ij i ij

j k a i p a

c n c mp pkk

jloss il jl li lk a i p a l

n

j

e e g f b f f g e b

P V V a a y S

Page 138: SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK ...read.pudn.com/downloads799/sourcecode/math/3153436/Thesis_fin… · SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK RECONFIGURATION

126

In (6.13), the results of voltages depend on system topology and output power of DG

units, which are decision variables in the optimization problem of minimizing power loss.

Besides, these constraints are required when minimizing power loss:

(1) Voltage Limits

All voltage magnitude deviations be within 5% of the norminal value.

0.95∙|Vnorm| ≤ |Via|, |Vi

b|, |Vi

c| ≤ 1.05∙|Vnorm|, i=1, 2,..., N. (6.14)

Voltage unbalance or imbalance in short is often expressed as the negative sequence

component of the voltage divided by the positive sequence component according to the

IEEE Standard 1250-2011 [94]. Alternative definitions consider the unbalance as the

maximum deviation divided by the average of the three phases [95]. Voltage unbalance is

an undesired attribute that can cause excessive heating in motors and result in unbalanced

currents and noncharacteristic harmonics for electronic equipment such as adjustable

speed drives. Imbalance in phase currents may furthermore lead to excessive levels of

neutral currents, which may cause nuisance line trips. The ANSI C84.1-2006 standard

recommends that voltage unbalance be limited to 3%.

(6.15)

(2) Current Limits

Branch currents are computed using (6.12), and each current is limited by

(6.16)

where, 𝐼𝑖𝑚𝑎𝑥 is the ampacity of branch i.

(3) DG Capacity Limits

max max

, ,, ,,p pDG i DG iDG i DG iP P Q Q (6.17)

3%, , 3, , ,

pc

i i pi i

i p a

V avgwhere avg V p a b c

avg

,max,p

ibranch iI I

Page 139: SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK ...read.pudn.com/downloads799/sourcecode/math/3153436/Thesis_fin… · SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK RECONFIGURATION

127

where, 𝑃𝐷𝐺,𝑖𝑚𝑎𝑥, 𝑄𝐷𝐺,𝑖

𝑚𝑎𝑥 are the maximum active power and reactive power for the ith

DG

unit.

(4) System Structure Constraints

System structure constraints are same as those used in balanced system study. First, the

distribution system is radial without meshes, thus

(6.18)

All loads are served without disconnections, so

rank(A) = N – d (6.19)

In addition, at least one branch is open in each loop, so

(6.20)

6.2 Optimal Planning of DG Units

Figure 6.2 The framework of the strategy.

According to the above study, the factors to affect system power losses include system

topology and the amount, locations and output power of DG units in the system. A study

framework is proposed to take all these factors into consideration to minimize power

1

M

k

k

S N d

1

1kM

i ki

S M

Decide the

Optimal

Locations

and Capacity

of DG Units

Opened

Switches…...

…...

System Data Acquisition

Reconfigure

Hour t

…...

Q1

…...

P1

Q2P2

QKPK

Determine system

topology and the

actual output

power of all DG

units for the

current operation

time window

Page 140: SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK ...read.pudn.com/downloads799/sourcecode/math/3153436/Thesis_fin… · SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK RECONFIGURATION

128

losses, shown as Fig. 6.2. The penetration of DG units is defined as the ratio of the buses

connecting with DG units to the total amount of buses in the system and its value is pre-

given. All DG units connecting at the same bus could be aggregated into a single cluster,

so it is assumed that each bus only has one aggregated DG unit installed. Then, in order

to determine the optimal results of switch states and DG output power during real-time

operation, the optimal locations and capacity of all DG units in the system are solved

primarily.

6.2.1 Optimal Locations of DG Units

The sensitivity of power losses with respect to the active power injection at each bus is

computed to determine the most sensitive buses for installing DG units. Since the

integration of DG units will add positive active power injections, so the best location is

the one with the most negative sensitivity in order to get the largest power loss reduction.

First, we can denote (6.13) as

(6.21)

Voltage vectors and power injections are related by (6.11), as

(6.22)

If a small change [ P, Q]T is added into the power injection vector [Pinject, Qinject]

T,

the change in voltage vector is solved from

0

00

inject

injectinject injectx x

Peh h h h

f Qe f P Q (6.23)

Further, the induced changes in power losses are

Ploss

= g e , f( )

h e,f ,Pinject,Q

inject( ) = 0

Page 141: SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK ...read.pudn.com/downloads799/sourcecode/math/3153436/Thesis_fin… · SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK RECONFIGURATION

129

loss

g gP

e

fe f (6.24)

Finally, the sensitivity vector of the power losses with respect to the power injection at

each bus is obtained as

1

[ ]g g

S

inject inject

h h h hM

e f e f P Q (6.25)

With the sensitivity vector solved, the sensitivity of total power losses with respect to

each phase of the power injection at each bus can be obtained. It is assumed that only

three-phase buses are considered as candidate locations, and the sensitive index of a bus

is computed as the average value of three phases. Thus, the sensitivity vector is first

formed as (6.25) but only the results of the sensitivity for three-phase buses are computed

to analyze.

6.2.2 Optimal Capacity of DG Units

The optimal capacities of DG units are solved in order to minimize power losses in the

unbalanced distribution system with the initial topology. This case can be considered as

the worst scenario in the reconfiguration study because DG units must generate the

maximal power into the grid without the additional support of reconfiguring the network.

The optimization problem can be formulated as

(6.26)

where, x = [e, f]T, u = [PDG, QDG ]

T. f (x, u) is power flow equations. g (x, u) represents

the constraints (6.14)~(6.17).

min

. .

lossu

J P

s t

x,u

f(x,u) = 0

g(x,u) 0

Page 142: SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK ...read.pudn.com/downloads799/sourcecode/math/3153436/Thesis_fin… · SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK RECONFIGURATION

130

With the introduction of penalty function into the objective function, inequality

constraints can be eliminated, as

(6.27)

where, H is the total amount of inequality constraints. Each penalty function is defined

as

(6.28)

The equality constraints f(x,u) is always true since the power flow computation is first

solved to calculate power losses. As a result, (6.26) is changed into an unconstrained

optimization problem, the minimizer of which is solved numerically using quasi-Newton

method.

Primarily, this theorem is proved [96]: Let 𝑭: 𝑅𝑛 → 𝑅𝑛 be continuously differentiable

in an open convex set 𝐷 𝑅𝑛 . Assume that there exists 𝑢∗ ∈ 𝑅𝑛 and 𝑟,𝛽>0, such that

𝑁(𝑢∗, 𝑟) 𝐷, 𝑭(𝑢∗) = 0, 𝐻(𝑢∗)−1 exists with ‖𝐻(𝑢∗)−1‖ ≤ 𝛽, and 𝐻 ∈ 𝐿𝑖𝑝𝛾(𝑁(𝑢∗, 𝑟)).

Then there exist 𝜀 > 0 such that for all 𝑢0 ∈ 𝑁(𝑢∗, 𝑟) the sequence 𝑢1, 𝑢2, … generated by

𝑢𝑘+1 = 𝑢𝑘 − 𝐻(𝑢𝑘)−1𝐹(𝑢𝑘) is well defined, and converges to 𝑢∗.

The derivative of (6.27) is given by

(6.29)

where, the first term at the rightmost side of the equation is same as the sensitivity

matrix given in (6.25) with the columns representing for the buses connecting with DG

units selected, and the second term could be obtained by differentiating (6.14)~(6.17).

1

min ( ) ( , )H

uc loss i i i

i

J P g

x,u

2

0, 0( , ) 0.

, 0

i

i i i i

i i i

if gg and

g if g

1

( , )H

uc lossi i i

i

dJ dP dg

d d d

x,u x,u

F uu u u

Page 143: SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK ...read.pudn.com/downloads799/sourcecode/math/3153436/Thesis_fin… · SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK RECONFIGURATION

131

Because the hessian matrix is hard to solve directly, the minimizer for (6.27) could be

solved using secant method with positive definite secant update, as

(6.30)

And, the initial value H0 is set to be |Juc(u0)|∙I. The approximated hessian matrix

obtained is symmetric and positive definite. After using (6.30) to get a local Newton step,

the backtracking line-search [97] is added to ensure the global convergence, and each

next Newton step is chosen so that the Armijo condition is satisfied, as

(6.31)

6.3 Network Reconfiguration and Optimal Operation of DG Units

After installing DG units and scheduling their optimal capacity as the above

procedures, system power loss has been minimal for the initial system structure. It is

expected that the power loss could be reduced further if the system is reconfigured

optimally. Besides, due to time-varying loads, power loss will not be always minimal for

a fixed network structure and constant DG output power, so there is a need for

reconfiguring the network and curtailing DG power from time to time. Thus, an

optimization problem with the objective of minimizing the total costs of power losses and

curtailing the output power of DG units is defined for each operation period, and the

problem formulation is given as

,

-1k+1 k k k

k k+1 k k k+1 k

T Tk k k k k k

k+1 k T Tk k k k k

u u - H F u

s = u - u y = F u - F u

y y H s s HH = H + -

y s s H s

1 10.001T

uc k uc k k k kJ u J u F u u u

Page 144: SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK ...read.pudn.com/downloads799/sourcecode/math/3153436/Thesis_fin… · SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK RECONFIGURATION

132

1 2 max, ,

1

3 max, ,

1

, max, , max,

min ,

. . (6.14) ~ (6.20),

, ,

1 ~ , , , , 1 ~ 24.

K cp p

loss DG i DGact it

i p a

K cp pDG i DGact i

ti p a

p p p pDGact i DG i DGact i DG i

t t

J w P w P P

w Q Q T

s t and

P P Q Q

i K p a b c t

DGactS PQ

(6.32)

where, T is the amount of tie-switches in the system. K is the amount of DG units in

the system. ∆T is the planned operation period in hour. 𝑃𝐷𝐺𝑚𝑎𝑥,𝑖𝑝

and 𝑄𝐷𝐺𝑚𝑎𝑥,𝑖𝑝

are the

optimal capacity of the ith

DG unit solved in 6.2.2. (𝑃𝐷𝐺𝑎𝑐𝑡,𝑖𝑝

)𝑡 and (𝑄𝐷𝐺𝑎𝑐𝑡,𝑖

𝑝)

𝑡 are the

actual phase-p active and reactive output power of the ith

DG unit for the operating time t,

w1~w3 are electricity tariff in USD/kWh, and their values are assumed as 1 in the

following study.

A hierarchical, decentralized approach has been proposed to reconfigure balanced

distribution systems in Chapter IV. With necessary improvements, this approach can be

used to solve both optimal topology and DG outputs simultaneously for unbalanced

distribution systems. Fig. 6.3 shows the flowchart of the revised hierarchical

decentralized approach, and a timescale of 24 hours is included.

(1) Network Decomposition

The procedures to decompose the entire distribution network are same as those

illustrated in Chapter IV. Decomposed subsystems are arranged layer by layer, and the

lowest-layer subsystems form the basis of the entire system, and they include all buses

and loads, as well as DG units. Each higher-layer subsystem is composed of several

lower-layer subsystems and the highest-layer subsystem denotes the entire distribution

system.

Page 145: SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK ...read.pudn.com/downloads799/sourcecode/math/3153436/Thesis_fin… · SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK RECONFIGURATION

133

1. Network decomposition1. Network decomposition

STOPSTOP

2. Apply multi-agent framework2. Apply multi-agent framework

t = 1t = 1

Collect all useful system data at hour-tCollect all useful system data at hour-t

3. Enable the lowest-layer agents and use GA to

solve the optimization problem.

3. Enable the lowest-layer agents and use GA to

solve the optimization problem.

Any changes?Any changes?

YES

NO

Initialization:pop_size, max_gen. Let gen=1, and encode the 1st generation.

Initialization:pop_size, max_gen. Let gen=1, and encode the 1st generation.

Satisfy all constraints? Satisfy all constraints?

Select an offspring from all new chromosomesSelect an offspring from all new chromosomes

Delete this

offspring from

the population

Delete this

offspring from

the population

Keep this offspring in the population

and compute its operating costs

Keep this offspring in the population

and compute its operating costs

Elitism selection from the remained

feasible population

Elitism selection from the remained

feasible population

All offsprings are evaluated?All offsprings are evaluated?

YES

NO

k=k+1k=k+1

k>max_genk>max_gen STOPGenerate the solutions.

STOPGenerate the solutions.

YESNO

Cross OverCross Over

MutationMutation

NO

YES

4. Move upwards to enable upper-layer agents and use the heuristic algorithm to find the optimal switching-pairs for

the studied loops.

4. Move upwards to enable upper-layer agents and use the heuristic algorithm to find the optimal switching-pairs for

the studied loops.

5. Move upwards until finishing studying all upper layers. 5. Move upwards until finishing studying all upper layers.

t = t+1t = t+1

t>24?t>24?NO

YES

Wait u

ntil n

ext o

peratio

n

time w

indow

arrives.

Wait u

ntil n

ext o

peratio

n

time w

indow

arrives.

Figure 6.3 The flowchart of the proposed methodology.

(2) Apply Multi-Agent Framework

Page 146: SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK ...read.pudn.com/downloads799/sourcecode/math/3153436/Thesis_fin… · SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK RECONFIGURATION

134

An intelligent agent consisting of a data unit, a computation unit and a decision unit is

assigned to each subsystem, and it is used to solve the sub-problem for the assigned

subsystem and exchange information with other agents.

Because of the possible existence of DG units in the lowest-layer subsystems, the

lowest-layer agents should be capable to decide both optimal system topologies and

optimal DG outputs for their local systems, so the optimization problem for each lowest-

layer agent is formulated as (6.32) with refining all variables as those in its local

subsystem. Differently, all higher-layer agents only need to determine whether the

common tie-switches should be closed or not based on the decision plans solved in lower-

layer agents, so each embedded optimization problem is a pure reconfiguration problem,

and it is formulated as

min , ,

. . (6.16) ~ (6.21).

loss at the studied subsystem solved solvedJ P T

s t

S S PQ (6.33)

where, Sat the studied subsystem is the set of switch states to solve; Ssolved is the set of switch

states that are already solved at the lower-layer agents; PQsolved is the actual output power

of DG units determined at the lowest-layer agents.

(3) Solve Optimization Problems at the Lowest-Layer Agents

The optimization problems defined in lowest-layer agents are mixed-integer nonlinear

ones with both switch states and DG outputs as decision variables. According to the

discussions of three proposed methods in Chapter III, it is known that both the revised

GA and the hybrid algorithm are able to solve DG outputs by adding DG power into the

decision variables. However, it is also known that the revised GA has much better

accuracy and computational speed than the hybrid algorithm. Thus, the revised GA is

Page 147: SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK ...read.pudn.com/downloads799/sourcecode/math/3153436/Thesis_fin… · SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK RECONFIGURATION

135

chosen to solve the mixed-integer nonlinear optimization problem (6.32) defined in

lowest-layer agents. Because of the existence of DG power in the decision variables,

some changes are made in the algorithm.

OS1~OST P1a Q1a P1b Q1b P1c Q1c ... PK,a QK,a PK,b QK,b PK,c QK,c

Figure 6.4 The genes included in each chromosome.

Each chromosome in a population is defined as Fig. 6.4 and it has T+6K genes in total:

(a) The first T genes represent the opened switches.

(b) The following 6K genes are the active and reactive power generated from K DG

units.

It is assumed that there are both half chance to apply the cross-over and mutation

operators. The cross-over operator randomly selects two chromosomes (A, B) and then

exchanges their information to create two new chromosomes (C, D) following the rule

based on one-point technique and arithmetical operator:

(a) Select a gene i from T+6K genes randomly.

(b) If i ≤ T, 𝐶(1: 𝑖) = 𝐴(1: 𝑖), 𝐶(𝑖 + 1: 𝑇) = 𝐵(𝑖 + 1: 𝑇) , and 𝐶(𝑇 + 1: 𝑇 + 6𝐾) =

0.2 ∙ 𝐴(𝑇 + 1: 𝑇 + 6𝐾) + 0.8 ∙ 𝐵(𝑇 + 1: 𝑇 + 6𝐾).

(c) If i >T, 𝐶(1: 𝑇) = 𝐴(1: 𝑇), 𝐶(𝑇 + 1: 𝑖) = 0.8 ∙ 𝐴(𝑇 + 1: 𝑖) + 0.2 ∙ 𝐵(𝑇 + 1: 𝑖) ,

and𝐶(𝑖 + 1: 𝑇 + 6𝐾) = 0.2 ∙ 𝐴(𝑖 + 1: 𝑇 + 6𝐾) + 0.8 ∙ 𝐵(𝑖 + 1: 𝑇 + 6𝐾).

The other chromosome D is obtained in the opposite way to C by reversing A and B in

the above equations.

The mutation operator randomly changes one gene in the selected chromosome to

introduce new information into the offspring. If the selected gene denotes an opened

Page 148: SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK ...read.pudn.com/downloads799/sourcecode/math/3153436/Thesis_fin… · SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK RECONFIGURATION

136

switch, it is replaced by another switch in the corresponding loop; otherwise, it is

replaced by another feasible value within the capacity of DG units.

Before evaluating fitness values of the new population, all repeated chromosomes are

deleted and the feasibility of each offspring is evaluated by checking system structure

constraints and voltage/current constraints in turn. Then, the fitness values of all feasible

offsprings are computed and the elitism is used to select the best population.

At last, the optimal topologies of all lowest-layer subsystems and the optimal outputs

of DG units are solved. Coordination between agents is conducted when necessary, as

explained in Chapter IV. Then, the final results are transferred into upper-layer agents to

activate the computations in them.

(4) Enable the Upper-Layer Agents and Move Upwards

With switch states and DG outputs solved in lower-layer agents known, the proposed

heuristic algorithm based on branch-exchange and single-loop optimization is used to

solve the optimal topologies of upper-layer subsystems. Keep on until all layers are

studied. Then the optimal topology of the entire distribution system and the actual output

power of all DG units are both acquired for the present time window based on the timely

system data.

Thus, distribution feeders are reconfigured and the operations of DG units are

regulated optimally, and such status will be kept same until the next time window arrives

when the operation plan for next period is re-evaluated.

Page 149: SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK ...read.pudn.com/downloads799/sourcecode/math/3153436/Thesis_fin… · SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK RECONFIGURATION

137

6.4 Case Study

The proposed methodology to plan and operate DG units and reconfigure unbalanced

distribution feeders are tested on two cases including a 25-bus unbalanced distribution

system and the revised IEEE 123-bus test system.

6.4.1 Gaussian-Mixture Load Modeling

Because time-variant loads could affect the result of sensitive matrix, Monte Carlo

simulation is carried out to determine the most sensitive buses based on a great quantity

of historical load data. A lot of statistical methods have been given to model the loads,

such as Gaussian distribution [98], Weibull distribution [99], Beta distribution [100], etc.

Gaussian-Mixture Model (GMM) [101] is used to model the load because it can fairly

represent different types of load distributions as a convex combination of several normal

distributions with respective means and variances. The probability density function (pdf)

of a GMM is given by

∙N (μi, σi) (6.34)

where, AM is the amount of mixture components, and wi is the proportion of each

component.

With 2013 full-year load data of four different areas given in [102], four different

GMMs of load pdfs with three mixture components are obtained as Fig. 6.5 and the

critical parameters are also marked. In order to apply the GMM to different test systems,

the horizontal axis is given as the per unit values.

1

AM

i

if z w

Page 150: SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK ...read.pudn.com/downloads799/sourcecode/math/3153436/Thesis_fin… · SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK RECONFIGURATION

138

Figure 6.5 GMM approximations of load pdfs.

6.4.2 Case I: 25-Bus Unbalanced Distribution System

Fig. 6.6 shows the diagram of the 25-bus distribution system [103]. Both line

impedance and load distribution are unbalanced. Total loads are 1073.3 kW and 792 kVar

(phase-A), 1083.3 kW and 801 kVar (phase-B), and 1083.3 kW and 800 kVar (phase-C).

The initial power losses at three phases are 450.36 kW and the minimum voltage is 0.93

pu.

12

3

4

5

6

718

2312

814139

10

11 17

1516

22

19 2120 24

25

TS-1

TS-3TS-2

Figure 6.6 Single-line diagram of the 25-bus unbalanced distribution system.

(1) Optimal Planning of DG Units

Each load is applied with a GMM randomly, so the actual load power is the initial

value multiplied with the per unit value generated by GMM. Monte Carlo simulation is

Page 151: SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK ...read.pudn.com/downloads799/sourcecode/math/3153436/Thesis_fin… · SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK RECONFIGURATION

139

conducted and it is shown that buses 11, 17, 10, 9, 15, 16, 14 and 8 are always the eight

most sensitive buses for all 500 samples.

In order to prove the effectiveness of reducing power losses through installing DG

units at the most sensitive buses, the power loss of the initial system, the system with

eight DG units installed at the above eight buses respectively, the system with eight DG

units installed at the buses computed as [61] and the system with eight DG units installed

at other buses randomly chosen are compared and the results are given in Fig. 6.7. If the

sensitive buses are selected according to the method given in [61], the results are buses 2,

3, 4, 6, 7, 10, 18, 23. Each DG unit is assumed to be three-phase balanced and each phase

is 40 kW. It clearly shows that the power losses are minimal if eight DG units are

installed at the sensitive buses selected using the proposed approach.

Figure 6.7 Power loss in the system with DG units installed at different locations.

After the locations of DG units are confirmed, the optimal capacity of each DG unit

could be solved. Three scenarios are studied: (1) only one DG unit is installed at the most

sensitive bus 11; (2) two DG units are installed at buses 11 and 17 respectively; (3) three

DG units are installed at buses 11, 17 and 10 respectively. The limits of DG sizes are also

500 kW/ 500kVA for each phase. The proposed quasi-Newton algorithm converges

quickly after 5~20 iterations for different scenarios. The optimal capacities of DG units

for three scenarios are given in Table 6.1. Besides, the values of some key performance

indicators (KPI) are also given.

Page 152: SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK ...read.pudn.com/downloads799/sourcecode/math/3153436/Thesis_fin… · SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK RECONFIGURATION

140

It shows that the optimal capacity of DG units could be solve successfully with all

system constraints solved. The integration of DG units could help reduce power loss,

boost voltages and reduce voltage unbalance. The results of scenarios II and III are much

better than those of scenario I, so it is indicated that the integration of several dispersed

DG units of small capacity is more helpful than the integration of one DG unit of large

capacity. Because the integration of two DG units has already improved the system

performance greatly, the addition of the 3rd

DG unit does not help much, as the

comparison results between scenarios II and III. Thus, two DG units are determined to be

installed at buses 11 and 17 finally.

Table 6.1 Optimal Capacity of DG Units for Three Scenarios

Location

Optimal Capacity

Phase-A Phase-B Phase-C

P

(kW)

Q

(kVar)

P

(kW)

Q

(kVar)

P

(kW)

Q

(kVar)

Scenario I

Bus-11 382.96 388.21 437.35 351.91 273.35 157.17

KPI Min voltage at three phases = [0.966,0.965,0.956 pu];

Power Loss=225.38 kW; Max Voltage Unbalance=2.389%

Scenario II

Bus-11 214.0 155.79 213.26 163.42 213.72 162.34

Bus-17 212.8 154.98 212.04 162.37 212.86 161.5

KPI Min voltage at three phases = [0.964,0.965,0.969 pu];

Power Loss=195.5 kW; Max Voltage Unbalance=0.405%

Scenario III

Bus-11 138.62 104.09 148.46 105.5 147.8 106.97

Bus-17 135.86 102.24 145.69 103.1 146.0 105.11

Bus-10 151.92 115.82 160.53 115.5 161.11 115.99

KPI Min voltage at three phases = [0.964,0.965,0.969 pu];

Power Loss =188.34 kW, Max Voltage Unbalance=0.396 %

(2) Optimal Hourly Operation

The decomposed subsystems and hierarchical reconfiguration agents for the 25-bus

Page 153: SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK ...read.pudn.com/downloads799/sourcecode/math/3153436/Thesis_fin… · SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK RECONFIGURATION

141

unbalanced test system are given in Fig. 6.8. System-1 and System-2 are two lowest-layer

decomposed subsystems that include all buses and loads. Two DG units are both at

System-2, so the optimization problem in Agent-2 is defined as (6.32) while the

optimization problem in Agent-1 can be simplified as a pure reconfiguration problem,

which is defined as (6.33).

Buses 1~5, 18~25

System-1

(Tie-switches 1)

Layer-1

Layer-0

Buses 6~17,

System-2

(Tie-switch 3)

TS-2

25- Bus Distribution System

Agent-1

Reconfigure System-1

Agent-2

Reconfigure System-2

Agent-3

Whether close TS-2?

1 2

3

Decomposed Subsystems Hierarchical Computation Agents

Figure 6.8 Decomposed systems and hierarchical reconfiguration agents for the 25-bus system.

Figure 6.9 Four groups of load shapes.

Fig. 6.9 shows four groups of 24-hour load curves using as real-time load data for both

25-bus test system and 123-bus test system. The operating period is set to be 1 h and the

starting point is at 0:00. The optimal switching results are given in Table 6.2, and the

actual outputs of DG units determined for 24 hours are also given in Fig. 6.10. Total

power losses in the system after hourly reconfiguration are also shown in Fig. 6.11.

Table 6.2 Simulation Results of The Optimal Switching Plan

Time

Window

Opened

Switches

Time

Window

Opened

Switches

Time

Window

Opened

Switches

Initial 25~27 8~9 h 17, 3, 6 17~18 h 17, 3, 6

0~1 h 17, 2, 6 9~10 h 17, 3, 6 18~19 h 17, 3, 6

1~ 2 h 17, 2, 6 10~11 h 17, 24, 14 19~20 h 17, 3, 6

2~3 h 17, 2, 6 11~12 h 17, 3, 6 20~21 h 17, 3, 6

0.3

0.5

0.7

0.9

1.1

0:0

01

h2

h3

h4

h5

h6

h7

h8

h9

h1

0 h

11

h1

2 h

13

h1

4 h

15

h1

6 h

17

h1

8 h

19

h2

0 h

21

h2

2 h

23

h

p.u

.

Time

Shape-1

Shape-2

Shape-3

Shape-4

Page 154: SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK ...read.pudn.com/downloads799/sourcecode/math/3153436/Thesis_fin… · SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK RECONFIGURATION

142

3~4 h 17, 2, 6 12~13 h 17, 24, 14 21~22 h 17, 3, 6

4~5 h 17, 2, 6 13~14 h 17, 3, 6 22~23 h 17, 24, 13

5~6 h 17, 2, 6 14~15 h 17, 24, 27 23~24 h 17, 3, 6

6~7 h 17, 2, 6 15~16 h 17, 24, 14

7~8 h 17, 24, 14 16~17 h 17, 3, 6

Figure 6.10 Optimal outputs of two DG units in the 25-bus system for 24 hours.

200

205

210

215

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24

kW

Hour / h

Active Output Power of the DG Unit at Bus-11

Pa

Pb

Pc

40

60

80

100

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24

kW

Hour / h

Reactive Output Power of the DG Unit at Bus-11

Qa

Qb

Qc

192

202

212

1 2 3 4 5 6 7 8 9 101112131415161718192021222324

kW

Hour / h

Active Output Power of the DG Unit at Bus-17

Pa

Pb

Pc

30

50

70

90

110

1 2 3 4 5 6 7 8 9 101112131415161718192021222324

kV

ar

Hour / h

Reactive Output Power of the DG Unit at Bus-17

Qa

Qb

Qc

Page 155: SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK ...read.pudn.com/downloads799/sourcecode/math/3153436/Thesis_fin… · SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK RECONFIGURATION

143

Figure 6.11 System power losses for different scenarios during 24 hours.

6.4.3 Case II: Revised IEEE 123-Bus Unbalanced Distribution System

Fig. 6.12 shows the configurations of the revised IEEE 123-bus system with four

initially opened tie-switches. Compared to the benchmark IEEE 123-bus test system

given in [104], all voltage regulators and transformers are deleted in order to fully

address the performance of the proposed study on revising voltage profiles and reducing

power losses. Total loads are 1420 kW and 775 kVar at phase a, 915 kW and 515 kVar at

phase b, and 1155 kW and 635 kVar at phase c. System power loss is 129.3 kW and the

minimum voltage is 0.895 p.u.. The maximum voltage unbalance is 3.57%.

149 1 7 8

13

152 52

18

23

25

21

28

2930 250

13535

42

44

40

4748 50

49

51 151TS-3

2

3

45 6

12

11

10

149

34

15

1617

20 19

22

24

27 26

31

32

33

41

43

45 46

3637 38 39

53 54 5556

57 60

160

6762

64

65

63

66

97

101

105

197

108

300

98 99 100 450

86

76

87

72

93 9189

95

77

78 79

82

81

80

83

61

TS-2

TS-1

59 58

69 70 7168

73 74 75

84 85

102 103 104

106 107

109 110 112 113 114

111

88909294

96

TS-4

Three-Phase Line

Single-Phase or

Two-Phase Line

Figure 6.12 The configuration of the revised IEEE 123-bus test system.

(1) Optimal Planning of DG Units

0

10

20

30

40

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24Po

wer

Lo

ss /

kW

Hour / h

Page 156: SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK ...read.pudn.com/downloads799/sourcecode/math/3153436/Thesis_fin… · SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK RECONFIGURATION

144

Similarly, each load is applied with a GMM randomly, so the actual load power is the

initial value multiplied with the per unit value generated by GMM. Monte Carlo

simulation is conducted and twenty most sensitive buses are in the order of buses 95, 93,

91, 89, 83, 82, 87, 81, 80, 86, 79, 78, 77, 76, 108, 300, 105, 72, 100, 450, based on 500

samples. It shows that all these sensitive buses gather at the downstream of the network,

and several consecutive sensitive buses are usually at the same feeder. If multiple DG

units need be installed, in order to take better use of DG units to help serve the loads at

different feeders, the most sensitive buses at different feeders are selected as the locations.

Thus, it is noted that the sensitivity analysis could not guarantee the selected locations are

really optimal when installing multiple DG units, but it could give good choices to install

DG units so that the power loss reduction could be larger.

After selecting candidate locations for installing DG units, the optimal capacity of each

DG unit will be solved. Three scenarios are studied: (1) only one DG unit is installed at

the most sensitive bus 95; (2) two DG units are installed at buses 95 and 83 respectively;

(3) three DG units are installed at buses 95, 83 and 108 respectively. The optimal

capacities of DG units for three scenarios are given in Table 6.3, and the values of KPIs

are also included.

It shows that the optimal capacity of DG units could be solved successfully with all

system constraints satisfied. The integration of DG units could help reduce power loss,

boost voltage and reduce voltage unbalance. When a DG unit is connecting at bus-95,

more than 300 kW need be generated from phase-A to keep all KPIs within limits.

Instead, when multiple DG units are integrated, the required sizes become much smaller,

Page 157: SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK ...read.pudn.com/downloads799/sourcecode/math/3153436/Thesis_fin… · SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK RECONFIGURATION

145

and the KPIs are also improved. As a result, it is decided to install three DG units at buses

95, 83 and 108, and their sizes are designed as the results in scenario III.

Table 6.3 Optimal Capacity of DG Units for Three Scenarios

Location

Optimal Capacity

Phase-A Phase-B Phase-C

P

(kW)

Q

(kVar)

P

(kW)

Q

(kVar)

P

(kW)

Q

(kVar)

Scenario I

Bus-95 327.36 321.68 189.55 130.58 188.88 307.77

KPI

Power Loss=73.49 kW,

Min voltage at three phases = [0.95,0.958, 0.956 pu],

Max voltage unbalance=2.29%, Max loading = 97%.

Scenario II

Bus-95 175.06 164.72 87.67 59.8 101.41 175.55

Bus-83 175.15 161.75 86.46 60.25 103.78 178.89

KPI

Power loss = 67.79 kW,

Min voltage at three phases =[0.951, 0.95, 0.964 pu],

Max voltage unbalance=2.54%, Max loading = 95%.

Scenario III

Bus-95 112.77 125.5 107.33 91.71 89.8 98.26

Bus-83 112.77 125.45 107.38 91.74 89.75 98.24

Bus-108 115.71 131.73 108.78 89.97 87.22 97.73

KPI

Power loss = 56.02 kW,

Min voltage at three phases = [0.953, 0.988, 0.95 pu], Max

voltage unbalance =2.29%, Max loading = 93%.

(2) Optimal Hourly Operation

If closing tie-switches 1~4, four loops loop1~loop4 are formed. Based on the proposed

cut-vertex set concept, the graph of 123-bus test system is drawn as Fig. 6.13, and the

corresponding decomposed structure and the hierarchical arrangement of computational

agents are given in Fig. 6.14. System-1 and System-2 are two lowest-layer subsystems

and all three DG units are locating at System-2.

Page 158: SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK ...read.pudn.com/downloads799/sourcecode/math/3153436/Thesis_fin… · SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK RECONFIGURATION

146

Figure 6.13 The graph of 123-bus system.

Figure 6.14 Decomposed systems and hierarchical reconfiguration agents for the 123-bus system.

The optimal switching results are given in Table 6.4, and the actual outputs of DG

units determined for 24 hours are also given in Fig. 6.15. Fig. 6.16 shows the results of

power losses for the system with the implementation of the proposed optimal operation,

and they are compared with the results of the system without reconfiguration or any DGs

(Scenario I) and the results of the system without reconfiguration but with uncontrolled

DGs that are always generating maximum capacity (Scenario II). It proves that the

integration of DG units by following the optimal planning procedures can help reduce

power losses by around 50%, and further, the proposed optimal operation strategy

consisting of network reconfiguration and optimal curtailing DG power can get much

more power loss reduction, with final power losses lower than 20 kW.

Besides, voltage profiles and line loading levels of the system with the implementation

of optimal operation are checked: all voltages are within 5% deviations from the nominal

value, and the maximum voltage unbalances and maximum line loading levels for 24

hours are concluded as Fig. 6.17. After conducting the proposed optimal operation, the

Loop

2

Loop

1Loop

4

Loop

3

Cut-Vertex Set

T

TT

(Tie-switches

1 and 2)

Layer-1

Layer-0

System-2TS-4

123- Bus Distribution System

Agent-1

Reconfigure System-1

Agent-2

Reconfigure System-2

Agent-3

Whether close TS-4?

1 2

3

Decomposed Subsystems Hierarchical Computation Agents

Buses 53~114, 160, 197, 300, 450

System-1

Buses 149, 1~52, 135, 151,

152, 250

(Tie-switch 3)

Page 159: SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK ...read.pudn.com/downloads799/sourcecode/math/3153436/Thesis_fin… · SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK RECONFIGURATION

147

voltage unbalance level has reduced to be lower than 1.5% and all lines are loaded less

than 50%.

Besides, with the application of the hierarchical decentralized approach, the

computation time for one-time operation is 10.1 seconds, which is about half of the time

cost by using the centralized approach.

Table 6.4 Simulation Results of The Optimal Switching Plan

Time Window Opened Switches Time Window Opened Switches

Initial 123~126 12~13 h 57, 124, 21, 121

0~1 h 60, 124, 21, 121 13~ 14 h 57, 124, 21, 126

1~ 2 h 57, 124, 21, 126 14~15 h 60, 124, 21, 121

2~3 h 60, 124, 21, 121 15~16 h 57, 124, 21, 126

3~4 h 57, 124, 21, 126 16~17 h 60, 124, 21, 121

4~5 h 60, 124, 21, 121 17~18 h 57, 124, 21, 126

5~6 h 60, 124, 21, 126 18~19 h 57, 124, 21, 121

6~7 h 60, 124, 21, 121 19~20 h 60, 124, 21, 126

7~8 h 60, 124, 21, 126 20~21 h 60, 124, 21, 121

8~9 h 60, 124, 21, 121 21~22 h 57, 124, 21, 126

9~10 h 57, 124, 21, 126 22~23 h 60, 124, 21, 121

10~11 h 60, 124, 21, 121 23~24 h 60, 124, 21, 126

11~12 h 60, 124, 21, 126

60

80

100

120

1 3 5 7 9 11 13 15 17 19 21 23Ou

tpu

t P

ow

er /

kW

(kV

ar)

Hour / h

DG Unit at Bus-83

Pa

Qa

Pb

Qb

Pc

Qc

60

80

100

120

140

1 3 5 7 9 11 13 15 17 19 21 23

Ou

tpu

t P

ow

er /

kW

(kV

ar)

Hour / h

DG Unit at Bus-95 Pa

Qa

Pb

Qb

Pc

Qc

Page 160: SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK ...read.pudn.com/downloads799/sourcecode/math/3153436/Thesis_fin… · SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK RECONFIGURATION

148

Figure 6.15 The optimal outputs of three DG units in the revised 123-bus system for 24 hours.

Figure 6.16 System power losses for different scenarios during 24 hours.

Figure 6.17 Maximum voltage unbalance and line loading level in the revised 123-bus system during

24 hours.

60

80

100

120

140

1 3 5 7 9 11 13 15 17 19 21 23

Ou

tpu

t P

ow

er /

kW

(kV

ar)

Hour / h

DG Unit at Bus-108

Pa

Qa

Pb

Qb

Pc

Qc

0

20

40

60

80

100

120

1 3 5 7 9 11 13 15 17 19 21 23

Po

wer

Lo

ss /

kW

Hour / h

Optimal

Scenario I

Scenario II

0

0.5

1

1.5

1 3 5 7 9 11 13 15 17 19 21 23

%

Max Voltage Unbalance

0

25

50

1 3 5 7 9 11 13 15 17 19 21 23

%

Hour / h

Max Line Loading

Page 161: SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK ...read.pudn.com/downloads799/sourcecode/math/3153436/Thesis_fin… · SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK RECONFIGURATION

149

Chapter 7 Conclusions and Future Work

This dissertation makes contributions to two important topics in smart distribution

automation including network reconfiguration and energy management. Network

reconfiguration is realized by changing the status of sectionalizing switches (normally

closed) and tie-switches (normally open), and can be used to reduce power losses by

transferring loads from heavily loaded feeders to lightly loaded feeders without violating

system security and stability constraints, and can also be used to restore loads in response

to problems that have occurred in the system. Energy management in the distribution

system aims at controlling and coordinating the operations of multiple distributed

generation units, as well as dispatching DG energy outputs in an optimal manner.

The conclusions of the research work reported in this dissertation are summarized as

below.

(1) Network reconfiguration is an optimal decision to determine which network switches

should be closed or opened so that system operations can be optimized. This problem

can be formulated as a mixed-integer, nonlinear, constrained optimization problem

where the states of switches are the only decision variables. Based on the

open/closed status, three different states including 0, 1 and -1 are defined for each

Page 162: SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK ...read.pudn.com/downloads799/sourcecode/math/3153436/Thesis_fin… · SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK RECONFIGURATION

150

maneuverable switch. Accordingly, system power flow equations can be represented

as a function these of switch states.

(2) Three new methods for reconfiguring distribution systems are proposed in Chapter

III, including the heuristic algorithm based on branch-exchange and single-loop

optimization, the hybrid method based on OPF and heuristic correction, and the

revised genetic algorithm. Each method can solve the reconfiguration problem

successfully and system losses can be reduced greatly. Because on the approach used

for each method, the performances of these three methods differ considerably. Both

the heuristic algorithm and the hybrid algorithm could not guarantee globally optimal

solutions, and the revised GA can obtain the optimal solution after enough

generations. The heuristic algorithm always has the best computational efficiency,

around several seconds to tens of seconds, so it is the best choice for on-line

operation, especially with the development of smart grid technology with more

complicated, stochastic and dynamic behaviors.

(3) A hierarchical, decentralized method for reconfiguring distribution feeders is

proposed in Chapter IV, and it is different from all previous methods given in the

literature. The proposed hierarchical decentralized network reconfiguration method

takes advantage of network decomposition and a multi-agent architecture to obtain

the optimal configuration, and the computation time for obtaining the near-optimal

configuration can be greatly reduced. Moreover, although multiple agents are

deployed, the necessary information exchange among them is limited to switch states

in their own subsystems, so the burden of communication and information transfer is

quite reasonable.

Page 163: SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK ...read.pudn.com/downloads799/sourcecode/math/3153436/Thesis_fin… · SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK RECONFIGURATION

151

A demonstration system is built using Matlab/Simulink, which is composed of the

distribution system and the multiple agents that are used to reconfigure the system

using the decentralized approach. Simulation results clearly demonstrate that the

hierarchical decentralized reconfiguration approach can converge to a good (near-

optimal) solution with greatly reduced computational time as compared with other

methods. Thus, this hierarchical decentralized approach is a promising option with

reasonable trade-offs between efficiency and optimality in view of an increasing

emphasis on implementing real-time distribution system automation.

The terminology of “dynamic network reconfiguration” is used to address

reconfiguring the distribution network over varying time windows based on real-time

system data. A dynamic network reconfiguration strategy is proposed, and a time-

ahead planning technique is used to detect faults or changes in generations and loads

so as to re-evaluate the reconfiguration problem. Simulation results have shown that

the near-optimal topology for each operating window is successfully obtained, and

total energy losses are greatly reduced after reconfiguration. It is also observed that

the implementation of time-ahead planning can help achieve more energy loss

reductions. In addition, the reconfiguration results for the scenario when faults occur

are also given.

The application of multi-agents for solving the decentralized optimization

problems involves activating lowest-layer agents in response to any changes that

occur in an operating window. Computations in the upper-layer agents are not

necessarily needed providing a much faster response to time-varying loads and DGs,

Page 164: SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK ...read.pudn.com/downloads799/sourcecode/math/3153436/Thesis_fin… · SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK RECONFIGURATION

152

as well as contingencies and disturbances. This feature is significant for long-term

operations, and greatly enhances the contributions of the proposed approach.

(4) Detailed dynamic modeling of multiple DG units including wind turbine, micro-

turbine, PV cells, fuel cells and supercapacitor energy storage are studied in Chapter

V, and both grid-connected and islanded control strategies are also studied for short-

term transient simulations. Both steady state and dynamic behaviors of the system

are analyzed according to the simulations. State-space models of both grid-

connected and islanded systems are given, and small-signal stability based on the

proposed state-space model is analyzed.

At steady state, all distributed generation units operate stably and provide power

for the loads. These units help support voltage (mitigate voltage sag) and ensure

local loads have sufficient power. Wind speed fluctuations induce similar DFIG

transients, however the pitch angle control system adjusts the pitch angle to extract

maximum wind power if wind speed is less than the nominal value and limits the

output power to protect the device if the wind speed is larger than the nominal value.

Changes in solar irradiance cause PV generation to change, but the PV system tracks

the maximum power point for each condition. When PV and fuel cell generation are

insufficient to meet the load demand, the supercapacitor will discharge to make up

the difference. As a result, the supercapacitor energy storage system helps to

maintain DC bus voltage during the transients and the AC grid is unaffected by DC

microgrid disturbances; overall stability of the system improved.

The electromagnetic simulation and the development of primary (reactive) control

systems for distributed generation systems or microgrids are critical but very

Page 165: SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK ...read.pudn.com/downloads799/sourcecode/math/3153436/Thesis_fin… · SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK RECONFIGURATION

153

challenging. This work provides a good starting point for understanding the

behaviors of distributed generation units during both grid-connected and islanded

operations, and is also provides a good foundation for developing higher-level

energy management strategy for the entire distribution system with multiple DG

units.

(5) Distribution systems are generally unbalanced due to non-uniform load distribution

and nonsymmetrical conductor spacing on three-phase lines, this it essential to study

the reconfiguration problem on unbalanced distribution networks. Network

reconfiguration studies are carried out on unbalanced distribution systems without

the simplification of single-phase equivalents. A novel sensitivity method is

proposed to determine the optimal locations of DG units, and the capacities of

installed DG units are obtained in order to minimize system power losses under the

initial system structure. A penalty method is used to change the nonlinear

programming problem into an unconstrained optimization problem, and the

minimum is determined using the proposed quasi-Newton method. During real-time

operation, both system topology and actual DG outputs are regulated using the

revised hierarchical decentralized approach, in which the heuristic algorithm and

genetic algorithm are cooperating to solve the reconfiguration problem and manage

DG outputs simultaneously. Simulation results of the revised IEEE 123-bus test

system have shown the effectiveness and efficiency of the proposed approaches for

planning and operation of DGs and reconfiguring the distribution network.

A comprehensive study on smart distribution automation, especially on network

reconfiguration and energy management has been presented in this dissertation.

Page 166: SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK ...read.pudn.com/downloads799/sourcecode/math/3153436/Thesis_fin… · SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK RECONFIGURATION

154

Distribution network management, optimal operation and energy management of DGs are

two important features in future smart distribution systems. Distributed generation

systems can work in conjunction with the grid with appropriate controls. Timely network

reconfiguration is conducted based on information from the grid and integrated DGs, and

corresponding decisions are made and sent back to the grid and DGs. The operation of

DGs and the grid will be improved based on the decisions that are implemented, where

network reconfiguration and DG energy management provide a closed-loop feedback

system as illustrated as Fig. 7.1, where each of them actually affects and plays an

important role with the other.

Figure 7.1 The conceived framework.

It is expected that the future distribution system would evolve into such a system. All

the studies included in this dissertation have paved the way for future research.

Additional efforts will be needed in order to implement the results of this dissertation in

Page 167: SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK ...read.pudn.com/downloads799/sourcecode/math/3153436/Thesis_fin… · SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK RECONFIGURATION

155

practical utility applications, and the following research topics will be of great interest in

achieving this goal.

(1) HILS and Hardware Test: The proposed hierarchical decentralized approach is tested

using simulations instead of a real hardware test bed. Before applying a new

approach to real utility systems, it is necessary to test it using hardware-in-the loop

simulation (HILS) and a hardware demo system. A lab-scale smart grid

demonstration system is being built in Case Western Reserve University with the

support of Rockwell Automation, and some details are provided in [105] and [106].

A new agent-based open source tool, VOLLTRON [107], has been developed by

Pacific Northwest National Laboratory, and this tool provides a software platform

and agent execution environment that fulfills security requirements. It can be used to

fulfill the essential requirements of resource management and security for agent

operation in smart grids. All these have paved the way for future work on HILS and

hardware testing.

(2) Microgrid: Distributed generation and microgrids have been important parts of

modern distribution grids. In the study presented in this dissertation, the integration

of microgrids can help improve system performance as a static energy resource, and

this is the case assumed in all reconfiguration studies. Future studies will include the

dynamics of microgrids into the reconfiguration problem.

(3) Protection: Reconfiguring the network topology may bring a lot of issues into the

existing protection system, and may require changing the relay settings. Some

studies related with protection systems were discussed in two early papers [108] and

[109] and although a large number of reconfiguration approaches were proposed in

Page 168: SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK ...read.pudn.com/downloads799/sourcecode/math/3153436/Thesis_fin… · SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK RECONFIGURATION

156

the past 30 years, almost all these studies either neglect the impacts on the protection

system or assume that the initial settings of the protection system are still appropriate

after changing system topology. Hence, future research is needed to evaluate and

determine the necessary protocols required for smart grid technologies where there

are changes in network topology, as well as identify any potential limitations.

(4) Transient Study: Network reconfiguration studies are generally considered as steady-

state studies without studying the transients that are induced when opening/closing

network switches. Although the switching operation can cause transient stability

concerns, similar studies conducted in transmission systems have shown that

transmission switching could be a possible control mechanism to alleviate transient

stability issues [110], [111]. Future research is needed to determine whether more

frequent switching actions in distribution network will cause transient stability

concerns.

Page 169: SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK ...read.pudn.com/downloads799/sourcecode/math/3153436/Thesis_fin… · SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK RECONFIGURATION

157

Reference

[1] D. Haughton and G. T. Heydt, “Smart distribution system design: Automatic reconfiguration for

improved reliability,” in IEEE PES General Meeting, 2010, pp. 1–8.

[2] “http://www.eia.gov/totalenergy/data/annual/index.cfm.” .

[3] N. R. Friedman, “Distributed energy resources interconnection systems: Technology review and

research needs,” National Renewable Energy Laboratory, 2002. [Online]. Available:

http://www.nrel.gov/docs/fy02osti/32459.pdf.

[4] REN21, “Renewables 2014 Global Status Report,” Production, 2014. [Online]. Available:

http://www.ren21.net/ren21activities/globalstatusreport.aspx.

[5] “Electric Power Monthly,” 2013. [Online]. Available: http://www.eia.gov/electricity/monthly/.

[6] I. EG&G Technical Services, Fuel Cell Handbook, vol. 7 Edition. 2004, pp. 1–352.

[7] O. Yamamoto, “Solid oxide fuel cells: fundamental aspects and prospects,” Electrochim. Acta, vol.

45, no. 15–16, pp. 2423–2435, May 2000.

[8] H. Wei, W. Ziping, N. Ming, Z. Jianhua, G. Yuanbo, and W. Chong, “Dynamic modelling and

simulation of microturbine generation system for the parallel operation of microgrid,” in 1st

International Conference on Sustainable Power Generation and Supply, SUPERGEN ’09, 2009.

[9] R. H. Staunton and B. Ozpineci, “Microturbine power conversion technology review,” Oak Ridge

National Laboratory, 2003. [Online]. Available:

http://web.ornl.gov/~webworks/cppr/y2003/rpt/117904.pdf.

[10] K. Clement-Nyns, E. Haesen, and J. Driesen, “The Impact of Charging Plug-In Hybrid Electric

Vehicles on a Residential Distribution Grid,” IEEE Trans. Power Syst., vol. 25, no. 1, pp. 371–380,

Feb. 2010.

[11] L. Pieltain Fernandez, T. Gomez San Roman, R. Cossent, C. Mateo Domingo, and P. Frias,

“Assessment of the Impact of Plug-in Electric Vehicles on Distribution Networks,” IEEE Trans.

Power Syst., vol. 26, no. 1, pp. 206–213, Feb. 2011.

Page 170: SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK ...read.pudn.com/downloads799/sourcecode/math/3153436/Thesis_fin… · SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK RECONFIGURATION

158

[12] A. Maitra, J. Taylor, D. Brooks, M. Alexander, and M. Duvall, “Integrating plug-in-electric

vehicles with the distribution system,” in Electricity Distribution - Part 1, 2009. CIRED 2009. 20th

International Conference and Exhibition on, 2009, pp. 1–5.

[13] M. Duvall, E. Knipping, M. Alexander, L. Tonachel, and C. Clark, “Environmental Assessment of

Plug-In Hybrid Electric Vehicles. Volume 1: Nationwide Greenhouse Gas Emissions,” Electr.

Power Res. Institute, Palo Alto, CA, vol. 1015325, 2007.

[14] J. Cobb, “Global Plug-in Car Sales Now Over 600,000,” 2014. [Online]. Available:

http://www.hybridcars.com/global-plug-in-car-sales-now-over-600000/.

[15] S. F. Bush, Smart Grid: Communication-Enabled Intelligence for the Electric Power Grid. Wiley-

IEEE Press, 2014, p. 570.

[16] J. G. Rolim and L. J. B. Machado, “A study of the use of corrective switching in transmission

systems,” IEEE Trans. Power Syst., vol. 14, no. 1, pp. 336–341, 1999.

[17] W. Shao and V. Vittal, “Corrective Switching Algorithm for Relieving Overloads and Voltage

Violations,” IEEE Trans. Power Syst., vol. 20, no. 4, pp. 1877–1885, Nov. 2005.

[18] K. W. Hedman, S. S. Oren, and R. P. O’Neill, “A review of transmission switching and network

topology optimization,” in 2011 IEEE Power and Energy Society General Meeting, 2011, pp. 1–7.

[19] E. B. Fisher, R. P. O’Neill, and M. C. Ferris, “Optimal Transmission Switching,” IEEE Trans.

Power Syst., vol. 23, no. 3, pp. 1346–1355, Aug. 2008.

[20] A. Merlin and H. Back, “Search for a minimal-loss operating spanning tree configuration in an

urban power distribution system,” in In Proc. 5th Power System Computation Conference (PSCC),

1975.

[21] D. Shirmohammadi and H. Hong, “Reconfiguration of electric distribution networks for resistive

line losses reduction,” IEEE Trans. Power Deliv., vol. 4, no. 2, pp. 1492–1498, Apr. 1989.

[22] S. Goswami and S. Basu, “A new algorithm for the reconfiguration of distribution feeders for loss

minimization,” IEEE Trans. Power Del., vol. 7, no. 3, pp. 1484–1491, 1999.

[23] T. E. McDermott, I. Drezga, and R. P. Broadwater, “A heuristic nonlinear constructive method for

distribution system reconfiguration,” IEEE Trans. Power Syst., vol. 14, no. 2, pp. 478–483, 1999.

[24] S. Civanlar, J. J. Grainger, H. Yin, and S. S. H. Lee, “Distribution feeder reconfiguration for loss

reduction,” IEEE Trans. Power Deliv., vol. 3, no. 3, pp. 1217–1223, Jul. 1988.

[25] M. E. Baran and F. F. Wu, “Network reconfiguration in distribution systems for loss reduction and

load balancing,” IEEE Trans. Power Deliv., vol. 4, no. 2, pp. 1401–1407, Apr. 1989.

[26] J. Y. Fan, L. Zhang, and J. D. McDonald, “Distribution network reconfiguration: Single loop

optimization,” IEEE Trans. Power Syst., vol. 11, pp. 1643–1647, 1996.

[27] F. V. Gomes, S. Carneiro, J. L. R. Pereira, M. P. Vinagre, P. A. N. Garcia, and L. R. Araujo, “A

New Heuristic Reconfiguration Algorithm for Large Distribution Systems,” IEEE Trans. Power

Syst., vol. 20, no. 3, pp. 1373–1378, Aug. 2005.

Page 171: SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK ...read.pudn.com/downloads799/sourcecode/math/3153436/Thesis_fin… · SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK RECONFIGURATION

159

[28] G. Raju and P. R. Bijwe, “An Efficient Algorithm for Minimum Loss Reconfiguration of

Distribution System Based on Sensitivity and Heuristics,” IEEE Trans. Power Syst., vol. 23, no. 3,

pp. 1280–1287, Aug. 2008.

[29] F. V. Gomes, S. Carneiro, J. L. R. Pereira, M. P. Vinagre, P. A. N. Garcia, and L. R. De Araujo, “A

New Distribution System Reconfiguration Approach Using Optimum Power Flow and Sensitivity

Analysis for Loss Reduction,” IEEE Trans. Power Syst., vol. 21, no. 4, pp. 1616–1623, Nov. 2006.

[30] H. P. Schmidt, N. Ida, N. Kagan, and J. C. Guaraldo, “Fast Reconfiguration of Distribution

Systems Considering Loss Minimization,” IEEE Trans. Power Syst., vol. 20, no. 3, pp. 1311–1319,

Aug. 2005.

[31] H.-D. Chiang and R. Jean-Jumeau, “Optimal network reconfigurations in distribution systems. I. A

new formulation and a solution methodology,” IEEE Trans. Power Deliv., vol. 5, no. 4, pp. 1902–

1909, 1990.

[32] H.-D. Chiang and R. Jean-Jumeau, “Optimal network reconfigurations in distribution systems. II.

Solution algorithms and numerical results,” IEEE Trans. Power Deliv., vol. 5, no. 3, pp. 1568–

1574, Jul. 1990.

[33] H.-C. Chang and C.-C. Kuo, “Network reconfiguration in distribution systems using simulated

annealing,” Electr. Power Syst. Res., vol. 29, no. 3, pp. 227–238, May 1994.

[34] C.-T. Su, C.-F. Chang, and J.-P. Chiou, “Distribution network reconfiguration for loss reduction by

ant colony search algorithm,” Electr. Power Syst. Res., vol. 75, no. 2–3, pp. 190–199, Aug. 2005.

[35] C.-F. Chang, “Reconfiguration and Capacitor Placement for Loss Reduction of Distribution

Systems by Ant Colony Search Algorithm,” IEEE Trans. Power Syst., vol. 23, no. 4, pp. 1747–

1755, Nov. 2008.

[36] J. Kennedy and R. Eberhart, “Particle swarm optimization,” in Proceedings of ICNN’95 -

International Conference on Neural Networks, 1995, vol. 4, pp. 1942–1948.

[37] H.-T. Yang, Y.-T. Tzeng, and M.-S. Tsai, “Loss-Minimized Distribution System Reconfiguration

by Using Improved Multi-agent Based Particle Swarm Optimization,” in 2010 Asia-Pacific Power

and Energy Engineering Conference, 2010, pp. 1–6.

[38] A. Swarnkar, N. Gupta, and K. Niazi, “Reconfiguration of radial distribution systems with fuzzy

multi-objective approach using adaptive particle swarm optimization,” Power Energy Soc. …, vol.

25, pp. 1734–1741, 2010.

[39] S. Sivanagaraju, J. V. Rao, and P. S. Raju, “Discrete Particle Swarm Optimization to Network

Reconfiguration for Loss Reduction and Load Balancing,” Electr. Power Components Syst., vol.

36, no. 5, pp. 513–524, Apr. 2008.

[40] A. Y. Abdelaziz, F. M. Mohammed, S. F. Mekhamer, and M. A. L. Badr, “Distribution Systems

Reconfiguration using a modified particle swarm optimization algorithm,” Electric Power Systems

Research, vol. 79. pp. 1521–1530, 2009.

[41] a. Y. Abdelaziz, F. M. Mohamed, S. F. Mekhamer, and M. a. L. Badr, “Distribution system

reconfiguration using a modified Tabu Search algorithm,” Electr. Power Syst. Res., vol. 80, no. 8,

pp. 943–953, Aug. 2010.

Page 172: SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK ...read.pudn.com/downloads799/sourcecode/math/3153436/Thesis_fin… · SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK RECONFIGURATION

160

[42] D. Zhang, Z. Fu, and L. Zhang, “An improved TS algorithm for loss-minimum reconfiguration in

large-scale distribution systems,” Electr. Power Syst. Res., vol. 77, no. 5–6, pp. 685–694, Apr.

2007.

[43] K. Nara, A. Shiose, M. Kitagawa, and T. Ishihara, “Implementation of genetic algorithm for

distribution systems loss minimum re-configuration,” IEEE Trans. Power Syst., vol. 7, no. 3, pp.

1044–1051, 1992.

[44] J. Z. Zhu, “Optimal reconfiguration of electrical distribution network using the refined genetic

algorithm,” Electr. Power Syst. Res., vol. 62, no. 1, pp. 37–42, May 2002.

[45] L. Lu, Q. Luo, J. Liu, and C. Long, “An Improved Particle Swarm Optimization for

Reconfiguration of Distribution Network,” 2008 Fourth Int. Conf. Nat. Comput., pp. 453–457,

2008.

[46] K. Prasad, R. Ranjan, N. C. Sahoo, and A. Chaturvedi, “Optimal Reconfiguration of Radial

Distribution Systems Using a Fuzzy Mutated Genetic Algorithm,” IEEE Trans. Power Deliv., vol.

20, no. 2, pp. 1211–1213, Apr. 2005.

[47] L. M. O. Queiroz and C. Lyra, “Adaptive Hybrid Genetic Algorithm for Technical Loss Reduction

in Distribution Networks Under Variable Demands,” IEEE Trans. Power Syst., vol. 24, no. 1, pp.

445–453, Feb. 2009.

[48] J. Mendoza, R. Lopez, D. Morales, E. Lopez, P. Dessante, and R. Moraga, “Minimal Loss

Reconfiguration Using Genetic Algorithms With Restricted Population and Addressed Operators:

Real Application,” IEEE Trans. Power Syst., vol. 21, no. 2, pp. 948–954, May 2006.

[49] H. D. De Macedo Braz and B. A. De Souza, “Distribution network reconfiguration using genetic

algorithms with sequential encoding: Subtractive and additive approaches,” IEEE Trans. Power

Syst., vol. 26, pp. 582–593, 2011.

[50] R. T. Ganesh Vulasala, Sivanagaraju Sirigiri, “Feeder Reconfiguration for Loss Reduction in

Unbalanced Distribution System Using Genetic Algorithm,” Int. J. Electr. Electron. Eng., vol. 3,

pp. 754–762, 2009.

[51] G. V. Loganathan, “A New Heuristic Optimization Algorithm: Harmony Search,” Simulation, vol.

76, no. 2, pp. 60–68, Feb. 2001.

[52] R. Srinivasa Rao, S. V. L. Narasimham, M. Ramalinga Raju, and A. Srinivasa Rao, “Optimal

network reconfiguration of large-scale distribution system using harmony search algorithm,” IEEE

Trans. Power Syst., vol. 26, pp. 1080–1088, 2011.

[53] E. RomeroRamos, A. GomezExposito, J. RiquelmeSantos, and F. LlorensIborra, “Path-Based

Distribution Network Modeling: Application to Reconfiguration for Loss Reduction,” IEEE Trans.

Power Syst., vol. 20, no. 2, pp. 556–564, May 2005.

[54] E. Romero-Ramos, J. Riquelme-Santos, and J. Reyes, “A simpler and exact mathematical model

for the computation of the minimal power losses tree,” Electr. Power Syst. Res., vol. 80, pp. 562–

571, 2010.

[55] H. M. Khodr, J. Martinez-Crespo, M. A. Matos, and J. Pereira, “Distribution systems

reconfiguration based on OPF using benders decomposition,” IEEE Trans. Power Deliv., vol. 24,

pp. 2166–2176, 2009.

Page 173: SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK ...read.pudn.com/downloads799/sourcecode/math/3153436/Thesis_fin… · SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK RECONFIGURATION

161

[56] R. A. Jabr, R. Singh, and B. C. Pal, “Minimum loss network reconfiguration using mixed-integer

convex programming,” IEEE Trans. Power Syst., vol. 27, pp. 1106–1115, 2012.

[57] Y. Oualmakran, J. Melendez, and S. Herraiz, “Opportunities and challenges for smart power

restoration and reconfiguration smart decisions with smart grids,” in 11th International Conference

on Electrical Power Quality and Utilisation, 2011, pp. 1–6.

[58] L. L. Pfitscher, D. P. Bernardon, L. N. Canha, V. F. Montagner, V. J. Garcia, and A. R. Abaide,

“Intelligent system for automatic reconfiguration of distribution network in real time,” Electr.

Power Syst. Res., vol. 97, pp. 84–92, 2013.

[59] V. Spitsa, X. Ran, R. Salcedo, J. F. Martinez, R. E. Uosef, F. de Leon, D. Czarkowski, and Z.

Zabar, “On the Transient Behavior of Large-Scale Distribution Networks During Automatic Feeder

Reconfiguration,” IEEE Trans. Smart Grid, vol. 3, no. 2, pp. 887–896, Jun. 2012.

[60] Y. Wu, C. Lee, L. Liu, and S. Tsai, “Study of Reconfiguration for the Distribution System With

Distributed Generators,” IEEE Trans. Power Deliv., vol. 25, no. 3, pp. 1678–1685, Jul. 2010.

[61] R. S. Rao, K. Ravindra, K. Satish, and S. V. L. Narasimham, “Power Loss Minimization in

Distribution System Using Network Recon fi guration in the Presence of Distributed Generation,”

vol. 28, no. 1, pp. 317–325, 2013.

[62] I.-K. Song, W.-W. Jung, J.-Y. Kim, S.-Y. Yun, J.-H. Choi, and S.-J. Ahn, “Operation Schemes of

Smart Distribution Networks With Distributed Energy Resources for Loss Reduction and Service

Restoration,” IEEE Trans. Smart Grid, vol. 4, no. 1, pp. 367–374, Mar. 2013.

[63] V. F. Martins and C. L. T. Borges, “Active Distribution Network Integrated Planning Incorporating

Distributed Generation and Load Response Uncertainties,” IEEE Trans. Power Syst., vol. 26, no. 4,

pp. 2164–2172, Nov. 2011.

[64] H. A. Mostafa, R. El-Shatshat, and M. M. A. Salama, “Multi-objective optimization for the

operation of an electric distribution system with a large number of single phase solar generators,”

IEEE Trans. Smart Grid, vol. 4, pp. 1038–1047, 2013.

[65] E. P. Systems and V. Ratings, “ANSI C84.1-2006 American National Standard,” 2006.

[66] D. Committee, IEEE Std 1159TM-2009, IEEE Recommended Practice for Monitoring Electric

Power Quality, vol. 2009. 2009, pp. c1 –81.

[67] E. Davison and N. Tripathi, “The optimal decentralized control of a large power system: Load and

frequency control,” IEEE Trans. Automat. Contr., vol. 23, 1978.

[68] W. Qiu, V. Vittal, and M. Khammash, “Decentralized power system stabilizer design using linear

parameter varying approach,” IEEE Trans. Power Syst., vol. 19, pp. 1951–1960, 2004.

[69] G. Hug-Glanzmann and G. Andersson, “Decentralized optimal power flow control for overlapping

areas in power systems,” IEEE Trans. Power Syst., vol. 24, pp. 327–336, 2009.

[70] M. E. Elkhatib, R. El Shatshat, and M. M. A. Salama, “Decentralized reactive power control for

advanced distribution automation systems,” IEEE Trans. Smart Grid, vol. 3, pp. 1482–1490, 2012.

Page 174: SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK ...read.pudn.com/downloads799/sourcecode/math/3153436/Thesis_fin… · SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK RECONFIGURATION

162

[71] S. D. J. McArthur, E. M. Davidson, V. M. Catterson, A. L. Dimeas, N. D. Hatziargyriou, F. Ponci,

and T. Funabashi, “Multi-Agent Systems for Power Engineering Applications—Part I: Concepts,

Approaches, and Technical Challenges,” IEEE Trans. Power Syst., vol. 22, no. 4, pp. 1743–1752,

Nov. 2007.

[72] J. S. Heo and K. Y. Lee, “A Multiagent-System-Based Intelligent Reference Governor for

Multiobjective Optimal Power Plant Operation,” IEEE Trans. Energy Convers., vol. 23, no. 4, pp.

1082–1092, Dec. 2008.

[73] C.-X. Dou and B. Liu, “Multi-Agent Based Hierarchical Hybrid Control for Smart Microgrid,”

IEEE Trans. Smart Grid, vol. 4, no. 2, pp. 771–778, Jun. 2013.

[74] S. Chakrabarti, M. Kraning, E. Chu, R. Baldick, and S. Boyd, “Security Constrained Optimal

Power Flow via proximal message passing,” in 2014 Clemson University Power Systems

Conference, 2014, pp. 1–8.

[75] “S-function.” [Online]. Available: http://www.mathworks.com/help/simulink/sfg/s-function-

examples.html.

[76] N. Rugthaicharoencheep and S. Sirisumrannukul, “Feeder reconfiguration for loss reduction in

three phase distribution system under unbalanced loading conditions,” Univ. Power Eng. Conf.

(UPEC), 2010 45th Int., 2010.

[77] Y. J. Jeon, J. C. Kim, J. O. Kim, K. Y. Lee, and J. R. Shin, “An Efficient Simulated Annealing

Algorithm for Network Reconfiguration in Large-Scale Distribution Systems,” IEEE Power Eng.

Rev., vol. 22, no. 7, pp. 61–62, 2002.

[78] H. M. Abdar, A. Chakraverty, D. H. Moore, J. M. Murray, and K. A. Loparo, “Design and

implementation a specific grid-tie inverter for an agent-based microgrid,” in 2012 IEEE

Energytech, 2012, pp. 1–6.

[79] M. Z. Hussin, M. H. A. Hamid, Z. M. Zain, and R. A. Rahman, “An evaluation data of solar

irradiation and dry bulb temperature at Subang under Malaysian climate,” in Proceedings -

ICSGRC 2010: 2010 IEEE Control and System Graduate Research Colloquium, 2010, pp. 55–60.

[80] E. Spahic and J. Morren, “Mathematical model of the Double Fed Induction Generator for Wind

Turbines and its Control Quality,” … , Energy Electr. …, no. Figure 1, pp. 1–6, 2007.

[81] F. D. Kanellos and N. D. Hatziargyriou, “Optimal Control of Variable Speed Wind Turbines in

Islanded Mode of Operation,” IEEE Trans. Energy Convers., vol. 25, no. 4, pp. 1142–1151, Dec.

2010.

[82] C. Wang, “Modeling and control of hybrid wind/photovoltaic/fuel cell distributed generation

systems,” Montana State University, 2006.

[83] W. Qiao, “Dynamic modeling and control of doubly fed induction generators driven by wind

turbines,” in 2009 IEEE/PES Power Systems Conference and Exposition, 2009, pp. 1–8.

[84] S.-K. Kim, J.-H. Jeon, C.-H. Cho, E.-S. Kim, and J.-B. Ahn, “Modeling and simulation of a grid-

connected PV generation system for electromagnetic transient analysis,” Solar Energy, vol. 83. pp.

664–678, 2009.

Page 175: SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK ...read.pudn.com/downloads799/sourcecode/math/3153436/Thesis_fin… · SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK RECONFIGURATION

163

[85] N. Gyawali, Y. Ohsawa, and O. Yamamoto, “Dispatchable power from DFIG based wind-power

system with integrated energy storage,” in IEEE PES General Meeting, 2010, pp. 1–7.

[86] M. C. Cavalcanti, G. M. S. Azevedo, B. A. Amaral, K. C. de Oliveira, F. A. S. Neves, and D. Lins,

“Efficiency Evaluation in Grid Connected Photovoltaic Energy Conversion Systems,” in IEEE 36th

Conference on Power Electronics Specialists, 2005., 2005, pp. 269–275.

[87] T. Esram and P. L. Chapman, “Comparison of Photovoltaic Array Maximum Power Point Tracking

Techniques,” IEEE Trans. Energy Convers., vol. 22, no. 2, pp. 439–449, Jun. 2007.

[88] J. Larminie and A. Dicks, Fuel Cell Systems Explained. West Sussex, England, England: John

Wiley & Sons, Ltd,., 2003.

[89] B. Huang, P. Li, D. Wang, F. Ding, and C. Wang, “Modeling and analysis of PEMFC in distributed

generation system,” in 2009 International Conference on Sustainable Power Generation and

Supply, 2009, no. 50625722, pp. 1–5.

[90] M. Soltani and S. M. T. Bathaee, “A new dynamic model considering effects of temperature,

pressure and internal resistance for PEM fuel cell power modules,” in 2008 Third International

Conference on Electric Utility Deregulation and Restructuring and Power Technologies, 2008, pp.

2757–2762.

[91] “Supercapacitor.” [Online]. Available: http://en.wikipedia.org/wiki/Supercapacitor.

[92] M. E. Glavin, P. K. W. Chan, S. Armstrong, and W. G. Hurley, “A stand-alone photovoltaic

supercapacitor battery hybrid energy storage system,” in 2008 13th International Power

Electronics and Motion Control Conference, 2008, pp. 1688–1695.

[93] F. Ding, P. Li, B. Huang, F. Gao, and C. Wang, “Modeling and simulation of grid-connected hybrid

photovoltaic/battery distributed generation system,” in Electricity Distribution, 2010, pp. 1–10.

[94] INSTITUTE OF ELECTRICAL AND ELECTRONICS ENGINEERS, “IEEE Std 1250 - IEEE

Guide for Identifying and Improving Voltage Quality in Power Systems,” IEEE Std 1250-2011

(Revision of IEEE Std 1250-1995). pp. 1–70, 2011.

[95] D. Committee, IEEE Std 1159TM-2009, IEEE Recommended Practice for Monitoring Electric

Power Quality, vol. 2009. 2009, pp. c1 –81.

[96] J. E. Dennis and R. B. Schnabel, Numerical Methods for Unconstrained Optimization and

Nonlinear Equations, vol. 16. Society for Industrial and Applied Mathematics, 1996, p. 378.

[97] J. E. Dennis and R. B. Schnabel, Numerical Methods for Unconstrained Optimization and

Nonlinear Equations, vol. 16. Society for Industrial and Applied Mathematics, 1996, p. 378.

[98] Z. Fikri, “Statistical load analysis for distribution network planning,” Royal Institute Technology,

Sweden, 1975.

[99] G. W. Irwin, W. Monteith, and W. C. Beattie, “Statistical electricity demand modelling from

consumer billing data,” IEE Proceedings C Generation, Transmission and Distribution, vol. 133. p.

328, 1986.

Page 176: SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK ...read.pudn.com/downloads799/sourcecode/math/3153436/Thesis_fin… · SMART DISTRIBUTION SYSTEM AUTOMATION: NETWORK RECONFIGURATION

164

[100] R. Herman and J. J. Kritzinger, “The statistical description of grouped domestic electrical load

currents,” Electric Power Systems Research, vol. 27. pp. 43–48, 1993.

[101] R. Singh, B. C. Pal, and R. A. Jabr, “Statistical Representation of Distribution System Loads Using

Gaussian Mixture Model,” IEEE Trans. Power Syst., vol. 25, no. 1, pp. 29–37, Feb. 2010.

[102] “Backcasted load profiles.” [Online]. Available: http://www.ercot.com/mktinfo/loadprofile/alp/.

[103] G. K. Viswanadha Raju and P. R. Bijwe, “Efficient reconfiguration of balanced and unbalanced

distribution systems for loss minimisation,” IET Gener. Transm. Distrib., vol. 2, no. 1, p. 7, 2008.

[104] “RADIAL DISTRIBUTION TEST FEEDERS IEEE Distribution Planning Working Group

Report,” Power, vol. 6, pp. 975–985, 1991.

[105] D. Moore, J. Murray, F. P. Maturana, T. Wendel, and K. A. Loparo, “Agent-based control of a DC

MicroGrid,” in 2013 IEEE Energytech, 2013, pp. 1–6.

[106] F. P. Maturana, R. J. Staron, D. L. Carnahan, and K. A. Loparo, “Distributed control concepts for

future power grids,” in 2013 IEEE Energytech, 2013, pp. 1–6.

[107] J. Haack, B. Akyol, N. Tenney, B. Carpenter, R. Pratt, and T. Carroll, “VOLTTRONTM: An agent

platform for integrating electric vehicles and Smart Grid,” in 2013 International Conference on

Connected Vehicles and Expo (ICCVE), 2013, pp. 81–86.

[108] R. P. Broadwater, J. C. Thompson, R. E. Lee, and H. Maghdan-D, “Computer-aided protection

system design with reconfiguration,” IEEE Trans. Power Deliv., vol. 6, no. 1, pp. 260–266, 1991.

[109] Y.-Y. Hsu and J.-H. Yi, “Planning of distribution feeder reconfiguration with protective device

coordination,” IEEE Trans. Power Deliv., vol. 8, no. 3, pp. 1340–1347, Jul. 1993.

[110] S. Chen and H. Glavitsch, “Stabilizing switching,” IEEE Trans. Power Syst., vol. 8, pp. 1511–

1517, 1993.

[111] L. Chen, Y. Taka, H. Okamoto, R. Tanabe, and A. Ono, “Optimal operation solutions of power

systems with transient stability constraints,” IEEE Trans. Circuits Syst. I Fundam. Theory Appl.,

vol. 48, no. 3, pp. 327–339, Mar. 2001.


Recommended