+ All Categories
Home > Documents > SULTANATE OF OMAN Security... · 2018. 3. 14. · SULTANATE OF OMAN LICENCE CONDITION (26)...

SULTANATE OF OMAN Security... · 2018. 3. 14. · SULTANATE OF OMAN LICENCE CONDITION (26)...

Date post: 07-Feb-2021
Category:
Upload: others
View: 2 times
Download: 0 times
Share this document with a friend
44
SULTANATE OF OMAN LICENCE CONDITION (26) TRANSMISSION SECURITY STANDARD Second edition As Approved by Authority for Electricity Regulation July 2016
Transcript
  • SULTANATE OF OMAN

    LICENCE CONDITION (26)

    TRANSMISSION SECURITY STANDARD

    Second edition

    As Approved by Authority for Electricity Regulation – July 2016

  • Transmission Security Standard Oman Electricity Transmission Company S.A.O.C

    - 1 -

    CONTENTS

    Page

    1 Introduction to the OETC Transmission Security Standard 3

    1.1 Roles and scope 3

    1.2 Structure and reach of the TSS in the OETC licensed transmission system 4

    2 System design and operational Values 7

    2.1 Introduction 7

    2.2 System parameters under various conditions 7

    3 Design of the Main Interconnected Transmission System 9

    3.1 Introduction 9

    3.2 MITS design criteria 9

    3.3 MITS – Intact System requirements at Peak Demand 10

    3.4 MITS – Following a Restricted Period Fault Outage 11

    3.5 MITS – Following a Maintenance Period Fault Outage 12

    3.6 Variations to the MITS design criteria 12

    4 Design of generation connections and GSO connections 13

    4.1 Introduction 13

    4.2 Generation connection design criteria 13

    4.3 Generation & GSO connections – Intact System requirements at Peak Demand 14

    4.4 Generation & GSO connections – Following a Restricted Period Fault Outage 15

    4.5 Generation & GSO connections – Loss of Power Infeed constraints 16

    4.6 Generation & GSO connections – Loss of Power Infeed during Planned Outages 17

    4.7 Generation & GSO connections – Transmission Capacity & Loss of Power Infeed 18

    4.8 GSO connections – Loss of Power Infeed constraints 18

    4.9 Variations to generation connection design criteria or Table 4.6 19

    5 Design of demand connections 20

    5.1 Introduction 20

    5.2 Demand connection design criteria 20

    5.3 Demand connection capacity requirements 20

    5.4 Demand connections – Intact System conditions at Peak Demand values 21

    5.5 Demand connections – Following a Restricted Period Fault Outage 22

    5.6 Demand connections – Following a Maintenance Period Fault Outage 23

    5.7 Demand connections – Following a Restricted Period Unplanned Outage 24

    5.8 Additional demand connection requirements 24

  • Transmission Security Standard Oman Electricity Transmission Company S.A.O.C

    - 2 -

    5.9 Variations to demand connection design criteria 24

    5.10 Demand Classes 25

    6 OETC licensed transmission system operational criteria 27

    6.1 Introduction 27

    6.2 Operational security criteria 27

    6.3 Operation – Prevailing System Conditions 28

    6.4 Operation – Outcomes following a Fault Outage 29

    6.5 Managing OETC licensed transmission system conditions and values 30

    6.6 Conditional further operational security criteria 30

    6.7 Restoration of OETC licensed transmission system following a Secured Event 31

    6.8 Variations to operational security criteria 31

    7 Definitions 33

    List of figures

    Figure 1.1 – Representation of the OETC licensed transmission system and other GSO systems ....... 5

    Figure 1.2 – Generation connections, GSO connections and Grid Supply Points ................................. 6

    Figure 5.1 – Demand Classes – Demand Group schematics ............................................................... 26

    List of tables

    Table 2.1 – OETC licensed transmission system – system parameter values ....................................... 8

    Table 3.1 – MITS – Intact System requirements at Peak Demand values ........................................... 10

    Table 3.2 – MITS – Following a Restricted Period Fault Outage.......................................................... 11

    Table 3.3 – MITS – Following a Maintenance Period Fault Outage ..................................................... 12

    Table 4.1 – Generation & GSO connections – Intact System requirements at Peak Demand ............ 14

    Table 4.2 – Generation & GSO connections – Following a Restricted Period Fault Outage ............... 15

    Table 4.3 – Generation & GSO connections – Loss of Power Infeed following a system outage ........ 16

    Table 4.4 – Generation & GSO connections – Loss of Power Infeed during Planned Outages .......... 17

    Table 4.5 – Generation & GSO connections – Following a Loss of Power Infeed ............................... 18

    Table 4.6 – GSO connections – Loss of Power Infeed of following a system outage .......................... 19

    Table 5.1 – Demand connections – Intact System requirements at Peak Demand ............................. 21

    Table 5.2 – Demand connections – Following a Restricted Period Fault Outage ................................ 22

    Table 5.3 – Demand connections – Following a Maintenance Period Fault Outage ............................ 23

    Table 5.4 – Demand connections – Following a Restricted Period Unplanned Outage ....................... 24

    Table 5.5 – Demand connections – Demand Class specification ......................................................... 25

    Table 6.1 – Operational outcomes during Prevailing System Conditions ............................................. 28

    Table 6.2 – Operational outcomes following a Fault Outage ................................................................ 29

  • Transmission Security Standard Oman Electricity Transmission Company S.A.O.C

    - 3 -

    1 INTRODUCTION TO THE OETC TRANSMISSION SECURITY STANDARD

    1.1 Roles and scope

    1.1.1 This document sets out the Transmission Security Standard (the “Standard” or “TSS”)

    that the Oman Electricity Transmission Company S.A.O.C (“OETC”) will implement for

    the planning and operation of its licensed transmission system. The TSS has been

    prepared in accordance with Condition 26 of OETC's Transmission and Dispatch

    Licence.

    1.1.2 The TSS contains technical terms and phrases specific to electricity transmission

    systems and the electricity sector that may differ from their common usage. For this

    reason ‘Definitions’ have been included in section 7. Throughout this document,

    defined terms are shown in italics with capital initial letters. Other terms with an initial

    capital letter and in normal font are defined in the Grid Code.

    1.1.3 For ease of use, the component elements of the TSS are presented according to the

    functional parts of the OETC licensed transmission system to which they primarily

    apply, including, but not limited to:

    a The Main Interconnected Transmission System (“MITS”) and the Dhofar Power System

    b The generation connections at which a Production Facility feeds into the MITS and GSO connections both internal to Oman and internationally

    c Demand connections, where demand is connected, including:

    i Grid Supply Points, and

    ii Demand Groups

    d The operational security criteria

    1.1.4 Taken together, each of elements described in sections 1.1.3a to 1.1.3c inclusive

    make up the OETC licensed transmission system, as shown in Figure 1.1.

    1.1.5 The criteria for radially connected generation, GSO connections and demand

    connections are consistent with the criteria applied to the MITS. However, they are

    conditioned by the criteria for the relevant generation connections, GSO connections

    and/or demand connections.

    1.1.6 The criteria presented in the TSS represent normal requirements for the planning and

    operation of the OETC licensed transmission system. Any departure from the TSS

    criteria shall be subject to detailed risk and economic studies. These shall include

    consideration of the costs associated with the use and/or introduction of out-of-merit

    generation as an alternative to network reinforcement. To the extent permitted and

    required within the TSS, OETC shall seek derogations from the relevant provisions of

    the TSS.

  • Transmission Security Standard Oman Electricity Transmission Company S.A.O.C

    - 4 -

    1.1.7 Additional criteria, for example covering more detailed and other aspects of quality of

    supply, are contained in the Grid Code and Distribution Code, which should be read in

    conjunction with the TSS.

    1.1.8 As described above and illustrated in Figure 1.2, there will be many parts of the

    OETC licensed transmission system where more than one set of criteria apply. In

    such parts, the requirements of all relevant criteria shall be met. Figure 1.1 provides

    an overall view of the OETC licensed transmission system. Figure 1.2 shows the

    more detailed reach and overlap of the TSS criteria. Thus Figure 1.2 governs in

    terms of the application of TSS criteria.

    1.1.9 While it is a requirement for Transmission Capacity to meet the TSS criteria, it does

    not follow that Transmission Capacity should be reduced so that it only meets the

    minimum requirement of those criteria.

    1.2 Structure and reach of the TSS in the OETC licensed transmission system

    1.2.1 Figure 1.1 below shows the relationship between the various elements of the OETC

    licensed transmission system.

    1.2.2 Figure 1.2 below shows the reach and overlap of the various design criteria specified

    in the TSS.

    1.2.3 Figure 1.2 governs over Figure 1.1.

  • Transmission Security Standard Oman Electricity Transmission Company S.A.O.C

    - 5 -

    Figure 1.1 – Representation of the OETC licensed transmission system and

    other GSO systems

    GSO system

    GCCIA system

    MIT

    S

    Pro

    duction F

    acility

    Pro

    duction F

    acility

    Ge

    ne

    ratio

    n

    co

    nne

    ctio

    n

    Ge

    ne

    ratio

    n

    co

    nne

    ctio

    nO

    ET

    C lic

    en

    sed

    tra

    nsm

    issio

    n s

    yste

    m

    GS

    O i

    nte

    rco

    nne

    ctio

    n

    MIT

    S d

    esig

    n c

    rite

    ria

    Genera

    tion c

    onnection d

    esig

    n c

    rite

    ria

    GSO system

    PDO system

    GS

    O inte

    rco

    nne

    ctio

    nG

    SO

    inte

    rco

    nne

    ctio

    n

    De

    ma

    nd

    co

    nne

    ctio

    n

    Future

    De

    ma

    nd

    co

    nne

    ctio

    n

    Dem

    and G

    roup

    Dh

    ofa

    r P

    ow

    er

    Syste

    mP

    roduction

    Facility

    Dem

    and c

    onnection d

    esig

    n c

    rite

    ria

    GS

    O inte

    rconnection d

    esig

    n c

    rite

    ria

    Dem

    and G

    roup

    De

    ma

    nd

    Gro

    up

    Dem

    and c

    onnection

    Ge

    ne

    ratio

    n c

    onne

    ctio

    n

  • Transmission Security Standard Oman Electricity Transmission Company S.A.O.C

    - 6 -

    Figure 1.2 – Generation connections, GSO connections and Grid Supply Points

  • Transmission Security Standard Oman Electricity Transmission Company S.A.O.C

    - 7 -

    2 SYSTEM DESIGN AND OPERATIONAL VALUES

    2.1 Introduction

    2.1.1 The Grid Code specifies various parameters including frequency, voltage, harmonic

    distortion and flicker. These parameters contribute to the quality of supply

    experienced by Users.

    2.2 System parameters under various conditions

    2.2.1 For purposes of the TSS and in respect of frequency and voltage, four conditions are

    identified for determining system parameter values, as follows:

    a Normal conditions – being conditions that apply on a continuous basis; these are the preferred conditions of the OETC licensed transmission system

    b Disturbed conditions – being conditions in which the voltages are the same as for normal conditions, but the frequency limits have been changed and include, as a lower limit, the Normal Infeed Loss Risk frequency limit

    c Stretched Conditions – being conditions that have two parts:

    i Continuous Stretched Conditions that are not time dependant

    ii Time limited Stretched Conditions that may only be experienced for no more than sixty continuous seconds

    d Unacceptable Conditions – being conditions that are never allowed in planning, design or operation

    2.2.2 Transient frequency deviations that occur outside the limits of continuous operation

    Stretched Conditions and last less than sixty seconds shall only occur at reasonably

    infrequent intervals. This governs all relevant TSS criteria.

    2.2.3 Table 2.1 sets out the required values for the system parameters.

  • Transmission Security Standard Oman Electricity Transmission Company S.A.O.C

    - 8 -

    Table 2.1 – OETC licensed transmission system – system parameter values

    Explanatory notes for Table 2.1:

    a. The frequency values are derived from the Grid Code

    b. The frequency value of 47.50 Hz is equal to the Infrequent Infeed Loss Risk frequency limit, also referred to as the “IILR frequency limit”

    c. The frequency value of 49.50 Hz is equal to the Normal Infeed Loss Risk frequency limit, also referred to as the “NILR frequency limit”

    d. Refer also to Unacceptable Frequency Conditions

    Low High Low High Low High Low High Low High

    ˂ ≥ ˂ ≥ ˂ ≥ ≤ > ≤ > ≤ >

    47.50 49.50 50.50 51.50

    380 400 420

    198 220 242

    119 132 145

    Quality of Supply – System Parameter values

    Parameter

    Unacceptable conditions

    Stretched conditions

    Target

    Disturbed conditions

    Normal conditions

    Voltage

    kV

    49.95

    390

    209

    125

    51.5049.95 50.05 50.05 50.50

    380

    198

    119

    420

    242

    145

    410

    231

    139

    Less than

    60 seconds

    Less than

    60 seconds

    Frequency

    Hz47.50 50.0049.50

  • Transmission Security Standard Oman Electricity Transmission Company S.A.O.C

    - 9 -

    3 DESIGN OF THE MAIN INTERCONNECTED TRANSMISSION SYSTEM

    3.1 Introduction

    3.1.1 As at the approval date, the MITS and Dhofar Power System are connected via a

    local GSO system owned and operated by PDO.

    3.1.2 For the purposes of this section the MITS design criteria shall apply equally to the

    MITS and the Dhofar Power System.

    3.2 MITS design criteria

    3.2.1 Collectively, sections 3.3, 3.4 and 3.5 set out the design criteria for the MITS (the

    “MITS design criteria”).

  • Transmission Security Standard Oman Electricity Transmission Company S.A.O.C

    - 10 -

    3.3 MITS – Intact System requirements at Peak Demand

    3.3.1 The minimum Transmission Capacity of the MITS shall be planned and designed to

    achieve the outcomes specified in Table 3.1 for the following Background Conditions:

    i Peak Demand values;

    ii The expected generation schedule;

    iii Expected GSO connection transfers1 (if any), and

    iv Prior to any Secured Event

    Table 3.1 – MITS – Intact System requirements at Peak Demand values

    MITS

    Intact System design requirements for Peak Demand values

    System Equipment loading

    a) System Equipment shall not exceed Pre-Fault Rating levels

    b) System Equipment shall be within the relevant Technical Limits

    c) Circuit-breakers shall not be subjected to calculated fault current in excess of their Technical Limits

    System parameters

    For the OETC licensed transmission system there shall be:

    a) No Unacceptable Frequency Conditions

    b) Voltage levels within normal conditions

    c) No Insufficient Performance Margins

    System stability There shall be no System Instability

    1 GSO connection transfers show power import or export for the OETC licensed transmission system

  • Transmission Security Standard Oman Electricity Transmission Company S.A.O.C

    - 11 -

    3.4 MITS – Following a Restricted Period Fault Outage

    3.4.1 Using Peak Demand values, the Background Conditions described in section 3.3 and

    following a specified Fault Outage, the Transmission Capacity for the MITS shall be

    planned and designed to achieve the outcomes specified in Table 3.2.

    Table 3.2 – MITS – Following a Restricted Period Fault Outage

    MITS

    Outcomes following a Restricted Period Fault Outage at Peak Demand values

    Following any one of the following: These outcomes shall be achieved:

    1) A Fault Outage of a single Transmission Circuit

    2) A Fault Outage of a single section of Busbar

    3) A Fault Outage of a single GSO connection circuit

    4) A Fault Outage of either: (i) a single Generation Unit; or (ii) a number of Generation Units, connected to the MITS through a single circuit-breaker

    a) No loss of supply to Grid Supply Points except as provided for in Table 5.5

    b) No loss of supply from a Production Facility or GSO system greater than the Normal Infeed Loss Risk

    c) System Equipment shall be within the relevant Technical Limits

    d) No Unacceptable Frequency

    Conditions

    e) No Unacceptable Voltage Conditions

    f) No Insufficient Performance Margins

    g) No System Instability

  • Transmission Security Standard Oman Electricity Transmission Company S.A.O.C

    - 12 -

    3.5 MITS – Following a Maintenance Period Fault Outage

    3.5.1 During the Maintenance Period, while using the expected OETC licensed

    transmission system demand and the expected generation schedule but excluding

    any forecast GSO connection import or export, with a Planned Outage of a single

    Transmission Circuit or a single section of Busbar, and following the specified Fault

    Outages, the MITS shall be designed to achieve the outcomes specified in Table 3.3.

    Table 3.3 – MITS – Following a Maintenance Period Fault Outage

    MITS

    Outcomes following a Maintenance Period Fault Outage

    Following any one of the following: These outcomes shall be achieved:

    1) A Fault Outage of a single Transmission Circuit

    2) A Fault Outage of a single section of Busbar

    3) A Fault Outage of a single GSO connection circuit

    4) A Fault Outage of either: (i) a single Generation Unit; or (ii) a number of Generation Units connected to the MITS through a single circuit-breaker

    a) No loss of supply to Grid Supply

    Points except as provided for in

    Table 5.5

    b) System Equipment shall be within

    the relevant Technical Limits

    c) No Unacceptable Frequency

    Conditions

    d) No Unacceptable Voltage

    Conditions

    e) No Insufficient Performance

    Margins

    f) No System Instability

    3.5.2 Where necessary to satisfy the above MITS design criteria during the Maintenance

    Period, and unless operational measures can be applied to ensure adequate

    Transmission Capacity, investment analysis shall be applied.

    3.6 Variations to the MITS design criteria

    3.6.1 No variation to the MITS design criteria is permitted.

  • Transmission Security Standard Oman Electricity Transmission Company S.A.O.C

    - 13 -

    4 DESIGN OF GENERATION CONNECTIONS AND GSO CONNECTIONS

    4.1 Introduction

    4.1.1 This section presents the criteria to be applied for the direct connection of one or

    more Production Facilities or GSO systems to the OETC licensed transmission

    system. The criteria in this section will also apply to the connections from a Grid

    Supply Point or Demand Group to the OETC licensed transmission system by which

    Generation Units embedded within a User’s network (e.g. a distribution network) are

    connected to the OETC licensed transmission system.

    4.1.2 In those parts of the OETC licensed transmission system where the criteria of any of

    section 3 and section 5 also apply, then those criteria shall also be met.

    4.2 Generation connection design criteria

    4.2.1 Collectively, sections 4.3, 4.4, 4.5, 4.6 and 4.7 set out the design criteria for

    connecting a Production Facility or GSO systems and any other Generation Units to

    the OETC licensed transmission system (the “generation connection design criteria”).

    4.2.2 The generation connection design criteria apply to GSO connections.

    4.2.3 The generation connection design criteria apply to all forms of generation, such as but

    not limited to:

    a Synchronous machines

    b Asynchronous machines, such as, for example, solar or wind powered generators

    4.2.4 In designing generation connections or GSO connections to meet the TSS, the

    following shall be considered:

    a The Loss of Power Infeed resulting from a Fault Outage on the Generation Circuits or GSO connection circuits themselves; and

    b The effects of a Fault Outage on the OETC licensed transmission system

    4.2.5 When any new Production Facility, consisting of one or more Generation Units, or a

    GSO connection, is proposed to be added to the OETC licensed transmission system,

    then any system studies, planning, development and design shall consider the full

    simultaneous power of all of the proposed Generation Units or GSO connections

    operating together.

  • Transmission Security Standard Oman Electricity Transmission Company S.A.O.C

    - 14 -

    4.3 Generation & GSO connections – Intact System requirements at Peak Demand

    4.3.1 Using Peak Demand values, the Background Conditions described in section 3.3 and

    prior to any Secured Event, the minimum Transmission Capacity for generation

    connections and GSO connections shall be planned and designed to achieve the

    outcomes specified in Table 4.1.

    Table 4.1 – Generation & GSO connections – Intact System requirements at

    Peak Demand

    Generation connections and GSO connections

    Intact System design requirements for Peak Demand values

    Transmission and System Equipment loading

    a) System Equipment shall not exceed Pre-Fault Rating levels

    b) System Equipment shall be within the relevant Technical Limits

    c) Circuit-breakers shall not be subjected to predicted fault current in excess of their Technical Limits

    System parameters

    On the OETC licensed transmission system there shall be:

    a) No Unacceptable Frequency Conditions

    b) Voltage levels within normal conditions

    c) No Insufficient Performance Margins

    System stability There shall be no System Instability

  • Transmission Security Standard Oman Electricity Transmission Company S.A.O.C

    - 15 -

    4.4 Generation & GSO connections – Following a Restricted Period Fault Outage

    4.4.1 Using Peak Demand values, the Background Conditions described in section 3.3 and

    following the specified Secured Events, the Transmission Capacity for generation

    connections and GSO connections shall be planned and designed to achieve the

    outcomes specified in Table 4.2.

    Table 4.2 – Generation & GSO connections – Following a Restricted Period

    Fault Outage

    Generation connections and GSO connections Outcomes following a Restricted Period Fault Outage at Peak Demand values

    Following any one of the following: These outcomes shall be achieved:

    1) A Fault Outage of a single Transmission Circuit

    2) A Fault Outage of a single GSO connection circuit

    3) A Fault Outage of a single section of Busbar

    4) An Unplanned Outage of a single Transmission Circuit followed by a Fault Outage of a further single Transmission Circuit

    5) An Unplanned Outage of a Generation Circuit followed by a Fault Outage of a single Transmission Circuit

    a) No loss of supply to a Grid Supply Point except as permitted in Table 5.5

    b) No loss of supply from Production Facilities or GSO systems greater than the Infrequent Infeed Loss Risk

    c) System Equipment shall be within the relevant Technical Limits

    d) No Unacceptable Frequency

    Conditions

    e) No Unacceptable Voltage Conditions

    f) No Insufficient Performance Margins

    g) No System Instability

  • Transmission Security Standard Oman Electricity Transmission Company S.A.O.C

    - 16 -

    4.5 Generation & GSO connections – Loss of Power Infeed constraints

    4.5.1 Starting with an Intact System and including any forecast GSO connection import or

    export, generation connections and GSO connections shall be planned, designed,

    developed and constructed to achieve the outcomes specified in Table 4.3.

    Table 4.3 – Generation & GSO connections – Loss of Power Infeed following a

    system outage

    Generation connections and GSO connections

    Intact System

    Requirements for Loss of Power Infeed following a system outage

    Following the specified system outage

    There shall be:

    Planned Outage or fault on any single Transmission Circuit

    No Loss of Power Infeed from Production Facilities

    Planned Outage of any single section of Busbar on the MITS

    Fault Outage of any single Generation

    Circuit or single section of Busbar

    Any Loss of Power Infeed from

    Production Facilities shall not exceed

    the Normal Infeed Loss Risk

    Fault Outage of any single Busbar

    coupler circuit-breaker or Busbar

    section circuit-breaker on the MITS

    Any Loss of Power Infeed from

    Production Facilities shall not exceed

    the Infrequent Infeed Loss Risk

  • Transmission Security Standard Oman Electricity Transmission Company S.A.O.C

    - 17 -

    4.6 Generation & GSO connections – Loss of Power Infeed during Planned Outages

    4.6.1 Generation connections and GSO connections shall be planned, designed, developed

    and constructed such that, during the specified Planned Outages, any Loss of Power

    Infeed shall achieve the outcomes specified in Table 4.4.

    Table 4.4 – Generation & GSO connections – Loss of Power Infeed during

    Planned Outages

    Generation connections and GSO connections

    Loss of Power Infeed during Planned Outages

    During the

    Planned Outage

    of

    If there is a

    Fault Outage

    on the MITS of:

    Then:

    A single Transmission

    Circuit

    a further single

    Transmission Circuit;

    or

    a single section of

    Busbar

    Any Loss of Power

    Infeed from Production

    Facilities shall not

    exceed the Infrequent

    Infeed Loss Risk

    a single Busbar coupler

    circuit-breaker;

    or

    a single Busbar section

    circuit-breaker

    A single section of

    Busbar on the MITS

    a single Transmission

    Circuit;

    or

    a further single section

    of Busbar

    a single Busbar coupler

    circuit-breaker;

    or

    a single Busbar section

    circuit-breaker

  • Transmission Security Standard Oman Electricity Transmission Company S.A.O.C

    - 18 -

    4.7 Generation & GSO connections – Transmission Capacity & Loss of Power

    Infeed

    4.7.1 The Transmission Capacity for Generation connections and GSO connections shall

    be planned such that, for all OETC licensed transmission system conditions, the Loss

    of Power Infeed of the same magnitude as the Normal Infeed Loss Risk or Infrequent

    Infeed Loss Risk respectively is secured as specified in Table 4.5.

    Table 4.5 – Generation & GSO connections – Following a Loss of Power Infeed

    Generation connections and GSO connections

    Outcomes following a Loss of Power Infeed

    Following: None of these outcomes shall occur:

    Normal Infeed Loss Risk

    a) Loss of supply to a Grid Supply Point except as permitted in Table 5.5

    b) Loss of supply from any Production Facility or GSO system greater than the Normal Infeed Loss Risk

    c) System Equipment exceeding the relevant Technical Limits

    d) OETC licensed transmission system frequency falls below the NILR frequency limit

    e) Unacceptable Voltage Conditions

    f) Insufficient Performance Margins

    g) System Instability

    Infrequent Infeed Loss Risk

    a) Cascade failure of the OETC licensed transmission system

    b) OETC licensed transmission system frequency falls to below the IILR frequency limit

    c) OETC licensed transmission system frequency remains below the NILR frequency limit for longer than 60 continuous seconds

    d) Unacceptable Voltage Conditions

    4.8 GSO connections – Loss of Power Infeed constraints

    4.8.1 Starting with an Intact System, GSO connections shall be planned, designed,

    developed and constructed to achieve the outcomes specified in Table 4.6.

  • Transmission Security Standard Oman Electricity Transmission Company S.A.O.C

    - 19 -

    Table 4.6 – GSO connections – Loss of Power Infeed of following a system

    outage

    GSO connections

    Intact System

    Requirements for Loss of Power Infeed following a system outage

    Following the specified system outage

    There shall be:

    On any single GSO connection circuit:

    1) A Planned Outage, or

    2) An Unplanned Outage, or

    3) A Fault Outage

    No Loss of Power Infeed

    4.9 Variations to generation connection design criteria or Table 4.6

    4.9.1 OETC may seek derogation for variation to the generation connection design criteria

    and/or the requirements of Table 4.6, based on technical and economic analysis of

    design options relative to the characteristics of the generation or GSO to be

    connected.

  • Transmission Security Standard Oman Electricity Transmission Company S.A.O.C

    - 20 -

    5 DESIGN OF DEMAND CONNECTIONS

    5.1 Introduction

    5.1.1 This section presents the planning and design criteria for the connection of Demand

    Groups to the OETC licensed transmission system.

    5.1.2 In those parts of the OETC licensed transmission system where the criteria of

    sections 3 and 4 also apply, then those criteria must also be met.

    5.2 Demand connection design criteria

    5.2.1 All the criteria listed in this section 5 comprise the demand connection design criteria.

    5.3 Demand connection capacity requirements

    5.3.1 The connection of a particular Demand Group shall meet the criteria set out in

    sections 5.4 through to and including 5.7 under the following Background Conditions:

    a When there are neither Planned Outages nor Unplanned Outages, the Group Demand shall be set equal the value at the time of Peak Demand;

    b When there is a Planned Outage local to the Demand Group, the Group Demand shall be set equal to the relevant Maintenance Period Demand;

    c Any Transfer Capacity (i.e. the ability to transfer demand from one Demand Group to another) declared by Distribution Licensees shall be represented taking account of any restrictions on the timescales in which the Transfer Capacity applies. Any Transfer Capacity declared by the Distribution Licensees to be available for use in planning timescales must be available for use in such planning timescales; and

    d Any generation available within a Demand Group shall be taken into account by considering its forecast generation as provided by the relevant Generation Unit owner

  • Transmission Security Standard Oman Electricity Transmission Company S.A.O.C

    - 21 -

    5.4 Demand connections – Intact System conditions at Peak Demand values

    5.4.1 For Peak Demand values and prior to any Secured Event, the minimum Transmission

    Capacity of any demand connection, its relevant Transmission Circuits and Demand

    Groups shall be planned and designed to achieve the outcomes specified in

    Table 5.1.

    Table 5.1 – Demand connections – Intact System requirements at Peak Demand

    Demand connections

    Demand Group

    Intact System design requirements for Peak Demand values

    System Equipment loading

    a) System Equipment shall not exceed Pre-Fault Rating levels

    b) System Equipment shall be within the relevant Technical Limits

    c) Circuit-breakers shall not be subjected to predicted fault current in excess of their Technical Limits

    System parameters

    For the OETC licensed transmission system there shall be:

    a) No Unacceptable Frequency Conditions

    b) Voltage levels within normal conditions

    c) No Insufficient Performance Margins

    System stability There shall be no System Instability

  • Transmission Security Standard Oman Electricity Transmission Company S.A.O.C

    - 22 -

    5.5 Demand connections – Following a Restricted Period Fault Outage

    5.5.1 Using Peak Demand values, the Background Conditions described in section 5.3 and

    following a specified Fault Outage, the Transmission Capacity for the connection of a

    Grid Supply Point to a Demand Group shall be planned and designed to achieve the

    outcomes specified in Table 5.2.

    Table 5.2 – Demand connections – Following a Restricted Period Fault Outage

    Demand connections

    Demand Group

    Outcomes following a Restricted Period Fault Outage at Peak Demand values

    Following: These outcomes shall be met:

    A Fault Outage of a single Transmission Circuit

    a) No loss of supply to Grid Supply Points such that the provisions set out in Table 5.5 are not met

    b) System Equipment shall be within the relevant Technical Limits

    c) No Unacceptable Frequency

    Conditions

    d) Voltage levels within normal conditions

    e) No Insufficient Performance Margins

    f) No System Instability

  • Transmission Security Standard Oman Electricity Transmission Company S.A.O.C

    - 23 -

    5.6 Demand connections – Following a Maintenance Period Fault Outage

    5.6.1 During the Maintenance Period, using Maintenance Period Demand values, with the

    Background Conditions described in section 5.3, the Transmission Capacity for the

    connection of a Grid Supply Point to a Demand Group shall be planned to achieve the

    outcomes specified in Table 5.3.

    Table 5.3 – Demand connections – Following a Maintenance Period Fault

    Outage

    Demand connections

    Demand Group

    Outcomes following a Maintenance Period Fault Outage

    During the Planned Outage of either:

    And following a further:

    These outcomes shall be met:

    A single Transmission Circuit;

    or

    A single Generation Unit

    Fault Outage of a

    single

    Transmission

    Circuit

    a) No loss of supply to

    Grid Supply Points

    such that the

    provisions set out in

    Table 5.5 are not met

    b) System Equipment

    shall be within the

    relevant Technical

    Limits

    c) No Unacceptable

    Frequency Conditions

    d) OETC licensed

    transmission system

    voltage levels within

    normal conditions

    e) No Insufficient

    Performance Margins

    f) No System Instability

    5.6.2 Where necessary to satisfy the above demand connection design criteria during the

    Maintenance Period, and unless operational measures can be applied to ensure

    adequate Transmission Capacity, investment analysis shall be applied.

  • Transmission Security Standard Oman Electricity Transmission Company S.A.O.C

    - 24 -

    5.7 Demand connections – Following a Restricted Period Unplanned Outage

    5.7.1 Using Peak Demand values, the Background Conditions described in section 5.3 and

    following a specified Unplanned Outage, the Transmission Capacity for the

    connection of a Grid Supply Point to a Demand Group shall be planned and designed

    to achieve the outcomes specified in Table 5.4.

    Table 5.4 – Demand connections – Following a Restricted Period Unplanned

    Outage

    Demand connections

    Demand Groups

    Outcomes following an Unplanned Outage at Peak Demand values

    After any one of the following: These outcomes shall be met:

    1) An Unplanned Outage of a single Transmission Circuit

    2) An Unplanned Outage of a single section of Busbar

    a) No loss of supply to Grid Supply Points for a Demand Group of greater than 2 MW

    b) System Equipment shall be within the relevant Technical Limits

    c) No Unacceptable Frequency

    Conditions

    d) OETC licensed transmission system voltage levels within normal conditions

    e) No Insufficient Performance Margins

    f) No System Instability

    5.8 Additional demand connection requirements

    5.8.1 In addition to the requirements of sections 5.4 through to and including 5.7 and for the

    Background Conditions described in section 5.3, the system shall be planned such

    that operational switching does not cause Unacceptable Voltage Conditions.

    5.9 Variations to demand connection design criteria

    5.9.1 OETC may seek derogation for variation to the demand connection design criteria in

    this section 5, based on technical and economic analysis of design options relative to

    the characteristics of the demand or embedded Generation Units to be connected.

  • Transmission Security Standard Oman Electricity Transmission Company S.A.O.C

    - 25 -

    5.10 Demand Classes

    5.10.1 The Demand Classes are set out in Table 5.5.

    Table 5.5 – Demand connections – Demand Class specification

    Demand connections

    Demand Class definition and supply restoration times

    Dem

    and C

    lass

    Demand Class

    boundaries

    OETC licensed transmission system configuration

    Following a system outage during the Restricted Period

    A Planned Outage followed by

    a single Fault Outage during the Maintenance Period

    Low MW

    >

    High MW

    Required level of served

    demand

    MW

    Time to restore served

    demand

    Required level of served

    demand

    MW

    Time to restore served

    demand

    A 0 2

    Total Group Demand

    Repair time of faulted

    circuit

    Maintenance Period

    Demand for the Demand

    Group

    No requirement

    B 2 6 3 hours No

    requirement

    C 6 20 15 minutes Return time of Planned

    Outage

    D 20 115 Momentary Interruption

    allowed

    Return time of Planned

    Outage

    E 115 300 Momentary Interruption

    allowed

    Momentary Interruption

    allowed

    F 300 No loss of supply for the Secured Events described in

    the MITS design criteria in section 3

  • Transmission Security Standard Oman Electricity Transmission Company S.A.O.C

    - 26 -

    5.10.2 Figure 5.1 shows the Demand Classes as appropriate and the related Demand

    Groups.

    Figure 5.1 – Demand Classes – Demand Group schematics

  • Transmission Security Standard Oman Electricity Transmission Company S.A.O.C

    - 27 -

    6 OETC LICENSED TRANSMISSION SYSTEM OPERATIONAL CRITERIA

    6.1 Introduction

    6.1.1 This section sets out the operational requirements, conditions, outcomes and system

    states that should be achieved either through automatic control, operator intervention,

    or any combination of these, as required by the circumstances.

    6.1.2 The overall objective is always to maintain the values of system parameters within the

    normal conditions as set out in section 2 and especially Table 2.1.

    6.2 Operational security criteria

    6.2.1 For the OETC licensed transmission system, sections 6.3 and 6.4 set out the normal

    operational security criteria for its operation and maintenance, while section 6.6

    provides for further conditional security criteria, together, the “operational security

    criteria”.

  • Transmission Security Standard Oman Electricity Transmission Company S.A.O.C

    - 28 -

    6.3 Operation – Prevailing System Conditions

    6.3.1 At all times prior to any Secured Event, the OETC licensed transmission system shall

    be operated so as to achieve the outcomes specified in Table 6.1.

    Table 6.1 – Operational outcomes during Prevailing System Conditions

    OETC licensed transmission system

    Operational outcomes during Prevailing System Conditions

    System Equipment loading

    a) System Equipment shall not exceed Pre-Fault Rating levels

    b) System Equipment shall be within the relevant Technical Limits

    c) Circuit-breakers shall not be subjected to fault current in excess of their Technical Limits

    System parameters

    For the OETC licensed transmission system, there shall be:

    a) No Unacceptable Frequency Conditions

    b) Voltage levels within normal conditions

    c) No Insufficient Performance Margins

    System stability There shall be no System Instability

  • Transmission Security Standard Oman Electricity Transmission Company S.A.O.C

    - 29 -

    6.4 Operation – Outcomes following a Fault Outage

    6.4.1 At all times during Prevailing System Conditions and following a specified Fault

    Outage, the OETC licensed transmission system shall be operated to achieve the

    outcomes specified in Table 6.2.

    Table 6.2 – Operational outcomes following a Fault Outage

    OETC licensed transmission system

    Required operational outcomes following a Fault Outage

    Following any one of the following: These outcomes shall be achieved:

    1) A Fault Outage of a single

    Transmission Circuit

    2) A Fault Outage of a single section

    of Busbar, where there are no

    derogations to the design of the

    relevant substation

    3) A Fault Outage of a single GSO

    connection circuit

    4) A Fault Outage of either: (i) a

    single Generation Unit; or (ii) a

    number of Generation Units

    connected to the MITS through a

    single circuit-breaker

    a) No loss of supply to Grid Supply

    Points except as provided for in

    Table 5.5

    b) System Equipment shall be within

    the relevant Technical Limits

    c) No Unacceptable Frequency

    Conditions

    d) No Unacceptable Voltage

    Conditions

    e) No Insufficient Performance

    Margins

    f) No System Instability

  • Transmission Security Standard Oman Electricity Transmission Company S.A.O.C

    - 30 -

    6.5 Managing OETC licensed transmission system conditions and values

    6.5.1 If the any one of the outcomes set out in Table 6.1 and Table 6.2 cannot be achieved,

    then the following actions should be taken, preferably in sequence, until the OETC

    licensed transmission system has been secured such that the outcomes of Table 6.1

    and Table 6.2 are met:

    a Change the system voltage profile by:

    i Adjusting tap changers

    ii Adjusting reactive power compensation equipment

    iii Adjusting excitation of any, or all, Generation Units

    b Through operational switching, adjusting the OETC licensed transmission system configuration and topology

    c Returning System Equipment from any Planned Outage

    d Constraining Production Facilities through temporary disconnection

    e Constraining generation

    f Constraining load and demand

    i Operator initiated load shedding

    ii Automatic load shedding

    6.5.2 Prior to constraining load and demand as contemplated in section 6.5.1f above, and

    to the extent possible, OETC senior management shall be informed of the intended

    operator action.

    6.6 Conditional further operational security criteria

    6.6.1 During Major Risk Periods, OETC shall implement measures to mitigate the

    consequences of this risk. Such measures may include, but are not limited to:

    a Providing additional reserve,

    b Enhancing OETC licensed transmission system voltage prior to expected increases in demand,

    c Securing, as far as possible, appropriate two-circuit combinations, or

    d Reducing system transfers, for example through re-dispatching of Production Facilities or import or export over GSO connections

    6.6.2 If, following a Fault Outage, any one of the outcomes required in section 6.4 is not

    being met, it is acceptable to utilise short-term post-fault actions to avoid

    Unacceptable Overloading of System Equipment which may include a requirement for

    Group Demand reduction; however, this will not be used as a method of increasing

    reserve to cover abnormal post-fault generation reduction. Where possible these

  • Transmission Security Standard Oman Electricity Transmission Company S.A.O.C

    - 31 -

    post-fault actions shall be notified to the appropriate User. Normally the provisions of

    the Grid Code will be applied. This may include emergency manual demand

    disconnection and/or re-dispatching of Production Facilities. Additional post-fault

    actions beyond the Grid Code provisions may be applied, but only where they have

    been agreed in advance with the appropriate Distribution Licensee, Production

    Facility or GSO.

    6.7 Restoration of OETC licensed transmission system following a Secured Event

    6.7.1 Following the occurrence of a Secured Event, measures shall be taken to re-secure

    the system to the above operational security criteria as soon as reasonably

    practicable. To achieve this, it is permissible to put operational measures in place

    before the occurrence of a Secured Event to facilitate the subsequent restoration of

    system security.

    6.8 Variations to operational security criteria

    6.8.1 OETC shall be permitted to submit a derogation application in relation to any

    requirement of the operational security criteria, provided that such derogation

    application is in accordance with the appropriate requirements of the demand

    connection design criteria in section 5.

    6.8.2 Provided it is in accordance with the appropriate requirements of the demand

    connection design criteria, it is acceptable that there may be associated Loss of

    Power Infeed due to a Secured Event, for example by virtue of the design of the

    generation connections, GSO connections and/or the designed switching

    arrangements at the substations concerned. Refer to Table 5.5.

    6.8.3 The principles of the operational security criteria shall be applied at all times except in

    special circumstances where OETC, following consultation with the appropriate User,

    may need to give instructions to the contrary to preserve overall OETC licensed

    transmission system integrity.

  • Transmission Security Standard Oman Electricity Transmission Company S.A.O.C

    - 33 -

    7 DEFINITIONS

    Term Meaning

    Background Conditions For system study purposes, this will include, but not be limited to,

    any parameters that are relevant to the behaviour and dynamics

    of the OETC licensed transmission system, such as:

    a) OETC licensed transmission system configuration

    b) The electrical location and duration of Planned Outages

    and/or Unplanned Outages

    c) Voltage levels at Grid Supply Points

    d) Forecast demand at Grid Supply Points

    e) Transfer Capacity between Demand Groups that may not

    make use of circuits within the OETC licensed transmission

    system

    f) Connected Production Facilities

    g) Dispatched Generation Units

    h) Available Generation Units which have not been dispatched

    i) Energised GSO connection circuits

    Specific Background Conditions required for particular Secured

    Events are specified throughout the TSS

    Busbar The common connection point of two or more Transmission

    Circuits

    Demand Class This is designated by a letter “A” through “F” for the relevant

    Demand Group and the security of supply that should be

    provided for the relevant Demand Group. Refer to Table 5.5 and

    Figure 5.1

    Demand Group A site or group of sites which collectively take power from the

    remainder of the OETC licensed transmission system through a

    Grid Supply Point. Refer to Table 5.5 and Figure 5.1

    Dhofar Power System For the purpose of the TSS, the Dhofar Power System is that part

    of the OETC licensed transmission system that is located in the

    Dhofar Governorate, centred on Salalah, but does not include

    radially connected Generation Units, GSO connections, and/or

    radially connected Grid Supply Points.

  • Transmission Security Standard Oman Electricity Transmission Company S.A.O.C

    - 34 -

    Term Meaning

    Fault Initiation Event When any one of the following occurs:

    a) Fault Outage of a single Transmission Circuit

    b) Fault Outage of a single section of Busbar

    c) Fault Outage of a single GSO connection circuit

    d) Fault Outage of either: (i) a single Generation Unit; or (ii) a

    number of Generation Units, connected to the MITS through

    a single circuit-breaker

    Fault Outage An outage of one or more items of System Equipment,

    Generation Units and/or GSO connection circuits initiated by

    automatic action, unplanned at that time, which may or may not

    involve the passage of fault current

    Generation Circuit The sole electrical connection between one or more Generation

    Units at a Production Facility and the MITS; a radial circuit which,

    if removed, would disconnect one or more Generation Units

    Grid Supply Point

    GSP

    A point of supply from the OETC licensed transmission system to

    any of, or any combination of:

    a) Distribution Licensees

    b) Non-embedded Customers

    Group Demand Means the demand, expressed in MW or MVA, associated with

    the relevant Demand Group

    GSO Means a grid system operator and may mean either an

    international connected party or an internal connected party, or

    both of them, as required by the context.

    A GSO is capable of importing power from and exporting power

    to the OETC licensed transmission system

    High Frequency Limits Means:

    a) If above 50.50 Hz, then returning to be equal to, or below,

    50.50 Hz within 60 seconds; and

    b) Never above 51.50 Hz

    Refer to Table 2.1

    Refer to the Grid Code

  • Transmission Security Standard Oman Electricity Transmission Company S.A.O.C

    - 35 -

    Term Meaning

    Infrequent Infeed Loss Risk

    IILR

    That level of loss of power infeed risk which is covered over long

    periods operationally by frequency response to: (i) avoid a

    deviation of system frequency outside the range 49.50 Hz to

    50.50 Hz for more than 60 seconds; and (ii) never below

    47.50 Hz (Table 2.1).

    As at the approval date, it has a value of:

    For the MITS:

    a) 1,200 MW.

    b) The remaining GSO interconnection circuit rating less any

    import from the GSO interconnection

    For the Dhofar Power System:

    c) 40 MW.

    d) The remaining GSO interconnection circuit rating less any

    import from the GSO interconnection

    Insufficient Performance Margins

    For all time periods, and in particular the during Post-fault

    Periods, there are Insufficient Performance Margins when the

    voltage on any relevant portion of the OETC licensed

    transmission system has values within the range of Unacceptable

    Voltage Conditions and occurs under any one of the following

    conditions:

    a) Based on international best practise, a 5% increase in Group

    Demand above the level prevailing prior to the occurrence of

    the relevant Secured Event; or

    b) The unavailability of any single reactive compensator or other

    reactive power provider; or

    c) The loss of any one automatic switching system or any

    automatic voltage control system for on-load tap changing

    Intact System This is the OETC licensed transmission system with no:

    a) Planned Outages

    b) Unplanned Outages

    c) Fault Outages

  • Transmission Security Standard Oman Electricity Transmission Company S.A.O.C

    - 36 -

    Term Meaning

    Loss of Power Infeed Means the output of a Generation Unit or a group of Generation

    Units or the import from GSO system(s) disconnected from the

    OETC licensed transmission system by a Secured Event, less the

    demand disconnected from the OETC licensed transmission

    system by the same Secured Event.

    For the avoidance of doubt if, following such a Secured Event,

    demand associated with the normal operation of the affected

    Generation Unit or Generation Units is automatically transferred

    to a supply point which is not disconnected from the system, e.g.

    the station board, then this shall not be deducted from the total

    Loss of Power Infeed to the OETC licensed transmission system.

    For the purpose of operational criteria, the Loss of Power Infeed

    includes the output of a single Generation Unit, CCGT module, or

    boiler lost as a result of such an event.

    Low Frequency Limits Means:

    a) If below 49.50 Hz, then returning to above 49.50 Hz within 60

    seconds, and

    b) Never below 47.50 Hz

    Refer also to Table 2.1

    Refer to the Grid Code

    Main Interconnected Transmission System

    MITS

    For the purpose of the TSS, the Main Interconnected

    Transmission System or MITS is that part of the OETC licensed

    transmission system that is interconnected at 400 kV, 220 kV or

    132 kV but does not include radially connected Generation Units,

    GSO connections, and/or radially connected Grid Supply Points.

    For purposes of the TSS, the MITS includes the Dhofar Power

    System unless required otherwise by the context

    Refer to section 3.1 for the Dhofar Power System

    Maintenance Period For MITS: Means the period between 00:00 on 1st October and

    24:00 on 31st March of the next following year.

    For Dhofar: Means the period between 00:00 on 1st July and

    24:00 on 31st March of the next following year.

  • Transmission Security Standard Oman Electricity Transmission Company S.A.O.C

    - 37 -

    Term Meaning

    Maintenance Period Demand

    This is the highest demand during the Maintenance Period, taking

    due account of the Group Demand. If no better forecast is

    possible from the data available, Maintenance Period Demand

    shall be estimated as the Group Demand multiplied by 67%.

    Major Risk Period A Major Risk Period is one during which Secured Events are:

    a) judged to be significantly more likely than under the

    circumstances addressed by the normal TSS criteria, or

    b) judged to have a significantly greater impact than normal, or

    c) events not normally secured against which are judged to be

    significantly more likely than normal such that measures

    should be taken to mitigate their impact

    An example would be country-wide extreme weather conditions

    Momentary Interruption Means a loss of power that lasts for no more than one (1) minute

    from the start of the relevant Fault Initiation Event, with the

    restoration of power intended to be performed by automatic

    equipment

    Non-embedded Customer A customer, except for a Distribution Licensee, receiving

    electricity direct from the OETC irrespective of from whom it is

    supplied

    Normal Infeed Loss Risk

    NILR

    Means that value of lost power infeed that would cause the OETC

    licensed transmission system frequency to fall to a value equal to

    but not below the NILR frequency limit (Table 2.1).

    As at the approval date, and it has a value of:

    For the MITS:

    a) 600 MW

    b) The remaining GSO interconnection circuit rating less any

    import from the GSO interconnection

    For the Dhofar Power System:

    c) 25 MW

    d) The remaining GSO interconnection circuit rating less any

    import from the GSO interconnection

  • Transmission Security Standard Oman Electricity Transmission Company S.A.O.C

    - 38 -

    Term Meaning

    Operational Intertripping The automatic tripping of circuit-breakers to remove OETC

    licensed transmission system Generation Units, GSO

    connections and/or Demand Groups. It does not provide

    additional Transmission Capacity and must not lead to

    Unacceptable Frequency Conditions for any Secured Event

    Peak Demand The estimated summer peak demand (expressed in MW and

    MVar) on the OETC’s licensed transmission system. This

    includes both transmission and distribution losses and represents

    the demand to be met by Generation Units (directly connected or

    embedded) which are connected to OETC’s licensed

    transmission system and by electricity imported into the OETC

    licensed system from GSO systems across GSO connections

    Planned Outage An outage or one or more items of System Equipment,

    Generation Units and/or GSO connections, initiated by manually

    instructed action which:

    a) Shall be confined to the Maintenance Period

    b) Shall be planned at least seven (7) days in advance of the

    event, or as prescribed by the Grid Code

    Post-fault Period Means the period commencing with:

    a) Automatic fault detection, followed by

    b) Automatic fault clearance, followed by

    c) Transient behaviour and

    d) Subsequent recovery to Steady State conditions

    Pre-Fault Rating The OETC specified pre-fault capability of transmission

    equipment. Due allowance shall be made for specific conditions

    (such as ambient or seasonal temperatures), agreed time-

    dependent loading cycles of equipment and any additional

    relevant procedures.

    Refer also to Technical Limit

    Prevailing System Conditions

    These are conditions on the OETC licensed transmission system

    prevailing at any given time and will therefore normally include

    Planned Outages and Unplanned Outages, but excluding any

    Fault Outage

  • Transmission Security Standard Oman Electricity Transmission Company S.A.O.C

    - 39 -

    Term Meaning

    Restricted Period For MITS: Means the period other than the Maintenance Period,

    occurring between 00:00 on 1st April and 24:00 on 30th

    September of any year.

    For Dhofar: Means the period other than the Maintenance

    Period, occurring between 00:00 on 1st April and 24:00 on 30th

    June of any year.

    The period is during which:

    a) No Planned Outage shall occur

    b) Unplanned Outages may only be permitted as prescribed in

    the Grid Code

    c) The summer Peak Demand will occur

    Secured Event A contingency on the OETC licensed transmission system, or any

    part thereof, which shall be considered for the purposes of

    assessing system security and which, should it occur, must not

    result in the remaining parts of the OETC licensed transmission

    system being in breach of the TSS criteria. Secured Events are

    individually specified throughout the TSS. More onerous

    unsecured events may occur and additional operational

    measures within the requirements of the Grid Code may be

    utilised to maintain the overall integrity of the OETC licensed

    transmission system.

    A Secured Event may be caused by, it is not limited to, any of the

    Fault Initiation Events

    Steady State A condition of a power system in which all automatic and manual

    corrective actions, such as, but not limited to, tap changing and

    switching of circuits, have taken place and all of the operating

    quantities that characterise it can be considered constant for the

    purpose of analysis

    Stretched Conditions In respect of either voltage or frequency, or both, when the

    relevant system parameters have values that fall outside the

    limits for disturbed conditions, but have not yet reached the

    values for Unacceptable Conditions

    Refer to Table 2.1

  • Transmission Security Standard Oman Electricity Transmission Company S.A.O.C

    - 40 -

    Term Meaning

    System Condition Has the meaning shown in Table 2.1 and addresses the following

    conditions on the OETC licensed transmission system:

    a) Normal conditions

    b) Disturbed conditions

    c) Stretched Conditions

    d) Unacceptable Conditions

    Refer to Table 2.1

    System Equipment Any equipment installed on the OETC licensed transmission

    system to enable the bulk transfer of electricity. This will include,

    but is not limited to Transmission Circuits, Busbars, transformers,

    reactors, capacitors, circuit-breakers, links, isolators and voltage

    control and management equipment

    System Instability System Instability may occur as a result of:

    a) poor damping – where electromechanical oscillations of

    Generation Units are such that the resultant peak deviations

    in machine rotor angle and/or speed at the end of a 20

    second period remain in excess of 15% of the peak

    deviations at the outset (i.e. the time constant of the slowest

    mode of oscillation exceeds 12 seconds); or

    b) pole slipping – where one or more transmission connected

    synchronous Generation Units lose synchronism with the

    remainder of the system to which it is connected

    For the purpose of assessing the existence of System Instability,

    a Fault Outage is taken to include a solid three phase to earth

    fault (or faults) anywhere on the transmission system with an

    appropriate clearance time. Clearance times used should be

    consistent with the fault location and appropriate to the actual

    protection, signalling equipment, trip and interposing relays, and

    circuit breakers involved in clearing the fault.

  • Transmission Security Standard Oman Electricity Transmission Company S.A.O.C

    - 41 -

    Term Meaning

    Technical Limit These represent the values of technical parameters usually

    specified in type test certificates, which set out the manufacturer

    specified rating for the relevant equipment, usually classified as:

    a) ‘Continuous rating’

    b) ‘Short duration’ or ‘peak rating’

    Values may also be adjusted on the basis of environmental

    conditions such as, but not limited to, ‘ambient temperature’ and

    ‘humidity’

    Refer also to Pre-Fault Rating

    Transfer Capacity That circuit capacity from adjacent Demand Groups which can be

    made available within the times stated in Table 5.5

    Transmission Capacity The ability of a network to transmit electricity. It does not include

    the use of Operational Intertripping except in respect of

    section 5.3.1c

    Transmission Circuit Part of the OETC licensed transmission system between two or

    more circuit-breakers which includes, for example, transformers,

    reactors, cables and overhead lines but excludes Busbars,

    Generation Circuits and GSO connection circuits

    Unacceptable Conditions In respect of either voltage, or frequency, or both, when the

    relevant system parameters have values that fall outside the

    limits for Stretched Conditions.

    Refer to:

    Section 2.2.1d

    Table 2.1

    Unacceptable Frequency Conditions

    These are conditions where the OETC licensed transmission

    system frequency does not meet the criteria for either:

    a) High Frequency Limits, or

    b) Low Frequency Limits

    Refer to:

    Section 2.2.1d

    Section 2.2.2

    Table 2.1

  • Transmission Security Standard Oman Electricity Transmission Company S.A.O.C

    - 42 -

    Term Meaning

    Unacceptable Overloading The overloading of any System Equipment beyond its specified

    time-related capability. Due allowance shall be made for specific

    conditions (such as ambient or seasonal temperature), pre-fault

    loading, agreed time-dependent loading cycles of equipment and

    any additional relevant procedures

    Refer to Pre-Fault Rating and Technical Limit

    Unacceptable Voltage Conditions

    Unacceptable Voltage Conditions occur when the values of

    voltage fall in the Unacceptable Conditions range of values

    Refer to:

    Section 2.2.1d

    Table 2.1

    Unplanned Outage An outage or one or more items of System Equipment,

    Generation Units and/or GSO connections by manually instructed

    action which has not been subject to the recognised outage

    planning process of the Grid Code

    -o0o-


Recommended