+ All Categories
Home > Documents > Upper Hudson River Sediment Remediation

Upper Hudson River Sediment Remediation

Date post: 28-Feb-2022
Category:
Upload: others
View: 5 times
Download: 0 times
Share this document with a friend
1
PROJECT HIGHLIGHTS Phase 1: Cashman Dredging & Marine Contracting worked 24 hours a day, six days a week, for six months, to complete the first phase of work. Ultimately, 288,000 cubic yards (yd 3 ) of sediment were removed, surpassing EPA’s 2009 target. Phase 2: Cashman began the multi-seasoned second phase of work dredging, transporting sediments by barge to the processing facility, and shipping dewatered sediments by rail to disposal facilities. From May through November 2012, Cashman removed +663,000 yd 3 of sediment during the season, far surpassing EPA’s target of 350,000 yd 3 . Cashman also constructed a second unloading wharf at the processing facility during the winter 2012 season to accommodate the large volume of dredged materials. From April through November 2013, +628,000 yd 3 of sediment were removed. e 2014 season commenced in early May; good weather and low river flows allowed Cashman to remove +583,000 yd 3 , again exceeding goals. During the project, dredging techniques and technologies were refined, which enabled industry-leading dredging precision while also increasing dredge productivity across a wide range of varied site conditions, from extremely shallow water to work in front of dams. e final season of dredging was performed from May to October 2015 and approximately 250,000 yd 3 of PCB-impacted sediment was removed. Upper Hudson River Sediment Remediation Location: Upper Hudson River, Fort Edward - Troy, NY Contractor: Cashman Dredging & Marine Contracting Company, LLC Subcontractor: Clean Earth Contract Completion: 2015 Dollar Value: Confidential Material Disposal: Upland Disposal Volume: 2,700,000 yd 3 Awarding Authority / Owner: General Electric Cashman Dredging was part of the “world-class team” assembled to conduct the largest PCB sediment remediation project in U.S. history. More than 2.76 million yd 3 of sediment from a 40-mile stretch of the upper Hudson River between Fort Edward and Troy, NY were removed, and 100 percent of the PCBs targeted by the EPA were addressed. T: 617-890-0600 | F: 617-890-0606 | 549 South Street, Quincy, MA 02169 | [email protected] FORT EDWARD - TROY, NEW YORK
Transcript

PROJECT HIGHLIGHTS

– Phase 1: Cashman Dredging & Marine Contracting worked24 hours a day, six days a week, for six months, to completethe first phase of work. Ultimately, 288,000 cubic yards (yd3) ofsediment were removed, surpassing EPA’s 2009 target.

– Phase 2: Cashman began the multi-seasoned second phaseof work dredging, transporting sediments by barge to theprocessing facility, and shipping dewatered sediments by rail todisposal facilities.

– From May through November 2012, Cashman removed+663,000 yd3 of sediment during the season, far surpassingEPA’s target of 350,000 yd3.

– Cashman also constructed a second unloading wharf atthe processing facility during the winter 2012 season toaccommodate the large volume of dredged materials.

– From April through November 2013, +628,000 yd3 of sedimentwere removed.

– The 2014 season commenced in early May; good weather andlow river flows allowed Cashman to remove +583,000 yd3, again exceeding goals.

– During the project, dredging techniques and technologies wererefined, which enabled industry-leading dredging precisionwhile also increasing dredge productivity across a wide rangeof varied site conditions, from extremely shallow water to workin front of dams.

– The final season of dredging was performed from May toOctober 2015 and approximately 250,000 yd3 of PCB-impactedsediment was removed.

Upper Hudson River Sediment Remediation

Location: Upper Hudson River,Fort Edward - Troy, NY

Contractor: Cashman Dredging & Marine Contracting Company, LLC

Subcontractor: Clean Earth

Contract Completion: 2015

Dollar Value: Confidential

Material Disposal: Upland Disposal

Volume: 2,700,000 yd3

Awarding Authority / Owner:

General Electric

Cashman Dredging was part of the “world-class team” assembled to conduct the largest PCB sediment remediation project in U.S. history. More than 2.76 million yd3 of sediment from a 40-mile stretch of the upper Hudson River between Fort Edward and Troy, NY were removed, and 100 percent of the PCBs targeted by the EPA were addressed.

T: 617-890-0600 | F: 617-890-0606 | 549 South Street, Quincy, MA 02169 | [email protected]

F O R T E D W A R D - T R O Y , N E W Y O R K

Recommended