Date post: | 28-Dec-2015 |
Category: |
Documents |
Upload: | muriel-todd |
View: | 215 times |
Download: | 0 times |
1
Copper Stabilizer Continuity Measurement Project
CSCM Mini ReviewPowering Implementation
H. Thiesen 30 November 2011
2
CSCM powering implementation
Outline• Voltage and current requirements• Modification of RB power converter• RB circuit powering configuration• RQ circuit powering configuration• How to power RQ circuits with RB power converter?• Validation tests before CSCM of RB circuit• Validation tests before CSCM of RQD and RQF circuits• Preparation phase (summary)• Powering tests• Recovery phase• Conclusion
H. T
hie
sen
– 3
0 N
ove
mb
er 2
011
3
Voltage and current requirements
t1 t2
500 A
4-6 kA
60 s
PC in voltage mode PC in current mode
Trip by mQPS th
T = 20 K
I
t
• The initial objective of the project was a possible increase of LHC energy at 5 TeV in 2012.
• CSCM consists to warm up the arc at 20 K and to generate current pulses (4-6 kA) inside the circuit.
• The magnets are not superconducting
• The current passes through the by pass diodes
H. T
hie
sen
– 3
0 N
ove
mb
er 2
011
4
Voltage and current requirements
• Assumption (to be verified): 1.7 < Vdiode < 2 V at 20 K
• The magnets are not superconducting (30 mW/0.1H)
• The current passes through the by pass diodes
RB circuit
[6kA
/300
V]
Open circuit Short circuit
RQ circuits (in series)
[6kA
/250
V]
Open circuit Short circuit
H. T
hie
sen
– 3
0 N
ove
mb
er 2
011
The actual power converter ratings are RB=[13kA/±190V] and RQ=[13kA/18V]=> New 2MW power converters
5
• CSCM requires [6kA,300V] power converters (for 5 TeV)
• Connect in series both RB power converters (UAx3 and UAx7)
• [13kA,380V] can be reach with this solution
• 500 m between the power converters
• How to control the both converters (2 independent electronics)?
• Modify the RB power converter
• Normal configuration: 2 bridges in // to reach [13kA,190V]
• CSCM configuration: 2 bridges in series to reach [6.5kA,380V]
Þ Modification of actual RB power converter configuration:• Individual system tests (IST) before to power the circuits
Þ Same converter for the 3 main circuits (RB, RQD and RQF)• Hardware intervention between two measurements
Voltage and current requirementsH
. Th
iese
n –
30
No
vem
ber
201
1
6
Modification of RB power converter
• RB power converter modification
(+)
(-)
6x240mm2
• Put in series the both thyristor bridges• Change Vout_meas• Put output diode to suppress voltage
oscillations (before DCCTs)
100 W
100 W
H. T
hie
sen
– 3
0 N
ove
mb
er 2
011
7
Modification of RB power converter
• Results of P-Hall
Tests in P-Hall with 4 W load
U_bridge
U_out
U_out
I_out
H. T
hie
sen
– 3
0 N
ove
mb
er 2
011
-1000
0
1000
2000
3000
4000
5000
6000
7000
0 0.05 0.1 0.15 0.2 0.25 0.3 0.35
2*EE
0*EE
8
RB circuit powering configuration
• RB powering configuration
• To reduce voltage constraint in case of switch opening (2 kV at 6 kA) which can damage the circuit or the diodes, it is important to short circuit the both EE systems (do not forget to remove the SC after the tests)
• In this configuration the diode voltages are enough to discharge quickly the energy stored in the circuit in case of runaway
RB 300 V300V
1x240mm2 1x240mm2Rearth(500V)
time (s)
current (A)
< 350 ms
Þ max. voltage to earth in case of fault is #400 V at 20K
0V150V
150V300V
Þ Minimal impact on EE system, IST (before and after CSCM) is not needed
Vdiode = 0.7 VL = 5 mHVout Pc = 0V
H. T
hie
sen
– 3
0 N
ove
mb
er 2
011
9
From Standard ELQA procedure (Edms:788197)
From SM18 Test benches:
Proposed ELQA Test for CSCM
Pressure in the cold masses of the ARC: P > 5.5 bar (> 4.0 bar is acceptable)
Pressure in the DFBAs: P > 1.8 bar (same condition as TP4-C)
Circuit @ 300 K, p=1 bar @ 1.9 K p=1 bar
Main Dipole vs GND 600 V 600 V, 1900 V and 3100 V
Circuit TP4-C,T=80K, p=6 bar
TP4-E,T=1.9K, p=1 bar
Main Dipole vs GND 600 V 1900 V
Circuit Max Voltage expected
@20 K
ELQA HVQ,T=20 K, p> 5.5 bar (>
4.0 bar)
Max leakage current after 300s.
Main Dipole vs GND 400 V 600 V (standard value) 50 µA
From G. D’AngeloH. T
hie
sen
– 3
0 N
ove
mb
er 2
011
RB circuit powering configuration
10
RB circuit powering configuration
• Impact on the PIC (Power Interlock Controller – link between QPS and PC)
• PIC is an important element for the protection of the circuit during CSCM.
• PPermit (software INTK with mainly cryo and UPS conditions) is needed to run
• Global abort must be disabled
• CS (cryo start) and CM (cryo maintain) must be disabled
• UPS OK will be maintained during the CSCM to avoid hardware modification of this signal => UPSs (both points) must be operational
• Other impact
• Electrical distribution must be operational
• Water distribution must be operational
H. T
hie
sen
– 3
0 N
ove
mb
er 2
011
11
RQ circuit powering configuration
• 2 possible configurations
• Individual CSCM configuration
• Series CSCM configuration
RQF
Þ Easier to realize
Þ More realistic for the by pass diodes
RQD
RQF
RB Earth system
RB Earth system
RB
RB
RQF EE system
RQF EE system
RQD EE system
H. T
hie
sen
– 3
0 N
ove
mb
er 2
011
12
RQ circuit powering configuration
• Series configuration
• To reduce voltage constraints for the circuit at 20K (magnet to ground) we propose to short circuit one EE system
0
1000
2000
3000
4000
5000
6000
7000
0 0.2 0.4 0.6 0.8 1 1.2
2*EE
1*EE
0*EE
0.25
0.36
0.85
time (s)
current (A)Vdiode = 0.7 VL = 10 mHVout PC = 0 V
RQD
RQF
RB300V
0V
0V
-150V
150V
75V
-75V
0V
(-300V)
RB Earth system
RQF EE system
RQD EE system
Þ max. voltage to earth in case of fault is #300 V at 20K
H. T
hie
sen
– 3
0 N
ove
mb
er 2
011
13
From Standard ELQA procedure (Edms:788197)
From SM18 Test benches:
Proposed ELQA Test for CSCM
Pressure in the cold masses of the ARC: P > 5.5 bar (> 4.0 bar is acceptable)
Pressure in the DFBAs: P > 1.8 bar (same condition as TP4-C)
Circuit @ 300 K, p=1 bar @ 1.9 K p=1 bar
Main Quad vs GND 180 V 180 V, 900 V
Circuit TP4-C,T=80K, p=6 bar
TP4-E,T=1.9K, p=1 bar
Main Quad vs GND 120 V 240 V
Circuit Max Voltage expected @20 K
ELQA HVQ,T=20 K, p> 5.5 bar
(> 4.0 bar)
Max leakage current after
300s.
Main Quad vs GND 200 V one by one, or 300 V both in series
360 V(max voltage*1.2)
20 µA
ELQA under this condition has not been done before, but it should not be a problem!
H. T
hie
sen
– 3
0 N
ove
mb
er 2
011
RQ circuit powering configuration
From G. D’Angelo
14
How to power RQ circuits with RB power converter?
• DC connection
• Link RQ circuits to RB power converter with 6x240mm2 DC cables at the power converter level (can be done during RB modifications)
6x240mm2 (1.25 mW)
RQF RQD RB
RB power converterRQD power converterRQF power converter
H. T
hie
sen
– 3
0 N
ove
mb
er 2
011
15
How to power RQ circuits with RB power converter?
• Earth fault detection system
• Connect the RB earth fault detection system to the middle point of RQ discharge resistor (IST before and after CSCM of RQ circuits)
• Remote control
• Change the WorldFIP address by using “derivFIP” (IST before and after CSCM of RQ circuits)
• PIC
• Link the RQ PIC signals to RB power converter
Interface Box *
to RB power converterto RQD PIC
to RQF PIC
* not needed if individual powering
H. T
hie
sen
– 3
0 N
ove
mb
er 2
011
16
• PIC interface box
• Signal exchanged between power converters and PIC
• Cable connected => use only RQD signal (RQF signal short circuited)
• PC failure => use only RQD signal (RQF signal short circuited)
• SwOpRq => use only RQD signal (RQF signal short circuited)
• PPermit => put the both signals in series
• FastPA => Put the both signals in series
How to power RQ circuits with RB power converter?
RB converter
PIC_RQD
PIC_RQF
Signal from power converter to PIC
Signal from PIC to power converter
• Other external interlocks
• water cooled DC cables (not used)
• Current lead thermal switches (not installed today)
RB converter
PIC_RQD
PIC_RQF
H. T
hie
sen
– 3
0 N
ove
mb
er 2
011
17
Validation tests before CSCM of RB circuit
• Individual System Test (IST)
• CSCM needs important modification of powering circuits (RB, RQD and RQF) => Validation tests before CSCM
• The 1st step is to valid the “new-RB” power converter with external resistor
• Local tests
• Safety issues are limited
H. T
hie
sen
– 3
0 N
ove
mb
er 2
011
18
Validation tests before CSCM of RB circuit
• PIC tests
• PIC tests are the second step of the powering validation
• Objective of these tests is to validate the circuit protection system
• PPermit
• FastPA
• PCfailure
• Condition for the PIC tests
• Ready to powering but new-RB power converter still connected to the 4W load (not connected to the circuits).
• PIC tests are done from the CCC
• Safety issues are limited
• Question: Do we need to repeat PIC tests with current?
After IST of PC (and IST of QPS) and PIC tests=>
Green light for CSCM
H. T
hie
sen
– 3
0 N
ove
mb
er 2
011
19
Validation tests before CSCM of RQD and RQF circuits
• Individual System Test (IST)
• IST of new-RB power converter is needed except if it done before for CSCM of RB circuit
• Check of the address of new-RB power converter
• PIC tests
• new-RB power converter must be connected (or reconnected) to 4 W load. tests
• PIC tests are done from the CCC
• Interaction with Xmas stop is limited
• Safety issues are limited
H. T
hie
sen
– 3
0 N
ove
mb
er 2
011
20
Preparation phase (summary)
• Different tasks
• Modification of RB power converter
• Installation of EE system short circuits (both RB and RQF)
• Installation of DC cables between RB power converter and RQD and RQF water colled DC cables (at the power converter level)
• PIC software straps (global abort, CS and CM)
• Installation of the PIC interface box
• Installation of the DerivFIP
• Modification of RQ Earth point (between RB CSCM and RQ CSCM)
• IST of new-RB power converter
• PIC tests for RB CSCM
• PIC tests for RQ CSCM (between RB CSCM and RQ CSCM).
• Time and Resources
• 2 weeks and 1 extra day between RB CSCM and RQ CSCM
• 1 Engineer + 2 power technicians + 2 electro-mechanics
H. T
hie
sen
– 3
0 N
ove
mb
er 2
011
21
Powering tests
• Open issues
• Identification of the CSCM loads (magnets with diodes in parallel)
• Behavior of new-RB power converter with the CSCM loads
• Start up and current regulation of new-RB power converter with the CSCM loads
• Time and Resources
• 2 weeks (with the reconfiguration day between RB CSCM and RQ CSCM)
• 1 Engineer + 1 power technician
H. T
hie
sen
– 3
0 N
ove
mb
er 2
011
22
Recovery phase
• Different tasks
• Reconfiguration of RB power converter
• Remove EE system short circuits (both RB and RQF)
• Remove DC cable between RB power converter and RQD and RQF water colled DC cable (at the power converter level)
• Remove PIC software straps (global abort, CS and CM)
• Remove the PIC interface box
• Remove the DerivFIP
• Change RQ Earth point (between RB CSCM and RQ CSCM)
• IST of RB power converter
• PIC tests for RB power converter
• PIC tests for RQ power converters
• Time and Resources
• 2 weeks and 1 extra day between RB CSCM and RQ CSCM
• 1 Engineer + 2 power technicians + 2 electro-mechanics
H. T
hie
sen
– 3
0 N
ove
mb
er 2
011
23
Conclusion
• CSCM requests important modifications of main circuits (RB, RQD and RQF)
• Power converter, EE systems, PIC, QPS
• IST and PIC tests are needed before CSCM and between RB CSCM and RQ CSCM
• Still open issues mainly linked with the power converter control with the CSCM loads
• Full recommissioning (PIC1, PCC, PIC2, PLI1, etc…) of the main circuits after CSCM.
• CSCM tests can be done only by specialists and time is needed.
• Tests procedure must be written and approved
H. T
hie
sen
– 3
0 N
ove
mb
er 2
011
24H. T
hie
sen
– 3
0 N
ove
mb
er 2
011