Date post: | 14-Apr-2018 |
Category: |
Documents |
Upload: | alpine-classes |
View: | 217 times |
Download: | 0 times |
of 12
7/30/2019 2.1 IACS-Reduction of GHG Emissions-rev-1(1)
1/12
2.1 Reduction of GHG emissions
Energy Efficiency Design Index
Tripartite 18-19 September 2009
Pierre C. Sames
Chairman IACS EG/ENV
7/30/2019 2.1 IACS-Reduction of GHG Emissions-rev-1(1)
2/12
Tripartite Seoul - 2009-09-18 and -19 2last modified: 2009-09-14, PCS/GL
Contents
EEDI verification
two stages
reference speed
electrical power
table
EEDI baselines
guidelines
correction factors
EEDI safety impact
minimum speed
Outlook
7/30/2019 2.1 IACS-Reduction of GHG Emissions-rev-1(1)
3/12
Tripartite Seoul - 2009-09-18 and -19 3last modified: 2009-09-14, PCS/GL
Introduction
The EEDI guidelinesconsolidate the results of
the discussions from five
sessions.
The formulation for the
EEDI has matured and itcan now be thoroughly
tested, at least for the
dominant ship types.
However, issues related to
verification and applicationremain open and these
issues are discussed in the
following.
7/30/2019 2.1 IACS-Reduction of GHG Emissions-rev-1(1)
4/12
Tripartite Seoul - 2009-09-18 and -19 4last modified: 2009-09-14, PCS/GL
Two-stage EEDI verification (1/2)
The two-stage verification process for the EEDI wasconfirmed and agreed.
In the view of IACS, the first phase of theverification process should be limited to anexamination of input parameters, without a formal
approval.
data examination of input parameters, to checkcompliance with EEDI requirements beforeproceeding with the construction,
sea trials verification to formally verify the shipsEEDI.
It is underlined that some EEDI elements cannot andshould not be checked before construction andduring sea trials. In this sense, guidance is needed.
7/30/2019 2.1 IACS-Reduction of GHG Emissions-rev-1(1)
5/12
Tripartite Seoul - 2009-09-18 and -19 5last modified: 2009-09-14, PCS/GL
Two-stage EEDI verification (2/2)
7/30/2019 2.1 IACS-Reduction of GHG Emissions-rev-1(1)
6/12
Tripartite Seoul - 2009-09-18 and -19 6last modified: 2009-09-14, PCS/GL
EEDI verification what if?
When a vessel fails to meet the required EEDI,enforced speed reduction is the most powerful
measure.
EEDI for typical 5000 TEU vessel (65.000 DWT)
024
68
101214161820
15 17 19 21 23 25
Speed (knots)
gCO2/(t*nm)
EEDI attained
EEDI required
7/30/2019 2.1 IACS-Reduction of GHG Emissions-rev-1(1)
7/12
Tripartite Seoul - 2009-09-18 and -19 7last modified: 2009-09-14, PCS/GL
EEDI verification reference speed
The estimate of the reference speed during designis performed with established methods and tools
such as speed-power tables.
The EEDI condition (full load for most ship types -
at 75% MCR) likely cannot be checked during sea
trials. Therefore, an appropriate method (e.g. ISO
15016) needs to be agreed.
Speed power curves of sea trial and full load
conditions and an outline of the estimation method
of power curves should be provided by theshipbuilder. This is highly sensitive data!
IACS shares CESA concerns that sensitive data
requires efficient measures of know-how protection
in the context of the EEDI verification.
7/30/2019 2.1 IACS-Reduction of GHG Emissions-rev-1(1)
8/12
Tripartite Seoul - 2009-09-18 and -19 8last modified: 2009-09-14, PCS/GL
EEDI verification electrical power
balance table
Verification of the electrical power balance isrequired for vessels with diesel-electric propulsion
and when a direct calculation of auxiliary power is
performed.
CLIA provided a draft guidance for the verification
of this table in MEPC 59/4/28.
IACS has started contributing to the development of
such guidance.
A workshop with industry is being organised by
IACS to align state of the art approval with EEDI-
related verification requirements.
This workshop is planned for beginning of
November 2009, at IACS offices in London.
7/30/2019 2.1 IACS-Reduction of GHG Emissions-rev-1(1)
9/12
Tripartite Seoul - 2009-09-18 and -19 9last modified: 2009-09-14, PCS/GL
EEDI baselines
The baseline format wasconfirmed.
The [WG] Chairmansuggested that calculationfor obtaining the parameterof a and c in the formulashould be conducted in a
transparent manner withinthe Organization.
A guidance for computingbaselines is needed.
IACS pointed to relevantissues when baselines arecomputed (MEPC 59/4/44). Inparticular, contact to theoriginal data provider LRFPshould be established toensure correct use of data.
Key results of sampling for EEDI baseline
input data (100 samples)
50
60
70
80
90
100
0 10 20 30 40
percent difference
nosamp
les
(cumulat
ed)
Installed main power
Capacity
7/30/2019 2.1 IACS-Reduction of GHG Emissions-rev-1(1)
10/12
Tripartite Seoul - 2009-09-18 and -19 10last modified: 2009-09-14, PCS/GL
EEDI correction factors for CSR
China suggested to develop correctionfactors for CSR bulk carriers (MEPC
59/4/20).
IACS agrees that with application of CSR,
hull steel weight would increase and CSR
vessels will be penalised when a baseline
is derived without taking CSR vessels into
account.
IACS is currently collecting relevant
information and is open in principle to a
possible co-sponsoring of a submission.
7/30/2019 2.1 IACS-Reduction of GHG Emissions-rev-1(1)
11/12
Tripartite Seoul - 2009-09-18 and -19 11last modified: 2009-09-14, PCS/GL
EEDI minimum speed
With an EEDI implemented, IACS isconcerned that installed main engine
power might be reduced to a minimum.
It was asked twice recently (ITF and ICS)
which minimum speed (and associated
minimum installed power) would guarantee
safe operation even in adverse conditions.
IACS recommends that such reserves andmargins are credited and appropriate
correction factors are included in the EEDI
to take account of these.
7/30/2019 2.1 IACS-Reduction of GHG Emissions-rev-1(1)
12/12
Tripartite Seoul - 2009-09-18 and -19 12last modified: 2009-09-14, PCS/GL
Outlook
IACS continuescontributing to the
development of the EEDI.
IACS also sees the industry
challenge to meet a
possible future emission
target.