+ All Categories
Home > Documents > ATPS - Security Analysis S8

ATPS - Security Analysis S8

Date post: 07-Apr-2018
Category:
Upload: ashwin-gopinath
View: 218 times
Download: 0 times
Share this document with a friend

of 18

Transcript
  • 8/6/2019 ATPS - Security Analysis S8

    1/18

    Security AnalysisSecurity Analysis

    To execute very quickly 3basic ways

    Study PS with approximate but very fast

    algorithms

    Select only important cases for detailed analysis

    Use computer system made up of multipleprocessors

  • 8/6/2019 ATPS - Security Analysis S8

    2/18

    Approximate ModelApproximate Model

    Various names: D factor methods

    Linear sensitivity methods

    DC power flow methods

    Linear sensitivity method Only branch MW flows are calculated (within 5% accuracy)

    No knowledge of MVAR flows & voltage magnitudes

  • 8/6/2019 ATPS - Security Analysis S8

    3/18

    Contingency SelectionContingency Selection

    This technique is also called Contingency Screening

    Eliminate all or most of the nonviolation cases

    Only run complete power flows on critical cases

  • 8/6/2019 ATPS - Security Analysis S8

    4/18

    Computer systemComputer system

    Many processors

    Running separate cases

    In parallel

  • 8/6/2019 ATPS - Security Analysis S8

    5/18

    Linear Sensitivity FactorsLinear Sensitivity Factors

    One of the easiest ways to provide quick calculation

    of possible overloads

    Show approximate change in line flows for changesin generation on the network configuration

    Derived from DC load flow

    Basically TWO typesGeneration shift factors

    Line outage distribution factors

  • 8/6/2019 ATPS - Security Analysis S8

    6/18

    Generation shift factorsGeneration shift factors(Linear estimates)(Linear estimates)

    Defined as

    i

    lli

    P

    fa

    (

    (!

    !l Line index

    where

    !i Bus index

    !( lf Change in MW power flow on linel

    when a change ingeneration occurs at bus i

    !(i

    P Change in generation at bus i

  • 8/6/2019 ATPS - Security Analysis S8

    7/18

    Assumption:

    Change in generation is exactlycompensated by an opposite change in

    generation at the reference bus

    All other generators remain fixed

    Then the factor represents the

    sensitivity of the flow on the line l to achange in generation at bus i

    iP(

    ia

  • 8/6/2019 ATPS - Security Analysis S8

    8/18

    Case 1:Case 1:

    Outage of a large generating unitOutage of a large generating unit

    Assumed that all the generation lost would be made up by the

    reference generation

    If generator was generating MW, and it was lost

    New power flow on each line could be calculated using a

    precalculated set of a factors as follows

    forl= 1..L

    r

    iP

    iPr

    iP

    ilill Paff S

  • 8/6/2019 ATPS - Security Analysis S8

    9/18

    Outage flow on each line can be compared to its limit

    Those exceeding their limit is flagged for alarming. i.e.loss of generator on bus i would result in an overload online l

    Using Superposition, the effects of simultaneous changeson several generating buses can be calculated (since aare Linear estimates)

    !

    lf Flow on line lafter the generator on bus ifails

    !

    lf Flow before the failure

    lf

  • 8/6/2019 ATPS - Security Analysis S8

    10/18

    Case 2 : Loss of generator on bus iwere

    compensated by governor action throughoutthe interconnected system

    Assumption :

    Remaining generators pick up in proportion to theirmaximum MW rating

    Thus, the proportion of generation pick up fromunit j (j i) would be

    !

    k

    k

    j

    jiP

    P

    max

    max

    K

    k i

  • 8/6/2019 ATPS - Security Analysis S8

    11/18

    Flow on line l, under the assumption that all the

    generators in the interconnection participate inmaking up the loss

    Assumes that no unit will actually hit its maximum

    More detailed generation pick up algorithm that took

    account of generation limits would be required, if

    this is apt to be the case

    !maxk

    P Maximum MW rating for generator k

    !jiK Proportionality factor for pick up on generating

    unit jwhen unit ifails

    {

    ((ij

    ijiljilill PaPaff ][ KS

  • 8/6/2019 ATPS - Security Analysis S8

    12/18

    Line outage distribution factorsLine outage distribution factors

    Apply to the testing for overloads whentransmission circuits are lost

    S

    k

    lkl

    f

    fd

    (!

    , where

    !kld ,

    !( lf

    !S

    kf

    Line outage distribution factor when monitoring line

    lafter an outage on line k

    Change in MW flow on line l

    Original flow on line kbefore it was outaged

  • 8/6/2019 ATPS - Security Analysis S8

    13/18

    If power on line l & line k is known, the flow on line l with line k out

    can be determined using d factors

    By precalculating line outage distribution factors, a very fast

    procedure can be set up to test all lines in the network for overload

    for the outage of a particular line

    This procedure can be repeated for the outage of each line in turn,

    with overloads reported to the operations personnel in the form of

    alarm messages

    SS

    kklll fdff ,!

    !kl ff , Preoutage flows on lines l& k, respectively

    !

    lf Flow on line lwith line kout

  • 8/6/2019 ATPS - Security Analysis S8

    14/18

    Contingency analysis usingContingency analysis usingsensitivity factorssensitivity factors

  • 8/6/2019 ATPS - Security Analysis S8

    15/18

  • 8/6/2019 ATPS - Security Analysis S8

    16/18

    Line flows must be checked against - as well as

    Assumptions:

    1. Generator output for each of the generators in the system is

    available

    Line flow for each transmission line in the network is also available

    (satisfied with telemetry system or with state estimation technique)

    max

    lfmax

    lf

  • 8/6/2019 ATPS - Security Analysis S8

    17/18

    2. Sensitivity factors have been calculated & stored & they are

    correct

    (Valid as long as transmission network has not undergone any

    significant switching operations that would change its structure -

    have provision for updating the factors when the network is

    switched)

    3. All generation pick up will be made on the reference bus

    (If this is not the case, substitute the corresponding equation in

    generator outage loop)

  • 8/6/2019 ATPS - Security Analysis S8

    18/18

    ReferenceReference

    AllenAllen JJ..WoodWood andand BruceBruce FF..Woolenberg,Woolenberg,

    PowerPower generation,generation, operationoperation andand control,control,JohnJohn WileyWiley && sonssons IncInc..


Recommended