Date post: | 07-Apr-2018 |
Category: |
Documents |
Upload: | ashwin-gopinath |
View: | 218 times |
Download: | 0 times |
of 18
8/6/2019 ATPS - Security Analysis S8
1/18
Security AnalysisSecurity Analysis
To execute very quickly 3basic ways
Study PS with approximate but very fast
algorithms
Select only important cases for detailed analysis
Use computer system made up of multipleprocessors
8/6/2019 ATPS - Security Analysis S8
2/18
Approximate ModelApproximate Model
Various names: D factor methods
Linear sensitivity methods
DC power flow methods
Linear sensitivity method Only branch MW flows are calculated (within 5% accuracy)
No knowledge of MVAR flows & voltage magnitudes
8/6/2019 ATPS - Security Analysis S8
3/18
Contingency SelectionContingency Selection
This technique is also called Contingency Screening
Eliminate all or most of the nonviolation cases
Only run complete power flows on critical cases
8/6/2019 ATPS - Security Analysis S8
4/18
Computer systemComputer system
Many processors
Running separate cases
In parallel
8/6/2019 ATPS - Security Analysis S8
5/18
Linear Sensitivity FactorsLinear Sensitivity Factors
One of the easiest ways to provide quick calculation
of possible overloads
Show approximate change in line flows for changesin generation on the network configuration
Derived from DC load flow
Basically TWO typesGeneration shift factors
Line outage distribution factors
8/6/2019 ATPS - Security Analysis S8
6/18
Generation shift factorsGeneration shift factors(Linear estimates)(Linear estimates)
Defined as
i
lli
P
fa
(
(!
!l Line index
where
!i Bus index
!( lf Change in MW power flow on linel
when a change ingeneration occurs at bus i
!(i
P Change in generation at bus i
8/6/2019 ATPS - Security Analysis S8
7/18
Assumption:
Change in generation is exactlycompensated by an opposite change in
generation at the reference bus
All other generators remain fixed
Then the factor represents the
sensitivity of the flow on the line l to achange in generation at bus i
iP(
ia
8/6/2019 ATPS - Security Analysis S8
8/18
Case 1:Case 1:
Outage of a large generating unitOutage of a large generating unit
Assumed that all the generation lost would be made up by the
reference generation
If generator was generating MW, and it was lost
New power flow on each line could be calculated using a
precalculated set of a factors as follows
forl= 1..L
r
iP
iPr
iP
ilill Paff S
8/6/2019 ATPS - Security Analysis S8
9/18
Outage flow on each line can be compared to its limit
Those exceeding their limit is flagged for alarming. i.e.loss of generator on bus i would result in an overload online l
Using Superposition, the effects of simultaneous changeson several generating buses can be calculated (since aare Linear estimates)
!
lf Flow on line lafter the generator on bus ifails
!
lf Flow before the failure
lf
8/6/2019 ATPS - Security Analysis S8
10/18
Case 2 : Loss of generator on bus iwere
compensated by governor action throughoutthe interconnected system
Assumption :
Remaining generators pick up in proportion to theirmaximum MW rating
Thus, the proportion of generation pick up fromunit j (j i) would be
!
k
k
j
jiP
P
max
max
K
k i
8/6/2019 ATPS - Security Analysis S8
11/18
Flow on line l, under the assumption that all the
generators in the interconnection participate inmaking up the loss
Assumes that no unit will actually hit its maximum
More detailed generation pick up algorithm that took
account of generation limits would be required, if
this is apt to be the case
!maxk
P Maximum MW rating for generator k
!jiK Proportionality factor for pick up on generating
unit jwhen unit ifails
{
((ij
ijiljilill PaPaff ][ KS
8/6/2019 ATPS - Security Analysis S8
12/18
Line outage distribution factorsLine outage distribution factors
Apply to the testing for overloads whentransmission circuits are lost
S
k
lkl
f
fd
(!
, where
!kld ,
!( lf
!S
kf
Line outage distribution factor when monitoring line
lafter an outage on line k
Change in MW flow on line l
Original flow on line kbefore it was outaged
8/6/2019 ATPS - Security Analysis S8
13/18
If power on line l & line k is known, the flow on line l with line k out
can be determined using d factors
By precalculating line outage distribution factors, a very fast
procedure can be set up to test all lines in the network for overload
for the outage of a particular line
This procedure can be repeated for the outage of each line in turn,
with overloads reported to the operations personnel in the form of
alarm messages
SS
kklll fdff ,!
!kl ff , Preoutage flows on lines l& k, respectively
!
lf Flow on line lwith line kout
8/6/2019 ATPS - Security Analysis S8
14/18
Contingency analysis usingContingency analysis usingsensitivity factorssensitivity factors
8/6/2019 ATPS - Security Analysis S8
15/18
8/6/2019 ATPS - Security Analysis S8
16/18
Line flows must be checked against - as well as
Assumptions:
1. Generator output for each of the generators in the system is
available
Line flow for each transmission line in the network is also available
(satisfied with telemetry system or with state estimation technique)
max
lfmax
lf
8/6/2019 ATPS - Security Analysis S8
17/18
2. Sensitivity factors have been calculated & stored & they are
correct
(Valid as long as transmission network has not undergone any
significant switching operations that would change its structure -
have provision for updating the factors when the network is
switched)
3. All generation pick up will be made on the reference bus
(If this is not the case, substitute the corresponding equation in
generator outage loop)
8/6/2019 ATPS - Security Analysis S8
18/18
ReferenceReference
AllenAllen JJ..WoodWood andand BruceBruce FF..Woolenberg,Woolenberg,
PowerPower generation,generation, operationoperation andand control,control,JohnJohn WileyWiley && sonssons IncInc..