+ All Categories
Home > Documents > CNS In-pile Replacement Project · 2. Project dose constraint –10 mSv for any individual 3....

CNS In-pile Replacement Project · 2. Project dose constraint –10 mSv for any individual 3....

Date post: 11-Oct-2020
Category:
Upload: others
View: 1 times
Download: 0 times
Share this document with a friend
23
CNS In-pile Replacement Project W. Bermudez and A. Eltobaji December 2017
Transcript
Page 1: CNS In-pile Replacement Project · 2. Project dose constraint –10 mSv for any individual 3. Project dose target –5 mSv per person 4. Design target –2.5 mSv per person • CNS

CNS In-pile Replacement Project

W. Bermudez and A. Eltobaji

December 2017

Page 2: CNS In-pile Replacement Project · 2. Project dose constraint –10 mSv for any individual 3. Project dose target –5 mSv per person 4. Design target –2.5 mSv per person • CNS

COREPCS PIPE

The CNS In-Pile is a 3m tall

structure and it goes here

CRYO-PIPE

What is the project?• To replace the Cold Neutron Source (CNS) as it is

approaching the end of its design life.

Page 3: CNS In-pile Replacement Project · 2. Project dose constraint –10 mSv for any individual 3. Project dose target –5 mSv per person 4. Design target –2.5 mSv per person • CNS

Why do we need to replace it?• Moderator vessel is made from AlMg5.

• Thermal neutrons cause damage to Al

alloys through transmutation – Al

transmuted to Si.

• Si is insoluble in Al and will form particles

or potentially Mg2Si particles – solution

hardening.

• Fast neutrons displace Al atoms from their

initial lattice position => point defects and

dislocations => more susceptible to

cracking.

Page 4: CNS In-pile Replacement Project · 2. Project dose constraint –10 mSv for any individual 3. Project dose target –5 mSv per person 4. Design target –2.5 mSv per person • CNS

Life extension of the CNS In-pile

• Manufacturer’s rated design life is 10

years at full power. This will come in

early 2019.

• No real data for AlMg5 in this

environment for >10 years operation.

• NSTLI – Materials - report concluded

that manufacturing defects and/or

operational defects are not likely to be

of sufficient size to result in critical

crack instability after 15 years of

operation.• weld residual stress (WRS) and the decreasing irradiation

toughness are the major parameters in determining critical crack sizes.

Page 5: CNS In-pile Replacement Project · 2. Project dose constraint –10 mSv for any individual 3. Project dose target –5 mSv per person 4. Design target –2.5 mSv per person • CNS

Installation schedule

Project Initiation and Scoping Phase

We are

here2014

Target

2015 2016 202420182017

Design and Build Phase

Initiate and Scoping

Concept design

Manoeuvre definition

Funding

Case

Detailed Engineering – In-pile and mockup

Construction and procedure development

RFT

2023

Installation Phase

Licensing

Training

Installation

Long

Shutdown

Documentation

Page 6: CNS In-pile Replacement Project · 2. Project dose constraint –10 mSv for any individual 3. Project dose target –5 mSv per person 4. Design target –2.5 mSv per person • CNS

CNS Mk2 – how is it different?

• Conceptual designs based on calculations

benchmarked by measurements.

• Possible gains of 11% to 35% in source

brightness at the long wavelengths (> 8Å).

0,90

1,00

1,10

1,20

1,30

1,40

1,50

2,00 4,00 6,00 8,00 10,00 12,00 14,00

Rat

io

Wavelength λ (Å)

case2

case3

case4

Case 1 as reference datum

Case 3 was selected

Page 7: CNS In-pile Replacement Project · 2. Project dose constraint –10 mSv for any individual 3. Project dose target –5 mSv per person 4. Design target –2.5 mSv per person • CNS

Manoeuvre development - Constraints

1. ANSTO dose limit – 15 mSv/year per person

2. Project dose constraint – 10 mSv for any individual

3. Project dose target – 5 mSv per person

4. Design target – 2.5 mSv per person

• CNS Replacement project - 25 mSv.man

• Expect to need 9 persons minimum (based on radiation

dose). Fatigue, dehydration, etc. may affect this number.

• Expect to operate on 2 extended shifts (10 hours) per day

(this setup was used successfully with Cold Guide 2 installation in 2012).

Page 8: CNS In-pile Replacement Project · 2. Project dose constraint –10 mSv for any individual 3. Project dose target –5 mSv per person 4. Design target –2.5 mSv per person • CNS

The original CNS installation

Page 9: CNS In-pile Replacement Project · 2. Project dose constraint –10 mSv for any individual 3. Project dose target –5 mSv per person 4. Design target –2.5 mSv per person • CNS

What is different now?

Need to remove

these nuts

120mSv/hr at

contact!

Need to remove

all the pipework

and support

bracket in order

to remove the

CNS in-pileBackground

radiation

~100µSv/hr.

(Based on

previous tasks)

Likely

radioactive

contamination

everywhere!

The top flange of the CNS is here

There will be

residual heat

within the walls

It’s a confined

space!

Page 10: CNS In-pile Replacement Project · 2. Project dose constraint –10 mSv for any individual 3. Project dose target –5 mSv per person 4. Design target –2.5 mSv per person • CNS

Manoeuvre development methodology

1. ALARA

2. High automation (low dose, complexity and

cost) vs low automation (higher dose, less

complexity)

3. Some tasks would be hard to automate e.g.

welding pipes, removing certain nuts with

limited access, seal groove preparation, etc.

4. The decision was to automate repetitive

tasks and manually perform the complex

tasks. This means using distance (long

tools), shielding and optimising the duration

of the tasks.

Page 11: CNS In-pile Replacement Project · 2. Project dose constraint –10 mSv for any individual 3. Project dose target –5 mSv per person 4. Design target –2.5 mSv per person • CNS

Manoeuvre development

• Manoeuvre development step-by-step in

mock-up (no radiation PPE)

• Manoeuvre development step-by-step in

mock-up (with radiation PPE)

(with ANSTO WHS and Radiation

protection assistance)

• Abnormal operations and recovery

scenarios

• Training before installation

Simulation of rescue scenarios

Page 12: CNS In-pile Replacement Project · 2. Project dose constraint –10 mSv for any individual 3. Project dose target –5 mSv per person 4. Design target –2.5 mSv per person • CNS

5 main steps to the manoeuvre 1. Reactor shut down, process set up

for opening and Level 13 preparation

(pool top area)

Purge the lines, bring components and

tools to Level 13

Remove silicon rack, protection covers

and other sensitive equipment

Line the area with plastic

2. CNS removal, CNS disassembly and

final storage

3. New CNS assembly and reactor pool

preparation

4. New CNS installation in reactor pool

5. CNS testing, cold and hot

commissioning

Page 13: CNS In-pile Replacement Project · 2. Project dose constraint –10 mSv for any individual 3. Project dose target –5 mSv per person 4. Design target –2.5 mSv per person • CNS

Removal of the existing CNS

• Shielded workbox

for a person to

enter the pool.

• Use the water as

shielding.

• Drop water level to

as low as +4300

(just under the

CNS flange)

depending on the

task.

Need to cut

pipes here

Page 14: CNS In-pile Replacement Project · 2. Project dose constraint –10 mSv for any individual 3. Project dose target –5 mSv per person 4. Design target –2.5 mSv per person • CNS

Removal of the existing CNS

• Shielded workbox can be

configured for different

tasks.

Page 15: CNS In-pile Replacement Project · 2. Project dose constraint –10 mSv for any individual 3. Project dose target –5 mSv per person 4. Design target –2.5 mSv per person • CNS

Removal of the existing CNS Cutting of vacuum and deuterium lines

– improvements for future replacements.

Disconnection and cutting of heavy water

lines – improvements for future replacements.

Page 16: CNS In-pile Replacement Project · 2. Project dose constraint –10 mSv for any individual 3. Project dose target –5 mSv per person 4. Design target –2.5 mSv per person • CNS

Removal of the existing CNS

CNS flange unbolting/bolting

Page 17: CNS In-pile Replacement Project · 2. Project dose constraint –10 mSv for any individual 3. Project dose target –5 mSv per person 4. Design target –2.5 mSv per person • CNS

Removal of the existing CNS

Attachment of lifting equipment to CNSOverall weight of assembly ~600kg

Page 18: CNS In-pile Replacement Project · 2. Project dose constraint –10 mSv for any individual 3. Project dose target –5 mSv per person 4. Design target –2.5 mSv per person • CNS

CNS Pipework Disassembly

LEVEL 13

LEVEL 10

Pool wall

Control

Room wall

CNS Storage

Pipework for the new CNS in-pile is assembled here too.

Shielded

support

Page 19: CNS In-pile Replacement Project · 2. Project dose constraint –10 mSv for any individual 3. Project dose target –5 mSv per person 4. Design target –2.5 mSv per person • CNS

CNS Installation – Alignment device

Electrical cylinder

Guides for CNS

(polypropylene)

100 mm lead

Shielding ~300 kg

CNS ready for

insertion

Page 20: CNS In-pile Replacement Project · 2. Project dose constraint –10 mSv for any individual 3. Project dose target –5 mSv per person 4. Design target –2.5 mSv per person • CNS

CNS Installation – lifting of new CNSNew pipe support

frame and lifting device

to allow for one motion

insertion.

Page 21: CNS In-pile Replacement Project · 2. Project dose constraint –10 mSv for any individual 3. Project dose target –5 mSv per person 4. Design target –2.5 mSv per person • CNS

Mock-up of reactor pool and CNS• Mock-up built - Full-scale ½ pool

• To be used to develop the procedure.

• Will be used to train technicians

Page 22: CNS In-pile Replacement Project · 2. Project dose constraint –10 mSv for any individual 3. Project dose target –5 mSv per person 4. Design target –2.5 mSv per person • CNS

Mock-up of reactor pool and CNS• Development of the manoeuvre has

commenced.

Page 23: CNS In-pile Replacement Project · 2. Project dose constraint –10 mSv for any individual 3. Project dose target –5 mSv per person 4. Design target –2.5 mSv per person • CNS

Thank you


Recommended