+ All Categories
Home > Documents > Mailing list for 15 - wrpc · Minutes of 15th WRPC meeting held on 12th November 2010 ANNEXURES...

Mailing list for 15 - wrpc · Minutes of 15th WRPC meeting held on 12th November 2010 ANNEXURES...

Date post: 23-Mar-2021
Category:
Upload: others
View: 3 times
Download: 0 times
Share this document with a friend
101
Transcript
Page 1: Mailing list for 15 - wrpc · Minutes of 15th WRPC meeting held on 12th November 2010 ANNEXURES Annexure Particulars Annexure-1(a) Participants attending TCC meeting held on 11.11.2010
Page 2: Mailing list for 15 - wrpc · Minutes of 15th WRPC meeting held on 12th November 2010 ANNEXURES Annexure Particulars Annexure-1(a) Participants attending TCC meeting held on 11.11.2010

Mailing list for 15th WRPC meeting (minutes): List of members of Western Regional Power Committee

List of members of Technical Co-ordination Committee

1 CMD, MPPTCL & Chairman, WRPC 1 Managing Director, GSECL, Vadodara. 2 Member (GO&D), CEA, New Delhi 2 Chief Engineer (GM), CEA, New Delhi. 3 Managing Director, CSPTCL, Raipur. 3 Chief Engineer (Trans.), CSPTCL, Raipur. 4 Managing Director, CSPDCL, Raipur. 4 Executive Director (O & M), CSPDCL, Raipur. 5 Managing Director, CSPGCL, Raipur. 5 Executive Director, CSPGCL, Raipur 6 Chief Engineer (LD), SLDC, Bhilai. 6 Chief Engineer (R & C), GETCO, Vadodara. 7 Chairman, GSECL, Vadodara 7 Addl General Manager (RA&C), MGVCL, Vadodara 8 Managing Director, GETCO, Vadodara. 8 Executive Director (O&M-Gen), MPPGCL, Jabalpur.9 Chairman & Managing Director, MGVCL, Vadodara. 9 Asst. General Manager, MPMKVVNL, Bhopal 10 Chief Engineer (LD), SLDC, GETCO, Vadodara. 10 Director (Operation), MSETCL, Mumbai. 11 Chairman & Managing Director, MPPGCL, Jabalpur. 11 Director (Operation), MSEGCL, Mumbai. 12 Chairman & Managing Director, MP MKVVCL, Bhopal.

12 Director (Operation), MSEDCL, Mumbai.

13 CE(LD), SLDC, MPPTCL, Jabalpur. 13 Superintending Engineer (Comml), ED, Goa 14 Managing Director, MSETCL, Mumbai. 14 Executive Engineer, DD, Nani Daman 15 Managing Director, MSEGCL, Mumbai. 15 Executive Engineer, DNH, Silvassa 16 Managing Director, MSEDCL, Mumbai. 16 Regional Executive Director, NTPC Ltd., WRHQ,

Mumbai. 17 Chief Engineer (LD), SLDC, MSETCL, Kalwa. 17 Chief Engineer (Trans), NPCIL, Mumbai. 18 Chief Electrical Engineer, ED, Goa 18 Executive Director, WRTS-I, PGCIL, Nagpur. 19 Secretary(P), UT of Daman & Diu, Moti Daman. 19 Executive Director, WRTS-II, PGCIL, Vadodara. 20 Secretary(P), UT of DNH, Silvassa. 20 General Manager, Tata Power Company, Mumbai 21 Director (Comml.), NTPC Ltd., New Delhi. 21 General Manager (Power), RGPPL, Ratnagiri 22 Director (Operation), NPCIL, Mumbai. 22 General Manager, ISP, NHDC Ltd, Madhya Pradesh23 Director (Operation), PGCIL, Gurgaon. 23 Executive Director (O&M), Torrent Power,

Surat 24 Chief Executive Officer, NLDC, New Delhi. 24 Chief General Manager (Baroda Operations),

GIPCL, Vadodara 25 Executive Director, WRLDC, Mumbai. 25 Vice President, Reliance Energy Ltd., Mumbai. 26 Executive Director, Tata Power Company, Mumbai. Special Invitees 27 Managing Director, RGPPL, Noida 1 Member (Power System), CEA, New Delhi. 28 Chief Executive Director, NHDC Ltd, Bhopal. 2 Chairman & Managing Director, MP Tradeco,

Jabalpur. 29 Member (Power), NCA, Indore. 3 Managing Director, GUVNL, Vadodara. 30 Executive Director, Torrent Power, Surat 31 Managing Director, GIPCL, Vadodara Copy to 32 CEO, RETL, New Delhi 1 Chief Engineer (PP), MSEDCL, Mumbai 33 CEO & Director, Reliance Energy Ltd., Mumbai. 2 Executive Director (Comml), PGCIL, Gurgaon. 34 Member Secretary, WRPC, Mumbai 3 Member Secretary, ERPC, Kolkata 4 Member Secretary, SRPC, Bangalore 5 Member Secretary, NERPC, Shillong 6 Member Secretary, NRPC, New Delhi

Page 3: Mailing list for 15 - wrpc · Minutes of 15th WRPC meeting held on 12th November 2010 ANNEXURES Annexure Particulars Annexure-1(a) Participants attending TCC meeting held on 11.11.2010

Minutes of 15th WRPC meeting held on 12th November 2010

C O N T E N T S

ITEM NO. PARTICULARS Page No.

ITEM No.1 CONFIRMATION OF THE MINUTES OF THE 14th MEETING OF WRP COMMITTEE 3

ITEM No.2 INCLUSION OF NON-ISTS ASSETS FOR IMPLEMENTATION OF POINT CONNECTION METHOD FOR POINT OF CONNECTION CHARGES

4

ITEM No.3 CERC (RATES, CHARGES AND TERMS AND CONDITIONS FOR USE OF INTERVENING TRANSMISSION FACILITIES REGULATIONS, 2010

11

ITEM No.4 UTILISATION OF 220 KV D/C KOLHAPUR –CHIKODI LINE FOR TRANSFER OF POWER BETWEEN WR AND SR 15

ITEM No.5

TRANSMISSION CHARGES & LOSSES FOR USE OF MPPTCL TRANSMISSION SYSTEM FOR TRANSFER OF POWER ON 220 KV BADOD-KOTA & BADOD-MODAK LINES AND GETCO TRANSMISSION SYSTEM FOR TRANSFER OF POWER TO NR ON ZERDA (KANSARI) – KANKORLI & ISSUES RAISED BY CHHATTISGARH DURING WRPC MEETING

17

ITEM No.6

TRANSMISSION CHARGES FOR USE OF MSETCL TRANSMISSION SYSTEM FOR CONVEYANCE OF CENTRAL SECTOR POWER TO GOA AND RGPPL POWER TO GOA, DD & DNH FOR THE PERIOD 1.04.10 TO 31.03.2011

19

ITEM No.7 DECISIONS TAKEN DURING 30th MEETING OF STANDING COMMITTEE ON POWER SYSTEM PLANNING IN WR 20

ITEM No.8 LAND REQUIREMENT FOR 400/220 KV GIS SUBSTATION AT DAMAN 23

ITEM No.9 LAND REQUIREMENT FOR ESTABLISHMENT OF GIS S/S AT VADODARA 24

ITEM No.10 RECOMMENDATIONS OF PSDF GROUP 24

ITEM No.11 CONSTITUTION OF VALIDATION COMMITTEE FOR CERC (SHARING OF INTER-STATE TRANSMISSION CHARGES AND LOSSES) REGULATIONS, 2010

28

ITEM No.12 REVISION OF TRANSMISSION CHARGES FOR THE PERIOD OF APRIL 2009 TO MARCH 2010 AS PER THE DECISION TAKEN DURING 13TH WRPC MEETING

29

ITEM No.13

INCLUSION OF 220 KV BUDHIPADAR-KORBA CKRCUIT –III FOR APPORTIONMENT OF ER NTPC SCHEDULED ENERGY ON ER-WR LINK ALLOWING OPTCL TO RAISE WHEELING CHARGES OVER 220 KV BUDHIPADAR-KORBA-I,II & III.

30

ITEM No.14 PERFORMANCE OF WR GRID DURING AUGUST 2010 TO OCTOBER 2010 31

ITEM No.15 ANTICIPATED POWER SUPPLY POSITION IN WESTERN REGION FOR THE PERIOD FROM OCTOBER 2010 TO JANUARY 2011

34

ITEM No.16 PLANNING TO MEET CONSUMER LOADS 35 ITEM No.17 WIDE AREA MEASUREMENT SYSTEM (WAMS) IN WR 36 ITEM No.18 ONGOING TRANSMISSION SCHEMES IN WESTERN REGION 37 ITEM No.19 ONGOING GENERATION SCHEMES IN WESTERN REGION 40 ITEM No.20 POWER SYSTEM DEVELOPMENT FUND 41

Page 4: Mailing list for 15 - wrpc · Minutes of 15th WRPC meeting held on 12th November 2010 ANNEXURES Annexure Particulars Annexure-1(a) Participants attending TCC meeting held on 11.11.2010

Minutes of 15th WRPC meeting held on 12th November 2010

ITEM No.21 PAYMENTS OF UI AND REACTIVE ENERGY CHARGES 42

ITEM No.22 DEVELOPMENT OF SOFTWARE FOR ISSUANCE OF RTA & RTDA 44

ITEM No.23 GRANT OF CONNECTIVITY 44

ITEM No.24 DECLARATION OF TRANSMISSION ELEMENTS INTO COMMERCIAL OPERATION BY PGCIL 46

ITEM No.25 RENOVATION AND MODERNISATION OF WRPC OFFICE BUILDING 47

ITEM No.26 DATE AND VENUE OF NEXT WRPC MEETING 48

Page 5: Mailing list for 15 - wrpc · Minutes of 15th WRPC meeting held on 12th November 2010 ANNEXURES Annexure Particulars Annexure-1(a) Participants attending TCC meeting held on 11.11.2010

Minutes of 15th WRPC meeting held on 12th November 2010

ANNEXURES

Annexure Particulars Annexure-1(a) Participants attending TCC meeting held on 11.11.2010 Annexure-1(b) Participants attending 15th WRPC meeting held on 12.11.2010Annexure-1.1 PGCIL letter no. C-LDC-WR-FO-01 dated 20.09.2010 Annexure-1.2 MP Tradco letter no. 05-01/1709 dated 06.09.2010

Annexure-2.1 List of lines proposed to be certified as ISTS lines, state owned Interstate / Inter-regional lines ISTS lines and deemed ISTS lines

Annexure-2.2 List of lines certified as ISTS lines, state owned Interstate / Inter-regional lines ISTS lines and deemed ISTS lines

Annexure-5.1 Gist of discussions between CSPTCL, WRLDC and WRPC, after the TCC meeting on 11.11.2010

Annexure-6.1 MP Tradco letter dated 20.09.2010

Annexure-9 PGCIL vide letter No. WRTS-II:VDR:WRSS-II:GETCO:2937 dated 16.10.10

Annexure-14.1(a) The details of frequency profile during the period from August 2010 to October 2010

Annexure-14.1(b) Power supply position in WR for the period from August 2010 to October 2010

Annexure- 14.2 The month wise detail of voltages at 400 kV and 765 kV sub-stations during the month of August 2010 to October 2010

Annexure-14.3 Month-wise details of UFR operation in Western Region during the period August 2010 to October 2010

Annexure-15 Anticipated power supply position in the region for the period from October 2010 to January 2011

Annexure-16 Planning to meet the Consumer Load-format for data submission

Annexure-18 Details of ongoing transmission schemes in WR

Annexure-19 Details of on going generation schemes in WR both under State as well as Central Sector

Annexure-22 The record notes of discussions held on 12.10.10 at NRPC

Annexure-25 Constituent wise details of amount to be released for renovation and modernization of WRPC office building

Page 6: Mailing list for 15 - wrpc · Minutes of 15th WRPC meeting held on 12th November 2010 ANNEXURES Annexure Particulars Annexure-1(a) Participants attending TCC meeting held on 11.11.2010

Minutes of 15th WRPC meeting to be held on 12th November 2010 at Udaipur

1

MINUTES OF 15 TH MEETING OF WESTERN REGIONAL POWER COMMITTEE HELD ON 12TH NOVEMBER 2010 AT UDAIPUR

The Technical Co-ordination Committee and 15th Western Regional Power Committee

meetings were held on 11th and 12th November 2010 respectively at Udaipur which was

hosted by National Thermal Power Corporation Ltd. The list of participants is at

Annexure-1 (a) and Annexure -1 (b) respectively.

Shri S. C. Pandey, RED(WR), NTPC Ltd., welcomed the members and participants of

the 15th WRPC meeting and stated that NTPC is honored to host this WRPC meeting at

Udaipur. He briefly highlighted the salient features of NTPC stating that NTPC has an

available capacity of 32694 MW of which 8070 MW is in WR as on date. He stated that

NTPC have recently added 500 MW at Jhajhar in Haryana and 500 MW at Korba and

660 MW at Sipat would be commissioned in WR in FY 2010-11. He said that 16840

MW capacities under construction, another 7000 MW is under tendering process and

13000 MW under FR preparation. He added that NTPC is making efforts to achieve

75000 MW plus capacity by the year 2017 out of which 10866 MW is in WR and project

work at Mauda-I and Vindhyachal-IV is progressing satisfactorily. He stated that

NTPC’s operational performance for all running stations has been very satisfactory and

they have surpassed the Govt. of India MOU in the first half of the current financial year

and shown confidence in surpassing all the previous levels of operational performance

in current financial year with the support of WR constituents. He thanked Chairman,

WRPC for giving them the opportunity to host this meeting.

Chairman, WRPC on behalf of WRPC, welcomed the members of WRPC and

participants representing various power utilities of Western Region viz. CSPTCL,

CSPDCL, CSPGCL, GETCO, GSECL, MGVCL, MPPGCL MKVVCL MSETCL MSEGCL

MSEDCL Goa Electricity Department, DD & DNH, NTPC, POWERGRID, NPCIL, NCA,

NHDC, Torrent Power, RGPPL, GIPCL, TPC, RETL, SLDCs, WRLDC, NLDC, CEA in

15th meeting of WRPC hosted by NTPC at Udaipur.

He thanked NTPC authorities for consenting to host this meeting of WRPC and making

excellent arrangements for the meeting and for comfortable stay of the members

attending the TCC and WRPC meetings.

Page 7: Mailing list for 15 - wrpc · Minutes of 15th WRPC meeting held on 12th November 2010 ANNEXURES Annexure Particulars Annexure-1(a) Participants attending TCC meeting held on 11.11.2010

Minutes of 15th WRPC meeting to be held on 12th November 2010 at Udaipur

2

He highlighted the salient features of operation of WR grid during August and

September 2010 stating that these months have been comfortable because hardly any

advisory messages were issued to Western Region Constituent members and also

need was not felt to implement load regulatory measures. He requested all members to

make efforts to implement load regulatory measures in line with availability of power so

that efforts could be made to flatten the load curve to the extent possible and to ensure

that overdrawals from the system are avoided strictly during low frequency regime. He

further stated that all states have already formulated their load regulatory measures

plan and was confident that and with the experience of past years, WR will succeed in

maintaining our system in a satisfactory manner because WRPC system is known to be

one of the best managed Transmission System in the Country.

He stated that in view of the implementation of CERC Regulations 2010 w.e.f 1.1.2010

on sharing of Inter-State Charges and losses the related agenda items are included in

this agenda for discussion/ approval based on the outcome from sub-committees of

WRPC in the last quarter. The implementation agency i.e. NLDC designated by CERC

has undertaken the estimation of allocation of Transmission charges and losses at

various nodes in the region and has held three meetings of implementation committee

to review progress on various activities in this process. First phase of capacity building

workshops conducted by the Implementing agency to acquaint the regional utilities on

the new tariff is completed. Second phase of the capacity building workshop has

commenced in this month. The various transmission schemes agreed in 30th Standing

Committee Meeting of CEA on Power System Planning for Western Region that were

taken up in 14th WRPC meeting for endorsement of WR Power Committee were

separately discussed subsequently by WR constituents. During discussions at Nagpur,

more or less, there has been consensus on the detailed report of 30th Standing

Committee. He said that in case however, there are any minor modifications or

changes, the same may have to be submitted to Standing Committee because the

schemes are evolved by Standing Committee on the basis of detailed studies

conducted by CTU in association with CEA. In the special meeting, organised by Power

Grid Corporation of India at Nagpur, apart from discussions on the report of Standing

Committee, the detailed progress of various Intra-State and Inter- State transmission

schemes under five different categories was discussed. Priority transmission lines were

identified and special attention was paid to such of the transmission lines and

Page 8: Mailing list for 15 - wrpc · Minutes of 15th WRPC meeting held on 12th November 2010 ANNEXURES Annexure Particulars Annexure-1(a) Participants attending TCC meeting held on 11.11.2010

Minutes of 15th WRPC meeting to be held on 12th November 2010 at Udaipur

3

substations, wherein delay in implementation is likely to jeopardise interests of

constituent members. The participating members had assured that they will make all out

efforts to speed up construction activities so that completion of transmission projects in

a coordinated manner within time bound schedule could be ensured. Special group and

committees formed during the last WRPC meeting have discussed issues relating to

scheduling of STOA transactions related to embedded State generators and proposals

for schemes to be considered for funding through PSDF etc. The suggestions have

been included in agenda for consideration. He complemented the efforts made by the

groups towards this activity. At the end, he thanked NTPC for excellent arrangements

made by them to for the meeting and stay. He also thanked members and participants

of the meeting for attending the same and their valuable support.

ITEM No.1: CONFIRMATION OF THE MINUTES OF THE 14th MEETING OF WRP

COMMITTEE

Member Secretary, WRPC stated that Minutes of 14th meeting of WRP Committee held

on 19th August 2010 at Mumbai were sent to the members vide letter no.

WRPC/Minutes/AS/2010/8185 dated 3.09.2010.

He further stated that comments have been received on Minutes of the meeting from

Addl. GM (LD&C), PGCIL vide letter no. C-LDC-WR-FO-01 dated 20.09.2010 (enclosed

at Annexure-1.1) suggesting modification in Item No. 3.2 (ii) of the minutes as “TCC

recommended for OPGW with 24 fibres. Out of this, maximum 12 Nos. can be used for

POWERGRID Telecom business. Out of remaining 12 No. fibres, presently as

indicated by PGCIL, 6 Nos. are required to meet communication/SCADA etc.

requirement of WR grid and balance 6 Nos. spares fibers, if need be, shall be used by

POWERGRID with the approval of WRPC. “ and CGM (Comml), MP Tradco, vide letter

no. 05-01/1709 dated 06.09.2010 (enclosed at Annexure-1.2) suggesting modification

in last para of Item No. 7 as “ WRP Committee deliberated the matter and Chairman,

WRPC/CMD, MPPTCL directed M/s Torrent Power Co. Ltd. to depute the concerned

officer to Jabalpur alongwith all the relevant documents within a week's time, sit

together with MP Power Tradeco Ltd and sort out the issue for initiation to supply of 100

MW power to MP Power Tradeco.”

Page 9: Mailing list for 15 - wrpc · Minutes of 15th WRPC meeting held on 12th November 2010 ANNEXURES Annexure Particulars Annexure-1(a) Participants attending TCC meeting held on 11.11.2010

Minutes of 15th WRPC meeting to be held on 12th November 2010 at Udaipur

4

Chairman WRPC stated that as assets are under the custody of POWERGRID, spares

fibers, if need be, shall be used on recommendation of POWERGRID with the approval

of WRPC. Referring to the amendment sought by MP Tradeco it was noted that a

meeting was being convened on 15th November at Jabalpur, wherein the issue is likely

to be discussed and resolved. As such no reservations might exist on the amendment

sought.

The Committee discussed and agreed to the same. The minutes of the 14th WRPC meeting were confirmed without any amendments. ITEM No.2: INCLUSION OF NON-ISTS ASSETS FOR IMPLEMENTATION OF POINT

CONNECTION METHOD FOR POINT OF CONNECTION CHARGES

Member Secretary, WRPC stated that CERC Regulations, 2010 on "Sharing on

transmission charges and Losses" regulation 2010 are to come in force from 1.1.2011.

The determination of transmission charges as per this Regulation is required to be

limited to the network owned, operated and maintained by the ISTS Licensees or those

transmission licensees / SEBs whose assets have been certified by RPCs as being

used for inter-state transmission.

Only such assets as above will be included in for implementation of point connection

method for point of connection charges. Preparation of a cogent network requires

consideration of state owned lines also. The YTC for such lines shall be based on the

YTC of the transmission licensee / SEB as approved by the Appropriate Commission.

Member Secretary, WRPC stated that in 56th Commercial Committee meeting of WRPC

held on 22.10.2010 the matter to identify the lines owned and operated by the

States/transmission licensees that would come under the category of Certified ISTS

lines and required to be certified by the RPCs was discussed. GETCO, MPPTCL,

CSPTCL had submitted the list of state lines used for Inter-state transmission of power

for inclusion in certification by the WRPC. The Commercial Committee had discussed

and recommended criteria to be adopted for identifying such lines as follows:-

1. Connectivity of State transmission utilities of the region with CTU network within the regional boundary: The state transmission utilities of the region should

Page 10: Mailing list for 15 - wrpc · Minutes of 15th WRPC meeting held on 12th November 2010 ANNEXURES Annexure Particulars Annexure-1(a) Participants attending TCC meeting held on 11.11.2010

Minutes of 15th WRPC meeting to be held on 12th November 2010 at Udaipur

5

be connected to ISTS (CTU) network. In case of no direct connection by CTU line,

the intervening state owned lines(s) with the shortest path to the nearest ISTS (CTU)

sub-station/line, at the highest voltage level would be considered for inclusion in

POC charge and would require certification by RPCs.

Application: With the above Gujarat, Maharashtra, MP, Chhattisgarh systems are

well connected to ISTS network. However Goa and Diu are not directly connected

to CTU network.

In the case of Goa, Mapusa is ISTS (CTU) node and 400 kV Mapusa-Kolhapur D/c

is ISTS (CTU) line. But this line is not connected to the ISTS (CTU) network, the

nearest point up to which connectivity through State system is to be established is

400 kV Chandrapur, which receives power from ISGS stations over ISTS (CTU)

network from 400 kV Bhadravati-Chandrapur line of CTU. Thus the path on 400 kV

is Chandrapur – Parli – Solapur – Karad - Kolhapur may be considered for POC

charge as Certified ISTS lines.

In the case of Diu, considering the lines that are coming up by March, 2012, the

nearest point up to which connectivity through State system is to be established is

400 kV Jetpur, which would receive power from ISGS stations over ISTS (CTU)

network from 400 kV Mundra - Jetpur ISTS (CTU) line nearest ISTS (CTU). From

400 kV Jetpur sub-station of Gujarat State, the state lines of Gujarat system that

provide connectivity to Diu are 220 kV Jetpur- Keshod-Timbdi-Dhokadva and and 66

kV Dhokadva -Una which may be considered for POC charge as Certified ISTS

lines.

2) Connectivity of inter-regional transmission lines in the State with CTU network within the regional boundary: The Inter-Regional lines emanating from a

State in the own region which transfer Inter-Regional power should get connected to

the nearest ISTS (CTU) network in own region. The inter-regional line transferring

power is either CTU owned line or State owned line. In case of no direct connection

of the State sub-station of own region of the inter-regional line, the intervening state

owned line(s) with the shortest path to the nearest ISTS (CTU) sub-station/line, at

the highest voltage level in the own region would be considered for inclusion in POC

Page 11: Mailing list for 15 - wrpc · Minutes of 15th WRPC meeting held on 12th November 2010 ANNEXURES Annexure Particulars Annexure-1(a) Participants attending TCC meeting held on 11.11.2010

Minutes of 15th WRPC meeting to be held on 12th November 2010 at Udaipur

6

charge and would require certification by RPCs. Lower voltage paths or parallel

paths, if any, will not be considered.

Application:

(i) 400 kV Kansari (Zerda)-Kankroli line is an ISTS (CTU) Inter Regional Line. The

400 kV Kansari (Zerda) sub-station of Gujarat State does not have direct

connectivity with CTU point in the own region. The nearest CTU network point is at

400 kV Dehgam. The connectivity from 400 kV Dehgam - Soja- Zerda lines may

be considered for POC charge as Certified ISTS lines.

(ii) 220 kV Budhipadar - Raigarh is Inter Regional (IR) CTU line and two circuits 220

kV Budhipadar- Korba (E) are state owned Inter-regional lines which are also ISTS

lines between States of the two regions viz. ER and WR. Korba (E) is connected to

ISTS line 220 kV Raigarh-Korba (E). Hence State owned portions of 220 kV two

ckts, Korba (E)-Budhipadar getting connected to ISTS network at Korba (E) itself

may be considered for POC charge as Certified ISTS lines.

(iii) 220 kV Badod-Kota and Badod-Modak are state-owned Inter-regional lines. These

get connected to nearest ISTS (CTU) sub-station at Indore or Nagda. The nearest

connectivity to either Indore or Nagda ISTS (CTU) sub-station may be considered

for certified ISTS lines-namely either 220 kV Indore(Jaitppura)-Ujjain-Badod or

220kV Nagda-Ujjain-Badod. The State-owned portions of 220 kV Badod-Kota and

Badod-Modak alongwith the connectivity of state owned lines with CTU point either

at 220 kV Indore or at 220 kV Ujjain may be considered for POC charge as

Certified ISTS lines.

220 kV Auraiya-Malanpur and Auriya - Mehgam is an IR line. The nearest ISTS

(CTU) sub-station is 220 kV Gwalior. The connectivity is 220 kV Malanpur -

Mehgaon (Gwalior) and 220 kV Malanpur-Gwalior (PG). Hence State owned

portions of 220 kV Auraiya-Mehgaon-Malanpur-Gwalior, Auraiya-Malanpur-Gwalior

lines may be considered POC charge as Certified ISTS lines.

The following points had also been noted in the context of identification of non-ISTS

lines for inclusion under the POC charge:

Page 12: Mailing list for 15 - wrpc · Minutes of 15th WRPC meeting held on 12th November 2010 ANNEXURES Annexure Particulars Annexure-1(a) Participants attending TCC meeting held on 11.11.2010

Minutes of 15th WRPC meeting to be held on 12th November 2010 at Udaipur

7

1) Central Electricity Regulatory Commission (Indian Electricity Grid Code)

Regulations, 2010 defines under 2 (qq) “Inter State Transmission System (ISTS)”

means

i) Any system for the conveyance of electricity by means of a main transmission

line from the territory of one State to another State

ii) The conveyance of electricity across the territory of an intervening State as well

as conveyance within the State which is incidental to such inter-state

transmission of energy.

iii) The transmission of electricity within the territory of State on a system built,

owned, operated, maintained or controlled by CTU;

2) In view of above it was pointed out that out of all those inter-state lines which are

owned, operated and maintained by SEBs as their assets and being used for

inter-state transmission require to be included in POC charge calculation.

3) CERC Regulations, 2010 on "Sharing on transmission charges and Losses"

regulation 2010, under 2 (k) defines Deemed Inter State Transmission System

(Deemed ISTS) means “such transmission system which has regulatory approval

of the Commission as being used for interstate transmission of power and

qualified as ISTS for the purpose of these Regulations unless otherwise

specified;”

4) All lines that have regulatory approval of the Commission as being used for

interstate transmission of power are classified as Deemed ISTS category and

would therefore not need certification by RPC.

5) CERC Regulations, 2010 (Rates, Charges and Terms and Conditions for use of

Intervening Transmission Facilities) Regulations, 2010 dated 23.9.2010, have

been issued. These regulations shall apply only where a contract path can be

identified. Further these Regulations apply to the intervening transmission

facilities which are incidental to inter-State transmission owned or operated by a

licensee and are used or proposed to be used by any trading licensee or

distribution licensee for transmission of power through long-term access, medium

term open access or short term open access.

Page 13: Mailing list for 15 - wrpc · Minutes of 15th WRPC meeting held on 12th November 2010 ANNEXURES Annexure Particulars Annexure-1(a) Participants attending TCC meeting held on 11.11.2010

Minutes of 15th WRPC meeting to be held on 12th November 2010 at Udaipur

8

Prior to the notification of the above Regulation on Rates, Charges and Terms

and Conditions, the agreements entered into either through mutual consent of

the contracting parties or on the orders passed by the Appropriate Commission,

for use of any intervening transmission facilities, shall continue to have effect

notwithstanding inconsistency, if any, with these regulations till the expiry of such

agreements.

In TCC meeting, PGCIL representative had stated that the criteria based on the

evaluation of extent of actual ISTS power flow quantum on the non-ISTS lines should be

used for listing out the elements for inclusion under POC charge. ED (Finance), GUVNL

stated that GETCO system used for evacuation of power from Kakrapar and Kawas

ISGS stations needed to be included under PoC charges. The matter was discussed. It

was clarified that as the injection into the State grid from the above ISGS stations takes

place through ISTS lines, wherein the State grid has direct connectivity to the ISTS

network, the state network as per the criteria has accordingly not come under

consideration for POC. GUVNL queried about any similar case elsewhere and how the

treatment for POC purpose is considered. ED, WRLDC stated that similar situation

exists in RAPS in NR, and how this case is treated shall be reverted back.

The TCC discussed the criteria recommended by the Commercial Committee of WRPC

Proposed list of lines identified for certification as per Annexure-2.1 (Annexure-2 of the

agenda notes) was perused and discussed.

TCC suggested the following:-

i. 132 kV Balaghat-Dongargarh line may be certified only if it is kept in operation

not otherwise. As at present the line is not kept in operation, it may not be

included in ISTS list.

ii. If any other lines is found eligible on the basis of above mentioned criteria for the

certification, the same may be included in the list.

iii. YTC of the respective lines as approved by the appropriate Commission, shall be

furnished by the concerned utilities to the implementing agency for needful.

Page 14: Mailing list for 15 - wrpc · Minutes of 15th WRPC meeting held on 12th November 2010 ANNEXURES Annexure Particulars Annexure-1(a) Participants attending TCC meeting held on 11.11.2010

Minutes of 15th WRPC meeting to be held on 12th November 2010 at Udaipur

9

On the basis of above, TCC had recommended to adopt criteria for inclusion of non-

ISTS lines for POC charge as suggested by the Commercial Committee and to include

non-ISTS lines for POC charge as per the Annexure- 2.2.

The WR Power Committee discussed the issue. PGCIL representative had stated that

the criteria based on the precise evaluation of extent of actual ISTS power flow quantum

on the non-ISTS lines should be used for listing out the elements for inclusion under

POC charge. The Committee members observed that under interconnected grid

conditions, the identification mechanism for listing out non-ISTS lines based on CTU

connectivity criteria as recommended by Commercial Committee/TCC as above would

be in order.

ED (Finance), GUVNL stated that GETCO system used for evacuation of power from

Kakrapar and Kawas ISGS stations needs to be included under PoC charges. It was

clarified that as the injection into the State grid from the above ISGS stations takes

place through ISTS lines, wherein the State grid has direct connectivity to the ISTS

network, the state network has accordingly as per the criteria not come under

consideration for POC charge. Further identification of non-ISTS lines to be adopted is

on the basis of availability of CTU connectivity of the node which handles ISTS power,

although the utilization of State’s shares from ISGS stations located within or outside

the State takes place from load point of view.

GUVNL suggested that similar case elsewhere if any and the treatment for POC charge

purpose may be examined. ED, WRLDC stated that similar situation exists in RAPS in

NR, and how this case is treated may be studied. GUVNL requested WRLDC to

examine how much of GETCO system is being used for evacuation of ISGS generation

to other beneficiaries.

In the above context it was intimated that under regulation 7 (1) (t) (vii) of the CERC

regulations on Sharing of transmission charges and losses), Regulations 2010, the

regulations preserve the existing arrangement for evacuation system of power from

ISGS using STU lines which is reproduced as below:

Page 15: Mailing list for 15 - wrpc · Minutes of 15th WRPC meeting held on 12th November 2010 ANNEXURES Annexure Particulars Annexure-1(a) Participants attending TCC meeting held on 11.11.2010

Minutes of 15th WRPC meeting to be held on 12th November 2010 at Udaipur

10

"Long term beneficiaries of ISGS connected to STU network shall continue to pay the

transmission charges for the STU network as per the existing arrangement"

The Committee members further discussed the related matters and decisions taken on

the same as follows:-

i. In regard to query for MSETCL, for lines like Nasik-Navsari or Pandhurna-

Kalmeshwar shown against GETCO or MPPTCL, it was agreed that each of the

utilities at either end has a stake in the POC of lines corresponding to the portion

in their respective jurisdiction.

ii. Regarding inclusion of 132 kV Balaghat-Dongargarh interstate line for POC

charge, the Committee suggested that same may not be considered as the line is

in not in operation, since long period and is not kept in operation. It was decided

that the same may not be included for certification as ISTS line.

iii. The lines at items 1 to 4 & 7 and 8 under A of Annexure-2 of the proposed list

in the agenda notes for POC consideration would be reviewed after

commissioning of 400 kV Mundra-Bachau-Ranchodpura D/c line of

POWERGRID and 400 kV Ranchodpura – Zerda D/c line by Reliance IPTC and

400 kV Nagda-RAPS-C D/c lines.

iv. Further the concerned owner utility of the certified ISTS line shall immediately

furnish to the Implementing Agency (NLDC) the YTC of the respective lines as

approved by the appropriate commission.

v. WRLDC shall examine how much of GETCO system is being used for

evacuation of ISGS generation to other beneficiaries for further needful.

vi. The WRP Committee approved the criteria recommended by TCC as above and on the basis of above, approved the list of state owned Interstate / Inter-regional lines for certification as ISTS lines, the other ISTS lines and deemed ISTS lines for inclusion under POC charge which is placed at

Page 16: Mailing list for 15 - wrpc · Minutes of 15th WRPC meeting held on 12th November 2010 ANNEXURES Annexure Particulars Annexure-1(a) Participants attending TCC meeting held on 11.11.2010

Minutes of 15th WRPC meeting to be held on 12th November 2010 at Udaipur

11

Annexure-2.2. It was agreed that any other non-ISTS line that comes up and meets the criteria agreed as above, may be considered for certification as ISTS line.

ITEM No.3: CERC (RATES, CHARGES AND TERMS AND CONDITIONS FOR USE OF INTERVENING TRANSMISSION FACILITIES REGULATIONS, 2010

3.1 Member Secretary, WRPC stated that Hon’ble CERC issued regulation on Rates,

charges and Terms and Conditions for use of intervening transmission Facilities vide

No. L-1/10/2009-CERC dated 23.09.2010. The salient features of this regulation are

given below:

a) These regulations shall apply only where a contract path can be identified.

b) These regulation shall apply where the intervening transmission facilities

incidental to inter-state transmission owned or operated by a licensee, are used

or proposed to be used by any trading licensee or distribution licensee for

transmission of power through long-term access, medium term open access or

short term open access and where the contracting parties have failed to

mutually agree on the rates and charges for the usage of such intervening

transmission facilities as envisaged under the proviso of sub-section(1) of

Section 36 of the Act.

c) The agreements entered into prior to the notification of these Regulations,

either through mutual consent of the contracting parties of on the orders passed

by the Appropriate Commission, for use of any intervening transmission

facilities, shall continue to have effect notwithstanding inconsistency, if any,

with these regulations till the expiry of such agreements.

d) The rates and charges for usage of intervening transmission facilities shall be

as specified under Schedule-I to these regulations. The rates and charges

specified based on contract path are for a standard distance of 50 Km or a part

thereof.

Provided that in case the annual revenue requirement of the contract path in

question has already been determined by the Commission or any State

Electricity Regulatory Commission then the sharing of the transmission charges

so determined, by the applicant, will be in the ratio of the average power flow in

Page 17: Mailing list for 15 - wrpc · Minutes of 15th WRPC meeting held on 12th November 2010 ANNEXURES Annexure Particulars Annexure-1(a) Participants attending TCC meeting held on 11.11.2010

Minutes of 15th WRPC meeting to be held on 12th November 2010 at Udaipur

12

MW of the transaction determined on post-facto basis, to the peak capacity of

the power flow in MW in the line as given in Schedule-II.

e) Transmission loss: The transmission losses for line length of every 50 Km used

shall be as follows:

S. No. Type of transmission system Line losses %

1 400 kV 0.5

2 220 kV 1.0

3 132 kV 4.3

4 66 kV 8.0

f) SCHEDULE-I

Sr. No.

Type of transmission system

Line Capacity Rates and charges for Long-Term Access and medium Term Open Access

Rates and charges for short Term Open Access

MW Rs./ MW/year Rs./ MWh

400 kV (D/C) 900 97.584 11.14

400 kV (S/C) 450 109.006 12.44

220 kV (D/C) 500 118.198 13.49

220 kV (S/C) 250 145.318 16.59

132 kV (D/C) 180 182.525 20.84

132 kV (S/C) 90 325.209 37.12

66 kV (D/C) 54 540.399 61.68

66 kV (S/C) 27 682.244 77.88

g) SCHEDULE-II

S. No. Voltage ( kV) Line loading capacity considered

1 400 kV 450

2 220 kV 250

3 132 kV 90

4 66 kV 27

Page 18: Mailing list for 15 - wrpc · Minutes of 15th WRPC meeting held on 12th November 2010 ANNEXURES Annexure Particulars Annexure-1(a) Participants attending TCC meeting held on 11.11.2010

Minutes of 15th WRPC meeting to be held on 12th November 2010 at Udaipur

13

3.2 Member Secretary, WRPC stated that In accordance with the directions given by

the Hon’ble Commission in the order dated 31.07.2009 in the petition No.

64/2008 and 67/2008, WRPC Secretariat had worked out the transmission

charges payable to GETCO for conveyance of Central Sector power to DD &

DNH for the period 1.04.10 to 31.03.2011 which have been vetted by the

Commission vide its order dated 31.07.2010.

3.3 Member Secretary, WRPC stated that as per the discussions in 13th WRPC

meeting held on 9th April 2010 and 55th CCM of WRPC held on 15th July 2010,

WRPC vide letter dated 17.08.2010 had sent the calculations to WR constituents

on the basis of contract path method for transmission charges for use of

MSETCL transmission system for conveyance of Central Sector power to Goa for

the year 2010-11 (implemented in the REAs of August 2010 onwards). The

transmission charges for use of MSETCL transmission system for use of

MSETCL transmission system for transmission of RGPPL power to Goa, DD &

DNH were also sent to all the constituents.

In view of 3.1 (c) above these charges are to be valid for the year 2010-11 (i.e.

upto month of March 2011).

The matter was discussed during 56th Commercial Committee Meeting held on

22.10.2010 at WRPC office, Mumbai. The Committee had opined that in case the

transmission charges for wheeling Central sector power to DD & DNH through

GETCO system and wheeling of Central sector power to Goa through MSETCL

system are calculated as per rates, charges and Terms and Conditions for use of

intervening transmission as per CERC regulation on Rates, charges and Terms

and Conditions, 2010, the transmission charges of the intervening states'

systems would not be sharable by other regional beneficiaries. The Commercial

Committee suggested that existing practice of calculation of wheeling charges

may be continued till the validity of the Charges communicated as above in

accordance with the CERC norms vide order dated 31.07.2009 i.e. March 2011.

Subsequent to that these charges may be governed as per CERC regulations on

sharing on transmission charges and losses Regulation 2010.

Page 19: Mailing list for 15 - wrpc · Minutes of 15th WRPC meeting held on 12th November 2010 ANNEXURES Annexure Particulars Annexure-1(a) Participants attending TCC meeting held on 11.11.2010

Minutes of 15th WRPC meeting to be held on 12th November 2010 at Udaipur

14

3.4 In 56th CCM, the mechanism for billing & sharing the charges of wheeling of

RGPPL power to Goa, DD & DNH through MSETCL transmission system w.e.f.

start of scheduling of RGPPL power to Goa, DD & DNH on achieving full load of

1940 MW was discussed by the commercial committee in line with the

methodology for billing the charges for wheeling the transmission charges for use

of MSETCL transmission system for wheeling Central Sector power to Goa and

wheeling of ISTS power to DD, DNH through GETCO system. The constituent

members opined that all beneficiaries do not have share in RGPPL power.

GUVNL, CSPDCL expressed that they would not share the wheeling charges for

wheeling RGPPL power to Goa, DD & DNH through MSETCL transmission

system.

The Commercial Committee suggested that in such a case CERC Regulation,

2010 (Rates, Charges and Terms and Conditions for use of Intervening

Transmission Facilities) Regulations, 2010 dated 23.9.2010 may be applicable

for utilization of RGPPL power for Goa, DD & DNH only.

The TCC had discussed the issue and recommended that the existing practice of

calculation of wheeling charges for Gujarat and Maharashtra systems may be continued

till the validity of the Charges upto March 2011. Subsequent to that these charges may

be governed as per CERC regulations on sharing on transmission charges and losses

Regulation 2010.

TCC had further recommended that the payment of transmission charges may be

governed by CERC Regulation, 2010 (Rates, Charges and Terms and Conditions for

use of Intervening Transmission Facilities) Regulations, 2010 dated 23.9.2010 for

utilization of RGPPL power for Goa, DD & DNH only.

WRP Committee endorsed recommendations of TCC as above.

Page 20: Mailing list for 15 - wrpc · Minutes of 15th WRPC meeting held on 12th November 2010 ANNEXURES Annexure Particulars Annexure-1(a) Participants attending TCC meeting held on 11.11.2010

Minutes of 15th WRPC meeting to be held on 12th November 2010 at Udaipur

15

ITEM No.4: UTILISATION OF 220 KV D/C KOLHAPUR –CHIKODI LINE FOR TRANSFER OF POWER BETWEEN WR AND SR

Member Secretary, WRPC stated that a meeting was held on 06.05.2010 regarding

utilization of 220 kV D/c Kolhapur-Chikodi line for exchange of power between SR and

WR under STOA. SRLDC vide letter dated 13.05.2010 had sent methodology for

utilization of the above line and had requested comments on the same. The matter was

discussed in the 412th OCC meeting of WRPC held on 14.06.2010 and 413th OCC

meeting held on 14.07.2010. Subsequently the matter was also taken up by SR in the

SRPC meeting and methodology proposed to be adopted for utilization of the above line

in radial mode was discussed. Also, a meeting between WRPC, MSETCL, MSEDCL,

WRLDC & SRPC was held on 14.10.2010 at WRPC, Mumbai to discuss the issue of

utilization of 220 kV D/c Kolhapur-Chikodi line relating to the methodology for utilization

of the above line was discussed and following were the conclusions:

1) Power flow on the above line would be in radial mode, with Chikodi loads in

Maharashtra system in case of export of power from WR to SR and Maharashtra

loads in Karnataka system in case of export of power from SR to WR.

As the energy transfer is to take place in line with provision under clause 16(1)

and 16(2) under Complementary Commercial Mechanism at Annexure-I of IEGC

2010 for inter-regional Exchanges, the interface for scheduling and UI accounting

will be at Western region end for the above energy exchange between Western

and Southern Region.

2) The loss part in wheeling of the actual power through Maharashtra system was

not addressed in the above methodology to compensate the Maharashtra State

system. It was therefore recommended that the percentage applicable losses for

Maharashtra system on the actual drawl or injection at Kolhapur metering point

would be deducted from Maharashtra drawl from the grid.

3) CE(PP), MSEDCL stated that the matter would be taken up with their

management for necessary action and they would revert back on the decision.

Page 21: Mailing list for 15 - wrpc · Minutes of 15th WRPC meeting held on 12th November 2010 ANNEXURES Annexure Particulars Annexure-1(a) Participants attending TCC meeting held on 11.11.2010

Minutes of 15th WRPC meeting to be held on 12th November 2010 at Udaipur

16

4) CE(PP), MSEDCL queried about the time frame of transactions and whether

Maharashtra would get priority in case they wanted to import the power. WRLDC

clarified that the utilization of above line comes under the purview of Short Term

Open Access (STOA) and as such the STOA methodology as per the regulations

in vogue, would be applicable for the transactions concerning above.

5) Before permitting of STOA by WRLDC on the above line, SLDC, Kalwa,

MSETCL would intimate the availability of the line for STOA purposes in terms of

quantum of load, period and duration. Accordingly WRLDC would proceed as per

STOA method and intimate all concerned agencies.

6) With above inclusions, the methodology discussed by SRPC was found to be in

order.

The matter was discussed in 56th Commercial Committee Meeting held on

22.10.2010 at WRPC office, Mumbai upon query by MSEDCL about the time frame

of transactions and whether Maharashtra would get priority in case they wanted to

import the power, WRLDC had clarified that the utilization of above line comes under

the purview of Short Term Open Access (STOA) and as such the STOA

methodology as per the Regulations in vogue, would be applicable as open access

on Kolhapur-Chikodi route shall have to be non-discriminatory.

Following methodology for compensation of losses of Maharashtra system through

adjustment in drawal of Maharashtra without making any change in drawal schedule

of Maharashtra State was agreed by Commercial Committee:

1. Kolhapur end of Kolhapur-Chikodi line will be treated as one of drawal points in

calculation of drawal of Maharashtra.

2. Depending on direction of flow over above line the SEM reading at Kolhapur will

be modified by a factor of 1/(1-0.0485) in case power flow from Kohapur to

Chikodi and by a factor of 1.0485 in case power flow from Chikodi to Kolhapur.

TCC recommended the above decision of Commercial Committee and WRP Committee approved the same.

Page 22: Mailing list for 15 - wrpc · Minutes of 15th WRPC meeting held on 12th November 2010 ANNEXURES Annexure Particulars Annexure-1(a) Participants attending TCC meeting held on 11.11.2010

Minutes of 15th WRPC meeting to be held on 12th November 2010 at Udaipur

17

ITEM No.5: TRANSMISSION CHARGES & LOSSES FOR USE OF MPPTCL

TRANSMISSION SYSTEM FOR TRANSFER OF POWER ON 220 KV BADOD-KOTA & BADOD-MODAK LINES AND GETCO TRANSMISSION SYSTEM FOR TRANSFER OF POWER TO NR ON ZERDA (KANSARI) – KANKORLI & ISSUES RAISED BY CHHATTISGARH

Member Secretary, WRPC stated that during 14th WRPC meeting held on 19.08.2010

above issues were discussed wherein WR Power Committee constituted a Group

comprising of representatives from SLDCs, WRLDC and WRPC to look into the issues

raised by Chhattisgarh in regard to scheduling of STOA transactions mechanism and to

suggest for working out the losses in respect of usage of MPPTCL transmission system

for transfer of power to NR through, Badod-Modak and Badod-Kota 220 kV lines and

GETCO transmission network for transfer of power to NR from WR through Zerda

(Kansari) – Kankroli link. Accordingly, a meeting of the group to discuss above issues

was held at WRPC office Mumbai on 23.09.2010. MP Power Transmission Co. Ltd. vide

no 07-05/RPC/195 dated 21.10.2010 had communicated that suggestions relating to Sr

no 4 & 8 were not agreed by them and requested to amend the same. ED, WRLDC

subsequently vide letter No. WRLDC/OS/02 dated 25.10.2010 had also submitted

WRLDC views on the suggestions of outcome.

5.1 The TCC suggested that as items 4 and 8 of the outcome of the discussions

were not agreeable by all the members and may not be included in the

recommendations. TCC further noted observation of WRLDC on the outcome on

discussions of the group.

Due to divergent views, the Chairman TCC suggested that the matter regarding

scheduling of STOA transactions mechanism may be further discussed amongst

CSPTCL, WRPC and WRLDC after the TCC meeting and outcome of the same may be

discussed in WRPC meeting on 12.11.2010.

Member Secretary, WRPC stated that the matter relating to the revision of schedule

upon under injection by the State generators was discussed between CSPTCL, WRLDC

and WRPC, after the TCC meeting on 11.11.2010. The Gist of discussion was placed

before WRPC (Copy at Annexure-5.1).

Page 23: Mailing list for 15 - wrpc · Minutes of 15th WRPC meeting held on 12th November 2010 ANNEXURES Annexure Particulars Annexure-1(a) Participants attending TCC meeting held on 11.11.2010

Minutes of 15th WRPC meeting to be held on 12th November 2010 at Udaipur

18

WR Power Committee discussed the outcome. The Committee centered on two main

issues relating to UI payment defaults and the generation scheduling of the State

entities/embedded generators under STOA. The committee suggested that in case of

default by any state utility in UI payment to the State UI pool the concerned SLDC may

take up matter with the State Regulatory Commission for the remedy on similar lines as

applicable under CERC provision for regional UI pool through opening LC for recovery

of the default amount or even requesting for stopping the STOA. The Committee arrived

at opinion that currently under injection by embedded generators/State entities of

capacity below 100 MW presently although is not contributing towards congestion/grid

security problems, the problem might become serious in terms of grid security and

repercussions arising on commercial gaming in case more number of embedded

generators/state entities come up and start intentionally adopting to sustained under-

injection or even no-injection particularly on finding that scheduled power rate is higher

than the prevailing real-time UI rate. In such cases the current regulation does not

provide for revision/reduction of the generators’ schedule which would require

amendment. The Committee further deliberated and arrived at consensus as following:

i) The issue of payment default could be taken up by SLDC with the Appropriate

Commission in the first instance so that the payments are recovered.

However if an intra-state entity continuously defaults for two weekly cycle, the

nodal agency could be requested by the SLDC to cancel the STOA approval

granted. This would require an amendment in Regulations for which the

matter needed to be taken up with CERC.

ii) Regarding the issue of sustained under-injection, it was agreed that such

under-injection was not inconsistent with any of the current Regulation/s due

to which practice could continue indefinitely. Further such under-injection by

very small generator did not cause any network problem due to which the

SLDC could not take any actions on real time basis.

Considering that more such cases might be encountered in future which has a long term

potential to threaten grid security and/or distort the electricity market (which is

essentially a physical delivery market), it was decided that SLDC Chhattisgarh would

Page 24: Mailing list for 15 - wrpc · Minutes of 15th WRPC meeting held on 12th November 2010 ANNEXURES Annexure Particulars Annexure-1(a) Participants attending TCC meeting held on 11.11.2010

Minutes of 15th WRPC meeting to be held on 12th November 2010 at Udaipur

19

monitor such instances of under-injection and document the same. Such intra state

entities could be issued a notice by the SLDC asking them to explain this behavior and

correct the same. Failure to do so could entail the SLDC canceling the standing

clearance given to such intra state entities for STOA/Power Exchange. This would

however require an amendment in the CERC Regulations on Open Access for which

the committee felt that the matter needed to be taken up with CERC.

In view of above, the WR Power Committee suggested that CSPTCL may file a petition with CERC accordingly. 5.2 Regarding the matter for evolving mechanism for compensation of losses on

transfer of power to NR over MPPTCL and GUVNL network, the TCC recommended

the methodology agreed in CCM viz. the losses on intra-state systems for actual inter-

regional power transfer on Badod- Kota, Badod- Modak inter-regional link and 400 kV

Kansari (Zerda)-Kankroli inter-regional link shall be pooled amongst the constituents

of WR based on percentage losses approved by the State Commission for State

transmission system in respective states. It would be reviewed after commissioning of

400 kV Mundra-Bachau-Ranchodpura D/c line of POWERGRID and 400 kV

Ranchodpura – Zerda D/c line by Reliance IPTC and 400 kV Nagda-RAPS-C D/c

lines.

WRP Committee approved the recommendation of TCC which may be implemented from prospective date i.e. from 01.11.2010.

ITEM No.6: TRANSMISSION CHARGES FOR USE OF MSETCL TRANSMISSION SYSTEM FOR CONVEYANCE OF CENTRAL SECTOR POWER TO GOA AND RGPPL POWER TO GOA, DD & DNH FOR THE PERIOD 1.04.10 TO 31.03.2011

Member Secretary, WRPC stated that the issue regarding calculation of transmission

charges for use of MSETCL transmission system for conveyance of Central Sector

power to Goa for the year 2010-11 was discussed during 13th WRPC meeting & 55th

Commercial Committee Meeting. Accordingly, WRPC vide letter dated 17.08.2010

have issued the calculations for transmission charges for use of MSETCL transmission

system for conveyance of ISTS power to Goa for the year 2010-11 (implemented in the

Page 25: Mailing list for 15 - wrpc · Minutes of 15th WRPC meeting held on 12th November 2010 ANNEXURES Annexure Particulars Annexure-1(a) Participants attending TCC meeting held on 11.11.2010

Minutes of 15th WRPC meeting to be held on 12th November 2010 at Udaipur

20

REAs of August 2010 onwards) and transmission charges for use of MSETCL

transmission system and for use of MSETCL transmission system for transmission of

RGPPL power to Goa, DD & DNH were sent to all the constituents.

Chief General Manager (L&RA), MP Tradco vide letter dated 20.09.2010 (copy

enclosed at Annexure-6.1) have submitted their observations on computation of above

transmission charges.

This matter was discussed during 56th Commercial Committee Meeting held on

22.10.10 wherein MSETCL representative had stated that normal income tax rate

@33.2175 % is applicable to MSETCL for FY 2010-11. Commercial Committee

expressed that as MPTradco was not represented in this meeting issue can be

discussed in presence of MPTradco and discussion was deferred for next meeting.

WRP Committee noted the same. ITEM No.7: DECISIONS TAKEN DURING 30th MEETING OF STANDING

COMMITTEE ON POWER SYSTEM PLANNING IN WR

Member Secretary, WRPC stated that as suggested by Chairman, WRPC/CMD,

MPPTCL during 14th WRPC meeting held on 19th August, 2010 at Mumbai the various

decisions taken during the 30th meeting of the Standing Committee on Power System

Planning in Western Region held on 8th July 2010 were discussed during the 3rd

meeting for reviewing progress of various Transmission Schemes in Western Region

held on 6th September, 2010 at Nagpur. MSETCL and CSPTCL had suggested

following amendment in items pertaining to Standing Committee in the minutes of

meeting held on 6th September, 2010 at Nagpur:

Comments by MSETCL: 1. Establishment of proposed HVDC sub-station (PG) Dhule under transmission

system within WR associated with New IPPs in Chhattisgarh

(a) MSETCL indicated that in its presentation in the meeting it had intimated that

MSPGCL had planned 3000 MW generation near Dhule at Dondaicha and 1350 MW

generation of M/s India Bulls at Sinnar in Nasik District was planned. In view of the

Page 26: Mailing list for 15 - wrpc · Minutes of 15th WRPC meeting held on 12th November 2010 ANNEXURES Annexure Particulars Annexure-1(a) Participants attending TCC meeting held on 11.11.2010

Minutes of 15th WRPC meeting to be held on 12th November 2010 at Udaipur

21

same they have planned parallel additional corridors in Dhule-Nashik-Malegaon area

and therefore had suggested POWERGRID to review the decision of establishing

HVDC s/s at Dhule with +/- 600 kV Raigarh(Kotra)-Dhule(PG) HVDC Bipolar link and

400 kV interconnecting lines with Malegaon, Nashik, Dhule(MSETCL) which

POWERGRID had agreed and requested to include the same in the minutes. MD,

GETCO had indicated that in case the HVDC s/s was not required at Dhule the same

may be shifted to Vadodara.

(b) The flows from Raipur pooling station to the following proposed 765 kV lines by

POWERGRID under transmission system within WR associated with New IPPs in

Chhattisgarh as per the load study done by MSETCL were very less on 765 kV 2 x

D/C Raipur pooling station to Wardha (PG) and 765 kV 2 x D/C Wardha-Aurangabad

(PG) lines compared to the capacity of lines and suggested to consider only 1xD/C

instead of 2xD/C lines.

2. Establishment of 765/400 kV GIS s/s at Pune under Krishnapatnam UMPP

In the above meeting while expressing difficulties by POWERGRID in acquiring land at

Pune for establishing AIS at Pune, MSETCL had opined that POWERGRID should go

in for AIS instead of proposed GIS at Pune and for difficulties in availability of land

MSETCL shall assist for taking up at Government level if POWERGRID required so

and requested to include this in the minutes.

Comments by CSPTCL:-

Regarding point on establishment of HVDC station at Dhule and metallic conductor

provision against use of earth return path, CSPTCL requested to include the technical

deliberation leading to the conclusion arrived at on account of the fact that even in

bipole operation, some D.C. current flows to the earth return which is found damaging to

several installations e.g. pipeline buried in the ground etc. and therefore to have a

trouble free HVDC operation metallic return is necessary which was agreed in the

meeting.

Page 27: Mailing list for 15 - wrpc · Minutes of 15th WRPC meeting held on 12th November 2010 ANNEXURES Annexure Particulars Annexure-1(a) Participants attending TCC meeting held on 11.11.2010

Minutes of 15th WRPC meeting to be held on 12th November 2010 at Udaipur

22

During TCC meeting, regarding MSETCL suggestion to review /amendment of

transmission schemes relating to HVDC s/s (PG) Dhule was discussed and it was

intimated that the scheme for HVDC S/s at Dhule was discussed in detail in the 30th

Standing Committee and was evolved through carrying out studies by CTU in

association with CEA in consideration for evolving common transmission system for

upcoming IPP generation projects in Chhattisgarh (about 15000 MW), proposed Dhule-

II (1600 MW) generation project considering alongwith its associated transmission

system. Based on above a comprehensive transmission corridors including +/- 600 kV

4000MW Raigarh(Kotra)-Dhule (PG) HVDC link was identified and agreed to in the

Standing Committee meetings.

In the TCC meeting, the Committee suggested that as the above schemes were

evolved through the process of detailed studies conducted by CTU in association with

CEA in consideration of power evacuation from various IPPs / Generators coming up in

Chhattisgarh and the same had been concurred/ firmed up by the Standing Committee

on Power System Planning for Western Region, The need for developing hybrid

corridors comprising AC and DC systems for high capacity transmission systems was

expressed in the Standing Committee meetings. Keeping in view the progress of IPP

projects and in line with the Regulatory approval for implementation of high capacity

transmission corridors for IPP projects in Chhattisgarh, including the HVDC system as

above, the implementation of the transmission elements shall require to be taken up.

The frequent reviews may create bottlenecks in power evacuation. However, the

reviews/modification needed if any could be taken up in the standing Committee on

PSP for WR for discussion and consideration.

Regarding establishment of GIS 765/400 kV s/s at Pune, MSETCL was requested to

resolve the issue regarding land availability for AIS by 30th November 2010 else

POWERGRID may go in for GIS s/s.

The matter was discussed in WRP Committee meeting and while discussing the

amendment requested in the minutes pertaining to items of standing committee

Chairman, WRPC stated that generally there had been consensus on the detailed

report of 30th Standing Committee. In case, there were any modifications or changes,

the same may have to be submitted to the Standing Committee as the schemes are

Page 28: Mailing list for 15 - wrpc · Minutes of 15th WRPC meeting held on 12th November 2010 ANNEXURES Annexure Particulars Annexure-1(a) Participants attending TCC meeting held on 11.11.2010

Minutes of 15th WRPC meeting to be held on 12th November 2010 at Udaipur

23

evolved by Standing Committee on the basis of detailed studies conducted by CTU in

association with CEA. Further, the matter relating to implementation of intrastate

projects in Maharashtra State linked with the above schemes may be conveniently

discussed with CTU by the State separately for optimizing the transmission system

requirements and the plan so arrived at may be discussed by the Standing Committee

for concurrence. MSETCL were suggested to proceed with accordingly. Director (O),

PGCIL requested MSETCL to visit PGCIL office at New Delhi with the study report of

MSETCL and PGCIL and MSETCL would discuss to sort out issues. The

implementation of transmission elements agreed in Standing Committees shall however

be taken up by PGCIL keeping in view the progress of IPP projects.

WRP Committee discussed. The Committee in general was in agreement with the decisions of the Standing Committee and suggested that any further reviews / modification sought by utilities in the transmission planning may be taken up with the Standing Committee on Power System Planning for Western Region. The implementation of transmission elements agreed in Standing Committees may however be taken up by PGCIL keeping in view the progress of IPP projects.

ITEM No. 8: LAND REQUIREMENT FOR 400/220 KV GIS SUBSTATION AT DAMAN

Member Secretary, WRPC stated that during 14th WRPC meeting held on 19.08.10,

Chairman, WRPC requested Daman & Diu to confirm the acquisition of 8-12 acres of

Land for establishing 400/220kV GIS station at Daman by PGCIL. PGCIL has intimated

that as on date no land has been allocated which is causing delay in preparation of

Feasibility Report and tying up the funding agency.

DD representative during TCC meeting held on 11.11.2010 stated that they have

identified the land for substation and the necessary formalities for acquisition are in

advanced stage.

WRP Committee noted the same.

Page 29: Mailing list for 15 - wrpc · Minutes of 15th WRPC meeting held on 12th November 2010 ANNEXURES Annexure Particulars Annexure-1(a) Participants attending TCC meeting held on 11.11.2010

Minutes of 15th WRPC meeting to be held on 12th November 2010 at Udaipur

24

ITEM No. 9: LAND REQUIREMENT FOR ESTABLISHMENT OF GIS S/S AT VADODARA

Member Secretary, WRPC stated that in the 30th Standing Committee meeting, PGCIL

had informed about the difficulty in acquisition of land of about 125-130 acres for

establishment of 765/400 kV AIS s/s at Vadodara. PGCIL vide letter No. WRTS-

II:VDR:WRSS-II:GETCO:2937 dated 16.10.10 (copy enclosed at Annexure-9) has

intimated that PGCIL & GETCO had discussions on 28.09.10 and it was agreed by

them that the availability of 125-130 acres of land is very difficult in the vicinity of

Vadodara and recommended that GIS s/s may be installed instead of AIS s/s for which

land requirement is to be tune of 50-60 acres. PGCIL intimated that to avoid further

delay they are going ahead in initiating the process of acquisition of land.

TCC recommended for establishment of GIS s/s at Vadodara in view of the difficulties of

availability of land.

WRP Committee endorsed the above recommendation of TCC. ITEM No. 10 : RECOMMENDATIONS OF PSDF GROUP Member Secretary, WRPC stated that during 14th WRPC meeting held on 19.08.2010, a

Committee comprising representatives from MSETCL, GETCO, MPPTCL, CSPTCL,

NTPC, WRLDC, POWERGRID and WRPC was formed to discuss, identify types of

projects, schemes, activities to be included in the proposal / schemes to be submitted to

Management Committee of PSDF based on relevant Regulations of CERC specified for

this purpose.

The Committee constituted as above met on 7.09.10 and 19.10.2010 to discuss the

proposals suggested by the WR constituents/utilities the minutes of the meetings were

circulated to the constituents' representatives of the Committee detailing the proposals

suggested and discussions therein.

In the second meeting of the above Committee held on 19.10.2010 the Committee had

recommended following proposals for procurement through PSDF:-

Page 30: Mailing list for 15 - wrpc · Minutes of 15th WRPC meeting held on 12th November 2010 ANNEXURES Annexure Particulars Annexure-1(a) Participants attending TCC meeting held on 11.11.2010

Minutes of 15th WRPC meeting to be held on 12th November 2010 at Udaipur

25

1. Proposal for Procurement of Spare Transformers and Reactors by PGCIL:

(i) Considering the fact that Western Region caters to major load demand and

considering the population of transformers and requirement, the Committee

suggested that there is a need to keep one transformer per State and two

reactors for the region as a whole as spare. As approved by WR Power

Committee in 14th WRPC meeting to procure 400/220 kV ICTs of 315 MVA

capacity. Out of the total four nos proposed to be procured by POWERGRID,

three ICTs of three phase units of 315 MVA and one ICT of three single phase

units were recommended may be procured.

(ii) Regarding reactors, considering the future systems and likely higher voltages,

125 MVAR bus reactors would be more effective than having 50-80 MVAR

reactors suggested by some of the utilities. As such the Committee

recommended that two nos of 125 MVAR reactors as spare that can be procured

from the PSDF subject to the technical feasibility of operating 125 MVAR

reactors in 80 MVAR installations when required. In case of the non-feasibility,

one 80 MVAR and one 125 MVAR may be procured.

(iii) The Committee had identified the strategic locations where the spare

transformers and reactors will be kept so as to facilitate with ease the

deployment of the same when required. The locations identified were Jabalpur,

Dehgam, Raipur and Pune in Madhya Pradesh, Gujarat, Chhattisgarh and

Maharashtra States respectively.

(iv) Regarding the spare transformers as the same would not be kept under charged

condition, the Committee suggested that PGCIL shall ensure that the

transformers shall be available whenever required and preventive maintenance

such as oil circulation, as confirmed by the OEM would be followed.

(v) The Committee had recommended that moving trailer mounted types with GIS

bay would facilitate ease of change of location as per system requirement. Hence

the same may be explored for future requirements.

WR Power Committee discussed the proposal recommended by the PSDF committee

as above. The WR Power Committee suggested that all four 315 MVA ICTs of three

phase units may be procured instead of three ICTs of three phase units of 315 MVA and

one ICT of three single phase units in view of fact that provision for spare single phase

Page 31: Mailing list for 15 - wrpc · Minutes of 15th WRPC meeting held on 12th November 2010 ANNEXURES Annexure Particulars Annexure-1(a) Participants attending TCC meeting held on 11.11.2010

Minutes of 15th WRPC meeting to be held on 12th November 2010 at Udaipur

26

units exists for installations equipped with single phase units and further that the

majority of existing installations are equipped with three phase units.

2. Proposal for Procurement of ERS Substations:

As suggested by in 14th WRPC meeting to discuss the proposal submitted by

POWERGRID to procure two ERS-substations of 400 kV level through PSDF, the

Committee discussed the issue. It was intimated by POWERGRID that the dimension

for 400/220 kV one single phase 117 MVA transformer of ERS was 15 m x 3 m x 4.8

m and weighed 72.5 tonnes. The Committee members therefore felt that it was difficult

to accommodate the ERS equipment at the existing substations with respect to overall

dimensions of the trailer-equipment and weight wherever the need would arise under

emergency situations.

In view of the above, the Committee had not recommended the procurement of ERS-

substations at 400 kV level in this phase. The Committee had suggested that the

procurement for ERS for lower kV level i.e. 220 kV could, however, be explored by

POWERGRID. The TCC agreed to the recommendation of PSDF group and did not recommend the

procurement of ERS-substations at 400 kV level in this phase. The TCC discussed

and it suggested that the procurement for ERS of lower kV level i.e. 220 kV, 110 kV /

132 kV could, however, be explored by the constituent states. WR Power Committee

endorsed the recommendation of TCC. 3. Proposal for Installation of H.T. Shunt Capacitors: The members indicated that the requirement for installation of shunt capacitors as

worked out by the Study Committee of WR at various locations is for achieving proper

reactive power balance and smooth voltage profile in the grid. It suggested that the

requirement for the year 2010-11 and onwards may be worked out and could be

financed through fund. The Committee for PSDF had discussed and recommended that

financing 20% of the actual cost of the capacitors (on similar lines as proposed in NR)

installed during 2010-11 and onwards may be taken under PSDF.

Page 32: Mailing list for 15 - wrpc · Minutes of 15th WRPC meeting held on 12th November 2010 ANNEXURES Annexure Particulars Annexure-1(a) Participants attending TCC meeting held on 11.11.2010

Minutes of 15th WRPC meeting to be held on 12th November 2010 at Udaipur

27

TCC discussed and agreed to the recommendation of the PSDF Committee as above.

WR Power Committee discussed and agreed to the proposal recommended by the

TCC.

4. Proposals from GETCO: The PSDF committee had discussed the proposals given by GETCO and recommended

following proposals for consideration:

(i) Establishment of on-wheel power transformer testing laboratory.

(ii) Design of monopole tower structure for 66 kV Double circuit line

(iii) Design of monopole tower structure for 220 kV Double circuit line

The above Committee had discussed these proposals and suggested that the same

relate to system improvement facilities viz. establishment of on wheel power transformer

testing laboratory (facilitates improvement in reliability, reduction in failure rate, saving in

huge capital investment due to sudden transformer failures etc.), design of monopole

tower structure for 66 kV Double circuit line and for 220 kV double circuit lines

(facilitates tower design with lower ROW against conventional tower structures,

upgradation of existing line using same available corridor, faster erection due to fewer

requirements and use of lesser floor space) which may be recommended for

procurement under PSDF.

TCC discussed the above proposals. Chairman, TCC /CMD, MPPTCL suggested that

design of monopole D/c tower structure at 132/110 kV level and on-wheel testing

laboratory for EHV grade transformer oil may also be included. The proposal for these

would be submitted by MPPTCL. TCC recommended the proposals submitted by

GETCO as above and agreed to the addition of 132/110 kV monopole D/c tower

structure design for procurement through PSDF. WR Power Committee discussed the

recommendation given by TCC. CMD MPPTCL stated that proposal in respect of

132/110 kV monopole D/c tower structure design and on-wheel testing laboratory for

EHV grade transformer oil shall be submitted by MPPTCL. As the implementation of

132/110 kV monopole D/c tower structure design would be on similar lines as that for

Page 33: Mailing list for 15 - wrpc · Minutes of 15th WRPC meeting held on 12th November 2010 ANNEXURES Annexure Particulars Annexure-1(a) Participants attending TCC meeting held on 11.11.2010

Minutes of 15th WRPC meeting to be held on 12th November 2010 at Udaipur

28

GETCO, he requested GETCO to provide necessary details to MPPTCL relating to the

same for needful action. GETCO agreed to the same.

The proposals approved by WRP Committee as above are summarized below:

(i) Four numbers spare transformers of 315 MVA, 3 phase transformers may be procured as spare and may be kept at Jabalpur, Dehgam, Raipur and Pune.

(ii) Two numbers reactors, one 80 MVAR and one 125 MVAR may be procured as spare.

(iii) The procurement for ERS of 400 kV level was not recommended by the WR Power Committee, however the WR Power Committee suggested to explore the possibility for procuring the ERS for 220 kV and 132/110 kV levels. This activity may be undertaken by the constituent states.

(iv) Financing 20% of the actual cost of the capacitors (on similar lines as proposed in NR) installed during 2010-11 and onwards may be taken under PSDF.

(v) Establishment of on wheel power transformer testing laboratory (vi) Design of monopole tower structure for 66 kV Double circuit line (vii) Design of monopole tower structure for 220 kV Double circuit line (viii) Design of monopole tower structure at 132/110 kV Double Circuit line

and on-wheel testing laboratory for EHV grade transformer oil. It was decided that if PSDF fund is not available for activities at (i) & (ii), the procurement should be taken up through normal process. The detailed schemes for the above mentioned WR Power Committee approved proposals shall be prepared by the respective proposing utilities in a specified format for further needful in line with the procedures under CERC (PSDF) Regulations, 2010. ITEM No. 11: CONSTITUTION OF VALIDATION COMMITTEE FOR CERC (SHARING

OF INTER-STATE TRANSMISSION CHARGES AND LOSSES) REGULATIONS, 2010

CERC vide letter No. L-1/44/2010-CERC dated 28.09.2010 in pursuance of Regulation

7(G) and 7(I) of CERC (sharing of Inter State transmission charges and Losses),

Page 34: Mailing list for 15 - wrpc · Minutes of 15th WRPC meeting held on 12th November 2010 ANNEXURES Annexure Particulars Annexure-1(a) Participants attending TCC meeting held on 11.11.2010

Minutes of 15th WRPC meeting to be held on 12th November 2010 at Udaipur

29

Regulations, 2010 had requested to nominate one member from Constituents /

States/utilities from WRPC for the Validation Committee to be constituted by the

Commission wherein another Member is Member Secretary.

Chairman, WRPC have nominated Shri A. B. Bhairve, Chief Engineer (LD), MPPTCL

and Shri M. M. Dhoke as alternative member. Same has been intimated to Secretary,

CERC vide letter dated 6.10.2010.

WRP Committee noted as above. ITEM No.12: REVISION OF TRANSMISSION CHARGES FOR THE PERIOD OF

APRIL 2009 TO MARCH 2010 AS PER THE DECISION TAKEN DURING 13TH WRPC MEETING

12.1 Member Secretary, WRPC stated that in 13th WRPC meeting the methodology for

working out the weighted average share for sharing of transmission charges of inter-

regional links and sharing of wheeling charges for wheeling of Central Sector power to

Goa, DD and DNH was discussed. WR Power Committee decided to include all LTOA

customers of ISTS of Western Region on the basis of the CERC (Terms & Conditions of

Tariff) Regulations, 2009 under clauses 33(2) (iv) and 33(7) of Regulation- that

generator is required to share both the intra and inter-regional transmission charges to

the extent of Long Term Open Access granted until the actual beneficiary is identified by

the Generator w.e.f. April 2009 and for wheeling of ISTS power to DD and DNH and

wheeling/transmission charges paid to MSETCL for wheeling of Central sector power to

Goa August 2009 in the context of CERC order dated 31.07.2009.

WRPC accordingly vide letter dated 4th October 2010 had issued the revision in the

Page A-4 of the REAs alongwith share calculation sheets for the period April 2009 to

March 2010 for needful by the concerned agencies.

The matter was discussed during 56th Commercial Committee Meeting held on

22.10.2010 at WRPC office, Mumbai wherein GM, Torrent Power, had intimated that

they have filed a petition in CERC seeking clarification against above decision for

sharing of inter-regional transmission charges and wheeling of ISTS power to DD &

DNH through GETCO transmission system and wheeling of ISTS power to Goa through

MSETCL transmission system.

Page 35: Mailing list for 15 - wrpc · Minutes of 15th WRPC meeting held on 12th November 2010 ANNEXURES Annexure Particulars Annexure-1(a) Participants attending TCC meeting held on 11.11.2010

Minutes of 15th WRPC meeting to be held on 12th November 2010 at Udaipur

30

Commercial Committee had noted that bills were revised as per decision taken by the

Committee in 13th WR Power Committee meeting for inclusion of LTOA users of ISTS to

share the inter-regional link transmission charges viz. ER-WR, NR-WR and SR-WR on

proportionate basis as per the CERC Tariff Regulations, 2009. The Commercial

Committee had recommended that till CERC gives decision on above in view of the

petition, the present practice of billing & sharing of transmission charges as per the

above decision taken may be followed. TCC and WR Power Committee noted and

endorsed the same.

12.2 In TCC meeting, it was intimated by MSETCL that monthly wheeling charges

payable to Maharashtra have not been credited by POWERGRID w.e.f. Aug-2009.

POWERGRID intimated that the credit is being passed on to all the constituents as per

the REA details on monthly basis. POWERGRID intimated that the accumulation arising

out on revising the REA is paid immediately upon receiving the same from other paying

utilities. It further intimated that credit could not be passed on to MSETCL due to non-

receipt of the same from GUVNL on account of arrears due for the years 2004-05-2008-

09. However, they have started billing and passing the credit to MSETCL on monthly

basis w.e.f. September 2010 and the previous dues w.e.f. Aug-2009 will be cleared in

due course.

TCC requested POWERGRID to continue to release every month to Maharashtra and

Gujarat the amount received from all paying utilities corresponding to each month as

per the REA details issued.

WRP Committee noted the same. ITEM No.13: INCLUSION OF 220 KV BUDHIPADAR-KORBA CKRCUIT –III FOR

APPORTIONMENT OF ER NTPC SCHEDULED ENERGY ON ER-WR LINK ALLOWING OPTCL TO RAISE WHEELING CHARGES OVER 220 KV BUDHIPADAR-KORBA-I,II & III.

Member Secretary, WRPC stated that during 56th Commercial committee Meeting of

WRPC held on 22nd October, 2010 at Mumbai in view of OPTCL letter no. R&T-Bill-

31/2006/ (Vol-II)/6817 dated 11.10.2010 communicating CERC decision in Petition No

6/2004 with IA No 12/2007 in the matter of fixation of wheeling charges in respect of

Page 36: Mailing list for 15 - wrpc · Minutes of 15th WRPC meeting held on 12th November 2010 ANNEXURES Annexure Particulars Annexure-1(a) Participants attending TCC meeting held on 11.11.2010

Minutes of 15th WRPC meeting to be held on 12th November 2010 at Udaipur

31

transmission system of grid corporation of Orissa Ltd. for wheeling of power from NTPC

power stations in Eastern Region (ER) through their system to Madhya Pradesh

Electricity Board w.e.f. 1.04.2001 and direction to allocate wheeling charges payable to

the OPTCL based on contract path method. The issue relating to specified contract path

i.e. Rourkela-Tarkera-Budhipadar 220 kV D/c as incidental on all the three ckts i.e. 220

kV Budhipadar ckts I, II & III, was deliberated and it was agreed that all constituents of

WR and OPTCL shall abide by CERC order on the subject. Any adjustment/ refund

shall be subject to any further judicial order on the subject. Apportionment

corresponding to the three circuits i.e. 220 kV Budhipadar ckts I, II & III shall be done for

OPTCL system and apportionment corresponding to the two circuits shall be done for

Chhattisgarh.

TCC discussed the matter and agreed with the recommendations of the Commercial Committee as above. WRPC approved the same. ITEM No.14: PERFORMANCE OF WR GRID DURING AUGUST 2010 TO OCTOBER

2010 14.1 SYSTEM PERFORMANCE

Member Secretary, WRPC stated that during August, 2010 and October, 2010 system

frequency was in the permissible range of 49.5 Hz to 50.20 for 93.49 % and 85.89 % of

time. Frequency remained below 49.50 Hz for 8.19 % of time during August, 2010 and

for 0.95 % of time during October, 2010. In higher frequency regime, system frequency

was above 50.20 Hz in the range of 4.20% and 12.28 % of time respectively in August,

2010 and September, 2010. The monthly average frequency was in the range of 49.85

Hz (in August 2010) to 49.94 Hz (in October, 2010).

The maximum period frequency was below 49.2 Hz was 1.78 % of time during August

2010 and 0.01% of time during October, 2010.

The number of occasions when instantaneous frequency touched 48.8 Hz was 16

occasions during August 2010 whereas it was ‘Nil’ occasions in October 2010. Thus the

System performance was better than as that in the last quarter. The detail of frequency

profile for the months of August to October 2010 is placed at Annexure-14.1(a).

Page 37: Mailing list for 15 - wrpc · Minutes of 15th WRPC meeting held on 12th November 2010 ANNEXURES Annexure Particulars Annexure-1(a) Participants attending TCC meeting held on 11.11.2010

Minutes of 15th WRPC meeting to be held on 12th November 2010 at Udaipur

32

WRLDC issued advisory messages of type A, B and C to WR constituents for curtailing

over drawal as below:

Message type /Constituent A B C Total GETCO August -2010 1 2 0 3 September-2010 3 Nil Nil 3 October -2010 Nil Nil Nil Nil MPPTCL August -2010 7 Nil Nil 7 September-2010 Nil Nil Nil Nil October -2010 2 Nil Nil 2 CSPTCL August -2010 Nil Nil Nil Nil September-2010 1 Nil Nil 1 October -2010 Nil Nil Nil Nil MSETCL August -2010 15 05 Nil 20 September-2010 9 2 Nil 11 October -2010 1 Nil Nil 1 DNH August -2010 Nil Nil Nil Nil September-2010 Nil Nil Nil Nil October -2010 Nil Nil Nil Nil GOA August -2010 1 Nil Nil 1 September-2010 Nil Nil Nil Nil October -2010 Nil Nil Nil Nil

No regulatory measures were required to be taken.

There were net inter-regional export of 2130.49 MUs and 1305.5 MUs by WR against

net export schedule of 1753.109 MUs, and 881.613 MUs respectively in August and

September 2010.

The instances of overdrawal and TTC violation by neighbouring regions were taken up

by WRLDC in real time. The messages issued by WRLDC for curtailment of overdrawl/

TTC violation to other regions.

Page 38: Mailing list for 15 - wrpc · Minutes of 15th WRPC meeting held on 12th November 2010 ANNEXURES Annexure Particulars Annexure-1(a) Participants attending TCC meeting held on 11.11.2010

Minutes of 15th WRPC meeting to be held on 12th November 2010 at Udaipur

33

LINK NR ER MPPTCL MSETCL TOTAL

No of O/D Messages

August -2010 34 26 Nil Nil 60

September-2010 4 3 Nil Nil 7

October-2010 1 1 Nil Nil 2

No of TTC Messages

August -2010 45 Nil Nil Nil 45

September-2010 2 1 1 1 5

October-2010 Nil 1 1 1 3

During August 2010 to October 2010 period, the maximum unrestricted demand of

Western Region was in range of 33989 MW and 40179 MW, as compared to 37060 MW

and 38739 MW during the same period last year respectively. The region faced capacity

shortage in the range of 3842 MW and 5840 MW (peak deficit of 10.67 % &14.53 %)

during August 2010 & October 2010 respectively. The per day energy requirement

during August 2010 to October 2010 was in the range of 648.33 MUs to 791.55 MUs.

The energy shortage was 49.90 MUs per day to 91.53 MUs per day during the above

period. The details of unrestricted peak demand, demand met and energy requirement

and availability are as furnished at Annexure-14.1 (b).

Overall voltage profile had been satisfactory during the period under review. However,

instances of low and high voltages beyond the IEGC specified operating range were

observed at some of the EHV sub-stations in the region. Minimum voltage of 363 kV &

364 kV was noted on 9th August & 7th August 2010 at 400 kV Bhilai & Gwalior

substation respectively. Higher voltages in the range of 421 kV to 441 kV were noted.

Most of the 400 kV lines had to be remained open continuously to control high voltages

viz SSP-Rajgarh, SSP-Dhule, Khandwa- Rajgarh, ISP-Nagda, Nagda-Dehgam (one ckt

on few occasions), Wardha – Akola I, Raipur – Bhadravati, 765 kV Seoni – Bina had to

be opened to control high voltages. SSP units run in synchronous condenser mode for

216 m/c hrs. in the month of August, 2010. Flow on HVDC, C`pur-Padghe was kept at

minimum possible limit during night off-peak hours to minimize the effect on high

voltage due to filter banks of HVDC station.

Page 39: Mailing list for 15 - wrpc · Minutes of 15th WRPC meeting held on 12th November 2010 ANNEXURES Annexure Particulars Annexure-1(a) Participants attending TCC meeting held on 11.11.2010

Minutes of 15th WRPC meeting to be held on 12th November 2010 at Udaipur

34

14.2 The detail of voltages at important 400 kV and 765 kV sub-stations for the months

August 2010 and October 2010 is placed at Annexure- 14.2. In order to control

incidences of high voltages during low load periods, installation of reactors at following

locations as planned by various utilities is in the process as per following schedule:

S.No. 400 kV Substation

Size (MVAR)

Implementing agency

Expected commissioning date

1. Khandwa 1x125 PGCIL Commissioned on 30th Sep. 2010

2. Dhule 2x50 MSETCL 1x50 MVAr is already commissioned. 2nd reactor is expected in December 2010 end.

3. Dehgam 1x125 PGCIL October 2010

4. Kasor 1x125 GETCO October 2010

5 Soja 1x80 GETCO November 2010

6 Rajgarh 1x125 PGCIL September 2011

The Committee had noted that timely commissioning of the above reactors is likely to

help in smoothening of high voltage profile.

14.3 AUFLS Performance. The month-wise details relating to performance of AUFLS scheme in Western Region

during the period August 2010 to October 2010 in terms of quantum of load relief

obtained and number of occasions the UFR operated is at Annexure-14.3.

WRP Committee noted the same. ITEM No.15: ANTICIPATED POWER SUPPLY POSITION IN WESTERN

REGION FOR THE PERIOD FROM OCTOBER 2010 TO JANUARY 2011

The anticipated power supply position in the region for the period from October 2010 to

January 2011 is at Annexure-15. The period under consideration consist of winter

season. The demand during the period starts increasing from October 2010. During this

period the regional demand is likely to be moderate. The anticipated regional demand is

likely to vary between 39940 MW to 40910 MW and the capacity shortage will vary from

11.13 % to 13.95 %. In terms of energy, the unrestricted requirement is expected to

range from 23928 MUs to 25000 MUs with regional energy deficit of the order of 4.86 %

Page 40: Mailing list for 15 - wrpc · Minutes of 15th WRPC meeting held on 12th November 2010 ANNEXURES Annexure Particulars Annexure-1(a) Participants attending TCC meeting held on 11.11.2010

Minutes of 15th WRPC meeting to be held on 12th November 2010 at Udaipur

35

to 7.53 %. The anticipated Peak demand shortage of 255 to 1225 MW in Gujarat, 450

to 635 MW in Chhattisgarh, 4775 to 5250 MW in Maharashtra, 1365 to 2025 MW in

Madhya Pradesh, 70 to 145 MW in Goa, 75 to 140 MW in DD & 17 MW to 94 MW in

DNH is likely to prevail.

WRP Committee noted the same. ITEM No. 16: PLANNING TO MEET CONSUMER LOADS

The Commission in order dated 15th December, 2009 in suo-motu Petition No.152/2009

relying on the provisions of Grid Code, 2009 {Regulations 5.3.3 & 6.4.8} directed at

Para 4 as follows:

Quote

We direct all the State Transmission Utilities in the country including State Electricity

Boards / Departments where a separate STU has not yet been constituted to submit the

report as per Annexure A to this order, to this Commission, their respective State

Commission and State Government, and the Regional Load Despatch Centre for the

first week of January, April, July and December by the last day of the preceding

November, February, May and August respectively

Unquote Accordingly, all the State Transmission Utilities / State Electricity Boards / Departments

where a separate STU has not yet been constituted are required to submit the report on

“Planning to meet the Consumer Load” for the period first week of January, April, July

and December by the last day of the preceding November, February, May and August

respectively. It has been observed that only few of the State Utilities are sending this

report. The constituents of Western Region are requested to submit the report regularly

to the Central Commission as per format enclosed at Annexure-16.

WRP Committee noted the same.

Page 41: Mailing list for 15 - wrpc · Minutes of 15th WRPC meeting held on 12th November 2010 ANNEXURES Annexure Particulars Annexure-1(a) Participants attending TCC meeting held on 11.11.2010

Minutes of 15th WRPC meeting to be held on 12th November 2010 at Udaipur

36

ITEM No.17: WIDE AREA MEASUREMENT SYSTEM (WAMS) IN WR

Member Secretary, WRPC stated that the matter regarding implementation of WAMS in

WR was discussed during 11th meeting of WRPC held on 25th September 2009 at

Raipur and also during 13th meeting of WRPC held on 9th April 2010. A meeting of Task

Force on WAMS was proposed by WRPC on 10th March 2010 to discuss the modalities

etc. regarding implementation of WAMS Project in WR. However, GM (LD & C), PGCIL

vide letter dated 5th March 2010 had intimated that in view of CERC order directing one

time expenses from UI Fund towards the above project, PGCIL had taken up the issue

with CSIR and on their approval they would sign the agreement with CSIR and other

consortium partners. It is proposed to hold separate meeting with the constituents

thereafter. During 13th WRPC meeting PGCIL were requested to expedite issues

concerning approval/ signing of the agreement etc. with CSIR and other consortium

partners so that a meeting of Task Force on WAMS could be called at the earliest for

further needful action. POWERGRID vide communication dated 21.10.2010 have

intimated that POWERGRID Board have approved the Project with certain conditions.

The acceptance of the conditions by the consortium members had not been received by

them thereby resulting delay in signing of necessary agreement with CSIR for moving

ahead with the Project Implementation. POWERGRID further intimated that they have

requested consortium partners to send their response within two weeks' time.

During TCC meeting held on 11.11.2010, POWERGRID intimated that their Board have

approved the Project with certain conditions like availability of software for all RLDCs

and NLDC. The acceptance of the conditions by the consortium members had not been

received by them thereby resulting delay in signing of necessary agreement with CSIR

for moving ahead with the Project Implementation. POWERGRID further intimated that

they have requested consortium partners to send their response within two weeks' time.

Chairman WRPC suggested that in the presentations/ exposures on WAMS systems

made by eminent experts like Shri A.G.Phadke may be attended by the regional utilities

for the benefit of all constituents.

WRP Committee noted the same.

Page 42: Mailing list for 15 - wrpc · Minutes of 15th WRPC meeting held on 12th November 2010 ANNEXURES Annexure Particulars Annexure-1(a) Participants attending TCC meeting held on 11.11.2010

Minutes of 15th WRPC meeting to be held on 12th November 2010 at Udaipur

37

ITEM No.18: ONGOING TRANSMISSION SCHEMES IN WESTERN REGION

Member Secretary, WRPC stated that in accordance with the decision taken in the 12th

WRPC meetings held on 16th January 2010 at Vadodara 3rd meeting was held on 6th

September 2010 at PGCIL, WRHQ Office, Nagpur to review status of ongoing

transmission projects in the Western Region.

The status of the construction of transmission schemes under execution by Gujarat

Electricity Transmission Company Ltd., Madhya Pradesh Power Transmission Company

Ltd., Chhattisgarh State Power Transmission Company Ltd., Maharashtra State

Electricity Transmission Company Ltd, PGCIL & Reliance Power Transmission Ltd. was

reviewed and discussed in detail under various heads agreed during 2nd TRM meeting.

The following emerged during the discussion:

(i) It was observed that several ROW issues relating to land acquisition and

environment clearance in the States including Maharashtra were attributing mainly

to the progress of timely completion of transmission line construction work.

(ii) MD, GETCO stated that in Gujarat State the ROW issues have been mostly

addressed by GETCO by way of allowing adequate compensation.

(iii) Chairman, WRPC / CMD, MPPTCL stated that to expedite transmission line

completion activity a standard provision for compensation should be in place under

State Govt. norms which can be allowed to provide compensation wherever arises

to resolve matter so that project works get proceeded further without involving

delays to this account.

(iv) MD, MSETCL, stated that local issues arising out of ROW problems are under

active consideration by Maharashtra State Government.

He said, however to address forest clearance and other related administrative

issues arising out in construction of 400 kV lines in the Maharashtra State and to

expedite work for 400 kV Vapi(PG)-Navi Mumbai D/C line he would shortly arrange

a meeting with concerned State authorities and implementing agency viz. PGCIL.

Page 43: Mailing list for 15 - wrpc · Minutes of 15th WRPC meeting held on 12th November 2010 ANNEXURES Annexure Particulars Annexure-1(a) Participants attending TCC meeting held on 11.11.2010

Minutes of 15th WRPC meeting to be held on 12th November 2010 at Udaipur

38

(v) ED, WRLDC, POSCO requested to expedite construction of 400 kV D/C Gandhar-

Navsari and 400 kV D/C Navsari- Mumbai line (Boisar) line in view of excessive

loading of network associated with Sugen TPS for power flow towards Maharashtra

State. Director (Project), PGCIL said that PGCIL will make all efforts to complete

400 kV D/C Gandhar-Navsari and 400 kV D/C Navsari- Mumbai line (Boisar) as per

revised schedule.

(vi) ED WRTS-I, PGCIL stated that due to change in location from Bhiwandi to Boisar for

400 kV D/C Navsari- Mumbai line(Boisar), BOQ got changed and earlier award had

to be annulled for project. For the new location fresh award will be given shortly

which would take minimum 18 months from the date of award for completion of the

work.

(vii) Reliance Energy Transmission Ltd intimated that work of LILO of Lonikhand

(MSEB)-Kalwa (MSEB) 400 kV D/C at Pune (PG) would match with the readiness

of Pune sub-station. MSETCL intimated that all State system associated with Pune

sub-stations would be completed by December 2010 and loads would be ready by

March 2011.

(viii) CSPTCL intimated that the finalized list in respect of Chhattisgarh system would be

furnished as per the discussions in the prescribed format.

(ix) MSETCL requested PGCIL to expedite commissioning of 400 kV Wardha (PG)-

Aurangabad (PG), 400 kV Wardha (PG)- Parli (PG), 400 kV Parli (PG) –

Bhadravati (PG), 400 kV Parli (PG) – South Solapur (PG), 400 kV South Solapur

(PG) – Kolhapur MSETCL, 400 kV Aurangabad MSETCL-Pune (PG) , 400 kV

Parli (PG)- Parli MSETCL, 400 kV Aurangabad (PG)- Aurangabad (II) MSETCL,

400 kV Parli (PG)- Pune (PG), LILO of 400 Kv Lonikand- Kalwa at Pune (PG) and

LILO of 400 kV Solapur – Karad S/C at South Solapur, PGCIL was further

requested by MSETCL to prepone the commissioning schedule of 400 kV Wardha

(PG)- Aurangabad (PG) line so as to complete before September 2012 for

evacuation of power from eastern part of Maharashtra.

(x) Updated status of the all lines was discussed. The updated status for priority lines

identified is as below:-

Page 44: Mailing list for 15 - wrpc · Minutes of 15th WRPC meeting held on 12th November 2010 ANNEXURES Annexure Particulars Annexure-1(a) Participants attending TCC meeting held on 11.11.2010

Minutes of 15th WRPC meeting to be held on 12th November 2010 at Udaipur

39

S.No. Line Implementing Agency

Anticipated target

1 400 kV D/C Mundra (Adani) - Varsana D/C line

Gujarat Dec-10

2 400 kV Tappar( Varsana)-Hadala line Gujarat Oct -10 220 kV V D/C Varsana (Tappa)-Morbi Gujarat Charged on

31.3.2010 4 400 kV D/C line from Bhusawal II to

Aurangabad (Loc. No. 1 to 270) Maharashtra Oct-10

5 400 kV D/C Birsighpur(MPGENCO)-Damoh(PG)

PGCIL Oct-10

6 400 kV Vapi(PG)-Navi Mumbai D/C line

PGCIL Dec-11

7 400 kV D/C Mundra-Bachchau- Ranchodpur line (Triple snowbird)

PGCIL Dec-11

8 400 kV D/C Gandhar-Navsari line PGCIL Dec-11 9 400 kV D/C Navsari- Mumbai line(Boisar) PGCIL June-12 10 400 kV D/C Ranchi – Rourkela PGCIL Dec-10 11 400 kV D/C Rourkela – Raigarh PGCIL Dec-10 12 400 kV D/C Raigarh – Raipur PGCIL 30.09.2010 13 LILO of Lonikhand(MSEB)-

Kalwa(MSEB)400 kV D/C at Pune(PG) Reliance (IPTC route)

Dec-10

14 LILO of Solapur(MSEB)-Karad(MSEB)400 kV D/C at Pandharpur/Solapur(PG)

Reliance (IPTC route)

Oct-10

15 400 kV D/C Limbdi(Chorania)(GEB)-Ranchodpura(Vadavi)(GEB)

Reliance (IPTC route)

Dec-10

16 400 kV D/C Ranchodpura(Vadavi)(GEB)-Zerda(Kansari)(GEB)

Reliance (IPTC route)

Dec-10

17 400 kV D/C Rajgarh(PG) – Karamsad (GEB)

Reliance (IPTC route)

May- 11

The details of ongoing transmission schemes under construction are enclosed at

Annexure-18.

Following transmission lines have been commissioned in Western Region during

2010-11 up to September. 2010:-

S.N. State/ Agency

400kV/ 220kV

Length in Ckt. Kms.

Name of Transmission Line

Date of Charging

1 Madhya Pradesh.

220kV 54.00 Maheshwar-Nimrani Line

12.04.10

2 Chhattisgarh 220 kV

50.90 220kV DCSS Khedamara-220kV S/S Bematara

18.05.10

3 Gujarat 220kV 118.00 220kV Viramgam-Bhat line

29.05.10

Page 45: Mailing list for 15 - wrpc · Minutes of 15th WRPC meeting held on 12th November 2010 ANNEXURES Annexure Particulars Annexure-1(a) Participants attending TCC meeting held on 11.11.2010

Minutes of 15th WRPC meeting to be held on 12th November 2010 at Udaipur

40

4 Gujarat 220kV 71.25 220kV Bhat-Salejada line

01.06.10

5 Madhya Pradesh

220kV 266.60 Chhindwara-Betul 220kV DCDS Line

03.06.10

6 Maharashtra 220kV 46.00 220 kV Chandrapur- Warora for 220 kV Wani

10.06.10

7 Maharashtra 400kV 54.75 400 kV D/C Jaigad- New Koyana line (Ckt.-I)

06.04.10

8 Chhattisgarh 220kV 42.94 LILO of 220kV Bhatapara-Raipur (PGCIL) at Doma

10.07.10

9 Maharashtra 400kV 137.43 Dabhol-Nagothane II ckt.

24.08.10

10 Madhya Pradesh

220kV 7.8 LILO of 220kV Satna- Bansagar line at Kotar S/S

15.08.10

11 Powergrid 400kV 440.00 400 kV D/C Raigarh – Raipur

30.09.10

Total 1289.67

During TCC meeting held on 11.11.2010, Chairman TCC intimated that he received

letter from M/s Reliance requesting him to assist in ROW problems. He intimated that

he had requested Reliance to intimate the concerned persons/ agency with whom he

issue can be addressed. Reply from Reliance is awaited. He further stated that MP

state’s line associated with implementation of WR system strengthening was 220 kV line

Maheshwar-Nimrani was commissioned on 12.4.2010 as per the schedule and stressed

that the schedule of schemes for generating stations and the associated transmission

network should match with each other for deriving the desired benefit.

ITEM No. 19: ONGOING GENERATION SCHEMES IN WESTERN REGION The generating units expected to be commissioned during current year are as follows:

Name of the Power Projects Unit No.

Capacity (MW) Schedule Date of Commissioning

GUJARAT (i) Mundra TPP Ph-I, APL 4 330 Nov. 2010 (ii) Hazira CCPP (GSEG) GT+ST 350 Mar. 2011 (iii)Mundra STPP APL (iv) Ukai TPS Ext.

1 6

660 490

Jan. 2011 Feb. 2011

MADHYA PRADESH (i) Satputa TPS Ext. 10 250 Nov. 2010

Page 46: Mailing list for 15 - wrpc · Minutes of 15th WRPC meeting held on 12th November 2010 ANNEXURES Annexure Particulars Annexure-1(a) Participants attending TCC meeting held on 11.11.2010

Minutes of 15th WRPC meeting to be held on 12th November 2010 at Udaipur

41

Name of the Power Projects Unit No.

Capacity (MW) Schedule Date of Commissioning

(ii) Satputa TPS Ext. 11 250 March 2011 MAHARASHTRA (i) JSW Energy, Ratnagiri (4x300) 2 300 Sep. 2010 (ii) JSW Energy, Ratnagiri (4x300) 3 300 Dec. 2010 (iii) JSW Energy, Ratnagiri (4x300) 4 300 March 2011 CENTRAL SECTOR – NTPC (i) Sipat-I, TPP 1 660 Nov. 2010 2 660 May 2011 3 660 Nov 2011 (ii) Korba STPP Stage-III 7 500 Oct 2010

The details of ongoing generation schemes in WR both under State as well as Central

Sector are enclosed at Annexure-19.

Following Generating units have been commissioned in Western Region during 2010-11

up to September. 2010

S.No. State/Agency Name of Project Unit No. Capacity in MW

Date of Sync./Comml.

1 Gujarat Surat Lignite TPP Extn.

3 125.00 12.04.10

2 Gujarat Surat Lignite TPP Extn.

4 125.00 23.04.10

3 Maharashtra Wardha Warora TPP

1 135.00 05.06.10

4 Gujarat Mundra TPP Ph-2 3 330.00 02.08.10 5 Maharashtra JSW Energy TPP 1 300.00 24.08.10 6 Maharashtra Wardha Warora

TPP 2 135.00 10.10.10

Total 1150 WRP Committee noted the same. ITEM No. 20: POWER SYSTEM DEVELOPMENT FUND

20.1 CERC vide order dated 4th June 2010 have issued regulation called the Central

Electricity Regulatory Commission (Power System Development Fund) Regulations

2010. As per the provision under the above regulations, a fund to be called the “Power

System Development Fund” shall be constituted and there shall be credited thereto.-

a) Congestion charges standing to the credit of the “Congestion Charge Account”

Page 47: Mailing list for 15 - wrpc · Minutes of 15th WRPC meeting held on 12th November 2010 ANNEXURES Annexure Particulars Annexure-1(a) Participants attending TCC meeting held on 11.11.2010

Minutes of 15th WRPC meeting to be held on 12th November 2010 at Udaipur

42

b) Congestion amount arising from the difference in the market prices of different

regions

c) Unscheduled Interchange charges standing to the credit of the “Unscheduled

Interchange Pool Account Fund”

d) RLDC reactive energy charges standing to the credit of Reactive Energy

Charges Account;

e) Such other charges as may be notified by the Commission from time to time;

f) Provided that amounts representing the sources as specified in sub-clauses (a)

to (d) and lying in the custody of Central Transmission Utility together with

interest earned thereon upto 30th of April, 2010 shall be credited to the Fund.

20.2 Regulation 7 of the Power System Development Fund, Regulation 2010 specifies

that an officer of the level of General Manager or above is to be nominated by each of

the five Regional Power Committee as member of Management Committee. DGM,

NLDC & Secretary, PSDF vide letter dated 20.09.10 had requested for nomination from

WRPC which was to be sent by 25.9.2010. Chairman, WRPC had nominated Member

Secretary, WRPC as a member of the Management Committee from WRPC. The same

has been intimated to Secretary, PSDF vide letter dated 24.09.10.

WRP Committee noted the same. ITEM No.21: PAYMENTS OF UI AND REACTIVE ENERGY CHARGES

21.1 As per the information received from WRLDC, the status of payment to UI pool

account and Reactive Energy Pool account as on 28.10.2010 i.e. upto week 11.10.10 to

17.10.10 of the current financial year is given below: -

UI Pool Account Reactive Energy Pool Account Constituents Dues (in Rs.) Constituents Dues (in Rs.)CHHATTISGARH -93,908,415 CHHATTISGARH -22,466,483MADHYA PRADESH 115,413,749 MADHYA PRADESH 4,028,940GUJARAT -77,834,935 GUJARAT 16,104,219MAHARASHTRA 189,168,339 MAHARASHTRA -2,792,970GOA -6,948,293 GOA -2,792,386DD 73,077,957 DD 2,385,602DNH 7,489,693 DNH 3,759,148NTPC -21,173,114 NR Exchange -139,745,159

Page 48: Mailing list for 15 - wrpc · Minutes of 15th WRPC meeting held on 12th November 2010 ANNEXURES Annexure Particulars Annexure-1(a) Participants attending TCC meeting held on 11.11.2010

Minutes of 15th WRPC meeting to be held on 12th November 2010 at Udaipur

43

UI Pool Account Reactive Energy Pool Account SR Exchange -13,374,900 ER Exchange 118,086,398 Jindal Power 36,937,396 HVDC Vindhyachal -45,153 HVDC Bhadravati -285,217 Lanco Amarkantak -24,969,157 Mundra APL 0 Diff. due to -2,049,346,587 Diff. due to Addl. UI -1,352,344,529 Diff. due to capping155 -1,323,595,100 Net Total -4,563,397,027 -1,773,930

WRP Committee noted the same. 21.2 The requirement of LC to be opened by the entities of WR as per the provisions in

Central Electricity Regulatory Commission (Unscheduled Interchange Charges and

related matters) (Amendment) Regulations, 2010 was noted by WRP Committee in 14th

WRPC meeting as below:

Sr. No. Entity of WR LC requirement for payment of UI charges

1 Chhattisgarh 802 Lacs

2 Madhya Pradesh 373 Lacs

3 Gujarat 1238 Lacs

4 Maharashtra 928 Lacs

5 Goa 79 Lacs

6 Daman & Diu 137 Lacs

7 Dadra & Nagar Haveli

124 Lacs

8 Jindal Power 279 Lacs

During 56th CCM, WRLDC had intimated that requirement of LC amount in respect of

Madhya Pradesh, DD and Goa has been increased on account of exceeded weekly

payable liability. Madhya Pradesh, DD and Goa have been requested to open the LC for

the revised amount by WRLDC. The revised amount of LC as intimated by WRLDC is

288 Lacs, 354 Lacs and 2210 Lacs for DD, DNH and Madhya Pradesh respectively.

WRLDC further informed that Jindal Power Ltd. has opened LC in favour of WRLDC.

Page 49: Mailing list for 15 - wrpc · Minutes of 15th WRPC meeting held on 12th November 2010 ANNEXURES Annexure Particulars Annexure-1(a) Participants attending TCC meeting held on 11.11.2010

Minutes of 15th WRPC meeting to be held on 12th November 2010 at Udaipur

44

During 56th CCM, GUVNL sought clarification if SLDC are required to open LC as

system operator for the states. It was intimated that LD/Transco/ Discom should open a

Letter of Credit (LC) as applicable in respective States. POSOCO, WRLDC requested to

open a Letter of Credit (LC) by month end.

WRP Committee noted the same. ITEM No.22: DEVELOPMENT OF SOFTWARE FOR ISSUANCE OF RTA & RTDA Member Secretary, WRPC stated that a meeting amongst Member Secretaries of all

regions was held at NRPC office, New Delhi on 12.10.10 to discuss the provision under

regulations regarding implementation of sharing of transmission charges and losses on

common platform in all the RPCs to harmonise the accounting. In this connection,

Member Secretary, NRPC indicated that they had attempted the format for preparation

of Regional Transmission Accounts (RTA) and shared with other RPCs. He further

indicated that ABT based Energy accounting software is being developed for Northern

Region at an estimated cost of Rs. 10 lakh through DOEACC, a society under Ministry

of Communication and IT. GOI and the software for sharing of Inter-State transmission

charges and losses could also be developed through DOEACC and the cost of these

could be shared equally by all regions for which Member Secretaries agreed with the

suggestion.

The cost estimates would be made available by NRPC in due course. The record notes

of discussions held on 12.10.10 is enclosed at Annexure-22.

WRP Committee in principle approved the sharing of the cost. ITEM No.23: GRANT OF CONNECTIVITY 23.1 PGCIL have intimated that the connectivity to following IPPs have been granted

as per the provisions of the CERC (Grant of Connectivity, Long Term Access and

Medium-term Open Access in inter-state transmission and related matters) Regulations

2009.

Sr.

No

Particulars of

IPP

MW Location Point of connectivity

Page 50: Mailing list for 15 - wrpc · Minutes of 15th WRPC meeting held on 12th November 2010 ANNEXURES Annexure Particulars Annexure-1(a) Participants attending TCC meeting held on 11.11.2010

Minutes of 15th WRPC meeting to be held on 12th November 2010 at Udaipur

45

1 Gupta Energy Pvt. ltd

540 Maharashtra LILO of 400 kV Bhadravari-Parli one circuit at GEPL w.e.f. 1.11.2011

2 SJK Powergen Limited

1320 Madhya Pradesh

765/400 kV Jabalpur Pooling station at 400 kV level w.e.f. 1.06.2014

3 Visa Steel Limited

450 Chhattisgarh 400 kV Raigarh Pooling Station w.e.f. 1.08.2013

4 Chitrangi Power Pvt. ltd

3960 MW

Madhya Pradesh

765 Vindhyachal pooling station w.e.f 1.03.2013

5 Essar Power MP Ltd.

600 Madhya Pradesh

Bus extension of Mahan TPS Ph-I (with 400 kV interconnection to WR pooling station at Bilaspur w.e.f. 1.03.2013

6 Adani Power Ltd

400 Gujarat Dedicated system with CTU w.e.f.1.06.2011

7 Pipavav Energy ltd

1200 Gujarat 400 kV Pirana(PG) w.e.f.1.01.2013

8 Raigarh Energy ltd.

600 Chhattisgarh 400 kV Raigarh Pooling station w.e.f. 1.12.2013

9 Cosmos sponge & Power Ltd.

350 Chhattisgarh Raigarh Pooling stations w.e.f. 1.06.2013

10 Lanco Vidarbha Thermal Power Pvt. Ltd

1320 Maharashtra LILO of 765 kV Seoni –Wardha S/c at LANCO Vidarbha TPS w.e.f. 1.01.2013

11 Essar Power Gujarat Ltd

3240 Gujarat 400 kV Bachau S/s w.e.f. 1.06.2012

Representative of GETCO raised the query regarding injection of power at UI/STOA

without having to pay transmission charges of LTOA upon the grant of connectivity.

ED, WRLDC stated that LTA is for enabling the synchronizing of the generator to the

grid for testing purposes etc. only. However the utility can inject power on regular basis

after identifying the beneficiaries and obtaining the Long-term open Access thereof from

the CTU.

WRP Committee noted the same. 23.2 EXTENTION OF START DATE OF BPTA REQUEST BY VARIOUS LONG

TERM OPEN ACCESS APPLICANT IN WR

Page 51: Mailing list for 15 - wrpc · Minutes of 15th WRPC meeting held on 12th November 2010 ANNEXURES Annexure Particulars Annexure-1(a) Participants attending TCC meeting held on 11.11.2010

Minutes of 15th WRPC meeting to be held on 12th November 2010 at Udaipur

46

PGCIL vide letter dated C/OS/WRPC-15th /Agenda dated 27.10.2010 intimated that long

term open access has been granted to following applicants for transfer of power from

their respective generation projects to target beneficiary/regions.

I. Air liquide LTOA-6 MW, Injection point – Wani/Chandrapur (MSETCL), Drawal point - 66 kV Raneri S/s of GETCO PGCIL further intimated that M/s Air liquide requested to extend the start date of

BPTA to Jan-2011 from Aug-2010 because of delay in commissioning of

generating station. II. Visa power

LTOA-1062 MW, Injection point – 765/400 kV Raigarh (kotra) Pooling station in Chhattisgarh Target beneficiary – WR/NR PGCIL further intimated that M/s Visa power requested to extend the start date of

BPTA to Oct-2013 from Jan-2013 because of delay in commissioning of

generating station. WRP Committee agreed to the above. ITEM No.24: DECLARATION OF TRANSMISSION ELEMENTS INTO COMMERCIAL

OPERATION BY PGCIL 24.1 PGCIL had intimated that 400 kV, 50 MVR bus reactor at Gwalior along with its

associated bay under WRSS-II, Set-D transmission system has been charged on

17.08.2010 and put into regular operation in Western Region-II. Accordingly, the

monthly transmission charges of the above transmission element along with associated

bays will be payable by concerned WR constituents w.e.f. 1.09.2010.

24.2 PGCIL had intimated that 125 MVR, 400 kV bus reactor at Khandwa along with

its associated bays under WRSS-VII has been charged successfully on 30.09.2010 and

put into regular operation in Western Region -II. Accordingly, the monthly transmission

charges of the above transmission line along with associated bays will be payable by

concerned WR constituents w.e.f. 1.10.2010

24.3 PGCIL vide letter No. WR-II/VDR/503 dated 1.10.2010 intimated that 220 kV D/c

Vapi-Khadoli transmission line alongwith its associated bays under WRSS-V

Page 52: Mailing list for 15 - wrpc · Minutes of 15th WRPC meeting held on 12th November 2010 ANNEXURES Annexure Particulars Annexure-1(a) Participants attending TCC meeting held on 11.11.2010

Minutes of 15th WRPC meeting to be held on 12th November 2010 at Udaipur

47

transmission system has been charged successfully on 15.09.2010. Accordingly, the

monthly transmission charges of the above transmission line along with associated bays

will be payable by concerned WR constituents w.e.f. 1.10.2010

24.4 PGCIL vide letter No. WRTS:Comm:NGP:522 dated 1.10.2010 intimated that

400 kV Raigarh-Raipur ckts III & IV under East – West corridor were put into regular

operation in WR and the same is under commercial operation w.e.f. 1.10.2010.

Accordingly, the monthly transmission charges of the above transmission line along with

associated bays will be payable by concerned WR constituents w.e.f. 1.10.2010

WRP Committee noted the same.

ITEM No.25: RENOVATION AND MODERNISATION OF WRPC OFFICE BUILDING Member Secretary, WRPC stated that during 13th WRPC meeting the matter regarding

renovation & Modernisation of WRPC Office Building was deliberated and agreed that

R&M work of WRPC building shall be done by POWERGRID on deposit basis. During

14th WRPC meeting the revised estimated cost of Rs 7,57,83,185/- was approved

based on recommendations of the sub committee renovation & Modernisation of WRPC

Office Building and also authorised sub- Committee to take decisions from time to time

required for completion of this work and put up the final bill duly examined after the work

is over.

As per the recommendations of the above sub-committee 50% payment of the

estimated cost is required to be made before placement of the LOA for Civil works and

initial mobilization & start of work activities at premises. Accordingly as per the sharing

pattern approved in 13th WRPC meeting WRPC had worked out the share of members

to be deposited towards first installment of 50 % payment (i.e. 50% of the total

estimated cost of Rs 7,57,83,185/-) as above.

During the TCC meeting held on 11.11.2010, Chairman, TCC said that requests from

NCA were being received for excluding them from contributing towards the R&M work

as O&M and other expenses payable are already being shared by SSP’s beneficiary

States which are to contribute the above R&M expenditure. NHDC and SLDCs had also

requested on similar ground. TCC discussed and recommended that only for this

Page 53: Mailing list for 15 - wrpc · Minutes of 15th WRPC meeting held on 12th November 2010 ANNEXURES Annexure Particulars Annexure-1(a) Participants attending TCC meeting held on 11.11.2010

Minutes of 15th WRPC meeting to be held on 12th November 2010 at Udaipur

48

particular R&M work, NCA, NHDC and SLDCs may be excluded from making payment

and distribute the sharing of the remaining amount amongst rest of the members in the

manner as approved in the 13th WRPC meeting.

WR Power Committee discussed and agreed to exclude NCA, NHDC and SLDCs from

contributing towards only for the this particular R&M work and distribute sharing of the

remaining amount amongst the rest of the members in the manner as approved by the

WR Power Committee in the 13th WRPC meeting and as per the payment schedule

decided in 14th WRPC meeting held on 19th August 2010. PGCIL intimated that they

have started tendering process and the order will be placed shortly thereafter so as to

commence work subsequent to the same.

Chairman, WRPC requested WRPC Sectt. to work out the revised contribution amount

as above and intimate the same to constituents in line with the payment schedule as

approved in the 14th WRPC meeting held on 19.8.2010 so that constituent members

accordingly release the first installment of payment by 30th November 2010. (the

constituent wise revised details of first installment of 50 % payment i.e. 50% of the total

estimated cost of Rs 7,57,83,185/- amount are as per the Annexure-25). The amount

may be deposited by the constituents through demand draft in favour of Member

Secretary, WRPC. This amount may be deposited in the existing current account in the

name of Chairman, WRPC named PSS fund of WRPC. Each State transmission utility

may send the combined contribution of the State and shall coordinate amongst its State

Distribution Company and State Generation Company for this purpose as per the

decision. The amount will be released to PGCIL as and when requested as per payment

schedule approved in 14th WRPC meeting.

The Committee requested WRPC members to expedite the respective payments to ensure timely payment to PGCIL as per the above. ITEM No.26: DATE AND VENUE OF NEXT WRPC MEETING Chief Electrical Engineer, Electricity Deptt., Goa agreed to host the next WRP meeting

at Goa during February-2011.

*************

Page 54: Mailing list for 15 - wrpc · Minutes of 15th WRPC meeting held on 12th November 2010 ANNEXURES Annexure Particulars Annexure-1(a) Participants attending TCC meeting held on 11.11.2010

Minutes of 15th WRPC meeting held on 12th November 2010

ANNEXURE

Page 55: Mailing list for 15 - wrpc · Minutes of 15th WRPC meeting held on 12th November 2010 ANNEXURES Annexure Particulars Annexure-1(a) Participants attending TCC meeting held on 11.11.2010

Annexure-1(a)

LIST OF PARTICIPANTS OF TCC MEETING HELD ON 11.11.2010 AT UDAIPUR

A. TECHNICAL COORDINATION COMMITTEE

MEMBERS

1. Shri R. K. Verma, CMD, MPPTCL & Chairman, TCC 2. Shri M. B. Mendhekar, ED(Gen), CSPGCL 3. Shri Vijay Singh, CE(Trans), CSPTCL 4. Shri S. D. Diwan, ED(O&M), CSPDCL 5. Shri K. S. Manothiya, CE(LD), CSPTCL 6. Shri N. H. Suthar, CE (LD), SLDC, GETCO 7. Shri P. H. Rana, MD, GSECL 8. Shri A. P. Bhairve, CE (LD), MPPTCL 9. Shri M. S. Rana, ED(O&M-Gen), MPPGCL 10. Shri U. G. Zalte, Dir (O), MSETCL 11. Shri S. G. Kelkar, CE (LD), MSETCL 12. Shri Nirmal Braganza, CEE, Elect. Deptt., Goa 13. Shri S. C. Pandey, RED(WR), NTPC Ltd. 14. Shri D. K. Valecha, ED, WRTS-I & II, PGCIL 15. Shri M. G. Raoot, ED, POSOCO, WRLDC 16. Shri R. K. Bhatnagar, GM, RGPPL 17. Shri R. B. Mathur, GM(ISP), NHDC Ltd. 18. Shri N. K. Bhandari, Member (Power), NCA, Indore 19. Shri A. N. Shah, CGM(Baroda Operations), GIPCL, Vadodara 20. Shri P. M. Hundiwale, Sr. VP, REL, Mumbai 21. Shri Manjit Singh, Member Secretary, WRPC

B. OTHERS

I. CHHATTISGARH

1. Shri G. S. Kalsi, MD, CSPTCL 2. Shri S. P. Chaturvedi, MD, CSPGCL 3. Shri P. M. Jog, Addl. CE, CSPTCL 4. Shri Sandeep Ghule, EE, CSPTCL

II. GUJARAT

1. Shri S. B. Khyalia, ED (Finance), GUVNL 2. Shri B. B. Mehta, SE (STU), GETCO

III. MADHYA PRADESH

1. Shri P. K. Singh, CE(Comml), MPPKVVCL, Jabalpur 2. Shri N. K. Bhogal, GM(Comml), MPMKVVCL, Bhopal

Page 56: Mailing list for 15 - wrpc · Minutes of 15th WRPC meeting held on 12th November 2010 ANNEXURES Annexure Particulars Annexure-1(a) Participants attending TCC meeting held on 11.11.2010

IV. MAHARASHTRA

1. Shri S. D. Shrouty, ED (STU), MSETCL 2. Shri A. S. Chavan, CE(PP), MSEDCL 3. Shri Satish Chavan, SE, MSETCL 4. Shri N. R. Sonkavday, SE(STU), MSETCL 5. Shri S. M. Telang, SE, MSPGCL

IV. ELECTRICITY DEPTT. GOA 1. Shri B. Nigalye, AEE IV. DAMAN & DIU 1. Shri Yogesh Tripathi, AE IV. DADRA & NAGAR HAVELI 1. Shri B. N. Mehta, SE(Power), DNH V. NTPC LTD.

1. Shri MKV Ramarao, ED(Comml), CC 2. Shri S. S. Sen, GM (OS), WRHQ 3. Shri Anil Nautiyal, DGM(Comml), WRHQ 4. Shri H. Harchandani, DGM(Comml), WRHQ 5. Shri K M K Prusty, DGM(Comml), WRHQ 6. Shri R. N. Pandey, AGM(Comml), WRHQ 7. Shri S. K. Sharma, AGM(Comml), CC 8. Shri B. S. Dhami, DGM(Comml) 9. Shri N. P. Shahar, DGM(Comml), WRHQ 10. Shri P. A. Pandey, DGM(Comml) 11. Shri D. Shrikhande, SM(Comml). WRHQ 12. Shri Manish Jain, Mgr(Comml), WRHQ

VI. NUCLEAR POWER CORPN. OF INDIA LTD. 1. Shri Sandeep Sarwate, Addl CE(Trans)

VII. POWERGRID CORPORATION OF INDIA LTD.

1. Shri Arun Kumar, ED(Comml), CC 2. Shri V. K. Khare, GM, WRTS-I 3. Shri Prashant Sharma, AGM(Comml), CC 4. Shri A. S. Kushwaha, AGM(LD&C), CC 5. Ms. Manju Gupta, DGM, CC 6. Shri Abhinav Verma, CM(Engg), WRTS-II

VIII. POWER SYSTEM OPERATION CORPORATION.

Page 57: Mailing list for 15 - wrpc · Minutes of 15th WRPC meeting held on 12th November 2010 ANNEXURES Annexure Particulars Annexure-1(a) Participants attending TCC meeting held on 11.11.2010

1. Shri G. Anbunesan, DGM, WRLDC 2. Shri S. R. Narsimhan, DGM(OS), WRLDC 3. Smt Sachala Mishra, CM, WRLDC

IX. TATA POWER COMPANY

1. Shri V.R. Shrikhande, DGM IX. RATNAGIRI GAS & POWER PVT. LTD

1. Shri Rohit Chhabra, DGM(Comml) XI. TORRENT POWER LTD.

1. Shri M. H. Kshatriya, GM(Comml) XIII. WESTERN REGIONAL POWER COMMITTEE

1. Shri O. P. Singh, SE (Opn), WRPC 2. Shri S. Satyanarayan, SE(O), WRPC 3. Shri M. M. Dhakate, AS, WRPC

Page 58: Mailing list for 15 - wrpc · Minutes of 15th WRPC meeting held on 12th November 2010 ANNEXURES Annexure Particulars Annexure-1(a) Participants attending TCC meeting held on 11.11.2010

Annexure-1(b)

LIST OF PARTICIPANTS OF 15th WRPC MEETING HELD ON 12.11.2010 AT UDAIPUR

A. WESTERN REGIONAL POWER COMMITTEE

MEMBERS

1. Shri R. K. Verma, CMD, MPPTCL & Chairman, WRPC 2. Shri Subodh K. Singh, MD, CSPDCL 3. Shri G. S. Kalsi, MD, CSPTCL 4. Shri S. P. Chaturvedi, MD, CSPGCL 5. Shri K. S. Manothiya, CE(LD), CSPTCL 6. Shri N. H. Suthar, CE (LD), SLDC, GETCO 7. Shri A. P. Bhairve, CE (LD), MPPTCL 8. Shri S. G. Kelkar, CE (LD), MSETCL 9. Shri Nirmal Braganza, CEE, Elect. Deptt., Goa 10. Shri R. N. Nayak, Dir(O), PGCIL 11. Shri M. G. Raoot, ED, POSOCO, WRLDC 12. Shri N. K. Bhandari, Member (Power), NCA, Indore 13. Shri Manjit Singh, Member Secretary, WRPC

B. OTHERS

I. CHHATTISGARH

1. Shri M. B. Mendhekar, ED(Gen), CSPGCL 2. Shri Vijay Singh, CE(Trans), CSPTCL 3. Shri S. D. Diwan, ED(O&M), CSPDCL 5. Shri P. M. Jog, Addl. CE, CSPTCL 6. Shri Sandeep Ghule, EE, CSPTCL

II. GUJARAT

1. Shri P. H. Rana, MD, GSECL 2. Shri S. B. Khyalia, ED (Finance), GUVNL 3. Shri B. B. Mehta, SE (STU), GETCO

III. MADHYA PRADESH

1. Shri M. S. Rana, ED(O&M-Gen), MPPGCL 2. Shri P. K. Singh, CE(Comml), MPPKVVCL, Jabalpur 3. Shri N. K. Bhogal, GM(Comml), MPMKVVCL, Bhopal 4. Shri Pramod Vaishya, MD, MPTRADCO 5. Shri K. C. Badkul, CGM, MPTRADCO

IV. MAHARASHTRA

Page 59: Mailing list for 15 - wrpc · Minutes of 15th WRPC meeting held on 12th November 2010 ANNEXURES Annexure Particulars Annexure-1(a) Participants attending TCC meeting held on 11.11.2010

1. Shri S. D. Shrouty, ED (STU), MSETCL 2. Shri U. G. Zalte, Dir (O), MSETCL 6. Shri A. S. Chavan, CE(PP), MSEDCL 7. Shri Satish Chavan, SE, MSETCL 8. Shri N. R. Sonkavday, SE(STU), MSETCL 9. Shri S. M. Telang, SE, MSPGCL

IV. ELECTRICITY DEPTT. GOA 1. Shri B. Nigalye, AEE IV. DAMAN & DIU 1. Shri Yogesh Tripathi, AE IV. DADRA & NAGAR HAVELI

1. Shri B. N. Mehta, SE(Power) 2. Shri R. C. Choubal, DE,

V. NTPC LTD.

1. Shri S. C. Pandey, RED(WR), NTPC Ltd. 2. Shri MKV Ramarao, ED(Comml), CC 3. Shri S. S. Sen, GM (OS), WRHQ 4. Shri Anil Nautiyal, DGM(Comml), WRHQ 5. Shri H. Harchandani, DGM(Comml), WRHQ 6. Shri K M K Prusty, DGM(Comml), WRHQ 7. Shri R. N. Pandey, AGM(Comml), WRHQ 8. Shri S. K. Sharma, AGM(Comml), CC 9. Shri B. S. Dhami, DGM(Comml) 10. Shri N. P. Shahar, DGM(Comml), WRHQ 11. Shri P. A. Pandey, DGM(Comml) 12. Shri D. Shrikhande, SM(Comml). WRHQ 13. Shri Manish Jain, Mgr(Comml), WRHQ

VI. NUCLEAR POWER CORPN. OF INDIA LTD.

1. Shri Sandeep Sarwate, Addl CE(Trans)

VII. POWERGRID CORPORATION OF INDIA LTD.

1. Shri D. K. Valecha, ED, WRTS-I & II, PGCIL 7. Shri Arun Kumar, ED(Comml), CC 8. Shri V. K. Khare, GM, WRTS-I 9. Shri Prashant Sharma, AGM(Comml), CC 10. Shri A. S. Kushwaha, AGM(LD&C), CC 11. Shri Kamal Sarkar, AGM, CC 12. Ms. Manju Gupta, DGM, CC 13. Shri Abhinav Verma, CM(Engg), WRTS-II

Page 60: Mailing list for 15 - wrpc · Minutes of 15th WRPC meeting held on 12th November 2010 ANNEXURES Annexure Particulars Annexure-1(a) Participants attending TCC meeting held on 11.11.2010

VIII. POWER SYSTEM OPERATION CORPORATION.

1. Shri G. Anbunesan, DGM, WRLDC 2. Shri S. R. Narsimhan, DGM(OS), WRLDC 3. Smt Sachala Mishra, CM, WRLDC

IX. TATA POWER COMPANY

1. Shri Ashok Sethi, VP 2. Shri V.R. Shrikhande, DGM

IX. RATNAGIRI GAS & POWER PVT. LTD

1. Shri R. K. Bhatnagar, GM 2. Shri Rohit Chhabra, DGM(Comml)

XI. NHDC LTD.

1. Shri R. B. Mathur, GM(ISP), NHDC Ltd. XI. TORRENT POWER LTD.

1. Shri M. H. Kshatriya, GM(Comml) XI. RELIANCE ENERGY LIMITED

1. Shri P. M. Hundiwale, Sr. VP, REL, Mumbai

XI. GUJARAT INDUSTRIES AND POWER CO. LTD. 1. Shri A. N. Shah, CGM(Baroda Operations)

XIII. WESTERN REGIONAL POWER COMMITTEE

1. Shri O. P. Singh, SE (Opn), WRPC 2. Shri S. Satyanarayan, SE(O), WRPC 3. Shri M. M. Dhakate, AS, WRPC

Page 61: Mailing list for 15 - wrpc · Minutes of 15th WRPC meeting held on 12th November 2010 ANNEXURES Annexure Particulars Annexure-1(a) Participants attending TCC meeting held on 11.11.2010
Page 62: Mailing list for 15 - wrpc · Minutes of 15th WRPC meeting held on 12th November 2010 ANNEXURES Annexure Particulars Annexure-1(a) Participants attending TCC meeting held on 11.11.2010
Page 63: Mailing list for 15 - wrpc · Minutes of 15th WRPC meeting held on 12th November 2010 ANNEXURES Annexure Particulars Annexure-1(a) Participants attending TCC meeting held on 11.11.2010
Page 64: Mailing list for 15 - wrpc · Minutes of 15th WRPC meeting held on 12th November 2010 ANNEXURES Annexure Particulars Annexure-1(a) Participants attending TCC meeting held on 11.11.2010

Annexure-2.1 Transmission lines of the transmission licensees of WR for certification: A Intra-State lines proposed for certification: Sr.No. Name of Line Remark GETCO 1 400 KV S/c Dehgam –Soja 2 400 KV S/c Soja – Kansari (Zerda) 3 220 KV D/c Jetpur-Keshod 4 220 KV S/c Keshod-Timbdi 5 220 KV S/c Timbdi-Dhokadva 6 66 KV Dhokadva-Una. M.P.Power Transmission Company Ltd

220 kV Nagda-Ujjain I&II 7 220 kV Indore-Jetpura-Ujjain I&II

Only one of the two Ckt which has least resistance path

8 220 kV Ujjain-Barod I&II 9 220 kV Mehgaon-Malanpur 10 220 kV Malanpur-Gwalior(PG) I&II MSETCL 11 400 kV Chandrapur- Parli 12 400 kV Parli-Sholapur 13 400 kV Sholapur- Karad 14 400 kV Karad- Kholapur B Inter-State/ Inter-Regional line

Inter State Transmission System (ISTS) vide Central Electricity Regulatory Commission (Indian Electricity Grid Code) Regulations, 2010 definition clause 2 “qq)

Sr.No. Name of Line Remark GETCO 1 220 KV D/c Navsari - Nasik Gujarat- Maharashtra Chhattisgarh 2 400 kV Bhilai-Seoni Chhattisgarh – M. P. 3 220 kV D/s Korba(E)-Budipadar Chhattisgarh – Orisa 4 220 kV D/s Kotmikala-Amarkantak Chhattisgarh – M. P. 5 132 kV Dongargarh - Balaghat Chhattisgarh – M. P. M.P.Power Transmission Company Ltd 6 220 KV Barod-Kota MP & Rajasthan 7 220 KV Barod-Modak MP & Rajasthan

Page 65: Mailing list for 15 - wrpc · Minutes of 15th WRPC meeting held on 12th November 2010 ANNEXURES Annexure Particulars Annexure-1(a) Participants attending TCC meeting held on 11.11.2010

8 220 kV Pandhurna-Kamleshwar MP & Maharashtra 9 220 kVAuriya-Malanpur MP&UP 10 220 kV Auriya-Mehgaon MP&UP 11 220 kV Kotmikala-Amarkantak-I&II MP & Chhattisgarh 12 400 kV Bhailai-Seoni MP & Chhattisgarh MSETCL 13 220 kV Amona - Mumbewadi Maharashtra- Goa 14 220 kV Amona - Kolhapur Maharashtra- Goa C Deemed Inter State Transmission System (Deemed ISTS) “such transmission

system which has regulatory approval of the Commission as being used for interstate transmission of power and qualified as ISTS for the purpose of these Regulations unless otherwise specified

GETCO 1 220 KV S/c Ambheti(Vapi-PGCIL)-Vapi(GETCO) 2 220 KV S/c Ambheti (Vapi-PGCIL)-Bhilad (GETCO) 3 220 KV D/c Ambheti (Vapi-PGCIL)-Bhilad (GETCO)

Page 66: Mailing list for 15 - wrpc · Minutes of 15th WRPC meeting held on 12th November 2010 ANNEXURES Annexure Particulars Annexure-1(a) Participants attending TCC meeting held on 11.11.2010

Annexure-2.2 Transmission lines of the non ISTS licensees for the year 2011-12 in WR as approved by WR Power Committee for inclusion in PoC charge method A Intra-State lines certified by WRP Committee: Sr.No. Name of Line Remark GETCO 1 400 KV S/c Dehgam –Soja 2 400 KV S/c Soja – Kansari (Zerda) 3 220 KV D/c Jetpur-Keshod 4 220 KV S/c Keshod-Timbdi 5 220 KV S/c Timbdi-Dhokadva 6 66 KV Dhokadva-Una. M.P.Power Transmission Company Ltd 7 220 kV Nagda-Ujjain ckts I&II 8 220 kV Ujjain-Barod ckts I&II 9 220 kV Mehgaon-Malanpur 10 220 kV Malanpur-Gwalior(PG) ckts I&II MSETCL 11 400 kV Chandrapur- Parli 12 400 kV Parli-Sholapur 13 400 kV Sholapur- Karad 14 400 kV Karad- Kholapur B Inter-State/ Inter-Regional line

Following are Inter State Transmission System (ISTS) [vide Central Electricity Regulatory Commission (Indian Electricity Grid Code) Regulations, 2010 definition clause 2 “qq)]

Sr.No. Name of Line Remark GETCO 1 220 KV D/c Navsari - Nasik Gujarat- Maharashtra Chhattisgarh 2 400 kV Bhilai-Seoni Chhattisgarh – M. P. 3 220 kV D/s Korba(E)-Budipadar Chhattisgarh – Orisa 4 220 kV D/s Kotmikala-Amarkantak Chhattisgarh – M. P. M.P.Power Transmission Company Ltd 5 220 KV Barod-Kota MP & Rajasthan 6 220 KV Barod-Modak MP & Rajasthan

Page 67: Mailing list for 15 - wrpc · Minutes of 15th WRPC meeting held on 12th November 2010 ANNEXURES Annexure Particulars Annexure-1(a) Participants attending TCC meeting held on 11.11.2010

7 220 kV Pandhurna-Kamleshwar MP & Maharashtra 8 220 kVAuriya-Malanpur MP&UP 9 220 kV Auriya-Mehgaon MP&UP 10 220 kV Kotmikala-Amarkantak- ckts I&II MP & Chhattisgarh 11 400 kV Bhilai-Seoni MP & Chhattisgarh MSETCL 12 220 kV Amona - Mumbewadi Maharashtra- Goa 13 220 kV Amona - Kolhapur Maharashtra- Goa C Deemed Inter State Transmission System (Deemed ISTS) “such transmission

system which has regulatory approval of the Commission as being used for interstate transmission of power and qualified as ISTS for the purpose of these Regulations unless otherwise specified

GETCO 1 220 KV S/c Ambheti(Vapi-PGCIL)-Vapi(GETCO) 2 220 KV S/c Ambheti (Vapi-PGCIL)-Bhilad (GETCO) 3 220 KV D/c Ambheti (Vapi-PGCIL)-Bhilad (GETCO)

Page 68: Mailing list for 15 - wrpc · Minutes of 15th WRPC meeting held on 12th November 2010 ANNEXURES Annexure Particulars Annexure-1(a) Participants attending TCC meeting held on 11.11.2010

Annexure-5.1

Gist of discussion held between CSPTCL, WRPC and WRLDC on the sidelines of the TCC meeting on 11th Nov 2010 at Udaipur.

11th Nov 2010

Two substantive issues emerged in these discussions.

i) Sustained under-injection by an embedded intra state entity which has been granted interstate Short Term Open Access (STOA).

ii) Default in payment of Unscheduled Interchange (UI) charges by intra state

entities to the state UI pool account which has occurred in the past. After discussion, consensus reached as under:

i) The second issue of payment default could be taken up by SLDC with the Appropriate Commission in the first instance so that the payments are recovered. However if an intra-state entity continuously defaults for two weekly cycle, the nodal agency could be requested by the SLDC to cancel the STOA approval granted. This would require an amendment Regulations for which the matter needed to be taken up with CERC as per the view of the Committee.

ii) Regarding the issue of sustained under-injection, it was stated by CSPTCL

that this was a one-off problem encountered in the past. It was agreed that such under-injection was not inconsistent with any of the current Regulations due to which practice could continue indefinitely. Further such under-injection by very small generator did not cause any network problem due to which the SLDC could not take any actions on real time basis.

Considering that more such cases might be encountered in future which has a long term potential to threaten grid security and/or distort the electricity market (which is essentially a physical delivery market), it was decided that SLDC Chhattisgarh would monitor such instances of under-injection and document the same. Such intra state entities could be issued a notice by the SLDC asking them to explain this behaviour and correct the same. Failure to do so could entail the SLDC canceling the standing clearance given to such intra state entities for STOA/Power Exchange. This would however require an amendment in the CERC Regulations on Open Access for which the committee felt that the matter needed to be taken up with CERC.

x-------x-------x

Page 69: Mailing list for 15 - wrpc · Minutes of 15th WRPC meeting held on 12th November 2010 ANNEXURES Annexure Particulars Annexure-1(a) Participants attending TCC meeting held on 11.11.2010
Page 70: Mailing list for 15 - wrpc · Minutes of 15th WRPC meeting held on 12th November 2010 ANNEXURES Annexure Particulars Annexure-1(a) Participants attending TCC meeting held on 11.11.2010
Page 71: Mailing list for 15 - wrpc · Minutes of 15th WRPC meeting held on 12th November 2010 ANNEXURES Annexure Particulars Annexure-1(a) Participants attending TCC meeting held on 11.11.2010
Page 72: Mailing list for 15 - wrpc · Minutes of 15th WRPC meeting held on 12th November 2010 ANNEXURES Annexure Particulars Annexure-1(a) Participants attending TCC meeting held on 11.11.2010
Page 73: Mailing list for 15 - wrpc · Minutes of 15th WRPC meeting held on 12th November 2010 ANNEXURES Annexure Particulars Annexure-1(a) Participants attending TCC meeting held on 11.11.2010
Page 74: Mailing list for 15 - wrpc · Minutes of 15th WRPC meeting held on 12th November 2010 ANNEXURES Annexure Particulars Annexure-1(a) Participants attending TCC meeting held on 11.11.2010
Page 75: Mailing list for 15 - wrpc · Minutes of 15th WRPC meeting held on 12th November 2010 ANNEXURES Annexure Particulars Annexure-1(a) Participants attending TCC meeting held on 11.11.2010

Sr.No. PARTICULARS Aug-10 Sep-10 Oct-101 MAXIMUM FREQUENCY (Hz)

1.1 Integrated over an hour 50.27 50.27 50.29

1.2 Instantaneous 50.65 50.79 50.60

2 MINIMUM FREQUENCY (Hz)

2.1 Integrated over an hour 49.18 49.18 49.58

2.2 Instantaneous 48.73 48.76 49.07

3 AVERAGE FREQUENCY (Hz) 49.85 49.85 49.94

4.1 48.6 Hz 0 0 0

4.2 48.8 Hz 16 9 0

4.3 51.0 Hz 0 0 0

5.1 Above 50.2 Hz 4.20 12.28 4.66

5.2 Above 50.3 Hz 0.75 4.55 0.79

5.3 Between 50.2 Hz & 49.5 Hz 87.61 85.89 94.39

5.4 Between 50.2 Hz & 49.2 Hz 94.02 87.36 95.33

5.5 Below 49.2 Hz 1.78 0.36 0.01

5.6 Below 49.5 Hz 8.19 1.83 0.95

5.7 Between 50.3 Hz & 48.5 Hz 99.25 95.45 99.21

Annexure-14.1(a)FREQUENCY PARTICULARS OF WESTERN REGION FOR THE PERIOD

AUGUST 2010 TO OCTOBER 2010

5PERCENTAGE TIME WHEN FREQUENCY WAS

4

NUMBER OF TIMES FREQUENCY TOUCHED

Page 76: Mailing list for 15 - wrpc · Minutes of 15th WRPC meeting held on 12th November 2010 ANNEXURES Annexure Particulars Annexure-1(a) Participants attending TCC meeting held on 11.11.2010

Aug Sep Oct Aug Sep Oct Aug Sep Oct Aug Sep OctAvailability (MW) 2776 2884 2853 8220 9563 10461 4592 5845 6290 13780 14366 15255Unrestricted demand (MW) 2846 2911 2958 8588 10001 11300 7260 6582 7095 16873 17308 18682Deficit(-)/Surplus(+) in MW -70 -27 -105 -368 -438 -839 -2668 -737 -805 -3093 -2942 -3427Deficit(-)/Surplus(+) in % -2.46 -0.93 -3.55 -4.29 -4.38 -7.42 -36.75 -11.20 -11.35 -18.33 -17.00 -18.34

Aug Sep Oct Aug Sep Oct Aug Sep Oct Aug Sep OctAvailability (MW) 2795 2853 2764 9586 9837 9964 4508 6197 6154 13822 14062 14411Unrestricted demand (MW) 2934 2972 2878 10179 10737 10855 5506 6875 6977 19555 17999 18784Deficit(-)/Surplus(+) in MW -139 -119 -114 -593 -900 -891 -998 -678 -823 -5733 -3937 -4373Deficit(-)/Surplus(+) in % -4.74 -4.00 -3.96 -5.83 -8.38 -8.21 -18.13 -9.86 -11.80 -29.32 -21.87 -23.28

Aug Sep Oct Aug Sep Oct Aug Sep Oct Aug Sep OctAvailability (MW) 425 428 438 271 251 328 510 594 523 29207 32181 34339Unrestricted demand (MW) 457 452 469 296 276 353 545 605 535 33989 36023 40179Deficit(-)/Surplus(+) in MW -32 -24 -31 -25 -25 -25 -35 -11 -12 -4782 -3842 -5840Deficit(-)/Surplus(+) in % -7.00 -5.31 -6.61 -8.45 -9.06 -7.08 -6.42 -1.82 -2.24 -14.07 -10.67 -14.53

Aug Sep Oct Aug Sep Oct Aug Sep Oct Aug Sep OctAvailability (MW) 378 397 410 223 227 237 460 461 461 30113 32465 32718Unrestricted demand (MW) 449 443 450 248 252 249 499 509 509 37060 38739 38624Deficit(-)/Surplus(+) in MW -71 -46 -40 -25 -25 -12 -39 -48 -48 -6947 -6274 -5906Deficit(-)/Surplus(+) in % -15.81 -10.38 -8.89 -10.08 -9.92 -4.82 -7.82 -9.43 -9.43 -18.75 -16.20 -15.29

Dadra & Nagar Haveli Western Region

Maharashtra

Goa Daman & Diu Dadra & Nagar Haveli Western Region

Madhya Pradesh

Gujarat Madhya Pradesh MaharashtraDetails

Annexure -14.1(b)(1/2) POWER SUPPLY POSITION IN WR FOR PERIOD FROM AUGUST 2010 TO OCTOBER 2010 (IN MW)

POWER SUPPLY POSITION IN WR FOR PERIOD FROM AUGUST 2010 TO OCTOBER 2010 (IN MW)

POWER SUPPLY POSITION IN WR FOR PERIOD FROM AUGUST 2009 TO OCTOBER 2009 (IN MW)

Details Chhatisgarh Gujarat

POWER SUPPLY POSITION IN WR FOR PERIOD FROM AUGUST 2009 TO OCTOBER 2009 (IN MW)

Chhatisgarh

Details

Goa Daman & DiuDetails

Page 77: Mailing list for 15 - wrpc · Minutes of 15th WRPC meeting held on 12th November 2010 ANNEXURES Annexure Particulars Annexure-1(a) Participants attending TCC meeting held on 11.11.2010

Annexure -14.1(b)(2/2)

Aug Sep Oct Aug Sep Oct Aug Sep Oct Aug Sep OctAvailability (MUs) 1033 1155 998 5013 5181 7005 2652 2817 3375 8587 8541 9394Unrestricted Requirement (MUs) 1044 1160 1003 5130 5294 7494 3155 3032 4102 9953 9684 10987Deficit(-)/Surplus(+) in MUs -11 -6 -6 -117 -113 -489 -502 -215 -727 -1366 -1143 -1593Deficit(-)/Surplus(+) in % -1.03 -0.48 -0.57 -2.29 -2.13 -6.52 -15.92 -7.09 -17.71 -13.72 -11.81 -14.50

Aug Sep Oct Aug Sep Oct Aug Sep Oct Aug Sep OctAvailability (MUs) 1248 1219 897 5958 6322 6194 2629 2861 3204 8737 8511 8905Unrestricted Requirement (MUs) 1297 1249 922 6082 6396 6254 3225 3423 3729 10570 10267 10618Deficit(-)/Surplus(+) : in MUs -49 -30 -25 -124 -74 -60 -596 -562 -525 -1833 -1756 -1714Deficit(-)/Surplus(+) : in % -3.78 -2.42 -2.68 -2.03 -1.16 -0.96 -18.48 -16.42 -14.07 -17.34 -17.10 -16.14

Details Aug Sep Oct Aug Sep Oct Aug Sep Oct Aug Sep Oct

Availability (MUs) 245.24 234.15 260.87 171.17 170.52 171.80 377.95 368.29 358.17 18080 18467 21563Unrestricted Requirement (MUs) 248.14 235.78 263.86 189.77 188.52 190.40 378.48 370.15 359.92 20098 19964 24400Deficit(-)/Surplus(+) : in MUs -2.90 -1.63 -2.99 -18.60 -18.00 -18.60 -0.53 -1.86 -1.75 -2018 -1497 -2837Deficit(-)/Surplus(+) : in % -1.17 -0.69 -1.13 -9.80 -9.55 -9.77 -0.14 -0.50 -0.49 -10.04 -7.50 -11.63

Aug Sep Oct Aug Sep Oct Aug Sep Oct Aug Sep OctAvailability (MUs) 227.24 231.39 245.27 150.85 150.70 148.06 331.02 308.80 314.37 19282 19603 19908Unrestricted demand (MUs) 234.78 235.38 249.47 169.45 168.70 156.99 350.32 323.02 334.14 21929 22062 22263Deficit(-)/Surplus(+) : in MUs -7.54 -3.99 -4.20 -18.60 -18.00 -8.93 -19.30 -14.22 -19.77 -2647 -2458 -2356Deficit(-)/Surplus(+) : in % -3.21 -1.70 -1.68 -10.98 -10.67 -5.69 -5.51 -4.40 -5.92 -12.07 -11.14 -10.58

Dadra & Nagar Haveli Western Region

POWER SUPPLY POSITION IN WR FOR PERIOD FROM AUGUST 2010 TO OCTOBER 2010 (IN MUs)

POWER SUPPLY POSITION IN WR FOR PERIOD FROM AUGUST 2009 TO OCTOBER 2009 (IN MUs)

POWER SUPPLY POSITION IN WR FOR PERIOD FROM AUGUST 2010 TO OCTOBER 2010 (IN MUs)

POWER SUPPLY POSITION IN WR FOR PERIOD FROM AUGUST 2009 TO OCTOBER 2009 (IN MUs)Goa Daman & Diu

Madhya Pradesh Maharashtra

Western RegionGoa Daman & Diu Dadra & Nagar Haveli

Chhatisgarh Gujarat Madhya Pradesh Maharashtra

Details

Details Chhatisgarh Gujarat

Details

Page 78: Mailing list for 15 - wrpc · Minutes of 15th WRPC meeting held on 12th November 2010 ANNEXURES Annexure Particulars Annexure-1(a) Participants attending TCC meeting held on 11.11.2010

400 kV S/SMonth Max Min Max Min Max Min Max Min Max Min Max Min Max Min

Aug-10 434 383 434 400 436 396 438 400 428 411 430 409 421 363

Sep-10 428 390 431 394 435 400 436 400 427 406 429 400 423 396

Oct-10 425 379 430 393 434 400 432 390 427 404 432 405 422 398

400 kV S/SMonth Max Min Max Min Max Min Max Min Max Min Max Min Max Min

Aug-10 426 385 431 383 431 364 434 401 441 404 768 742 786 745

Sep-10 428 372 431 385 431 380 432 398 438 397 774 738 789 731

Oct-10 418 358 431 395 428 391 432 385 431 392 774 735 787 729

Sipat (765 kV) Seoni (765 kV)Jetpur Bina Gwalior Nagda Khandwa

Annexure-14.2

BhilaiIndore Itarsi Karad Dhule

Voltages at the important 400 and 765 kV substations during the period AUGUST 2010 to OCTOBER 2010

Asoj Kasor

Page 79: Mailing list for 15 - wrpc · Minutes of 15th WRPC meeting held on 12th November 2010 ANNEXURES Annexure Particulars Annexure-1(a) Participants attending TCC meeting held on 11.11.2010

No. of Occasions

Max Load Relief at 48.8 Hz

No. of Occasions

Max Load Relief at 48.8 Hz

No. of Occasions Max Load Relief at 48.8 Hz

No. of Occasions

Max Load Relief at 48.8 Hz

1 01-Aug-10 0 0 0 0 0 0 0 02 02-Aug-10 0 0 0 0 0 0 0 03 03-Aug-10 0 0 0 0 0 0 0 04 04-Aug-10 0 0 0 0 0 0 0 05 05-Aug-10 0 0 0 0 0 0 0 06 06-Aug-10 1 32 0 0 0 0 1 797 07-Aug-10 0 0 0 0 0 0 0 08 08-Aug-10 0 0 0 0 0 0 0 09 09-Aug-10 2 23 0 0 4 62.8 3 106

10 10-Aug-10 4 77 2 3 4 79.9 4 9811 11-Aug-10 0 0 0 0 0 0 0 012 12-Aug-10 2 26 0 0 1 38.2 1 10013 13-Aug-10 1 25 0 0 0 0 1 7614 14-Aug-10 0 0 0 0 0 0 0 015 15-Aug-10 1 24 0 0 0 0 0 016 16-Aug-10 0 0 0 0 1 15 1 117 17-Aug-10 0 0 0 0 0 0 0 018 18-Aug-10 0 0 0 0 0 0 0 019 19-Aug-10 0 0 0 0 0 0 0 020 20-Aug-10 1 33 0 0 0 0 1 6521 21-Aug-10 0 0 0 0 0 0 0 022 22-Aug-10 0 0 0 0 0 0 0 023 23-Aug-10 0 0 0 0 0 0 0 024 24-Aug-10 0 0 0 0 0 0 0 025 25-Aug-10 0 0 0 0 0 0 0 026 26-Aug-10 2 40 1 3 2 42 1 12227 27-Aug-10 0 0 0 0 0 0 0 028 28-Aug-10 0 0 0 0 0 0 0 029 29-Aug-10 0 0 0 0 0 0 0 030 30-Aug-10 0 0 0 0 0 0 0 031 31-Aug-10 0 0 0 0 0 0 0 0

220 38 152 550

220 38 152 550

Under Frequency Operation in various Constituent System of Western Region during the month August 2010( Compiled from the data received from the constituents)

Annexure-14.3 (1/3)

Recommonded Load relief at 48.8

Sl. No Date Gujarat Chhattisgarh Madhya Pradesh

Recommonded Load relief at 48.6

Maharashtra

Page 80: Mailing list for 15 - wrpc · Minutes of 15th WRPC meeting held on 12th November 2010 ANNEXURES Annexure Particulars Annexure-1(a) Participants attending TCC meeting held on 11.11.2010

MaharashtraNo. of Occasions

Max Load Relief at 48.8 Hz

No. of Occasions

Max Load Relief at 48.8 Hz

No. of Occasions Max Load Relief at 48.8 Hz

No. of Occasions

Max Load Relief at 48.8 Hz

1 01-Sep-10 0 0 0 0 0 0 0 02 02-Sep-10 0 0 0 0 0 0 0 03 03-Sep-10 0 0 0 0 0 0 0 04 04-Sep-10 0 0 0 0 0 0 0 05 05-Sep-10 0 0 0 0 0 0 0 06 06-Sep-10 1 34.46 0 0 2 29.8 1 1187 07-Sep-10 0 0 0 0 0 0 0 08 08-Sep-10 0 0 0 0 0 0 0 09 09-Sep-10 0 0 0 0 0 0 0 0

10 10-Sep-10 0 0 0 0 0 0 0 011 11-Sep-10 0 0 0 0 0 0 0 012 12-Sep-10 0 0 0 0 0 0 0 013 13-Sep-10 0 0 0 0 0 0 0 014 14-Sep-10 0 0 0 0 0 0 0 015 15-Sep-10 0 0 0 0 0 0 0 016 16-Sep-10 0 0 0 0 0 0 0 017 17-Sep-10 0 0 0 0 0 0 0 018 18-Sep-10 0 0 0 0 0 0 0 019 19-Sep-10 0 0 0 0 0 0 0 020 20-Sep-10 2 28.17 0 0 2 24.6 2 7321 21-Sep-10 0 0 0 0 0 0 0 022 22-Sep-10 0 0 0 0 0 0 0 023 23-Sep-10 0 0 0 0 0 0 0 024 24-Sep-10 0 0 0 0 0 0 0 025 25-Sep-10 0 0 0 0 0 0 0 026 26-Sep-10 0 0 0 0 0 0 0 027 27-Sep-10 0 0 0 0 0 0 0 028 28-Sep-10 0 0 0 0 0 0 0 029 29-Sep-10 0 0 0 0 0 0 0 030 30-Sep-10 1 29.39 2 11.8 2 90.1 1 97

220 38 152 550

220 38 152 550Recommonded Load

relief at 48.6 Hz

Chhattisgarh

Recommonded Load relief at 48.8 Hz

Madhya PradeshSl. No Date Gujarat

Under Frequency Operation in various Constituent System of Western Region during the month September 2010( Compiled from the data received from the constituents)

Annexure-14.3 (2/3)

Page 81: Mailing list for 15 - wrpc · Minutes of 15th WRPC meeting held on 12th November 2010 ANNEXURES Annexure Particulars Annexure-1(a) Participants attending TCC meeting held on 11.11.2010

No. of Occasions

Max Load Relief at 48.8 Hz

No. of Occasions

Max Load Relief at 48.8 Hz

No. of Occasions Max Load Relief at 48.8 Hz

No. of Occasions

Max Load Relief at 48.8 Hz

1 01-Oct-10 0 0 0 0 0 0 0 02 02-Oct-10 0 0 0 0 0 0 0 03 03-Oct-10 0 0 0 0 0 0 0 04 04-Oct-10 0 0 0 0 0 0 0 05 05-Oct-10 0 0 0 0 0 0 0 06 06-Oct-10 0 0 0 0 0 0 0 07 07-Oct-10 0 0 0 0 0 0 0 08 08-Oct-10 0 0 0 0 0 0 0 09 09-Oct-10 0 0 0 0 0 0 0 0

10 10-Oct-10 0 0 0 0 0 0 0 011 11-Oct-10 0 0 0 0 0 0 0 012 12-Oct-10 0 0 0 0 0 0 0 013 13-Oct-10 0 0 0 0 0 0 0 014 14-Oct-10 0 0 0 0 0 0 0 015 15-Oct-10 0 0 0 0 0 0 0 016 16-Oct-10 0 0 0 0 0 0 0 017 17-Oct-10 0 0 0 0 0 0 0 018 18-Oct-10 0 0 0 0 0 0 0 019 19-Oct-10 0 0 0 0 0 0 0 020 20-Oct-10 0 0 0 0 0 0 0 021 21-Oct-10 0 0 0 0 0 0 0 022 22-Oct-10 0 0 0 0 0 0 0 023 23-Oct-10 0 0 0 0 0 0 0 024 24-Oct-10 0 0 0 0 0 0 0 025 25-Oct-10 0 0 0 0 0 0 0 026 26-Oct-10 0 0 0 0 0 0 0 027 27-Oct-10 0 0 0 0 0 0 0 028 28-Oct-10 0 0 0 0 0 0 0 029 29-Oct-10 0 0 0 0 0 0 0 030 30-Oct-10 0 0 0 0 0 0 0 031 31-Oct-10 0 0 0 0 0 0 0 0

0 0 0 0 0 0 0 0

220 38 152 550

220 38 152 550Recommonded Load

relief at 48.6 Hz

Sl. No Date Gujarat

Recommonded Load relief at 48.8 Hz

Chhattisgarh Madhya Pradesh Maharashtra

Under Frequency Operation in various Constituent System of Western Region during the month October 2010( Compiled from the data received from the constituents)

Annexure-14.3 (3/3)

Page 82: Mailing list for 15 - wrpc · Minutes of 15th WRPC meeting held on 12th November 2010 ANNEXURES Annexure Particulars Annexure-1(a) Participants attending TCC meeting held on 11.11.2010

Annexure-15

Details Oct Nov Dec Jan-11 Oct Nov Dec Jan-11 Oct Nov Dec Jan-11 Oct Nov Dec Jan-11

Availability (MW) 2355 2477 2513 2535 9415 9459 9024 9479 6064 6611 6299 6215 13978 14443 14497 14684Unrestricted demand (MW) 2989 2944 3036 2987 10637 10408 10075 9734 7425 8176 8264 8239 19155 19689 19613 19457

Deficit(-)/Surplus(+)(i) MW -634 -467 -524 -452 -1222 -950 -1052 -255 -1362 -1565 -1965 -2024 -5177 -5246 -5117 -4773

( ii) % -21.21 -15.88 -17.25 -15.15 -11.49 -9.12 -10.44 -2.62 -18.34 -19.14 -23.77 -24.57 -27.02 -26.65 -26.09 -24.53

Details Oct Nov Dec Jan-11 Oct Nov Dec Jan-11 Oct Nov Dec Jan-11 Oct Nov Dec Jan-11

Availability (MW) 405 414 358 414 206 208 187 207 482 493 450 492 34604 35804 35027 35725Unrestricted demand (MW) 476 507 504 484 282 304 326 348 576 510 515 560 39942 40903 40706 40201

Deficit(-)/Surplus(+)(i) MW -71 -93 -146 -70 -76 -96 -139 -141 -94 -17 -65 -68 -5338 -5098 -5679 -4476

(ii) % -14.89 -18.35 -29.05 -14.47 -26.99 -31.61 -42.64 -40.38 -16.35 -3.33 -12.60 -12.11 -13.36 -12.46 -13.95 -11.13

Details Oct Nov Dec Jan-11 Oct Nov Dec Jan-11 Oct Nov Dec Jan-11 Oct Nov Dec Jan-11

Availability (MUs) 1537 1583 1672 1676 6792 6537 6583 6396 3608 3941 3917 3921 9280 9021 9458 9678Unrestricted Requirement (MUs) 1640 1546 1651 1650 6802 6547 6593 6406 4089 4823 5108 5062 10574 10370 10813 10852

Deficit(-)/Surplus(+)(i) MUs -103 37 20 26 -10 -10 -10 -10 -481 -882 -1191 -1141 -1295 -1349 -1355 -1174

(ii) % -6.28 2.41 1.24 1.56 -0.15 -0.15 -0.15 -0.16 -11.75 -18.28 -23.31 -22.54 -12.24 -13.00 -12.53 -10.82

Details Oct Nov Dec Jan-11 Oct Nov Dec Jan-11 Oct Nov Dec Jan-11 Oct Nov Dec Jan-11

Availability (MUs) 268 254 235 271 131 123 116 130 336 316 306 335 22765 22584 23118 23244Unrestricted Requirement (MUs) 269 267 280 254 177 186 205 219 377 360 350 346 23928 24098 25000 24790

Deficit(-)/Surplus(+)(i) MUs -1 -13 -45 17 -46 -63 -89 -89 -41 -44 -44 -11 -1163 -1514 -1883 -1546

(ii) % -0.54 -4.92 -16.20 6.60 -26.08 -33.83 -43.24 -40.68 -10.89 -12.17 -12.64 -3.09 -4.86 -6.28 -7.53 -6.24

Western RegionGoa Daman & Diu Dadra & nagar Haveli

ANTICIPATED POWER SCENARIO IN WR FOR PERIOD FROM OCTOBER 2010 TO JANUARY 2011 (IN MUs)

Chhatisgarh Gujarat Madhya Pradesh Maharashtra

Goa Daman & Diu Dadra & nagar Haveli Western Region

ANTICIPATED POWER SCENARIO IN WR FOR PERIOD FROM OCTOBER 2010 TO JANUARY 2011 (IN MW)

MaharashtraChhatisgarh Gujarat Madhya Pradesh

Page 83: Mailing list for 15 - wrpc · Minutes of 15th WRPC meeting held on 12th November 2010 ANNEXURES Annexure Particulars Annexure-1(a) Participants attending TCC meeting held on 11.11.2010
Page 84: Mailing list for 15 - wrpc · Minutes of 15th WRPC meeting held on 12th November 2010 ANNEXURES Annexure Particulars Annexure-1(a) Participants attending TCC meeting held on 11.11.2010

Annexure-18.1 (1/3)

(A) Transmission Schemes associated with State Generating Stations

1 Utran CCPP (2009-10) (370 MW) June 091.1 220kV Utran-Kosamba D/C line No.1 86.00 143 143 143 86 May-10 Line work completed

1.2 220kV Utran-Kosamba D/C line No.2 86.00 144 2 Mar-11 Work under progress. Severe ROW problems

1.3 220kV Kosamba-Mobha line 176.80 275 11 May-11 Work in progress.

2 Sikka Unit 3&4 (2x250 MW) C.O.D.- Dec'12

2.1 220kV D/C Sikka-Moti Paneli line with Moose cond.

156.00 248 - - - Dec-10 Yet to be awarded.

2.2 LILO to Sikka from 220kV Jamnagar-Jetpur ckt. 1 116 178 - - - Mar-11 Yet to be awarded.

2.3 LILO to Sikka from 220kV Jamnagar-Jetpur ckt. 2 120 187 - - - Mar-11 Yet to be awarded.

3 Ukai Extension (2010-11) (500 MW) C.O. D.- Jul'11

3.1 400kV D/C Ukai-Kosamba line 136.2 189 - - - Aug-11 Work in progress.

3.2 400 kV D/C Kosamba-Chorania line (Package I)(From Chorania S/S to AP-54)

222.4 308 30 1 - Jul-11Work in progress.

3.3 400 kV D/C Kosamba-Chorania line (Package II)(From Kosamba S/S to AP-54)

234.6 328 - - - Jul-11Work in progress.

3.4 LILO to Kosamba from 400kV Asoj-Ukai line 64 95 79 64 - Dec-10 Work in progress. Severe ROW problems

3.5 220kV D/C Kosamba-Zagadia line 48.4 78 11 5 - Dec-10 Work in progress. 4 Dhuvaran CCPP-III (360 MW) July'13

4.1 LILO of 220kV Kasor-Vartej S/C at Dhuvaran CCPP-III 60 - - - - - Yet to be awarded.

4.2 LILO of 220kV Karamsad-Vartej S/C at Dhuvaran CCPP-III

60 - - - - - Yet to be awarded.

Remark Stub

setting Tower

erectedStringing complete

Status of Ongoing Transmission Progress in Gujarat (Sept.-10)

Sr. No. Name of Transmission lineLength in Ckt

Km

Total Location

Present Status as on 31.08.2010 Anticipated

completion Target

Page 85: Mailing list for 15 - wrpc · Minutes of 15th WRPC meeting held on 12th November 2010 ANNEXURES Annexure Particulars Annexure-1(a) Participants attending TCC meeting held on 11.11.2010

Annexure-18.1 (2/3)

(B) Transmission Schemes associated with IPP 5 Adani Power, Mundra (Bid-I) (1000 MW)

5.1 220 kV D/C Mundra(Adani)-Varsana line 164.00 256 256 256 164 Jan-10 Line charged on 26.01.105.2 400 kV D/C Mundra(Adani)-Varsana line 168.20 277 272 259 94.00 Nov-10 Work in progress.Severe ROW

problem5.3 400kV D/C Varsana-Hadala line 318 490 490 487 301.74 Oct-10 Work in progress.Severe ROW

problem5.4 220 kV D/C Varsana-Morbi line 214 353 353 353 214 Mar-10 Line Charged on 31.03.105.5 400kV D/C Hadala-Halvad line 161.56 244 43 - - Apr-11 Work in progress

6 Adani Power, Mundra (Bid-II)(2011-12) (1000 MW) Feb'12

6.1 400 kV D/C Mundra-Zerda line No. 1 660.12 921 - - - - Tender re-invited.6.2 400 kV D/C Mundra-Zerda line No. 2 660.12 921 5 - - Oct-11 Agency informed to recommence the

work7 Essar Power, Vadinar (Bid-3) (2011-12)(1000 MW)

Feb'117.1 400 kV D/C Vadinar-Hadala line 226.00 353 329 255 4.58 Dec-10 Work in progress7.2 400 kV D/C Vadinar-Amreli line 360.00 506 - - - - LOI placed

8 GSPC Pipavav Power Co. Ltd.(2010-11) (2x350 MW) Mar'11

8.1 220 kV D/C GPPCL-Dhokadva line 100 167 43 9 - Mar-11 Work in progress.Severe ROW problem

8.2 LILO to GPPCL from 220 kV Savarkundla-Otha Ckt. No. 1 93.00 151 87 79 24.40 Jan-11 Work in progress.Severe ROW problem

8.3 LILO to GPPCL from 220 kV Savarkundla-Otha Ckt. No. 2 82.60 131 23 2 - Jan-11 Work in progress

8.4 220 kV Otha-Sagapara line 95.60 163 - - - - Yet to be awarded.9 GSEG Extension Phase-I (350 MW) Jan'11

9.1 220 kV D/C GSEG-Kosamba line 124.00 197 119 76 - Nov-10 Work in progress9.2 220 kV D/C GSEG-Mota line with AL-59 conductor 111.06 182 18 - - Mar-11 Work in progress10 Bhavnagar Energy Co. Ltd.(BECL)(2011-12) (2x300

MW)10.1 220 kV BECL-Botad line 188.52 292 - - - - Estimate prepared10.2 220 kV BECL-Sagapara line 82.4 135 - - - - Estimate prepared10.3 LILO of 220kV Savarkundla-Vartej at BECL 56.2 97 - - - - Estimate prepared

Present Status as on 31.08.2010Sr. No. Name of Transmission line

Length in Ckt

Km

Total Location

Anticipated completion

TargetRemark Stub

setting Tower

erectedStringing complete

Page 86: Mailing list for 15 - wrpc · Minutes of 15th WRPC meeting held on 12th November 2010 ANNEXURES Annexure Particulars Annexure-1(a) Participants attending TCC meeting held on 11.11.2010

Annexure-18.1 (3/3)

(C) Transmission Schemes associated with PGCIL Substation

1 LILO OF 220 kV to Bhimasar from Morbi -Halvad ckt.no.1 215 331 103 63 - Mar-11 Work in progress.

2 LILO OF 220 kV to Bhimasar from Morbi -Halvad ckt.no.2 210 329 127 69 - Mar-11 Work in progress.

3 220kV D/C Bhat-Pirana line with AL-59 Cond. 28.94 55 25 15 - Dec-10 Work in progress.

(D) Transmission Schemes through IPTC route NIL

(E) Intrastate transmission schemes1 400kV Mundra-Hadala LILO to Halvad 89.4 124 - - - LOI placed on 28.09.10

2 220kV LILO to Kapadvanj from Wanakbori-Ranasan ckt.No. 2

30.31 49 49 48 28 Oct-10 Work in progress.

3 220 kV D/C Nakhatrana-Varsana line with AL-59 Cond. 213.60 334 184 108 - Mar-11 Work in progress.

4 220 kV D/C Tappar - Varsana line 8.00 15 15 15 7.8 Oct-10 Line work completed.5 220kV D/C Bhutiya - Kheralu line 98.63 163 90 47 - Jan-11 Work in progress. 6 220kV LILO to Kangasiyali from Gondal - Rajkot line 28.00 52 34 25 - Mar-11 Work in progress. 7 220 kV LILO to Shapur from Jetpur - Kesod line 3.22 7 3 - - Oct-10 Work in progress. 8 220 kV LILO at Mota S/S from 2nd Ckt.of Ukai(T)-Vav

line9.60 16 16 16 9.60 Line Work Completed.LILO work

pending.9 220 kV D/C Viramgam-Salejada 118.00 183 183 183 118.00 May-10 Viramgam-Bhat commissioned on

29.05.10 10 220 kV M/C LILO to Bhat from Viramgam-Salejada line 71.25 60 60 60 71.25 May-10 Bhat-Salejada commissioned on

01.06.10 11 220 kV LILO at Kukma s/s from one ckt. Of Shivlakha-

Nanikhakhar line. 34.00 54 40 40 17.74 Dec-10 Work in progress.

12 220kV D/C Tharad - Thavar line 97.09 152 27 - - Mar-11 Work in progress. 13 220kV D/C Tharad - Deodar line 77.46 124 28 - - Mar-11 Work in progress. 14 220kV D/C Sankhari - Jangral line 64.00 107 36 - - Mar-11 Work in progress.

Present Status as on 31.08.2010

Anticipated completion

TargetRemark Stub

setting Tower

erectedStringing complete

Sr. No. Name of Transmission lineLength in Ckt

Km

Total Location

Page 87: Mailing list for 15 - wrpc · Minutes of 15th WRPC meeting held on 12th November 2010 ANNEXURES Annexure Particulars Annexure-1(a) Participants attending TCC meeting held on 11.11.2010

Annexure-18.2 (1/2)

A.Transmission Schemes associated with evacuation and system strengthening scheme foown Generating Station.

1 Malwa-TPH-Pithampur 400KV DCDS Line 300 - - - - September/12 Forest proposal submitted

2 Malwa TPH-Chhegaon 400 KV DCDS Line 130 - - - - June/12 Survey Under progress

3 Chhegaon-Julwania 400 KV DCDS Line 230 - - - - September/12 Survey to be taken up

4 Satpura TPH-Ashta 400KV DCDS Line 470 - - - - December/12 Forest proposal under preparation.

5 Malwa TPH-Chhegaon 220KV DCDS Line 130 - - - - June/12 Survey under progress

BTransmission Schemes associated with evacuation and system strengthening scheme foGenerating Station set up by IPP.

1 400KV Bina S/s to BPSCL's Bina TPS 400KV DCDS Line 40 - - - - September/12 Complete work including survey

being carried out by BPSCL

2 Maheshwar-Nimrani 220KV DCDS Line 52.10 90 90 90 52.10 2010-11 Line charged on 12.04.2010

3 Maheshwar-Pithampur 220KV DCDS Line 108.00 189 184 158 52.29 December/10 Work is in progress

C Transmission Schemes associated with PGCIL Substation.

1 Pithampur-Indore (PGCIL) - 400 kV DCDS Line 130 - - - - June/12 Survey Under Progress.

2 LILO of 220 kV Amarkantak-Birsinghpur Line at 400 kV S/S Sukha (PGCIL) 331.80 547 547 547 277.518 December/10 Work is in progress

3 LILO of one circuit of 220KV Bina-Shivpuri at 765KV S/s PGCIL, Bina 1.66 5 2 - - March/11 Work is in progress

4 Indore 765 KV (PGCIL) -Indore-II (Jaitpura) 220KV DCDS Line 20 - - - - June/12 Survey to be taken up

Status of Ongoing Transmission Progress in Madhya Pradesh (Sept.-10)

Sr. No. Name of Transmission line Length inCkt Km

Total Location

Present Status as on 31.08.2010 Anticipated completion

TargetRemark

Stub setting

Tower erected

Stringing completed

Page 88: Mailing list for 15 - wrpc · Minutes of 15th WRPC meeting held on 12th November 2010 ANNEXURES Annexure Particulars Annexure-1(a) Participants attending TCC meeting held on 11.11.2010

Annexure-18.2 (2/2)

DTransmission Schemes and system strengthening schemes set up through IPTC Route.

NIL

NIL

E Intra-State Transmission Schemes

1 Chhindwara-Betul 220KV DCDS Line 266.60 458 458 458 266.6 2010-11 Line charged on 03.06.2010

2 LILO of 220KV Satna-Bansagar line at Kotar S/s 7.8 16 16 16 7.8 September/10 Line charged on 15.08.2010

3 Satna-Chhatarpur 220 kV DCDS Line 156.32 523 522 519 147.86 December/10 Work is in progress

4 LILO of one circuit of 220 kV Bhopal-Bina for Vidisha S/S 42.32 71 66 35 13.512 March/11 Work is in progress

5 Dewas-Ashta 220 kV DCDS Line 144.00 239 239 237 16.44 March/11 Work is in progress

6 LILO of 220KV Khandwa-Nepanagar Line at Chhegaon S/s 35.03 66 66 64 15.00 December/10 Work is in progress

7 Pithampur 400-Pithampur 220KV Interconnector (D/C) 20 - - - - March/12 Survey to be taken up

8 LILO of both CKT. OF Nimrani-Julwania 220KV Line at Julwania 400KV 40 - - - - March/12 Survey to be taken up

9 Ashta 400-Indore-II(Jetpura) 220 kV DCDS line 200 - - - - June/12 Survey to be taken up

10 Ratlam-Daloda 220 KV DCSS Line 60 - - - - March/12 Survey to be taken up

11 LILO of 220 KV DCDS Nagda-Neemuch line at Daloda S/S 16 - - - - March/12 Survey to be taken up

12 LILO of 220 KV Itarsi-Narsinghpur Line at Chichli S/s. 16 - - - - March/12 Survey to be taken up

Sr. No. Name of Transmission lineLength in Ckt

Km

Total Location

Present Status as on 31.08.2010 Anticipated

completion Target

Remark Stub setting

complet

Tower erected

Stringing completed

Page 89: Mailing list for 15 - wrpc · Minutes of 15th WRPC meeting held on 12th November 2010 ANNEXURES Annexure Particulars Annexure-1(a) Participants attending TCC meeting held on 11.11.2010

Annexure-18.3

(A) Transmission Schemes associated with State Generating Stations

1 1x500 MW Korba West TPP Power Evacuation Scheme

1.1 LILO of 400 kV Korba (West)-Bhilai at Raipur DCDS 50.00 69 17 4 - Dec.10 Work under progress.

1.2 400 kV Korba(West)- Khedamara DCDS Ckt. I &II 448.00 648+8G 362 129 - Oct.11 Work under progress.

1.3 220kV DCSS line between Khedamara and 220 kVS/S Bemetara

101.80 157 157 157 101.6 Mar.10 Charged on 18.05.10

2 2x500 MW Marwa TPP Power Evacuation Scheme

2.1 400 DCDS Marwa-Raipur(Raita) 300.00 500 - - - Jun.12 Work under progress.

2.2 LILOof 400kV K(W)-Khedamara line at Marwa (one ckt.)

120.00 - - - - Dec.11 Tender in Process.

2.3 220kV line Marwa to Banari DCDS 28.26 47 - - - Mar.11 Work started shortly.

(B) Transmission Schemes associated with IPP NIL

(C) Transmission Schemes associated with PGCIL Substation NIL

(D) Transmission Schemes through IPTC route NIL

(E) Intrastate transmission schemes

2.1 220 kV Korba -Bishrampur DCSS 306.00 509 347 294 37.67 Dec.-11 Final approval received from AIG(FC) New Delhi

2.2 LILO of 220 kV Bhatapara-Raipur (PGCIL) at Doma 42.94 76 76 76 42.38 Apr.-10 Work completed & Charged on 10.07.10.

2.3 LILO of 200 kV Korba-Siltara at Mopka DCDS 24.28 45 45 43 17.6 Dec.-10 Work under Progress.2.4 220 kV DCDS lines Chhuri-Mopka(Bilaspur) 180.00 270.0 61 15 - May.-11 Work under Progress.

2.5 220 kV line from existing 220 kV S/S Raigarh to Proposed 220 kV S/S Saraipali

200 325 114 9 Work under Progress.

2.6 220 kV DCDS line Bemetara to Mungeli 50 - - - - Apr.-12 T.C. bid opend on 28.08.10

Remark Stub

setting Tower

erectedStringing

completed

Status of Ongoing Transmission Progress in Chhattisgarh (Sept.-10)

Sr. No. Name of Transmission lineLength in Ckt

Km

Total Location

Present Status as on 31.08.2010 Anticipated

completion Target

Page 90: Mailing list for 15 - wrpc · Minutes of 15th WRPC meeting held on 12th November 2010 ANNEXURES Annexure Particulars Annexure-1(a) Participants attending TCC meeting held on 11.11.2010

Annexure-18.4 (1/3)

(A) Transmission Schemes associated with State Generating StationsI. 400 KV Lines

1 400 kv Dabhol-Nagothane IInd ckt. 137.431 342 342 342 137.431 Aug.10 Line charged on 24.08.10

2 400 KV D/C from 400 KV Bhusaval II - existing 400 KV Khadka.

7.373 26 26 26 7.497 June.10 Line charged on 31.03.10 (Ckt-I). Second Ckt. Of line test charged on 31.03.2010.

3 400 KV D/C line from Bhusaval-II to A'bad. (Loc. No. 1 to 270)

95 283 278 271 74.190 Oct.10 Work in progress.

4 400 KV D/C line from New Bhusaval - Aurangabad (Loc. No. 271 to Waluj S/S)

89.6 251 249 245 65.130 Oct.10 Work in progress.

5 400 KV S/C line from 400 KV New Khaperkheda - 400 KV Koradi

4.02 13 12 12 3.475 Mar.11

Major ROW problem at Loc. No. 1. An Appeal in Appellate Tribunal, Delhi is filed by MSETCL regarding Order no. 41/2009 received from MERC.

6 400 KV D/C line from Koradi-TPS to Wardha S/S 120 329 208 47 0 April 11 Work in progress.

7 LILO on 400 KV koradi- Chandrapur S/S line for 400KV khaparkheda II S/S.

2.88 8 8 8 2.882 Mar.10 Line charged on 12.10.09

II. 220KV Lines

1 LILO on 220 KV Tarapur-Borivali line for Boisar II S/S 8 15 15 12 4.350 Dec.10Loc. No. 11(Court case). Forest proposal submitted to CCF Thane on 17.01.09. Work held up due to Court case.

2220 KV Koradi II to Butibori II D/C line on M/C tower at 400 KV Koradi II S/S 53 176 63 10 0 Sept.11 Work in progress.

3220KV Parli TPS-Nanded M/C line( Waghala) 90.3 329 257 160 0 Dec.10

Work in progress. ( M/s. Bajaj )

4 220 kV D/C on D/C from 400 kV new Bhusaval - 220 kV Amalner S/S

182.2 326 303 285 65.459 Mar.11 Work in progress. ( M/s. ATSL )

5220 kV line D/C line on M/C tower from 400/220 kV new Bhusaval -II S/S - existing 400 kV Khadka

20 53 35 30 0.753 Mar.11 Work in progress.( Court case for Loc.No.20 ) ( M/s. ATSL )

6 220 kV Paras-Balapur MIDC M/C -M/C 5.61 30 12 Dec.10 Work in progress. ( M/s. Bajaj )

7 220 kV D/C on D/C by LILO on 220 KV Chandrapur-Warora for 220 KV Wani

46 84 84 84 23.5 JUNE.10 Line Charged on 10.06.10

8 220KV M/C- M/C from 400 New K'Kheda to 220KV Existing K'Kheda

3.5 19 15 15 2 SEPT.10 Work in progress. ( M/s.Shirke )

(B) EVACUATION (LINES & S/S) FOR IPPs

Mauda Transmission System1

400 KV D/C Jaigad - New Koyana line. 109.5 151 151 151 54.750 May 10Ckt.I charged on 06.04.10. Ckt.II charged on 07.07.10. Works by JPTL.

2400 KV D/C Jaigad - Karad line. 222 300 250 139 11.9 Jan. 11

Work in progress. Works by JPTL.

Remark Stub setting completed

Status of Ongoing Transmission Progress in Maharashtra (August-10)

Sr. No. Name of Transmission lineLength in Ckt Km

Total Location

Present Status as on 31.08.2010Anticipated completion

TargetTower

erectedStringing

completed

Page 91: Mailing list for 15 - wrpc · Minutes of 15th WRPC meeting held on 12th November 2010 ANNEXURES Annexure Particulars Annexure-1(a) Participants attending TCC meeting held on 11.11.2010

Annexure-18.4 (2/3)

I. 400KV Lines

1 400KV Chandrapur-II Wardha PGCIL Via Warora D/C 123 335 157 13 - APR.11 Work in progress. ( Quad conductor)( M/s. Cobra-KCL )

2 400KV D/C line from Koradi-II to Wardha S/S(PG) 120 329 214 48 - APR.11 Work in progress.( M/s. Cobra-KCL )

II. 220KV Lines

1 220KV D/c on M/C tower from 400KV PGCIL Talegaon to 220KV Urse 20.54 40 40 40 10.9 MAR.11

2 LILO on Apta-Kalwa & Kandalgaon-Kharghar for Navi Mumbai S/S 8 26 - - - Sep.11 Work awarded to M/S KPTL

4 220kV D/C line from Pune(PG) to Talegaon 8 12 - - - MAR.11

5 220kV D/C line from Chincholi(PG) to South Solapur 10.64 18 - - - MAR.11 Check survey partially completed.

6 220kV D/C line from Wardha(PG) to Ghatodi 322 510 - - - MAR.12

7 LILO on 220kV Bhugaon-Pusad SC at Wardha(PG) 15 - - - - Sep.11

(D) LINES & S/S LINKING WITH PROJECTS- IPTC Routes NIL

(E) SYSTEM STRENGTHENING LINES (INTRA STATE)

I. 220KV Lines

1 LILO of 220 kV Nashik -Kalwa ckt 3&4 ( Padghe - Kalwa) for Airoli 3 9 - - - March.10 Line is charged on 21.03.10 (Ckt -3) & S/s

chared on 22.03.10

2 220KV D/C Nagothane Wadkhal. 30 93 56 44 -Severe ROW problem. The contract is being closed. Estimate is under preparation for balance work for fresh tenderisation.

3 LILO on 220 KV Padghe - Kalwa for Temghar S/S. 1.5 8 7 6 1

Court case at Location No.3 &4 .Work in progress. Work obstructed by local land owners.( M/s. IVRCL )

4 LILO on 220 KV Mulund - Borivali by U/G cable for BhandupGIS S/S. 2 2 - - - JAN.11 U/G cable is supplied by the agency. Work

for cable trench in progress. (M/s EPIL)

5 220 KV D/C from Phursungi - 400 KV Jejuri S/S. 62 102 75 65 - DEC.10 Work in progress. ( M/s. Bajaj )

Present Status as on 31.08.2010 Anticipated completion

TargetRemark Stub setting

completedSr. No. Name of Transmission line

Length in Ckt

Km

Total Location Tower

erectedStringing

completed

(C.)- EVACUATION (LINES) LINKED WITH PGCIL

Page 92: Mailing list for 15 - wrpc · Minutes of 15th WRPC meeting held on 12th November 2010 ANNEXURES Annexure Particulars Annexure-1(a) Participants attending TCC meeting held on 11.11.2010

Annexure-18.4 (3/3)

I. 220KV Lines

6 shifting of 220KV Telco-Bhosari interconnecting bay at chinchwad S/s. 0.5 6 6 5 0.133 Sep.11

The order is short closureat Dn office & estimate for balance work is sanctioned by C.A. This work can be done after completion of Chinchwad phase-II S/S. (M/s Power Engg., Navi Mumbai)

7 220KV D/C line on M/c tower LILO on 220KV Bhosari-Chinchwad D/C on M/C. for 400KV Chakan S/s. 18 34 9 Dec.10

New design for 4.5 m narrow base Tower is being given as MIDC has given 5 mtr. Corridor. ( M/s.Shirke )

8 220 kV D/C on D/C LILO on 2nd ckt Kolhapur Phonda line 220 kV Halkarni 20 33 33 33 9.465 JUNE.10 Line ready. Work completed

9 220 KV D/C on D/C by LILO on Pusad- Parbhani line for Hingoli. 44 75 75 75 20.209 Oct.10 Work in progress.

( M/s. Jyoti )

10 220 kV Chitegaon - Shendra D/C Line. 86.2 154 69 54 14.17 DEC.10 Partly line charged on 14.06.10 for Shendra S/S. Work in Progress.

11 Reorientation of 220 KV Padegaon I & II, Babhaleshwar I&II, Chetegaon I&II and Jalna I&II at Aurangabad 8.84 14 14 12 7.5 Oct.10 Work in progress.

( M/s. Aster )

12 220 kV D/C line Jeur - Paranda 60 115 Alternate line LILO on 220kv Usmanabad -Barshi for paranda is given to M/s. Kalpataru

13 220 kV D/C Beed- Patoda line 86.338 151 126 104 Feb.11 Work in progress. ( M/s. Bajaj )

14 220KV D/C-D/C Jalna - Chikli 150 248 157 119 0.9 Feb.11 Work in progress. ( M/s. Bajaj )

15220 KV Line from PGCIL to 220 KV Wada S/S Section - 1 to 80

22 90 85 82 15.73 Dec 10

16220 KV Line from PGCIL to 220 KV Wada S/S , Section - 81 to Wada

31 121 88 84 12.19 Dec 10

Stub setting completed

Tower erected

Stringing completed

Work held up due to ROW problems. ROW problems & 3 Nos. Court Cases. Forest proposal yet to be approved.

Sr. No. Name of Transmission lineLength in Ckt Km

Total Location

Present Status as on 31.08.2010 Anticipated completion

TargetRemark

Page 93: Mailing list for 15 - wrpc · Minutes of 15th WRPC meeting held on 12th November 2010 ANNEXURES Annexure Particulars Annexure-1(a) Participants attending TCC meeting held on 11.11.2010

Annexure-18.5 (1/2)PROGRESS OF TRANSMISSION LINES UNDER CONSTRUCTION BY PGCIL (July 10)

Sr.No.

Name of transmission line Length in Ckt. Km

Total Locations

Anticipated Completion

REMARKS

Stub Setting completed

Tower erected

Stringing completed

Target

(Nos.) (Nos) (Ckm)

765 kV & 400 kV Lines 1 Western Region Stregthening Scheme-II1.1 SET-A: For absorbing import in eastern&central part of WR1.1.1 765 kV 2nd S/C Seoni(PG)-Wardha(PG) line (initially to be operated at

400kV)261 715 470 226 20 Mar-11

1.1.2 400 kV D/C Wardha (PG)-Parli (PG)(Quad.) 674 896 865 801 481 Mar-11 Works almost stand still due to heavy rains.1.1.3 400 kV D/C Raipur(PG)-Wardha(PG) line 741 989 953 884 475 Dec-10 Work affected due to ROW problem in line.

Forest strech of 107 hectare clearence awaited.

1.1.4 400 kV D/C Bhadravati (PG)-Parli(PG) line 776 1032 1001 782 334 Dec-10 Work affected due to ROW problem in line & heavy rains. Forest strech of 5-8 hectare. 1st stage forest clearence received.

1.1.5 400 kV D/C Parli(MSEB)-Parli(PG) line 14 - - - - Nov-10 Engg. & survey under progress.1.2 SET-B: For Regional strengthening in Southern Maharashtra

Implemented through IPTC route by Western Region Transmission (Mah) Pvt.Ltd. Progress indicated saperately

1.3 SET-C: For Regional strengthening in Gujarat Implemented through IPTC route by Western Region Transmission (Guj) Pvt.Ltd. Progress indicated saperately

1.4 SET-D: For Regional strengthening in Northern Madhaya Pradesh

1.4.1 400 kV D/C Korba(NTPC)-Birsighpur(MPGENCO) line 453 644 531 521 190 Dec-10 Forest strech of 157 hectare.1st stage forest clearence delayed.

1.4.2 400 kV D/C Birsighpur(MPGENCO)-Damoh(PG) line 454 637 637 635 448 Oct-10 works affected due to heavy rains.1.4.3 400 kV D/C Damoh(PG)-Bhopal(MPSEB) 432 577 577 577 432 Mar-10 Line Test charged & commissioned1.5 Trans. Sy. Associated with Gandhar-II (GBPP) *33 months from investment approval or from

date of tying up of FSA by NTPC whichever is later.

2 Western Region Stregthening Scheme-V2.1 400 kV Vapi(PG)-Navi Mumbai D/C line 258 385 104 45 - Oct-11 Severe Row problem being faced in

Maharashtra & DNH on allmost all locations. Compltion likely to be delayed.

2.2 220 kV Vapi-Khadoli (UT of DNH) D/C line 56 103 103 103 56 Jul-10 Erection completed & testing under progress.

2.3 LILO of Lonikhand(MSEB)-Kalwa(MSEB) 400 kV S/C line at Navi Mumbai

10 30 1 - - Mar-11 Engg. & survey in progress. Severe Row problem in Maharashtra on allmost all locations.

PRESENT STATUS

Page 94: Mailing list for 15 - wrpc · Minutes of 15th WRPC meeting held on 12th November 2010 ANNEXURES Annexure Particulars Annexure-1(a) Participants attending TCC meeting held on 11.11.2010

Annexure-18.5 (2/2)Sr.No.

Name of transmission line Length in Ckt. Km

Total Locations

(Nos)

Anticipated Completion

REMARKS

Stub Setting completed

Tower erected

Stringing completed

Target

(Nos.) (Nos) (Ckm)3 Western Region Stregthening Scheme-VI3.1 400 kV D/C Dehgam - Pirana line 92 139 124 120 72.00 Nov-104 Western Region Stregthening Scheme-IX4.1 LILO of 400 kV D/C Bina-Nagda line at Sujalpur 45 60 38 18 Jan-11 Tower erection commenced from Jun'105 Western Region Stregthening Scheme-X5.1 LILO of 765 kV S/C Sipat-Seoni line at WR Pooling station near Sipat 14 Feb. 12 Tendering under progress.

6 Western Region Stregthening Scheme-XI6.1 LILO of 765 kV S/C 2nd Sipat-Seoni line at WR Pooling station near

Sipat at Bilaspur (Pooling Stn.)24 Feb. 12 Tendering under progress.

7 Transmission System associated with Korba-III7.1 400 kV D/C Korba STPS-Raipur line 424 597 350 190 Jun. 11 Efforts being made to complete the line earlier.

8 Mauda Transmission System 8.1 400kV D/C Mauda STPS - Wardha line (Quad) 250 Oct. 12 Award placed in Mar'108.2 400kV D/C Mauda STPS - Khaperkheda line (Quad) 120 Oct. 12 Award placed in Mar'109 Transmission System Associated with Mundra UMPP9.1 Part-A Transmission System of Mundra UMPP9.1.1 400 kV D/C Mundra-Limbdi line (Tripal snowbard) 626 838 195 75 Dec. 119.1.2 400 kV D/C Mundra-Bachchau- Ranchodpur line (Tripal snowbard) 764 1028 698 422 91.00 Dec. 119.1.3 400 kV D/C Mundra-Bachchau- Jetpur line (Tripal snowbard) 666 900 278 116 Mar. 129.2 Part-B Regional System Strengthening in WR for Mundra UMPP9.2.1 400 kV D/C Gandhar-Navsari line 212 299 183 134 Dec. 119.2.2 400 kV D/C Navsari- Mumbai line 408 1020 67 32 Jun. 12 01 out of 02 pkgs awarded. Line is now

proposed to be terminated at Boiser S/stn in place of Mumbai new loc.

9.2.3 400 kV D/C Wardha- Aurangabad line 800 Oct. 12 Tendering under progress. 1200 kV towers.9.2.4 400 kV D/C Aurangabad - Aurangabad (MSETCL)line 60 Oct. 12 Tendering under progress.9.2.5 LILO of both Ckt of Kawas-Navsari 220 kV D/c at Navsari 68 130 1 Oct. 12

10 Transmission System Associated with Sasan UMPP10.1 Part-A Transmission System of Sasan UMPP10.1.1 765 kV Sasan-Satna line-I 257 694 435 219 40.00 Dec. 1210.1.2 765 kV Sasan-Satna line-II 260 705 130 28 Dec. 1210.1.3 765 kV Satna-Bina line-I 279 758 568 302 Dec. 1210.1.4 765 kV Satna-Bina line-II 276 738 402 201 42.00 Dec. 1210.1.5 765 kV Sasaram-Fatehpur line-II 356 950 1 Dec. 12 Foundation commenced from July'1010.1.6 765 kV Fatehpur-Agra line 303 889 2 Dec. 12 Foundation commenced from July'1010.1.7 400 kV Bina-Bina (MPPTCL) line 10 Dec. 12 Engg. in progress.10.1.8 LILO of both Ckt Vindhyachal-Jablapur 400 kV D/c at Sasan 16 Dec. 12 Engg. in progress.10.2 Part-B Regional System Strengthening in WR for Sasan UMPP10.2.1 765 kV Bina-Indore line 320 850 457 176 44.00 Dec. 1210.2.2 400 kV Indore-Indore(MPPTCL) (quad) line 120 154 87 Dec. 1211 Inter-regional lines11.1 East-West Transmission corridor strengthening scheme11.1.1 400 kV D/C Ranchi - Rourkela 290 401 387 382 256 Dec-10 ROW problem being addressed with help from

State Gov. Ist stage forest clearance received in Mar'10.Final clearance awaited. Critical.

11.1.2 400 kV D/C Rourkela - Raigarh 420 589 512 494 180 Dec-10 1st stage forest clearence accorded in Oct.09(100 kms. Stretch involved). Pending final clearence MOEF has given permission to work in the forest stretch. All efforts shall be made to complete the line at the earliest. Critical.

11.1.3 400 kV D/C Raigarh - Raipur 440 584 584 584 440 Sep-10 Line charged on 30.09.10

PRESENT STATUS

Page 95: Mailing list for 15 - wrpc · Minutes of 15th WRPC meeting held on 12th November 2010 ANNEXURES Annexure Particulars Annexure-1(a) Participants attending TCC meeting held on 11.11.2010

PROGRESS OF TRANSMISSION LINES UNDER CONSTRUCTION TROUGH IPTC ROUTE (Sept. 2010)

Sr.No.

Name of transmission line Length in Ckt. Km

Total Locations

(Nos)

Anticipated Completion

REMARKS

Stub Setting completed

Tower erected

Stringing completed

Target

(Nos.) (Nos) (Ckm)WRSSS-II (Set-B)

2.2 SET-B: For Regional strengthening in southern Maharashtra implemented through IPTC route by Western Region Transmission (Mah) Pvt.Ltd.

2.2.1 400 kV D/C Parli(PG)-Pune 646 886 431 31 - Sep-11 For Forest NOC all cases submitted. NOC obtained. For PTCC joint inspection completed.

2.2.2 400 kV D/C Pune(PG)-Aurangabad(MSEB) 472 623 291 7 - Apr-11 All cases submitted clearance received. GIB new alignment from 91/5 to 104/0 is under progress.For PTCC joint inspection completed.

2.2.3 400 kV D/C Parli(PG)-Solapur 272 355 101 8 - May-11 Forest clearence received.Power line Xing 3/7 proposals sent to CE, MSETCL.

2.2.4 400 kV D/C Solapur(PG)-Kolhapur(MSEB) 438 575 197 23 - Sep-11 For forest clearence all cases submitted & clearence received.For PTCC final report sent to Director PTCC. 3/4 proposals sent to CE(MSETCL), KARAD on 30.07.10

2.2.5 LILO of Lonikhand(MSEB)-Kalwa(MSEB)400 kV D/C at Pune(PG) 2.4 8 4 - - Dec-10 Forest clearence not required. PTCC clearance received.

2.2.6 LILO of Solapur(MSEB)-Karad(MSEB)400 kV D/C at Pandharpur/Solapur(PG)

232 298 298 294 79 Sep-10 Forest clearence submitted and received. For PTCC clearance received on 07.07.10.

WRSSS-II (Set-C)2.3 SET-C: For Regional strengthening in Gujarat implemented through

IPTC route by Western Region Transmission (Guj) Pvt.Ltd.

2.3.1 400 kV D/C Rajgarh(PG)-Karamsad(GEB) 468 652 450 144 - May-11 Forest proposal for Gujarat portion submitted to DFO. Tree enumeration permission granted for Gujarat portion.Forest proposal submitted for Jhabua range of MP portion. Dhar range inspection completed. Proposal under submission.

2.3.2 400 kV D/C Limbdi(Chorania)(GEB)-Ranchodpura(Vadavi)(GEB) 206 265 264 182 32 Dec-10 Forest clearence not required. For PTCC proposal submitted. Processed from Mumbai. File sent to Delhi.

2.3.3 400 kV D/C Ranchodpura(Vadavi)(GEB)-Zerda(Kansari)(GEB) 280 373 357 146 13 Dec-10 Forest clearence not required. For PTCC proposal submitted. Processed from Mumbai. File sent to Delhi.

PRESENT STATUS

Annexure-18.6

Page 96: Mailing list for 15 - wrpc · Minutes of 15th WRPC meeting held on 12th November 2010 ANNEXURES Annexure Particulars Annexure-1(a) Participants attending TCC meeting held on 11.11.2010

Annexure-19 (1/2)GENERATION SCHEMES UNDER CONSTRUCTION DURING 11th PLAN IN WESTERN REGION

Sr. No. Name of the Power Projects Unit No. Capacity (MW)

Schedule Date of Commissioning

A GUJARATGeneration Schemes included in 11th Plan

1 Kutch Lignite TPS 4 75 Commissioned on 01.10.20092 Sugen CCPP (Torrent Power Gen. Ltd.) Block -1 382.5 Commissioned on 20.11.2008

Block-2 382.5 commissioned on 07.05.09Block-3 382.5 commissioned on 08.06.09

3 Surat Lignite expansion- GIPCL 3 125 commissioned on 12.04.104 125 commissioned on 23.04.10

4 Utran GPP GT+ST 374 Commissioned on 10.10.20095 Sikka TPP Extn. 3 250 Jan. 2010

4 250 May. 20106 Ukkai TPS Extn. 6 490 Feb. 20117 Pipavav CCPP- GPCL & GSPC joint venture Block-1 350 Sep. 2010

Block-2 350 Mar. 20118 Mundra TPP Ph-1 (Adani Power Ltd.) 1 330 Commissioned on 04.08.2009

2 330 Commissioned on 17.03.109 Mundra TPP Ph-2 (Adani Power Ltd.) 3 330 Commissioned on 02.08.10

4 330 Oct. 201010 Mundra Ultra Mega TPP (Tata Power Ltd.) 1 800 Sep. 2011

2 800 Mar. 201211 Hazira CCPP Expansion GSEG GT+ST 350 Sep. 2010

Other Projects1 Gujarat Lignite-NLC & GPCL joint venture Stage-I 1500 2011-12

Stage-II 500 2012-132 Dhuvaran CCPP GSECL Stage-III 360 Mar. 20103 Pipavav TPP- Torrent Power 1000 2011-124 Bhavnagar Lignite TPP-joint venture 500 Apr. 20115 Mundra STPP (Adani Power Ltd.) 1 660 Jan. 2011

2 660 June. 2011

B MADHYA PRADESHGeneration Schemes included in 11th Plan

1 Amarkantak TPS 5 210 Commissioned on 15.06.20082 500 Apr. 2011

2 Satpura TPS Extn. 10 250 Nov. 201011 250 Mar.2011

Other Projects1 Maheshwar HEP - 400 2010-112 Malwa TPP 1 500 Dec. 2010

Page 97: Mailing list for 15 - wrpc · Minutes of 15th WRPC meeting held on 12th November 2010 ANNEXURES Annexure Particulars Annexure-1(a) Participants attending TCC meeting held on 11.11.2010

Sr. No. Name of the Power Projects Unit No. Capacity (MW)

Schedule Date of Commissioning

C CHHATTISGARHGeneration Schemes included in 11th Plan

1 Jindal PL 1 250 Commissioned on 08.12.072 250 Commissioned on 16.04.083 250 Commissioned on 15.06.084 250 Commissioned on 17.06.08

2 LANCO Amarkantak PL 1 300 Commissioned on 04.06.092 300 Commissioned on 25.03.10

3 Marwa TPP 1 500 Sept. 20122 500 Nov. 2012

4 Korba West-III TPP 1 500 Jun. 2012Other Projects

1 Bhaiyathan TPP Phase-I 1 500 Dec. 20122 500 Aug. 2013

2 IFFCO 1 660 Aug. 2012660 Dec. 2012

D MAHARASHTRAGeneration Schemes included in 11th Plan

1 New Parli TPS Extn. 2 250 Commissioned on 10.02.20102 Paras TPS Extn. 2 250 Commissioned on 27.03.103 Khaperkheda TPP Extn. 1 500 Mar. 20104 Bhusawal Extn. TPP 1 500 May. 2010

2 500 Sep. 20105 Trombay TPS Extn. (Tata Power Co.) 8 250 Commissioned on 14.01.20096 Ghatghar HPS (Hydro) 1 125 Commissioned on 13.05.08

2 125 Commissioned on 01.07.087 JSW Ratnagiri TPP (JSW Energy (Ratnagiri) Ltd.) 1 300 Commissioned on 24.08.10

2 300 Sep. 20103 300 Dec. 20104 300 Mar. 2011

Other Projects1 Koradi TPS Extn. 1 800 Oct. 20122 Dhopawe TPP 1 800 Nov. 2011

2 800 May 20123 Uran CCPP Block-1 700 Feb. 2010

Block-2 340 May. 20104 Koradi TPS Extn. (Replacemet of 4 x 120) 1 800 Apr 20125 Parli TPS (Replacement of 2x30) 1 250 May. 20106 Paras TPS (Replacement of 1x62.5) 1 250 May. 20107 Bhusawal TPS (Replacement of 1x62.5) 1 250 May. 20108 Chandrapur TPS Extn. 1 500 Dec. 2011

2 500 May. 20129 Wardha Warora TPP(M/S Wardha Power Co. Ltd.) 1 135 Commissioned on 05.06.10

10 Wardha Warora TPP(M/S Wardha Power Co. Ltd.) 2 135 Commissioned on 10.10.10

E CENTRAL SECTOR - NTPCGeneration Schemes included in 11th Plan

1 Sipat-II TPP 5 500 Commissioned on 27.12.08

2 Sipat-I TPP 1 660 Nov. 20102 660 May. 20113 660 Nov. 2011

3 Bhilai TPP (Joint venture with SAIL) 1 250 Commissioned on 22.04.09

2 250 Commissioned on 12.07.09

4 Korba STPS-III 7 500 Oct. 20105 Mauda TPP 1 500 2011-12

2 500 2012-13

Annexure-19 (2/2)

Page 98: Mailing list for 15 - wrpc · Minutes of 15th WRPC meeting held on 12th November 2010 ANNEXURES Annexure Particulars Annexure-1(a) Participants attending TCC meeting held on 11.11.2010
Page 99: Mailing list for 15 - wrpc · Minutes of 15th WRPC meeting held on 12th November 2010 ANNEXURES Annexure Particulars Annexure-1(a) Participants attending TCC meeting held on 11.11.2010
Page 100: Mailing list for 15 - wrpc · Minutes of 15th WRPC meeting held on 12th November 2010 ANNEXURES Annexure Particulars Annexure-1(a) Participants attending TCC meeting held on 11.11.2010
Page 101: Mailing list for 15 - wrpc · Minutes of 15th WRPC meeting held on 12th November 2010 ANNEXURES Annexure Particulars Annexure-1(a) Participants attending TCC meeting held on 11.11.2010

Annexure-25

75,783,185 37,891,593

1 CSPTCL2 CSPGCL3 CSPDCL4 GSECL5 GETCO6 MGVCL (DISCOM)7 MPPTCL8 MPPGCL9 MP MADHYA KVVCL10 MSETCL11 MSPGCL12 MSEDCL (DISCOM)13 GOA ELECY.DEPTT. 2,368,225 14 UT OF DD 2,368,225 15 UT OF DNH 2,368,225 16 NTPC 2,368,225 17 NPCIL 2,368,225 18 CTU(POWERGRID) 2,368,225 19 TPC 2,368,225 20 RGPPL 2,368,225 21 TORRENT POWER 2,368,225 22 GIPCL 2,368,225 23 RETL(TRADER) 2,368,225 24 REL 2,368,225

Total 37,891,600

SHARING OF EXPENDITURE FOR RENOVATION OF WRPC OFFICE BUILDING

Expenditure

SL.NO. ORGANISATION

2,368,225

2,368,225

2,368,225

2,368,225


Recommended