Date post: | 30-May-2018 |
Category: |
Documents |
Upload: | madhusudan-partani |
View: | 222 times |
Download: | 0 times |
of 20
8/9/2019 Scheduling 18A
1/20
PROJECTSCHEDULING
ATTANEJA
ENTERPRISE
Presented by:GROUP 10Anmol Sahni 91009
Chinmay Jagga 91013Madhusudan 91029Neha Arya 91036Radhika Gupta 91041Shivi Aggarwal 91052
Presented to:
Prof Neeta Gupta
8/9/2019 Scheduling 18A
2/20
FLOWOF T TION
1. INT ODUCTION
2. Process nalysis
3. Why cheduling isrequired?4. Scheduling equirements
5. Scheduling pproach
6. Scheduling & Control functions
7. Gantt Chart
8. Performancemeasurecalculations
9. Suggestions
8/9/2019 Scheduling 18A
3/20
Started in 1990
Rubber Products manufacturer
Produces on Made-to-order basis
Major Customers include:
Maruti Udyog Ltd.
Hero Honda Ltd.
Remsons Industries
Deepak Auto Ltd.
Suprajit Engg Ltd.
T NEJ ENTERPRISE
8/9/2019 Scheduling 18A
4/20
MANUFACTURINGPROCESS
8/9/2019 Scheduling 18A
5/20
RAW MATERIAL
STORAGE
KNEADING BY
KNEADER
MACHINE
BINS FOR STORAGE
ROLLED BY
2 ROLL MIXER
SHEETS CUT TO
SMALLER PIECES
LAID ON TABLE FOR
COOLING
MOULDING BY
HYDRAULIC PRESS
PRODUCT COLLECTED
IN BINS
INSPECTED VISUAL
AND QUALITY CHECKED
IS THE SAMPLE AS PER
REQMNT ?
STORED IN BINS
SECOND ROUND OF
INSPECTION
IS THE PIECE MEETING
REQMNTS?
DISPOSE
DISPOSE
NO
NO
YES
YES
COLLECTEDPACKAGED
PROCESSFLOWDIAGRAM
8/9/2019 Scheduling 18A
6/20
STAGE1:PROCURINGRAWMATERIAL
Mixing
CHEMICALS
RUBBER
Carbon 550
Magnesium Oxide
Poly Vinyl Chloride
Steric Carbyl Acid
Zinc OxideSulphur
ZDBC
Neoprene
Nitrile
Synthetic rubber
Silicon rubber
JSR
KSR
8/9/2019 Scheduling 18A
7/20
STAGE2:MIXINGOFRAWMATERIAL
A KNEADER MACHINE IS USEDTO MIX THE RAW MATERIALS
The temperature and time of thekneader machine is set according
to the grade of rubber to beproduced.
For example, EPDM requires 35-65 C for 7 minutes.
The mixture is then temporarilystored in the baskets until furtherprocessing is done.
8/9/2019 Scheduling 18A
8/20
STAGE3: TRANSFORMATION TO
SHEETS
ADouble RollingMachine is used for
this purpose. It usescold rolling to flattenthe rubber.
These sheets are thencooled onlong table.
8/9/2019 Scheduling 18A
9/20
STAGE4:MOULDING
HANDMOULDING
MACHINEMOULDING
8/9/2019 Scheduling 18A
10/20
STAGE5:FINISHING, INSPECTIONAND
PACKAGING
FINISHING: 2 ROUNDS
Once done at the factory. Then the products are sent to an
outsourced location where second round of inspection is carried
out.
INSPECTION
The various products formed are subjected to quality
improvement tests. The standards of qualifying are set by the
customer.
PACKAGINGPackaging is not done at the factory. The place of
packaging is around 3 kilometers from the factory. A considerable
amount is paid as rent per day for this place. Packets of 400, 500
and 1000 pieces are made.
8/9/2019 Scheduling 18A
11/20
Scheduling Approach:Low Volume Job Shop
8/9/2019 Scheduling 18A
12/20
Why scheduling isrequired?
yIncreased throughputyDecreased turnaround time
yUser deadlines met
yUsers made responsible for providing input on
scheduleyImproved communications with users
yAvoidance of overloading and underuse of
resources
y
Job delays more readily apparentyDocumentation of scheduling deviations and their
causes
yReduced confusion within the facility
yPredictability of the effects of an increased workload
8/9/2019 Scheduling 18A
13/20
Scheduling Requirements
yCurrent state of the shop
yResource and equipment status
y
Future ordersyDue dates
yQuantity
yShop Layout
yOutside services, r aw materialavailability
yHistorical equipment performance
8/9/2019 Scheduling 18A
14/20
Scheduling AndControl Functions
1.Allocate orders, equipment, and personnel to work
centers or other specified locations.
2.Determine the sequence of order performance (that
is, establish job priorities).
3.Initiate performance of the scheduled work.
4.Shop-floor control (or production activity control):a.Review the status and control the progress of orders as
they are being worked on.
b.Expedite late and critical orders.
8/9/2019 Scheduling 18A
15/20
JobSequencing
Setting up Priority Rules to order jobs.
Performance measures to evaluate priority
rules:1. Meeting due dates of customers.
2.Minimizing the flow time.
3.Minimising work-in-process inventory.
4.Minimising idle time of machines or
workers.
8/9/2019 Scheduling 18A
16/20
Gantt Chart
Stage
10 15 25 35 45 60 65 75 85 95 105 115 120 130 140 150 160 165
Mixing
RollingDrying
Cutting
Moulding
Cooling
1st finishing
2nd finishing
Weighing & packaging
Time (in minutes)Stage
10 15 25 35 45 60 65 75 85 95 105 115 120 130 140 150 160 165
Mixing
RollingDrying
Cutting
Moulding
Cooling
1st finishing
2nd finishing
Weighing & packaging
Time (in minutes)
8/9/2019 Scheduling 18A
17/20
Kneader machine : 10 minutesRubber stored in bins : 45 minutesRolling : 5 minutesDrying : 30 minutes
Cutting to smaller sheets : 15 minutesMoulding : 5 minutesCooling : 30 minutes1st finshing : 25 minutes (per 200 pieces)Collection in bins for transporting : 120 minutes2nd finishing : 30 minutes (per 200 pieces)
Stored in bins : 75 minutesWeighing and Packaging : 15 minutes
TOTAL 405 minutes( 6 hours 45 minutes )
THROUGHPUT TIME
8/9/2019 Scheduling 18A
18/20
Kneader machine : 10 minutes
Rolling : 5 minutes
Drying : 30 minutes
Cutting to smaller sheets : 15 minutes
Moulding : 5 minutes
Cooling : 30 minutes
1st finshing : 25 minutes (per 200 pieces)
2nd finishing : 30 minutes (per 200 pieces)
Weighing and Packaging : 15 minutes
TOTAL : 165 minutes
(2 hour 45 minutes)
VALUEADDED TIME
8/9/2019 Scheduling 18A
19/20
SUGGESTIONS
Modification in Layout
Packaging Place
Reduce Wastage
Safety Measures
8/9/2019 Scheduling 18A
20/20