Tamarack Recharge Project
How field data collection and
modeling were used to
determine stream impacts for
the water court case
What Makes the Tamarack Model Unique?
• Nothing new in the science. Standard
MODFLOW finite difference model.
• What is unique is the large amount of data
available for the model setup and calibration.
• The litigation process may be of some interest.
Note: one novel aspect is that we used metric units
– see the slide on lessons learned
TEAM PROJECT
• Colorado State University
• CO State Engineer’s Office
• Colorado Parks & Wildlife
• Northern CO Water Conservancy District
Main Modeling Team:
Model Objectives
1. Determine timing, amount
and location of impacts to the
South Platte River.
2. Optimize the design and
operation of the recharge
project
3. Define the impacts of the
recharge operation on
wildlife habitat at the
Tamarack SWA,
Modeling Time Line (Looking Back)
Phase 1: Pilot Model (2001-2002)
Phase 2: Expanded Model and Calculated
Initial Stream Depletions for Water Court
Case (2003)
Phase 3: Water Court Negotiations -
Expanded model again and conducted
additional testing per negotiations with
Objectors (2004 – 2012).
River Starts as Constant Head Boundary
Phase 1: Focus on Main Recharge Area
Geologic Study Area:
Tamarack SWA Boundary
Based on data from 88 well logs:
• 10 Cross-sections were drafted
• 3 Contour maps were created
A
A’
B’
B
Clay, Shale, Brule
Aquitard
South Platte
River
South Platte Alluvium
Sand Dunes
North A
South A’
Schematic Cross-Section A-A’
West End of Tamarack SWA
Brule, Clay,
Shale Aquiclude
Paleo
Channel
South Platte
River
South Platte Alluvium
Sand Dunes
North
B
South
B’
Schematic Cross-Section B-B’
East End of Tamarack SWA
Brule, Clay,
Shale Aquiclude
ET and Recharge:
•Area divided into 3 zones: riparian, meadow and sand hills
•Riparian & Meadow Zones: 85% of the precipitation goes
directly to meet ET. ETS package used varies ET with depth.
•5% of precipitation recharges Sand Hills Area
Phase 1: Calibration Data
•31 groundwater and 2 stream stage monitoring locations
with survey elevation accuracy of 0.1 foot.
•10 Monitoring periods from Nov 2000 thru Oct 2001
•Total of 267 Groundwater Level Calibration Points
Phase 1: Final Calibration after PEST
Optimized K
River Floodplain=360 ft/day
Paleo Channel = 230 ft/day
Sand Hills = 360 ft/day
Optimized Sy
River Floodplain=0.2
Paleo Channel = 0.1
Sand Hills = 0.1
Phase 1: Lessons Learned
• Noticed that with high conductivities, the impact of the
recharge operations spread out considerable distances. Need
to move boundaries out in Phase II
• Good calibration, lots of data, constant head boundary
appeared reasonable.
• For a good water balance one needed to set the closure
criteria very low (0.00005 feet) for calculating stream
impacts using MODFLOW. Use of a large matrix solver
(SAMG) was also very useful
Phase 2: Expand Model and Calculate Stream Depletions
Crook Bridge
Red Lion Bridge
Expanded Time Period:
•Feb 1997 to Oct 2004
•Total Calibration Points increased to 466
Expanded Grid: both to the west and to the east
New Grid:13 by 2.5 miles
Phase 2 Calibration
Even better, Normalized RMS
1.95% with same aquifer parameters
as Phase 1
Phase 2: Calculate Stream Depletions
Methodology:
• Change ET – Allowing ET to change with depth results in
seasonal variations in stream depletions. Handled by
changing ET to negative recharge based on water budget
analysis.
• Developed scaled down model to calculate unit response
functions of all wells and ponds
• SDF – Why don’t they match model results for the ponds?
0.00
500.00
1000.00
1500.00
2000.00
2500.00
3000.00
3500.00
4000.00
Ap
r-01
Ap
r-02
Ap
r-03
Apr-0
4
Mar-0
5
Ma
r-06
Ma
r-07
Ma
r-08
Ma
r-09
Ma
r-10
Cu
mu
lati
ve
Pro
jec
t R
ec
ha
rge
to
Riv
er
(ac
re-f
ee
t)
Day
Comparison of Modflow and SDF Image Well Methods Example Tamarack Recharge Project Pond
Tamarack Recharge Model (MODFLOW)
Image-Well Adjusted SDF = 65 days (Calibrated)
SDF = 65 days
-3000
-2000
-1000
0
1000
2000
3000
4000
5000
6000
7000
Jan-97 Jan-98 Jan-99 Jan-00 Jan-01 Jan-02 Jan-03 Jan-04 Jan-05 Jan-06
acre
-feet
Date
Cumulative Project
Accretions
Cumulative TOTAL
Project Impacts
The Bigger Picture on Project Accretions
Phase 2: Lessons Learned
• Good calibration, based on lots of data, constant head
boundary appeared reasonable. Ready for Court!!
• For Tamarack, move wells as close to the river as
practical and have ponds at several locations to
provide flexibility with recharge.
• SDF method not appropriate for structures near the
edge of the aquifer.
PHASE 3 : Water Court
Unique Historical Context:
• South Platte Water Court Arena in the 2000’s was extremely
active. A large number of recharge and augmentation water court
applications submitted and trial schedule booked for many years
out.
Empire Lodge Decision (2001) – Marked the end of SEO
approval of SSPs w/o a pending water court augmentation
plan.
GASP a non-profit well-augmentation company founded in
1972 ceased operations in 2003. At its peak GASP served
~4,000 wells in NE Colorado.
• CPW: State Government Agency
PHASE 3 : Water Court
First model issue:
ET – Objectors noted that recharge raises water
levels increases ET.
Solution – Ran model with ET changing with
depth under several different operational
scenarios and determined that ET credits were reduced by ~5%. Agreement was made that
all project accretions would be decreased by
5% at the river to account for ET.
Second and Most Contentious Model Issue:
Streambed Conductivity – Objectors did not like
the S. Platte River constant head boundary for
wells close to the river.
Proposed Solution – • Expand the model across the river and change the South
Platte River boundary to a river boundary. But.. what to
use for the streambed parameters?
• Ran not 1 but 2 of the most excellent aquifer pumping
tests ever seen on the S. Platte. With such a
collaborative effort between all interested
consultant/engineers – How could it not provide the
definitive streambed conductivity value.
• Site 1: Iliff Site: 8
miles upstream from
Tamarack near the
town of Iliff. Pumping
Well 80 feet from
river, pumped for 2
days
Site 2: Red Lion Site:
– Just downstream of
Tamarack SWA.
Pumping well 120
feet from river,
pumped for 4 days
Photo courtesy of TZA
Water Engineers, Inc.
• Groundwater elevations:
Measured at 10 to 6 locations
• Stream stage: Measured at 3
stream stage sites.
Photo courtesy of TZA
Water Engineers, Inc.
Photo courtesy of Miller Groundwater
Engineering, LLC
Stream flow: Measured before, during and after pumping.
DWR hydrographers also conducted measurements for
QA/QC.
Photo courtesy of Miller Groundwater
Engineering, LLC
Aquifer Performance Test Results
1. Streambed leakance (Ksb/m) interpreted from the APT testing
ranged from: 1.69 to 775 ft/day/ft (Note that one objector
proposed a preferred value of 0.011 ft/day/ft)
2. However, only Ksb/m values below 10-20 ft/day/ft
significantly impact the Recharge Project.
3. Data from these tests was used in numerous water court case
negotiations on the Lower South Platte River.
4. Recently published journal articles indicate that the streambed
leakance parameter is grid dependant and may be best
estimated by calibration.
Decreed Results
Compromise reached a week before trial:
For wells located less than 900 feet from the river: URFs
calculated using a stream leakance value of 20
ft/day/ft for project accounting . Additional
limitations applied for leasing of any project credits.
For structures located more than 900 feet from the river:
URFs calculated using the original model with the
South Platte River modeled as a constant head
boundary.
Phase 3 - Lessons Learned:
• Model was helpful in running scenarios and analyzing
project impacts of objector proposals.
• Think twice about having more than one model objective
when going to water court.
• More stream flow calibration data would have been very
helpful!!!!
• NEVER USE METRIC UNITS – especially when going
to water court!!!
One Final Question for Discussion:
Tamarack Recharge Project negotiations
took place under “ye olde” Water Court
Rules.
Would the results or process be any
different under the 2009 Water Court
Rule 11 on Expert Testimony??????
QUESTIONS