+ All Categories
Home > Documents > SAINT CHARLES

SAINT CHARLES

Date post: 21-Jan-2022
Category:
Upload: others
View: 1 times
Download: 0 times
Share this document with a friend
34
1 SAINT CHARLES SEPTEMBER 2021 DEPARTMENTAL REPORT Larry Dobrosky, Director of Administration
Transcript
Page 1: SAINT CHARLES

1

SAINT CHARLES

SEPTEMBER 2021

DEPARTMENTAL REPORT

Larry Dobrosky, Director of Administration

Page 2: SAINT CHARLES

2

INDEX

PAGE

ADMINISTRATION 3

CITY CLERK 5

COMMUNICATION TECHNOLOGY 7

COMMUNITY DEVELOPMENT 8

CVB 12

ECONOMIC DEVELOPMENT 14

ENGINEERING 17

FINANCE 20

FIRE 22

HUMAN RESOURCES 25

LEGAL 27

MUNICIPAL COURTS 28

PARKS & RECREATION 29

POLICE 32

PUBLIC WORKS 34

Page 3: SAINT CHARLES

3

ADMINISTRATION

HIGHLIGHTS

Community Development Department – Director Interviews.

Employee Recognition Program Committee preparing final draft of the new program

“Employee Spotlight Awards” for presentation to City Council in November.

Attended Governor’s Bicentennial Inaugural Parade and Ball on September 18th.

Attended Businessmen’s and Police Prayer Breakfast meetings September 8th and

September 21st.

Union 148 negotiations initiated.

Brown Bag Lunch Meeting conducted September 21st – Succession Planning.

Development discussions continue.

Larry Perney and Don Stolberg attended MML Conference at Union Station, St. Louis.

Department Head Leadership Expectations development ongoing.

Performance Improvement Review Team Program development ongoing.

WORK SESSION FOLLOW-UP/UPDATES

Employee Recognition Program – November, 2021

Charley/Ride STC (formerly SCAT) – November, 2021

2022 Budget – November, 2021

Foundry Art Centre – November/December, 2021

Personnel Manual Revision – December, 2021

Riverpointe – December, 2021

Health Clinic Partnership – December, 2021

Special Events – December, 2021

Medical Marijuana Dispensaries/Ordinance Options – December, 2021

City Financial Statement Review – January, 2022

Convention Center Oversite Committee – January, 2022

Strategic Plan – February, 2022

MoDot Design-Build Project Delivery – TBD

NOTE: Above are new program implementation, studies on other items presented to the Council and an

estimated follow-up date when staff will update Council on progress. These timeframes may change based on

schedules and priorities.

MANAGEMENT POLICY MANUAL UPDATES (St. Charles City Employee Portal)

Selection of Towing Service Providers – Effective 9/29/21

Page 4: SAINT CHARLES

4

ADMINISTRATION

HIGHLIGHTS

NAME OF PROJECT CONTRACTOR

ORIGINAL

AMOUNT OF

PROJECT ($)

CHANGE

ORDER

AMOUNT

AGGREGATE AMOUNT

OF ALL CHANGE

ORDERS/AMENDMENTS

DESCRIPTION OF WHY CHANGE ORDER

WAS NEEDED DEPT.

CIPM Manholes Visu Sewer of Missouri, LLC 97,731.27$ $2,036.08 $99,767.35 Manhole repair and rehabilitation Public Works

Lincoln Elementary Safe

Routes to School

Gershenson Construction

Company, Inc. 887,019.75$ $27,571.40 $953,032.45

Additional work and materials necessary

to complete the project. Engineering

Wapelhorst Park Pull Boxes (2) Reinhold Electric, Inc. 191,486.00$ $3,508.00 $194,994.00

Provide and install (2) Pull Boxes at

Wapelhorst Park, includes OT fees

associated with weekend fiber work at

Parks.

Communication

Technology

Standard Hydrated Lime Mississippi Lime Company 480,000.00$ $74,000.00 $554,000.00

Additional Hydrated Lime supply for

remainder of 2021. Public Works

Animal Control Facility

Improvement

Interstate Restoration, LLC

dba First Onsite 27,898.57$ $925.00 $28,823.57

Installation of new drop ceiling for Mold

remediation. Public Works

Asphalt Microsurfacing

Donelson Construction

Company, LLC 350,000.00$ $41,647.12 $391,647.12 Additional asphalt microsurfacing services Public Works

CHANGE ORDERS/AMENDMENTS RECEIVED

VENDOR NAME DESCRIPTION DEPARTMENT $ AMOUNT

Trekk Design Group, LLC Review of Sewer Flow Variations - 7 Locations Public Works $ 16,025.00

A.D. Frazier & Associates, Inc. Repair Dekker Vacuum Pump / W&C New Town VAC Pump Rebuild Public Works $ 16,245.00

Bax Engineering Company

Surveying & Engineering Services to prepare construction bid

documents for stormwater improvements near Prairie Haute Drive

and Eau Claire Drive Engineering $ 29,478.00

Insituform Technologies USA, LLC 48" CIPP Rehab / Stormwater Infrastructure Public Works $ 68,900.00

Masters Contracting, Inc. Replacement of Retaining Wall at 1996 West Adams Public Works $ 11,200.00

WM Financial Strategies Municipal Advisor Services (COPs or Special Obligation Bonds) Finance $ 19,000.00 A1A Sandblasting Mississippi Plant Clarifier No. 3 Painting Public Works $ 32,200.00

CONTRACTS RECEIVED/APPROVED ($10,000 - $100,000)

Page 5: SAINT CHARLES

5

CITY CLERK

HIGHLIGHTS (Q3 2021 – July through September)

The City’s budget preparations began during the third quarter. To assist in the process, the Clerk’s Office works with Administration to coordinate the necessary City Council Meetings and Work Sessions for annual CIP and Operating Budget discussions.

In July, an Election was conducted to determine the City’s new Council President and Council Vice President, and the new City Council Line of Succession was established by lottery. In August, our Councilmembers were appointed to the Council’s Street Committee and as Council Liaisons to the City’s Boards, Commissions and Committees.

In September, two of our City Councilmembers attended the MML’s Annual Conference, held at Union Station in St. Louis this year. The Clerk’s Office handles these arrangements; Conference and Event Registrations and Conference Packet preparations. Follow-up includes expense reimbursements and invoice payments. In addition, one of our Deputy City Clerks attended the Missouri City Clerks and Finance Officers Association (MoCCFOA) annual Master Academy which is held on the first day of the MML Conference.

We’re making headway with the uploading of our past Ordinances and Resolutions to “E-Code” on the City’s Website. As this project progresses, the Community, along with our City’s Staff, will have online access to more of the City’s past legislative documents.

Our new Deputy, Emily, is our Records Manager, and she has made significant progress with the following:

o Launched our G1 Storage Area Clean-Up and Reorganization Project. (See photos on the next page)

Identified 71 boxes of files stored on G1 that had been microfilmed; determined these files were on file with the state and met destruction criteria.

Received Council approval to dispose of the 71 boxes on September 7 and proceeded with destruction on September 17.

Identified nine boxes of Board of Adjustment minutes dated 1969-1991 that had been microfilmed and were on file with the state; these files will be placed on a Records Destruction Form for approval at a future Council Meeting.

Reorganized the remaining boxes stored in the Clerk’s space on G1 into three sections: Ordinances, Resolutions and Contracts.

Reduced the amount of G1 storage space utilized by the Clerk’s Office by 50% (nine full shelves to four and a half shelves).

Developed plans to review, categorize and either archive or destroy the files stored in the remaining boxes.

o Established records management priorities and projects and created a project board to display the status of each item. (See photos on the next page)

Inventoried files stored in The Clerk’s Office in an effort to establish a schedule for future projects.

Inventoried microfilm repository and organized the contents of the drawers. Gathered Resolutions from 2013-2018 and sent for microfilming. Reviewed 1998 files. Separated permanent and non-permanent records. Disseminated 2021 General Record Retention Schedule and 2021 Municipal

Record Retention Schedule to the Custodian of Records for each Department (this document is updated annually in August).

Page 6: SAINT CHARLES

6

CITY CLERK

HIGHLIGHTS (Q3 2021 – July through September)

During our third quarter, members of the City Clerk’s Staff participated as members of the Communication Ambassador Committee and the Employee Recognition Committee.

In July, the two Deputy City Clerks attended the Monthly Eastern Division Meeting of the MoCCFOA.

In September, the two Deputy City Clerks attended the City’s required Fraud and Ethics Training.

During our third quarter, the City Clerk and members of her staff attended a total of 12 City Council Meetings and Council Sub Committee Meetings. Preparations involve generating the Agenda and coordinating with other departments to obtain agenda items. The most significant and critical post-meeting responsibility is the preparation, compilation and proofing/editing of minutes for each meeting.

During the first three quarters of 2021 the City Clerk’s Office processed 150 Ordinances, 32 Resolutions and 292 Contracts (not including Change Orders, Amendments, Renewals or Easements.)

During the first three quarters of 2021 the City Clerk’s Office processed or assisted with 175 Official Records Requests (Sunshine Law Requests) received from the public (individuals, businesses, law firms, other organizations, etc.) This number does not include requests that are currently pending, or the requests we regularly receive from our City Departments/Employees.

Page 7: SAINT CHARLES

7

Blue line represents August 01 through August 31, 2021

COMMUNICATION TECHNOLOGY

WEB SITE ROKU

36,277 visits

28,981 unique visitors

2 min, 33 sec average visit duration

62,702 page views

49,384 unique page views

2,667 total searches on our website

SOCIAL MEDIA YOU TUBE

In September, we had 1,200 views on our

YouTube Channel.

Top 5 Videos:

What’s Happening! September 2021

40 Years of Christmas Traditions

STCnow 9-16-21

STCnow 9-9-21

Legends & Lanterns: Wicked Witch of

the East

MEDIA PRODUCTIONS COMMUNICATION PROJECTS

STC Now – 4 episodes ● Planning/promotion for 2nd Paw Parade

Pet of the Week with Five Acres – 4 episodes ● Assisted Lindenwood with their

City Meetings: City Council, Landmarks Board, Homecoming Parade

Planning & Zoning, Board of Adjustment ● Communication Ambassador meeting

Paw Parade promotions ● PW communication projects meeting

Legends and Lanterns; promotions & Haunted Tour I.T. PROJECTS

videos ● City-wide software systems exploration

COMMUNICATION PROJECTS ● Fiber project underway, almost done

Working on November newsletter ● Remaining 2021 computer replacement

Page 8: SAINT CHARLES

8

COMMUNITY DEVELOPMENT

BUILDING PERMITS

Section 1:New Residential Buildings Buildings Housing Units

101 15 15 3,451,047

102

103

104

105

0 15 15 3,451,047.00

Section 2: New Residential

Buildings Rooms

213

214

215 5 226,231 1 inground pool; 3 ret walls; 1 shed;

Section 3: New Non-Residential BuildingsValuation of Construction

(Omitting Cents)DESCRIPTION

318

319

320

321

322

323

324

325

326

327 1,148,351 DPM St Charles self storage bldg

328

329 3 384,246Boulders pool cabana; Elmhaven sales trailer; pocket

park brick patio/planters

Section 4:ADDITIONS, ALTERATIONS

Valuation of Construction

(Omitting Cents)DESCRIPTION

434 2,066,501 20 int/alt/add, 20 decks; 3 solar; 4 fire repr

437 1,602,998 4 alterations/int; 1 cell tower mod; 3 solar

438 800

Section 5:DEMOLITIONS AND RAZING

Number of Housing Units DESCRIPTION

645

Two-Family Buildings 646

Three and Four Family Buildings 647

Five or More Family Buildings 648

All Other Buildings and Structures 649

TOTALS 80 # Permits 8,880,174 Value

Residential Structures Other Than Buildings

Single-Family Houses, Attached -

Separated by ground to roof wall -

No units above or below, and -

Separate heating systems & utility meters

Two-Family Buildings

Hotels, Motels, And Tourist Cabins

(transient accommodations only)

Other Nonhousekeeping Shelter

Three and Four Family Buildings

Five or More Family Buildings

TOTAL: Sum of 101-105

Non-Housekeeping Buildings

Number of:

Single-Family Houses, Detached

(Excluding Mobile Homes)

Item No. DESCRIPTIONValuation of Construction

(Omitting Cents)

Commercial Structures Other Than Buildings

Amusement, Social and Recreational

Churches and Other Religious

Industrial

Parking Garages (Buildings & Open Decked)

Service Stations and Repair Garages

Hospitals and Institutional

Offices, Banks, and Professional

Public Works and Utilities

Schools and Other Educational

Stores and Customer Services

Other Nonresidential Buildings

47

1

OF BUILDINGS Number of BuildingsSingle-Family Houses

(Attached and Detached)

Additions of Residential Garages and Carports

(attached and detached)

AND CONVERSIONS

Nonresidential and Nonhousekeeping (Com) 8

1

Residential - Classify Additions of Garages and

Carports in Item 438. Includes Decks.

Number of Buildings

Page 9: SAINT CHARLES

9

COMMUNITY DEVELOPMENT

HIGHLIGHTS (Q3 2021 – July through September)

PLANNING DIVISION

Following is the activities report for the third quarter (July through September) of 2021 for the Department of Community Development. The information is organized and presented by division.

2021 Totals Board/Review Type

Time Period P&Z Com.

BOA Landmarks Plats Façade Grants Total

January 9 2 4 1 0 16

February 10 0 9 0 0 19

March 10 1 16 2 0 29

April 13 1 12 2 0 28

May 7 0 21 2 0 30

June 13 2 13 4 0 32

July 11 1 15 4 0 31

August 10 0 5 2 0 17

September 5 1 15 2 0 23

2021 Quarterly P&Z Com. BOA Landmarks Plats Façade Grants Total

1st Quarter 29 3 29 3 0 64

2nd Quarter 33 3 46 8 0 90

3rd Quarter 26 2 35 8 0 71

2020 Totals Board/Review Type

Time Period

P&Z Com.

BOA Landmarks Plats Façade Grants Total

January 7 2 6 3 0 18

February 11 0 11 2 0 24

March 9 2 7 3 0 21

April 9 0 13 0 0 22

May 7 6 9 5 0 27

June 12 2 14 1 0 29

July 10 3 14 0 0 27

August 10 2 17 1 0 30

September 3 2 14 0 0 19

2020 Quarterly P&Z Com. BOA Landmarks Plats Façade Grants Total

1st Quarter 27 4 24 8 0 63

2nd Quarter 28 8 36 6 0 78

3rd Quarter 23 7 45 1 0 76

Page 10: SAINT CHARLES

10

COMMUNITY DEVELOPMENT

HIGHLIGHTS (Q3 2021 – July through September)

BUILDING DIVISION

NUMBER

OF VALUE OF

HOUSING

UNITS

CONSTRU

CTION

Jul 24 6,430,155

Aug 25 7,403,556

Sept 15 3,451,047

NUMBER

OFVALUE OF

BUILDINGSCONSTRU

CTION

Jul 0 0

Aug 1 350,000

Sept 2 1,462,097

NUMBER

OFVALUE OF

PERMITSCONSTRU

CTION

Jul 39 1,093,431

Aug 54 1,779,887

Sept 48 2,067,301

NUMBER

OFVALUE OF

PERMITSCONSTRU

CTION

Jul 6 1,417,700

Aug 14 2,263,008

Sept 8 1,602,998

MONTH

MONTH

MONTH

MONTH

COMMERCIAL CONSTRUCTION

ALTERATIONS, ADDITIONS & INTERIOR FINISHES

RESIDENTIAL CONSTRUCTION

ALTERATIONS, ADDITIONS AND INTERIOR FINISHES

COMMERCIAL CONSTRUCTION

NEW BUILDINGS

0

5

10

15

20

25

Jul Aug Sept

24 25

15

NUMBER OF HOUSING UNITS

NUMBER OF HOUSINGUNITS

0

1,000,000

2,000,000

3,000,000

4,000,000

5,000,000

6,000,000

7,000,000

8,000,000

Jul Aug Sept

6,430,155

7,403,556

3,451,047

VALUE OF CONSTRUCTION

VALUE OF CONSTRUCTION

RESIDENTIAL CONSTRUCTION

NEW SINGLE FAMILY AND MULTI-FAMILY

0

0.5

1

1.5

2

Jul Aug Sept

0

1

2

NUMBER OF BUILDINGS

NUMBER OF BUILDINGS

0

200,000

400,000

600,000

800,000

1,000,000

1,200,000

1,400,000

1,600,000

Jul Aug Sept

0

350,000

1,462,097

VALUE OF CONSTRUCTION

VALUE OF CONSTRUCTION

0

10

20

30

40

50

60

Jul Aug Sept

39

5448

NUMBER OF PERMITS

NUMBER OF PERMITS

0

500,000

1,000,000

1,500,000

2,000,000

2,500,000

Jul Aug Sept

1,093,431

1,779,887

2,067,301

VALUE OF CONSTRUCTION

VALUE OFCONSTRUCTION

0

2

4

6

8

10

12

14

Jul Aug Sept

NUMBER OF PERMITS

NUMBER OF PERMITS

0

500,000

1,000,000

1,500,000

2,000,000

2,500,000

Jul Aug Sept

VALUE OF CONSTRUCTION

VALUE OFCONSTRUCTION

Page 11: SAINT CHARLES

11

COMMUNITY DEVELOPMENT

HIGHLIGHTS (Q3 2021 – July through September)

COMMUNITY DEVELOPMENT BLOCK GRANT (CDBG) DIVISION

CODE ENFORCEMENT Rental Units

Home Improvement Loan Inspections &

First Time Home Buyer Inspections

Code Enforcement Cases

TOTAL 154 10 103

HOME IMPROVEMENT

PROGRAM Clients

Participating Applications in

Progress Projects Completed Rehabbing

TOTAL 88 28 5 60

1ST TIME HOME BUYER PROGRAM Clients Participating

Applications in Progress Homes Purchased

TOTAL 18 2 7

TRANSPORTATION PROGRAM Clients Participating

Disabled or Dialysis Clients

Elderly Not Disabled

Number of Trips

TOTAL 88 56 21 420

CODE ENFORCEMENT DIVISION

Page 12: SAINT CHARLES

12

CVB

HIGHLIGHTS (Q3 2021 – July through September)

Operations/Marketing

o Riverfest culminated with a grand fireworks display July 4th weekend. Vendor

Booth requests and crowds were strong for this year’s event. Next year’s display

will be held on Monday, July 4th, 2022.

o The Fall-Winter 2021-2022 Main Street Map & Directory was printed and currently

in circulation. Copies can be obtained at the CVB.

o Auditions and Onboarding occurred for Legends & Lanterns and St. Charles

Christmas Traditions. A total cast of 109 this year for both events with 21 new cast

members.

o Jenna Schuermeyer joined the CVB staff as a Special Events Coordinator.

o Finished and lunched fresh design to our discoverstcharles.com website.

Foundry

o The Block Party Exhibit at Lambert Airport was installed in Concourse 2 and will be

on display thru March 2022. The Exhibit includes photographs and artwork created

from a “Steam Rolling” process showcased at Block Party which occurred this

summer.

o Art Camp registrations ended strong for the 8-week sessions bringing in revenue of

approximately $53,000.00. This year’s Art Camp classes focused on going

“Green”!

o Paige Jenkins joined the Foundry staff as Special Events Coordinator.

o First Fridays began in July. Each first Friday of the month, the FAC will be open for

extended hours through 8pm for visitors to spend time in the galleries, meet

resident studio artists, engage with the community, and enjoy a wide array of art

programming, entertainment, and special events.

St. Charles Convention Center

o Fire inspection meeting with the CC, CVB and SCFD reviewed policies and

procedures and concluded with appropriate plan of action.

o A big welcome to newly hired Director of Food and Beverage, Richard McConnell.

o Recent improvements to the building include outside brick and concrete work and

some internal areas of worn carpet, should be repaired by end of 2021.

Page 13: SAINT CHARLES

13

CVB

HIGHLIGHTS (Q3 2021 – July through September)

Sales Department

o Group Sales

Third Quarter actualized conference and events included more than 22,000

attendees in the destination with 5000 room nights. A few of the group

highlights are below:

State Wars Roller Hockey Tournament – in our destination for 2

weeks with approximately 10,000+ attendees and 2373 room nights.

Estimated event impact to the destination is $2,704,585. CVB

sponsored event tournament at the Rec-Plex with a Sporting event

tax credit from Missouri DED.

Munce Group – Expo held at the Convention Center with 700+ room

nights.

ATD Tools, Inc. (ITEG Expo) – returns bi-annually and brings 400

room nights.

St. Charles is leading our competitive set at 60% occupancy in partner

hotels YTD through August. This is an increase of 29% compared to 2020.

Attended Connect Marketplace 2021 with 2000 planners in attendance for

all markets. Collectively we had 120 planner appointments with our

Convention Center partners and welcomed many to our Saint Charles

booth. We sponsored a hotel room drop for 800 planners which promoted

our destination and booth.

Future Booking highlights:

After working with our client, American Veterans, for one year and

recently presenting at their 2021 convention, St. Charles won the bid

to host their National Convention in 2025. This conference includes

1200+ attendees and their families with 2500+ room nights for the

area.

Missouri Parks and Recreation Assoc. definite for March 2024 with

500 attendees and 360 room nights.

o Convention Services

Provided convention services for 6 conventions including 18 hospitality

tables.

Page 14: SAINT CHARLES

14

ECONOMIC DEVELOPMENT

HIGHLIGHTS (Q3 2021 – July through September)

September new business licenses – 18

Frenchtown

o Shipping container village – Developer has acquired first parcel and has engaged

engineering and architectural design firms.

o Trailer park at Third and Wilkinson has been cleared in preparation for public

parking lot.

o Good News Brewery has submitted building plans.

o Frenchtown Tattoo Company has opened at 911 N. Second Street.

o ACF site visits and inquiries remain strong.

Riverpointe – With the announcement of Chicken N Pickle, pickleball combined with a

Chicken themed restaurant, inquiries from other developers has significantly increased.

Fountain Lakes – Responded to 2 request for information, one for manufacturing facility

and one distribution warehouse.

New Economic Development Website – Our new site is under construction and will

feature success stories of our local businesses with first-hand accounts of why they chose

St. Charles and how we helped them through the processes of opening or expanding their

business.

St. Charles County Port Authority – Working with the County to develop a strategic plan

that will include St. Charles City development areas.

Jalea – A new Peruvian Restaurant is coming to N. Main Street.

Wineolgy – has opened at 3767 New Town Blvd. They are focused Missouri wines and

will be a whole new way to learn about, taste, purchase and enjoy Missouri wines.

Page 15: SAINT CHARLES

15

Business Name Contact Name License Type Activity Type Industrial Code Business Address CityZip

Code

Phone

Number

360 Painting Of O'Fallon Burkart, Matt Non Retail LicenseGeneral Contractor

ResidentialResidential Building Construction 3412 Mackey Wherry St St Charles 63301 (314) 452-7933

Beltone Hearing Aid Center Mmcmillin, Brad Retail Merchant License Retail Health & Allied Services Not Elsewhere Cla 2045 Zumbehl Rd St Charles 63303 (636) 724-8200

Boaz Tactical Little, Alex Non Retail License Business Offices Miscellaneous Business Services 117 S Main St St Charles 63301 (636) 364-8773

Designs By Maryann Pugh LLC Pugh, Mary Ann Non Retail LicenseRemodel Contractor

ResidentialResidential Building Construction 301 Canary Ln St Charles 63301 (636) 541-4899

Ed Stone Commercial Edward Stone Non Retail License Real Estate Broker Real Estate Agents And Managers 2480 Executive Dr Ste 111 St Charles 63303 (636) 685-0115

Frenchtown Tattoo Company Heidorn, Derek Non Retail License Artists Miscellaneous Business Services 911 N 2nd St St Charles 63301 (314) 313-2712

Hopper Agency Korte, Sheila Non Retail License Business Offices Insurance Agents, Brokers And Service 2145 S Old Hwy 94 Unit B St Charles 63303 (636) 947-7600

Industrial Wire Rope Supply Co, Inc. Korn, John Non Retail License Wholesaler Miscellaneous Equipment And Supplies 2086 Exchange Dr St Charles 63303 (636) 255-0600

Little Hills Architecture Beucke, Michelle Non Retail License Architects Engineering Architectural And Surveying Services 602 N Benton Ave St Charles 63301 (636) 578-9973

Lung Ins. Agency Lung, Gary Non Retail License Insurance Agent Insurance Agents, Brokers And Service 2248 Bluestone Dr St Charles 63303 (314) 330-5864

Peth Architects Peth, Michael Non Retail License Architects Engineering Architectural And Surveying Services 506 S Main St St Charles 63301 (314) 412-5387

Revive Tan Wagoner, Ryan Retail Merchant License Retail Tanning Salons 3726 Elm St St Charles 63301 (636) 940-4055

Shabab Plus Smoke Shop LLC Hamed, Tareq Retail Merchant License Retail Miscellaneous Retail Stores, Not Elsewhere 1384 S 5th St St Charles 63301 (314) 583-2588

St. Louis Electric Inc Jackson, James Non Retail License Business Offices Electric Services 2451 Executive Dr Ste 107 St Charles 63303 (314) 607-8970

Tropical Travel Micheletti, Randy Non Retail License Business Offices Travel Agency 2421 Aurelein Ct St Charles 63301 (636) 208-3336

Vision Marketing + Promotions, Inc. Pogue, Richard Retail Merchant License Clothing - All Other Misc Apparel, Accessory Stores 3734 Elm St St Charles 63301 (636) 400-1500

Wireless Vision Ammori, Saber Non Retail License Business Offices Miscellaneous Business Services 1377 Bass Pro Dr St Charles 63301 (248) 406-4630

Wireless Vision LLCWireless Vision

LLCNon Retail License Business Offices Miscellaneous Business Services 2941 Veterans Memorial Pkwy St Charles 63303 (248) 406-4630

ECONOMIC DEVELOPMENT

NEW BUSINESS LICENSES

ST. CHARLES COUNTY RESIDENTIAL BUILDING UNITS

Page 16: SAINT CHARLES

16

ECONOMIC DEVELOPMENT

ST. CHARLES COUNTY MISSOURI WIDE HOUSING PERMITS

1000000# Lots # Units Est. Cost # Lots # Units Est. Cost # Lots # Units Est. Cost # Lots # Units Est. Cost # Lots # Units Est. Cost # Lots # Units Est. Cost # Lots # Units Est. Cost # Lots # Units Est. Cost

JanuarySingle Family Detached 11 4.77 47 10.05 33 8.53 10 3.76 10 3.20 8 1.43 28 8.84 147 40.60

Single Family Attached 1 4 0.90 - - - - - - - - - - - - - - - - - - 1 4 0.90

Multi-Family - - - - - - - - - - - - - - - - - - - - - - - -

New Commercial - - - - 1 0.62 - - - - - 6 41.10 7 41.72

FebruarySingle Family Detached 13 4.94 33 7.42 58 15.14 10 2.82 12 3.97 5 0.96 38 12.38 169 47.63

Single Family Attached - - - - - - 6 6 1.13 - - - - - - - - - 6 6 1.13

Multi-Family - - - - - - - - - - - - - - - - - - - - -

New Commercial 1 12.07 1 0.93 - - 1 0.08 - - - - - - 3 13.07

MarchSingle Family Detached 9 3.64 37 7.99 43 11.76 34 9.87 10 3.09 4 0.70 37 11.31 174 48.37

Single Family Attached 1 4 0.95 - - - 8 8 1.35 - - - - - - - - - - - - 9 12 2.29

Multi-Family - - - - - - - - - - - - - - - - - - - - - - - -

New Commercial 1 0.58 1 0.90 - - 4 2.58 - - - - 1 13.00 7 17.06

AprilSingle Family Detached 17 6.27 36 10.45 38 10.63 14 5.54 15 5.22 9 5.84 41 12.33 170 56.28

Single Family Attached - - - - - - 6 6 1.13 - - - - - - - - - - - - 6 6 1.13

Multi-Family - - - - - - - - - - - - - - - 8 192 26.27 8 192 26.27

New Commercial - - 1 0.15 1 4.56 - - - - 2 1.93 4 6.64

MaySingle Family Detached 8 3.24 25 4.61 36 9.69 25 7.76 10 4.46 - - 28 8.44 132 38.19

Single Family Attached - - - - - - - - - - - - - - - - - - - - - - - -

Multi-Family 2 3 1.42 - - - - - - - - - - - - - - - - - - 2 3 1.42

New Commercial - - 1 1.50 - - 1 1.20 - - 2 3.21 1 0.85 5 6.76

JuneSingle Family Detached 26 10.40 28 5.10 24 7.19 29 10.05 8 2.69 7 1.16 41 12.85 163 49.44

Single Family Attached - - - 1 2 0.20 - - - - - - - - - - - - 1 2 0.57 2 4 0.77

Multi-Family - - - - - - - - - - - - - - - - - - - - - - - -

New Commercial - - 1 1.75 - - 1 0.10 - - - - 4 4.10 6 5.95

JulySingle Family Detached 10 3.84 15 2.92 24 6.43 23 6.42 5 2.06 - - 16 4.75 93 26.42

Single Family Attached - - - - - - - - - - - - - - - - - - - - - - - -

Multi-Family - - - - - - - - - - - - - - - - - - - - - - - -

New Commercial - - 2 1.35 - - - - - - - - - - 2 1.35

AugustSingle Family Detached 14 7.09 18 4.34 25 7.40 18 6.76 4 1.37 1 0.20 23 7.24 103 34.39

Single Family Attached - - - - - - - - - - - - - - - - - - - - - - - -

Multi-Family - - - - - - - - - - - - - - - 6 120 9.40 7 198 26.87 13 318 36.27

New Commercial 1 0.94 1 0.35 - - - - - - - - - - 2 1.29

SeptemberSingle Family Detached 12 4.50 12 3.03 15 3.45 21 6.63 10 4.39 2 0.40 33 10.77 105 33.17

Single Family Attached - - - - - - - - - - - - - - - - - - 1 2 0.73 1 2 0.73

Multi-Family - - - - - - - - - - - - - - - 2 24 2.80 - - - 2 24 2.80

New Commercial - - 1 3.00 - - 3 2.84 - - - - 1 10.12 5 15.96

TOTALSSingle Family Detached 120 48.70 251 55.90 296 80.21 184 59.63 84 30.45 36 10.70 285 88.90 1,256 374.48

Single Family Attached 2 8 1.84 1 2 0.20 20 20 3.61 - - - - - - - - - 2 4 1.30 25 34 6.95

Multi-Family 2 3 1.42 - - - - - - - - - - - - 8 144 12.20 15 390 53.14 25 537 66.76

New Commercial 3 13.59 9 9.93 1 0.62 11 11.35 - - 2 3.21 15 71.09 41 109.78

* St. Charles County includes unincorporated St. Charles County, Augusta, New Melle, Weldon Spring, and West Alton.

St. Peters Wentzville 2021 Total CountySt. PaulLake St. Louis O'Fallon St. Charles City * County

Page 17: SAINT CHARLES

17

ENGINEERING

HIGHLIGHTS (Q3 2021 – July through September)

Project Updates

Benton Avenue and North Main Storm Sewer Improvements: The first phase is under construction as Floodgate #3 (see below). The remaining portion of the project, which includes storm sewer and water main improvements on Transit Street and Barthel Ave, is on hold awaiting final easement acquisitions.

Boone’s Lick Storm Sewers: The design consultant submitted four alternatives of a detention basin by Boone’s Lick Park to meter the flow and runoff. Staff was reviewed the alternatives and submitted back comments which include revising the alternatives. Revision will be finished the end of October.

Boschert Creek Pine to Kingshighway: The City opened bids on March 3rd. Fischer Grading was the low bid. Fischer Grading cleared the trees and brush from the creek bank, replaced an old sanitary sewer main, and began installing the composite revetment and storm sewer improvements. Fischer Grading has finished constructing one of the two block retaining walls and beginning the construction of the second wall as well as continuing to install the composite revetment.

Boschertown Road Phase II: Staff and the design consultant have been coordinating with utilities on relocation. Appraisals have been completed for the small amount of ROW and easements needed to construct the improvements. Final design will be completed later this year with bidding in early 2022.

Bridle Spur Culvert Replacement: This contract has been awarded to Gershenson Construction. Notice to Proceed date was 7/6/21. All storm related work is complete. Concrete roadway still needs to be replaced on Bridle Spur along with new sod and site clean-up. On schedule to meet November completion date.

Systemic Safety Improvements: This contract has been awarded to Gershenson Construction. A preconstruction meeting is scheduled for 10/12/21 with a Notice to Proceed the week afterwards. This project is primarily signing and striping work with some concrete work for bump outs at some intersections. Expect completion in early May 2022.

Clark Street Storm Sewer Improvements: Easement acquisitions are underway.

Crystal Springs Creek Rio Vista to S River Rd: Bids were opened on September 15, 2021. Fischer Grading was the apparent low bidder at $1,357,247.00. Board of Public Works approved at the September 27, 2021 meeting. Contract is set for Council reading on October 5, 2021.

Duchesne & Hawthorn Culvert Replacements: Easement acquisitions have been completed. The pre-final plans and specifications are being reviewed. Comments will be sent to GBA and incorporated into the final bid documents. Construction is expected to begin in spring 2022.

Floodgate #3: This project is the first phase of the Benton Avenue and North Main Storm Sewer Improvements mentioned above. The contractor has completed the outfall structure and continues storm sewer improvements. The contractor continues to work on installing new storm sewers and storm sewer structures. The project will continue into the Fall of 2021.

Page 18: SAINT CHARLES

18

ENGINEERING

HIGHLIGHTS (Q3 2021 – July through September)

Project Updates - continued

Frenchtown Basin 15 Private Source Disconnect: Smoke testing has been completed by George Butler Associates to investigate storm water infiltration. A list of 100 properties where repairs are recommended was approved by the Board of Public Works in September. Design will continue in order to make the necessary repairs on the sanitary sewer in Spring 2022.

Frenchtown and Elm Point Levee Studies: Staff provided comments on the Frenchtown study draft report which Reitz & Jens will incorporate into an updated report.

Little Hills Expressway & Mel Wetter Parkway Roundabout: Project is out to bid with a bid opening 10/21/21. Most of the project will be constructed next year, 2022.

Muegge Interchange and MO 94 Improvements: Project has been bid and awarded to Gershenson Construction. Project will begin later this year and will be completed in year 2023.

Nathan and Rosebrae: All construction is complete. Final change order, payment and project closeout is underway.

Perry Street Storm Sewers: Pace Construction began work on May 17. They have installed the 72” RCP through Frontier Park and have tunneled and pushed 60” RCP under Riverside Drive and Main Street. They have begun laying 60” RCP beneath Water Street. They will continue to lay storm sewers and sanitary sewer lines beneath Water Street, 2nd Street and Perry Street throughout the fall and into the winter. Expect intermittent closures and detours on Water Street, 2nd Street and Perry Street as work progresses along these corridors. Project completion expected Spring of 2022.

RIVERPOINTE: The first 7-acres of the Riverpointe Development have been completed and are ready for development. The City has received all remaining permits for the construction in hand. The City has continued to stockpile fill on the project site to elevate the property, and is working with a contractor who will be elevating the entirety of the property in the coming months the level of the KATY Trail. The City is nearing completion for a new sanitary sewer lift station and duct bank for the relocation of overhead Ameren transmission and Charter cable lines. The Ameren duct bank work and subsequent pavement repairs are completed. Utility poles bisecting the site are expected to be removed in the coming months. The City has entered into an agreement with TowerCo to relocate the existing cell phone tower adjacent to Fire Station 2. A Memorandum of Understanding for the relocation of the KATY Trail around the perimeter of the site was approved by the City and State Parks. The City completed the tree clearing efforts for the upcoming development and demolished all of the remaining dilapidated residential structures onsite. All outside funding agreements with the County Road Board and Missouri Department of Transportation have been finalized. Construction and marketing efforts continue.

Riverside Sanitary Trunkmain Replacement: CMT provided an alternatives analysis report and a preferred alternative was selected for preliminary design. The preliminary design plans will be submitted in November.

Page 19: SAINT CHARLES

19

ENGINEERING

HIGHLIGHTS (Q3 2021 – July through September)

Signal at Zumbehl Rd and Ipswich Ln: Staff awarded a design contract to Bartlett and West. The consultant has started surveying the property.

South Fifth Street Construction Project: Preliminary plans have been completed and staff are currently review the plans. Two sanitary layout alternatives have been drawn up to replace the existing main. Staff will be looking into a three alternative that involves pipe bursting.

Spring Mill Water Quality: The scheduled project completion date has been extended to mid- October 2021 due to unseasonably wet summer. The silt removal, rock revetment, drain valve at the overflow structure, and sod is complete. The concrete apron and entrance are currently under construction.

Signal at Zumbehl Rd and Ipswich Ln: Staff awarded a design contract to Bartlett and West. The consultant has started surveying the property.

Zumbehl Road Culvert: Easement acquisitions are complete. Right-of-way clearance has

been requested from MoDOT. Once received, the final bid documents will be submitted to

MoDOT and St. Charles County for review and approval. Construction is expected to

begin in early 2022.

Number of Permits and Plan Reviews: 149 permits / 41 plan reviews and Planning & Zoning Reviews

SEPTEMBER 2021

Utility Locates September 2021 September 2020 2021 Year to Date

City Utility Locates Received 1,440 1,271 9,590

City Utility Locates Completed 1,314 1,210 9,145

New Engineering Permits Received 48 44 394

Active Engineering Permits 85 80 653

Planning & Zoning Plan Review 9 2 68

Improvement Plans Received 1 5 62

Advertised 3 0 11

Contracts Routed 24 24 132

Currently in Design 20 3*

Currently under Construction 8 7*

Traffic & Stop Sign Requests

Speed Studies 0 1 0

Stop Sign 0 0 1

Traffic Calming 0 1 3

Parking 0 2 1

*Projects started this year

Page 20: SAINT CHARLES

20

FINANCE

HIGHLIGHTS (Q3 2021 – July through September)

Implemented tier based rates for water and sewer billing

Enhanced Tourism Tax audit process to include review of gross receipts for accuracy

Calculated and paid out wellness bonuses

Recorded and posted four Purchasing and Accounts Payable videos for staff training

Calculated and sent New Town NID and Special Business District Assessments to St. Charles County Collector for inclusion on the 2021 real estate tax bills

Mayor’s recommended 2022 operating budget completed and presented to Council on September 30th as required by Charter

Insurance coverage applications for 2022 were submitted

Implemented “Finance Fridays” in a partnership with Media for socials postings

COLLECTION & BILLING ACTIVITIES (Q3 2021 – July through September)

UTILITY MANAGEMENT WORK ORDERS GENERATED 3rd Quarter Last Quarter Increase

Type Jul-21 Aug-21 Sep-21 Totals Avg/Mo Averages (Decrease)

Delinquent Shut-Offs 165 209 186 560 187 190 (3)

Delinquent On 158 191 175 524 175 177 (2)

Door-Tag Shut Offs 20 20 30 70 23 16 7

Re-Reads 37 23 41 101 34 38 (4)

Inspect for Leaks 17 13 9 39 13 13 0

Move Ins 345 325 365 1035 345 317 28

Move Outs 319 319 302 940 313 285 28

TOTALS 1,061 1,100 1,108 3,269 1,090 1,036 54

INCOMING CALL STATISTICS 3rd Quarter Last Quarter Increase

Description Jul-21 Aug-21 Sep-21 Totals Avg/Mo Averages (Decrease)

# Work Days 21 22 21 64 21 21 0

Call Volume

Total Calls Received 2,329 2,422 2,427 7,178 2,393 1,312 1,081

Average Calls/Day 111 110 116 112 61 51

Call Duration

Total Call Time for Month (hrs) 107.36 103.63 106.33 317.32 105.77 56.98 48.79

Average Call Time (min) 2.75 2.56 2.61 2.64 2.60 0.04

LICENSING ACTIVITY 3rd Quarter Last Quarter Increase

Description Jul-21 Aug-21 Sep-21 Totals Avg/Mo Averages (Decrease)

New Licenses Issued 26 46 41 113 38 37 1

License Renewals Processed 2 17 2 21 7 48 (41)

Page 21: SAINT CHARLES

21

FINANCE

COLLECTION & BILLING ACTIVITIES (Q3 2021 – July through September)

RECEIPT ENTRY 3rd Quarter Last Quarter Increase

Description Jul-21 Aug-21 Sep-21 Totals Avg/Mo Averages (Decrease)

Water/Sewer Payments

# Transactions 12,789 11,777 13,083 37,649 12,550 12,620 (70)

Total Payment Amount $2,297,565 $1,504,702 $2,654,704 $6,456,971 $2,152,324 1,702,982 449,342

Gaming/Tax Receipts

# Transactions 133 97 45 275 92 124 (32)

Total Payment Amount $4,114,788 $4,063,760 $4,847,144 $13,025,693 $4,341,898 4,097,125 244,773

Business Licenses

# Transactions 219 186 101 506 169 285 (116)

Total Payment Amount $36,213 $15,974 $9,101 $61,287 $20,429 144,512 (124,083)

Other Receipts

# Transactions 1,726 1,862 1,713 5,301 1,767 1,805 (38)

Total Payment Amount $3,948,260 $2,265,308 $1,603,384 $7,816,951 $2,605,650 3,396,740 (791,090)

Page 22: SAINT CHARLES

22

FIRE

HIGHLIGHTS Fire Operations/Administration Activities

o Participated in honoring Lance Corporal Jared Schmitz o Participated in St. Charles Night Out o Participated at the POW-MIA Recognition Program o Participated in Drive by Birthday for 100 year old o Participated in Lindenwood Homecoming Parade o Participated in subdivision block party (Diekamp Homestead) o Replaced 6 batteries in smoke detectors o Participated in 5 Fire Truck Displays o Provided an Ambulance Display for safety week o Conducted a tour of Station 1 for Academy of Sacred Heart o Installed 9 smoke detectors

Fire Experience o 6 structure fires o 1 river/boat rescue events o 16 fire incidents o 879 total incidents o 0 Civilian injuries or deaths o 0 Firefighter injuries or deaths o Total fire loss $221,728 o Total value saved $456,235

Public Relations o Facebook Posts total was 20 o Page followers were up by 8,283 o Page likes were up to 7.6K o Post reach totaled 115,129 (4 posts reaching 50.4K, 48.8K, 29.5K and 27.9K

respectively)

Training Division o 2 members were sent to a 40 hour course and received certification as Missouri

State Fire investigators o The training division held three days of training for all crews covering pumping

apparatus and familiarization of specialized rescue equipment

Logistics Division o Replaced a grate at Station 3 o Facilities continue to handle most maintenance issues o Station rehab/rebuild continues to meet

EMS Highlights o 32 hours of EMS standby provided for OctoberFest o 12 opiate overdoses needing the use of Narcan o 24 hours EMS education provided to all shifts

Page 23: SAINT CHARLES

23

FIRE

HIGHLIGHTS Fire Prevention Activity

Annual Fire Inspections 361

Occupancy Inspections 28

Fire Protection Systems Testing 9

Operational Permit Inspections – Events and Tents 8

Plan Reviews – New buildings/alterations 11

Complaints 1

Misc. – Environmental assessments, inspections and consultations

22

TOTAL 440

Fire Department Permits Issued 3

EMS Billing

o Billing team is operating within a two business day turn-around time – currently

working on trips with date of service 10/10 which were imported on 10/12/2021.

EMS BILLING

2021Net Collections Date of Service Trips

Date of Service Trips

2020

January $132,509.70 417

February $129,460.20 378

March $178,847.80 413

April $159,207.50 421

May $158,285.90 439

June $190,521.80 454

July $187,504.40 481

August $197,696.00 474

September $195,772.80 427

TOTAL $1,529,806.10 3904 4501

January - December

EMS BILLING Net Collections 2021 Net Collections 2020

1st Quarter $437,704.90 $158,768.50

2nd Quarter $508,015.30 $425,592.70

3rd Quarter $580,973.20 $378,246.00

4th Quarter - $443,760.30

Page 24: SAINT CHARLES

24

FIRE

HIGHLIGHTS

EMS Experience

Rescue, EMS Incidents 1

Medical assist, assist EMS crew 5

Emergency medical service incident 2

Invalid assist 44

EMS calls excluding vehicle accidents 584

Motor vehicle accidents with injuries 30

Motor vehicle/pedestrian accident 0

Motor vehicle accidents without injuries 11

Extrication, Rescue-Other 3

Removal of victim(s) from stalled elevator 1

Water & ice related rescue, other 1

Rescue or EMS standby 5

TOTAL EMS incidents September 687

Page 25: SAINT CHARLES

25

HUMAN RESOURCES

OPEN POSITIONS

Position Title

Number

of

Positions

Open

City

Department

Date Position

Vacated

Status of Recruitment

Important Notes

Community Development Director 1 CD Start Date Scheduled

Plans Examiner 1 CD 6/4/2021 Offer Pending

Special Events Coordinator 1 CVB/Foundry 5/26/2021 Filled

Construction Inspector 1 Engineering 8/13/2021 Filled

Technology and Innovaction Director (New Position) 1 T.I. New Position Recruitment in Progress

Parks Maintenance Worker II - Turf Manager (New Position) 1 Parks New Position Filled

Police Dispatch 2 PD 10/5/2020 Recruitment in Progress

Police Officer 5 PD 1 Filled

Police Service Supervisor - Communications Unit Supervisor (New Position) 1 PD New Position Filled on Internal Basis

Building Maintenance Mechanic 1 PW 9/20/2021 Offer Pending

Fleet Mechanic 1 PW 12/14/2020 Offer Pending

Water Operator - Mechanic 1 PW 8/26/2020 Recruitment in Progress

Water Distribution Worker 1 PW 8/11/2021 Offer Pending

Street Equipment Operator 1 PW 8/1/2021 Offer Pending

Sewer Maintenanace Equipment Operator 2 PW 4/24/2021 Interviews Scheduled

Admin Assoc V 1 CVB On Hold

Admin Associate V - Economic Development 1 ED 1/31/2020 On Hold

Development Specialist 1 ED 12/13/2020 On Hold

Assistant City Engineer 1 Engineering 10/3/2021 On Hold

Admin Associate V - Engineering 1 Engineering 5/29/2020 On Hold

Financial Analyst 1 Finance 9/30/2020 On Hold

Emergency Operations position 1 Fire On Hold

Fire Code Officer 1 Fire Position Restructure - 2022

Governmental Relations Coordinator 1 Mayor/Admin New Position On HoldPolice Services Officer II 1 PD 6/12/2020 On Hold

Police Service Supervisor - Communications 2 PD 7/2/2021 On Hold

Public Safety Mechanic 1 PD 12/31/2020 On Hold

Utilities Supervisor 1 PW 2/7/2021 On Hold

Part Time Positions

PT Reception Desk Coordinator 1 CVB Recruitment in Progress

PT Support Staff 1 CVB/Foundry Recruitment in Progress

Police Services Officer - PT 1 PD On Hold

Parking Enforcement Officer - PT 1 PD 5/23/2016 On Hold

Street Maintenance Worker - PT 1 PW 5/17/2019 Interviews Scheduled

Sewer Maintenance Worker - PT 1 PW 6/17/2020 Offer Pending

Water Plant Worker - PT 1 PW 8/14/2020 Offer Pending

Water Distribution Worker - PT 1 PW 11/2/2020 Interviews Scheduled

PT Building Maintenance Workers - Facilities 1 PW 11/15/2020 Recruitment in Progress

SCAT - PT 6 PW 1/22/2019 On Hold

Clean Team - PT 1 PW On Hold

Seasonal PositionsParks Cashiers 10 Parks 9/1/2018 Open until season

Parks Concessions Workers 100 Parks 9/1/2019 Open until season

Parks Day Camp Counselors 100 Parks 9/1/2019 Open until season

Parks Lifeguards 100 Parks 9/1/2019 Open until season

Youth Sports Instructors 20 Parks 9/1/2019 Open until season

Seasonal Park Rangers Parks 1/3/2020 Open until season

Lead Concession Attendants Parks 1/3/2020 Open until season

Bartender - Parks Parks 1/3/2020 Open until season

Seasonal Maint. /Construction Workers Parks 1/3/2020 Open until season

POSITIONS UNDER REVIEW

Full Time Positions

Page 26: SAINT CHARLES

26

HUMAN RESOURCES

NEW HIRES

Name of New Employee Department/Division Position Start Date Miscellaneous Information

Dwayne Briggs Community Development Animal Control Officer 9/7/2021

Dwayne is joining the City of Saint Charles Community

Development Department as an Animal Control Officer. He

has over nineteen (19) years of working with Animals in

several different roles. Dwayne is thrilled to continue his

career with us.

Olivia Beseda Police Police Officer 9/7/2021

Olivia is joining the City of Saint Charles Police Department

as a Police Officer. She has successfully completed her

training at Eastern Missouri Police Academy. She is bringing

with her all of her skills and trainings that she has learned at

the Academy. Olivia is excited to be starting her career with

us.

Brenton Foust Police Police Officer 9/7/2021

Brenton is joining the City of Saint Charles Police

Department as a Police Officer. He brings with him eight (8)

years of experience in the Police force. Brenton is excited

about continuing his career with us.

Tanner Kistner Police Police Officer 9/7/2021

Tanner joins the City of Saint Charles Police Department as a

Police officer. He brings with him four (4) years of working

in the Sheriff’s office. Tanner is thrilled about beginning his

career with the City of Saint Charles.

Roger Mauzy Police Police Officer 9/7/2021

Roger joins the City of Saint Charles Police Department as a

Police Officer. He brings with him fifteen (15) years in the

Police Force. With his years of knowledge in the Police

force, he will bring with him several skills and abilities that

will be an beneficial to his team. Roger is elated to be

starting his career with us.

Robert Will Police Police Officer 9/13/2021

Robert joins the City of Saint Charles Police Department as a

Police Officer. He brings with him fourteen (14) years of

experience in the Police Force. Robert is thrilled to be

joining us and share his knowledge with his team.

Paige Jenkins Foundry Special Events Coordinator 9/14/2021

Paige joins the City of Saint Charles CVB - Foundry

Department as an Special Events Coordinator. She brings

with her four (4) years of teaching experience. Paige is

astounded to be starting her career with us.

Shawn Creason Parks Parks Maintenance II - Turf Manager 9/20/2021

Shawn joins the City of Saint Charles as a Parks Maintenance

II – Turf Manager. He brings with him three (3) years of

experience in working as a Maintenance Worker. Shawn is

excited about continuing his career with us.

NEW HIRES - September 2021

Page 27: SAINT CHARLES

27

LEGAL

HIGHLIGHTS (Q3 2021 – July through September)

Riverpointe matters

Liquor Commission matters

Real Estate purchases and sales

Business License (tourism tax) enforcement

Wellhead Protection District EPA matters

Villages of Provence Neighborhood Improvement District bond issuance

Merz Tract Neighborhood Improvement District formation and bond issuance

Diode Dynamics Chapter 100 Taxable Industrial Revenue Bonds issue

Charlestown Crossing Community Improvement District formation

Cost Reimbursement Agreement Plaza Way project

General Obligation Bond Issue

Revisions to Rules of Council Procedure

Westgate 200 Chapter 100 Taxable Industrial Revenue Bonds amendment

CVB Wine Tour

406 Morgan Street Dangerous Building

Abandoned / Uninhabited Property Ordinance(s)

ACF / St. Charles Properties matters

Labor Negotiations

Personnel matters

Litigation matters

Parks / Recreation matters

Christmas Tradition matters

Use Tax matters

Business license matters

Convention Center matters

Façade Grant matters

Planning & Zoning matters

Sunshine law (FOIA) matters

Various ordinance related matters

Codification matters

These activities were in addition to the daily counsel and advice provided to elected officials

and employees, litigation, ordinance preparation, correspondence, contract drafting and

review, legal opinions, employment law, real estate and privileged matters.

Page 28: SAINT CHARLES

28

MUNICIPAL COURTS

HIGHLIGHTS (Q3 2021 – July through September)

The Court has moved forward with a new plan to resolve adjudicated cases that have not had

any action on them for quite some time. We have joined with Linebarger (a collection agency)

to contact these defendants and hopefully collect the uncollectable. We have started to see

some positivity with payments. There isn't much, but it is a start.

We sent three Court Associates to the Fall MACA Conference in September. The training

covered fingerprint cards, docket coding of cases, bank reconciliation, and questions and

answers sessions. They brought much-needed information back, which we will implement.

We are still having in-person sessions for Court. The only difference now is that we are

requesting that you wear a mask while in the Courtroom. There has been a slow increase of

more defendants coming back to Court. We are hoping to see this increase more over time.

I want to thank this team I work with. This team is always striving to achieve a more efficient

way of doing processes and procedures.

Page 29: SAINT CHARLES

29

PARKS & RECREATION

HIGHLIGHTS (Q3 2021 – July through September)

Infrastructure o Updated electrical services at Blanchette Ball fields o Installed new electrical service panel at Blanchette between fields 1 and 2 o Chip seal treatment completed on Frontier Park trails o Installed sidewalks and gazebo at Graystone Park o Trouble-shooting at McNair Aquatic Facility to determine leaking issues o Re-rocked and sprayed Katy Trail in Frontier Park for dust mitigation o Light repairs at Vogt Bros Park, McNair Day Camp, Wapelhorst, Blanchette, and

McNair Sport Court o Irrigation repairs at St. Charles Soccer Complex (7 leaks and 100 ft. of pipe) o Irrigation and drinking fountain repairs complete at Wapelhorst playground and Shelter

2 o Fencing and goal repairs at McNair Sport Court o Repaired main breaker for Blanchette Field #2 o Power-washed Frontier Restroom o Asphalt sealing at Boschert Greenway, McNair accessible lots o Small asphalt patches throughout parks o Graffiti removal at Skate Park and Fountain Lakes restroom o Converted Frontier restroom to LED lighting o Sanitary sewer issues repaired at Bales restrooms o McNair Day Camp ballfields drinking fountain repaired o Fiber install work with contractors o Upgraded Motorcycle classroom lighting to LED o New park signs installed at Boone’s Lick Park, Frenchtown Park, and Fox Hill Park o Installed 6 new memorial benches o Trouble-shoot and help install water filter components at Wapelhorst Aquatic Facility

Grounds o Re-graded and added new Dura Edge surfacing on Blanchette ballfields o Brush-hog mowing at Fountain Lakes, Webster Park, Greenways, and Eco Trails o Cleared mud and debris underneath 370 Bridge o Installed goal posts and moved bleachers at McNair Football Field o Braille Trail Pond leak issues start (Sept.) and initial draining and clean out o Regular cleaning of Blanchette Landing (approximately 5 times per month) o Storm clean-up (7/9 and 7/10) o Weed spray and clean-up around DuSable Dog Park, Soccer Park maintenance

compound, Hunker Street parking area at Fox Hill Park, and fence-lines throughout parks

o Graded, seeded, and established grounds at Graystone Park o Fertilized all of Frontier Park

Equipment o New soccer nets at Wapelhorst and McNair Day Camp soccer fields o Begin winterizing concession stands and equipment o All HVAC filters changed o New hardware for flag poles at Braille Trail and Motorcycle Range o Rangers received 2 New AR-15 Rifles, new rifle optics, rifles lights, and Bipods

Page 30: SAINT CHARLES

30

PARKS & RECREATION

HIGHLIGHTS (Q3 2021 – July through September)

Planning o Prepped St. Charles Soccer Complex for Fall Soccer o Prepped and staffed August Food Trucks at Blanchette Park o Prepped Frontier Park for Bicentennial, Riverfest, Festival of the Little Hills, Irishfest,

and Oktoberfest o Move food trailer to McNair Football Field o Prepped portable stage for Jewish Festival o Redesigned Play brochure o Updated ePlay layout o Updated filing system for Community Garden o Began planning for 2022 projects and equipment replacements

Training o 6 staff viewed online training video for CNC sign routing machine o Ranger Sergeant Larry Dampier attended firearms instructor school o Staff attended ethics and fraud training o Leah Pyatt attended “desktop publishing” class

Staffing Updates o Chief Ranger Mike Wilkins sworn in Oath of Office o Hired and started new Maintenance II – Turf Manager Shawn Creason o Added one new seasonal maintenance employee o Mid-year evaluations completed o Provided training for PT admin Chelsey Summe after she began during June busy

season REPORT BY THE NUMBERS (Q3 2021 – July through September)

Page 31: SAINT CHARLES

31

PARKS & RECREATION

REPORT BY THE NUMBERS (Q3 2021 – July through September)

Page 32: SAINT CHARLES

32

POLICE

HIGHLIGHTS

Community/Department Activities

September 7 Officer Beseda, Officer Mauzy, Officer Foust, and Officer Kistner

all started admin training.

September 7-10 Captain Floyd attended the FBINAA re-trainer.

September 14 Officer Will started admin training.

September 14 St. Charles Night Out

September 16 St. Charles Officer assisted in the funeral procession of Lance

Corporal Schmidt.

September 17 Ashley Michael has been named the new dispatch supervisor.

September 18 St. Charles Police Mounted Unit participated at the Bicentennial

Inauguration Parade in Jefferson City.

September 21 SLAPCA Annual Police Officer Memorial Prayer Breakfast

September 24-26 Oktoberfest (no major problems)

September 30 Supervisors attended Fraud and Ethics training at the PD.

Notable incidents

September 3 Officers responded to an officer in need at Lucas and Hunt,

regarding a large fight in progress.

September 8 The St. Charles Police assisted and participated in the dignified

transfer of Lance Corporal Schmidt from Lambert to Baue.

September 11 Detective Riggins and Detective Follmer responded to Vinita Park

in reference to a Major Case call out.

September 15, 16, 17 SEU conducting saturated patrol and selective enforcement in

conjunction with O’Fallon PD and several other agencies in St.

Louis County in an attempt to deter and catch people stealing

vehicle and car clouting. There has been a major spike in vehicle

thefts and break-ins.

September 15 There was a possible road rage incident near the Convention

Center and VMP. The victim reported that an unknown subject

fired a gun, hitting his car. No one was injured and the suspect

fled the scene. The investigation is ongoing.

September 22 Felony domestic assault on Moore Avenue. Suspect pushed

victim down stairs and pointed a handgun at her. He was arrested

and warrants were obtained.

September 25 Seven subjects forced entry into a residence on Elm Street and

robbed the resident. The case is under investigation.

September 27 Bomb threat at St. Joseph Hospital.

September 30 Shots were fired towards a residence at the 200 block of Sherman

Drive. No one was injured. A suspect was identified and the

investigation is on-going.

Page 33: SAINT CHARLES

33

POLICE

HIGHLIGHTS

There were four (4) fatal overdoses. There were six (6) overdoses where officer

administered NARCAN and the victim survived.

Operational Numbers for September 2021 (compared to September in previous years)

CALLS FOR SERVICE 2017 2018 2019 2020 2021

Phone 3,064 3,290 3,094 3,297 3,014

Self 4,162 4,470 4,502 3,826 4,302

TOTAL 7,226 7,760 7,596 7,123 7,316

Incidents 1,024 1,110 1,046 807 852

Traffic Accidents 190 194 186 141 149

Arrests 320 372 361 226 298

Page 34: SAINT CHARLES

34

PUBLIC WORKS

Facilities Maintenance Sept. 2021 Sept. 2020 2021 YTD 2020 YTDPreventative WO 596 894 5,141 6,357

WO Request 6 20 461 198

Created 1,394 1,195 11,330 9,342

Closed/Completed 1,379 1,179 11,300 9,241

Still Pending (Months End) 15 16 30 49

Status Changed (3 day goal) 93.65% 93.15% 93.59% 91.62%

Closed (7 day goal) 94.02% 93.98% 93.89% 93.04%

Street 16 30 164 205

Water / Serviice Specialist 1352 1,136 10,987 8,979

Sewer 7 12 112 141

Traffic 4 1 51 24

Water Initial Read 330 265 2,593 2,446

Water Final Read 328 296 2,678 2,508

Delinquent Off 190 118 1,693 642

Delinquent On 175 115 1,499 592

New Tap/Set 45 47 309 315

Meter Change-Outs 87 81 699 736

Work Orders

Created 602 431 3,342 3,526

Completed 575 438 3,243 3,360

Work Order Cost $364,384 $230,879 $2,150,734 $1,718,200

CompletedWork Orders - By DivisionWater 273 68 1,773 513

Sewer 213 256 713 1,908

Trafiic 64 62 354 465

Street 36 52 414 474

Water Distribution Sept. 2021 Sept. 2020 2021 YTD 2020 YTDService Specialist Activities (Total SRs) 1,358 1,094 9,034 8,583

Water Production (million gallons) 257 260.0 MG 2,091.9MG 2035.29MG

Public Works DivisionMiles Swept 263.2 190.35 2,299.17 1,938.30

Potholes Patched 70 275 1,471 5,797

Street Repairs 34 58 359 418

Traffic Signal Repairs 6 7 31 47

Streetlight Repairs 20 7 100 110

Street Sign Repairs 23 20 152 244

Utility DivisionManhole/Inlet Inspections 118 88 496 863

Water Valve Inspections 1 8 134 2,269

Water Main Breaks 2 6 49 45

Sewer Line Repairs 4 9 144 109

New Town Canister ActivityAlarms Responded To 15 22 150 181

Sanitary Sewer MaintenanceLinear Feet Flushed 18,584 34,489 71,979 168,727

Linear Feet Televised 16,686 9,189 68,755 71,506

Storm Sewer MaintenanceLinear Feet Flushed 0 0 468 1,045

Linear Feet Televised 247 153 824 1,431

Water Service Line ProgramApplications Received 6 4 34 25

Applications Approved 5 4 34 25

Total Number Repaired 4 3 34 23

Sanitary Lateral ProgramApplications Received 9 17 105 142

Applications Approved 11 16 103 137

Total Number Repaired 8 14 86 125

Service Requests

Service Request Goal

Service Requests - By Division

Service Specialist/Meter Reader


Recommended