Dear Resident CITYLINK TULLA WIDENING: NOISE WALL CONSTRUCTION WORKS ALONG CITYLINK FREEWAY, TRAVANCORE We are writing to inform you about the construction of the new noise wall that will take place in your area from April as part of the CityLink Tulla Widening project. The CityLink Tulla Widening project involves adding lanes and other measures to improve the flow of traffic across the 24 kilometre section of freeway from the CityLink tunnels to Melbourne Airport. The project will also provide travel time savings per trip between Melbourne Airport and the West Gate Freeway during peak periods. The project will deliver a safer, more reliable freeway. Generally, an additional lane is being added in each direction, as well as upgrades at key interchanges including Bell Street, Mount Alexander Road/Flemington Road and on the Bolte Bridge to West Gate Freeway entry ramp. CPB Contractors is the construction contractor for the Bulla Road to Power Street section of the project. Where we will be We will be working within Moonee Ponds Creek in-between Travancore Park and CityLink, as shown in red on the map below.
Transcript
Page 1: citylinktullawidening.vic.gov.aucitylinktullawidening.vic.gov.au/__data/assets/word_doc…  · Web viewThe project will deliver a safer, ... Installing metal support poles and concrete

Dear Resident

CITYLINK TULLA WIDENING: NOISE WALL CONSTRUCTION WORKS ALONG CITYLINK FREEWAY, TRAVANCORE

We are writing to inform you about the construction of the new noise wall that will take place in your area from April as part of the CityLink Tulla Widening project.

The CityLink Tulla Widening project involves adding lanes and other measures to improve the flow of traffic across the 24 kilometre section of freeway from the CityLink tunnels to Melbourne Airport. The project will also provide travel time savings per trip between Melbourne Airport and the West Gate Freeway during peak periods.

The project will deliver a safer, more reliable freeway. Generally, an additional lane is being added in each direction, as well as upgrades at key interchanges including Bell Street, Mount Alexander Road/Flemington Road and on the Bolte Bridge to West Gate Freeway entry ramp.

CPB Contractors is the construction contractor for the Bulla Road to Power Street section of the project.

Where we will beWe will be working within Moonee Ponds Creek in-between Travancore Park and CityLink, as shown in red on the map below.

Mooltan Street

Hockey Lane

Delhi CourtCityLink

Page 2: citylinktullawidening.vic.gov.aucitylinktullawidening.vic.gov.au/__data/assets/word_doc…  · Web viewThe project will deliver a safer, ... Installing metal support poles and concrete

When works will occurWorks are scheduled to occur from April until August 2016. Our construction hours will be 7am to 6pm Monday to Saturday. On occasions we may need to work outside of these time frames to ensure public and worker safety. We will notify you in advance of any changes to these hours.Please note no works will take place over the Easter period.

What we are doing Drilling holes using heavy machinery, known as a bored piling rig, to install underground

concrete support piles Installing metal support poles and concrete noise wall panels

What you may notice during construction Construction personnel at work Noise from heavy equipment when in use around Travancore Park and Moonee Ponds

Creek, such as excavators, cranes, bored piling rig, trucks and site vehicles when in use These works will not impact your property or use of the park.

If you have any questions or concerns regarding this notification, please phone 1300 783 947 and select 1 or email us at [email protected]

We are committed to keeping residents and businesses informed and minimising the inconvenience during construction, while keeping the community and our workers safe at all times. Managing and protecting the environment is also important to us and we are working with local and state government adhering to environmental laws to ensure the impact to the natural ecosystem is minimised.

This work may be rescheduled in the event of unsuitable weather or other unavoidable circumstances. We apologise for any inconvenience and appreciate your understanding.

If you have any questions or feedback regarding this notification, please phone 1300 783 947 and select 1 or email us at [email protected] To keep up-to-date with upcoming works and changes to traffic conditions visit citylinktullawidening.vic.gov.au

Interpreter service For an interpreter, please call the Translating Interpreting Service (ITS National)

131 450

Yours sincerely,

Community Relations TeamCPB ContractorsCityLink Tulla Widening: Bulla Road to Power Street

24/03/2016, Ref: 0065 F03